1 Technical Journal of Engineering and Applied Sciences Available online at TJEAS Journal21332/ ISSN TJEAS Project Cash Flow Forecasting Using Value at Risk Mohammad Reza Feylizadeh 1*, Morteza Bagherpour 2 1. Department of Industrial Engineering, Islamic Azad University, Shiraz branch, Shiraz, Iran 2. Department of industrial Engineering, Iran University of Science and Technology, Tehran, Iran Corresponding author: Mohammad Reza Feylizadeh ABSTRACT: At the start of a project, project manager would like to understand trend of money receipt and payments in future. However, accuracy of project cash flow always is an important issue since receipt and payments are probabilistically known. On the hand, value at risk (VAR) is a statistical technique used to measure and quantify the level of financial risk within a firm or investment portfolio over a specific time horizon. Although VAR is a powerful technique for measuring financial risks, it mostly applied in financial firms. In this paper, VAR is applied in project cash flow forecasting. The approach proposed in this paper, employed different probabilistic conditions of a project such as extra works, changes and s. The approach is successfully implemented through a construction project. Forecasting, Risk Management, Simulation, statistical technique INTRODUCTION In project management systems, it is essential to aware of the project cash flow. An accurate prediction of cash flow leads project manager to effective monitoring of the project. The importance of cash flow forecasting comes from this fact that the required cash should be announced to sponsor. The sponsor will support the project from financial source according to cash flow forecast. Note that cash flow shall be under control all the time to ensure project profitability. However, the accuracy of project cash flow is still under investigation by many researchers. In this respect, initially fuzzy modelling of project scheduling has been considered for analysing cash flow (Bonnal et al., 24). After that a reliable cash flow prediction in construction projects was pointed out to assists the project manager in a better position to identify problems and develop appropriate managerial strategies to overcome forthcoming issues (Cheng and Roy, 21). Also it was pointed out that with a reliable estimation of project s cash flow, contractor will be able to improve the financial position of projects (Hwee and Tiong, 22). It was stated cash flow forecasting plays the role of an early warning system for program and projects and he suggested a cash flow forecasting model based on bottom estimation of contractor costs (Maravas and Pantouvakis, 211; Mavrotas et al., 2). It was generated a model for cash flow forecasting using weighed mean of cost categories. This model was built based on the planed value and the actual cost happened on job site (Park et al., 2). On the other side, VAR has been extensively applied through financial firms. That was why; market forecasting under risk condition had been focused (Berkowitz, 2; Christoffersen, 1998) and then many models has been suggested and fitted for modelling of market and financial firms under probabilistic and risk conditions (Dowd, 22; Dowd, 2). Kupiec (2) examined verification of different financial risk management models to select the better choice. The approaches discussed above mostly relied on information existing at job site levels or applying fuzzy logic models. None of them has been argued modelling of project cash flow where input variables are probabilistically given. Also, there are many s in construction projects to be covered through modelling of cash flows. Finally, it is pointed out that whole the parameters under risk should be financially measured using Monte Carlo simulation study.

2 Tech J Engin & App Sci., 3 (2): , 213 Problem Statement Consider a construction project is being executed. There are several phases to be completed to hand over the project. In order to recognize cash flow behaviour and its forecasting, probabilistic parameters and s should be analysed. Through this procedure, the following inputs should be considered: Extra works resulting variation of order Changes during project execution Reworks resulting employer inspection and approval process Probabilistic nature of incurred cost (happening of actual costs) On the other hand, time schedule, as one of important input for forecasting of project cash flow, is deterministically known and during project execution is being changed. The aim of this study is to measure financial risks of a project resulting from value at risk technique during project execution under different conditions of the project undertaken. Modelling Procedure The following steps should be implemented in order to forecast a project cash flow: Step 1 Initialize project time schedule Step 2 Initialize input parameters (extra works, changes, s ) Step 3 Information gathering for selected inputs Step 4 Initialize VAR model and cash flow at risk Step Run MonteCarlo simulation Step 6 Verify simulation study Step 7 Set different conditions of the project (develop the model) Step 8 Report outputs Step 9 Suggest corrective actions Step 1 Run the above mentioned procedure while stopping condition satisfied. The stopping condition maybe includes: Set number of simulation run more than 1, Set error function to be less than 1 % A mix of both strategies The approach proposed above is an embedded system including project management and financial risk management. If both applied altogether, a project manager would be confident of the accuracy of cash flow forecasting. case study data Consider a construction project which cost estimation is equal to 11 M USD. The project is achieved more than percent progress. After data gathering process, the data has been summarized in Table 1. Items phase 1 phase 2 phase 3 phase 4 phase phase 6 phase 7 phase 8 phase 9 Table1. Data gathering for cash flow forecasting Description Upper bound % Most likely % Lower bound % change change Extra work Extra work 1 Extra work RESULTS The results have been obtained after 1, simulation run software. Distributed cash flow has been then obtained as given in Figure

3 Tech J Engin & App Sci., 3 (2): , 213 Figure 1. Project value at risk using simulation study As it is indicated above, value at risk with percent level of significance, is equal to 122. It means that with a 9 percent level of confidence, cash flow is less than 122 for whole the project. Also Figure 2 indicates cash flow for extra work with a 9 percent confident is between Figure 2. Cash flow simulation for extra works Figure 3 illustrates the cash flow simulation for change orders. It reveals that this amount has not a significant impact on the total project cash flow. 2683

4 Tech J Engin & App Sci., 3 (2): , 213 Figure 3. Value at risk for change order Value at risk using cash flow simulation also has been studied for s which is presented in Figure 4. Figure 4. Value at risk for s The above mentioned reports indicate value at risk for extra works is higher than the other affecting factors on cash flow forecasting. This type of risk maybe transferred to the employer where the actual quantities exceed the planned one as mentioned in the contract. Thus, this type of analysis will assist both employer and contractor to finance the required amount based on 9 percent confidence and take it into budgetary estimate for further action. After running VAR the profitability index also would be automatically updated. CONCLUSION REMARK AND FURTHER RECOMMENDATIONS VAR has been mostly applied through financial firms. In this paper, VAR employed for project cash flow forecasting where several probabilistic parameters have been associated. The project cash flow including extra works, change orders and s have simulated to determine financial risks of the project undertaken. Different scenarios have been developed and simulated using 9 percent confidence interval. The approach should be periodically updated and the obtained results will forward to employer in order to finance the required cash and 2684

5 Tech J Engin & App Sci., 3 (2): , 213 updating profitability index. Moreover, risk mitigation strategies can be applied to enhance performance of the project. This issue can be focused as a future research work. Additionally, value engineering can be embedded to this system to reduce total cash required for the project undertaken. REFERENCES Berkowitz J. 2. Testing Density Forecasts, with Applications to Risk Management. Graduate School of Management, University of California, Irvine Bonnal P, Gourc K, Lacoste G. 24. Where do we stand with fuzzy project scheduling? Journal of Construction Engineering and Management 13(1): Cheng M, Roy A. 21. Evolutionary fuzzy decision model for cash flow prediction using timedependent support vector machines. International journal of project management 29:6 6 Christoffersen P Evaluating Interval Forecasts. International Economic Review 39: Dowd K. 22. A Bootstrap Backtest. Risk 1(1):9394 Dowd K. 2. Measuring Market Risk, 2nd edn. John Wiley and Sons, Chichester and New York Hwee N, Tiong R. 22. Model on cash flow forecasting and risk analysis for contracting firms. International journal of project management 2: Kupiec PH Techniques for Verifying the Accuracy of Risk Management Models. Journal of Derivatives 3(2):7384 Maravas A, Pantouvakis J Project cash flow analysis in the presence of uncertainty in activity duration and cost. International journal of project management 13(1):111 Mavrotas G, Caloghirou Y, Koune J. 2. A model on cash flow forecasting and early warning for multiproject programmes: application to the Operational Programme for the Information Society in Greece. International journal of project management 23: Park H, Han S, Russell J. 2. Cash Flow Forecasting Model for General Contractors Using Moving Weights of Cost Categories. Journal of Management and Engineering 4 (164): Value At Risk (VAR) 268

Applying Fuzzy Control Chart in Earned Value Analysis: A New Application

Applying Fuzzy Control Chart in Earned Value Analysis: A New Application World Applied Sciences Journal 3 (4): 684-690, 2008 ISSN 88-4952 IDOSI Publications, 2008 Applying Fuzzy Control Chart in Earned Value Analysis: A New Application Siamak Noori, Morteza Bagherpour and Abalfazl

More information

Amajor benefit of Monte-Carlo schedule analysis is to

Amajor benefit of Monte-Carlo schedule analysis is to 2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to

More information

Volume 2, Issue 12, December 2014 International Journal of Advance Research in Computer Science and Management Studies

Volume 2, Issue 12, December 2014 International Journal of Advance Research in Computer Science and Management Studies Volume 2, Issue 12, December 2014 International Journal of Advance Research in Computer Science and Management Studies Research Article / Survey Paper / Case Study Available online at: www.ijarcsms.com

More information

Rehabilitation Scenarios for Sustainable Water Mains. University, Montreal, Quebec, Canada, PH (514) 848-2424 ext. 8779; FAX (514) 848-7965; email:

Rehabilitation Scenarios for Sustainable Water Mains. University, Montreal, Quebec, Canada, PH (514) 848-2424 ext. 8779; FAX (514) 848-7965; email: Rehabilitation Scenarios for Sustainable Water Mains Khaled Shahata 1 ; Tarek Zayed 2 ; and Saad Al-Jibouri 3 1 Graduate Student, Department of Building, Civil, and Environmental Engineering, Concordia

More information

Fuzzy Probability Distributions in Bayesian Analysis

Fuzzy Probability Distributions in Bayesian Analysis Fuzzy Probability Distributions in Bayesian Analysis Reinhard Viertl and Owat Sunanta Department of Statistics and Probability Theory Vienna University of Technology, Vienna, Austria Corresponding author:

More information

Credit Risk Stress Testing

Credit Risk Stress Testing 1 Credit Risk Stress Testing Stress Testing Features of Risk Evaluator 1. 1. Introduction Risk Evaluator is a financial tool intended for evaluating market and credit risk of single positions or of large

More information

In initial planning phases In monitoring and execution phases

In initial planning phases In monitoring and execution phases Project management What is it? Project management is a framework for a range of tools for helping plan and implement development and change projects. A range of tools exist, including: Gantt charts (bar

More information

ORACLE S PRIMAVERA RISK ANALYSIS

ORACLE S PRIMAVERA RISK ANALYSIS ORACLE S PRIMAVERA RISK ANALYSIS KEY FEATURES Risk Analysis Guide Schedule Check Templated Quick Risk Risk Register Wizard Risk Register Risk Analysis Every project has risks. The organizations that succeed

More information

Multiproject Scheduling in Construction Industry

Multiproject Scheduling in Construction Industry Multiproject Scheduling in Construction Industry Y. Gholipour Abstract In this paper, supply policy and procurement of shared resources in some kinds of concurrent construction projects are investigated.

More information

The Role Of Management Accounting In Budget Control

The Role Of Management Accounting In Budget Control J. Appl. Environ. Biol. Sci., 5(4S)95-100, 2015 2015, TextRoad Publication ISSN: 2090-4274 Journal of Applied Environmental and Biological Sciences www.textroad.com The Role Of Management Accounting In

More information

The Study of Working Capital Strategies in Life Cycle of Companies

The Study of Working Capital Strategies in Life Cycle of Companies 2013, World of Researches Publication Ac. J. Acco. Eco. Res. Vol. 2, Issue 4, 77-88, 2013 Academic Journal of Accounting and Economic Researches www.worldofresearches.com The Study of Working Capital Strategies

More information

Project Cash Flow. Scenario Testing

Project Cash Flow. Scenario Testing Project Cash Flow By Dr. Ibrahim Assakkaf The Need Scenario Testing Cash flows can be estimated by attempting to assess flows from 1. Project in progress. 2. Projects under contract but not yet begun.

More information

Quantitative Risk Analysis with Microsoft Project

Quantitative Risk Analysis with Microsoft Project Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials

More information

A COMPACT MODEL FOR PREDICTING ROAD TRAFFIC NOISE

A COMPACT MODEL FOR PREDICTING ROAD TRAFFIC NOISE Iran. J. Environ. Health. Sci. Eng., 2009, Vol. 6, No. 3, pp. 181-186 A COMPACT MODEL FOR PREDICTING ROAD TRAFFIC NOISE 1* R. Golmohammadi, 2 M. Abbaspour, 3 P. Nassiri, 4 H. Mahjub 1 Department of Occupational

More information

Web Service Monitoring Scheduler based on evaluated QoS in Dynamic Environment

Web Service Monitoring Scheduler based on evaluated QoS in Dynamic Environment Quest Journals Journal of Software Engineering and Simulation Volume 2 ~ Issue 3 (2014) pp: 01-08 ISSN(Online) :2321-3795 ISSN (Print):2321-3809 www.questjournals.org Research Paper Web Service Monitoring

More information

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost

More information

Introduction. Evaluating Value for Money. Hans de Kievit Senior PPP Consultant. Projects: Auditing Public Private Partnerships; the work continues

Introduction. Evaluating Value for Money. Hans de Kievit Senior PPP Consultant. Projects: Auditing Public Private Partnerships; the work continues Evaluating Value for Money Auditing Public Private Partnerships; the work continues Seminar for Supreme Audit Institutions 26 and 27 November 2012 The Hague, The Netherlands Introduction Hans de Kievit

More information

Fundamentals Level Skills Module, Paper F8 (IRL) 1 (a) Audit procedures procurement and purchases system

Fundamentals Level Skills Module, Paper F8 (IRL) 1 (a) Audit procedures procurement and purchases system Answers Fundamentals Level Skills Module, Paper F8 (IRL) Audit and Assurance (Irish) December 2007 Answers 1 (a) Audit procedures procurement and purchases system Procedure Obtain a sample of e-mails from

More information

Risk Analysis and Quantification

Risk Analysis and Quantification Risk Analysis and Quantification 1 What is Risk Analysis? 2. Risk Analysis Methods 3. The Monte Carlo Method 4. Risk Model 5. What steps must be taken for the development of a Risk Model? 1.What is Risk

More information

International Journal of Mechatronics, Electrical and Computer Technology

International Journal of Mechatronics, Electrical and Computer Technology A Method for Increasing Modifiability in Enterprise Architecture Implementation Using Cloud Computing Narges Rahmani 1*, Sayed Mehran Sharafi 2 and Bahman Zamani 3 1 Graduate Student, Department of Computer

More information

CONTENTS. List of Figures List of Tables. List of Abbreviations

CONTENTS. List of Figures List of Tables. List of Abbreviations List of Figures List of Tables Preface List of Abbreviations xiv xvi xviii xx 1 Introduction to Value at Risk (VaR) 1 1.1 Economics underlying VaR measurement 2 1.1.1 What is VaR? 4 1.1.2 Calculating VaR

More information

Measurement of Banks Exposure to Interest Rate Risk and Principles for the Management of Interest Rate Risk respectively.

Measurement of Banks Exposure to Interest Rate Risk and Principles for the Management of Interest Rate Risk respectively. INTEREST RATE RISK IN THE BANKING BOOK Over the past decade the Basel Committee on Banking Supervision (the Basel Committee) has released a number of consultative documents discussing the management and

More information

DEVELOPMENT OF FUZZY LOGIC MODEL FOR LEADERSHIP COMPETENCIES ASSESSMENT CASE STUDY: KHOUZESTAN STEEL COMPANY

DEVELOPMENT OF FUZZY LOGIC MODEL FOR LEADERSHIP COMPETENCIES ASSESSMENT CASE STUDY: KHOUZESTAN STEEL COMPANY DEVELOPMENT OF FUZZY LOGIC MODEL FOR LEADERSHIP COMPETENCIES ASSESSMENT CASE STUDY: KHOUZESTAN STEEL COMPANY 1 MOHAMMAD-ALI AFSHARKAZEMI, 2 DARIUSH GHOLAMZADEH, 3 AZADEH TAHVILDAR KHAZANEH 1 Department

More information

seic.com/institutions

seic.com/institutions Nonprofit Management Research Panel Liquidity Pool Management for U.S. Colleges and Universities Gain a better understanding of your school s financial risks and the benefits of integrating the investment

More information

Sensitivity Analysis of Safety Measures for Railway Tunnel Fire Accident

Sensitivity Analysis of Safety Measures for Railway Tunnel Fire Accident Sensitivity Analysis of Safety Measures for Railway Tunnel Fire Accident Sanglog Kwak, Jongbae Wang, Yunok Cho Korea Railroad Research Institute, Uiwnag City, Kyonggi-do, Korea Abstract: After the subway

More information

Checklist for Operational Risk Management

Checklist for Operational Risk Management Checklist for Operational Risk Management I. Development and Establishment of Comprehensive Operational Risk Management System by Management Checkpoints - Operational risk is the risk of loss resulting

More information

Online Publication Date: 1 st August 2012 Publisher: Asian Economic and Social Society

Online Publication Date: 1 st August 2012 Publisher: Asian Economic and Social Society Online Publication Date: 1 st August 2012 Publisher: Asian Economic and Social Society The Study of Improvement of the Level of Access to Capital Market on Efficiency of Tehran Stock Exchange Amir Hossein

More information

Predictive time series analysis of stock prices using neural network classifier

Predictive time series analysis of stock prices using neural network classifier Predictive time series analysis of stock prices using neural network classifier Abhinav Pathak, National Institute of Technology, Karnataka, Surathkal, India abhi.pat93@gmail.com Abstract The work pertains

More information

Benefits Realization from IS & IT, and Change Management of roles and the working practices of individuals and teams.

Benefits Realization from IS & IT, and Change Management of roles and the working practices of individuals and teams. : Delivering Value from IS & IT Investments John Ward and Elizabeth Daniel John Wiley & Son Ltd ISBN: 9780470094631, 399 pages Theme of the Book This book explores a process and practical tools and frameworks

More information

THE INSURANCE BUSINESS (SOLVENCY) RULES 2015

THE INSURANCE BUSINESS (SOLVENCY) RULES 2015 THE INSURANCE BUSINESS (SOLVENCY) RULES 2015 Table of Contents Part 1 Introduction... 2 Part 2 Capital Adequacy... 4 Part 3 MCR... 7 Part 4 PCR... 10 Part 5 - Internal Model... 23 Part 6 Valuation... 34

More information

COMPUTING DURATION, SLACK TIME, AND CRITICALITY UNCERTAINTIES IN PATH-INDEPENDENT PROJECT NETWORKS

COMPUTING DURATION, SLACK TIME, AND CRITICALITY UNCERTAINTIES IN PATH-INDEPENDENT PROJECT NETWORKS Proceedings from the 2004 ASEM National Conference pp. 453-460, Alexandria, VA (October 20-23, 2004 COMPUTING DURATION, SLACK TIME, AND CRITICALITY UNCERTAINTIES IN PATH-INDEPENDENT PROJECT NETWORKS Ryan

More information

WestminsterResearch http://www.westminster.ac.uk/research/westminsterresearch

WestminsterResearch http://www.westminster.ac.uk/research/westminsterresearch WestminsterResearch http://www.westminster.ac.uk/research/westminsterresearch A web-based hybrid system for blended electronic, mobile and social media marketing planning Shuliang Li Jim Zheng Li School

More information

CITIGROUP INC. BASEL II.5 MARKET RISK DISCLOSURES AS OF AND FOR THE PERIOD ENDED MARCH 31, 2013

CITIGROUP INC. BASEL II.5 MARKET RISK DISCLOSURES AS OF AND FOR THE PERIOD ENDED MARCH 31, 2013 CITIGROUP INC. BASEL II.5 MARKET RISK DISCLOSURES AS OF AND FOR THE PERIOD ENDED MARCH 31, 2013 DATED AS OF MAY 15, 2013 Table of Contents Qualitative Disclosures Basis of Preparation and Review... 3 Risk

More information

Monte Carlo Simulations for Patient Recruitment: A Better Way to Forecast Enrollment

Monte Carlo Simulations for Patient Recruitment: A Better Way to Forecast Enrollment Monte Carlo Simulations for Patient Recruitment: A Better Way to Forecast Enrollment Introduction The clinical phases of drug development represent the eagerly awaited period where, after several years

More information

Evaluating the Critical success factors of strategic customer relationship management (SCRM) in textile industry (with Fuzzy Approach)

Evaluating the Critical success factors of strategic customer relationship management (SCRM) in textile industry (with Fuzzy Approach) International Research Journal of Applied and Basic Sciences 2015 Available online at www.irjabs.com ISSN 2251-838X / Vol, 9 (9): 1560-1567 Science Explorer Publications Evaluating the Critical success

More information

Building and Using Spreadsheet Decision Models

Building and Using Spreadsheet Decision Models Chapter 9 Building and Using Spreadsheet Decision Models Models A model is an abstraction or representation of a real system, idea, or object. Models could be pictures, spreadsheets, or mathematical relationships

More information

Financial Risk Management

Financial Risk Management IEOR E4723: Topics In Quantitative Finance Financial Risk Management Summer 2008, Instructor: Allan M. Malz, 1.5 credits DRAFT Syllabus Course description This course introduces students to the understanding

More information

Chapter - 9. Credit Management

Chapter - 9. Credit Management Chapter - 9 Credit Management Purpose You can use Credit Management to minimize financial risks for your organization. Credit Management makes it possible for you to carry out credit checks in transaction

More information

Dimitris Katsianis. University of Athens Dept of Informatics & Telecommunications email:dkats@di.uoa.gr

Dimitris Katsianis. University of Athens Dept of Informatics & Telecommunications email:dkats@di.uoa.gr Techno Economic Methodology for the Evaluation of Telecommunication Investment Projects. Sensitivity and Risk Analysis Incorporation Dimitris Katsianis University of Athens Dept of Informatics & Telecommunications

More information

Margin Calculation Methodology and Derivatives and Repo Valuation Methodology

Margin Calculation Methodology and Derivatives and Repo Valuation Methodology Margin Calculation Methodology and Derivatives and Repo Valuation Methodology 1 Overview This document presents the valuation formulas for interest rate derivatives and repo transactions implemented in

More information

1) What kind of risk on settlements is covered by 'Herstatt Risk' for which BCBS was formed?

1) What kind of risk on settlements is covered by 'Herstatt Risk' for which BCBS was formed? 1) What kind of risk on settlements is covered by 'Herstatt Risk' for which BCBS was formed? a) Exchange rate risk b) Time difference risk c) Interest rate risk d) None 2) Which of the following is not

More information

UNCERTAINTIES OF MATHEMATICAL MODELING

UNCERTAINTIES OF MATHEMATICAL MODELING Proceedings of the 12 th Symposium of Mathematics and its Applications "Politehnica" University of Timisoara November, 5-7, 2009 UNCERTAINTIES OF MATHEMATICAL MODELING László POKORÁDI University of Debrecen

More information

A System Dynamics Approach to Reduce Total Inventory Cost in an Airline Fueling System

A System Dynamics Approach to Reduce Total Inventory Cost in an Airline Fueling System , June 30 - July 2, 2010, London, U.K. A System Dynamics Approach to Reduce Total Inventory Cost in an Airline Fueling System A. Al-Refaie, M. Al-Tahat, and I. Jalham Abstract An airline fueling system

More information

ijcrb.webs.com INTERDISCIPLINARY JOURNAL OF CONTEMPORARY RESEARCH IN BUSINESS NOVEMBER 2013 VOL 5, NO 7 Abstract

ijcrb.webs.com INTERDISCIPLINARY JOURNAL OF CONTEMPORARY RESEARCH IN BUSINESS NOVEMBER 2013 VOL 5, NO 7 Abstract Relationship management training to improve the performance of individual public managers in Yazd Seyed Mohammad Reza Madani Department of Public Administration, Science and Research Branch, Islamic Azad

More information

University of Huddersfield Repository

University of Huddersfield Repository University of Huddersfield Repository Hajjaji, Mufeed, Denton, Paul and Jackson, Steve The effectiveness of using project management tools and techniques for delivering projects Original Citation Hajjaji,

More information

Reliability Modeling Software Defined

Reliability Modeling Software Defined Reliability Modeling Software Defined Using Titan Reliability Modeling Software May 30, 2014 Prepared by: The Fidelis Group 122 West Way, Suite 300 Lake Jackson, TX 77566 Fidelis Group, LLC All Rights

More information

3 Results. σdx. df =[µ 1 2 σ 2 ]dt+ σdx. Integration both sides will form

3 Results. σdx. df =[µ 1 2 σ 2 ]dt+ σdx. Integration both sides will form Appl. Math. Inf. Sci. 8, No. 1, 107-112 (2014) 107 Applied Mathematics & Information Sciences An International Journal http://dx.doi.org/10.12785/amis/080112 Forecasting Share Prices of Small Size Companies

More information

Better decision making under uncertain conditions using Monte Carlo Simulation

Better decision making under uncertain conditions using Monte Carlo Simulation IBM Software Business Analytics IBM SPSS Statistics Better decision making under uncertain conditions using Monte Carlo Simulation Monte Carlo simulation and risk analysis techniques in IBM SPSS Statistics

More information

Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D.

Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D. Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D. Critical Path Method Scheduling - Some Important Reservations The critical path method (CPM) of scheduling a project is a key tool for project

More information

Real Option Liabilities and New Product Development

Real Option Liabilities and New Product Development Journal of Applied Business and Economics Real Option Liabilities and New Product Development Mark J. Shrader Gonzaga University Many financial academics and practitioners have long realized that the standard

More information

CRASHING-RISK-MODELING SOFTWARE (CRMS)

CRASHING-RISK-MODELING SOFTWARE (CRMS) International Journal of Science, Environment and Technology, Vol. 4, No 2, 2015, 501 508 ISSN 2278-3687 (O) 2277-663X (P) CRASHING-RISK-MODELING SOFTWARE (CRMS) Nabil Semaan 1, Najib Georges 2 and Joe

More information

REDUCING UNCERTAINTY IN SOLAR ENERGY ESTIMATES

REDUCING UNCERTAINTY IN SOLAR ENERGY ESTIMATES REDUCING UNCERTAINTY IN SOLAR ENERGY ESTIMATES Mitigating Energy Risk through On-Site Monitoring Marie Schnitzer, Vice President of Consulting Services Christopher Thuman, Senior Meteorologist Peter Johnson,

More information

Identification and Prioritization of Knowledge Flow Barriers Based on Organizational Knowledge Management Cycle (OKMC)

Identification and Prioritization of Knowledge Flow Barriers Based on Organizational Knowledge Management Cycle (OKMC) Identification and Prioritization of Knowledge Flow Barriers Based on Organizational Knowledge Management Cycle (OKMC) Hessam Zandhessami * Assistant Professor, Department of Industrial Management, Qazvin

More information

Managing Risks and Optimising an Energy Portfolio with PLEXOS

Managing Risks and Optimising an Energy Portfolio with PLEXOS Managing Risks and Optimising an Energy Portfolio with PLEXOS Tom Forrest, B.Com. (Hons) Senior Power Market Consultant - Europe 1 Introduction Energy markets inherently exhibit far greater risk compared

More information

Evaluation of the Financial Investment Kist Outcome of Iran Joint Stock Insurance Company in the Years 2006-2012

Evaluation of the Financial Investment Kist Outcome of Iran Joint Stock Insurance Company in the Years 2006-2012 2015, TextRoad Publication ISSN: 2090-4274 Journal of Applied Environmental and Biological Sciences www.textroad.com Evaluation of the Financial Investment Kist Outcome of Iran Joint Stock Insurance Company

More information

Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson

Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson Page 1 of 13 Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models Martin Hopkinson Abstract Monte Carlo schedule risk analysis has become a widely practiced

More information

TEST PLAN Issue Date: <dd/mm/yyyy> Revision Date: <dd/mm/yyyy>

TEST PLAN Issue Date: <dd/mm/yyyy> Revision Date: <dd/mm/yyyy> DEPARTMENT OF HEALTH AND HUMAN SERVICES ENTERPRISE PERFORMANCE LIFE CYCLE FRAMEWORK CHECKLIIST TEST PLAN Issue Date: Revision Date: Document Purpose The purpose of

More information

Waste Transfer Pricing Methodology for the disposal of higher activity waste from new nuclear power stations

Waste Transfer Pricing Methodology for the disposal of higher activity waste from new nuclear power stations Waste Transfer Pricing Methodology for the disposal of higher activity waste from new nuclear power stations December 2011 Contents Contents... i Introduction... 1 Executive Summary... 1 Background...

More information

Capital Adequacy: Advanced Measurement Approaches to Operational Risk

Capital Adequacy: Advanced Measurement Approaches to Operational Risk Prudential Standard APS 115 Capital Adequacy: Advanced Measurement Approaches to Operational Risk Objective and key requirements of this Prudential Standard This Prudential Standard sets out the requirements

More information

Cash Flow Estimation for Engineering Projects using Project Management Software

Cash Flow Estimation for Engineering Projects using Project Management Software RESEARCH Cash Flow Estimation for Engineering Projects using Project Management Software Vivek C. Datey* ABSTRACT Organizations undertaking engineering projects as a business activity face difficulties

More information

CASH FLOW MATCHING PROBLEM WITH CVaR CONSTRAINTS: A CASE STUDY WITH PORTFOLIO SAFEGUARD. Danjue Shang and Stan Uryasev

CASH FLOW MATCHING PROBLEM WITH CVaR CONSTRAINTS: A CASE STUDY WITH PORTFOLIO SAFEGUARD. Danjue Shang and Stan Uryasev CASH FLOW MATCHING PROBLEM WITH CVaR CONSTRAINTS: A CASE STUDY WITH PORTFOLIO SAFEGUARD Danjue Shang and Stan Uryasev PROJECT REPORT #2011-1 Risk Management and Financial Engineering Lab Department of

More information

Simulating Insurance Portfolios using Cloud Computing

Simulating Insurance Portfolios using Cloud Computing Mat-2.4177 Seminar on case studies in operations research Simulating Insurance Portfolios using Cloud Computing Project Plan February 23, 2011 Client: Model IT Jimmy Forsman Tuomo Paavilainen Topi Sikanen

More information

RAVEN: A GUI and an Artificial Intelligence Engine in a Dynamic PRA Framework

RAVEN: A GUI and an Artificial Intelligence Engine in a Dynamic PRA Framework INL/CON-13-28360 PREPRINT RAVEN: A GUI and an Artificial Intelligence Engine in a Dynamic PRA Framework ANS Annual Meeting C. Rabiti D. Mandelli A. Alfonsi J. J. Cogliati R. Kinoshita D. Gaston R. Martineau

More information

plans based on actual cost, schedule and technical progress of work [1, 9].

plans based on actual cost, schedule and technical progress of work [1, 9]. An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan

More information

Stochastic Framework for Cash Flow Forecasting Considering Owner's Delay in Payment by Use of Monte Carlo Simulation

Stochastic Framework for Cash Flow Forecasting Considering Owner's Delay in Payment by Use of Monte Carlo Simulation Stochastic Framework for Cash Flow Forecasting Considering Owner's Delay in Payment by Use of Monte Carlo Simulation Abdollah Hoseini, Prof. and Reza Andalib, Ph.D. Cand. and Behrouz Gatmiri, Prof. University

More information

Scheduling Process Maturity Level Self Assessment Questionnaire

Scheduling Process Maturity Level Self Assessment Questionnaire Scheduling Process Maturity Level Self Assessment Questionnaire Process improvement usually begins with an analysis of the current state. The purpose of this document is to provide a means to undertake

More information

Section A. Index. Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting techniques... 1. Page 1 of 11. EduPristine CMA - Part I

Section A. Index. Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting techniques... 1. Page 1 of 11. EduPristine CMA - Part I Index Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting techniques... 1 EduPristine CMA - Part I Page 1 of 11 Section A. Planning, Budgeting and Forecasting Section A.2 Forecasting

More information

(Refer Slide Time: 01:52)

(Refer Slide Time: 01:52) Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This

More information

Duration: 1 Semester of which L/S/LW: 2/0/2 Language: English

Duration: 1 Semester of which L/S/LW: 2/0/2 Language: English Module description: Risk Management Degree programme: European Management Responsible for the module: No.: MA- 04-03- 03-1 Degree: Master of Arts Prof. Dr. Tilo Wendler Semester: 3 Hours per week per semester:

More information

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

THE PROJECT MANAGEMENT KNOWLEDGE AREAS THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Forecasting expected losses is a critical function of any. Estimating Environmental. liabilities. One Price Does Not Fit All. by Edward Sullivan

Forecasting expected losses is a critical function of any. Estimating Environmental. liabilities. One Price Does Not Fit All. by Edward Sullivan Estimating Environmental Liabilities One Price Does Not Fit All by Edward Sullivan Forecasting expected losses is a critical function of any position in which risk management professionals may be called

More information

Risk Workshop Overview. MOX Safety Fuels the Future

Risk Workshop Overview. MOX Safety Fuels the Future Risk Workshop Overview RISK MANAGEMENT PROGRAM SUMMARY CONTENTS: Control Account Element Definition ESUA Form Basis of Estimate Uncertainty Calculation Management Reserve 1. Overview 2. ESUA Qualification

More information

Validation of low-default portfolios in the Basel II Framework

Validation of low-default portfolios in the Basel II Framework Basel Committee Newsletter No. 6 (September 2005) Validation of low-default portfolios in the Basel II Framework The purpose of this Newsletter is to set forth the views of the Basel Committee Accord Implementation

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane samlane@aol.com Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,

More information

Contents. List of Figures. List of Tables. List of Examples. Preface to Volume IV

Contents. List of Figures. List of Tables. List of Examples. Preface to Volume IV Contents List of Figures List of Tables List of Examples Foreword Preface to Volume IV xiii xvi xxi xxv xxix IV.1 Value at Risk and Other Risk Metrics 1 IV.1.1 Introduction 1 IV.1.2 An Overview of Market

More information

Fatemeh Akbari* Master of Industrial Engineering Islamic Azad University, Zahedan Brench, Iran

Fatemeh Akbari* Master of Industrial Engineering Islamic Azad University, Zahedan Brench, Iran To Design and to Present a Tool to Prevent Extra Expense Incurring in School Reconstruction Projects (A case study: Reconstruction Department affiliated to School Equipment and Development Unit in Sistan

More information

Performance (conformance to specifications) Cost Time

Performance (conformance to specifications) Cost Time TED UNIVERSITY SDT Space & Defense Technologies Project Management Seminars To discuss project organizations, their advantages and introduce principles, functions and methods of project management Focus:

More information

Matching Investment Strategies in General Insurance Is it Worth It? Aim of Presentation. Background 34TH ANNUAL GIRO CONVENTION

Matching Investment Strategies in General Insurance Is it Worth It? Aim of Presentation. Background 34TH ANNUAL GIRO CONVENTION Matching Investment Strategies in General Insurance Is it Worth It? 34TH ANNUAL GIRO CONVENTION CELTIC MANOR RESORT, NEWPORT, WALES Aim of Presentation To answer a key question: What are the benefit of

More information

SCRAM: A Method for Assessing the Risk of Schedule Compliance

SCRAM: A Method for Assessing the Risk of Schedule Compliance SCRAM: A Method for Assessing the Risk of Schedule Compliance Adrian Pitman Defence Material Organisation Australia Angela Tuffley Red Bay Consulting Pty Ltd Australia Betsy Clark Software Metrics Inc.

More information

Using Primavera Software in Resource Allocation and Project Evaluation of Construction Projects

Using Primavera Software in Resource Allocation and Project Evaluation of Construction Projects Using Primavera Software in Resource Allocation and Project Evaluation of Construction Projects Hamed Ziaidoostan 1, Hamidreza Ghaneh 2, Matin Amanin 3, Mohamadmahi Gholipoor 4 1,2,3,4-M A Student of Business

More information

Energy Portfolio Management Tools and Resources for Regulators

Energy Portfolio Management Tools and Resources for Regulators Energy Portfolio Management Tools and Resources for Regulators NARUC Annual Convention in Miami, Florida November 15, 2006 Bruce Biewald Portfolio Management Tools Report This presentation draws from Energy

More information

A comparative study of bankruptcy prediction models of Fulmer and Toffler in firms accepted in Tehran Stock Exchange

A comparative study of bankruptcy prediction models of Fulmer and Toffler in firms accepted in Tehran Stock Exchange Journal of Novel Applied Sciences Available online at www.jnasci.org 2013 JNAS Journal-2013-2-10/522-527 ISSN 2322-5149 2013 JNAS A comparative study of bankruptcy prediction models of Fulmer and Toffler

More information

Asset Liability Management

Asset Liability Management e-learning and reference solutions for the global finance professional Asset Liability Management A comprehensive e-learning product covering Global Best Practices, Strategic, Operational and Analytical

More information

J. Appl. Environ. Biol. Sci., 4(3)253-260, 2014. 2014, TextRoad Publication

J. Appl. Environ. Biol. Sci., 4(3)253-260, 2014. 2014, TextRoad Publication J. Appl. Environ. Biol. Sci., 4(3)253-260, 2014 2014, TextRoad Publication ISSN: 2090-4274 Journal of Applied Environmental and Biological Sciences www.textroad.com Investigation of the Influence of Human

More information

Asset Liability Management for Insurance Companies

Asset Liability Management for Insurance Companies e-learning and reference solutions for the global finance professional Asset Liability Management A comprehensive e-learning product covering Global Best Practices, Strategic, Operational and Analytical

More information

What Merchants Need to Know About EMV

What Merchants Need to Know About EMV Effective November 1, 2014 1. What is EMV? EMV is the global standard for card present payment processing technology and it s coming to the U.S. EMV uses an embedded chip in the card that holds all the

More information

Measuring Exchange Rate Fluctuations Risk Using the Value-at-Risk

Measuring Exchange Rate Fluctuations Risk Using the Value-at-Risk Journal of Applied Finance & Banking, vol.2, no.3, 2012, 65-79 ISSN: 1792-6580 (print version), 1792-6599 (online) International Scientific Press, 2012 Measuring Exchange Rate Fluctuations Risk Using the

More information

Life Cycle Cost Analysis (LCCA)

Life Cycle Cost Analysis (LCCA) v01-19-11 Life Cycle Cost Analysis (LCCA) Introduction The SHRP2 R-23 Guidelines provide a number of possible alternative designs using either rigid of flexible pavements. There is usually not a single

More information

Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman

Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government

More information

CUSTOMER RELATIONSHIP MANAGEMENT (CRM) AND ITS IMPACT ON PERFORMANCE IMPROVEMENT OF COMPANIES IN IRAN TELECOMMUNICATIONS

CUSTOMER RELATIONSHIP MANAGEMENT (CRM) AND ITS IMPACT ON PERFORMANCE IMPROVEMENT OF COMPANIES IN IRAN TELECOMMUNICATIONS CUSTOMER RELATIONSHIP MANAGEMENT (CRM) AND ITS IMPACT ON PERFORMANCE IMPROVEMENT OF COMPANIES IN IRAN TELECOMMUNICATIONS Siamak Alipour 1, Shahram Golrang Arabani 2, Mohammad Talebi Asadi 3, Reza Zareii

More information

SENSITIVITY ANALYSIS AND INFERENCE. Lecture 12

SENSITIVITY ANALYSIS AND INFERENCE. Lecture 12 This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike License. Your use of this material constitutes acceptance of that license and the conditions of use of materials on this

More information

Simulation and Lean Six Sigma

Simulation and Lean Six Sigma Hilary Emmett, 22 August 2007 Improve the quality of your critical business decisions Agenda Simulation and Lean Six Sigma What is Monte Carlo Simulation? Loan Process Example Inventory Optimization Example

More information

Project Governance a board responsibility. Corporate Governance Network

Project Governance a board responsibility. Corporate Governance Network Project Governance a board responsibility Corporate Governance Network November 2015 1 Contents Page Introduction 3 Board responsibilities 3 What is project governance? 4 The boards duties in respect of

More information

THE EFFECT OF COMPONENTS OF A 4 PARTS MODEL OF CASH FLOW STATEMENT ON OPERATIONAL PERFORMANCE IN FIRMS ENLISTED IN TEHRAN STOCK EXCHANGE

THE EFFECT OF COMPONENTS OF A 4 PARTS MODEL OF CASH FLOW STATEMENT ON OPERATIONAL PERFORMANCE IN FIRMS ENLISTED IN TEHRAN STOCK EXCHANGE ISSN: 0976-2876 (Print) ISSN: 2250-0138(Online) THE EFFECT OF COMPONENTS OF A 4 PARTS MODEL OF CASH FLOW STATEMENT ON OPERATIONAL PERFORMANCE IN FIRMS ENLISTED IN TEHRAN STOCK EXCHANGE YADOLLAH TARIVERDI

More information

Assessing Project Time Management of the Contractors with Using ANP

Assessing Project Time Management of the Contractors with Using ANP 2011 2nd International Conference on Education and Management Technology IPEDR vol.13 (2011) (2011) IACSIT Press, Singapore Assessing Project Time Management of the Contractors with Using ANP Jalil Ebrahimpour

More information

What Went Wrong Right? Recognizing Risk Impacts on Cost and Schedule. Scope Development

What Went Wrong Right? Recognizing Risk Impacts on Cost and Schedule. Scope Development What Went Wrong Right? Recognizing Risk Impacts on Cost and Schedule Scope Development 1 2 Course Outline Session 1: Session 2: Session 3: Session 4: Overview of the Risk Management Process Determining

More information

Predictive Modeling. Age. Sex. Y.o.B. Expected mortality. Model. Married Amount. etc. SOA/CAS Spring Meeting

Predictive Modeling. Age. Sex. Y.o.B. Expected mortality. Model. Married Amount. etc. SOA/CAS Spring Meeting watsonwyatt.com SOA/CAS Spring Meeting Application of Predictive Modeling in Life Insurance Jean-Felix Huet, ASA June 18, 28 Predictive Modeling Statistical model that relates an event (death) with a number

More information

Tutorial Paper on Quantitative Risk Assessment. Mohammad Reza Sohizadeh Abyaneh Seyed Mehdi Mohammed Hassanzadeh Håvard Raddum

Tutorial Paper on Quantitative Risk Assessment. Mohammad Reza Sohizadeh Abyaneh Seyed Mehdi Mohammed Hassanzadeh Håvard Raddum Tutorial Paper on Quantitative Risk Assessment Mohammad Reza Sohizadeh Abyaneh Seyed Mehdi Mohammed Hassanzadeh Håvard Raddum Abstract This paper shows how to carry out a quantitative risk assessment,

More information

Chapter 6. (PMBOK Guide)

Chapter 6. (PMBOK Guide) Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information