1 Floods Management and Drainage System in Haryana Table of Contents 1. Introduction History of Major Floods in Haryana Floods of 1976 & Flood of Drainage Masterplan Flood of Flood of Flood of Flood of Flood of Masterplan of Flood Control Works Protection Works Mitigation Works Damage Reduction Works Flood Forecasting and warning The Surface Water Drainage System of Haryana The Yamuna Basin The Ghaggar Basin (Part of Indus Basin) Brief on Design of Drains in Haryana General Design Capacity Alignment of Drains Drains Section Cross Section and Side Slopes of Drains Full Supply Level of Drains Hydraulic Slope of Drains Berm Width of Drains Conclusions... 10
2 Flood Management and Drainage System in Haryana Page 2 of 10 Floods Management and Drainage System in Haryana By Jai Singh Ahlawat * and Rajeev Bansal ** Haryana Irrigation Department, Chandigarh 1. Introduction Haryana, a small state situated in northwest of India was carved out of the then joint Punjab on November 1, 1966 and covers about 4.4 million hectare land area, of which about 3.9 million hectare is arable. In the North, the state is bounded by the Shivalik range of mountains and in the East by the river Yamuna. Aravalli range running South of Delhi and the desert of Rajasthan form the boundary on the Southwest. In the Northwest, the Ghaggar River forms part of the boundary with Punjab. The elevations of the state vary from 400 m in the North to 210 m on Rohtak-Hisar axis, 310 m in South Narnaul, 190 m in the Southeast outfall point of River Yamuna and 190 m in Southwest outfall point in Ghaggar. This clearly indicates that there is sufficient scope for natural surface drainage provided the proper surface drainage network is there. This also negates the euphoria created about geographic shape of the state being saucer or bowl. 2. History of Major Floods in Haryana Brief description of major floods experienced by Haryana from 1976 to till date is given below in chronological order. 2.1 Floods of 1976 & 1977 The state experienced very heavy floods during 1976 and In the southwest parts of Haryana 50/100 years return period floods were witnessed both during 1976 and The northern part of Haryana experienced such heavy floods during 1976, except Kaithal area, which experienced heavy flooding during Flood of 1978 The floods during the year 1978 were the direct result of heavy rainfall in Haryana as well as in the catchment areas of river Yamuna in Himachal Pradesh. The discharge in Yamuna was more than 19,825 m 3 /sec (700,000 cusecs) on 3 rd September As a result of this high water level, the districts of Ambala, Karnal, Sonepat, Faridabad, Gurgaon and adjoining areas of Delhi were also affected. 2.3 Drainage Masterplan After the devastation of the floods of 1978, the State prepared a masterplan costing Rs. 150 Crores and executed most of them for long-term mitigation measures of flood. The following schemes were part of the masterplan: Construction of Ujhina Diversion Drain for Gurgaon and Faridabad districts. * Engineer-in-Chief, Haryana Irrigation Department, Chandigarh. ** ADE, Environment Cell, Haryana Irrigation Department, Chandigarh.
3 Flood Management and Drainage System in Haryana Page 3 of 10 Construction of KCB Drain for Rohtak district. Construction of Link Drains. Construction of Ring bunds around villages. Construction of River embankments and river protection works along river Yamuna. Remodelling of Drain No. 8, Diversion Drain No. 8, Main Drain No. 2 etc. Construction of Storage along canals and natural storages at Bhindawas, Bibipur, Massani Barrage on River Sahibi, Ottu Weir, Kotla lake etc. 2.4 Flood of 1983 Whereas the floods in the year 1978 were caused by rivers on account of heavy rainfall in their catchment areas (which lie outside the State), the floods in 1983 were caused by extremely intensive rainfall within the State. This caused flooding in the districts of Rohtak, Sonepat, Jind, Gurgaon, Hisar, Bhiwani, Faridabad, Kurukshetra, Karnal and Sirsa. The Rohtak district was worst affected where Drain No.8 was not able to carry the required discharge from Gohana areas for a number of days inundating the entire Gohana Subdivision. The situation in Rohtak town was also grim as about 1 m (3 to 4 ft) water remained standing in large parts of the town. Since Delhi had not completed the outfall drains in their areas, the floodwater submerged fields in Bahadurgarh, Jhajjar and most part of Rohtak district. Extensive damage to property, life, and cropped land was caused resulting in damage estimated at Rs. 500 million. 2.5 Flood of 1988 There were heavy rainfalls in Haryana during August 1988, which affected 615 villages in Ambala, Karnal, Kurukshetra, Jind, Sirsa, Hisar, Faridabad and Sonepat districts. The heavy rainfall in catchment areas of Himachal Pradesh resulted in very heavy discharge in river Ghaggar, which was 2,275 m 3 /sec (80,398 cusecs) on 8 th August Such a high discharge was last recorded in After the heavy rains of July and August, there were also incessant rains throughout the State in September which again caused flash floods in the Ambala, Karnal, Kurukshetra, Jind, Sonepat, Hisar, Sirsa and Faridabad districts resulting in losses of human lives and of cattle. Flood protection works, crops and infrastructure were badly damaged. 2.6 Flood of 1993 In 1993 high stages in the river Ghaggar, coinciding with heavy precipitation on the Ghaggar drainage tract inundated large areas in the districts of Ambala, Kurukshetra, Kaithal, Fatehabad and Sirsa. Similarly, large areas were inundated in the Karnal, Jind, Sonepat, and Rohtak districts of the Yamuna drainage tract and in the Bhiwani and Jhajjar districts of the Internal Central tract. There was continuous heavy rainfall for 76 hours from 9 th July onwards which resulted in flooding of all rivers and drains. The total rainfall from 10 th July to 12 th July and again from 22 nd July to 23 rd July was of the order of more than 50% of the average annual rainfall in just five days. Heavy rainfall was also experienced in Punjab areas and as a result of this, a thick sheet of water flow entered Haryana through the SYL canal inundating a large number of villages. This inundation caused losses of human lives, of cattle, and destroyed large cropped areas and other property.
4 Flood Management and Drainage System in Haryana Page 4 of Flood of 1995 In 1995 high stages in the Ghaggar River coincided once more with high rainfall over much of the State causing inundations of large areas. The rainfall that led to the large inundations in 1995 was between 200 mm to 250 mm during September 2-4, following earlier heavy rains from 26 th August to 30 th August, which had already caused inundations. The districts of Rohtak, Bhiwani, Hisar, Jind, Kaithal, Ambala, Rewari and Sonepat were largely inundated and the situation was exacerbated by entry of floodwater from Punjab through the SYL canal. Floodwater also entered hundreds of villages in Rohtak, Bhiwani, Dadri, Gohana, Ambala Cantt., Ambala City, Panipat, Kaithal, Siwani, Pehowa, Tohana, Narwana, Hansi, and Barwala, Rewari and Ratia towns were also affected. All the cities and rural areas were under 0.6 to 3 m (2 to 10 ft) floodwater and the water remained stagnant for many days due to the non-availability of natural drainage system in Jind, Hisar, Rohtak and Bhiwani districts. All drains and canals overflowed and were not able to drain out the surface runoff. Road networks, Public Health installations including water works, electric installations etc. were submerged and badly damaged. The total cropped area affected by floods was 573,319 ha during this year and crop damages were assessed as Rs. 11,880 million. 2.8 Flood of 1998 In October 1998 very heavy precipitation, 1100 mm from 15 th to 18 th October, caused inundations of large areas, in the Kaithal district and Narwana-Tohana areas in Ghaggar Drainage Tract. Hansi areas (in the Hisar district), and areas in Jind, Rohtak, Jhajjar, Bhiwani and Rewari districts situated in the Internal drainage tract were also inundated for prolonged period. The Yamuna reached a peak discharge of 15,320 m 3 /sec (5,41,000 cusecs) in October 1998 causing heavy damages to the existing river protection works. In its drainage tract there was flooding in some low lying areas in Sonepat and Karnal districts as well as in some areas of the Faridabad and Gurgaon districts near the river itself. Due to this unseasonal and incessant rains in combination with high flows in river Yamuna, 111,000 ha (2.75 Lac acres) area of the State were inundated. 2.9 Masterplan of 1998 Another masterplan for drainage costing Rs Crores has been prepared in 1998 and following major schemes have been envisaged: - Development of a surface gravity drainage network for Ghaggar basin in Kaithal, Jind, Hisar, Fatehabad and Sirsa districts. Construction of Meham Lakhanmajra drain for Rohtak district. Construction of Darba Ghaggar Drain for Sirsa district. Construction of Kalwan Kinana Drain for Jind district. Construction of Numerous small link drains. 3. Flood Control Works In general terms flood control and management can be divided into four, mutually nonexclusive, main categories of structural as well as non-structural measures that may all be implemented in a river basin. The four main categories referred to above may be summarized as follows:
5 Flood Management and Drainage System in Haryana Page 5 of Flood Protection Works on the river itself, aimed at containing flood flows within the river course. These works, of a structural nature, comprise construction of structures, or works on the river itself. 2. Flood mitigation works in the catchment. These works aim at reducing flood peaks by small storage dams, maintaining (or increasing) rainfall retention and reducing erosion in the catchment through soil conservation methods. 3. Damage reduction works in the flood plain. Works under this category include drainage systems, flood zoning, land-use restrictions, flood proofing; and 4. Flood warning, evacuation and emergency relief. 3.1 Protection Works Flood Protection Works on the river itself, aimed at containing flood flows are carried out within the river course. These works are structural and comprise of construction of various structures, or works on the river itself. In Haryana number of flood protection works are carried out such as embankments, studs, drains etc and an infrastructure has been created for the same. At district level Flood Control Committees are constituted under the chairmanship of the Deputy Commissioner and consists of senior officers of Irrigation Department, Public Health Department, Building & Roads and Police Department. These committees carry out inspections of Flood Protection Works from time to time for planning the schemes for the coming flood season and recommend the same to the Government. The schemes recommended by the Flood Control Committees are then technically scrutinized first by the concerned Superintending Engineers and further by Technical Appraisal Committee, the highest technical committee consisting of Chief Engineers and other senior officers of the Haryana Irrigation Department. After detailed technical scrutiny, the feasible schemes are recommended for evaluation and approval of the highest authority i.e. Flood Control Board, chaired by Hon ble Chief Minister, Haryana and administrative secretaries of concerned departments. Thus a very elaborate and well-structured system has been put in place, which has been working effectively for flood control measures. Every year about 30 Crores Rupees are spent on flood protection works in the state. Besides, high embankments called Ring Bunds with proper approaches and ramps are also constructed around villages prone to flooding. The objective is to protect population from floods, which would otherwise maroon these villages and towns. This measure alone has saved a number of villages and towns from floods over the last many years. 3.2 Mitigation Works Flood mitigation works in the catchment is the second important measure of flood protection. The aim of these works is to reduce flood peaks by small storage dams, maintaining (or increasing) rainfall retention and reducing erosion in the catchment through soil conservation methods. The catchment areas of the major rivers i.e. Yamuna and Ghaggar do not lie in Haryana. Still the State takes every possible step for all treatments for soil conservation in their catchment area. A large number of small bunds for storage and soil conservation are being constructed in hilly areas of the State under the Integrated Watershed Development Project, which is being executed by the Haryana Agriculture Department very successfully.
6 Flood Management and Drainage System in Haryana Page 6 of 10 Haryana Irrigation Department has constructed such small storage cum soil conservation/cut off bunds in Aravalli range of hills in the districts of Gurgaon, Rewari and Mohindergarh. These bunds are effective in conserving soil, recharging of groundwater and create moisture in soil for Rabi crops. 3.3 Damage Reduction Works Damage reduction works in the flood plain include drainage systems, flood zoning, land-use restrictions, flood proofing etc. The need of flood plain zoning has been recognized in India at various forums in the past. The Central Flood Control Board urged the State Governments in 1957 to take up flood plain zoning and if necessary, enact legislation for the purpose. The necessity of flood plain zoning was recommended by The Ministers Committee (1964) and Ministers Committee on Floods and Flood Relief (1972). It also endorsed that necessary legislation should be enacted in the states". In 1975, the Central Government circulated a model bill for flood plain zoning with the request the States may enact necessary legislation with suitable modifications. The Rashtriya Barh Ayog also endorsed the concept of flood plain management measures in its report (1980). The GOI has issued guidelines for flood plain regulations based on the regulations issued by the Federal Emergency Management Unit (FEMA) of the US and other countries. 3.4 Flood Forecasting and warning An essential and critical component in any flood plain is an effective flood forecasting system and an ancillary flood warning system. This is particularly so in India in general and in Haryana in particular, where population pressures have increased human encroachments into the flood plains with ever increasing damages both in terms of losses of human lives, losses of cattle and losses of crops. Similar to other countries, India also lays great stress on flood management by both structural and non-structural measures as expressed by India s National Commission on Floods in Flood forecasting and flood warning is recognised as an essential and highly cost-effective component of flood management regardless of the degree of flood protection provided. India s experience in FF and FW has generally been very good, FF has proven to be quite accurate and FW has proven to be a major factor in saving lives and reducing property losses. 4. The Surface Water Drainage System of Haryana Haryana is covered by two main Drainage basins: The Yamuna basin of 16,330 km 2 or 37% of the area of the State, the Ghaggar basin (Part of Indus Basin) of km 2 or 63% of the area of the State. The drainage conditions in each of the two zones is as follows: 4.1 The Yamuna Basin The eastern part of the State (the Yamuna Basin) has the most elaborate drainage network comprising about 350 main and tributary drains of a total length of 3,000 km. Yet the system is still not capable of draining accumulated surface water from all lands sufficiently fast and, following heavy rains during the monsoon season, there are many pockets of standing water, which can be attributed mainly to non construction of the field drains at micro level. The main drains of this Zone are as follows:
7 Flood Management and Drainage System in Haryana Page 7 of 10 (1) Main Drain No.2, running from the left bank of the Sirsa Branch Irrigation Canal to Panipat and draining the Chautang and the northern part of the basin discharging into the Yamuna near Panipat; (2) Diversion Drain No.8, running from Gohana to Sonepat draining the central part of the basin and discharging into the Yamuna north of Delhi s northern border; (3) Drain No.8 extending the Nai Nallah Drain from Gohana to Delhi, discharging into the Najafgarh drainage system at the Bhindawas Lake (also called Jahajgarh Lake); (4) The Najafgarh Drain connecting the Najafgarh Lake and the Yamuna River; (5) The Gaunchi Main Drain draining east and west Faridabad and discharging into the Yamuna along with the Ujjina Diversion Drain at Hassanpur. In addition there are several small gravity drains and numerous permanent pumping stations with a total capacity of 1,240 cusecs in this basin, lifting accumulated water from depressed areas in Sonepat, Rohtak, Faridabad and Gurgaon districts into canals. 4.2 The Ghaggar Basin (Part of Indus Basin) The Ghaggar basin covers an area of km 2 or 63 % of Haryana s area in the districts of Ambala, Kurukshetra (in part), Kaithal, Fatehabad, Sirsa, Jind, Hisar, Bhiwani, and Mahendragarh. The Ghaggar River runs along the boundary between Haryana and Punjab states, crossing it at several points. Though less severe than in the Yamuna Zone, flooding in this Zone is exacerbated by cross-ghaggar inflows (from the Punjab) in the districts of Kaithal, Fatehabad and Sirsa. Constructed embankments along Ghaggar River and its tributaries have reduced the frequency of inundation but not eliminated it as heavy rainfall and inflows across the Ghaggar River, still persist. The main drains of this Zone are as follows: (1) Saraswati Drain taking discharge from Bibipur lake and running along Kurukshetra and Pehowa area and outfalling into River Ghaggar. (2) Amin Drain (3) Kaithal Drain. (4) Pundri Drain No. 1 and 2. (5) Kassan Drain. (6) Rangoi Nallah (7) Rangoi Diversion Drain (8) Hisar Drain (9) Hansi Drain (10) Rori Ghaggar Drain. Besides, there are a number of other tributary and link drains. Many drains, such as Pundri Drain No. 1 and 2, Kassan Drain and others, terminate along irrigation canals and drainage effluents are discharged by gravity or pump-lifted. In the Sirsa district the Rori-Ghaggar Drain has been constructed to drain frequently inundated areas in the district. At Kaithal an outfall into the Ghaggar has been provided at the terminal of the Kaithal Drain. Therefore, the accumulated surface runoff needs collection, conveyance and disposal of the runoff into two out flowing rivers: the Yamuna and the Ghaggar through proper well designed drainage channels. The area serviced by River Yamuna has an elaborate efficient network but the area covered by Ghaggar basin needs a good main drain, which can be networked by service drains.
8 Flood Management and Drainage System in Haryana Page 8 of Brief on Design of Drains in Haryana 5.1 General Surface drainage of agricultural land essentially constitutes removal and disposal of excess water from the land surface. The design capacity of drainage channels is determined in three steps: - Determination of design storms i.e. depth of rainfall of desired frequency of recurrence during a selected time interval. This is determined from rainfall intensity frequency analysis. Conversion of rainfall to actual run-off giving due consideration to soil characteristics, land cover, cropping conditions, land use and topography. Computation of necessary channel capacity giving due regard to the degree pf protection required and the tolerance of crops to flooding. It is a normal practice to allow water to accumulate to shallow depths for certain duration of time that will not cause serious damage to the crops sown and will help in recharging groundwater. The drainage channel should have sufficient capacity to remove the volume of run-off during this crop tolerance period. Though flood routing methods provide precise analysis of complex run-off removal situations in normal cases. It is a usual practice to assume that the drainage channels run at full capacity during the entire period determined for run-off removal. 5.2 Design Capacity The entire existing drainage system in Haryana was designed on the basis of an empirical formula viz. Boston Society Formula. Q = C A Where Q = discharge in cusecs A = catchment area in square miles C = coefficient to account for catchment characteristics, rainfall (upto 500 mm) etc. and is taken as (i) 200 for area having rainfall less than 20 inches or 500 mm; (ii) 480 for area having rainfall 20 inches to 30 inches or 500 mm to 750 mm and (iii) 2000 for sub-mountainous areas rainfall more than 30 inches or 750 mm. In working out the drain capacity, a reduction factor was applied, which depended on catchment area. The reason was to effect economy and also that smaller sections gave a better hydraulic performance than those designed for peak discharge. This reduction factor was kept as: - (i) 1/12 for drains of 100 square miles catchment area; (ii) 1/8 for drains of 101 to 250 square miles catchment area and (iii) 1/4 for drains of 250 square miles and above catchment area.
9 Flood Management and Drainage System in Haryana Page 9 of 10 Banks of carrier drains wherever required and cross drainage works were designed for peak discharge as per the above formula. 5.3 Alignment of Drains The drains are generally aligned along the lowest valley line. As far as possible, the alignment of the main or outfall drains is kept along the center of the area to be drained. The alignment of the drain is kept away from the depressions, ponds, marshes or villages so that its hydraulic performance is not adversely affected. In case the drain is to be taken across the valley either to reduce the length or for proper outfall conditions, the embankment should not be of excessive height so as to minimize the danger of flooding in the event of breach in embankment. Alignment of drains should avoid the depressions, which cannot be drained out by gravity. In case of unavoidable circumstances when the drain has to be passed through a depression, the embankment should be provided on both sides. 5.4 Drains Section Normally the cut section is provided in drains, which is adequate for design discharges and no embankment is essential. But when an embankment is necessary in order to accommodate a portion of design discharge or where disposal of excavated soil is costly, it is kept of low height and gaps are provided in embankments so as to allow unrestricted inflows. In forced circumstances where embankment has to be provided for design discharge, inlets have been provided to allow water of the surrounding area to enter the drain. In incidences of floods higher than the channel capacity, water can spill over the area during high flood and return to the channel when flood recedes. 5.5 Cross Section and Side Slopes of Drains A trapezoidal section is provided and side slope depends upon the nature of material excavated. In loamy soils of Haryana the slopes of 1:1 for cut sections and 1.5:1 for embankments have been provided. The side slope in sandy soils should be flatter. 5.6 Full Supply Level of Drains The Full Supply Level in drains is never kept more than 0.3 m above the average ground level. Where a drain outfalls into a main drain or river, the FSL at outfall is kept higher than the HFL of the main drain or river so as to avoid flat slopes leading to recurring silting problems or need for high embankments. 5.7 Hydraulic Slope of Drains The longitudinal slope depends upon the natural country slope. This has generally been restricted to a minimum of 0.10 m per Km so as to ensure minimum velocity required to avoid silting problem, which has resulted in rise in FSL above NSL by more than 0.3 m. For such reaches it is better to keep slope even less than 0.10 as silt free water reaches the drain. 5.8 Berm Width of Drains Berm in drain is provided between the toe of embankment and the section of the drain. It should be equal to the depth of the drain subject to a minimum of 1m.
10 Flood Management and Drainage System in Haryana Page 10 of Conclusions As is evident from the history, flood is a frequent event in the state. A large area in the flood plains of the Yamuna and Ghaggar rivers are inundated by either flood from the rivers, and/or by heavy precipitation. The following Measures are necessary for tackling the problems of perpetual flood. The storage dams across Yamuna River, outside the Haryana State need be constructed at priority. The small storage dams for water harvesting and soil conservation in the Shivalik foothills as taken up at higher pace as these dams would not only provide necessary irrigation water to farmers but would be a good treatment of soil in catchment area of the rivers. The catchment area should also be taken up so as to ensure soil conservation and avoid sudden flooding. Proper data acquisition and base needs to be improved, and maps need to be prepared for flooded areas based on the data and statistics of flooding events, flooding depth, duration and frequencies etc. Establishment of flood forecasting station is another priority for the state for which the Indian Metrological Department or Central Water Commission can be requested contacted. There is a Flood Warning (FW) system in the state but it needs to be revamped and designed for the needs of Haryana.
Dr S.K. GUPTA Scientist D Central Ground Water Board. 25 th FEB. 2014
GROUND WATER SCENARIO AND MANAGEMENT OPNTIONS IN NCR, DELHI Dr S.K. GUPTA Scientist D Central Ground Water Board 25 th FEB. 2014 National Capital Region, Delhi National Capital Region Sl No State District
Results of the survey:-
RURAL DEVELOPMENT DEPARTMENT, HARYANA No. of Rural BPL Households in the State alongwith Definition of Rural Poverty At the instance of the Ministry of Rural Development, Govt. of India, the Below Poverty
PRSENTATION ON DRAINAGE SYSTEM DELHI 25.07.2014 EAST DELHI MUNICIPAL CORPORATION
PRSENTATION ON DRAINAGE SYSTEM OF DELHI EAST DELHI MUNICIPAL CORPORATION 25.07.2014 MAP OF DELHI SHOWING MCD s, NDMC & DCB ABOUT DELHI DELHI MANIFESTS UNCONTROLLED URBANISATION POPULATION INDUSTRIALISATION
CHAPTER - VI FLOOD DAMAGES
CHAPTER - VI FLOOD DAMAGES 6.1 General Generally flood is defined as an unusually high stage in a river normally the level at which the river overflows its banks and inundates the adjoining area. In other
URBAN DRAINAGE CRITERIA
URBAN DRAINAGE CRITERIA I. Introduction This division contains guidelines for drainage system design and establishes a policy for recognized and established engineering design of storm drain facilities
Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
Lower Raritan Watershed Management Area Stormwater & Flooding Subcommittee Strategy Worksheet LRSW-S3C1
Strategy Name: Reduce Existing Potential for Flood Damages LRSW-S3C1. Develop and implement a program to: Minimize flood damages through the use of structural measures. Minimize flood damages through the
Chapter 2 Brief Overview of the Yamuna River Basin and Issues
Chapter 2 Brief Overview of the Yamuna River Basin and Issues Abstract This chapter presents the current status of the Yamuna river basin as well as brief description of its catchments. This chapter also
Department of Technical Education Haryana
Department of Technical Education Haryana 1 Skilling and creating productive job employment for youth is one of the biggest challenges that we face today. The Prime Minister s National Council on Skill
Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
Module 3. Irrigation Engineering Principles. Version 2 CE IIT, Kharagpur
Module 3 Irrigation Engineering Principles Lesson 9 Regulating Structures for Canal Flows Instructional objectives On completion of this lesson, the student shall be able to learn: 1. The necessity of
Standard Operating Procedures for Flood Preparation and Response
Standard Operating Procedures for Flood Preparation and Response General Discussion Hurricanes, tropical storms and intense thunderstorms support a conclusion that more severe flooding conditions than
Action plans for hotspot locations - Ash Study
Appendix 9 Action plans for hotspot locations - Ash Study Ash Vale North 1. Local evidence indicates the culvert could not discharge during December 2013 because the outlet was blocked on the western side
Riprap-lined Swale (RS)
Riprap-lined Swale (RS) Practice Description A riprap-lined swale is a natural or constructed channel with an erosion-resistant rock lining designed to carry concentrated runoff to a stable outlet. This
Domestic Policy Framework on Adaptation to Climate Change in Water Resources: Case Study for India. Working Together to Respond to Climate Change
Domestic Policy Framework on Adaptation to Climate Change in Water Resources: Case Study for India Working Together to Respond to Climate Change WATER ACCOUNTING OF INDIA S TOTAL WATER RESOURCES Unutilizable
Prattsville Berm Removal Project. 1.0 Project Location
Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed
The Alternatives of Flood Mitigation in The Downstream Area of Mun River Basin
The Alternatives of Flood Mitigation in The Downstream Area of Mun River Basin Dr.Phattaporn Mekpruksawong 1, Thana Suwattana 2 and Narong Meepayoong 3 1 Senior Civil Engineer, Office of Project Management,
Swannanoa River Flood Risk Management Study
Swannanoa River Flood Risk Management Study Measures Evaluated to Reduce Future Flood Damages City of Asheville U.S. Army Corps of Engineers Flooding History Part of the 132 square mile Swannanoa River
5.14 Floodplains and Drainage/Hydrology
I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important
FLOOD PROTECTION BENEFITS
IV. (340 points) Flood Protection Benefits A. Existing and potential urban development in the floodplain (50) 1. Describe the existing and potential urban development at the site and the nature of the
Flood Mitigation and Management in Bangkok Metropolitan Area
กร งเทพมหานคร Flood Mitigation and Management in Bangkok Metropolitan Area Present By Mr. Kriangkrai Phamornpol Department of Drainage and Sewerage Bangkok Metropolitan Administration 1 Flood Mitigation
Outlet stabilization structure
Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection
How To Understand And Understand The Flood Risk Of Hoang Long River In Phuon Vietnam
FLOOD HAZARD AND RISK ASSESSMENT OF HOANG LONG RIVER BASIN, VIETNAM VU Thanh Tu 1, Tawatchai TINGSANCHALI 2 1 Water Resources University, Assistant Professor, 175 Tay Son Street, Dong Da District, Hanoi,
Ponds- Planning, Design, Construction
United States Department of Agriculture Soil Conservation Service Agriculture Handbook Number 590 Ponds- Planning, Design, Construction This handbook describes the requirements for building a pond. It
General Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage
Determination Case number: 227307 General Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage 4 April 2011 Background 1. The Applicants insured their home contents
Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes
Chapter 2 Flash Flood Science A flash flood is generally defined as a rapid onset flood of short duration with a relatively high peak discharge (World Meteorological Organization). The American Meteorological
WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE
WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE May 24, 2005 Table of Contents Introduction...3 Definitions...3 Types of Wetland Restorations...4 Re-Contouring...4 Engineered...4 Water
Emergency Spillways (Sediment basins)
Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]
CHAPTER 2 HYDRAULICS OF SEWERS
CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination
Development of Rural Drinking Water Security Plan A Case Study from Raipur Block, Bhilwara District, Rajasthan
Development of Rural Drinking Water Security Plan A Case Study from Raipur Block, Bhilwara District, Rajasthan Dr. B. K. Bhadra Scientist/Engr. SF Regional Remote Sensing Centre (RRSC-W) NRSC/ISRO, Dept.
ORDINANCE NO. 2013 -
ORDINANCE NO. 2013 - AN ORDINANCE OF BREVARD COUNTY, FLORIDA AMENDING CHAPTER 62, LAND DEVELOPMENT REGULATIONS SECTION 62-2891, LOT DRAINAGE, AND CHAPTER 22 BUILDINGS AND BUILDING REGULATIONS, SECTION
CHAPTER 3 STORM DRAINAGE SYSTEMS
CHAPTER 3 STORM DRAINAGE SYSTEMS 3.7 Storm Drains 3.7.1 Introduction After the tentative locations of inlets, drain pipes, and outfalls with tail-waters have been determined and the inlets sized, the next
Computing Stormwater Runoff Rates and Volumes
New Jersey Stormwater Best Management Practices Manual February 2004 C H A P T E R 5 Computing Stormwater Runoff Rates and Volumes This chapter discusses the fundamentals of computing stormwater runoff
Micromanagement of Stormwater in a Combined Sewer Community for Wet Weather Control The Skokie Experience
Micromanagement of Stormwater in a Combined Sewer Community for Wet Weather Control The Skokie Experience Robert W. Carr 1 * and Stuart G. Walesh 2 1 Water Resources Modeling, LLC, 4144 S. Lipton Ave,
5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES
5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES Flood damage reduction consists of two basic techniques structural and non-structural. Structural methods modify the flood and take the flood away from people
Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains
1 P age Module 7: Hydraulic Design of Sewers and Storm Water Drains Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 2 P age 7.1 General Consideration Generally, sewers are laid at steeper
Type of Sewer Systems. Solomon Seyoum
Type of Sewer Systems Solomon Seyoum 0 Learning objectives Upon completion of this lecture, the participants will be able to differentiate between types of sewer systems and discuss different aspects of
SUSTAINABLE URBAN DRAINAGE SYSTEMS
overflow can lead into a permeable conveyance system to increase further the benefit and reduce the need for pipe systems. Pollutant removal rates have been shown to be high, with some pollutants being
CITY UTILITIES DESIGN STANDARDS MANUAL
CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.
London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document
LOCAL FLOOD RISK MANAGEMENT STRATEGY Summary Document October 2013 Local Flood Risk Management Strategy Summary 1 Introduction 2 Partner responsibilities 3 What do we know about flooding in the borough?
Module 6 : Quantity Estimation of Storm Water. Lecture 6 : Quantity Estimation of Storm Water
1 P age Module 6 : Quantity Estimation of Storm Water Lecture 6 : Quantity Estimation of Storm Water 2 P age 6.1 Factors Affecting the Quantity of Stormwater The surface run-off resulting after precipitation
GUIDELINES FOR THE CONTINUATION OF SCHEME ON REPAIR, RENOVATION AND RESTORATION (RRR) OF WATER BODIES IN XII TH PLAN
GUIDELINES FOR THE CONTINUATION OF SCHEME ON REPAIR, RENOVATION AND RESTORATION (RRR) OF WATER BODIES IN XII TH PLAN Government of India Ministry of Water Resources October, 2013 I N D E X PARA NO. CONTENTS
A. Flood Management in Nevada
Nevada Division of Water Planning A. Flood Management in Nevada Introduction Flooding has been a concern for Nevada communities since the first settlers moved to the territory in the mid-1800 s. Fourteen
CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE
1008 STORM DRAINAGE (3/24/05) 1008.01 PURPOSE To minimize the amount of stormwater runoff resulting from development utilizing nonstructural controls where possible, maintain and improve water quality,
Frequently-Asked Questions about Floodplains and Flood Insurance FLOOD INSURANCE
Frequently-Asked Questions about Floodplains and Flood Insurance What is a floodplain? The floodplain is any area covered by water during normal water flows, and which could be inundated as a result of
Flood Emergency Response Planning: How to Protect Your Business from a Natural Disaster RIC005
Flood Emergency Response Planning: How to Protect Your Business from a Natural Disaster RIC005 Speakers: Tom Chan, CEO, Global Risk Miyamoto Greg Bates, Principal, Global Risk Consultants Learning Objectives
DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods
DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES Run-off Analysis Methods This document sets forth the minimum design, technical criteria and specifications for the
Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can
Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can do his or her share to protect Ohio's water resources
Stormwater Management Functional Servicing Report
Stormwater Management Functional Servicing Report Part of Lot 12, Concession 10 Township of Cavan Monaghan Ian Cameron Rural Subdivision Engage Project No. 14016 Engage Engineering Ltd. January 7, 2015
The Hydrologic Cycle. precipitation evaporation condensation transpiration infiltration surface runoff transport groundwater water table.
The Hydrologic Cycle Page 1 of 1 Name Directions: The hydrologic cycle consists of the processes that change and move water through the earth s system. Use the terms below to label the hydrologic cycle.
STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION
STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION Design Criteria Drainage Area The drainage area for storm drain inlets shall not exceed one acre. The crest elevations of these practices shall
Table 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA April 17, 2013 Goal To develop a basic understanding of PA Department of Environmental Protection (DEP) and US Army Corps of Engineers
Climate change impacts on city of Gdansk and its vicinity (Vistula Delta, Poland)
Final International ASTRA Conference Espoo, 10-11 December, 2007 Climate change impacts on city of Gdansk and its vicinity (Vistula Delta, Poland) Dorota Kaulbarsz, Zbigniew Kordalski, Wojciech Jeglinski
Flooding Hazards, Prediction & Human Intervention
Page 1 of 10 EENS 3050 Tulane University Natural Disasters Prof. Stephen A. Nelson Flooding Hazards, Prediction & Human Intervention This page last updated on 19-Oct-2015 Hazards Associated with Flooding
2011 HYDRAULICS MANUAL
STATE OF LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT P.O. Box 94245 Baton Rouge, Louisiana 70804-9245 http://www.dotd.la.gov/ HYDRAULICS MANUAL Hydraulics (225) 379-1306 PREFACE The following
Water Resource. 1 Initiating and Sustaining Water Sector Reforms : A Synthesis World Bank in collaboration with the Government of India, Ministry of
WATER RESOURCES OF INDIA by Kalipada Chatterjee Climate Change Centre Development Alternatives Introduction Water is essential for human civilisation, living organisms, and natural habitat. It is used
Innovative Practices of e-governance in Health Sector
Innovative Practices of e-governance in Health Sector MedLEaPR (Medico Legal Examination and Post Mortem Reports) System FSL & other Laboratory Tests Reports integrated with MedLEaPR System MCTS (Mother
STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date
STORMWATER POLLUTION PREVENTION PLAN TEMPLATE Disclaimer: This template was developed for guidance purposes only in an effort to assist Construction Storm Water permit applicants in meeting state and local
Planning, Health and Environment Division
18 Planning, Health and Environment Division A Planning Guide to Sustainable Drainage Systems Introduction Working in co-operation with the Environment Agency, Severn Trent Water Ltd., the Highway Authority
AZ EGER-PATAK HIDROLÓGIAI VIZSGÁLATA, A FELSZÍNI VÍZKÉSZLETEK VÁRHATÓ VÁLTOZÁSÁBÓL ADÓDÓ MÓDOSULÁSOK AZ ÉGHAJLATVÁLTOZÁS HATÁSÁRA
AZ EGER-PATAK HIDROLÓGIAI VIZSGÁLATA, A FELSZÍNI VÍZKÉSZLETEK VÁRHATÓ VÁLTOZÁSÁBÓL ADÓDÓ MÓDOSULÁSOK AZ ÉGHAJLATVÁLTOZÁS HATÁSÁRA GÁBOR KEVE 1, GÉZA HAJNAL 2, KATALIN BENE 3, PÉTER TORMA 4 EXTRAPOLATING
Rational Method Hydrologic Calculations with Excel. Rational Method Hydrologic Calculations with Excel, Course #508. Presented by:
Rational Method Hydrologic Calculations with Excel, Course #508 Presented by: PDH Enterprises, LLC PO Box 942 Morrisville, NC 27560 www.pdhsite.com Calculation of peak storm water runoff rate from a drainage
Objective 4: Enhanced community education, flood awareness and preparedness
Objective 4: Enhanced community education, flood awareness and preparedness Understanding the extent and full impacts of flooding is essential for planning for potential future pressures on the drainage
Organization Chart for Design Organization
CANAL DESIGN Organization Chart for Design Organization Chief Engineer (Design), SSNNL, Gandhinagar Superintending Engineer, Narmada Project Design Circle, Gandhinagar Unit-1 Unit-2 Unit-3 Unit-4 Unit-5
3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN
3.4 DRAINAGE PLAN This section describes the existing onsite drainage characteristics and improvements proposed within this Specific Plan. Following this description, drainage plan development standards
PT. B.D. SHARMA UNIVERSITY OF HEALTH SCIENCES, ROHTAK CENTER-WISE COLLEGE LIST
01 R.P.INDERPRASTHA INSTT OF MEDICAL SCIENCES, KARNAL 01 G N M (F) SCHOOL OF NURSING GENERAL HOSPITAL, KARNAL 20 02 GANDHI SCHOOL OF NURSING, G.T. ROAD, BYE PASS, KARNAL-132001 30 03 R. P. INDERAPRASTHA
THE APPRAISAL OF REAL ESTATE 3 RD CANADIAN EDITION BUSI 330
THE APPRAISAL OF REAL ESTATE 3 RD CANADIAN EDITION BUSI 330 REVIEW NOTES by CHUCK DUNN CHAPTER 10 Copyright 2010 by the Real Estate Division and Chuck Dunn. All rights reserved ARE 3 rd EDITION REVIEW
Burnt River Black River and Gull River Flood Contingency Plan
Burnt River Black River and Gull River Flood Contingency Plan Objective: The objective of this plan is to preplan and prepare for flooding events in the Burnt River, Black River and Gull River area of
City of Shelbyville Site Inspection Checklist
City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather
Drainage Analysis for the McKownville Area
Drainage Analysis for the McKownville Area Town of Guilderland Albany County, New York Prepared by: DELAWARE ENGINEERING, P.C. 28 Madison Avenue Extension Albany, New York 12203 June 2010 Town of Guilderland
WATER CONSERVATION TECHNICAL BRIEFS
WATER CONSERVATION TECHNICAL BRIEFS TB 2 Rainwater Harvesting and Artificial Recharge to Groundwater SAI Platform August 2009 This document has been produced for internal information purposes only among
GUIDELINES FOR REPAIR, RENOVATION AND RESTORATION
GUIDELINES FOR REPAIR, RENOVATION AND RESTORATION OF WATER BODIES WITH DOMESTIC SUPPORT Government of India Ministry of Water Resources 2009 I N D E X CONTENTS PAGE NO. 1. Introduction 1 2. Basic Features
Rural Flooding: The Potential Role of Forestry
Rural Flooding: The Potential Role of Forestry Nadeem Shah, Tom Nisbet, & Huw Thomas Centre for Forestry and Climate Change Structure Background Woodland and Flood Alleviation The Theory. Studies on Woodland
APPENDIX B DESIGN GUIDELINES FOR APPROVED TREATMENT METHODS
APPENDIX B DESIGN GUIDELINES FOR APPROVED TREATMENT METHODS PLANTER BOXES 1. Determine the impervious area contributing flow to the planter box (see Chapter 4.2). 2. Assumption: Typical soil infiltration
Roosevelt Water Conservation District ROOSEVELT WATER CONSERVATION DISTRICT
ROOSEVELT WATER CONSERVATION DISTRICT RESPONSE TO ARIZONA POWER AUTHORITY REQUEST FOR INFORMATION DATED SEPTEMBER 12, 2012 PRESENTED OCTOBER 24, 2012 RWCD is an irrigation district that was established
Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans
APPENDIX IV Version: February 2, 2015 Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans Please fill in all blanks and please reference the plan sheets/pages where the information may
Updates on Pervious Pavement Design and Construction. Jason T. Peterein, P.E. June 19, 2012
Updates on Pervious Pavement Design and Construction Jason T. Peterein, P.E. June 19, 2012 Program Outline Pervious Pavement Basics Pervious Pavement Construction Maintenance MSD Regulations Update Permeable
Retention/Irrigation. Design Considerations. Soil for Infiltration Area Required Slope Environmental Side-effects
Description Retention/irrigation refers to the capture of stormwater runoff in a holding pond and subsequent use of the captured volume for irrigation of landscape of natural pervious areas. This technology
WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED
WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED WLPS BUNCEFIELD REBUILD Flood Risk Assessment Green Lane Hemel Hempstead Hertfordshire HP2 7HZ September 2009 Prepared
IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure
IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure (December 2013) IUCN does not engage in projects which involve the design, construction or rehabilitation
Components of a Basement Flooding Protection Plan: Sewer System Improvements. November 2000
Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 SEMCOG 2000 Prepared
Watershed Works Manual
National Rural Employment Guarantee Act Watershed Works Manual DRAINAGE LINE TREATMENT: GABION STRUCTURE Baba Amte Centre for People s Empowerment Samaj Pragati Sahayog September 2006 Drainage Line Treatment:
FLOOD. Some of the salient aspects pertaining to flood are compiled and collated for benefit of common people.
1 FLOOD Among all the natural disasters afflicting the country frequently river floods are the most devastating, which cause maximum damages of life and property in India. Total flood prone areas in India
Structural Damage Due to Floods
Structural Damage Due to Floods By Craig D. Rogers, P.E. The Federal Emergency Management Agency (FEMA) reports that each year approximately 90 percent of all disaster-related property damage results from
Chapter 5.0. Stormwater Credits for Innovative Site Planning
Chapter 5.0 Stormwater Credits for Innovative Site Planning Chapter 5. Stormwater Credits...Introduction 5.0 Stormwater Credits In Maryland, there are many programs at both the State and local level that
10/4/2012. 40 slide sample of Presentation. Key Principles to Current Stormwater Management
40 slide sample of Presentation Please contact [email protected] if you would like the complete presentation Key Principles to Current Stormwater Management Distributed Control Measures Integrated
Storm Drain Inlet Protection
Source: Caltrans Construction Site Best Management Practices Manual, 2003. Description Applications Installation and Implementation Requirements Devices installed at storm drain inlets to detain and/or
Appendix A. Lists of Accomplishments and Project Costs. UMRWD 10 Year Plan Update. Appendix A UPPER MINNESOTA RIVER WATERSHED DISTRICT
UPPER MINNESOTA RIVER WATERSHED DISTRICT Lists of Accomplishments and Project Costs 10 Year Plan Update UMRWD 10 Year Plan Update Page A 1 UMRWD LIST OF ACCOMPLISHMENTS Since its inception in 1967, the
Flood Zone Investigation by using Satellite and Aerial Imagery
Flood Zone Investigation by using Satellite and Aerial Imagery Younes Daneshbod Islamic Azad University-Arsanjan branch Daneshgah Boulevard, Islamid Azad University, Arsnjan, Iran Email: [email protected]
CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1
CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm
Flooding Fast Facts. flooding), seismic events (tsunami) or large landslides (sometime also called tsunami).
Flooding Fast Facts What is a flood? Flooding is the unusual presence of water on land to a depth which affects normal activities. Flooding can arise from: Overflowing rivers (river flooding), Heavy rainfall
TENNESSEE GAS PIPELINE COMPANY, L.L.C.
TENNESSEE GAS PIPELINE COMPANY, L.L.C. HYDROLOGIC & HYDRAULIC CALCULATIONS FOR WATERBODIES CROSSED BY CONNECTICUT PIPELINE EXPANSION PROJECT CONNECTICUT LOOP Submitted by: Tennessee Gas Pipeline Company,
Discussion about the practicability of implementing flood risk. management and urban flood insurance in China. Longhua Gao, Xiaoqing Zhou
Discussion about the practicability of implementing flood risk management and urban flood insurance in China Longhua Gao, Xiaoqing Zhou Abstract: This paper explains the flood risk management at first,
ARTICLE II STORM DRAINAGE. (From Ordinance No. 1987-17; August 4, 1987; Sections III through VIII)
ARTICLE II STORM DRAINAGE (From Ordinance No. 1987-17; August 4, 1987; Sections III through VIII) SECTION 2.1 Standard Provisions Standard Provisions All construction for storm drainage in the development
Flood Frequency Analysis Using the Gumbel Distribution
Flood Frequency Analysis Using the Gumbel Distribution Never Mujere University of Zimbabwe, Department of Geography and Environmental Science, Box MP 167, Mount Pleasant, Harare E-mail [email protected]
Stormwater Drainage Design for Parking Lots
PDHonline Course C201 (4 PDH) Stormwater Drainage Design for Parking Lots 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org www.pdhcenter.com
Storm Drain Inlet Protection - IP
Storm Drain Inlet Protection - IP DEFINITION A temporary protective device formed around a storm drain drop inlet to trap sediment. PURPOSE To prevent sediment from entering storm drainage systems, prior
Appendix C - Risk Assessment: Technical Details. Appendix C - Risk Assessment: Technical Details
Appendix C - Risk Assessment: Technical Details Page C1 C1 Surface Water Modelling 1. Introduction 1.1 BACKGROUND URS Scott Wilson has constructed 13 TUFLOW hydraulic models across the London Boroughs