Hackensack Meadowlands Tide Gates Inspection Report
|
|
|
- Madlyn Atkinson
- 9 years ago
- Views:
Transcription
1 Hackensack Meadowlands Tide Gates Inspection Report prepared in conformity to The National Flood Insurance Program Community Rating System by The New Jersey Meadowlands Commission One DeKorte Park Plaza Lyndhurst, New Jersey March 27, 2006
2
3 TABLE OF CONTENTS Content Table of Contents Page i 1. Executive Summary 1 2. Inspection Process 2 3. Summary of Tide Gate Conditions 3.1 All Water Control Structures 3.2 Tide Gate Structures 3.3 Pump Station Structures 4. Inspection Reports 4.1 Carlstadt Broad Street and 20 th Street Tide Gate Dell Road Tide Gate East Riser Tide Gates J.P. Smith Tide Gate Lower Muddabach Tide Gate Moonachie Creek Tide Gates Peach Island Creek Tide Gates Waitex Tide Gate Yellow Freight Tide Gates 4.2 Kearny Belezza Tide Gate Bergen Avenue Tide Gate Cayuga Dike Pump Station and Tide Gates Dead Horse Creek Tide Gates Fish House Road Tide Gate Frank s Creek Tide Gates Harrison Avenue Tide Gate Standard Chlorine Tide Gate Trumbull Asphalt Tide Gate USPS Tide Gate 4.3 Little Ferry DePeyster Pump Station Losen Slote Pump Station and Tide Gates Hackensack Meadowlands Tide Gates Inspection Report Page i
4 4.4 Moonachie West Riser Tide Gates 4.5 North Arlington Kingsland Creek Tide Gate 4.6 Ridgefield Overpeck Creek Tide Gates 4.7 Rutherford Rutherford Tide Gates 4.8 Secaucus Acorn Road Tide Gate Born Street Pump Station and Tide Gates Farm Road Tide Gate Golden Avenue Pump Station Koelle Boulevard Tide Gate Meadowlands Parkway Tide Gate Mill Ridge Road Tide Gates Penhorn Creek Pump Station River Road Tide Gates and Pump Station Route 3 West DOT Tide Gate Secaucus High School Pump Station St. Paul s Avenue Tide Gates and Pump Station Syms Tide Gate 4.9 Teterboro Teterboro Pump Station Hackensack Meadowlands Tide Gates Inspection Report Page ii
5 1. Executive Summary The New Jersey Meadowlands Commission ( NJMC ) participates in the Federal Emergency Management Agency s (FEMA) Community Rating System ( CRS ) on behalf of the 14 municipalities within the Hackensack Meadowlands District. This program is voluntary and recognizes and encourages community floodplain management activities that exceed the minimum National Flood Insurance Program ( NFIP ) requirements. Property owners and tenants in the Hackensack Meadowlands District currently enjoy a flood insurance discount due to the continued efforts by the NJMC to exceed the program requirements. As required per the CRS Coordinator s Manual Activity 540, Drainage System Maintenance, the NJMC evaluated the functionality of all of the tide gates and pump stations within the District. The conditions of the facilities, along with maintenance recommendations, have been documented based on numerous inspections. From the analysis of this inspection data, the NJMC has identified deficiencies in the water control structures and has been able to rate the overall condition of the District s storm surge protection measures. Hackensack Meadowlands Tide Gates Inspection Report Page 1
6 2. Inspection Process Prior to each inspection, NJMC reviewed the 2004 CRS Activity 540 inspection reports in order to have a basic understanding of each flood control structure and its previously reported condition for comparison. Utilizing GIS data, NJMC also verified each structure s location and noted any significant changes to land uses with their respective drainage areas per aerial photos. GEOD Consulting surveyed most of the drainage structures for a project authorized by the Army Corps of Engineer in The site plans provided excellent support by providing pipe sizes, invert elevations, as well as basic system dimensions. Due to the significant tidal impact on the structures, the tide gates were inspected at low and high tide condition. By inspecting during both conditions, the NJMC was able to observe both how well each tide gate was sealing against high tide backwater pressure, and how freely the tide gates were opening to allow upstream channels to empty during low tide. Also, low tide inspections provide a good view of typically submerged system components such as hinges, trash rack, and scour control, while high tide inspections help to identify seepage, undermining, and poor tide gate contact to its seal. Inspecting at various tide conditions also provides a better observation of the impact fluvial flooding will have during high tide conditions. There are several tide gate locations where high tide conditions and high intensity rainfall event will cause severe flooding in the area. Pump stations were inspected during the tide change from low to high only. Each of the pump stations was inspected with the respective municipality s Department of Public Works (DPW) present to ensure access to all facilities. Additionally, the NJMC requested that each pump station be tested during the inspection to ensure the system is operating properly. During each of the inspections, NJMC performed a general survey of the upstream and downstream area and verified that the garbage racks were clean, the tide gates were seating properly, if any part of the flood control structure was damaged, and if damaged, the extent of damage and the required maintenance necessary. All inspections included pictures of the drainage structures, including upstream of structure (if possible), downstream of structure, and any areas of concern around the facility. Each tide gate and pump station mapped location was checked and revised, as necessary, using field notes and aerial photography. Hackensack Meadowlands Tide Gates Inspection Report Page 2
7 3. Summary of Tide Gate Conditions The following tables are the summary of all the water control structures within the Meadowlands District followed by a detailed breakdown of conditions for each facility. Hackensack Meadowlands Tide Gates Inspection Report Page 5
8 4. Inspection Reports Inspection reports are found in alphabetical order within each municipality s sub-section. A memo has been filed in this section for each tide gate that the NJMC has found to have been removed (decommissioned) or is no longer necessary for flood control. Hackensack Meadowlands Tide Gates Inspection Report Page 10
9 Site ID/Name: Location: Broad Street and 20 th Street Tide Gate Intersection of Broad Street and 20 th Street - Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 10:10 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gate is not seating properly and is lodged open with sediment and debris. The silt is interfering with the functionality of the gate. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance The tide gate currently does not have a trash rack system and is in need of one due to the amount of debris that the ditch has accumulated. The drainage ditch needs to be dredged in order to keep up with the amount of sediment that collects in front of the gate. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 12
10 Site ID/Name: Broad Street and 20 th Street Tide Gate (Block: 120 Lot: 13) Date: 12/08/05 Time: 10:10 AM Tide Conditions: Low Photo 1 Description: 1 steel flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 13
11 Site ID/Name: Broad Street and 20 th Street Tide Gate (Block: 120 Lot: 13) Date: 12/08/05 Time: 10:10 AM Tide Conditions: Low Photo 2 Description: Downstream view from tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 14
12 Site ID/Name: Location: Broad Street and 20 th Street Tide Gate Intersection of Broad Street and 20 th Street - Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 1:50 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and Wai Lee Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions * Non-Functional Notes On Condition/Problems: The tide gate is malfunctioning due to a build up of debris around the opening. * During low tide condition, the system was found to be nonfunctional. Please see attached low tide condition report. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance The gate appears to be working during high tide conditions. The storm sewer in the area need to be maintained regularly due to the build up of sedimentation. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 15
13 Site ID/Name: Broad Street and 20 th Street Tide Gate (Block: 120 Lot: 13) Date: 12/08/05 Time: 1:50 PM Tide Conditions: High Photo 1 Description: Location of steel flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 16
14 Site ID/Name: Broad Street and 20 th Street Tide Gate (Block: 120 Lot: 13) Date: 12/08/05 Time: 1:50 PM Tide Conditions: High Photo 2 Description: Downstream view from tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 17
15 Site ID/Name: Location: Dell Road Tide Gate Intersection of Starke Road and Dell Road - Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:25 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and John Enquist Type of Inspection: Yearly Post-Storm Complaint Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Notes On Condition/Problems: No problems observed. Catch Basin Culvert Outfall Other Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Make sure any debris and sediment remains clear of the tide gate structure. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 18
16 Site ID/Name: Dell Road Tide Gate (Block: Lot: 28) Date: 12/08/05 Time: 9:25 AM Tide Conditions: Low Photo 1 Description: Metal flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 19
17 Site ID/Name: Dell Road Tide Gate (Block: Lot: 28) Date: 12/08/05 Time: 9:25 AM Tide Conditions: Low Photo 2 Description: Downstream view from tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 20
18 Site ID/Name: Location: Dell Road Tide Gate Intersection of Starke Road and Dell Road - Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 1:45 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gate appears to be working properly during high tide conditions. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance The drainage ditch should be maintained regularly in order to keep the gate free from the build-up of sediment and debris. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 21
19 Site ID/Name: Dell Road Tide Gate (Block: Lot: 28) Date: 12/07/05 Time: 1:45 PM Tide Conditions: High Photo 1 Description: Metal flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 22
20 Site ID/Name: Dell Road Tide Gate (Block: Lot: 28) Date: 12/07/05 Time: 1:45 PM Tide Conditions: High Photo 2 Description: Upstream view from tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 23
21 Site ID/Name: Location: East Riser Tide Gates Across the street from 368 Starke Road - Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:40 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gates are not seating properly and water is entering into the system through gates two and four. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance The trash rack needs immediate repair and cleaning. Debris has collected and blocks the flow of water through the gates. The roadway is also in need of repair due to settling above the tide gates. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 24
22 Site ID/Name: East Riser Tide Gates (Block: 123 Lot: 16) Date: 12/08/05 Time: 9:40 AM Tide Conditions: Low Photo 1 Description: Tide gate structure Hackensack Meadowlands Tide Gates Inspection Report Page 25
23 Site ID/Name: East Riser Tide Gates (Block: 123 Lot: 16) Date: 12/08/05 Time: 9:40 AM Tide Conditions: Low Photo 2 Description: Upstream end of the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 26
24 Site ID/Name: East Riser Tide Gates (Block: 123 Lot: 16) Date: 12/08/05 Time: 9:40 AM Tide Conditions: Low Photo 3 Description: Upstream view from tide gates and view of the trash rack system Hackensack Meadowlands Tide Gates Inspection Report Page 27
25 Site ID/Name: Location: East Riser Tide Gates Across the street from 368 Starke Road - Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 1:55 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gates are malfunctioning and not seating properly, specifically tide gates two and four. The water is entering through the gates and entering the upstream system during high tide conditions. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance The trash rack needs to be maintained regularly. There is a build up of debris and sediment that blocks the flow of water. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 28
26 Site ID/Name: East Riser Tide Gates (Block: 123 Lot: 16) Date: 12/07/05 Time: 1:55 PM Tide Conditions: High Photo 1 Description: Tide gate structure Hackensack Meadowlands Tide Gates Inspection Report Page 29
27 Site ID/Name: East Riser Tide Gates (Block: 123 Lot: 16) Date: 12/07/05 Time: 1:55 PM Tide Conditions: High Photo 2 Description: Upstream view from tide gates and view of the trash rack system Hackensack Meadowlands Tide Gates Inspection Report Page 30
28 Site ID/Name: East Riser Tide Gates (Block: 123 Lot: 16) Date: 12/07/05 Time: 1:55 PM Tide Conditions: High Photo 3 Description: Downstream view from the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 31
29 Site ID/Name: East Riser Tide Gates (Block: 123 Lot: 16) Date: 12/07/05 Time: 1:55 PM Tide Conditions: High Photo 4 Description: Upstream end of the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 32
30 Memorandum To: Nicolas Agnoli From: Wai Lee Cc: File Date: February 6, 2006 Re: J.P. Smith Tide Gate New Jersey Meadowlands Commission The tide gate located in the intersection of 13 th Street and Division Street in Carlstadt was inspected on December 19, 2005 during low and high tide conditions. The water elevation in the vicinity of the tide gate did not change regardless of the tidal conditions. The tide gate is constantly submerged and cannot be inspected. After a detailed analysis of the topographic data and aerial mapping, NJMC has determined tidal water cannot reach the tide gate, and therefore, it is recommended that the J.P. Smith Tide Gate no longer be inspected. Hackensack Meadowlands Tide Gates Inspection Report Page 33
31 Site ID/Name: Location: J.P. Smith Tide Gate Intersection of 13 th Street and Division Street - Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 2:15 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Frank Coppola and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Access to the tide gate was unavailable. The area is fenced in with a lock on the fence. A key is needed from the property owner. The tide gate is no longer in operation and needs to be decommissioned. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 34
32 Site ID/Name: J. P. Smith Tide Gate (Block: 111 Lot: 5) Date: 12/19/05 Time: 2:15 PM Tide Conditions: Low Photo 1 Description: Remains of existing tide gate structure Hackensack Meadowlands Tide Gates Inspection Report Page 35
33 Hackensack Meadowlands Tide Gates Inspection Report Page 36
34 Site ID/Name: Location: J.P. Smith Tide Gate Intersection of 13 th Street and Division Street - Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 10:15 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Frank Coppola and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: No access to the tide gate was available. Area is fenced in with a lock on the fence. A key is needed from the property owner. The gate is no longer in operation and needs to be decommissioned. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 37
35 Site ID/Name: J. P. Smith Tide Gate (Block: 111 Lot: 5) Date: 12/19/05 Time: 10:15 AM Tide Conditions: High Photo 1 Description: Existing tide gate structure shown Hackensack Meadowlands Tide Gates Inspection Report Page 38
36 Memorandum To: Nicolas Agnoli From: Wai Lee Cc: File Date: February 6, 2006 Re: Lower Muddabach Tide Gate New Jersey Meadowlands Commission Lower Muddabach Tide Gate, located in Block 137, Lot 46 in Carlstadt, has not been inspected due to access issues. The remote area of the site requires a boat for inspection. The weather from the winter hinders inspection by boats due to unsafe conditions on the boat. Inspection is pending on acceptable weather conditions. Hackensack Meadowlands Tide Gates Inspection Report Page 39
37 Site ID/Name: Location: Moonachie Creek Tide Gate Block 137, Lot 7 (next to Williams Corporation Transco Pipeline) File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 1:00 AM / PM Conditions: Rain (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: John Enquist and Wai Lee Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gate appears to be functioning properly. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance There is some debris that has built up in front of the trash rack system that needs to be removed. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 40
38 Site ID/Name: Moonachie Creek Tide Gate (Block: 137 Lot: 7) Date: 12/29/05 Time: 1:00 PM Tide Conditions: Low Photo 1 Description: Tide gate shown in the open position Hackensack Meadowlands Tide Gates Inspection Report Page 41
39 Site ID/Name: Moonachie Creek Tide Gate (Block: 137 Lot: 7) Date: 12/29/05 Time: 1:00 PM Tide Conditions: Low Photo 2 Description: View of trash rack on upstream side of the tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 42
40 Site ID/Name: Moonachie Creek Tide Gate (Block: 137 Lot: 7) Date: 12/29/05 Time: 1:00 PM Tide Conditions: Low Photo 3 Description: View of tide gate structure Hackensack Meadowlands Tide Gates Inspection Report Page 43
41 Site ID/Name: Location: Moonachie Creek Tide Gate Block 137, Lot 7 (next to Williams Corporation Transco Pipeline) File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 8:00 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: John Enquist and Tina Schvejda Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gate appears to be working properly during high tide conditions. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance There is minimal debris that has built up and needs to be removed in front of the trash rack. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 44
42 Site ID/Name: Moonachie Creek Tide Gate (Block: 137 Lot: 7) Date: 12/29/05 Time: 8:00 AM Tide Conditions: High Photo 1 Description: Trash rack system Hackensack Meadowlands Tide Gates Inspection Report Page 45
43 Site ID/Name: Moonachie Creek Tide Gate (Block: 137 Lot: 7) Date: 12/29/05 Time: 8:00 AM Tide Conditions: High Photo 2 Description: Tide gate headwall Hackensack Meadowlands Tide Gates Inspection Report Page 46
44 Site ID/Name: Moonachie Creek Tide Gate (Block: 137 Lot: 7) Date: 12/29/05 Time: 8:00 AM Tide Conditions: High Photo 3 Description: Downstream of the tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 47
45 Site ID/Name: Location: Peach Island Creek Tide Gates Located next to 350 Gotham Parkway - Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:15 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gates are not seating properly due to sediment and debris that has built up around the brim of the gates Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance There is some debris that has collected in front of the trash rack and blocks the flow of water through the tide gates Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 48
46 Site ID/Name: Peach Island Creek Tide Gates (Block: Lot: 11) Date: 12/08/05 Time: 9:15 AM Tide Conditions: Low Photo 1 Description: 4 metal flap gates Hackensack Meadowlands Tide Gates Inspection Report Page 49
47 Site ID/Name: Peach Island Creek Tide Gates (Block: Lot: 11) Date: 12/08/05 Time: 9:15 AM Tide Conditions: Low Photo 2 Description: Upstream view from gates Hackensack Meadowlands Tide Gates Inspection Report Page 50
48 Site ID/Name: Peach Island Creek Tide Gates (Block: Lot: 11) Date: 12/08/05 Time: 9:15 AM Tide Conditions: Low Photo 3 Description: Downstream view from gates Hackensack Meadowlands Tide Gates Inspection Report Page 51
49 Site ID/Name: Location: Peach Island Creek Tide Gates Located next to 350 Gotham Parkway - Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 1:30 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gates do not seat properly during high tide conditions and a small amount of water continues to seep through and into the upstream system. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance There is a build-up of some sediment and debris located along the trash rack that blocks the flow of water. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 52
50 Site ID/Name: Peach Island Creek Tide Gates (Block: Lot: 11) Date: 12/07/05 Time: 1:30 PM Tide Conditions: High Photo 1 Description: Trash rack on upstream side of the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 53
51 Site ID/Name: Peach Island Creek Tide Gates (Block: Lot: 11) Date: 12/07/05 Time: 1:30 PM Tide Conditions: High Photo 2 Description: 4 metal flap gates Hackensack Meadowlands Tide Gates Inspection Report Page 54
52 Site ID/Name: Peach Island Creek Tide Gates (Block: Lot: 11) Date: 12/07/05 Time: 1:30 PM Tide Conditions: High Photo 3 Description: Downstream view from the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 55
53 Site ID/Name: Location: Waitex Tide Gate 50 Broad Street Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 10:20 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gate appeared to be functioning properly at the time of the inspection. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Debris that has collected in front of the trash rack needs to be removed. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 56
54 Site ID/Name: Waitex Tide Gate (Block: 120 Lot: 18) Date: 12/08/05 Time: 10:20 AM Tide Conditions: Low Photo 1 Description: Metal flap gate with a trash rack Hackensack Meadowlands Tide Gates Inspection Report Page 57
55 Site ID/Name: Waitex Tide Gate (Block: 120 Lot: 18) Date: 12/08/05 Time: 10:20 AM Tide Conditions: Low Photo 2 Description: Downstream view from the tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 58
56 Site ID/Name: Location: Waitex Tide Gate 50 Broad Street - Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 2:15 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gate appeared to functioning properly at the time of the inspection. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 59
57 Site ID/Name: Waitex Tide Gate (Block: 120 Lot: 18) Date: 12/07/05 Time: 2:15 PM Tide Conditions: High Photo 1 Description: Metal flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 60
58 Site ID/Name: Waitex Tide Gate (Block: 120 Lot: 18) Date: 12/07/05 Time: 2:15 PM Tide Conditions: High Photo 2 Description: Downstream view from the tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 61
59 Site ID/Name: Location: Yellow Freight Tide Gates Located next to 390 Starke Road - Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:30 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gates are not seating properly and debris has accumulated in front of the tide gates. The tide gates are hard to access due to thick vegetation. Access may need to be made by boat in order to obtain a good view of the gates Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance The trash rack needs to be replaced. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 62
60 Site ID/Name: Yellow Freight Tide Gates (Block: Lot: 28) Date: 12/08/05 Time: 9:30 AM Tide Conditions: Low Photo 1 Description: Tide gate structure Hackensack Meadowlands Tide Gates Inspection Report Page 63
61 Site ID/Name: Yellow Freight Tide Gates (Block: Lot: 28) Date: 12/08/05 Time: 9:30 AM Tide Conditions: Low Photo 2 Description: Upstream view from tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 64
62 Site ID/Name: Location: Yellow Freight Tide Gates Located next to 390 Starke Road - Carlstadt File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 1:55 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and Wai Lee Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gates are not seating properly and debris has accumulated in front of the tide gates. A feasibility study will be initiated in 2006 to investigate the overall functionality of the tide gates and the need for repairs and/or replacement. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance There is a build-up of debris that has collected in front of the trash rack system and needs to be removed. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 65
63 Site ID/Name: Yellow Freight Tide Gates (Block: Lot: 28) Date: 12/08/05 Time: 1:55 PM Tide Conditions: High Photo 1 Description: Tide gate structure Hackensack Meadowlands Tide Gates Inspection Report Page 66
64 Site ID/Name: Yellow Freight Tide Gates (Block: Lot: 28) Date: 12/08/05 Time: 1:55 PM Tide Conditions: High Photo 2 Description: Downstream view from the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 67
65 Site ID/Name: Location: Belezza Tide Gate Belezza Company 2 Fish House Road - Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 3:00 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Frank Coppola and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gate is not seating properly due to debris and sediment. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance The tide gate needs a trash rack system installed on both the upstream and downstream side of the structure. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 69
66 Site ID/Name: Belezza Tide Gate (Block: 287 Lot: 81) Date: 12/19/05 Time: 3:00 PM Tide Conditions: Low Photo 1 Description: Tide gate shown with debris keeping it from closing properly Hackensack Meadowlands Tide Gates Inspection Report Page 70
67 Site ID/Name: Belezza Tide Gate (Block: 287 Lot: 81) Date: 12/19/05 Time: 3:00 PM Tide Conditions: Low Photo 2 Description: Upstream view from the tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 71
68 Site ID/Name: Belezza Tide Gate (Block: 287 Lot: 81) Date: 12/19/05 Time: 3:00 PM Tide Conditions: Low Photo 3 Description: Downstream view from the tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 72
69 Site ID/Name: Location: Belezza Tide Gate Belezza Company 2 Fish House Road - Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:00 AM / PM Conditions: Cloudy (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Wai Lee and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gate was not visible during high tide conditions. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: No pictures were taken at inspection since tide gate was not visible. Hackensack Meadowlands Tide Gates Inspection Report Page 73
70 Site ID/Name: Location: Bergen Avenue Tide Gate Block 275, Lot 3; Bergen Avenue - Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 1:40 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro and Frank Coppola Type of Inspection: Yearly Post-Storm Complaint Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Notes On Condition/Problems: No problems observed. Catch Basin Culvert Outfall Other Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 74
71 Site ID/Name: Bergen Avenue Tide Gate (Block: 275 Lot: 3) Date: 12/13/05 Time: 1:40 PM Tide Conditions: Low Photo 1 Description: Tideflex TM check valve structure Hackensack Meadowlands Tide Gates Inspection Report Page 75
72 Site ID/Name: Bergen Avenue Tide Gate (Block: 275 Lot: 3) Date: 12/13/05 Time: 1:40 PM Tide Conditions: Low Photo 2 Description: Downstream view from tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 76
73 Site ID/Name: Bergen Avenue Tide Gate (Block: 275 Lot: 3) Date: 12/13/05 Time: 1:40 PM Tide Conditions: Low Photo 3 Description: Downstream detention basin located at the tide gate outfall Hackensack Meadowlands Tide Gates Inspection Report Page 77
74 Site ID/Name: Location: Bergen Avenue Tide Gate Block 275, Lot 3; Bergen Avenue - Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 2:35 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and Wai Lee Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gate is a Tideflex TM check valve system. Minor debris accumulated. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance There is some debris that has accumulated in front of the gate that needs to be removed. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 78
75 Site ID/Name: Bergen Avenue Tide Gate (Block: 275 Lot: 3) Date: 12/08/05 Time: 2:35 PM Tide Conditions: High Photo 1 Description: Tideflex TM check valve structure Hackensack Meadowlands Tide Gates Inspection Report Page 79
76 Site ID/Name: Bergen Avenue Tide Gate (Block: 275 Lot: 3) Date: 12/08/05 Time: 2:35 PM Tide Conditions: High Photo 2 Description: Downstream view from tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 80
77 Site ID/Name: Bergen Avenue Tide Gate (Block: 275 Lot: 3) Date: 12/08/05 Time: 2:35 PM Tide Conditions: High Photo 3 Description: Downstream detention basin located at the outfall of the tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 81
78 Site ID/Name: Location: Cayuga Dike Pump Station & Tide Gates Block 287, Lot 33 (Next to access road from Route 7-Belleville Turnpike) File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 10:30 AM / PM Conditions: Sunny and windy (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Wai Lee and Nicholas Agnoli Army Corps of Engineers: Bryce Wisemiller, Milton Ricks, and Nuree Sarkar Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Maintenance Required: Immediate Repair Continued Upkeep Notes On Condition/Problems: Three existing tide gates were found but the tide gate structures did not appear to be functional. The pump station is abandoned and without electrical service. Flow of water between the Hackensack River and the marsh across the dike might be seeping through the old tide gate structures. No signs or indications were found to prove the dike has been breached in the past. Notes on Maintenance No interim maintenance is required because the Cayuga Dike system has deteriorated into a dilapidated state. An analysis of the Cayuga Dike system will be required to determine if the system is needed for flood control mitigation and should be repaired. Other Notes: May be candidate for decommissioning. Hackensack Meadowlands Tide Gates Inspection Report Page 82
79 Site ID/Name: Cayuga Dike Pump Station and Tide Gates (Block: 287 Lot: 33) Date: 3/14/06 Time: 10:30 AM Tide Conditions: High Photo 1 Description: View of old tide gate structure Hackensack Meadowlands Tide Gates Inspection Report Page 83
80 Site ID/Name: Cayuga Dike Pump Station and Tide Gates (Block: 287 Lot: 33) Date: 3/14/06 Time: 10:30 AM Tide Conditions: High Photo 2 Description: View of pump station underneath the NJ Turnpike Hackensack Meadowlands Tide Gates Inspection Report Page 84
81 Site ID/Name: Cayuga Dike Pump Station and Tide Gates (Block: 287 Lot: 33) Date: 3/14/06 Time: 10:30 AM Tide Conditions: High Photo 3 Description: View of discharge pipes from pump station to Hackensack River Hackensack Meadowlands Tide Gates Inspection Report Page 85
82 Site ID/Name: Cayuga Dike Pump Station and Tide Gates (Block: 287 Lot: 33) Date: 3/14/06 Time: 10:30 AM Tide Conditions: High Photo 4 Description: Looking inside of the Cayuga Dike Pump Station Hackensack Meadowlands Tide Gates Inspection Report Page 86
83 Site ID/Name: Cayuga Dike Pump Station and Tide Gates (Block: 287 Lot: 33) Date: 3/14/06 Time: 10:30 AM Tide Conditions: High Photo 5 Description: View of Cayuga Dike Pump Station s intake structure Hackensack Meadowlands Tide Gates Inspection Report Page 87
84 Site ID/Name: Location: Dead Horse Creek Tide Gate Block 253, Lot 5A; Bergen Avenue - Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 1:30 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro and Frank Coppola Type of Inspection: Yearly Post-Storm Complaint Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Notes On Condition/Problems: No problems observed. Catch Basin Culvert Outfall Other Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 88
85 Site ID/Name: Dead Horse Creek Tide Gates (Block: 253 Lot: 5a) Date: 12/13/05 Time: 1:30 PM Tide Conditions: Low Photo 1 Description: Tideflex TM check valve structure Hackensack Meadowlands Tide Gates Inspection Report Page 89
86 Site ID/Name: Dead Horse Creek Tide Gates (Block: 253 Lot: 5a) Date: 12/13/05 Time: 1:30 PM Tide Conditions: Low Photo 2 Description: Downstream view from tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 90
87 Site ID/Name: Location: Dead Horse Creek Tide Gate Block 253, Lot 5A; Bergen Avenue - Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 2:25 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and Wai Lee Type of Inspection: Yearly Post-Storm Complaint Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Notes On Condition/Problems: No problems observed. Catch Basin Culvert Outfall Other Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 91
88 Site ID/Name: Dead Horse Creek Tide Gates (Block: 253 Lot: 5a) Date: 12/08/05 Time: 2:25 PM Tide Conditions: High Photo 1 Description: Tideflex TM check valve structure Hackensack Meadowlands Tide Gates Inspection Report Page 92
89 Site ID/Name: Dead Horse Creek Tide Gates (Block: 253 Lot: 5a) Date: 12/08/05 Time: 2:25 PM Tide Conditions: High Photo 2 Description: Downstream view from tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 93
90 Site ID/Name: Location: Fish House Road Tide Gate Block 298 Lot 28; Fish House Road Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:10 AM / PM Conditions: Cloudy (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: John Enquist and Bob Segro Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The site contains a Tideflex TM check valve; it appears to be functional during low tide conditions. The discharge channel is clogged with debris and sediment. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance The drainage ditch downstream of the Tideflex TM is in need of a clean-out. Sediment and debris have collected and block the flow of water. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 94
91 Site ID/Name: Fish House Road Tide Gate (Block: 298 Lot: 28) Date: 2/6/06 Time: 9:10 AM Tide Conditions: Low Photo 1 Description: Downstream view from tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 95
92 Site ID/Name: Fish House Road Tide Gate (Block: 298 Lot: 28) Date: 2/6/06 Time: 9:10 AM Tide Conditions: Low Photo 2 Description: Tideflex TM check valve Hackensack Meadowlands Tide Gates Inspection Report Page 96
93 Site ID/Name: Location: Frank s Creek Tide Gates Block 284, Lot 9CA - Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 3:15 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Frank Coppola and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gates have debris (branches) wedged in them which is keeping them ajar. This is allowing water to enter the upstream system. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance The tide gates need to have the debris removed in order for them to work properly. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 97
94 Site ID/Name: Frank s Creek Tide Gates (Block: 284 Lot: 9ca) Date: 12/19/05 Time: 3:15 PM Tide Conditions: Low Photo 1 Description: Tide gate shown during low tide Hackensack Meadowlands Tide Gates Inspection Report Page 98
95 Site ID/Name: Frank s Creek Tide Gates (Block: 284 Lot: 9ca) Date: 12/19/05 Time: 3:15 PM Tide Conditions: Low Photo 2 Description: Debris (rock) shown lodged in-between the gate keeping it ajar Hackensack Meadowlands Tide Gates Inspection Report Page 99
96 Site ID/Name: Frank s Creek Tide Gates (Block: 284 Lot: 9ca) Date: 12/19/05 Time: 3:15 PM Tide Conditions: Low Photo 3 Description: Upstream view from the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 100
97 Site ID/Name: Location: Frank s Creek Tide Gates Block 284, Lot 9CA - Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 10:45 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Frank Coppola and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gates are not functioning properly. Water is seeping through during high tide conditions due to the tide gates not seating properly. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 101
98 Site ID/Name: Frank s Creek Tide Gates (Block: 284 Lot: 9ca) Date: 12/19/05 Time: 10:45 AM Tide Conditions: High Photo 1 Description: Notice water (bubbles) traveling upstream of the tide gate during high tide conditions Hackensack Meadowlands Tide Gates Inspection Report Page 102
99 Site ID/Name: Frank s Creek Tide Gates (Block: 284 Lot: 9ca) Date: 12/19/05 Time: 10:45 AM Tide Conditions: High Photo 2 Description: One of two metal flap gates Hackensack Meadowlands Tide Gates Inspection Report Page 103
100 Site ID/Name: Frank s Creek Tide Gates (Block: 284 Lot: 9ca) Date: 12/19/05 Time: 10:45 AM Tide Conditions: High Photo 3 Description: Upstream view from tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 104
101 Site ID/Name: Location: Harrison Avenue Tide Gates Harrison Avenue - Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 2:20 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro and Frank Coppola Type of Inspection: Yearly Post-Storm Complaint Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Notes On Condition/Problems: No problems observed. Catch Basin Culvert Outfall Other Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 105
102 Site ID/Name: Harrison Avenue Tide Gates (Block: 284 Lot: 2a-3b-3ba) Date: 12/13/05 Time: 2:20 PM Tide Conditions: Low Photo 1 Description: Tide gate structure Hackensack Meadowlands Tide Gates Inspection Report Page 106
103 Site ID/Name: Harrison Avenue Tide Gates (Block: 284 Lot: 2a-3b-3ba) Date: 12/13/05 Time: 2:20 PM Tide Conditions: Low Photo 2 Description: Downstream view from the tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 107
104 Site ID/Name: Location: Harrison Avenue Tide Gates Harrison Avenue - Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 2:45 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and Wai Lee Type of Inspection: Yearly Post-Storm Complaint Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Notes On Condition/Problems: No problems observed. Catch Basin Culvert Outfall Other Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 108
105 Site ID/Name: Harrison Avenue Tide Gates (Block: 284 Lot: 2a-3b-3ba) Date: 12/08/05 Time: 2:45 PM Tide Conditions: High Photo 1 Description: Tide gate structure Hackensack Meadowlands Tide Gates Inspection Report Page 109
106 Site ID/Name: Location: Standard Chlorine Tide Gate Rear parking lot of 1035 Belleville Turnpike Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 1:15 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: John Enquist and Steve Spero Keen Environmental: Matthew Sweed Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Tide gate appears to be functioning properly. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 110
107 Site ID/Name: Standard Chlorine Tide Gate (Block: 287 Lot: 49) Date: 12/28/05 Time: 1:15 PM Tide Conditions: Low Photo 1 Description: Metal flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 111
108 Site ID/Name: Location: Standard Chlorine Tide Gate Rear parking lot of 1035 Belleville Turnpike Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 8:30 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: John Enquist Keen Environmental: Matthew Sweed Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Tide gate appears to be functioning properly. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 112
109 Site ID/Name: Standard Chlorine Tide Gate (Block: 287 Lot: 79) Date: 12/28/05 Time: 8:30 AM Tide Conditions: High Photo 1 Description: Side view of tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 113
110 Memorandum To: Nicolas Agnoli From: Wai Lee Cc: File Date: February 6, 2006 Re: Trumbull Asphalt Tide Gate New Jersey Meadowlands Commission The tide gates in the property of Owens-Corning Fiberglas Corporation, located on 1249 Newark Turnpike, Kearny, were inspected on December 16, 2005 during high tide conditions and January 6, 2006 during low tide conditions. Two headwalls were found during the inspection but no additional structures were visible. Additionally, site plans from GEOD Consulting did not reveal any tide gate structures at the headwalls. The water elevation in the vicinity of the headwalls did not change regardless of the tidal conditions. After a detailed analysis of the topographic data and aerial mapping, NJMC has determined tidal water cannot reach the headwalls. Therefore, it is recommended that the Trumbull Asphalt Tide Gate no longer be inspected or considered to be part of the District s flood control system. Hackensack Meadowlands Tide Gates Inspection Report Page 114
111 Site ID/Name: Location: Trumbull Asphalt Tide Gate 1249 Newark Turnpike File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 8:45 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: John Enquist and Bob Segro Owen Corning: Raul Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Headwalls were found during the inspection. The tide gate can not be found due to stagnant water around the structures. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Confirm the removal of the tide gates. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 115
112 Site ID/Name: Trumbull Asphalt (Block: 287 Lot: 67) Date: 1/6/06 Time: 8:45 AM Photo 1 Description: Location of possible submersed tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 116
113 Site ID/Name: Trumbull Asphalt (Block: 287 Lot: 67) Date: 1/6/06 Time: 8:45 AM Photo 2 Description: Possible location of a old tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 117
114 Site ID/Name: Location: Trumbull Asphalt Tide Gates 1249 Newark Turnpike - Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:15 AM / PM Conditions: Cloudy (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Wai Lee and John Enquist Owens Corning: Jeff Wawrzeniak Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Located the headwall and sump pump. There were no tide gates visible at the time of the inspection. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Jeff stated he was unaware of any tide gate structures located within the property. Hackensack Meadowlands Tide Gates Inspection Report Page 118
115 Site ID/Name: Trumbull Asphalt (Block: 287 Lot: 67) Date: 12/16/05 Time: 9:15 AM Photo 1 Description: Sump pump system Hackensack Meadowlands Tide Gates Inspection Report Page 119
116 Site ID/Name: Trumbull Asphalt (Block: 287 Lot: 67) Date: 12/16/05 Time: 9:15 AM Photo 2 Description: Location of old headwall Hackensack Meadowlands Tide Gates Inspection Report Page 120
117 Site ID/Name: Trumbull Asphalt (Block: 287 Lot: 67) Date: 12/16/05 Time: 9:15 AM Photo 3 Description: Possible location of tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 121
118 Site ID/Name: Location: USPS Tide Gate 1200 Harrison Avenue - Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 1:55 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro and Frank Coppola Type of Inspection: Yearly Post-Storm Complaint Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Notes On Condition/Problems: No problems observed. Catch Basin Culvert Outfall Other Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 122
119 Site ID/Name: USPS Tide Gate (Block: 275 Lot: 1) Date: 12/13/05 Time: 1:55 PM Tide Conditions: Low Photo 1 Description: Metal flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 123
120 Site ID/Name: Location: USPS Tide Gate 1200 Harrison Avenue - Kearny File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 2:45 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and Wai Lee Type of Inspection: Yearly Post-Storm Complaint Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Notes On Condition/Problems: No problems observed. Catch Basin Culvert Outfall Other Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 124
121 Site ID/Name: USPS Tide Gate (Block: 275 Lot: 1) Date: 12/08/05 Time: 2:45 PM Tide Conditions: High Photo 1 Description: Metal flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 125
122 Site ID/Name: USPS Tide Gate (Block: 275 Lot: 1) Date: 12/08/05 Time: 2:45 PM Tide Conditions: High Photo 2 Description: Upstream view from the tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 126
123 Site ID/Name: USPS Tide Gate (Block: 275 Lot: 1) Date: 12/08/05 Time: 2:45 PM Tide Conditions: High Photo 3 Description: Box culvert downstream from gate Hackensack Meadowlands Tide Gates Inspection Report Page 127
124
125 Site ID/Name: Location: DePeyster Creek Pump Station and Tide Gate Located at the end of Dietrich Street Little Ferry File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:30 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Nicholas Agnoli and Wai Lee Little Ferry DPW: Mike Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: DePeyster Pump Station has been completely refurbished by J. Fletcher Creamer. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance A regular debris removal schedule has been followed by the Little Ferry DPW. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 129
126 Site ID/Name: DePeyster Creek Pump Station and Tide Gate (Block: 107 Lot: 2.01) Date: 12/21/05 Time: 9:30 AM Tide Conditions: Low Photo 1 Description: View of tide gate and the outlet pipes for the pump station Hackensack Meadowlands Tide Gates Inspection Report Page 130
127 Site ID/Name: DePeyster Creek Pump Station and Tide Gate (Block: 107 Lot: 2.01) Date: 12/21/05 Time: 9:30 AM Tide Conditions: Low Photo 2 Description: Downstream view from the pump station Hackensack Meadowlands Tide Gates Inspection Report Page 131
128 Site ID/Name: DePeyster Creek Pump Station and Tide Gate (Block: 107 Lot: 2.01) Date: 12/21/05 Time: 9:30 AM Tide Conditions: Low Photo 3 Description: Upstream view from pump station Hackensack Meadowlands Tide Gates Inspection Report Page 132
129 Site ID/Name: DePeyster Creek Pump Station and Tide Gate (Block: 107 Lot: 2.01) Date: 12/21/05 Time: 9:30 AM Tide Conditions: Low Photo 4 Description: View of generator system Hackensack Meadowlands Tide Gates Inspection Report Page 133
130 Site ID/Name: Location: Losen Slote Pump Station and Tide Gates Empire Boulevard (Block 106, Lot 3.01) Little Ferry File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 10:00 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Nicholas Agnoli and Wai Lee Little Ferry DPW: Mike Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Currently there is a removal of debris 6-7 times a year. Maintenance on generators is performed 3 times a year. The Little Ferry DPW performs a system check every Tuesday for an hour. The pump system needs an aerator system due to problems with ice in the winter. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Make sure that the debris is routinely removed. Install aerator system per DPW recommendation. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 134
131 Site ID/Name: Losen Slote Pump Station and Tide Gates (Block: 106 Lot: 3.01) Date: 12/21/05 Time: 10:00 AM Tide Conditions: Low Photo 1 Description: View of trash racks at in-take structure Hackensack Meadowlands Tide Gates Inspection Report Page 135
132 Site ID/Name: Losen Slote Pump Station and Tide Gates (Block: 106 Lot: 3.01) Date: 12/21/05 Time: 10:00 AM Tide Conditions: Low Photo 2 Description: Looking downstream at pump system Hackensack Meadowlands Tide Gates Inspection Report Page 136
133 Site ID/Name: Losen Slote Pump Station and Tide Gates (Block: 106 Lot: 3.01) Date: 12/21/05 Time: 10:00 AM Tide Conditions: Low Photo 3 Description: Upstream view from the pump station Hackensack Meadowlands Tide Gates Inspection Report Page 137
134 Site ID/Name: Losen Slote Pump Station and Tide Gates (Block: 106 Lot: 3.01) Date: 12/21/05 Time: 10:00 AM Tide Conditions: Low Photo 4 Description: View of pumps Hackensack Meadowlands Tide Gates Inspection Report Page 138
135
136 Site ID/Name: Location: West Riser Tide Gates 7 Purcell Court - Moonachie File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:50 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The cable system used for raising the gates is in poor shape and one cable has snapped completely. Undermining of the sheet pile cutoff must be investigated. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Drainage ditch needs to be cleaned out. The gates need cleaning and repairs made. Gates are timber and in the future may need to be replaced. A trash rack system also needs to be installed to keep debris out of the tide gates. The metal access walkway appears to be deteriorating and needs to be cleaned and repainted. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 140
137 Site ID/Name: West Riser Tide Gates (Block: 70 Lot: 7) Date: 12/08/05 Time: 9:50 AM Tide Conditions: Low Photo 1 Description: 4 timber tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 141
138 Site ID/Name: West Riser Tide Gates (Block: 70 Lot: 7) Date: 12/08/05 Time: 9:50 AM Tide Conditions: Low Photo 2 Description: Upstream view from the gates Hackensack Meadowlands Tide Gates Inspection Report Page 142
139 Site ID/Name: West Riser Tide Gates (Block: 70 Lot: 7) Date: 12/08/05 Time: 9:50 AM Tide Conditions: Low Photo 3 Description: Downstream view from the gates Hackensack Meadowlands Tide Gates Inspection Report Page 143
140 Site ID/Name: Location: West Riser Tide Gates 7 Purcell Court - Moonachie File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 1:45 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Tide gates are not seating properly. Maintenance needs to be performed on the gates. The gates foundation is also being undermined Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Routine cleaning will help keep the gates operating properly. Gates may need to be replaced with metal flap gates in the future, currently they are timber. A trash rack system would also help to alleviate the collection of debris. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 144
141 Site ID/Name: West Riser Tide Gates (Block: 70 Lot: 7) Date: 12/21/05 Time: 1:45 PM Tide Conditions: High Photo 1 Description: 4 timber tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 145
142 Site ID/Name: West Riser Tide Gates (Block: 70 Lot: 7) Date: 12/21/05 Time: 1:45 PM Tide Conditions: High Photo 2 Description: Upstream view of trash rack system Hackensack Meadowlands Tide Gates Inspection Report Page 146
143 Site ID/Name: West Riser Tide Gates (Block: 70 Lot: 7) Date: 12/21/05 Time: 1:45 PM Tide Conditions: High Photo 3 Description: Downstream view from the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 147
144 Memorandum To: Nicolas Agnoli From: Wai Lee Cc: File Date: February 6, 2006 Re: Kingsland Creek Tide Gate New Jersey Meadowlands Commission The tide gate located to the west of the PSE&G sub-station on Disposal Road in North Arlington was inspected on December 8, 2005 during high tide conditions and December 19, 2005 during low tide conditions. A headwall was found during the inspection but no additional structures were visible. Additionally, site plans from GEOD Consulting did reveal the existing metal flap was removed subsequent to field investigation after their project with the Army Corps of Engineers in After analyzing the survey from GEOD Consulting and NJMC s field investigation, it is recommended that the Kingsland Creek Tide Gate no longer be inspected or considered to be part of the District s flood control system. Hackensack Meadowlands Tide Gates Inspection Report Page 149
145 Site ID/Name: Location: Kingsland Creek Tide Gates NJMC Erie Landfill Facility Disposal Road North Arlington File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 3:35 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Frank Coppola and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Tide gates appear to have been removed. All that remains is the existing headwall and pipes that they were attached to. The tide gates are to be decommissioned. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 150
146 Site ID/Name: Kingsland Creek Tide Gate (Block: 193 Lot: 1) Date: 12/19/05 Time: 3:35 PM Tide Conditions: Low Photo 1 Description: Location of removed tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 151
147 Site ID/Name: Location: Kingsland Creek Tide Gate Disposal Road - PSE&G Sub-Stations North Arlington File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 3:15 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro, Frank Coppola, and Wai Lee Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Tide gate was removed according to a microstation drawing file from Army Corps of Engineers. This information could not be verified during high tide conditions. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 152
148 Site ID/Name: Kingsland Creek Tide Gate (Block: 193 Lot: 1) Date: 12/08/05 Time: 3:15 PM Tide Conditions: High Photo 1 Description: Tide gate structure Hackensack Meadowlands Tide Gates Inspection Report Page 153
149
150 Site ID/Name: Location: Overpeck Creek Tide Gates Between the northbound and southbound roadways of the NJ Turnpike File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:15 AM / PM Conditions: Sunny (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Wai Lee and Nicholas Agnoli Bergen County Engineering: Rocky Menzella Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Maintenance Required: Immediate Repair Continued Upkeep Notes On Condition/Problems: During the rehabilitation of Overpeck Creek tidal dam, the following work was accomplished: addition of new control building of the dam, addition of a new generator building northeast of the dam, extensive refurbishment of existing gate building, modification and refurbishment of piers, new radial gates and embedded metal work, new radial gate hoists, new bascule gates and embedded metalwork, new bascule gate operators and hydraulic power unit, new heating system for deicing gate wall plates, new wooden stanchion gates and embedded metalwork, new computerized control equipment and software and new reinforced cut-off wall to reduce seepage beneath the dam. Gate operation is fully automated. Notes on Maintenance The system is in excellent condition. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 155
151 Site ID/Name: Overpeck Creek Tide Gates (Block: 4005 Lot: 1) Date: 1/20/06 Time: 9:15 AM Tide Conditions: Low Photo 1 Description: View of the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 156
152 Site ID/Name: Overpeck Creek Tide Gates (Block: 4005 Lot: 1) Date: 1/20/06 Time: 9:15 AM Tide Conditions: Low Photo 2 Description: Overview of entire structure Hackensack Meadowlands Tide Gates Inspection Report Page 157
153 Site ID/Name: Overpeck Creek Tide Gates (Block: 4005 Lot: 1) Date: 1/20/06 Time: 9:15 AM Tide Conditions: Low Photo 3 Description: View of bascule tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 158
154 Site ID/Name: Location: Rutherford Tide Gates Adjacent to 299 Thomas E. Dunn Memorial Highway File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 3:00 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Frank Coppola and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Water continues to seep through the gates and enter the upstream system. Of the five original designed 3 foot pipes, only three are functional and they are partially silted with their flap gates in varying degrees of damage. Two of the flap gates (culvert no. 4 and 5) have been welded closed. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Army Corps is currently in the design phase of replacing the tide gates. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 160
155 Site ID/Name: Rutherford Tide Gates (Block: 227 Lot: 1) Date: 12/19/05 Time: 3:00 PM Tide Conditions: Low Photo 1 Description: View of tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 161
156 Site ID/Name: Rutherford Tide Gates (Block: 227 Lot: 1) Date: 12/19/05 Time: 3:00 PM Tide Conditions: Low Photo 2 Description: Upstream view from the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 162
157 Site ID/Name: Rutherford Tide Gates (Block: 227 Lot: 1) Date: 12/19/05 Time: 3:00 PM Tide Conditions: Low Photo 3 Description: Downstream view from the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 163
158 Site ID/Name: Location: Rutherford Tide Gates Adjacent to 299 Thomas E. Dunn Memorial Highway File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 10:00 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Frank Coppola and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Water continues to seep through the gates and enter the upstream system. Of the five original designed 3 foot pipes, only three are functional and they are partially silted with their flap gates in varying degrees of damage. Two of the flap gates (culvert no. 4 and 5) have been welded closed. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Army Corps is currently in the design phase of replacing the tide gates. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 164
159 Site ID/Name: Rutherford Tide Gates (Block: 227 Lot: 1) Date: 12/19/05 Time: 10:00 AM Tide Conditions: High Photo 1 Description: Location of the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 165
160 Site ID/Name: Rutherford Tide Gates (Block: 227 Lot: 1) Date: 12/19/05 Time: 10:00 AM Tide Conditions: High Photo 2 Description: Upstream view from the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 166
161 Site ID/Name: Rutherford Tide Gates (Block: 227 Lot: 1) Date: 12/19/05 Time: 10:00 AM Tide Conditions: High Photo 3 Description: Downstream view from the tide gates Hackensack Meadowlands Tide Gates Inspection Report Page 167
162 Site ID/Name: Location: Acorn Road Tide Gate Acorn River Playground & Secaucus Greenway File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 2:045 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro and Frank Coppola Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Tide gate appears to be in good condition and functioning properly. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 170
163 Site ID/Name: Acorn Road Tide Gate (Block: 203 Lot: 19.02) Date: 1/30/06 Time: 2:45 PM Tide Conditions: Low Photo 1 Description: Downstream view from the tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 171
164 Site ID/Name: Acorn Road Tide Gate (Block: 203 Lot: 19.02) Date: 1/30/06 Time: 2:45 PM Tide Conditions: Low Photo 2 Description: Location of the tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 172
165 Site ID/Name: Acorn Road Tide Gate (Block: 203 Lot: 19.02) Date: 1/30/06 Time: 2:45 PM Tide Conditions: Low Photo 3 Description: Upstream view from the tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 173
166 Site ID/Name: Location: Acorn Road Tide Gate Next to Secaucus High School baseball field File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:20 AM / PM Conditions: Cloudy (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Wai Lee, Nicholas Agnoli, and Bob Segro Secaucus DPW: Ed Rosen and Kevin Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Site contains one 30-inch metal flap gate. It appears to seal properly. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: This tide gate serves the drainage ditch from 236 Meadow Lane to the Hackensack River. Hackensack Meadowlands Tide Gates Inspection Report Page 174
167 Site ID/Name: Acorn Road Tide Gate (Block: 203 Lot: 19.02) Date: 1/13/06 Time: 9:20 AM Tide Conditions: High Photo 1 Description: Upstream view from tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 175
168 Site ID/Name: Acorn Road Tide Gate (Block: 203 Lot: 19.02) Date: 1/13/06 Time: 9:20 AM Tide Conditions: High Photo 2 Description: Location of tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 176
169 Site ID/Name: Location: Born Street Tide Gate and Pump Station Located at the end of Born Street - Secaucus File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 8:30 AM / PM Conditions: Cloudy (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Wai Lee, Nicholas Agnoli, and Bob Segro Secaucus DPW: Ed Rosen and Kevin Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The site contains a diesel emergency power generator, three pumps that are located inside the pump house, one Godwin back-up pump system, and two 48-inch flap gates that are connected in series. Access is restricted to the site due to a locked gate Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 177
170 Site ID/Name: Born Street Tide Gate and Pump Station (Block: 163 Lot: 1.01) Date: 1/13/06 Time: 8:30 AM Tide Conditions: High Photo 1 Description: Pump station outlet pipes Hackensack Meadowlands Tide Gates Inspection Report Page 178
171 Site ID/Name: Born Street Tide Gate and Pump Station (Block: 163 Lot: 1.01) Date: 1/13/06 Time: 8:30 AM Tide Conditions: High Photo 2 Description: First 48-inch metal flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 179
172 Site ID/Name: Born Street Tide Gate and Pump Station (Block: 163 Lot: 1.01) Date: 1/13/06 Time: 8:30 AM Tide Conditions: High Photo 3 Description: Second 48-inch metal flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 180
173 Site ID/Name: Born Street Tide Gate and Pump Station (Block: 163 Lot: 1.01) Date: 1/13/06 Time: 8:30 AM Tide Conditions: High Photo 4 Description: Godwin diesel back-up pump Hackensack Meadowlands Tide Gates Inspection Report Page 181
174 Site ID/Name: Born Street Tide Gate and Pump Station (Block: 163 Lot: 1.01) Date: 1/13/06 Time: 8:30 AM Tide Conditions: High Photo 5 Description: View of emergency power generator Hackensack Meadowlands Tide Gates Inspection Report Page 182
175 Site ID/Name: Location: Farm Road Tide Gates West end of Riverview Garden Complex - Secaucus File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 10:30 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Wai Lee, Nicholas Agnoli, and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gates at this location are not seating properly. The two gates are both metal flap gates. They are in a concrete chamber which is covered by unlocked steel grating. The tide gates are in series and appear to be redundant. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Gated access needs to be added at this location. The chamber in which the gates are housed needs to be cleaned out and repaired. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 183
176 Site ID/Name: Farm Road Tide Gates (Block: 193 Lot: 1) Date: 12/22/05 Time: 10:30 AM Tide Conditions: Low Photo 1 Description: Upstream view from gates Hackensack Meadowlands Tide Gates Inspection Report Page 184
177 Site ID/Name: Farm Road Tide Gates (Block: 193 Lot: 1) Date: 12/22/05 Time: 10:30 AM Tide Conditions: Low Photo 2 Description: View of metal flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 185
178 Site ID/Name: Farm Road Tide Gates (Block: 193 Lot: 1) Date: 12/22/05 Time: 10:30 AM Tide Conditions: Low Photo 3 Description: View of tide gate chamber Hackensack Meadowlands Tide Gates Inspection Report Page 186
179 Memorandum To: Nicolas Agnoli From: Wai Lee Cc: File Date: February 6, 2006 Re: Golden Avenue Pump Station New Jersey Meadowlands Commission Golden Avenue Pump Station, located at the end of Golden Avenue in Secaucus, has not been inspected. The pump station system is currently in construction phase. Inspection is pending once construction is complete. Hackensack Meadowlands Tide Gates Inspection Report Page 187
180 Site ID/Name: Location: Koelle Boulevard Tide Gate Koelle Boulevard and Mill Ridge Road - Secaucus File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 10:30 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro and Frank Coppola Type of Inspection: Yearly Post-Storm Complaint Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Notes On Condition/Problems: No problems observed. Catch Basin Culvert Outfall Other Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 188
181 Site ID/Name: Koelle Boulevard Tide Gate (Block: 225 Lot: 4.02) Date: 12/12/05 Time: 10:30 AM Tide Conditions: Low Photo 1 Description: Tide gate structure Hackensack Meadowlands Tide Gates Inspection Report Page 189
182 Site ID/Name: Koelle Boulevard Tide Gate (Block: 225 Lot: 4.02) Date: 12/12/05 Time: 10:30 AM Tide Conditions: Low Photo 2 Description: Downstream view from the tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 190
183 Site ID/Name: Location: Koelle Boulevard Tide Gate Koelle Boulevard and Mill Ridge Road Secaucus File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:55 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Frank Coppola and Bob Segro Type of Inspection: Yearly Post-Storm Complaint Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Notes On Condition/Problems: No problems observed. Catch Basin Culvert Outfall Other Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Keep the tide gate clear of any debris. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 191
184 Site ID/Name: Koelle Boulevard Tide Gate (Block: 225 Lot: 4.02) Date: 12/13/05 Time: 9:55 AM Tide Conditions: High Photo 1 Description: Tide gate structure shown during ice conditions Hackensack Meadowlands Tide Gates Inspection Report Page 192
185 Site ID/Name: Location: Meadowlands Parkway Tide Gate Meadowlands Parkway Armada Hess Property - Secaucus File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 8:30 AM / PM Conditions: Cloudy (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: John Enquist and Bob Segro Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The site contains a Tideflex TM check valve; it appears to be functional during low tide conditions. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 193
186 Site ID/Name: Meadowlands Parkway Tide Gate (Block: 100 Lot: 2) Date: 2/6/06 Time: 8:30 AM Tide Conditions: Low Photo 1 Description: Downstream view from tide gate Hackensack Meadowlands Tide Gates Inspection Report Page 194
187 Site ID/Name: Meadowlands Parkway Tide Gate (Block: 100 Lot: 2) Date: 2/6/06 Time: 8:30 AM Tide Conditions: Low Photo 2 Description: Tideflex TM check valve Hackensack Meadowlands Tide Gates Inspection Report Page 195
188 Site ID/Name: Location: Mill Ridge Road Tide Gate Behind 17 and 23 Mill Ridge Road Secaucus File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 11:30 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Bob Segro and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gate appears to seat properly. The gate is attached directly to storm drains located on Mill Ridge Road. In order to know if the gate is functional an inspection needs to be completed during a rain event to see if the gate opens. One of the tide gates found is located behind the property of 17 Mill Ridge Road. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance The hinges located on the gate appear to be rusted and need to be cleaned and lubricated. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 196
189 Site ID/Name: Mill Ridge Road Tide Gate (Block: 226 Lot: 20 & 23) Date: 1/25/06 Time: 11:30 AM Tide Conditions: Low Photo 1 Description: Metal flap gate shown Hackensack Meadowlands Tide Gates Inspection Report Page 197
190 Site ID/Name: Location: Penhorn Creek Pump Station Intersection of Secaucus Road and Penhorn Avenue -Secaucus File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:20 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Wai Lee, Nicholas Agnoli, and John Enquist Hudson County Roads Department: Helmut Mross Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The pump station could not be started during the time of the inspection due to the primer pipe being severed. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Primer pipe must be replaced. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 198
191 Site ID/Name: Penhorn Creek Pump Station (Block: 63 Lot: 2) Date: 12/22/05 Time: 9:20 AM Tide Conditions: Low Photo 1 Description: View of pump station Hackensack Meadowlands Tide Gates Inspection Report Page 199
192 Site ID/Name: Penhorn Creek Pump Station (Block: 63 Lot: 2) Date: 12/22/05 Time: 9:20 AM Tide Conditions: Low Photo 2 Description: View of pump Hackensack Meadowlands Tide Gates Inspection Report Page 200
193 Site ID/Name: Penhorn Creek Pump Station (Block: 63 Lot: 2) Date: 12/22/05 Time: 9:20 AM Tide Conditions: Low Photo 3 Description: Upstream view from pump station Hackensack Meadowlands Tide Gates Inspection Report Page 201
194 Site ID/Name: Penhorn Creek Pump Station (Block: 63 Lot: 2) Date: 12/22/05 Time: 9:20 AM Tide Conditions: Low Photo 4 Description: Downstream view from pump station Hackensack Meadowlands Tide Gates Inspection Report Page 202
195 Site ID/Name: Location: River Road Tide Gates and Pump Station Intersection of River Road and Acorn Road File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 8:50 AM / PM Conditions: Cloudy (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Wai Lee, Nicholas Agnoli, and Bob Segro Secaucus DPW: Ed Rosen and Kevin Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Maintenance Required: Immediate Repair Continued Upkeep Notes On Condition/Problems: Site contains one diesel Godwin back-up pump. There is restricted access to the site due to a locked gate. During the time of the inspection, the outfall was submerged. There are two tide gates located in a concrete vault in series. The gates are 30-inch metal flap gates. The tide gates appear to seat properly. In addition to the vault, there is a Tideflex TM check valve located at the discharge point on the Hackensack River. The pump wet well is between the metal tide gates and Tideflex. Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 203
196 Site ID/Name: River Road Tide Gates and Pump Station (Block: 195 Lot: 5) Date: 1/13/06 Time: 8:50 AM Tide Conditions: High Photo 1 Description: 1 st 30-inch flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 204
197 Site ID/Name: River Road Tide Gates and Pump Station (Block: 195 Lot: 5) Date: 1/13/06 Time: 8:50 AM Tide Conditions: High Photo 2 Description: 2 nd 30-inch flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 205
198 Site ID/Name: River Road Tide Gates and Pump Station (Block: 195 Lot: 5) Date: 1/13/06 Time: 8:50 AM Tide Conditions: High Photo 3 Description: View of submersible pump Hackensack Meadowlands Tide Gates Inspection Report Page 206
199 Site ID/Name: River Road Tide Gates and Pump Station (Block: 195 Lot: 5) Date: 1/13/06 Time: 8:50 AM Tide Conditions: High Photo 4 Description: Godwin back-up pump Hackensack Meadowlands Tide Gates Inspection Report Page 207
200 Site ID/Name: Location: Route 3 West Tide Gate 650 Route 3 West Royal Motel Secaucus File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 2:30 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Frank Coppola and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The tide gate appears to be working properly. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance There is limited access to the site due to a locked gate. The vegetation needs to be maintained regularly. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 208
201 Site ID/Name: Route 3 West Tide Gate (Block: 180 Lot: 23) Date: 12/19/05 Time: 2:30 PM Tide Conditions: Low Photo 1 Description: 1 metal flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 209
202 Site ID/Name: Location: Route 3 West D.O.T. Tide Gate 650 Route 3 West Royal Motel Secaucus File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:25 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Frank Coppola and Bob Segro Type of Inspection: Yearly Post-Storm Complaint Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Notes On Condition/Problems: No problems observed. Catch Basin Culvert Outfall Other Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Upstream view obstructed by vegetation. Hackensack Meadowlands Tide Gates Inspection Report Page 210
203 Site ID/Name: Route 3 West Tide Gate (Block: 180 Lot: 23) Date: 12/13/05 Time: 9:25 AM Tide Conditions: High Photo 1 Description: 1 metal flap gate Hackensack Meadowlands Tide Gates Inspection Report Page 211
204 Site ID/Name: Location: Secaucus High School Pump Station Located on the Secaucus High School s property File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:30 AM / PM Conditions: Cloudy (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Wai Lee, Nicholas Agnoli, and Bob Segro Secaucus DPW: Ed Rosen and Kevin Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The site contains three submersible pumps and one Godwin diesel back-up pump. The site is restricted by a locked fence and may be accessed with Secaucus DPW. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 212
205 Site ID/Name: Secaucus High School Pump Station (Block: 226 Lot: 17.01) Date: 1/13/06 Time: 9:30 AM Tide Conditions: High Photo 1 Description: View of outlet pipes Hackensack Meadowlands Tide Gates Inspection Report Page 213
206 Site ID/Name: Secaucus High School Pump Station (Block: 226 Lot: 17.01) Date: 1/13/06 Time: 9:30 AM Tide Conditions: High Photo 2 Description: View of pump systems Hackensack Meadowlands Tide Gates Inspection Report Page 214
207 Site ID/Name: Secaucus High School Pump Station (Block: 226 Lot: 17.01) Date: 1/13/06 Time: 9:30 AM Tide Conditions: High Photo 3 Description: Godwin diesel back-up pump system Hackensack Meadowlands Tide Gates Inspection Report Page 215
208 Site ID/Name: Location: St. Paul s Avenue Tide Gate and Pump Station PSE&G Plant - Secaucus File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 10:00 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Wai Lee, Nicholas Agnoli, and John Enquist Hudson County Roads Department: Helmut Mross Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: The pumps are used only during large storm events. The pumps can only be operated manually as the float switches are not functional. The priming pumps do not shut off automatically due to the elevation of the pump system being to low. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance The system is in need of new pumps. Self priming pumps would be the best type to install at this location. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 216
209 Site ID/Name: St. Paul s Avenue Tide Gate and Pump Station (Block: 1200 Lot: 51) Date: 12/22/05 Time: 10:00 AM Tide Conditions: Low Photo 1 Description: Metal flap gate shown closed Hackensack Meadowlands Tide Gates Inspection Report Page 217
210 Site ID/Name: St. Paul s Avenue Tide Gate and Pump Station (Block: 1200 Lot: 51) Date: 12/22/05 Time: 10:00 AM Tide Conditions: Low Photo 2 Description: Pump discharge pipes Hackensack Meadowlands Tide Gates Inspection Report Page 218
211 Site ID/Name: St. Paul s Avenue Tide Gate and Pump Station (Block: 1200 Lot: 51) Date: 12/22/05 Time: 10:00 AM Tide Conditions: Low Photo 3 Description: Pump station facility Hackensack Meadowlands Tide Gates Inspection Report Page 219
212 Site ID/Name: St. Paul s Avenue Tide Gate and Pump Station (Block: 1200 Lot: 51) Date: 12/22/05 Time: 10:00 AM Tide Conditions: Low Photo 4 Description: View of pumps Hackensack Meadowlands Tide Gates Inspection Report Page 220
213 Site ID/Name: St. Paul s Avenue Tide Gate and Pump Station (Block: 1200 Lot: 51) Date: 12/22/05 Time: 10:00 AM Tide Conditions: Low Photo 5 Description: Downstream view from the pump station facility Hackensack Meadowlands Tide Gates Inspection Report Page 221
214 Site ID/Name: St. Paul s Avenue Tide Gate and Pump Station (Block: 1200 Lot: 51) Date: 12/22/05 Time: 10:00 AM Tide Conditions: Low Photo 6 Description: Upstream view from the pump station facility Hackensack Meadowlands Tide Gates Inspection Report Page 222
215 Site ID/Name: Location: Syms Tide Gate Parking Lot of 1 Emerson Lane Secaucus File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:00 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Wai Lee, Nicholas Agnoli, and John Enquist Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: Flap gate is not seating properly. There is a piece of wood that is preventing the gate from functioning properly. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Remove the piece of wood. In order to access the tide gate, the inlet grate must be removed since the flap gate is located below grade. Other Notes: Hackensack Meadowlands Tide Gates Inspection Report Page 223
216 Site ID/Name: Location: Teterboro Pump Station Located at the end of Vincent Place - Teterboro File No.: SP-501 Tide Conditions: (Low, High) Date: Time: 9:00 AM / PM Conditions: Clear (Rain, Snow, High Wind, High/Low Tide, etc.) Inspected By: NJMC: Nicholas Agnoli and Wai Lee Teterboro DPW: John Fantacone Type of Inspection: Yearly Post-Storm Complaint System Designation: Tide Gate Drainage Ditch Natural Stream Pump System Catch Basin Culvert Outfall Other Overall Functionality:. Fully Functional Functional with Restrictions Non-Functional Notes On Condition/Problems: A new pump station is currently being constructed. The current conditions are: 3 out of 4 pumps function, 1 out of 4 tide gates function. The two tide gates that function at discharge are seating properly. Maintenance Required: Immediate Repair Continued Upkeep Notes on Maintenance Trash racks are clean and are in good condition. The construction by-pass appears to be undersized. The pump house is in good condition with a functional alarm system. Access needs to be cleared to all system components. The pumps were maintained as follows: pump #1 in 2006, pump # 2 in 2005 and pump #3 in Other Notes: The current system is to be taken out of service in Hackensack Meadowlands Tide Gates Inspection Report Page 225
217 Site ID/Name: Teterboro Pump Station (Block: 201 Lot: 12) Date: 12/21/05 Time: 9:00 AM Tide Conditions: Low Photo 1 Description: Flap gates shown on outlet structure Hackensack Meadowlands Tide Gates Inspection Report Page 226
218 Site ID/Name: Teterboro Pump Station (Block: 201 Lot: 12) Date: 12/21/05 Time: 9:00 AM Tide Conditions: Low Photo 2 Description: In-flow at pump station Hackensack Meadowlands Tide Gates Inspection Report Page 227
219 Site ID/Name: Teterboro Pump Station (Block: 201 Lot: 12) Date: 12/21/05 Time: 9:00 AM Tide Conditions: Low Photo 3 Description: View of pumps Hackensack Meadowlands Tide Gates Inspection Report Page 228
220 Site ID/Name: Teterboro Pump Station (Block: 201 Lot: 12) Date: 12/21/05 Time: 9:00 AM Tide Conditions: Low Photo 4 Description: Downstream view from the pump station Hackensack Meadowlands Tide Gates Inspection Report Page 229
221 Site ID/Name: Teterboro Pump Station (Block: 201 Lot: 12) Date: 12/21/05 Time: 9:00 AM Tide Conditions: Low Photo 5 Description: Upstream view from the pump station Hackensack Meadowlands Tide Gates Inspection Report Page 230
Homeowner s Guide to Drainage
Homeowner s Guide to Drainage a scottsdale homeowner s guide to drainage produced by the city of scottsdale s stormwater management division Transportation Department TABLE OF CONTENTS Introduction 2 Drainage
Appendix F: Bergen County Letters of Intent
Appendix F: Letters of Intent Appendix F: Letters of Intent Multi Jurisdictional All hazards Mitigation Plan Update 2014 Page F 1 LOI s Submitted Under Hurricane Sandy DR 4086 Applicant Name Type Title
PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013
PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 NAME LOCATION Audubon Properties, LLC. 4700 & 4960 Dauphin Island Parkway West side of Dauphin Island Parkway, 580
CASE STUDY. City of Grand Rapids Stormwater Asset Management Program. City of Grand Rapids. By the Numbers
United States Environmental Protection Agency CASE STUDY City of Grand Rapids Stormwater Asset Management Program Overview With increasing pressure to meet water quality targets, address population growth,
Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can
Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can do his or her share to protect Ohio's water resources
DRAINAGE :: DRAINAGE CONCERN FREQUENTLY ASKED QUESTIONS
DRAINAGE :: DRAINAGE CONCERN FREQUENTLY ASKED QUESTIONS The City of DeSoto s Department of Development Services is the point of contact for storm drainage related issues. The following are some frequently
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA April 17, 2013 Goal To develop a basic understanding of PA Department of Environmental Protection (DEP) and US Army Corps of Engineers
Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control
Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Project Name: Tax Map Parcel: Acreage: Plat: ADC Map & Grid Engineering
City of Shelbyville Site Inspection Checklist
City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather
COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY
COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY Revised: April 2014 Village of Wilmette, Illinois NPDES CSO Permit No. ILM580012 Chapter 1 Introduction This Operational and Maintenance
Lisgar District Basement Water Infiltration Investigation Answers to Residents Written Questions Received by Councillors Ward 10 Office
Lisgar District Basement Water Infiltration Investigation Part A Answers to Technical Questions 1. There has been a tremendous amount of work done everywhere along the creek. If there was nothing wrong
5.14 Floodplains and Drainage/Hydrology
I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important
Prattsville Berm Removal Project. 1.0 Project Location
Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed
First in Service First in Safety
7840 Nagle Avenue Morton Grove, Illinois 60053 847-470-5235 Fax - 847-965-9511 Wind Damage; Frequently Asked Questions: What can I do with branches that fall in my yard? Bring them out to the parkway;
FINAL TECHNICAL MEMORANDUM AWD-00002 FLOWS THROUGH FLOOD DAMAGE REDUCTION AREA July 16, 2012
FINAL TECHNICAL MEMORANDUM AWD-00002 FLOWS THROUGH FLOOD DAMAGE REDUCTION AREA July 16, 2012 Table of Contents TABLE OF CONTENTS Table of Contents... 1 Executive Summary... 2 1 Objective... 4 2 Study Approach...
Vermont Economic Resiliency Initiative (VERI) Community Forum Barre City & Barre Town
Vermont Economic Resiliency Initiative (VERI) Community Forum Barre City & Barre Town MEETING NOTES April 16, 2015 6:00 8:00 PM VERI Project Overview With funding from the US Economic Development Administration
Tookany Creek Flood Damage Reduction Feasibility Study Section 205 Continuing Authorities Program
Tookany Creek Flood Damage Reduction Feasibility Study Section 205 Continuing Authorities Program Field Inspection Notes 27 29 September 2012 Introduction The U.S. Army Corps of Engineers (Corps), in
Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile
Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality
ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND
ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND The Rose Creek Watershed (RCW) consists of three planning
Mission Creek Flood Control & Restoration Project. City of Fremont, Alameda County
Mission Creek Flood Control & Restoration Project City of Fremont, Alameda County Agenda Background Why are proposed improvements necessary? Proposed project components Challenges Construction schedule/phasing
Building Olive s Flood Resiliency
Building Olive s Flood Resiliency Informed Flood Mitigation Planning The Local Flood Analysis Flood Advisory Committee Meeting #1 Town of Olive s Community Room 4/14/15 What is an LFA? 1. Uses science
STORMWATER MANAGEMENT CHECKLIST
STORMWATER MANAGEMENT CHECKLIST *This checklist must be completed and part of the Land Disturbing Permit submittal for review if the acreage disturbed is one (1) acre or more: I. SUPPORTING DATA Narrative
Standard Operating Procedures for Flood Preparation and Response
Standard Operating Procedures for Flood Preparation and Response General Discussion Hurricanes, tropical storms and intense thunderstorms support a conclusion that more severe flooding conditions than
Structural Damage Due to Floods
Structural Damage Due to Floods By Craig D. Rogers, P.E. The Federal Emergency Management Agency (FEMA) reports that each year approximately 90 percent of all disaster-related property damage results from
London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document
LOCAL FLOOD RISK MANAGEMENT STRATEGY Summary Document October 2013 Local Flood Risk Management Strategy Summary 1 Introduction 2 Partner responsibilities 3 What do we know about flooding in the borough?
Preventing Storm Water Pollution: What We Can Do
Preventing Storm Water Pollution: What We Can Do ~Employee Training Series~ Streets and Drainage Maintenance PREPARED IN COOPERATION WITH THE Texas Commission on Environmental Quality AND U.S. ENVIRONMENTAL
Lower Raritan Watershed Management Area Stormwater & Flooding Subcommittee Strategy Worksheet LRSW-S3C1
Strategy Name: Reduce Existing Potential for Flood Damages LRSW-S3C1. Develop and implement a program to: Minimize flood damages through the use of structural measures. Minimize flood damages through the
Standard Operating Procedures Storm Drain System Maintenance
s Storm Drain System Maintenance SECTIONS 1. Storm Drain System Inspections 2. Storm Drain System Cleaning 3. Storm Drain System Repairs 4. Proper Disposal of Material Storm Sewer System Cleaning Directive
3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN
3.4 DRAINAGE PLAN This section describes the existing onsite drainage characteristics and improvements proposed within this Specific Plan. Following this description, drainage plan development standards
Type of Sewer Systems. Solomon Seyoum
Type of Sewer Systems Solomon Seyoum 0 Learning objectives Upon completion of this lecture, the participants will be able to differentiate between types of sewer systems and discuss different aspects of
CHAPTER 7 DRAINAGE OF PAVEMENTS
CHAPTER 7 DRAINAGE OF PAVEMENTS 7-1. Drainage control Adequate drainage of surface and ground water is one of the most important considerations in the design, construction, and maintenance of roads, railroads,
Harris County Flood Control District. Policy, Criteria, and Procedure Manual
Harris County Flood Control District Policy, Criteria, and Procedure Manual For Approval and Acceptance of Infrastructure General Review October 10, 2003 Draft Please Provide Written Comments to the HCFCD
JULY 24, 2009 WEST-END FLOODING INVESTIGATION ACTION PLAN. Presentation to Insurance Companies 19 January 2012
JULY 24, 2009 WEST-END FLOODING INVESTIGATION ACTION PLAN Presentation to Insurance Companies 19 January 2012 Topics of Discussion Investigation Levels of Service Cause of Flooding Analysis Undertaken
Estabrook Dam A Discussion of Alternatives. Public Scoping Meeting June 5, 2014
Estabrook Dam A Discussion of Alternatives Public Scoping Meeting June 5, 2014 Presenters Kevin Haley, PLA, Milwaukee County Don Pirrung, P.E., PH, AECOM Mike Hahn, P.E., PH, Southeastern Wisconsin Regional
CITY OF HIGHLAND PARK, ILLINOIS Stormwater Management Fact Sheet
CITY OF HIGHLAND PARK, ILLINOIS Stormwater Management Fact Sheet WHAT IS STORMWATER MANAGEMENT? Stormwater management is the method for channeling rainfall through pipes and sewers away from property to
Post-Flood Assessment
Page 1 of 7 Post-Flood Assessment CHAPTER 4 AGENCY COORDINATION Agency coordination is an essential element for the operation of the flood management systems in the Central Valley. Due to the nature of
later damage - Loss ControL
later damage - Loss ControL axisinsurance.ca Table of Contents EXECUTIVE SUMMARY... 1 FACILITY SYSTEMS WATER DAMAGE... 2 Frozen Pipes.....................................................................................
Protect your. home from. basement. have you done everything you can?
Protect your home from basement flooding have you done everything you can? No matter where you live in Winnipeg, your home can be at risk of basement flooding. Heavy rainstorms that fall over short periods
SECTION 5 DRAFTING STANDARDS
SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.
Activity Yes No N/A Notes
CE 2020 (Rev. 12/11) Page 1 of 5 PROJECT NAME AND SITE ADDRESS: CONTRACT NUMBER: ORACLE NUMBER: WDID NUMBER: CONTRACTOR NAME AND ADDRESS: PROJECT SITE RISK LEVEL: Risk Level 1 Risk Level 2 Risk Level 3
Flood Emergency Response Planning: How to Protect Your Business from a Natural Disaster RIC005
Flood Emergency Response Planning: How to Protect Your Business from a Natural Disaster RIC005 Speakers: Tom Chan, CEO, Global Risk Miyamoto Greg Bates, Principal, Global Risk Consultants Learning Objectives
HYDROLOGIC/HYDRAULIC MODELING OF WESTMINSTER WATERSHED ORANGE COUNTY, CALIFORNIA
HYDROLOGIC/HYDRAULIC MODELING OF WESTMINSTER WATERSHED ORANGE COUNTY, CALIFORNIA James Chieh, Ph.D., P.E., Senior Hydraulic Engineer, USACE, Los Angeles, California, [email protected]; Jay Pak,
Outlet stabilization structure
Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural
Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
LISGAR DISTRICT BASEMENT WATER INFILTRATION INVESTIGATION SUMMARY REPORT. Submitted to: City of Mississauga Mississauga, Ontario
LISGAR DISTRICT BASEMENT WATER INFILTRATION INVESTIGATION SUMMARY REPORT Submitted to: Mississauga, Ontario Submitted by: A division of Americas Limited 3215 North Service Road Burlington, ON L7N 3G2 Tel:
Chapter 4. Flood Control
Chapter 4. Flood Control As noted by their name, flood control measures control floodwaters and keep them from reaching damageable property. They are also called structural measures because they involve
CLIFTY CREEK PLANT MADISON, INDIANA
2015 DAM AND DIKE INSPECTION REPORT GERS-15-018 CLIFTY CREEK PLANT MADISON, INDIANA PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION 1 RIVERSIDE PLAZA COLUMBUS, OHIO Annual Dam and Dike Inspection
Integrating Asset Management Principals to Watershed Management: A Risk-Based Approach to Managing Stormwater Assets
Integrating Asset Management Principals to Watershed Management: A Risk-Based Approach to Managing Stormwater Assets Presenters: Mark VanAuken, PE, CMS4S, ENV SP Stormwater/MS4 Discipline Leader Kevin
Fort Dodge Stormwater Master Planning. Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M.
Fort Dodge Stormwater Master Planning Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M. Project Location Project Background Flooding History Localized flooding and storm sewer
Flood Risk Management
Flood Risk Management Value of Flood Risk Management Every year floods sweep through communities across the United States taking lives, destroying property, shutting down businesses, harming the environment
Flood Risk Management
Flood Risk Management Value of Flood Risk Management Value to Individuals and Communities Every year floods sweep through communities across the United States taking lives, destroying property, shutting
Small Dam Hazard Assessment Inventory
Small Dam Hazard Assessment Inventory What would happen if your dam were to fail? This is a question that most dam owners hope they will never have to answer. However it is a question you, as a responsible
DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY. a guide to PREVENTING SEWER BACKUPS AND FLOODING
DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY a guide to PREVENTING SEWER BACKUPS AND FLOODING Sewer backups and flooding can damage District homes and businesses. Sewer blockages are most commonly found
5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES
5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES Flood damage reduction consists of two basic techniques structural and non-structural. Structural methods modify the flood and take the flood away from people
Newbiggin House Farm,
Newbiggin House Farm, Near Waberthwaite Flood Investigation Report 32 Flood Event 30/8/2012 Cumbria County Council Version Undertaken by Reviewed by Approved by Date Preliminary Colin Parkes Anthony Lane
TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion
TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion Project Overview Sanitary Sewer System 2 Town of Surfside Project Overview Potable Water System 3 Town of Surfside Project Overview Storm Water
Oakwood Beach Storm Damage Prevention Project NJDEP-Bureau of Coastal Engineering Glenn Golden, Project Manager U.S. Army Corps Civil Works Programs
Oakwood Beach Storm Damage Prevention Project NJDEP- Glenn Golden, Project Manager U.S. Army Corps Civil Works Programs Branch Dwight Pakan, Project Manager, Philadelphia District The State of New Jersey
THE CORPORATION OF THE CITY OF GUELPH. THEREFORE the council of the Corporation of the City of Guelph enacts as follows:
THE CORPORATION OF THE CITY OF GUELPH By-law (1993)-14515 A by-law respecting storm water disposal from private property in the City of Guelph, to amend By-law (1987)-12602 and to adopt Municipal Code
SECTION 6A STORM DRAIN DESIGN Mar. 2002 S E C T I O N 6A STORM DRAIN - DESIGN
S E C T I O N 6A STORM DRAIN - DESIGN 6A.l Scope 6A.2 Storm Water Quantity 6A.3 Storm Drain Hydraulics 6A.4 Depths 6A.5 Locations 6A.6 Curved Storm Drains 6A.7 Manholes 6A.8 Catch basins 6A.9 Storm Drain
Background Information: The Mamquam River Floodplain Restoration Project
Background Information: The Mamquam River Floodplain Restoration Project The Mamquam River Floodplain Restoration project is being undertaken in partnership with the Squamish River Watershed Society, Fisheries
Emergency Spillways (Sediment basins)
Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]
COMMUNITY CERTIFICATIONS
National Flood Insurance Program Community Rating System COMMUNITY CERTIFICATIONS Public reporting burden for this form is estimated to average 4 hours for annual recertification, per response. The burden
WEST-END FLOODING INVESTIGATION 24 JULY 2009 RAINSTORM EVENT CONSOLIDATED REPORT AND ACTION PLAN
Background WEST-END FLOODING INVESTIGATION 24 JULY 2009 RAINSTORM EVENT MARCH 2011 TABLE OF CONTENT Summary Report 1. Background 2. Flood Investigation Process 3. Public Input 4. Level of Service Objective
CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE
1008 STORM DRAINAGE (3/24/05) 1008.01 PURPOSE To minimize the amount of stormwater runoff resulting from development utilizing nonstructural controls where possible, maintain and improve water quality,
ELASTOMERIC INLINE CHECK VALVES FOR CONTROL AND PREVENTION OF SANITARY SEWER OVERFLOW
A Red Valve Company And Tideflex Technologies White Paper 600 North Bell Avenue Carnegie, PA 15106 (412)279-0044 www.redvalve.com ELASTOMERIC INLINE CHECK VALVES FOR CONTROL AND PREVENTION OF SANITARY
Storm Drain System Operation and Maintenance
Santa Clara Valley Urban Runoff Pollution Prevention Program PUBLIC AGENCY ACTIVITIES Performance Standard and Supporting Documents for Storm Drain System Operation and Maintenance December 19, 1996 March
ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS
ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS PREPARED BY: DEPARTMENT OF ENVIRONMENT AND LANDS INDUSTRIAL ENVIRONMENTAL ENGINEERING DIVISION APRIL 16, 1992 - TABLE OF
Extreme Wet Weather in Brookfield. How to Keep Your Basement Dry During Heavy Rains and Floods
Extreme Wet Weather in Brookfield How to Keep Your Basement Dry During Heavy Rains and Floods Relating Stormwater Drainage to Sewer Backups Brookfield has two separate sewer systems Storm sewer system
MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH
MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH MARYLAND AVENUE BACKUPS COMMUNITY OUTREACH MEETING AGENDA Introductions History of PWSA Actions August 31 Storm Impacts Short
SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING
812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,
PREVENTING WET OR FLO ODED BASEMENTS
PREVENTING WET OR FLO ODED BASEMENTS TABLE OF CONTENTS Prevention Tips...Page 1 Why is there Water in my Basement?...Page 2 City of Saskatoon Sewer Systems...Page 3 Why Does Saskatoon Have Two Separate
Components of a Basement Flooding Protection Plan: Sewer System Improvements. November 2000
Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 SEMCOG 2000 Prepared
Protect Your Home From Flooding. A guide for Lethbridge Residents
Protect Your Home From Flooding A guide for Lethbridge Residents Every year, millions of litres of water flow into the City of Lethbridge s stormwater and wastewater collection systems from residential
Local Road Assessment and Improvement Drainage Manual
Local Road Assessment and Improvement Drainage Manual Donald Walker, T.I.C. Director, author Lynn Entine, Entine & Associates, editor Susan Kummer, Artifax, design Transportation Information Center University
Chehalis River Basin Flood Damage Reduction 2013-2015 Capital Budget Approved by Legislature in June 2013
Chehalis River Basin Flood Damage Reduction 2013-2015 Capital Budget Approved by Legislature in June 2013 1. Design alternatives for large capital flood projects (basinlevel water retention and Interstate
1. Water Line Maintenance 2. Sanitary Sewer Maintenance 3. Spill/Leak/Overflow Control, Response, and Containment
WATER AND SEWER UTILITY OPERATION AND MAINTENANCE Although sewage systems the operation and maintenance of public utilities are not considered themselves are not a chronic sources of stormwater pollution,
Muddy River Restoration Project Project Description
Muddy River Restoration Project Project Description Since the fall of 1996, the Muddy River has flooded three times, causing damage to residents, businesses institutions and the public transit system in
Scheduling Maintenance for Infiltration Basins and Trenches
Visual Inspection for Infiltration Practices Visual inspection is a rapid assessment procedure for qualitatively evaluating the functionality of a stormwater best management practice (BMP). Visual inspections
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection
July 20, 2015. Subject: 7 th Avenue Creek Project Update & Elevation Certificates
July 20, 2015 Subject: 7 th Avenue Creek Project Update & Elevation Certificates Below are a few updates regarding the 7 th Avenue Creek Project. As you may recall there are two concurrent and independent
Community Workshop 5. Overarching Goals for Machado Lake Ecosystem and Wilmington Drain Multi-Use Projects
City of Los Angeles Department of Public Works Bureau of Engineering Machado Lake Ecosystem Rehabilitation Project & Wilmington Drain Multi-Use Project Community Workshop 5 February 24, 2009 In association
STAFF REPORT TO COMMITTEE OF THE WHOLE
STAFF REPORT TO COMMITTEE OF THE WHOLE DATE: November 7 2012 TO: FROM: SUBJECT: ATTACHMENT(S): COMMITTEE OF THE WHOLE GINA LAYTE-LISTON, SUPERVISOR, WASTEWATER Stormwater Management Funding Strategy None
CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE
CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE The following template may be used as a general guide for development of a Stormwater Pollution Prevention Plan (SWPPP) for construction activities.
The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:
Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section
Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts. Submitted to: Town of Sudbury
Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts Submitted to: Town of Sudbury December 2011 Table of Contents 1.0 Introduction... 1 1.1 Responsibility...
GREEN ROOFS. Location. Design SMALL COMMERCIAL GUIDE CITY OF ATLANTA, GEORGIA DEPARTMENT OF WATERSHED MANAGEMENT
SMALL COMMERCIAL GUIDE CITY OF ATLANTA, GEORGIA DEPARTMENT OF WATERSHED MANAGEMENT GREEN ROOFS A green roof is a system consisting of waterproofing material, growing medium, and vegetation, and is used
Appendix A. Lists of Accomplishments and Project Costs. UMRWD 10 Year Plan Update. Appendix A UPPER MINNESOTA RIVER WATERSHED DISTRICT
UPPER MINNESOTA RIVER WATERSHED DISTRICT Lists of Accomplishments and Project Costs 10 Year Plan Update UMRWD 10 Year Plan Update Page A 1 UMRWD LIST OF ACCOMPLISHMENTS Since its inception in 1967, the
CHAPTER 5. Storm Sewer
CHAPTER 5 Storm Sewer A. Introduction All proposed developments shall have a properly designed and constructed storm water conveyance system. This chapter deals only with the conveyance system. Storm water
City of West Linn Public Works Design Standards 2010. Table of Contents
City of West Linn Public Works Design Standards Table of Contents SECTION TWO STORM DRAIN REQUIREMENTS... 1 2.0000 STORM DRAINS... 1 2.0010 General Design Requirements...1 2.0011 Site Drainage Plans...2
INFORMATION BULLETIN BUSINESS FLOOD PLANNING AND MITIGATION GUIDE ACE GLOBAL RISK ENGINEERING. Flood risk assessment. Introduction
ACE GLOBAL RISK ENGINEERING INFORMATION BULLETIN BUSINESS FLOOD PLANNING AND MITIGATION GUIDE Introduction The most common cause of flooding is due to established water storage areas (natural and man-made)
STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date
STORMWATER POLLUTION PREVENTION PLAN TEMPLATE Disclaimer: This template was developed for guidance purposes only in an effort to assist Construction Storm Water permit applicants in meeting state and local