A Review on Critical Risk Factors in the Life Cycle of Construction Projects
|
|
|
- George Warren
- 10 years ago
- Views:
Transcription
1 Journal of Civil Engineering Research 2014, 4(2A): DOI: /c.jce A Review on Critical Risk Factors in the Life Cycle of Construction Projects S. M. Renuka 1,*, C. Umarani 2, S. Kamal 3 1 Research Scholar, Department of Civil Engineering, CEG, Anna University, Chennai-25, India 2 Associate Professor, Department of Civil Engineering, CEG, Anna University, Chennai-25, India 3 Assistant Professor, Department of Civil Engineering, Annamalai University, Chidambaram, India Abstract In any country, infrastructure development will increase the growth of countries economy and generates the large amount of job opportunities. Hence those projects involve a large amount of investment to carry out. In view of that, if any sort of wastage (either time, resources etc) occurs that would lead to the huge monetary losses. These losses occur due to various risks associated with such mega projects. Consequently, these risks play a crucial role for the completion of project within the time schedule and planned budget. In this connection, this study mainly discusses the critical risk factors and its assessment techniques through comparative study of various international construction projects. About 50 relevant articles published over the last 25 years have been reviewed. The review resulted that a simple analytical tool will be developed for each project task to assess the risk easily and quickly, which will encourage the practitioners to do the risk analysis in their project. This review concluded that the earlier risk identification in the project and assessment during the bidding stage of the construction project will lead to the better estimation of the escalation on cost and time overrun. Such risk assessments help to include in the budget and scheduling for the successful completion of the project. Keywords Risk Factors, Risk Assessment Techniques, Construction Projects 1. Introduction 1.1. Risks in Construction Project The construction industry is often considered as a risky business due to its complexity and strategic nature. It incurs a numerous project stakeholders, internal and external factors which will lead to enormous risks. Unfortunately, the construction industry has a poor reputation in risk analysis when compared to other industries (Laryea, 2008). However, No construction project is risk free. Risk can be managed, minimized, shared, transferred, or accepted. It cannot be ignored (Latham 1994). Risk is a multi-facet concept according to (PMI, 2008) Project risk management is the processes concerned with identifying, analyzing, and responding to project risk. In the context of construction industry, it is the likelihood of the occurrence of a definite event or combination of events which occur during the whole process of construction. Construction involves many variables, and it is often difficult to determine cause and effect, dependence and correlations. Hence, those risks play a significant role in decision making and may affect the performance of a * Corresponding author: [email protected] (S. M. Renuka) Published online at Copyright 2014 Scientific & Academic Publishing. All Rights Reserved project (wiguna and scott, 2005). Risk is exposure to the consequences of uncertainty. As a result, subjective analytical methods that rely on historical information and the experiences of individuals and companies have been used to assess the impact of construction risk and uncertainty. Therefore, Risk assessment is a technique that aims to identify and estimate risks impacted upon by a project. Figure 1. Life Cycle of the Construction Project A construction project is plagued with various risks in all the stages of the life cycle of the project are shown in fig 1 (Zhao et al., 2010). Therefore Risk Management should be emphasized in construction project, regardless of the project size to assure the achievement of project objectives (Hwang et al., 2013). Risks have been represented as uncertain future
2 32 S. M. Renuka et al.: A Review on Critical Risk Factors in the Life Cycle of Construction Projects event by construction managers and researchers and so they tried to control systematically through risk management and analysis method since early stage of 1990 s. The purpose of this paper is to review and bring together these previous discussions about risk factors and to provide a comprehensive list of major sources of risk factors in the life cycle of construction projects based on extensive literature study. 2. History of Risks Management in Construction Projects 2.1. The 1990 s Origin of Risk Analysis in Construction Industry During 1990s risk factor identification and assessment technique became a hot research topic. Many contractors developed a series of thumb rules to analyze and assess risks. As a result many construction projects failed to achieve their time, cost and quality goals. (Al- Bahar, 1988) The project risks and uncertainties in cost and time can be managed by a systematic approach during estimation stage in order to minimize their effects. This approach involves identifying risk sources, assessing their effects on a project and selecting ways to control them. (Birnie and Yates, 1991). Accordingly, the sources of risk were categorized based on controllable and uncontrollable factors which will lead to cost and time overrun in a project (Akincl, 1998). Based on this result, different risk assessment models have been formulated to analyze and assess project risks during the bidding stage of a construction project (Mustafa and Bahar, 1991). Similarly few attempts were made by the researches like (Tah et al., 1993), (Wirba et al., 1996), (Dawood, 1998) in risk assessment by Probability- Impact assessment (P-I), Fuzzy Set Theory (FST) and Monte Carlo Simulation (MCS) The New Millennium- Arrival of New Systematic Approaches Till 2000, only few attempts have made on the identification and assessment of risk factors of the construction projects. As a result there was a lack of systematic approaches to identify and manage the risks in construction projects. (Chapman, 2001) grouped risks into four subsets: environment, industry, client and project. (Shen, 2001) categorized them into six groups with the nature of the risks i.e financial, legal, management, market, policy, and political. (Chen et al., 2004) proposed 15 risks affecting project cost and they were grouped under three heads: resource factors, management factors and parent factors. (Dikmen et al., 2007) used influence diagrams to define the factors which have influence on project cost. (Zeng et al., 2007) classified risk factors as human, site, material and equipment factors. In the post 2000 s many researchers made an attempt to propose the limitations and complexity of risk assessment tools such as Analytical hierarchy process (AHP), P-I, FST, MCS and decision support system The Post 2010 s Development of More Sophisticated Techniques There is a sharp increase in the number of risk identification and assessment papers published after More sophisticated models have been developed by various researchers for integrating the risk assessment in comprehensive decision making frame work. Rezakhani (2012) classified the risk factors under three heads: External, Legal and internal. External risk was sub divided into two subsets: unpredictable/ uncontrollable, predictable/ uncontrollable and Internal risk was sub divided into two subsets: Non- technical / controllable, Technical / controllable. Further he suggested a hierarchy based risk break down structure and identified the key risk factors. Goh et al (2013) identified 19 risk factors in the life cycle of the project under four heads such as Planning stage, Design stage, Procurement stage, construction stage, Handling over stage. They discussed the use of work shop with an integrated approach which includes brain storming, checklist, probability impact matrices, subjective judgment, and risk register. Finally they suggested that the risk management workshop will be useful for risk identification and analysis, as a means of managing risks. Many researchers have tried various approaches for representing the interdependencies between project risks and its complexity of the surrounding environment (Lazzerini and mkrtchyan, 2011). (Hwang et al., 2013) reported that risk management implementation is relatively low in small construction projects and this is due to lack of time and budget, low profit margin and not economical. The results indicated a positive correlation between RM implementation and improvement in project quality, cost and schedule performance of small projects. 3. Analysis and Discussion on Identification and Assessment of Critical Risk Factors 3.1. Different Types of Risk in Construction Projects Risks in construction have been classified in different ways. Tah et al. (1993) categorized project risks into external and internal risks and developed a fuzzy model for contractor s risk assessment at the tender stage. External risks are those that are prevalent in the external environment of projects, such as those due to inflation, currency exchange rate fluctuations, technology change, major client induced changes, politics, Climate, Weather Condition and major accidents or natural disasters. They are relatively non-controllable and so there is the need to continually scan and forecast these risks and in the context of a company s strategy. Similarly, internal risks are relatively more controllable and vary between projects. These internal risks cover uncertainties due to labour, plant, material and subcontractor, resources and the site conditions. Consequently many researchers identified several risk factors and they are classified into different types depends on
3 Journal of Civil Engineering Research 2014, 4(2A): the nature of risk such as Physical, Environmental, design, Financial, Contractual / legal, Construction, Political, Management, Natural hazards, Safety and Delay risk (Mustafa, 1991; Akincl et al., 1998; Prasanta kumar dey, 2002; Ghosh et al., 2004; Wiguna and scott, 2005; Enshasi and mosa, 2008; wang et al., 2010; Razakhani, 2012; Goh et al., 2013) Identification of Critical Risk Factors The critical risk factors identified by many researches done in different type projects like residential, industrial, commercial, infrastructure etc in various foreign countries are shown in table 1. From the table it is understood that, factors like, Country risk (Inflation, country economic Table 1. Critical Risk Factors condition), Environmental and geological risk (Weather and climatic conditions), Statutory Compliance Risk (Statutory clearance before planning a project), design risk (scope and design changes), Project Execution risk (new technology implementation, Poor Safety procedures, Construction Delays, Inadequate managerial skills, improper coordination between teams), Resource Risk(Lack of availability of resources) are the critical risk factors in various international projects. From this table it is concluded that, there is an urge for a knowledge map which depicts the sources of critical risk factors and its impact on the successful completion of the construction Project. According knowledge map has been developed and it is discussed below. Critical Risk Factors Scope and design changes, Technology Implementation Site conditions and Unknown Geological Condition Inflation, Country Economic Condition and rules and regulation. unavailability of funds, Financial failure Inadequate managerial skills, improper coordination between teams Lack of availability of resources Weather and climatic Conditions Statutory clearance and approvals Poor Safety procedures Construction Delays Mustafa et al (1991) Prasanta kumar dey, 2002 Ghosh et al (2004) Laryea, 2007 Enhassi and mosa, 2008 Sun & meng, 2009 Wang et al, 2010 Eybpoosh, 2011 Rezakhani, 2012 Goh et al 2013
4 34 S. M. Renuka et al.: A Review on Critical Risk Factors in the Life Cycle of Construction Projects 3.3. Knowledge Map From the review of literature, the major risk sources and their impact are identified. The knowledge map representing the risk sources affecting the project success is shown in figure 2. This flow chart consists of various risk factors, in which Engineering risks are predictable and those non engineering risks are non predictable. The predictable factors should be forecasted during the earlier stage of the project whereas the non predictable factors involve uncertainties; this should also be estimated for the successful completion of the project because these risks will affect the cost, time, quality of the project. Figure 2. Knowledge Map Representing the Risk Sources affecting the Project Success From the review of literature, the major risk sources and their impact are identified. The knowledge map representing the risk sources affecting the project success is shown in figure 2. This flow chart consists of various risk factors, in which Engineering risks are predictable and those non engineering risks are non predictable. The predictable factors should be forecasted during the earlier stage of the project whereas the non predictable factors involve uncertainties; this should also be estimated for the successful completion of the project because these risks will affect the cost, time, quality of the project Risk Assessment Techniques Recently, a number of systematic models have been proposed for use in the risk evaluation phase of the risk management process. Dey (2002) proposed a quantitative approach through an analytical hierarchy process and decision tree analysis. He argued that the probability models like MCS, FST, P-I required detailed quantitative information which is not normally available at the time of planning and its applicability in real project is also very limited. Thomas et al. (2006) used fault tree to model and assess risk probability and impact. They attempted to improve risk assessments by assessing risk levels of specific risk scenarios. Abdelgawad et al. (2010) explored the RM process using combined fuzzy Failure mode and effect analysis (FMEA) and Fuzzy AHP. These analyses map a relationship between impact and probability of occurrence and detection /control and the level of criticality of risk events to support PM team to establish corrective actions in a timely manner. Eybpoosh et al. (2011) demonstrated the causal relationship between the risk factor using SEM technique. They concluded that the SEM helps decision makers for risk identification and to develop alternative mitigation strategies at the earlier stage of the project. Tamosaitiene et al. (2013) developed a model using TOPIS-F method with fuzzy criteria values to assess risk in construction projects. Using this model risk assessment for three projects was compared with initial fuzzy decision making matrix and solution results were discussed. Laryea and hughes (2010) concluded that the assumptions underpinning analytical models of risk management may not be suitable in practice and why what actually happens in practice is important for those who seek to model the pricing of construction bids. The risk assessment techniques followed by various researches in various literatures is shown in fig 3. The various risk assessment techniques are Project Evaluation and review technique (PERT), Probability and Impact (P&I), Montecarlo simulation (MCS), Analytical Hierarchy process (AHP), Likelihood occurrence of risk (LR), and Fuzzy Logic. Few researches have made an attempt using Analytical neural network (ANN), Bayesian belief Network (BBN). This figure shows that most of the researches have done the risk assessment model in AHP, MCS and LR compared to other techniques. The proposed models carried out using these three techniques have showed good results in assessing the project risk in construction projects. Among different approach models AHP model is more effective, because of its systematic approach to structuring risk assessment problems by providing hierarchical approach. While assessing the project risk at the initial stage of the project, practitioners may not have sufficient data at that time. So it is essential to develop a simple regression model for each project specific task. Moreover, simplicity is a key factor for encouraging professionals to use risk assessment tools in practice.
5 Journal of Civil Engineering Research 2014, 4(2A): Figure 3. Risk assessment techniques adopted by various researches 4. Summary and Conclusions This paper discussed a review of literatures over past 3 decades on identification and assessment of risk factors in construction project. Almost 1000 international projects from various countries like UK, US, Australia, China, Hong kong, korea, Turkey, Mexico, Malaysia, Thailand etc were considered in this study. It mainly focused on the development of models for assessing the risk factors in construction projects. It also discusses the critical risk factors & its contribution in risk assessment techniques. The findings from the review are presented as table & charts. The table 1 discusses about the critical risk factors identified by researches in various construction projects. Then a knowledge map is developed and it is shown in fig 1. It represents the risk sources in construction project which affect the project success. An extensive literature survey revealed that researchers have shown a remarkable contribution towards risk identification and assessment. It is unfortunate that, there is still a wide gap between theory and practice and so many researchers have been done mostly on developed countries. In India, only few research works have been done in this area. This paper recommends that the risks factors affecting the life cycle of the construction projects needs to be identified. Then a frame work is to be design for quantifying the risk factors considering the uncertainties. It is necessary to develop a simple statistical model for risk assessment in construction projects considering small and medium sized projects also. Finally suitable recommendations are to be suggested, to mitigate the risks during the life cycle of the project to make the project success. ACKNOWLEDGEMENTS This paper presents the preliminary findings of a research project entitled Identification and assessment of risks in construction projects, sponsored by Anna Centenary Research Fellowship, Anna university, Chennai, India. REFERENCES [1] J.F. Al-Bahar, Risk management in construction Projects: A systematic analytical approach for contractors, Ph.D. Dissertation, Department of Civil Engineering, University of California, Berkeley, [2] Bon-Gang Hwang, Xianbo Zhao, Li Ping Toh, Risk management in small construction projects in Singapore: Status, barriers and impact, Elsevier International Journal of Project Management, Vol. 32, pp , [3] Burcu Akincl and Martin Fischer, Factors affecting contractors risk of cost overburden, ASCE Journal of Management in Engineering, Vol.14, No. 1, pp , [4] Birnie. J. and Yates. A., Cost predictions using decision/ risk analysis methodologies, Construction Management and Economics, Vol. 9, pp , [5] Chapman R.J., The Controlling Influences on Effective Risk Identification and Assessment for Construction Design Management, Internat. J. of Project Manag., Vol. 19, pp , [6] Chen H., Hao G., Poon S.W., Ng F.F., Cost Risk Management in West Rail Project of Hong Kong, AACE Internat. Trans., [7] Cheng Siew Goh, Hamzah Abdul- Rahman and Zulkiflee Abdul Samad, Applying Risk Management workshop for a public construction project: Case Study, ASCE Journal of Construction Engineering and Management, Vol. 139, No. 5, pp , [8] Dikmen I., Birgonul M., Han S., Using Fuzzy Risk Assessment to Rate Cost Overrun Risk in International Construction Projects, Internat. J. of Project Manag., Vol. 25, pp , [9] Dawood, N., Estimating project and activity duration: a risk management approach using network analysis, Construction Management and Economics, Vol.16, pp , 1998.
6 36 S. M. Renuka et al.: A Review on Critical Risk Factors in the Life Cycle of Construction Projects [10] Jolanta Tamosaitiene, Edmundas Kazimieras Zavadskas, Zenonas Turkis, Multi criteria risk assessment of a construction project, Elsevier Procedia computer science, Vol. 17, pp , [11] Laryea, S., Hughes, W., How contractors price risk in bids: theory and practice, Construction Management and Economics, Vol. 26, pp , [12] Latham, M., Constructing the team. HMSO London. [13] Lazzerini, B., Mkrtchyan, L., Analyzing risk impact factors using extended fuzzy cognitive maps, IEEE Systems Journal, Vol. 5, pp , [14] Laryea. S. and Hughes. W., Risk and price in the bidding process of contractors, ASCE Journal of construction management and Engineering, Vol. 137, No. 4, pp , [15] Mohamed Abdelgawad and Aminah Robinson Fayek, Risk Mangement in the construction Industry Using Combined Fuzzy FMEA and Fuzzy AHP, Journal of Construction Engineering and Management, Vol.136, pp , [16] Mustafa, M.A., Al-Bahar, J.F., Project risk assessment using the analytic hierarchy process, IEEE Transactions on Engineering Management, Vol. 38, pp ,1991. [17] Matineh Eybpoosh, Irem Dikmen, and M. Talat Birgonul, Identification of Risk Paths in International Construction Projects using Structural Equation Modeling, ASCE Journal of Construction Engineering and Management, Vol. 137, No. 12, pp , December [18] Mustafa, M.A. and J.F. Al-Bahar, Project Risk Assessment Using the Analytical Hierarchy Process, IEEE Trans. Eng. Manag. Vol. 3, No. 1, pp , [19] Dr. Prasanta Kumar Dey, Project Risk Management: A combined analytical hierarchy process and decision tree approach, Cost Engineering, Vol. 44, No. 3, pp , [20] I Putu Artama Wiguna and Stephen Scott, Nature of the critical risk factors affecting project performance in Indonesian Building Contracts, 21 st Annual ARCOM Conference, SOAS, University of London, Association of Researchers in Construction Management, Vol. 1, pp , [21] Pejman Rezakhani, Classifying key risk factors in construction Projects, BULETINUL INSTITUTULUI POLITRHNIC DIN IASI Construction and Architectural, Vol. LVIII(LXII), Fasc. 2, [22] Sun. M. and Meng. X., Taxonomy for change causes and effects in construction projects, International Journal of Project Management, Vol. 27, No. 6, pp , [23] Shou Qing Wang, Mohammed Fadhil Dulaimi, and Muhammad Yousuf Aguria, Risk management framework for construction projects in developing countries, Construction Management and Economics, Vol. 22, No. 3, pp , [24] Sid Ghosh, Jakkapan Jintanapakanont, Identifying and assessing the critical risk factors in an underground rail project in Thailand: a factor analysis approach, Elsevier International Journal of Project Management, Vol. 22, pp , [25] Shen L.Y., Wu G.W.C., Ng C.S.K., Risk Assessment for Construction Joint Ventures in China. J. of Constr. Engg. and Manag., Vol. 127, No.1, pp.76-81, [26] Tah, J.H.M., Thorpe, A. and McCaffer, R., Contractor project risks contingency allocation using linguistic approximation, Journal of Computing Systems in Engineering, Vol. 4, No. 2-3, pp , [27] Taroun, Towards a better modeling and assessment of construction risk Insights from a literature Review, Elsevier International journal of project management, [28] Wirba, E., Tah, J., Howes, R., Risk interdependencies and natural language computations. Engineering Construction and Architectural Management, Vol. 3, pp , [29] Zhao. Z.Y., Lv. Q.L., Zuo.J., Zillante. G., Prediction system for Change management in construction project, ASCE Journal of Construction Engineering and Management, Journal of construction Engineering management, Vol. 136, No.6, pp , [30] Zeng J., An M., Smith N.J., Application of a Fuzzy Based Decision Making Methodology to Construction Project Risk Assessment, Internat. J. of Project Manag., Vol. 25, pp , 2007.
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_risk_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern
A Risk Management System Framework for New Product Development (NPD)
2011 International Conference on Economics and Finance Research IPEDR vol.4 (2011) (2011) IACSIT Press, Singapore A Risk Management System Framework for New Product Development (NPD) Seonmuk Park, Jongseong
CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT
CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT Chaitali S. Pawar 1, Suman S. Jain 2, Abhijeet M. Gaikwad 3 1 Post Graduate Student, RMDSSOE, Pune, India. Email: [email protected] 2 Asso.
Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge
1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project
Risk assessment of river-type hydropower plants by using fuzzy logic approach
Risk assessment of river-type hydropower plants by using fuzzy logic approach S.Kucukali 1,* 1 Cankaya University, Department of Civil Engineering, Balgat, 06530 Ankara, Turkey * Corresponding author.
The Cost of Risks. Essence of Risk Quantification. PALISADE @RISK Forum Calgary 2008
PALISADE @RISK Forum Calgary 2008 The Cost of Risks Essence of Risk Quantification Disclaimer: This presentation material is provided for general information. The author shall not be held accountable for
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN April 2009 SLAC I 050 07010 002 Risk Management Plan Contents 1.0 INTRODUCTION... 1 1.1 Scope... 1 2.0 MANAGEMENT
Delay Computation Using Fuzzy Logic Approach
I.J. Intelligent Systems and Applications, 2012, 11, 84-90 Published Online October 2012 in MECS (http://www.mecs-press.org/) DOI: 10.5815/ijisa.2012.11.10 Delay Computation Using Fuzzy Logic Approach
Project risk management using multiple criteria decision-making technique and decision tree analysis: a case study of Indian oil refinery
Project risk management using multiple criteria decision-making technique and decision tree analysis: a case study of Indian oil refinery Prasanta Kumar Dey 1. Introduction The success parameters for any
Using Risk Assessment to Improve Highway Construction Project Performance
Using Risk Assessment to Improve Highway Construction Project Performance Mohamed F. Diab, MBA, Ph.D. and Amiy Varma, Ph.D., PE North Dakota State University Fargo, ND Khaled Nassar, Ph.D. American University
Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry
CIB World Building Congress 2007 549 CIB2007-370 Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry Dr Tabarak Ballal 1, Dr Taha Elhag 2 and Mr Salim Ambusaidy 3 1
PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview
PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview Sante Torino PMI-RMP, IPMA Level B Head of Risk Management Major Programmes, Selex ES / Land&Naval Systems Division
Project Risk Management. Presented by Stephen Smith
Project Risk Management Presented by Stephen Smith Introduction Risk Management Insurance Business Financial Project Risk Management Project A temporary endeavour undertaken to create a unique product
Risk Management of Construction - A Graduate Course
(pressing HOME will start a new search) ASC Proceedings of the 37th Annual Conference University of Denver - Denver, Colorado April 4-7, 2001 pp 95-100 Risk Management of Construction - A Graduate Course
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING
CHAPTER 9 PROJECT FINANCE AND CONTRACT PRICING In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will
Comparative Analysis of FAHP and FTOPSIS Method for Evaluation of Different Domains
International Journal of Research Studies in Computer Science and Engineering (IJRSCSE) August 2015, PP 58-62 ISSN 2349-4840 (Print) & ISSN 2349-4859 (Online) www.arcjournals.org Comparative Analysis of
CRASHING-RISK-MODELING SOFTWARE (CRMS)
International Journal of Science, Environment and Technology, Vol. 4, No 2, 2015, 501 508 ISSN 2278-3687 (O) 2277-663X (P) CRASHING-RISK-MODELING SOFTWARE (CRMS) Nabil Semaan 1, Najib Georges 2 and Joe
PROJECT RISK MANAGEMENT
11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
CONTRACTOR SELECTION WITH RISK ASSESSMENT BY
CONTRACTOR SELECTION WITH RISK ASSESSMENT BY USING AHP FUZZY METHOD Seyed Ali Tabatabaei Khodadadi 1, B. Dean Kumar 2 ¹Department of Civil Engineering, JNTUH CEH, Hyderabad -500085, India ²Associate Professor
Project Risk Management
Project Risk Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Risk Management
A Fuzzy AHP based Multi-criteria Decision-making Model to Select a Cloud Service
Vol.8, No.3 (2014), pp.175-180 http://dx.doi.org/10.14257/ijsh.2014.8.3.16 A Fuzzy AHP based Multi-criteria Decision-making Model to Select a Cloud Service Hong-Kyu Kwon 1 and Kwang-Kyu Seo 2* 1 Department
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Planning, Scheduling and Resource Optimization for A Villa by using Ms-Project 2010 Mr.
Improving the Predictability of the CapEx Portfolio
Improving the Predictability of the CapEx Portfolio Spring 2009 Westney Consulting Group, Inc. www.westney.com If the whipsaw of product price and project cost over the past 12 months has taught anything,
Sensitivity Analysis of Safety Measures for Railway Tunnel Fire Accident
Sensitivity Analysis of Safety Measures for Railway Tunnel Fire Accident Sanglog Kwak, Jongbae Wang, Yunok Cho Korea Railroad Research Institute, Uiwnag City, Kyonggi-do, Korea Abstract: After the subway
A Comprehensive Study on Cloud Computing Standardization
A Comprehensive Study on Cloud Computing Standardization Dr. Mukesh Chandra Negi Project Manager, Tech Mahindra Ltd, Noida, India ABSTRACT: Standard is a trust between standardization body, buyers and
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK Mihirkumar B. Naik 1, Dr. Neerajkumar D. Sharma 2, Prof. Bhavin K. Kashiyani 3 PG. Student, S.N. Patel Institute of Technology
DETERMINANTS OF PROJECT MANAGEMENT SUCCESS
DETERMINANTS OF PROJECT MANAGEMENT SUCCESS Gary Walker, Dr Shamil Naoum and Professor Rod Howes South Bank University, School of Construction, London. SW8 2JZ One of the features of the construction industry
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Establishment and application of performance assessment model of waste management in architectural engineering projects in China
Available online at www.sciencedirect.com Systems Engineering Procedia 1 (2011) 147 155 Conference Title Establishment and application of performance assessment model of waste management in architectural
Use a Risk Breakdown Structure (RBS) to Understand Your Risks
Use a Risk Breakdown Structure (RBS) to Understand Your Risks David Hillson, PhD, PMP, FAPM, MIRM, MCMI, Director of Consultancy, Management Professional Solutions Limited Introducing the Risk Breakdown
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
Project Risk Management: Methodology Development for Engineering, Procurement and Construction Projects a Case Study in the Oil and Gas Industry
American Journal of Civil Engineering 2015; 3(3): 75-79 Published online April 13, 2015 (http://www.sciencepublishinggroup.com/j/ajce) doi: 10.11648/j.ajce.20150303.14 ISSN: 2330-8729 (Print); ISSN: 2330-8737
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
Introduction. Project Management in New Zealand
AN ANALYSIS OF THE USE OF INFORMATION TECHNOLOGY FOR PROJECT MANAGEMENT IN THE NEW ZEALAND CONSTRUCTION INDUSTRY Dr Suzanne Wilkinson, Senior Lecturer, Department of Civil and Resource Engineering The
An Evaluation Model for Determining Insurance Policy Using AHP and Fuzzy Logic: Case Studies of Life and Annuity Insurances
Proceedings of the 8th WSEAS International Conference on Fuzzy Systems, Vancouver, British Columbia, Canada, June 19-21, 2007 126 An Evaluation Model for Determining Insurance Policy Using AHP and Fuzzy
Project Management. [Student s Name] [Name of Institution]
1 Paper: Assignment Style: Harvard Pages: 10 Sources: 7 Level: Master Project Management [Student s Name] [Name of Institution] 2 Project Management Introduction The project management also known as management
Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study
International Journal of Project Management 21 (2003) 321 326 www.elsevier.com/locate/ijproman Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana
ERM Learning Objectives
ERM Learning Objectives INTRODUCTION These Learning Objectives are expressed in terms of the knowledge required of an expert * in enterprise risk management (ERM). The Learning Objectives are organized
Risk Workshop Overview. MOX Safety Fuels the Future
Risk Workshop Overview RISK MANAGEMENT PROGRAM SUMMARY CONTENTS: Control Account Element Definition ESUA Form Basis of Estimate Uncertainty Calculation Management Reserve 1. Overview 2. ESUA Qualification
A Study on Risk Assessment for Small and Medium Software Development Projects
A Study on Risk Assessment for Small and Medium Software Development Projects Abdullahi Mohamud Sharif and Shuib Basri Universiti Teknologi PETRONAS, Bandar Seri Iskandar, 31750 Tronoh, Perak, Malaysia.
Available online at www.sciencedirect.com. ScienceDirect. Procedia CIRP 17 (2014 ) 628 634. Madani Alomar*, Zbigniew J. Pasek
Available online at www.sciencedirect.com ScienceDirect Procedia CIRP 17 (2014 ) 628 634 Variety Management in Manufacturing. Proceedings of the 47th CIRP Conference on Manufacturing Systems Linking supply
A Model for Implementing & Continuously Improving the Automated Change Management Process for Construction Mega Projects
A Model for Implementing & Continuously Improving the Automated Change Management Process for Construction Mega Projects *Sh. Karimidorabati, C. T. Haas, University of Waterloo 200 University Avenue West
SIMULATION TOOL FOR MANPOWER FORECAST LOADING AND RESOURCE LEVELING. Mikhail Hanna Janaka Y. Ruwanpura
Proceedings of the 2007 Winter Simulation Conference S. G. Henderson, B. Biller, M.-H. Hsieh, J. Shortle, J. D. Tew, and R. R. Barton, eds. SIMULATION TOOL FOR MANPOWER FORECAST LOADING AND RESOURCE LEVELING
Risk Review Process Basics
2011 PMOC Annual Meeting FEDERAL TRANSIT ADMINISTRATION Risk Review Process Basics Michael P. Wetherell, PE - Urban Engineers David N. Sillars, PE Sillars Consulting FEDERAL TRANSIT ADMINISTRATION 2011
Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2
Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2 P.G. Student, Department of Civil & Environmental Engineering, NITTTR, Bhopal,
An Assessment of Risk Identification in Large Construction Projects in Iran
Journal of Construction in Developing Countries, Supp. 1, 57 69, 2012 An Assessment of Risk Identification in Large Construction Projects in Iran Mehdi Tadayon 1, Mastura Jaafar 1 and Ehsan Nasri 2 Abstract:
THE LEAN-RESOURCES BASED CONSTRUCTION PROJECT PLANNING AND CONTROL SYSTEM
THE LEAN-RESOURCES BASED CONSTRUCTION PROJECT PLANNING AND CONTROL SYSTEM Tzu-An Chiang Department of Business Administration, National Taipei University of Business, Taipei (100), Taiwan [email protected]
PROJECT RISK MANAGEMENT IN THE QUEENSLAND ENGINEERING CONSTRUCTION INDUSTRY: A SURVEY
Lyons, Terry and Skitmore, Martin (2004) Project risk management in the Queensland engineering construction industry: a survey. International Journal of Project Management 22(1):pp. 51-61. Copyright 2004
Guidelines for a risk management methodology for product design
Guidelines for a risk management methodology for product design Viviane Vasconcellos Ferreira Federal University of Santa Catarina [email protected] André Ogliari Federal University of Santa Catarina
Risk Management Software TRM 1.0 for Shield Tunnelling Projects
ISGSR2007 First International Symposium on Geotechnical Safety & Risk Oct. 18~19, 2007 Shanghai Tongji University, China Risk Management Software TRM 1.0 for Shield Tunnelling Projects Q. F. Hu, H. W.
Schedule Risk Analysis Simulator using Beta Distribution
Schedule Risk Analysis Simulator using Beta Distribution Isha Sharma Department of Computer Science and Applications, Kurukshetra University, Kurukshetra, Haryana (INDIA) [email protected] Dr. P.K.
Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson
Page 1 of 13 Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models Martin Hopkinson Abstract Monte Carlo schedule risk analysis has become a widely practiced
Analytic Hierarchy Process for Design Selection of Laminated Bamboo Chair
Analytic Hierarchy Process for Design Selection of Laminated Bamboo Chair V. Laemlaksakul, S. Bangsarantrip Abstract This paper demonstrates the laminated bamboo chair design selection, the applicability
Application of Domino Theory to Justify and Prevent Accident Occurance in Construction Sites
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 6, Issue 2 (Mar. - Apr. 2013), PP 72-76 Application of Domino Theory to Justify and Prevent Accident
EFFECT OF PROJECT COST AND TIME MONITORING ON PROGRESS OF CONSTRUCTION PROJCT
EFFECT OF PROJECT COST AND TIME MONITORING ON PROGRESS OF CONSTRUCTION PROJCT Shreyash Raut 1, S S Pimplikar 2, Karan Sawant 3 1 Research Graduate ME Civil Construction & Management, Civil Engineering,
Risk Management in Infrastructure Projects in India
nternational Journal of nnovative Research in Advanced Engineering (JRAE) SSN: 9-6 ssue, Volume (April 0) Risk Management in nfrastructure rojects in ndia Chaitali S. awar * Suman S. Jain Jalinder R. atil
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS Rosli Abdul Rashid, Ismail Mat Taib, Wan Basiron Wan Ahmad, Md. Asrul Nasid, Wan Nordiana Wan Ali & Zainab Mohd Zainordin Department
A Risk Management Standard
A Risk Management Standard Introduction This Risk Management Standard is the result of work by a team drawn from the major risk management organisations in the UK, including the Institute of Risk management
Towards a New Paradigm for Management of Complex Engineering Projects: A System-of-Systems Framework
2015 System of Systems Engineering Collaborators Information Exchange (SoSECIE) Towards a New Paradigm for Management of Complex Engineering Projects: A System-of-Systems Framework Jin Zhu PhD Candidate
APPLICATION OF ICT BENEFITS FOR BUILDING PROJECT MANAGEMENT USING ISM MODEL
APPLICATION OF ICT BENEFITS FOR BUILDING PROJECT MANAGEMENT USING ISM MODEL S.V.S.N.D.L.Prasanna 1, T. Raja Ramanna 2 1 Assistant Professor, Civil Engineering Department, University College of Engineering,
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
Hazard Identification and Risk Assessment in Foundry
Hazard Identification and Risk Assessment in Foundry M.SaravanaKumar 1, Dr.P.SenthilKumar 2 1 (Industrial Safety Engineering, K.S.R, College of Engineering / Anna University, Chennai, India) 2 (Department
Life Cycle Cost Analysis (LCCA)
v01-19-11 Life Cycle Cost Analysis (LCCA) Introduction The SHRP2 R-23 Guidelines provide a number of possible alternative designs using either rigid of flexible pavements. There is usually not a single
Project Management Challenges in Software Development
Abstract Research Journal of Management Sciences ISSN 2319 1171 Project Management Challenges in Software Development Uma Sankar S.S. 1 and R. Jubi 2 1 Research and Development Centre, Bharathiar University,
FUNBIO PROJECT RISK MANAGEMENT GUIDELINES
FUNBIO PROJECT RISK MANAGEMENT GUIDELINES OP-09/2013 Responsible Unit: PMO Focal Point OBJECTIVE: This Operational Procedures presents the guidelines for the risk assessment and allocation process in projects.
Application of Time Management Tools and Techniques by Construction Industry Players: A Comparative Study between Kedah and Kelantan
Application of Time Management Tools and Techniques by Construction Industry Players: A Comparative Study between Kedah and Kelantan Ismaaini Ismail 1, Ismail Abdul Rahman 2, Aftab Hameed Memon 3, Ahmad
Vendor Evaluation and Rating Using Analytical Hierarchy Process
Vendor Evaluation and Rating Using Analytical Hierarchy Process Kurian John, Vinod Yeldho Baby, Georgekutty S.Mangalathu Abstract -Vendor evaluation is a system for recording and ranking the performance
Financial Trading System using Combination of Textual and Numerical Data
Financial Trading System using Combination of Textual and Numerical Data Shital N. Dange Computer Science Department, Walchand Institute of Rajesh V. Argiddi Assistant Prof. Computer Science Department,
APPLICATION OF PROJECT MONITORING TOOLS FROM OWNER S PERSPECTIVE
Volume.02, Issue. 06, June 2014 ISSN (online): 2348 7550 APPLICATION OF PROJECT MONITORING TOOLS FROM OWNER S PERSPECTIVE 1 Dr. V. M. Topkar, 2 Pise Akshay H. 1,2 Civil and Environmental Engineering Department,
Random forest algorithm in big data environment
Random forest algorithm in big data environment Yingchun Liu * School of Economics and Management, Beihang University, Beijing 100191, China Received 1 September 2014, www.cmnt.lv Abstract Random forest
Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for
Effective Front-End Project Management A Key Element in Achieving Project Success in Developing Countries
Effective Front-End Project Management A Key Element in Achieving Project Success in Developing Countries O O FANIRAN School of Civil and Environmental Engineering The University of New South Wales Sydney
Strategic Planning for the Textile and Clothing Supply Chain
, July 4-6, 2012, London, U.K. Strategic Planning for the Textile and Clothing Supply Chain Deedar Hussain, Manuel Figueiredo, Anabela Tereso, and Fernando Ferreira Abstract The expansion of textile and
RISK MANAGEMENT FOR INFRASTRUCTURE
RISK MANAGEMENT FOR INFRASTRUCTURE CONTENTS 1.0 PURPOSE & SCOPE 2.0 DEFINITIONS 3.0 FLOWCHART 4.0 PROCEDURAL TEXT 5.0 REFERENCES 6.0 ATTACHMENTS This document is the property of Thiess Infraco and all
A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry
A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry Pranam B 1, Madhusudan G Kalibhat 2, Sudharshan KR 3 1 Student, Master of Technology (Construction
An evaluation of the fire safety emergency cover toolkit
icccbe 2010 Nottingham University Press Proceedings of the International Conference on Computing in Civil and Building Engineering W Tizani (Editor) An evaluation of the fire safety emergency cover toolkit
STRATEGIC CAPACITY PLANNING USING STOCK CONTROL MODEL
Session 6. Applications of Mathematical Methods to Logistics and Business Proceedings of the 9th International Conference Reliability and Statistics in Transportation and Communication (RelStat 09), 21
TOURISM DEMAND FORECASTING USING A NOVEL HIGH-PRECISION FUZZY TIME SERIES MODEL. Ruey-Chyn Tsaur and Ting-Chun Kuo
International Journal of Innovative Computing, Information and Control ICIC International c 2014 ISSN 1349-4198 Volume 10, Number 2, April 2014 pp. 695 701 OURISM DEMAND FORECASING USING A NOVEL HIGH-PRECISION
Causes, Effects and Minimization of Delays in Construction Projects
Causes, Effects and Minimization of Delays in Construction Projects Divya.R 1, S.Ramya 2 Assistant Professor Department of Civil Engineering Bharathiyar Institute of Engineering for Women, Deviyakurichi
APPROACHES FOR PERFORMANCE MEASUREMENT OF URBAN RENEWAL MEGAPROJECTS
APPROACHES FOR PERFORMANCE MEASUREMENT OF URBAN RENEWAL MEGAPROJECTS Heedae Park Combined Master s & Doctoral Program Student Dept. of Civil Engineering, Yonsei University [email protected] Seung
Project Cash Flow Forecasting Using Value at Risk
Technical Journal of Engineering and Applied Sciences Available online at www.tjeas.com 213 TJEAS Journal21332/2681268 ISSN 2183 213 TJEAS Project Cash Flow Forecasting Using Value at Risk Mohammad Reza
INFORMATION SECURITY RISK ASSESSMENT UNDER UNCERTAINTY USING DYNAMIC BAYESIAN NETWORKS
INFORMATION SECURITY RISK ASSESSMENT UNDER UNCERTAINTY USING DYNAMIC BAYESIAN NETWORKS R. Sarala 1, M.Kayalvizhi 2, G.Zayaraz 3 1 Associate Professor, Computer Science and Engineering, Pondicherry Engineering
Subcontractor Selection Using Analytic Hierarchy Process
Volume 3 Number 3 2012 pp. 121-143 ISSN: 1309-2448 www.berjournal.com Subcontractor Selection Using Analytic Hierarchy Process Vesile Sinem Arıkan Kargı a Ahmet Öztürk b Abstract: Turkish textile firms
RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT
RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.
Project Risk Identification. IH 635 Managed Lanes Project Exhibit A to Project Development Plan 1
Project Risk Identification The Risk Matrix shown in the tables below sets out a synopsis of principal risk areas, how they are commonly allocated, managed or eliminated in typical concession projects,
Motivations. spm - 2014 adolfo villafiorita - introduction to software project management
Risk Management Motivations When we looked at project selection we just took into account financial data In the scope management document we emphasized the importance of making our goals achievable, i.e.
Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead
The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman)
The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman) 11/17/07 Introduction Editor's Note: We liked so much of this book that we asked for the author's permission to quote
Software Risk Management Practice: Evidence From Thai Software Firms
, March 12-14, 2014, Hong Kong Software Management Practice: Evidence From Thai Software Firms Tharwon Arnuphaptrairong Abstract Software risk management has been around at least since it was introduced