Risk assessment of river-type hydropower plants by using fuzzy logic approach
|
|
|
- Daniel Young
- 9 years ago
- Views:
Transcription
1 Risk assessment of river-type hydropower plants by using fuzzy logic approach S.Kucukali 1,* 1 Cankaya University, Department of Civil Engineering, Balgat, Ankara, Turkey * Corresponding author. [email protected] Abstract: In this paper, a fuzzy rating tool has been developed for river-type hydropower plant projects risk assessment and expert judgments have been used instead of probabilistic reasoning. The methodology is a multicriteria decision analysis which provides a f lexible and easily understood way to analyze project risks. The external risks, which are partly under the control of companies, have been considered in the model. The eleven classes of risk factors were determined based on the expert interviews, field studies and literature review as follows: site geology, land use, environmental issues, grid connection, social acceptance, financial, natural hazards, political/regulatory changes, terrorism, access to infrastructure and revenue. The relative importance (impact) of risk factors was determined from the survey results. The survey was conducted with the experts that have experience in river-type hydropower projects. The survey results revealed that the site geology and environmental issues were considered as the most important risks. The new risk assessment method enabled a Risk Index (R) value to be calculated, establishing a 4-grade evaluation system: low risk having R values between 1.2 and 1.6; medium risk, between 1.6 and 2; high risk, between 2 and 2.4; extreme risk, between 2.4 and 2.8. Applicability of the proposed methodology was tested on a real case hydropower project namely Kulp IV which was constructed on Dicle River in East Anatolia in Turkey. The proposed risk analysis will give investors a more rational basis on which to make decisions and it can prevent cost and schedule overruns. Keywords: Hydropower, Risk Analysis, Fuzzy Logic. 1. Introduction Renewable energy projects life cycle is full of various risks which will cause cost and schedule overrun or project failure. The surveys conducted by Gronbrekk et al. [1] and Komendantova et al. [2] identified the highest risk as political and regulatory changes for renewable energy projects in developing countries. Similarly, Ernst and Young [3] identified the most important business risk for 2010 as regulation and compliance. Construction of river-type hydropower plants involves uncertainties because of various external factors such as site geology, grid connection, and environmental issues. These factors increase the construction costs and duration. For example, in one of the river-type hydropower plant in Turkey, namely Kulp IV, the cost of civil works increased by a factor of two because of unpredicted geologic structure at the tunneling site. In another example, the judges have ruled against hydroelectric power plants in 33 completed cases in Turkey, issuing a stay of execution decision or canceling the construction altogether because of the environmental issues. In the literature there are several studies considering the risk analysis in construction projects [4] but risk analysis in renewable energy projects, especially for hydropower plants is very limited. In classical project risk analysis techniques, risk rating values are calculated by multiplying impact and probability values and direct analysis of these linguistic factors is often neglected [5]. Most existing risk analysis models, such as Monte Carlo simulation and tornado chart, are based on quantitative techniques which require numerical data. Kangari and Riggs [6] note that probabilistic models suffer from detailed quantitative information which is not normally available in the real construction world. However, much of the information related to risk analysis is not numerical [7]. Rather, this information is expressed as words or 1432
2 sentences in a natural language. These conceptual factors can be expressed in linguistic terms that are, so called fuzzy information [8]. Uncertainty factors such as poor geology or unstable policy fall into this category. The aim of this paper is to introduce a new approach for hydropower projects risk assessment through the fuzzy set concepts. 2. Methodology The eleven classes of risk factors were determined based on the expert interviews, field studies and literature review. The risk factors and their evaluation criteria are listed in Table 1. The risk factors are: site geology (geotechnical properties of the construction site), land use (right to use of the land for the construction of hydropower scheme), environmental issues (impact on ecosystem), grid connection (connection to the power system), social acceptance (impact on local community who use the river or the surrounding lands), financial (the status of the inflation and interest rate), natural hazards (earthquake, flooding and landslide), political/regulatory changes (level of political stability), terrorism (human-made disasters), access to infrastructure (road, electricity and water), revenue (cash flow). It should be noted that the financial, political/regulatory changes and terrorism were regarded as risks related to country conditions and their evaluation were done based on [9], [10]. In order to determine the relative importance (impact) of the risk factors, a survey was conducted with the experts from the banks and companies that have experience in the construction of river-type hydropower schemes. 14 experts were participated to the survey. The participants were asked to grade the importance of the risk factors regarding their importance and seriousness of concern. They graded the risk factors using a scale between 1-4, where 1 r epresents low and 4 very high". The experts ranked site geology and environmental issues as the most important risks for river-type hydropower plants (Fig.1). Fig.1 The importance of risk factors of river-type hydropower plants based on the survey results 1433
3 Table 1. Evaluation criteria of risk factors in river type hydropower plants Risk Factor Score (1) Score (2) Score (3) Score (4) Site Geology Rock mass quality is very good-good: RQD=% Rock mass quality is fair: RQD=%40-60 Rock mass quality is poor-very poor: RQD=%0-50 level Land use Environmental Issues Grid Connection Social Acceptance Financial a Property of Treasury Project has detailed Environmental Impact Report Close to power system Project has detailed Social Impact Report Economic performance of country is very high Forest Project has Environmental Impact Report Near to power system Project has Social Impact Report Economic performance of country is high Private property: Agricultural land Project has no Environmental Impact Report Far to power system Project has no Social Impact Report Economic performance of country is medium Soil with high ground water Private property: Residential area Project is in an ecological sensitive area. Connection to the power system has some limitations Local community benefit from the river or the surrounding lands Economic performance of country is low Natural Hazards Low risk Medium risk High risk Very high risk Change in Laws Political risk of Political risk Political risk of Political risk of and Regulations a country is low of country is country is high country is very Terrorism b Access to Infrastructure Revenue Terror risk index of country is low medium Terror risk index of country is medium Terror risk index of country is high high Terror risk index of country is extreme Very easy Easy Difficult Very difficult Design discharge is high reliable Design discharge is medium reliable Design discharge is low reliable a country related risk and its evaluation is based on [9], b terrorism risk index is based on [10] Design discharge is unreliable For each 11 parameter, an 1x4 input matrix was developed, each column corresponding scores 1-4. If the score for a parameter is 3 and the input matrix (I) for the parameter is: [ ] I = (1) 1434
4 Each parameter has an identical membership grading matrix. The fuzzy grading matrices were developed considering the degree of error a scoring observer may cause due to subjectivity and bias in the assessment process [11], [12]. Eq. (2) shows the fuzzy grading matrix (FG) used in this study: FG = Score (2) The fuzzy assessment matrix (FA) was obtained by multiplying input matrices (I) with fuzzy grading matrix (FG) of the parameter, FA = I FG ( j 1 to 11) (3) j j j = where, j is the row number of the fuzzy assessment matrices. The membership degree matrix (MD) was obtained by multiplying weight of parameters (w) with fuzzy assessment matrix (FA) and summing the columns resulting in a one row matrix; MD = w FA (4) A decision parameter computation was agreed upon f rom several scenarios considering membership degree versus attributes curves and formulation of Risk Index (R) was given as 1 A A34 R = (5) A A T where the area under the curve between the attributes i and j is named A ij with: i =1,2, 3, and j = 2, 3, 4,. The total area under the curve is A T. This enabled a Risk Index (R) value to be calculated, establishing a 4-grade evaluation system: Low risk having R values between 1.2 and 1.6; medium risk, between 1.6 and 2; high risk, between 2 and 2.4; extreme risk, between 2.4 and 2.8. The risk scale index represents the minimum and maximum values calculated by Eq.(5). 3. Investment Costs of Hydropower Schemes Hydro power is the backbone of carbon dioxide free energy generation, about 22% of the world s electricity production comes from hydropower installations [13]. Hydropower plants can be classified into two categories: storage and river-type. In storage type hydropower plants, dams are used to retain river flow in a reservoir. A river-type hydropower plant diverts a portion of river through a channel or tunnel (Fig.2). River-type hydro power plants are dependent on the prevailing flow rate and can present problems of reliability if the flow varies greatly with time of the year or the weather [14]. Small hydropower (SHP) plants are mostly included in this category. 1435
5 TAILRACE FOREBAY BYPASSED REACH DIVERSION CHANNEL WATER INTAKE ENVIRONMENTAL FLOW WEIR RIVER FLOW Fig.2 Site plan and components of a river-type hydropower plant Hall et al. [15] determined the specific investment cost (total investment cost of the project divided by the installed capacity) of river-type hydropower plant in USA in the range of $/kw. Also, they reported that the civil works account for 65-75% of capital cost. Each hydropower project is site specific that can explain the wide range of investment costs. Gordon [16] identified the main factors which can lead to cost overrun as the rate of inflation and site geology. The specific investment cost (SC) of a hydro power plant is the function of the net head (H) and installed capacity (P). It is well known from the literature that the SC increases as the head and installed capacity decreases [17], [18]. The investment cost a hydropower plant can be classified as follows: project design, land use and permits, financial, civil works, electro and hydro mechanical equipment, and grid connection (Table 3). 4. An Application of the Proposed Methodology The developed risk assessment technique was applied to a r eal-time hydropower project namely Kulp IV which was constructed on Dicle River in Diyarbakır in East Anatolia. The characteristics of the project are as follows: Gross head=77 m, discharge=20 m 3 /s, output=12.68 MW, energy=36.64 GWh/year, tunnel length=1885 m. Table 3 pr esents the investment cost analysis of Kulp IV hydropower plant. Actual cost of civil works and grid connection increased by a factor of two because of the poor geology and the technical demands by TEIAS, respectively. Table 4 shows the application of the risk assessment to the hydropower project. In the assessment fuzzy grading matrix provides more room for the justification of relationships between variables on the basis of fuzzy words. The project risk evaluation was done based on the criteria presented in Table 1. For example, Turkey has been ranked as extreme for Terrorism Risk Index by Maplecroft [9]. Therefore the risk factor of terrorism has a score of 4 for the project. Yet, project has no Environmental impact report, which yields the score of environmental issues as 4. B y applying this method to other risk factors, the Kulp IV hydropower project Risk index was calculated as 2.26 which means project involves high risk. 1436
6 Table 3. Analysis of the investment cost of Kulp IV hydropower plant (P=12.7 MW) Description Estimated Cost ($) Actual Cost ($) Rate of Increase Share of Total Cost Reason Project design 1,090,000 1,180, % 2.2% Additional project designs Poor geology (serpentine) at the Civil works 12,500,000 25,700, % 48.6% tunneling site Under estimated costs of EME a 6,790,000 7,490, % 14.2% Technical equipment demand HME b 8,900,000 4,800, % 9.1% The prices of DSI are very high compared to the market. Grid connection 2,600,000 5,400, % 10.2% Technical demands by TEIAS and length of the power supply line was increased Land Use and Permits 2,200,000 2,600, % 4.9% The cost of the forest usage permit was not taken into account Financial 3,100,000 5,700, % 10.8% Increase in interest rates because of the financial crisis a Electro mechanical equipment, b Hydro mechanical equipment Table 4. Fuzzy risk assessment rating tool application for Kulp IV Hydropower Plant No Risk Factor Score Relative Importance (W) Risk Assessment Input Matrix (I) Fuzzy Grading Matrix (FG) Fuzzy Logic Evaluation Fuzzy Assessment Matrix (FA) Membership Degree Geology Land Rent Environment Grid Connection Social Acceptance Financial Natural Hazard Political Changes Terorism Access to Insfrastructure Revenue Membership Degree Matrix (MD) FG=f(I) FA=FG*W Decision Parameter (R) A 12 A 23 A 34 A T R = 2.26 High Risk 1437
7 5. Conclusions In this research, a new methodology is proposed for risk rating of river-type hydropower plant projects. The relative importance of the risk factors was determined from the expert judgments. The survey results showed that the most concerned risks are site geology and environmental issues. These results are in agreement with the Gordon [16]. Applicability of the proposed methodology has been tested on a real case. Findings of the case study demonstrate that the proposed methodology can be easily applied by the professionals to quantify risk ratings. The advantage of the proposed methodology is it will give investors a more rational basis on which to make decisions and it can prevent cost and schedule overruns. Forecasting the measure of risk of a river-type hydropower plant can be made by any decision maker with the help of the fuzzy rating tool described in this paper. References [1] Gronbrekk, W., Barton, H., and Khoury, R.H., International sustainability tools for hydropower role, relevance and industry reporting trends. Proc., Hydro 2010 C onf., Lisbon, Portugal, [2] Komendantova, N., Patt, A., Barras, K. and Battaglini, A., Perception of risks in renewable energy projects: The case of concentrated solar power in North Africa, Energy Policy, 2011, In press. [3] Ernst and Young, Business Risk Report, ( ) [4] Zavadskas, E.K., Turskis, Z., Tamosaitiene, J., Risk assessment of construction projects, J. Civil Engineering and Management, 16, 2010, [5] Dikmen, I., Birgonul, M.T., Han, S., Using fuzzy risk assessment to rate cost overrun risk in international construction projects, Int J Project Management, 25, 2007, [6] Kangari, R. and Riggs, L.S., Construction risk assessment by linguistics, IEEE Transactions on Engineering Management, 36, 1989, [7] Mustafa, M.A., and Al-Bahar, J.F., Project risk assessment using the analytic hierarchy process, IEEE Transactions on Engineering Management, 38, 1991, [8] Kucukali, S., Baris, K., Turkey s short-term gross electricity demand forecast by fuzzy logic approach, Energy Policy, 38(5), 2010, [9] ECR-Euro Money Country Risk, ( [10] Maplecroft, Terrorism Risk Index, ( ) [11] Karakaya, S.T., Coastal Scenic Evaluation by Application of Fuzzy Logic Mathematics, Msc. Thesis, METU,The Graduate School of Natural and Applied Sciences, Dept.of Civil Eng., Ankara, Turkey, [12] Sahin, F., Scenic Evaluation of the Western Black Sea Coasts Using Fuzzy Logic, Msc. Thesis, ZKU, Graduate Sc. Of Natural and App. Sci., Dept. of Civil Eng., Zonguldak, Turkey, 2008 (inturkish). [13] Boyle, G., Renewable Energy: Power for a Sustainable Future. Oxford University Press,
8 [14] Kucukali, S. and Baris, K., Assessment of small hydropower (SHP) development in Turkey: Laws, regulations and EU policy perspective, Energy Policy, 37, 2009, [15] Hall, D.G., Hunt, R.T., Reeves, K.S. and Carroll, G.R., Estimation of Economic Parameters of U.S. Hydropower Resources, Idaho National Engineering and Environmental Laboratory, [16] Gordon, J.L., Hydropower costs estimates, J Water Power Dam Constr, 35, 1983, [17] Gordon, J.L. and Noel, C.R., The economic limits of small and low-head hydro, J Water Power Dam Constr, 38, 1986, [18] Aggidis, G.A., Luchinskaya, E., Rothschhild, R. and Howard, D.C., The costs of smallscale hydropower production: Impact on t he development of existing potential, Renewable Energy, 35, 2010,
Curriculum Vitae. Professor Serhat Kucukali
Curriculum Vitae Professor Serhat Kucukali Cankaya University Department of Civil Engineering, Eskisehir Yolu 29. Km, 06810, Ankara, Turkey E-mail: [email protected] Research Area of Interests Hydropower,
Frequently Asked Questions (FAQs) on Hydropower
Frequently Asked Questions (FAQs) on Hydropower What are the advantages of Hydropower? A renewable source of energy - saves scarce fuel reserves. Non-polluting and hence environment friendly. Long life
CHAPTER 3 RESEARCH DESIGN
CHAPTER 3 RESEARCH DESIGN 3.1 Introduction In general, micro-hydropower systems operate as Run-of-River type which means that neither a large dam or water storage reservoir is built nor is land flooded.
Asian Journal on Energy and Environment
As. J. Energy Env. 2005, 6(02), 139-144 Asian Journal on Energy and Environment ISSN 1513-4121 Available online at www.asian-energy-journal.info The Small Hydropower Project as the Important Renewable
Analytical Approach for Cost Estimation of Low Head Small Hydro Power Schemes
Analytical Approach for Cost Estimation of Low Head Small Hydro Power Schemes S.K. Singal and R.P. Saini Alternate Hydro Energy Centre, Indian Institute of Technology, Roorkee, India Email : [email protected]
Landslide hazard zonation using MR and AHP methods and GIS techniques in Langan watershed, Ardabil, Iran
Landslide hazard zonation using MR and AHP methods and GIS techniques in Langan watershed, Ardabil, Iran A. Esmali Ouri 1* S. Amirian 2 1 Assistant Professor, Faculty of Agriculture, University of Mohaghegh
An Evaluation Model for Determining Insurance Policy Using AHP and Fuzzy Logic: Case Studies of Life and Annuity Insurances
Proceedings of the 8th WSEAS International Conference on Fuzzy Systems, Vancouver, British Columbia, Canada, June 19-21, 2007 126 An Evaluation Model for Determining Insurance Policy Using AHP and Fuzzy
Chattichai WAISURASINGHA 1*, Prinya CHINDAPRASIRT 1, Winai SRI-AMPORN 1 and Sinee CHUANGCHAM 2
The Utilization of Geographic Information Systems and Multi-Criteria Decision Making with Local Community Participation for Selection of Site for Micro Hydropower Project: A Case Study of Chi River Basin,
Micro-hydro Power. Introduction. What is hydropower? System types. Power the entire farm Generate power to sell back to the national grid
Cronfa Amaethyddol Ewrop ar gyfer Datblygu Gwledig: Ewrop yn Buddsoddi mewn Ardaloedd Gwledig The European Agricultural Fund for Rural Development: Europe Investing in Rural Areas Micro-hydro Power Introduction
Micro-Hydro. Module 4.1. 4.1.1 Introduction. Tokyo Electric Power Co. (TEPCO)
Module 4.1 Micro-Hydro 4.1.1 Introduction Tokyo Electric Power Co. (TEPCO) Workshop on Renewable Energies November 14-25, 2005 Nadi, Republic of the Fiji Islands Subjects to be Covered in Workshop Potential
A Review on Critical Risk Factors in the Life Cycle of Construction Projects
Journal of Civil Engineering Research 2014, 4(2A): 31-36 DOI: 10.5923/c.jce.201401.07 A Review on Critical Risk Factors in the Life Cycle of Construction Projects S. M. Renuka 1,*, C. Umarani 2, S. Kamal
MICRO-HYDROPOWER NEED FOR ENERGY FOR RURAL DEVELOPMENT. By: Payman Hassan Rashed
MICRO-HYDROPOWER NEED FOR ENERGY FOR RURAL DEVELOPMENT Significant water resources are found in many developing countries. In areas where adequate water resources are present, harnessing the power of falling
Clean Development Mechanism Project Opportunities in Indonesia
Clean Development Mechanism Project Opportunities in Indonesia Pre-feasibility Report on a Micro Hydro Power CDM Project Center for Research on Material and Energy Institut Teknologi Bandung October 2002
e7/ppa Workshop on Renewable Energy - TEST ANSWER -
e7/ppa Workshop on Renewable Energy - TEST ANSWER - NAME UTILITY 1 Question 1: Give two kinds of gases that cause the global warming. Most serious Green house gas. CO 2 (Carbon dioxide), CH 4 (Methane),
Quantitative Inventory Uncertainty
Quantitative Inventory Uncertainty It is a requirement in the Product Standard and a recommendation in the Value Chain (Scope 3) Standard that companies perform and report qualitative uncertainty. This
Research on supply chain risk evaluation based on the core enterprise-take the pharmaceutical industry for example
Available online www.jocpr.com Journal of Chemical and Pharmaceutical Research, 2014, 6(6):593-598 Research Article ISSN : 0975-7384 CODEN(USA) : JCPRC5 Research on supply chain risk evaluation based on
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will
An Introduction to. Micro- Hydropower. Systems. Natural Resources Canada. Ressources naturelles Canada
An Introduction to Micro- Hydropower Systems Natural Resources Canada Ressources naturelles Canada Introduction Hydropower technology has been around for more than a century. Hydropower comes from converting
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_risk_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern
It s hard to avoid the word green these days.
Going green : Environmental jobs for scientists and engineers Alice Ramey Alice Ramey is an economist in the Office of Occupational Statistics and Employment Projections, BLS. She is available at (202)
River Basin Management in Croatia
River Basin Management in Croatia 2. INTERNATIONAL RIVER BASIN MANAGEMENT HIGH LEVEL SYMPOSIUM Cappadocia/NEVŞEHİR, Turkey 16-18 April 2013 2 Water sector responsibilities are shared among: Croatian Parliament
TURKEY S HYDROPOWER POTENTIAL and
ERE OTOPRODÜKTÖR, ELEKTRİK ÜRETİM, İLETİM ve DAĞITIM SANAYİ ve TİCARET A.Ş. TURKEY S HYDROPOWER POTENTIAL and REVIEW of ELECTRICITY GENERATION POLICIES from EU PERSPECTIVE FEASIBILITY CRITERIA FOR HEPP
Developments in Turkey in the Context of Participatory Approach Based on River Basin Management. Nermin ÇİÇEK, Özge Hande SAHTİYANCI
Developments in Turkey in the Context of Participatory Approach Based on River Basin Management Nermin ÇİÇEK, Özge Hande SAHTİYANCI The Ministry of Forestry and Water Affairs, General Directorate of Water
FACT SHEET 6: HYDRO ELECTRICITY
FACT SHEET 6: HYDRO ELECTRICITY Hydro comes from the Greek word hydra, meaning water. Hydro electricity is electricity produced from the energy contained in the downhill flow of water from rivers and lakes.
Hydroelectric power and development in Argentina
Hydroelectric power and development in Argentina Gustavo Alberto Devoto ENTE NACIONAL REGULADOR DE LA ELECTRICIDAD Avda. Madero 1020 8 floor Buenos Aires - ARGENTINA [email protected] Abstract: A description
Capacity planning for fossil fuel and renewable energy resources power plants
Capacity planning for fossil fuel and renewable energy resources power plants S. F. Ghaderi *,Reza Tanha ** Ahmad Karimi *** *,** Research Institute of Energy Management and Planning and Department of
OBJECT ORIENTED SOFTWARE SYSTEM BASED ON AHP
OBJECT ORIENTED SOFTWARE SYSTEM BASED ON AHP Soumi Ghosh Department of Computer Science & Engineering Amity School of Engineering and Technology Amity University, Sec-125, NOIDA, (U.P.), INDIA [email protected]
Linguistic Preference Modeling: Foundation Models and New Trends. Extended Abstract
Linguistic Preference Modeling: Foundation Models and New Trends F. Herrera, E. Herrera-Viedma Dept. of Computer Science and Artificial Intelligence University of Granada, 18071 - Granada, Spain e-mail:
REPUBLIC OF TURKEY MINISTRY OF FORESTRY AND WATER AFFAIRS
REPUBLIC OF TURKEY MINISTRY OF FORESTRY AND WATER AFFAIRS Turkey s position in the World Prof. Dr. Veysel EROĞLU Minister of Forestry and Water Affairs The Ministry of Forestry and Water Affairs, formerly
Alternative RE Approach Technical Support Document
Alternative RE Approach Technical Support Document 1.1. Introduction Renewable energy (RE) is a cost-effective approach for reducing carbon dioxide (CO 2) emissions from fossil fuel-fired electric generating
A Comparative Study of the Pickup Method and its Variations Using a Simulated Hotel Reservation Data
A Comparative Study of the Pickup Method and its Variations Using a Simulated Hotel Reservation Data Athanasius Zakhary, Neamat El Gayar Faculty of Computers and Information Cairo University, Giza, Egypt
OPTIMIZATION OF POWER OUTPUT OF A MICRO-HYDRO POWER STATION USING FUZZY LOGIC ALGORITHM
International Journal on Technical and Physical Problems of Engineering (IJTPE) Published by International Organization of IOTPE ISSN 2077-3528 IJTPE Journal www.iotpe.com [email protected] March 2013 Issue
Analysis of the electricity prices in the Slovak Republic and their impact on the individuals energy security
Analysis of the electricity prices in the Slovak Republic and their impact on the individuals energy security Abstract Martina Mokrišová Department of Finance and Accounting Faculty of Management University
PERFORMANCE EVALUATION OF SMALL HYDROPOWER PROJECTS IN MAHARASHTRA
PERFORMANCE EVALUATION OF SMALL HYDROPOWER PROJECTS IN MAHARASHTRA Patil Smita Dinkar 1 and Morankar D.V 2 1 Student M-Tech Civil (Hydraulic Engineering), Bharati Vidyapeeth Deemed University College of
The Brazilian Electricity Model: An Overview of the Current Structure and Market Design
The Brazilian Electricity Model: An Overview of the Current Structure and Market Design Élbia Melo 1, Evelina Maria de Almeida Neves 2, Luiz Henrique Alves Pazzini 3 Câmara de Comercialização de Energia
12 ENERGY. 12.1 Introduction
12 Energy 12.1 Introduction Otago is a hydro-electric power producing region and a major exporter of electricity in New Zealand today. The two large existing hydro-electric schemes in the region, Roxburgh
Comparative Analysis of FAHP and FTOPSIS Method for Evaluation of Different Domains
International Journal of Research Studies in Computer Science and Engineering (IJRSCSE) August 2015, PP 58-62 ISSN 2349-4840 (Print) & ISSN 2349-4859 (Online) www.arcjournals.org Comparative Analysis of
ENVIRONMENTAL MITIGATION AT HYDROELECTRIC PROJECTS Volume 1. Current Practices for Instream Flow Needs, Dissolved Oxygen, and Fish Passage
DOEIID-10360 Distribution Category: UC-22S ENVIRONMENTAL MITIGATION AT HYDROELECTRIC PROJECTS Volume 1. Current Practices for Instream Flow Needs, Dissolved Oxygen, and Fish Passage M. J. Sale G. F. Cada
A new Environmental Performance Index using analytic hierarchy process: A case of ASEAN countries
Article A new Environmental Performance Index using analytic hierarchy process: A case of ASEAN countries Wan Khadijah Wan Ismail, Lazim Abdullah Department of Mathematics, Faculty of Science and Technology,
San Francisco International Airport Enterprise Risk Management
San Francisco International Airport Enterprise Risk Management Mike Warren Airport Risk Manager WHAT IS ENTERPRISE RISK MANAGEMENT (ERM) It is a comprehensive program that focuses on a continuous and sustainable
Learning Management System Selection with Analytic Hierarchy Process
Learning Management System Selection with Analytic Hierarchy Process Aydın Çetin 1, Ali Hakan Işık 2, İnan Güler 1 1 Gazi University, Faculty Of Technology 2 Gazi University, Institute of Information Sciences
AN ECONOMICAL AND TECHNICAL CASE STUDY FOR A SMALL HYDROPOWER SYSTEM
AN ECONOMICAL AND TECHNICAL CASE STUDY FOR A SMALL HYDROPOWER SYSTEM Dumitru Dan POP 1, Vasile Simion CRĂCIUN, Liviu Neamţ, Radu Tîrnovan, Teodor VAIDA Technical University of Cluj Napoca, [email protected]
IEA ETSAP - Technology Brief E12 - May 2010 - www.etsap.org. Hydropower
Hydropower Highlights PROCESS AND TECHNOLOGY STATUS With a total capacity of 723 GW e (21% of the world s electrical capacity), hydropower generates approximately 319 TWh per year, equivalent to 16% of
Institut für Energietechnik Department of Energy Systems. Hydroelectric power. Elias Bartos 2/7 2010
Institut für Energietechnik Department of Energy Systems Hydroelectric power Elias Bartos 2/7 2010 1 Contents Different types of power plants Potential Economics Conclusion 2 Impoundment A dam is built
Sustainable. Infrastructure and Asset. Management. Kiyoshi KOBAYASHI
Sustainable Infrastructure and Asset Management Kiyoshi KOBAYASHI What is Asset Management? The optimal allocation of the scare budget between the new arrange-ment of infrastructure and rehabilitation/maintenance
A Green Sector Overview
A Green Sector Overview Micro Hydro Electric Power Ontario's Waterpower Resources: Past and Present The first hydroelectric generator in Canada was installed near Ottawa, which was the first city in North
Husum Wind Energy 6th of June 2013. Johannes Ritter Partner Solution Matrix [email protected] +49-178-8586084
Husum Wind Energy 6th of June 2013 Johannes Ritter Partner Solution Matrix [email protected] +49-178-8586084 Solution Matrix Europe s nr. 1 authority on Business Case 326 Business Case
TOSHKA PROJECT POWER OPERATION (Mubarak Pump Station)
Twelfth International Water Technology Conference, IWTC12 2008 Alexandria, Egypt 1 TOSHKA PROJECT POWER OPERATION (Mubarak Pump Station) N. M. Abdelsalam 1, M. M. Abdelaziz 2, A. F. Zobaa 3 and M. S. Aziz
Financing renewable energies. The role of the banking sector
Financing renewable energies The role of the banking sector Milan, 20 June 2014 UniCredit at a glance Key figures (March 2014) UniCredit is a leading European commercial bank with an international network,
National Electric Power Regulatory Authority
National Electric Power Regulatory Authority MECHANISM FOR DETERMINATION OF TARIFF FOR HYDROPOWER PROJECTS Preamble Conservative estimates show total hydroelectric potential in the country to be 45000
The Next Generation Science Standards (NGSS) Correlation to. EarthComm, Second Edition. Project-Based Space and Earth System Science
The Next Generation Science Standards (NGSS) Achieve, Inc. on behalf of the twenty-six states and partners that collaborated on the NGSS Copyright 2013 Achieve, Inc. All rights reserved. Correlation to,
A Resource Guide to In State Hydropower Production
A Resource Guide to In State Hydropower Production Thursday, October 11, 2007 Fairfax, VT Hydro Facility Owned & Operated by CVPS Published by: Winooski, VT Winooski One Hydro Electric Facility Introduction
Chapter 13 Quiz. Multiple Choice Identify the choice that best completes the statement or answers the question.
Chapter 13 Quiz Multiple Choice Identify the choice that best completes the statement or answers the question. 1. Which of the following is the correct type of energy utilized to produce tidal power? a.
A Fuzzy AHP based Multi-criteria Decision-making Model to Select a Cloud Service
Vol.8, No.3 (2014), pp.175-180 http://dx.doi.org/10.14257/ijsh.2014.8.3.16 A Fuzzy AHP based Multi-criteria Decision-making Model to Select a Cloud Service Hong-Kyu Kwon 1 and Kwang-Kyu Seo 2* 1 Department
Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge
1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project
Technology Fact Sheet for Mitigation B. Small Hydropower Technology i 1. Introduction 1.1. Historical - All over the World, hydropower sector is
Technology Fact Sheet for Mitigation B. Small Hydropower Technology i 1. Introduction 1.1. Historical - All over the World, hydropower sector is playing a great role in economic development since the last
SUPPLY CHAIN MANAGEMENT AND A STUDY ON SUPPLIER SELECTION in TURKEY
SUPPLY CHAIN MANAGEMENT AND A STUDY ON SUPPLIER SELECTION in TURKEY Pelin Alcan, Hüseyin Başlıgil, Melih Coşkun Yildiz Technical University, Besiktas, İstanbul, Turkey Abstract This study mainly focuses
Selection of Database Management System with Fuzzy-AHP for Electronic Medical Record
I.J. Information Engineering and Electronic Business, 205, 5, -6 Published Online September 205 in MECS (http://www.mecs-press.org/) DOI: 0.585/ijieeb.205.05.0 Selection of Database Management System with
Survey the environmental impacts of Manjil wind power, Hydroelectric power plant using the analytic hierarchy process
46 Survey the environmental impacts of Manjil wind power, Hydroelectric power plant using the analytic SAMANEH REZAEI KALLAJ 1, LEILA OOSHAKSARAEI 2*, ALIREZA MARDOOKHPOUR 3 1 Master Student, Department
Chapter 4 SUPPLY CHAIN PERFORMANCE MEASUREMENT USING ANALYTIC HIERARCHY PROCESS METHODOLOGY
Chapter 4 SUPPLY CHAIN PERFORMANCE MEASUREMENT USING ANALYTIC HIERARCHY PROCESS METHODOLOGY This chapter highlights on supply chain performance measurement using one of the renowned modelling technique
DEVELOPING FLOOD VULNERABILITY MAP FOR NORTH KOREA INTROUDUCTION
DEVELOPING FLOOD VULNERABILITY MAP FOR NORTH KOREA Soojeong Myeong, Research Fellow Hyun Jung Hong, Researcher Korea Environment Institute Seoul, South Korea 122-706 [email protected] [email protected]
Georgia Performance Standards Framework for Natural Disasters 6 th Grade
The following instructional plan is part of a GaDOE collection of Unit Frameworks, Performance Tasks, examples of Student Work, and Teacher Commentary. Many more GaDOE approved instructional plans are
Applying Fuzzy Control Chart in Earned Value Analysis: A New Application
World Applied Sciences Journal 3 (4): 684-690, 2008 ISSN 88-4952 IDOSI Publications, 2008 Applying Fuzzy Control Chart in Earned Value Analysis: A New Application Siamak Noori, Morteza Bagherpour and Abalfazl
Sensitivity Analysis for Small Hydropower Plant (SHP)
Sensitivity Analysis for Small Hydropower Plant (SHP) Adriana Catanase, William Phang 1 Agenda SBI/SCG Present and future of Small Hydro Power Plants valuating a small hydro project Small Hydro project
RENEWABLE ENERGY IN TURKEY
RENEWABLE ENERGY IN TURKEY SALİH BURAK AKAT DEPARTMENT OF RENEWABLE ENERGY RESOURCES ENERGY AND NATURAL RESOURCES ASISTANT EXPERT General Directorate of Renewable Energy (GDRE) General Directorate of Renewable
Engineering Geological Asset Management for Large Dams. Yasuhito SASAKI (1)
Engineering Geological Asset Management for Large Dams Yasuhito SASAKI (1) (1) Geology Research Team, Public Works Research Institute, Japan E-mail:[email protected] Abstract Comprehensive inspection
How To Write A Book On Risk Management
National Center for Risk and Economic Analysis of Terrorism Events CREATE FY2015 (Year 11) Call for White Papers CREATE, the DHS-sponsored Center of Excellence at the University of Southern California,
NOTE. Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand
Journal of Hydrology (NZ) 44 (2): 131-135, 2005 New Zealand Hydrological Society (2005) NOTE Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand W. E. Bardsley Department
Risk and vulnerability assessment of the build environment in a dynamic changing society
Risk and vulnerability assessment of the build environment in a dynamic changing society Limnei Nie SINTEF Building and infrastructure, P.O.Box 124 Blindern, NO-0314 Oslo, Norway. [email protected]
COST-BENEFIT ANALYSIS - TOOL FOR ALLOCATION OF FINANCIAL RESOURCES FOR MAJOR PROJECTS
COST-BENEFIT ANALYSIS - TOOL FOR ALLOCATION OF FINANCIAL RESOURCES FOR MAJOR PROJECTS EMILIA CLIPICI, FLORIN FRANT UNIVERSITY OF PITESTI [email protected] EFTIMIE MURGU UNIVERSITY OF RESITA [email protected]
Comparison between Vertical Handoff Decision Algorithms for Heterogeneous Wireless Networks
Comparison between Vertical Handoff Decision Algorithms for Heterogeneous Wireless Networks Enrique Stevens-Navarro and Vincent W.S. Wong Department of Electrical and Computer Engineering The University
A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM
A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM Giang Pham Hong, Michel Hotakhanh, Nga Pham Hong, Hoai Nam Nguyen, Abstract:Dams have been taken an important role in time and surface redistribution of water for
Methodologies for assessing Green Jobs Policy Brief
Methodologies for assessing Green Jobs Policy Brief Introduction By pioneering sustainable economic activities, both developed and developing countries stand to generate new jobs and strengthen their economies,
A Guide to Hazard Identification and Risk Assessment for Public Health Units. Public Health Emergency Preparedness Protocol
A Guide to Hazard Identification and Risk Assessment for Public Health Units Public Health Emergency Preparedness Protocol Emergency Management Unit Public Health Division Ministry of Health and Long-Term
Appendix J Online Questionnaire
Appendix J Online Questionnaire In accordance with the Paperwork Reduction Act, this questionnaire was approved by the Office of Management and Budget (OMB). The OMB control number and expiration date
Exploring the potential of energy recovery using micro hydropower systems in water supply systems
Water Utility Journal 7: 25-33, 2014. 2014 E.W. Publications Exploring the potential of energy recovery using micro hydropower systems in water supply systems I. Kougias *, T. Patsialis, A. Zafirakou and
Project Cash Flow Forecasting Using Value at Risk
Technical Journal of Engineering and Applied Sciences Available online at www.tjeas.com 213 TJEAS Journal21332/2681268 ISSN 2183 213 TJEAS Project Cash Flow Forecasting Using Value at Risk Mohammad Reza
Delay Computation Using Fuzzy Logic Approach
I.J. Intelligent Systems and Applications, 2012, 11, 84-90 Published Online October 2012 in MECS (http://www.mecs-press.org/) DOI: 10.5815/ijisa.2012.11.10 Delay Computation Using Fuzzy Logic Approach
Application of ARCGIS and Analytical Hierarchy Process in the Risk Assessment of Geological Disaster in Complex Mountains
Application of ARCGIS and Analytical Hierarchy Process in the Risk Assessment of Geological Disaster in Complex Mountains Li Li Lecturer Key Laboratory of Water Environment Evolution and Pollution Control
Application of Space Technology for Disaster monitoring and assessment current state in Vietnam
Application of Space Technology for Disaster monitoring and assessment current state in Vietnam Lai Anh Khoi SPACE TECHNOLOGY INSTITUTE 8th GEOSS Asian Pacific Symposium Beijing, Sep. 09-11, 2015 Types
Amir Bashirzadeh Tabrizi, Nassir Gifani. TOOSSAB Consulting Engineers Company e-mail: [email protected], [email protected].
International Renewable Energy Congress November 5-7, 2010 Sousse, Tunisia Economical and Environmental Effects of Pressure Reducer Valve Substituting by Small Hydro Power-Plants in Gravity Water Transmission
INT 3 Schedule Risk Analysis
INT 3 Schedule Risk Analysis David T. Hulett, Ph.D. Hulett & Associates, LLC ICEAA Professional Development and Training Workshop San Diego, CA June 9-12, 2015 1 Agenda Add uncertainty to the schedule,
joint Resource Optimization and Scheduler
www.siemens.com/spectrum-power joint Resource Optimization and Scheduler All forecasting and planning applications in one component. Answers for infrastructure and cities. joint Resource Optimization and
What are the Benefits?
Micro hydro power system introduction Not everyone is lucky enough to have a source of running water near their homes. But for those with river-side homes or live-on boats, small water generators (micro-hydro
Flood Risk Management
Flood Risk Management Value of Flood Risk Management Every year floods sweep through communities across the United States taking lives, destroying property, shutting down businesses, harming the environment
Flood Risk Management
Flood Risk Management Value of Flood Risk Management Value to Individuals and Communities Every year floods sweep through communities across the United States taking lives, destroying property, shutting
9 th International Scientific Conference
9 th International Scientific Conference E n e r g y a n d C l i m a t e C h a n g e 1 s t o p e n c a l l 12-13-14 October 2016 Athens, Greece Organized by Energy Policy and Development Centre (KEPA)
Managing sewer flood risk
Managing sewer flood risk J. Ryu 1 *, D. Butler 2 1 Environmental and Water Resource Engineering, Department of Civil and Environmental Engineering, Imperial College, London, SW7 2AZ, UK 2 Centre for Water
Assessment of hydropower resources
Assessment of hydropower resources Oliver Froend Assessment of hydropower resources Relevance of surveys, data assessment and analyses to the success of the project. Required data and field survey. Key
Decision Method for Unit Rehabilitation. John Yale Hydro Plant Engineering Manager Chelan County PUD
Decision Method for Unit Rehabilitation John Yale Hydro Plant Engineering Manager Chelan County PUD Public utility in Washington State, 1936 1,988 MW nameplate Two dams, three powerhouses on the Columbia
Degree of Uncontrollable External Factors Impacting to NPD
Degree of Uncontrollable External Factors Impacting to NPD Seonmuk Park, 1 Jongseong Kim, 1 Se Won Lee, 2 Hoo-Gon Choi 1, * 1 Department of Industrial Engineering Sungkyunkwan University, Suwon 440-746,
Forward-Looking Statement Disclosure
Forward-Looking Statement Disclosure Certain information contained in this article is forward looking information based on current expectations and plans that involve risks and uncertainties. Forward looking
Performance Analysis of Data Mining Techniques for Improving the Accuracy of Wind Power Forecast Combination
Performance Analysis of Data Mining Techniques for Improving the Accuracy of Wind Power Forecast Combination Ceyda Er Koksoy 1, Mehmet Baris Ozkan 1, Dilek Küçük 1 Abdullah Bestil 1, Sena Sonmez 1, Serkan