1 HVAC Air Duct Leakage Eli P. Howard, III Group Director Technical Resources SMACNA
2 Key Variables that Affect the Amount of Leakage Static Pressure Amount of Duct Openings in the Duct Surface Seams, Joints, Access Doors, Rod and Fastener Penetrations Workmanship
3 Duct Leakage is Related to Duct Surface Area Research in Europe and in the U.S. has led to the Conclusion that a Duct Surface Leakage Factor can be Identified by the Following Relationship: F = C L P N
4 Duct Leakage is Related to Duct Surface Area F = C L P N Where: F is a leak rate per unit of duct surface area (typically CFM/100SF) C L is a constant P is static pressure (typically in in. W.G. ) N is an exponent (most typically 0.65)
5 Duct Construction Standards Ductwork be Constructed for the Specific Pressure Classifications shown on the contract Drawings (1/2", 1", 2", 3", 4", 6", 10") Duct Construction per SMACNA HVAC Duct Construction Standards Ducts Sealed in accordance with Table 1-2 SMACNA HVAC Air Duct Leakage Test Manual 1985, HVAC-DCS 1995
6 Table 1-2 Standard Duct Sealing Requirements SEAL CLASS Sealing Requirements Applicable Static Pressure A B C Class A: All Transverse joints, longitudinal seams, and duct wall penetrations Class B: All Transverse joints and longitudinal seams only Class C: Transverse joints Construction Class 4 w.g. and up (1000 Pa) 3 w.g. (75-0 Pa) 2 w.g. (500 Pa) only In addition to the above, any variable air volume system duct of 1 (250 Pa) and 1/2 w.g. (125 Pa) construction class that is upstream of the VAV boxes shall meet Seal Class C.
7 Definitions Seam: Joining two longitudinally (in the direction of airflow) oriented edges of duct surface between two joints. Helical (spiral) lock seams are exempt from sealing requirements.
8 Definitions Joints: All other duct surface connections made on the perimeter are deemed to be joints including: Girth Joints Branch & Sub-Branch Intersections Duct Collar Tap-ins Fitting Subsections
9 Definitions Joints: (Continued) Louver and Air Terminal Connections to Ducts Access Door and Access Panel Frames and Jambs Duct, Plenum and Casing Abutments to Building Structures
10 Definitions Duct Wall Penetrations Control Rods/Levers Pressure Taps Fastener Penetrations
11 Duct System Designer Match Fan to System Pressure Losses Account for Equipment Leakage (Fans, Coils, VAV, etc.) Specify Duct Pressure Class Specify Amount & Manner of Leakage Testing
12 Duct Sealing Leakage is a Function of Static Pressure and System Size Designer Must Specify the Duct Pressure Class or Classes Required for Duct Construction Duct Construction at 1" & ½" Pressure Class Meet Seal Class C Recommended
13 Duct Sealing Unsealed Ducts may leak at the following Rates: Duct Pressure in Inches w.g. CFM/100 S.F
14 Sealants Liquids Consistency of Heavy syrup Can be Applied by Brush, Cartridge Gun or Powered Pump Contain percent Volatile Solvents Shrinkage when Drying
15 Sealants Liquids Recommended for Slip Type Joints where the Sealant Fills a Small Space Between Overlapping Pieces of Metal Where Clearances Exceed 1/16" Several Applications may be Necessary
16 Sealants Mastics More Suitable for Application as Fillet, in Groves or Between Flanges Have Excellent Adhesion and Elasticity Gaskets Durable, Soft Elastomer Butyl or Extruded Forms Used in Flange Joints Should Have Adhesive Backing for Ease of Application
17 Sealants Tapes Such Closures are Listed as Components of Systems Complying with UL 181 No Recognized Industry Performance Standards that set forth:» Peel Adhesion, Shear Adhesion» Tensile Strength» Temperature Limits» Accelerated Aging
18 Sealants Tapes Some test results are published in the product directories of the Pressure Sensitive Tape Council located in Glenview, Illinois. Shelf Life Difficult to Identify (6 mos.-1 yr.) Aging Characteristics Questionable Compatibility of the Adhesive with the Duct Material (Flexible, Non-metallic Ducts)
19 Sealants Heat-Applied Materials Hot Melts normally Shop Applied Thermally Activated Uses Heat to either Shrink Fit Closures or to Expand Compounds within Joint Systems Mastic and Embedded Fabric Woven Fabrics (Fibrous Glass Mesh, Gauze, Canvas, etc.) Sealing Compounds including Lagging Adhesive
20 Sealants Shelf Life may be one year or less often only 6 months. Installer should verify that shelf life has not been exceeded. Safety Considerations Sealants may be flammable in wet or partially cured state Use liquids & mastics in well-ventilated areas Observe printed precautions of manufacturers
21 Leakage Tests Need to verify leakage control by field testing is not present when adequate methods of assembly and sealing are used. Leakage tests for duct systems constructed to 3" w.g. or lower not recommended not cost effective.
22 Leakage Tests For Systems of 4" w.g. Class and higher: The designer must determine if any justification for testing exists. If so, he must clearly designate in the contract documents the portions of the system(s) to be tested and must specify the appropriate test methods.
23 Leakage Tests ASHRAE Energy Conservation Standards Series 90 text on Leakage Control generally requires tests only for pressures in excess of 3" w.g. Adequate airtightness can normally be ensured by Selecting static pressure construction class suitable for operating condition AND Sealing ductwork properly
24 Table 4-1 Applicable Leakage Classes DUCT CLASS ½", 1", 2' W.G. 3" W.G. 4", 6", 10" W.G. SEAL CLASS C B A SEALING APPLICABLE TRANSVERSE JOINTS ONLY TRANSVERSE JOINTS & SEAMS JOINTS, SEAMS & ALL WALL PENETRATIONS LEAKAGE CLASS RECTANGULAR METAL ROUND METAL
25 DUCT LEAKAGE CLASSIFICATION FIGURE 4-1
26 DUCT LEAKAGE CLASSIFICATION FIGURE 4-1
27 Test Procedures 1. Select a section of duct to be tested. 2. Select a test pressure not in excess of the pressure class rating of the duct. (Usually the actual operating pressure.) 3. Calculate the allowable leakage using leakage factors for the duct surface area.
28 Test Procedures 4. Select the blower and orifice suitable for the test airflow requirements. 5. Connect the blower and flowmeter to the duct section. 6. Provide temporary seals at all ends of the ductwork.
29 Test Procedures 7. Start the blower at a low airflow capacity, increasing the airflow until the test pressure is reached. 8. Adjust blower capacity until steadystate conditions at the test pressure are achieved.
30 Test Procedures 9. Record the airflow (across the orifice) at the steady state condition. 10. This airflow is the CFM leakage of the tested section of the duct.
31 ILLUSTRATION OF TESTING FIGURE 3-1
32 LEAKAGE TEST METER APPARATUS FLANGE TAPS FIG. 5-1
33 TYPICAL ORIFICE FLOW CURVES FIGURE 5-3
34 P in. w.g. 1.4" Orifice Size 2.625" 4.90" P in. w.g. 1.4" Orifice Size 2.625" 4.90" P in. w.g. 1.4" Orifice Size 2.625" 4.90" TABLE 5-2 ORIFICE FLOW RATE (SCFM) VS. PRESSURE DIFFERENTIAL (in. of Water)
35
36 13.6 4" w.g. Construction Class operating at 3.5" w.g. = Leakage Class 6 DUCT LEAKAGE CLASSIFICATION FIGURE 4-1
37 TABLE A-1 LEAKAGE AS PERCENT OF FLOW IN SYSTEM 3.4
38 NOTES TABLE A-1 LEAKAGE AS PERCENT OF FLOW IN SYSTEM GIVEN: ASSUME: From Fig. 4-1 Fan CFM = Leakage Class = C L 6 Duct Area = 4000 sf. Operating Pressure = 3.5 w.g. Fan CFM = = 4 Duct Area 4000 Leakage Factor = 13.6 CFM/100 sf. CALCULATION: % of flow = Leakage Factor = 13.6 = 3.40 Fan CFM 4 Duct Area
39 Questions & Answers
40 Through-Penetration Firestopping Eli P. Howard, III Group Director Technical Resources SMACNA
41 Today's Program Definition & Purpose Background & Terminology Codes & Regulations Specification Responsibilities Firestopping Selection Factors Typical Details/Drawings
42 Definition A through-penetration firestop system is a specific field erected construction of an assemblage of materials designed to prevent the spread of fire and its by-products for a prescribed period of time through openings which are made in floors and walls to accommodate through penetrating items such as ducts, metal and plastic pipes, electrical conduit, cables, cable trays, etc.
43 Definition A firestop system consists of three components: 1. A fire resistive assembly or fire barrier (wall, floor, etc.); 2. The penetrating items (ducts, pipes, conduits, etc.); and 3. The sealant material.
44 Purpose Outline Considerations in Specifying and Installing Through-Penetration Firestop Systems
45 Terminology Annular Space The distance from the inside edge of the opening to the outside of the penetrating item.
46 Terminology Area Separation A wall of fire-resistance-rated construction (expressed in hours), which serves to divide the floor area of a building into acceptable area limits as set forth in the code having jurisdiction.
47 Terminology Fire-Rated Partition A partition having an assembly of materials that will afford a given fireresistance rating (expressed in hours) to impede the spread of fire from one area to another.
48 Terminology Fire Wall A continuous (basement-to-roof) wall having adequate fire-resistance rating (expressed in hours) with adequate structural stability under fire conditions to completely subdivide a building or separate adjoining buildings to restrict spread of fire.
49 Terminology F Rating A rating, usually expressed in hours, indicating a specific length of time that a fire-resistive barrier can withstand fire before being consumed or permitting the passage of flame through an opening in the assembly.
50 Terminology Intumescence A characteristic of certain fire barrier products that when exposed to heat, expand, self-sealing and filling any void in the penetration. When exposed to flame, intumescent materials will form a hard char.
51 Terminology L Rating A rating, usually expressed in cubic feet per minute per square foot of opening, determined by the air leakage test. It is a measure of the ability of a fire-resistive assembly to resist air or smoke infiltration resulting from pressure differences. L ratings may be given for ambient and elevated temperatures.
52 Terminology T Rating A rating, usually expressed in hours, indicating the length of time that the temperature on the non-fire side of a fireresistance-rated assembly exceeds 325 above its ambient temperature.
53 Codes & Regulations Compliance to ASTM E119 & E814 Compliance to UL 263 & 1479 ICC Building Code NFPA5000 Building Code Local/State Code Authority
54 Specification Responsibilities
55 Architects It is Important that the Architect Clearly Identify All Fire Resistant Assemblies and their Hourly Ratings on the Drawings
56 Engineers/Systems Designers It is Important that the System Designers Clearly Identify on the Project Drawings All Penetrations of Fire Resistive Assemblies and the Details of the Required Materials and Methods to be Installed to Maintain the Fire Resistive Integrity of those Assemblies.
57 Building/Code Officials It is Mandatory that the Plans and Specifications Completely Identify All Fire Resistant Construction, Penetrations of those Designated Fire Resistant Assemblies, and the Details of How those Penetrations are to be Protected. It is the Responsibility of the Code Official to Determine that the Required Information is Contained in the Construction Documents.
58 HVAC/Electrical Contractors The HVAC and Electrical Contractors Are Not Responsible for the Quantity, Location and the Details of Producing or Maintaining the Required Fire Resistance Ratings of Assemblies which are Penetrated by the Materials and Systems Installed by their Trades Except as those Quantities and Details are Shown on the Drawings and in the Specifications.
59 Factors Determining the Selection of a Through-Penetration Firestop System
60 A. The Material and Construction Type (Wall, Floor, etc.) of the Fire Resistant Assembly being Penetrated: Concrete Brick/Block Gypsum Metal Wood
61 B. The Type of Penetrating Item: Metallic Pipes (Insulated/Uninsulated) Non-Metallic Pipes HVAC Ducts Cables Cable Trays/Busways/Conduits Combinations of the above
62 C. The Relative Geometry of the Opening and the Penetrating Item: Round Opening/Round Penetrant (Sleeved/Unsleeved) Rectangular Opening/Rectangular Penetrant/Round Penetrant/Combination Penetrants The Resulting Annular Space Between the Item and the Assembly that it Passes Through
63 D. The Required Rating of the Firestop System Determined by the Rating of the Penetrated Assembly: F Rating (Hours) T Rating (Hours) L Rating (CFM/SQ. FT)
64
65
66
67
68 Questions & Answers
Tremco Fire Protection Systems Group Technical Bulletin
Compartmentalization products and design play a key role in protecting lives and property from fire. Understanding the tools and techniques available for firestopping is of utmost importance to designers,
More informationGUIDELINE ON THROUGH-PENETRATION FIRESTOPPING
GUIDELINE ON THROUGH-PENETRATION FIRESTOPPING SECOND EDITION AUGUST 2007 SHEET METAL AND AIR CONDITIONING CONTRACTORS NATIONAL ASSOCIATION, INC. 4201 Lafayette Center Drive Chantilly, VA 20151-1209 www.smacna.org
More informationDuct Leakage Testing. Ken Helfers, TSI Inc. 2011, TSI Incorporated
Duct Leakage Testing Ken Helfers, TSI Inc. Agenda Need for duct leakage testing Duct leakage testing standards and regulations Performing duct leakage testing Why Test Ducts for Leakage? Conserve energy
More information4 Installation Requirements
4 Installation Requirements 9 4.1 Code Reference The authority having jurisdiction should be referenced to determine what law, ordinance or code shall apply in the use of flexible duct. Ducts conforming
More informationDESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS
DESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS A. SCOPE 1. This information is intended to assist contractors, installers and code officials in the proper design and installation of flexible
More informationAir-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association
Air-Conditioning, Heating, and Refrigeration Institute Sheet Metal and Air-Conditioning Contractors National Association GUIDELINE B-1997 ACKNOWLEDGEMENT These guidelines for Roof Mounted Outdoor Air-
More informationTerms and Definitions In Canada
Terms and Definitions In Canada Most of the following terms and definitions are taken directly from the National Building Code and referenced Test Methods. Learning these terms will provide an important
More informationFIRESTOPPING & SMOKE SEALS
SPECIFICATION SECTION 07 84 00 FIRESTOPPING & SMOKE SEALS 1 GENERAL 1.1 SECTION INCLUDES 1.1.1 Comply with Division 1, General Requirements and Documents referred to therein. 1.1.2 It is the intent of
More informationA ROAD MAP FOR YOUR CODE, SMOKE BARRIER & SMOKE PARTITION REQUIREMENTS
A ROAD MAP FOR YOUR CODE, SMOKE BARRIER & SMOKE PARTITION REQUIREMENTS International Code Council National Fire Protection Association Underwriters Laboratories Inc. 5203 Leesburg Pike, Suite 600 1 Batterymarch
More informationHVAC Duct Construction. Bob Wasilewski Project Manager, Technical Resources SMACNA
HVAC Duct Construction Bob Wasilewski Project Manager, Technical Resources SMACNA HVAC Duct Construction Standards WHAT? WHY? HOW? Today's Program 1 st 2 nd Edition HVAC-DCS Review Joints and Limitations
More informationDUCT SYSTEMS CHAPTER 6
CHAPTER 6 DUCT SYSTEMS SECTION 601 GENERAL 601.1 Scope. Duct systems used for the movement of air in air-conditioning, heating, ventilating and exhaust systems shall conform to the provisions of this chapter
More informationSECTION 15190 HVAC INSULATION. A. All work specified in this Section is subject to the provisions of Section 15010.
SECTION 15190 HVAC INSULATION PART ONE - GENERAL PART 1 - GENERAL 1.01 DESCRIPTION A. All work specified in this Section is subject to the provisions of Section 15010. B. All insulation products shall
More informationCHAPTER 6 DUCT SYSTEMS
CHAPTER 6 DUCT SYSTEMS SECTION MC 601 GENERAL 601.1 Scope. Duct systems used for the movement of air in air-conditioning, heating, ventilating and exhaust systems shall conform to the provisions of this
More informationFINAL December 2012 SECTION 233100 DUCTWORK
SECTION 233100 DUCTWORK 1.0 Acoustical duct lining in any part of the duct system is prohibited. All ductwork requiring insula tion shall be externally insulated (Refer to the Sheet Metal Ductwork Insulation
More information2015 1322) SIGNIFICANT CHANGES INCLUDING CODE COMMENTARY
MINNESOTA ENERGY CODE COMPLIANCE COLLABORATIVE 2015 Minnesota Residential Energy Code (MR 1322) SIGNIFICANT CHANGES INCLUDING CODE COMMENTARY (July 15, 2015 Update) Note: The following information contains
More informationFIRE AND SMOKE PROTECTION FEATURES
CHAPTER 7 FIRE AND SMOKE PROTECTION FEATURES SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials, systems and assemblies used for structural fire resistance and fire-resistance-rated
More informationHVAC Air Duct Leakage. November 2013 Presented By: Mark Terzigni Project Manager Technical Services SMACNA
HVAC Air Duct Leakage November 2013 Presented By: Mark Terzigni Project Manager Technical Services SMACNA Learning Objectives Understand the difference between System leakage and Duct leakage Understand
More information07 21 19 Guide Specification STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM
07 21 19 STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM 7819 Broadview Road Cleveland, OH 44131 800-522-4522 February, 2011 SPEC NOTE: This guide specification is intended for use when specifying
More informationThe Source of Firestop Expertise SM
The Source of Firestop Expertise SM Inspector Pocket Guide The following information is intended to provide construction and code enforcement professionals with basic checkpoints to ensure that the required
More informationGeneral Fire Code Requirements Within Commercial Tenant Spaces
FIRE DEPARTMENT in cooperation with Scope: General Fire Code Requirements Within Commercial Tenant Spaces This handout is designed to assist owners, architects, contractors and others in understanding
More informationFIRE DAMPER APPLICATION GUIDE
FIRE AND CEILING RADIATION DAMPERS FIRE DAMPER APPLICATION GUIDE Use this application guide to help determine what type of fire damper best suits the application. Below are listed the ten Metal-Fab fire
More informationA. Air-Conditioning and Refrigeration Institute: 1. ARI 850 - Commercial and Industrial Air Filter Equipment.
SECTION 23 40 00 - HVAC AIR CLEANING DEVICES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Activated carbon filters. 2. Extended surface rigid air filter with synthetic media. 3. Disposable panel
More informationFIRE-RESISTANCE-RATED CONSTRUCTION
CHAPTER 7 FIRE-RESISTANCE-RATED CONSTRUCTION SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials and assemblies used for structural fire resistance and fire-resistance-rated
More informationPassive Fire Protection
Firestopping Passive Fire Protection FS20 Firestop Compound 6 hour fire rated penetration seals for electrical and mechanical services FS20 Firestop Compound FS20 Firestop Compound is a Fire-Rated Penetration
More informationFIRE-RESISTANCE-RATED CONSTRUCTION
CHAPTER 7 FIRE-RESISTANCE-RATED CONSTRUCTION SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials and assemblies used for structural fire resistance and fire-resistance-rated
More informationVA25014B0516 VA CINCINNATI PROJECT NO. 539-328 INPATIENT BED TOWER ADDITION (4 TH AND 5 TH FLOORS) SECTION 09 29 00 GYPSUM BOARD
SECTION 09 29 00 GYPSUM BOARD PART 1 - GENERAL 1.1 DESCRIPTION This section specifies installation and finishing of gypsum board, vapor retarder and air and moisture barrrier. 1.2 RELATED WORK A. Installation
More informationFSD35, FSD36 AND FSD37 COMBINATION FIRE and SMOKE DAMPERS
3900 Dr. Greaves Rd. Kansas City, MO 64030 (816) 761-7476 FAX (816) 765-8955 INSTALLATION INSTRUCTIONS FSD35, FSD36 AND FSD37 COMBINATION FIRE and SMOKE DAMPERS 11/2 HOUR UL555 RATED UL555S LEAKAGE RATED
More informationFire Barriers & Fire Stopping
Presented by: Bill Lauzon, PE Lauzon Life Safety Consulting, LLC 262-945-4567 Lauzon.lsc@gmail.com Web: Lauzon-LSC.com Environmental Part 2 Life Safety Code Chapter 8 Fire Barriers & Fire Stopping 1 Fire
More informationSAM HOUSTON STATE UNIVERSITY
PART 1: GENERAL 1.01 General Requirements A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the
More informationB. Types of mechanical insulation specified in this section include the following:
SECTION 23 0700 HVAC INSULATION PART 1 - GENERAL 1.1 SUMMARY A. Extent of mechanical insulation required by this section is indicated on drawings and schedules, and by requirements of this section. B.
More informationFIRE AND SMOKE PROTECTION FEATURES
CHAPTER 7 FIRE AND SMOKE PROTECTION FEATURES SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials, systems and assemblies used for structural fire resistance and fire-resistance-rated
More informationFREQUENTLY ASKED QUESTIONS about HERS and CHEERS Provided by the California Energy Commission Consumer Energy Center
http://www.energy.ca.gov/ FREQUENTLY ASKED QUESTIONS about HERS and CHEERS Provided by the California Energy Commission Consumer Energy Center Relevant Standard The Residential Manual for Compliance with
More informationAsbestos Procedures. Asbestos Products
Asbestos Procedures Asbestos Products Where is asbestos known to be located on The Evergreen State College? Please see Appendix A for a list of known asbestos containing materials located on the Olympia
More informationB. Product Schedule: For each penetration firestopping system. Include location and design designation of qualified testing and inspecting agency.
SECTION 078413 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply
More informationRequirements for Fire Protection of Light Weight Floor Systems **Act 1 Revisited**
PHRC Webinar Series Tuesday, September 9, 2014 1:00 pm Requirements for Fire Protection of Light Weight Floor Systems **Act 1 Revisited** Presented by: Bryan Heitzmann Credit(s) earned on completion of
More informationSECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront
PART 1 GENERAL 1.01 Work Included SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS System 402 Flush-Glazed Screw Spline Storefront A. Furnish and install aluminum architectural storefront system
More informationGuidelines for energy efficient heating, ventilation and air conditioning (HVAC) systems
Guidelines for energy efficient heating, ventilation and air conditioning (HVAC) systems If you're a designer or a BCA, this guidance on the energy efficiency of HVAC systems in commercial buildings may
More informationUnified Physical Infrastructure (UPI) Strategies for Thermal Management
Unified Physical Infrastructure (UPI) Strategies for Thermal Management The Importance of Air Sealing Grommets to Improving Smart www.panduit.com WP-04 August 2008 Introduction One of the core issues affecting
More informationFire Barrier Duct Wrap 15A
3 Fire Barrier Duct Wrap 15A Commerical Kitchen Grease Duct Fire Protection System Product Data and Installation Instructions Compliance 1998 Edition Complies with International Mechanical Code Complies
More informationLife Safety Dampers Selection and Application Manual. Ceiling Radiation Dampers Fire Dampers Combination Fire Smoke Dampers Smoke Dampers
Life Safety Dampers Selection and Application Manual Ceiling Radiation Dampers Fire Dampers Combination Fire Smoke Dampers Smoke Dampers May 2014 1 2 Table of Contents HOW TO USE THIS MANUAL DAMPER APPLICATION
More informationEFFICIENT DUCT SYSTEM DESIGN
DUCT ACOUSTICAL EFFICIENT EFFICIENT DUCT SYSTEM DESIGN WHY SPIRAL DUCT SHOULD BE YOUR FIRST CHOICE 2 Aesthetically Pleasing & Easier to install Low air leakage Low pressure drop Lower air distribution
More informationSECTION 07 42 13 METAL WALL PANELS
Mitsubishi Plastics Composites America, Inc. 401 Volvo Parkway Chesapeake, VA 23320 Phone: (800) 422-7270 Fax: (757) 436-1896 E-mail: info@alpolic.com www.alpolic-northamerica.com This MANU-SPEC utilizes
More informationSun Windows General Information Sun New Construction Window Installation Instructions
Sun Windows General Information Section 1 G F H H H A. Apply Weather Resistive Barrier B. Apply Sill Flashing Tape C. Place Waterproof Sill Shims D. Caulk Back of Nail Fin Sides & Top, Set Window, Fasten
More informationPipe and Equipment Insulations. Zeston. PVC Insulated Fitting Covers Installation Instructions for Hot, Cold and USDA Piping Systems
Pipe and Equipment Insulations Zeston PVC Insulated Fitting Covers Installation Instructions for Hot, Cold and USDA Piping Systems Zeston PVC Insulated Fitting Covers Installation Instructions for Hot,
More informationState of Connecticut Department of Public Health RADON PROGRAM
State of Connecticut Department of Public Health RADON PROGRAM Scope The Connecticut Department of Public Health (DPH) Radon Program is providing this information for contractors who decide to build radon
More informationProduct Guide Specification
Reef Industries, Inc. 9209 Almeda Genoa Rd. Houston, Texas 77075 Toll Free (800) 231-6074 Phone (713) 507-4251 Fax (713) 507-4295 Web Site www.reefindustries.com E-Mail ri@reefindustries.com Product Guide
More informationAvoiding Air Barrier Pitfalls
Avoiding Air Barrier Pitfalls Design & Durability November 2013 Air barriers, when correctly installed, help buildings achieve high levels of energy efficiency by decreasing heat loss. For example, great
More informationThe Science of Rough Opening Preparation and Window Installation to Minimize Air Leakage
The Science of Rough Opening Preparation and Window Installation to Minimize Air Leakage Sam Hagerman, Hammer and Hand Sam@HammerandHand.com Florian Speier, Zola Windows Florian@ZolaWindows.com Paul Grahovac,
More informationBasic Fire Door Requirements
TECHNICAL DATA SERIES S D I 118-01 Basic Fire Door Requirements 2001 Steel Door Institute STEEL DOOR INSTITUTE 30200 DETROIT ROAD - CLEVELAND, OHIO 44145 Technical Data Series SDI 118-2001 Basic Fire Door
More informationChapter 8. Duct Design and Sealing
Chapter 8 Duct Design and Sealing Duct Materials The three most common types of duct material used in home construction are metal, rigid fiberglass duct board, and flex-duct. Both metal and fiberglass
More informationGreenGuard Housewrap Installation Guide
000768PACBPHW_Flashing Bro 5/23/03 2:52 PM Page 1 For the most current product information, go to www.green-guard.com. Pactiv Building Products believes the information and recommendations herein to be
More informationAABC Specifications for Testing and Balancing HVAC Systems
AABC Specifications for Testing and Balancing HVAC Systems The Associated Air Balance Council (AABC) Total System Balancing Specifications for HVAC Testing, Balancing and Performance Verification TOTAL
More informationHCD DSA OSHPD 1 2 1/AC AC SS SS/CC 1 2 3 4 2013 CALIFORNIA BUILDING CODE 199
CALIFORNIA BUILDING CODE MATRIX ADOPTION TABLE CHAPTER 7 FIRE AND SMOKE PROTECTION FEATURES (Matrix Adoption Tables are non-regulatory, intended only as an aid to the user. See Chapter for state agency
More informationSECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here)
SECTION 08332 COILING COUNTER DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Coiling Metal Counter Doors. B. Coiling Counter Fire Doors. 1.2
More informationCOMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES
COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES These guidelines are to be used for ALL commercial cooking hoods, ventilation systems and related fire suppression
More information2014 British Columbia Building Code Changes
District of Houston 250-845-2238 2014 British Columbia Building Code Changes A District of Houston interpretation of the 2014 Building Code Changes for 9.36 & 9.32 The following changes reflect the most
More informationFiberglas, Exterior Wall Thermal Insulation
PROJECT ENGINEER RESPONSIBILITY: This is a general specification guide, intended to be used by experienced construction professionals, in conjunction with good construction practice and professional judgment.
More informationWater Damage & Repair
Water Damage & Repair Chinatown Preservation Talks 2015 James Engler, P.A Glenn Mason, AIA Mason Architects Program Outline Terminology & Waterproofing Basics Discussion of why this is important Below
More informationFirestopping & Fireblocking:
Firestopping & Fireblocking: By Vickie J. Lovell A discussion of the definitions of firestopping and fireblocking will help fire protection engineers clarify existing code language and sort out prevailing
More informationWATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12
WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12 87 88 GOOD INDUSTRY PRACTICES 12 WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12.1 BACKGROUND Most roofs in Singapore are constructed using reinforced
More informationeading Performance Solutions
eading Solutions Manage Risk Save Time and Money Grow Business Responsive Leadership As a construction professional, you face countless challenges. Every day you are expected to finish projects efficiently
More informationDuPont Tyvek Commercial Air Barrier Assemblies Exceed Air Barrier Association of America, ASHRAE 90.1
Building Science Bulletin DuPont Tyvek Commercial Air Barrier Assemblies Exceed Air Barrier Association of America, ASHRAE 90.1 and IECC Air Leakage Requirements When Tested in Accordance with ASTM E2357
More informationRetardants Inc. The Decision You Make May Save A Life! 123 Columbia Court North Suite 201 Chaska, MN 55318
Fire Barrier Moldable Putty+ Pads 123 Columbia Court North Suite 201 Chaska, MN 55318 952-448-7377 FAX:952-448-2613 e-mail: info@fireretardantsinc.com Visit Our Web Site at www.fireretardantsinc.com Protecting
More informationB. ASTM C 533 Calcium Silicate Block and Pipe Thermal Insulation. C. ASTM C 547 Mineral Fiber Preformed Insulation
PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is
More informationHVAC INSTALLATION. Success with 2015 IECC Northeast & Mid-Atlantic. Checklist for Builders & Trades
Success with 2015 IECC Northeast & Mid-Atlantic Checklist for Builders & Trades COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED TEMPLATE 2015.1.0 PAGE 1 CHECKLIST: JOB READY 1. 2. 3. 4. 5. 6. 7. 8.
More informationBuilt to Last. Built for Beauty. Good. Solid. Logix. TM
Built to Last. Built for Beauty. Good. Solid. Logix. TM Quality, Value and Service Introducing LOGIX Insulated Concrete Forms. Based on the simple concept of interlocking blocks, LOGIX ICF gives you a
More informationFlamesafe Firestopping Products. Firestopping Products. http://flamesafe.rectorseal.com
Flamesafe Firestopping Products Firestopping Products http://flamesafe.rectorseal.com Engineering Tested By Fire RectorSeal Firestopping Products Since the birth of the firestopping industry almost three
More informationINTERNATIONAL ASSOCIATION OF CLASSIFICATION SOCIETIES. Interpretations of the FTP
INTERNATIONAL ASSOCIATION OF CLASSIFICATION SOCIETIES Interpretations of the FTP CONTENTS FTP1 Adhesives used in A or B class divisions (FTP Code 3.1, Res A.754 para. 3.2.3) June 2000 FTP2 Pipe and duct
More informationIECC Compliance Guide for Homes in Virginia
IECC Compliance Guide for Homes in Virginia Amended Version of 2012 International Energy Conservation Code July 14, 2014 Climate Zone Since the entire state of Virginia falls in the IECC Climate Zone 4,
More informationHVAC INSTALLATION SUCCESS WITH 2012 IECC DELAWARE. for Builders & Trades. Recommended Practices for Optimized Energy Savings
SUCCESS WITH 2012 IECC DELAWARE Recommended Practices for Optimized Energy Savings for Builders & Trades COPYRIGHT 2015 ADVANCED ENERGY. ALL RIGHTS RESERVED VERSION 2015.1.0 CHECKLIST: JOB READY 1. 2.
More informationReducing Injury and Damage Related to Electric Dryer Fires. Fire Containment Tests for the Second Edition of UL 2158
Reducing Injury and Damage Related to Electric Dryer Fires Fire Containment Tests for the Second Edition of UL 2158 Reducing Injury and Damage Related to Electric Dryer Fires: Fire Containment Tests for
More informationfoot skylight) is enough to knock a worker off their feet. A 10 mph wind gust on a 5 x 6 skylight develops a wind force of 270 lbs.
Skylight Installation Instructions This document provides instruction and guidelines for installation of both curb mount (CM) and self flashing (SF) unit skylights on flat, pitched (> or equal to 3/12
More informationHoliday Inn Express & Suites Covington (Newton County) 1. Standing-seam metal roofing, custom fabricated.
PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Standing-seam metal roofing, custom fabricated. 1.2 SUBMITTALS A. Product Data: For each type of product indicated. B. Shop Drawings: Show installation
More informationGENERAL FIRE SAFETY TERMS & DEFINITIONS
UCL Fire Technical Note - TN006 Fire Safety Technical Guide GENERAL FIRE SAFETY TERMS & DEFINITIONS Reference: BS4422-2005 Fire Safety Vocabulary - for further information and definitions BS EN ISO 13943-2000:
More informationInstallation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows
Installation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows americancraftsmanwindows.com Project Requirements: Read
More informationSECTION 07530 SINGLE PLY MEMBRANE ROOFING. 4. Minor repair to adjacent clay tile roofing and flashings.
SECTION 07530 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section includes the flowing: 1. Removal of existing roofing membrane. Existing bur roof has one overlay and penetration mastic is asbestos containing.
More informationUPDATE October 8, 2012 Chicago Roofing Contractors Association CHICAGOLAND S ROOFING, INSULATION, AIR-BARRIER REQUIREMENTS
UPDATE October 8, 2012 Chicago Roofing Contractors Association CHICAGOLAND S ROOFING, INSULATION, AIR-BARRIER REQUIREMENTS Executive Summary: There is a proposal at the Joint Committee on Administrative
More informationREFERENCE STANDARD RS 13 MECHANICAL VENTILATION, AIR CONDITIONING, AND REFRIGERATION SYSTEMS * LIST OF REFERENCED NATIONAL STANDARDS
REFERENCE STANDARD RS 13 MECHANICAL VENTILATION, AIR CONDITIONING, AND REFRIGERATION SYSTEMS * LIST OF REFERENCED NATIONAL STANDARDS **NFiPA 90A Standard for the Installation of Air Conditioning and Ventilating
More informationSECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION
SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION The purpose of this guide specification is to assist the specifier in correctly specifying Mechanical System Testing
More informationDuct Design. Presented by Dave Janquart
Duct Design Presented by Dave Janquart Overview of Topics Duct design Duct insulation SMACNA Standards Factors Influencing Duct Design Equipment Losses Air Velocity Duct Material Duct Size & Shape Length
More informationServices Enclosures and Protected Shafts - Maintaining Compartmentation
Introduction When a fire resisting element is used to provide fire compartmentation, every opening that allows services to pass through the element must be adequately protected by sealing, or fire stopping
More informationTHE DOW CHEMICAL COMPANY Issued: August 1, 2008 200 LARKIN CENTER 1605 JOSEPH DRIVE MIDLAND MICHIGAN 48674 (989) 638-8655 www.dowbuildingmaterials.
ICC EVALUATION SERVICE, INC. EvaluateP InformP Protect Los Angeles Business/Regional OfficeP 5360 Workman Mill RoadP Whittier, CA 90601 (562) 699-0543 phonep (562) 695-4694 fax DIVISION: Section: 6 WOOD
More informationDuct Construction Standards. Code Reference: 2013 Title 24, Part 6 Standards 150.0(m)1. UL Ratings
DUCTS - CONSTRUCTION DO YOU HAVE A PHOTO OF THIS? PLEASE SEND IT TO US! installation.feedback@ energycodeace.com R-H-DS1 Duct Construction Standards All air-distribution system ducts and plenums shall
More informationFIRESTOPPING. Cable. Firestopping is the technology used to
cns firestop 20-26 9/16/08 2:46 PM Page 20 Cable FIRESTOPPING Before starting a search for suitable firestop systems, you would be well-advised to decide what general type of firestopping technology you
More informationCURTAIN TYPE FIRE DAMPERS
URTAIN TYPE FIRE urtain Fire Damper Basics Definition of a Fire Damper: The National Fire Protection Association (NFPA) Standard 9A defines a fire damper as "a device, installed in an air distribution
More informationHIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS
BSW HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS BSW is a fully reinforced Pre-Applied system membrane designed for horizontal and vertical external blind-side
More informationMOCK-UP TEST REPORT. Rendered to: TUBELITE, INC. PROJECT: 200 Series Curtain Wall Mock-Up
MOCK-UP TEST REPORT Rendered to: TUBELITE, INC. PROJECT: 200 Series Curtain Wall Mock-Up Report No: 85616.01-120-32 Test Completion Date: 01/15/09 Report Date: 02/11/09 Record Retention End Date: 01/15/13
More informationElement D Services Heating, Ventilating, and Air Conditioning
PART 1 - GENERAL 1.01 OVERVIEW A. This section supplements Design Guideline Element D3041 on air handling distribution with specific criteria for projects involving design of a Data Center spaces B. Refer
More information24.301.161 INCORPORATION BY REFERENCE OF INTERNATIONAL. (1) The Department of Labor and Industry adopts and incorporates by
24.301.161 INCORPORATION BY REFERENCE OF INTERNATIONAL ENERGY CONSERVATION CODE (1) The Department of Labor and Industry adopts and incorporates by reference the International Code Council's International
More informationH-Stud Area Separation Wall System
12 TH EDITION 09 21 16.33/NGC H-Stud Area Separation Wall System 09 21 16.33 139 H-STUD AREA SEPARATION WALL SYSTEM The fire-protection of gypsum-based Area Separation Walls is demonstrated in dramatic
More informationCERTIFICATE NAME OF PRODUCT MANUFACTURER PRODUCT DESCRIPTION CERTIFICATION PROCEDURE. No VTT C-6044-10 Date of issue 11.10.2010, Updated July 1, 2011
CERTIFICATE NAME OF PRODUCT No VTT C-6044-10 Date of issue 11.10.2010, Updated July 1, 2011 H-CONTROL REFLEX+ reflective insulating vapour control layer for roof and wall applications MANUFACTURER ACTIS
More informationCITY OF LONG BEACH Department of Development Services BUILDING AND SAFETY BUREAU MECHANICAL PLAN REVIEW CHECKLIST
CITY OF LONG BEACH Department of Development Services BUILDING AND SAFETY BUREAU MECHANICAL PLAN REVIEW CHECKLIST PROJECT NO.: BMEC DATE: STATUS: INFORMATION PROJECT ADDRESS: WORK DESCRIPTION: APPLICANT
More informationRoof Systems Overview
Roof Systems Overview Cold Applied Built-Up Roofing Systems BURmastic Tremco s line of cold applied built-up roofing systems. BURmastic 200 Combines Tremco s expertise in asphalt blending technology with
More informationExcerpts from the Canadian National Building Code (NBC)
Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more
More informationSTANDARD PROCEDURES FOR INSTALLATION OF METAL ROOF SYSTEMS
ROOFING APPLICATION STANDARD (RAS) No. 133 STANDARD PROCEDURES FOR INSTALLATION OF METAL ROOF SYSTEMS 1. Scope 1.1 This application standard has been developed to provide consistent information for the
More informationOntario Fire Code SECTION 5.13 DIP TANKS. Illustrated Commentary. Office of the Ontario Fire Marshal
Ontario Fire Code SECTION 5.13 DIP TANKS Illustrated Commentary Office of the Ontario Fire Marshal Dip Tanks Illustrated Commentary 1 5.13.1. Location 5.13.1.1. Dip tank operations involving flammable
More informationSECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
More informationFire-Rated Glass and Glazing START
Fire-Rated Glass and Glazing START www.pilkington.com/fire Fire-Rated Glass and Glazing Pilkington Fire Protection Glass North America 946 Kane Street, Suite A Toledo, OH 43612 Provider Number: J200 Course
More informationHealthandSafetyOntario.ca. Introduction. Storage Containers. Storing Flammable Liquids
Flammable Liquids Storage Introduction This guideline is designed to help you store flammable liquids safely. It is based on the requirements of the Ontario Fire Code, Part 4, and of the Regulations for
More informationLIFE SAFETY UPDATE. FULL SPRINKLERING OF ALL NURSING FACILITIES ADDITIONAL CLARIFICATIONS Prepared by Eric Rosenbaum, P.E. Hughes Associates, Inc.
LIFE SAFETY UPDATE FULL SPRINKLERING OF ALL NURSING FACILITIES ADDITIONAL CLARIFICATIONS Prepared by Eric Rosenbaum, P.E. Hughes Associates, Inc. The purpose of this update is as follows: Remind all state
More information