Applying Fuzzy Control Chart in Earned Value Analysis: A New Application
|
|
|
- Jasper Hunt
- 10 years ago
- Views:
Transcription
1 World Applied Sciences Journal 3 (4): , 2008 ISSN IDOSI Publications, 2008 Applying Fuzzy Control Chart in Earned Value Analysis: A New Application Siamak Noori, Morteza Bagherpour and Abalfazl Zareei Department of Industrial Engineering, Iran University of Science and Technology, Tehran, Iran Abstract: As it is common in project management context, Earned value analysis usually integrates time and cost performance within the project scope. It helps the project manager to understand how to deal with project from two points of view. The first is to recognize current performance indexes and the second one is to provide a forecast to the future. However, most of decisions in this regard have taken based on Schedule Performance Index (SPI) and Cost Performance Index (CPI) while there is no a well organized control mechanism in which detect their situations as it is, not only numerically but also recognize/categorize current situation of the earned value management system linguistically. In this paper a fuzzy control chart approach associated with -cut is presented in order to control earned value performance indexes including linguistics terms. Also a new application, based on a Multi Period-Multi Product (MPMP) production control problem is illustrated and successfully implemented. Key word: Earned value analysis fuzzy control chart linguistic term production control problem INTRODUCTION Earned value management system assists to a simultaneous time and cost control system to be conducted in accordance with project scope. As it is common in project management context, earned value method is applied in order to accomplish project on time-on budget with acceptable level of quality. In this regard, two performance indexes called as Schedule Performance Index (SPI) and Cost Performance Index (CPI) to be taken which frequently used in earned value management and metrics. Traditionally, SPI and CPI can be calculated by dividing Earned Value (EV) on Planned Value (PV) and Actual Cost (AC) respectively. It is therefore desirable if SPI/CPI would be equal to one. In case of achieving a higher than for both indexes, it means that project performance from both indexes point of view is appropriate and consequently the project will be finished with less required budget sooner that expected in comparison with planned start time. However, in case of being over budget or requiring additional duration more than initial planned duration, where SPI/CPI are less than one, project situation is not proper and it should be taken into consideration for further preventive actions in which assist managers to follow up the project in near future much more better than before in order to achieve project objectives effectively. The most important question here is how to deal with earned value metrics (SPI, CPI) and how can we detect a control mechanism for those mentioned metrics. This problem becomes more important where those indexes to be controlled periodically in order to recognize project situation. By this reason, in this paper, a novel approach based on fuzzy control chart approach is proposed in which implements a control mechanism on earned value metrics. It certainly assists the project managers to deal with project performance and enable them to provide a better forecast accordingly. Review on fuzzy control chart: The first control chart was proposed by Shewhart [] in 920s which is still subject to new application areas. Further developments to improve the performance of control charts proposed by Shewhart [] are on the basis of usage of probability and fuzzy set theory integrated with the control charts [2]. Fuzzy set theory is required to model type of uncertainty which probability in not capable of modeling [3]. A stochastic decision method such as statistical decision analysis does not measure the imprecision in human behavior; on the other hand, fuzzy set theory captures the subjectivity of human behavior. The classical judgment in control charts are based on binary classification as in-control or out-ofcontrol while in fuzzy control charts several intermediate decisions such as rather-in-control or rather-out-of-control may be handled in order to cover linguistic terms that in classical control charts could not applied easily. Corresponding Author: Dr. Siamak Noori, Department of Industrial Engineering, Iran University of Science and Technology, Tehran, Iran 684
2 Marcucci [4] proposed two procedures using Shewhart-type control charts for linguistic terms. The first type is designed to detect changes in any of the quality proportions using Pearson statistic (χ 2 ) and the second type depends upon multinomial distribution, which can be approximated by a multivariate normal distribution and is designed to detect only increases in all but one of quality proportions. Wang and Raz [5] described an approach that can be assigned fuzzy sets to each linguistic term and then combined for each sample using fuzzy arithmetic. The sensitivity of performance of control charts was found to be influenced by the number of linguistic terms used in classifying the observations [6]. In control charts proposed by Kanagave et al. [7] for process average and process variability, the probability distribution exists behind the linguistic data was taken into consideration. Taleb and Limam [8] proposed the comparison of fuzzy and probability approaches of constructing fuzzy control charts based on average run length. Cheng [9] proposed the method of constructing a fuzzy control chart for a process with fuzzy outcomes. Fuzzy outcomes, in his paper, described in fuzzy numbers based on experts quality ratings. Gulbay et al. [2] developed -cut control charts for attributes. In their approaches the tightness of the inspection can be defined by selecting a suitable -cut. Cheng [0] proposed fuzzy control charts constructed by fuzzy outcomes derived from the subjective quality ratings provided by a group of experts. Gulbay and Kahraman [] presented some contributions to fuzzy control charts base on fuzzy transformation methods which are made by utilization of -cut. The -cut provides an ability to determine the tightness of the inspection properly. They developed an alternative approach namely Direct Fuzzy Approach (DFA) which does not require the use of defuzziffication and compare the linguistic data in fuzzy space without making any transformation. Faraz and Moghadam [2] proposed a fuzzy control chart for process average of a continuous quality characteristic and through an example; they proved that it is a better alternative to Shewhart X chart. Literature review on earned value analysis: Related researches which had been carried out in earned value mostly focused on application of earned value method in different projects as well as organizations. The other category also provided an insight to earned value development which earned value parameters was taken into considerations. As a closely related research, Anbari [3] provided an excellent insight to earned value management method and also proposed a simple control limit for earned value metric. He considered 685 simple numerical control limits as caution and poor area for evaluating SPI/CPI indexes respectively. However, he did not provide more detail for intermediate SPI/CPI amounts. As a recent work, Vandevoorde and Vanhoucke [4] not only focused on traditional earned value metrics, but also they developed earned schedule performance indicator namely SV(t) and SPI(t). Their proposed approach also was able to yield forecast total project duration. Moreover, their developed formula compared with three available methods in the literature based on testing three real life projects in several situations. Finally, they concluded the superiority of the proposed approach. However, they recommended that maybe based on situation e.g. project manager knowledge and project management team other methods also would be useful. Vitner et al. [5] applied a Data Envelopment Analysis (DEA) in order to performance evaluation in a multi project environment where each project has been defined uniquely. They integrated both Earned Value Management System (EVMS) and Multi Denominational Control System (MPCS). They also provided a new approach in order to reduce number of inputs and outputs in their developed approach to get better results in multi project environment. However, they pointed out, it was for the first time that DEA had been applied in project environment where it has been previously used in organizations e.g. hospital, banking etc. Cioffi [6] presented a new formalism notations used in earned value analysis and reproduced standard earned value parameters. He also presented additional quantities defined there. He pointed out that his proposed approach can accomplish because of several objectives e.g. earned value analysis can be used faster, easier, more frequently and more useful especially for non linear prediction. Prior to this work, Cioffi [7] presented an analytical parameterization for S-curve where the curves were normalized two basic parameters. However, it can be further used for earned value analysis when the curve appropriately fitted. Kim et al. [8] developed a model based on research conducted on a two year period in different types of projects and organizations e.g. public and private organizations as well as large and small projects. Firstly, they discussed the problems arising during earned value implementation e.g. too much cost and paper work. Secondly as another finding, based on their conceptual model, it is necessary to consider four group namely earned value users, EV methodology, implementation process and project environment together. As a major conclusion, they expressed that in
3 order to implement earned value method; it is not simple to introduce a methodology in an organization. Instead it should be embedded with overall organizational approaches such as colleague-based organizational culture, continuing top-level management attention and facilitating supporting systems e.g. project management office. Moslehi et al. [9] presented an integrated web based time and cost control system for construction projects which mapped Work Breakdown Structure (WBS) in to an object oriented model to enable generate earned value reports at control objects, resource levels. Moreover, in order to analyze project variance, a set of resource performance indicators used. This system also assists to share data in within a world wide web. Al-Jibouri [20] evaluated effectiveness of three monitoring systems namely leading parameters technique, variance method and activity based ratio technique in construction projects from both theoretical and experimental point of view. Their investigations indicated that activity based ration and variance method have a better performance than leading parameter technique. Also, they introduced activity based ratio a faster and simpler method in comparison with other two approaches. However, they pointed out that it is difficult to generalize the results found on their investigation and further it can be customized based on the nature of project and amount of information required for further actions. Stratton [2] discussed applying earned schedule analysis in order to estimate completion date. Firstly, he presented commonly earned value technique including Schedule Performance Index (SPI) and then SPI (t) that can be estimated based on dividing earned schedule on actual time where earned schedule can be calculated based on mapping earned value amount on time (horizontal) axis. As it is well indicated, although there are some researches about both earned value analysis and (fuzzy) control chart, no related research found in which applied both control chart and earned value analysis simultaneously even deterministically. However, in this paper, a fuzzy control chart is developed to manage earned value metrics e.g. SPI, CPI. The manager here is able to use intermediate decision levels as well as traditional control levels. PROPOSED FUZZY CONTROL CHART THROUGH EANRED VALUE ANALYSIS Anbari [3] presented a control chart called Target Performance Chart for evaluating CPI, SPI and consequently Critical Ration (CR). He divided the 686 Fig. : Fuzzy control chart based on -cut Fig. 2: Triangular fuzzy number (a,b,c) performance index through four parts namely poor, caution, good, super star. However, judgment in control chart proposed by Anbari [3] was mostly based on binary classification. To expand above mentioned judgment for further intermediate linguistic decisions, a fuzzy control chart is proposed based on -cut which several intermediate decisions as rather-poor, rathercaution, rather-good and rather-super-star can be taken into consideration (Fig. ). Control chart is designed in such a way that when a=, the control chart is the same as traditional one as Anbari [3] proposed and when a=0, only the intermediate decisions can be traced. The value of -cut represents the tightness of inspection and can be defined by the project manager or the experts experience while the higher value of a represents both tighter inspection or the control chart tends to classical case. In Fig., the proposed fuzzy control chart is illustrated. In classical control chart proposed by Anbari [3] the condition areas are divided by crisp numbers as 0.8,
4 Fig. 3: Samples of CPI Table : CPI status date CPI CPI S 2 Process decision Super stars G CPI G Good C CPI C Caution 2 CPI P G CPI S 2 C CPI G 2 P CPI C Poor CPI β = S CPI β 2 = G G 2 G2 C 2 C2 CPI P β 3 = C P 2.2 = [G,S ] = [. + 0.,.3 0. ] (6) Following, method of utilizing the proposed fuzzy control chart to make decision about the process condition based on CPI index is presented. It is obvious; the method proposed for CPI index can also be used for SPI index. The condition of process control after calculating CPI in status date (CPI ) can be stated as below (Table ). Alternatively, for a CPI which β i is calculated, the value of β i can be compared to a predefined acceptable percentage (β) and decisions can be made as follow:.0 and.2 while in fuzzy control chart proposed in this paper, the control limits are defined by triangular fuzzy number as 0.8,.0 and.2 which are determined as given in following equations (Note that a triangular fuzzy number is introduced by the notation (a, b, c) as shown in Fig. 2):.2 = (.,.2,.3) ().0 = (0.9,.0,.) (2) 0.8 = (0.7,0.8,0.9) (3) By determining the value of a, control limits are calculated by the following equations: 0.8 = [P,C ] = [ , ] (4) 2.0 = [C,G ] = [ ,. 0. ] (5) 687 If β β, it is rather super star Else it is rather good. If β 2 β, it is rather good Else it is rather caution. If β 3 β, it is rather caution Else it is rather poor. Note that the value of β can subjectively be defined by the experts experiences or directly by the project manager. When β=, the process control decision results in poor or caution or good or super-star and as β approaches to,the tightness of inspection increases. In Fig. 3, process control decisions for some examples are presented. Assume that β= 0.5, CPI samples illustrated in Fig. 3 results in ten types of different decisions: 2 3 CPI : super-star, CPI : good, CPI : caution, 4 5 CPI : poor, CPI : rather-poor (the value of β 3 is less than β), more than β), less than β), 6 CPI : rather-caution (the value of β 3 is 7 CPI : rather-caution (the value of β 2 is 8 CPI : rather good (the value of β 2 is
5 Fig. 4: Detailed time schedule for case study more than β), 9 CPI : rather-good ( the value of β is 0 less than β), CPI : rather-super-star ( the value of β is more than β). Table 2: The status of earned value metrics Values Process decision CPI Rather caution SPI Rather poor A NEW APPLICATION TO A MULTI PERIOD-MULTI PRODUCT PRODUCTION PLANNING PROBLEM CPI P β 3 = = = 0.82 C P (7) Here, a case study given in [22-24] is initially used. That is why; in their study only production planning data had been observed. Thus, corresponding data to actual costs and also earned value amount based on achieved progress is then added in this paper. Hereby, based on data observed in multi period-multi product production planning problem, a detailed time schedule is constructed as given in Fig. 4. In above time schedule, activities to be done in a specific period, product and machine center have been shown. The horizontal axis also indicates required completion time. Since time schedule has prepared, Planned Value (PV) and consequently Earned Value amount (EV) can be easily calculated. Actual costs of work performed based activity level also added in order to make a meaningful earned value analysis. In given example, CPI and SPI values are calculated and shown in proposed control chart (Fig. 5) up to status date (tenth day). Relevant decisions about process conditions will be determined as follows: (Assume that predefined acceptable percentage value (β) is equal to 0.5) CPI in status day is equal to Assume a = 0.5, referring to Table, the value of β 3 should be calculated in order to make a decision about the process condition. The value of β 3 is calculated as follow: 688 Comparing obtained value of β 3 with value of predefined acceptable percentage (β), will yield a rather caution decision. SPI value in status date is equal to which referring to Table, value of β 3 should be calculated and compared with β value: SPI P β 3 = = = 0.02 C P Schedule performance condition is therefore determined as rather poor. CPI and SPI values in status date and related process decisions are shown in Fig. 6 and Table 2 respectively. CONCLUSION REMARK AND FURTHER INVESTIGATIONS In this paper a novel approach based of fuzzy control chart concept is proposed in order to control SPI/CPI trend in earned value method while previously developed version was only focused on four crisp simple control limit and no attention to intermediate linguistic terms had been carried out. Since project management can be efficiently applied in different (8)
6 CPI SPI Fig.5: CPI and SPI in fuzzy control chart until the status date Planned value Earned value Actual costs Fig.6: Earned value analysis cases, it would be highly desirable to conduct such a widely developed approach for controlling corresponding matrices. The approach also implemented successfully in a manufacturing environment, where the reader can easily make a sense about production status and consequently adapt it using earned value analysis accordingly. Further investigations can be done by applying stochastic process in earned value analysis in order to detect earned value control mechanism as well as fuzzy control chart. It highly can be applied specially in real case projects where the nature of projects is stochastically known. ACKNOWLEDGMENTS: The authors wish to express their acknowledgments to Iran National Science Foundation (INSF) for financial support of this research. 689 REFERENCES. Shewhart, W.A., 93. Economic Control of Quality of Manufactured Product. D. Van Nostrand, Inc., Princeton, NJ, 2. Gulbay, M., C. Kahraman and D. Ruan, cut fuzzy control charts for linguistic data. International Journal of Intelligent Systems, 9: Laviolette, M., Jr.J.W. Seaman, J. Douglas Barrett, William H. Woodall, 995. A probabilistic and statistical view of fuzzy methods. Technometrics, 37: Marcucci, M., 985. Monitoring multinomial processes. Journal of Quality Technology, 7: Wang, J.H. and T. Raz, 990. On the construction of control charts using linguistic variables. International Journal of Production Research, 28:
7 6. Raz, T. and J.-H. Wang, 990. Probabilistic and membership approaches in the construction of control charts for linguistic data. Production Planning and Control, : Kanagawa, A., F. Tamaki and H. Ohta, 993. Control charts for process average and variability based on linguistic data. International Journal of Production Research, 3: Taleb, H. and M. Limam, On fuzzy and probabilistic control charts. International Journal of Production Research, 40: Cheng, C.B., Fuzzy process control based on fuzzy regression and possibility measures. IEEE, pp: Cheng, C.B., Fuzzy process control: Construction of control charts with fuzzy numbers. Fuzzy Sets and Systems, 54: Gulbay, M. and C. Kahraman, An alternative approach to fuzzy control charts: Direct fuzzy approach. Information Sciences, 77: Faraz, A. and M. Bameni Moghadam, Fuzzy control chart a better alternative for Shewhart average chart. Quality and Quantity, 4: Anbari, F.T., Earned value project management method and extensions. Project Management Journal, 34 (4): Vandevoorde, S. and M. Vanhoucke, A comparison of different project duration forecasting methods using earned value metrics. International Journal of Project Management, 24: Vitner, G., Sh. Rozenes and S. Spraggett, Using data envelope analysis to compare project efficiency in a multi-project environment. International Journal of Project Management, 24: Cioffi, D.F., Designing project management: A scientific notation and an improved formalism for earned value calculations. International Journal of Project Management, 24: Cioffi, D.F., A tool for managing projects: An analytic parameterization of the S-curve. International Journal of Project Management, 23: Kim, E.H., Jr.W.G. Wells and M.R. Duffey, A model for effective implementation of Earned Value Management methodology. International Journal of Project Management, 2: Moslehi, O., J. Li and S. Alkas, Web-based integrated project control system. Construction Management and Economics, 22: Al-Jibouri, S.H., Monitoring systems and their effectiveness for project cost control in construction. International Journal of Project Management, 2: Stratton, R.W., Applying Earned Schedule Analysis to EVM data for Estimating Completion Date. AACE International Transactions, EVM, 4: Byrne, M.D. and M.A. Bakir, 999. Production planning using a hybrid simulation-analytical approach. International Journal of Production Economics, 59: Kim, B. and S. Kim, 200. Extended model for a hybrid production planning approach. International Journal of Production Economics, 73: Byrne, M.D. and M. Hossain, Production planning: An improved hybrid approach, Int. J. Production Economics, pp:
Project Control with ProTrack
Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS
Project Cash Flow Forecasting Using Value at Risk
Technical Journal of Engineering and Applied Sciences Available online at www.tjeas.com 213 TJEAS Journal21332/2681268 ISSN 2183 213 TJEAS Project Cash Flow Forecasting Using Value at Risk Mohammad Reza
How To Manage A Project
Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management
A FUZZY LOGIC APPROACH FOR SALES FORECASTING
A FUZZY LOGIC APPROACH FOR SALES FORECASTING ABSTRACT Sales forecasting proved to be very important in marketing where managers need to learn from historical data. Many methods have become available for
Earned value method as a tool for project control
Budownictwo i Architektura 3 (2008) 15-32 Earned value method as a tool for project control Institute of Construction, Faculty of Civil and Sanitary Engineering, Lublin University of Technology, 20-618
PROJECT MONITORING AND CONTROL USING BURNDOWN CHARTS
The 4 th edition of the Interdisciplinarity in Engineering International Conference Petru Maior University of Tîrgu Mureş, Romania, 2009 PROJECT MOITORIG AD COTROL USIG BURDOW CHARTS Attila Vajda Sysgenic
Forecasting Project Schedule Completion by Using Earned Value Metrics
Forecasting Project Schedule Completion by Using Earned Value Metrics Ing. Stephan Vandevoorde Sr. Project Manager Fabricom Airport Systems [email protected] 1 Agenda Introduction Schedule performance indicators
Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166
Towards a Complete Earned Value Analysis Sam Sharp and Peter Hall Paper # 166 Planned vs Actual A purely accounting approach to project tracking involves the monitoring of status by simply comparing actual
Introduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
Application of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study
2011 International Conference on Management and Service Science IPEDR vol.8 (2011) (2011) IACSIT Press, Singapore Application of Earned Value Management System on an Infrastructure Project: A Malaysian
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB
Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
Earned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
New Tools for Project Managers: Evolution of S-Curve and Earned Value Formalism
New Tools for Project Managers: Evolution of S-Curve and Earned Value Formalism A Presentation at the Third Caribbean & Latin American Conference On Project Management, 21 23 May 2003 Denis F. Cioffi,
Why EVM Is Not Good for Schedule Performance Analyses (and how it could be )
Why EVM Is Not Good for Schedule Performance Analyses (and how it could be ) By Radenko Corovic, MBA Abstract Project performance researchers are unanimous that the conventional EVM (Earned Value Management)
Assessing Schedule Performance with Earned Value
FEATURED PAPER OCTOBER 2007 Time Is Up: Assessing Schedule Performance with Earned Value By Robert Van De Velde Time drives projects. Quick and accurate evaluation of schedule performance is crucial. Quantitative
plans based on actual cost, schedule and technical progress of work [1, 9].
An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan
An Evaluation Model for Determining Insurance Policy Using AHP and Fuzzy Logic: Case Studies of Life and Annuity Insurances
Proceedings of the 8th WSEAS International Conference on Fuzzy Systems, Vancouver, British Columbia, Canada, June 19-21, 2007 126 An Evaluation Model for Determining Insurance Policy Using AHP and Fuzzy
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION Author Bill Mowery MPM, PMP Keywords Earned Value Management, Earned Schedule, Project Management, Cost
Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2
Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2 P.G. Student, Department of Civil & Environmental Engineering, NITTTR, Bhopal,
ANALYTICS IN BIG DATA ERA
ANALYTICS IN BIG DATA ERA ANALYTICS TECHNOLOGY AND ARCHITECTURE TO MANAGE VELOCITY AND VARIETY, DISCOVER RELATIONSHIPS AND CLASSIFY HUGE AMOUNT OF DATA MAURIZIO SALUSTI SAS Copyr i g ht 2012, SAS Ins titut
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
AACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
Tracking Software Development Progress with Earned Value and Use Case Point
ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with
PREDICTION FINANCIAL DISTRESS BY USE OF LOGISTIC IN FIRMS ACCEPTED IN TEHRAN STOCK EXCHANGE
PREDICTION FINANCIAL DISTRESS BY USE OF LOGISTIC IN FIRMS ACCEPTED IN TEHRAN STOCK EXCHANGE * Havva Baradaran Attar Moghadas 1 and Elham Salami 2 1 Lecture of Accounting Department of Mashad PNU University,
Using Earned Value Management for Improving Processes. By Cynthia K. West
Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.
IST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
earned value management
earned value management in control of big productions an eyeon white paper october 2013 1 contents 4 ly escalation 5 linking and cost control 6 cost forecasting 6 implementation towards effective project
Earned Value and Agile Reporting
Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,
Adaptive Demand-Forecasting Approach based on Principal Components Time-series an application of data-mining technique to detection of market movement
Adaptive Demand-Forecasting Approach based on Principal Components Time-series an application of data-mining technique to detection of market movement Toshio Sugihara Abstract In this study, an adaptive
A Hybrid Heuristic Rule for Constrained Resource Allocation in PERT Type Networks
World Applied Sciences Journal 7 (10): 1324-1330, 2009 ISSN 1818-4952 IDOSI Publications, 2009 A Hybrid Heuristic Rule for Constrained Resource Allocation in PERT Type Networks Siamak Baradaran and S.M.T.
IMPROVING TRADITIONAL EARNED VALUE MANAGEMENT BY INCORPORATING STATISTICAL PROCESS CHARTS
IMPROVING TRADITIONAL EARNED VALUE MANAGEMENT BY INCORPORATING STATISTICAL PROCESS CHARTS Sou-Sen Leu P.O.Box 90-30, Taipei, [email protected] You-Che Lin P.O.Box 90-30, Taipei, [email protected]
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 [email protected]
Evaluating Strategic Project and Portfolio Performance
Evaluating Strategic Project and Portfolio Performance Abstract To assess performance at the portfolio level, it is vital to measure the performance of individual projects and consolidate the measurements
Schedule Adherence a useful measure for project management
Schedule Adherence a useful measure for project management Walt Lipke PMI Oklahoma City Chapter Abstract: Earned Value Management (EVM) is a very good method of project management. However, EVM by itself
An introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
Unit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT
CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT PREPARED BY James E Aksel, PMP [email protected] http://www.msprojectdblog.com http://www.projectpmo.com Page 1 of 19 Table
Project Duration Forecasting a comparison of Earned Value Management methods to Earned Schedule
Project Duration Forecasting a comparison of Earned Value Management methods to Earned Schedule Walt Lipke Member of Oklahoma City Chapter Project Management Institute (USA) Abstract: Earned Value Management
Summary. Chapter Five. Cost Volume Relations & Break Even Analysis
Summary Chapter Five Cost Volume Relations & Break Even Analysis 1. Introduction : The main aim of an undertaking is to earn profit. The cost volume profit (CVP) analysis helps management in finding out
Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Rules on using templates 1) Must reference the template used 2) Use
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
UNCERTAINTIES OF MATHEMATICAL MODELING
Proceedings of the 12 th Symposium of Mathematics and its Applications "Politehnica" University of Timisoara November, 5-7, 2009 UNCERTAINTIES OF MATHEMATICAL MODELING László POKORÁDI University of Debrecen
Agile and Earned Value. A white paper. October 2013. Author Stephen Jones, Sellafield Ltd
Agile and Earned Value A white paper October 2013 Author Stephen Jones, Sellafield Ltd This document is a whitepaper produced by the APM Planning, Monitoring and Control SIG. It represents the thoughts
Fuzzy regression model with fuzzy input and output data for manpower forecasting
Fuzzy Sets and Systems 9 (200) 205 23 www.elsevier.com/locate/fss Fuzzy regression model with fuzzy input and output data for manpower forecasting Hong Tau Lee, Sheu Hua Chen Department of Industrial Engineering
PROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_cost_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern
Earned Schedule Leads to Improved Forecasting
Lipke, Walt Norman, Oklahoma, USA Earned Schedule Leads to Improved Forecasting Abstract For project cost, analysts can predict the final value with some confidence using the Independent Estimate at Completion
Fast Fuzzy Control of Warranty Claims System
Journal of Information Processing Systems, Vol.6, No.2, June 2010 DOI : 10.3745/JIPS.2010.6.2.209 Fast Fuzzy Control of Warranty Claims System Sang-Hyun Lee*, Sung Eui Cho* and Kyung-li Moon** Abstract
A collection of Safran Project report samples for project professionals
A collection of Safran Project report samples for project professionals Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger www.safran.com Contents Introduction... 2 About the Reports
Prediction of Stock Performance Using Analytical Techniques
136 JOURNAL OF EMERGING TECHNOLOGIES IN WEB INTELLIGENCE, VOL. 5, NO. 2, MAY 2013 Prediction of Stock Performance Using Analytical Techniques Carol Hargreaves Institute of Systems Science National University
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
DEVELOPMENT OF FUZZY LOGIC MODEL FOR LEADERSHIP COMPETENCIES ASSESSMENT CASE STUDY: KHOUZESTAN STEEL COMPANY
DEVELOPMENT OF FUZZY LOGIC MODEL FOR LEADERSHIP COMPETENCIES ASSESSMENT CASE STUDY: KHOUZESTAN STEEL COMPANY 1 MOHAMMAD-ALI AFSHARKAZEMI, 2 DARIUSH GHOLAMZADEH, 3 AZADEH TAHVILDAR KHAZANEH 1 Department
Chapter 6. (PMBOK Guide)
Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
+ The Killer Question For Every Manager
+ Glen B. Alleman Thomas J. Coonce Big Data Meets Earned Value Management We have lots data. How can we use it to make predictive and prescriptive forecasts of future performance to increase Probability
EVM.01. Earned Value Analysis Why it Doesn't Work
EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects
Copyright 2010-2012 PEOPLECERT Int. Ltd and IASSC
PEOPLECERT - Personnel Certification Body 3 Korai st., 105 64 Athens, Greece, Tel.: +30 210 372 9100, Fax: +30 210 372 9101, e-mail: [email protected], www.peoplecert.org Copyright 2010-2012 PEOPLECERT
Better decision making under uncertain conditions using Monte Carlo Simulation
IBM Software Business Analytics IBM SPSS Statistics Better decision making under uncertain conditions using Monte Carlo Simulation Monte Carlo simulation and risk analysis techniques in IBM SPSS Statistics
Fault Analysis in Software with the Data Interaction of Classes
, pp.189-196 http://dx.doi.org/10.14257/ijsia.2015.9.9.17 Fault Analysis in Software with the Data Interaction of Classes Yan Xiaobo 1 and Wang Yichen 2 1 Science & Technology on Reliability & Environmental
Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?
Resource Loading: who and/or what needed where and when. Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded? Resource
TIME FORECASTING USING EARNED SCHEDULE
TIME FORECASTING USING EARNED SCHEDULE THE EUROPEAN EXPERIENCE (WITH THE HELP OF THE US) By Ing. Stephan Vandevoorde Manager Airport Systems, CofelyFabricom Director, EVM Europe Agenda The Start The beginnings
Estimating Cost at Completion - Judgment & EV Information
Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number
PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP
PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP PROJECTS PROGRESS WELL UNTIL 70% Quick progress until 60-70% complete. Then we discover the project is in distress.
Fuzzy Numbers in the Credit Rating of Enterprise Financial Condition
C Review of Quantitative Finance and Accounting, 17: 351 360, 2001 2001 Kluwer Academic Publishers. Manufactured in The Netherlands. Fuzzy Numbers in the Credit Rating of Enterprise Financial Condition
Earned value analysis in project management: Survey and research potential
Earned value analysis in project management: Survey and research potential Milind Padalkar, Saji Gopinath* Quantitative Methods & Operations Management Indian Institute of Kozhikode, Kerala, India [email protected]
Software Project Scheduling under Uncertainties
Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials
700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
Study Plan for the Master Degree In Industrial Engineering / Management. (Thesis Track)
Study Plan for the Master Degree In Industrial Engineering / Management (Thesis Track) Plan no. 2005 T A. GENERAL RULES AND CONDITIONS: 1. This plan conforms to the valid regulations of programs of graduate
INTERNATIONAL JOURNAL FOR ENGINEERING APPLICATIONS AND TECHNOLOGY. Ameet.D.Shah 1, Dr.S.A.Ladhake 2. [email protected]
IJFEAT INTERNATIONAL JOURNAL FOR ENGINEERING APPLICATIONS AND TECHNOLOGY Multi User feedback System based on performance and Appraisal using Fuzzy logic decision support system Ameet.D.Shah 1, Dr.S.A.Ladhake
Selection of Database Management System with Fuzzy-AHP for Electronic Medical Record
I.J. Information Engineering and Electronic Business, 205, 5, -6 Published Online September 205 in MECS (http://www.mecs-press.org/) DOI: 0.585/ijieeb.205.05.0 Selection of Database Management System with
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management
A Comparative Study of the Pickup Method and its Variations Using a Simulated Hotel Reservation Data
A Comparative Study of the Pickup Method and its Variations Using a Simulated Hotel Reservation Data Athanasius Zakhary, Neamat El Gayar Faculty of Computers and Information Cairo University, Giza, Egypt
Using Model of Fuzzy Decision Support Systems in Iran Khodro Company's Recruitment and Selection Systems
2012 International Conference on Innovation and Information Management (ICIIM 2012) IPCSIT vol. 36 (2012) (2012) IACSIT Press, Singapore Using Model of Fuzzy Decision Support Systems in Iran Khodro Company's
What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate
The outcome of any venture is most often affected by the ready availability of useful information on which timely decisions can be taken. For project success, the need is therefore to know where you re
COMBINING THE METHODS OF FORECASTING AND DECISION-MAKING TO OPTIMISE THE FINANCIAL PERFORMANCE OF SMALL ENTERPRISES
COMBINING THE METHODS OF FORECASTING AND DECISION-MAKING TO OPTIMISE THE FINANCIAL PERFORMANCE OF SMALL ENTERPRISES JULIA IGOREVNA LARIONOVA 1 ANNA NIKOLAEVNA TIKHOMIROVA 2 1, 2 The National Nuclear Research
A study of cash flows in projects with fuzzy activity durations
icccbe 2010 Nottingham University Press Proceedings of the International Conference on Computing in Civil and Building Engineering W Tizani (Editor) A study of cash flows in projects with fuzzy activity
Earned Value Management for Enterprise Resource Planning Implementations
Earned Value Management for Enterprise Resource Planning Implementations Venu Kotamraju Abstract ERP implementations are a special breed of projects. They are often characterized by aggressive timelines,
Identifying At-Risk Students Using Machine Learning Techniques: A Case Study with IS 100
Identifying At-Risk Students Using Machine Learning Techniques: A Case Study with IS 100 Erkan Er Abstract In this paper, a model for predicting students performance levels is proposed which employs three
Big Data with Rough Set Using Map- Reduce
Big Data with Rough Set Using Map- Reduce Mr.G.Lenin 1, Mr. A. Raj Ganesh 2, Mr. S. Vanarasan 3 Assistant Professor, Department of CSE, Podhigai College of Engineering & Technology, Tirupattur, Tamilnadu,
Nine Common Types of Data Mining Techniques Used in Predictive Analytics
1 Nine Common Types of Data Mining Techniques Used in Predictive Analytics By Laura Patterson, President, VisionEdge Marketing Predictive analytics enable you to develop mathematical models to help better
Getting insights about life cycle cost drivers: an approach based on big data inspired statistical modelling
Introduction A Big Data applied to LCC Conclusion, Getting insights about life cycle cost drivers: an approach based on big data inspired statistical modelling Instituto Superior Técnico, Universidade
Forecasting of Economic Quantities using Fuzzy Autoregressive Model and Fuzzy Neural Network
Forecasting of Economic Quantities using Fuzzy Autoregressive Model and Fuzzy Neural Network Dušan Marček 1 Abstract Most models for the time series of stock prices have centered on autoregressive (AR)
Measurement and Metrics Fundamentals. SE 350 Software Process & Product Quality
Measurement and Metrics Fundamentals Lecture Objectives Provide some basic concepts of metrics Quality attribute metrics and measurements Reliability, validity, error Correlation and causation Discuss
U.P.B. Sci. Bull., Series C, Vol. 77, Iss. 1, 2015 ISSN 2286 3540
U.P.B. Sci. Bull., Series C, Vol. 77, Iss. 1, 2015 ISSN 2286 3540 ENTERPRISE FINANCIAL DISTRESS PREDICTION BASED ON BACKWARD PROPAGATION NEURAL NETWORK: AN EMPIRICAL STUDY ON THE CHINESE LISTED EQUIPMENT
Cost VOLUME RELATIONS & BREAK EVEN ANALYSIS
1. Introduction The cost volume profit (CVP) analysis helps management in finding out the relationship of costs and revenues to profit. Cost depends on various factors like Volume of production Product
2.3 Solving Equations Containing Fractions and Decimals
2. Solving Equations Containing Fractions and Decimals Objectives In this section, you will learn to: To successfully complete this section, you need to understand: Solve equations containing fractions
Fuzzy Logic Based Revised Defect Rating for Software Lifecycle Performance. Prediction Using GMR
BIJIT - BVICAM s International Journal of Information Technology Bharati Vidyapeeth s Institute of Computer Applications and Management (BVICAM), New Delhi Fuzzy Logic Based Revised Defect Rating for Software
Project Management Institute (PMBOK 2000) PMP Preparation Worksheet
Project Integration Management Processes required to ensure that the various elements of the project are properly coordinated to meet / exceed stakeholder expectations. Project Plan Development Other ning
Abstract. Earned Value Management Basics
Earned Schedule: A Breakthrough Extension to Earned Value Management Kym Henderson Education Director, Project Management Institute, Sydney Australia Chapter Abstract Earned Schedule (ES) analysis is a
Simple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
Factorial Invariance in Student Ratings of Instruction
Factorial Invariance in Student Ratings of Instruction Isaac I. Bejar Educational Testing Service Kenneth O. Doyle University of Minnesota The factorial invariance of student ratings of instruction across
MISSING DATA TECHNIQUES WITH SAS. IDRE Statistical Consulting Group
MISSING DATA TECHNIQUES WITH SAS IDRE Statistical Consulting Group ROAD MAP FOR TODAY To discuss: 1. Commonly used techniques for handling missing data, focusing on multiple imputation 2. Issues that could
Predictive Analytics Tools and Techniques
Global Journal of Finance and Management. ISSN 0975-6477 Volume 6, Number 1 (2014), pp. 59-66 Research India Publications http://www.ripublication.com Predictive Analytics Tools and Techniques Mr. Chandrashekar