1 Project Management Principles applied to the Claims Process

2 Overview Traditional claims approaches Discussion of factors leading to change in approach Outline of Project Management Principles Applying Project Management Principles to a claim Summary

3 Traditional approaches Loss occurs. Notification to Insurers Adjuster attends quickly likely with engineering experts Adjuster requests information to establish cause and value of initial claim estimate to provide an initial reserve to Insurers. Adjuster may attend during repair period to view progress Adjuster will often establish his own As-Built and Rebuild costs independently of the Insured. Repairs complete - Plant back running Adjuster may attend to view completed repairs and validate scope Final Claim submitted Coverage and cost issues negotiated and eventually claim is settled.

4 Common Issues Varying and ultimately unrealized expectations on both sides Planning Communication Poor documentation Uncertainty over what has been accepted by Adjuster Poor reconciliation between claimed costs and settlement proposals Extended Claims duration Difficulty in substantiating claim No appreciation for required detailed validation of the claim Many key parties involved in repair move on while claim process continues Adversarial relations Misunderstandings result in frustration

5 Why done this way? Every situation is unique Claim process is unpredictable Insurance is just done that way

6 Results Claims remain unpredictable People involved in claims have poor reputation Unnecessarily contentious Impacts across organization

7 Why change Recognition that the claim process impacts more than the RM/Insurance group A recognition of the value of project management principles within companies. Stricter governance need for management controls and accountability Leaner organizations means focus is on: Being right sized for day-to-day business Less ability to handle surge jobs Impact to public companies Impact on cash flow The need for a better mousetrap.

8 Fundamentals of Project Management If you fail to plan you are planning to fail. If project content is allowed to change freely, the rate of change will exceed the rate of progress. If you don t define the goalposts, how do you know when you score

9 Characteristics of Successful Projects Clear Objectives Good Project Plan Communication Controlled Scope Stakeholder Support

10 Project Planning Project Charter Project Execution Plan (PEP) Task definition Responsibility matrix Calendar of activities Budget Risk Management Strategy Execute Plan

11 Project Charter/PEP Project Charter Define the scope of the project May be defined by: corporate role (JV operator?) Size or type of loss Project Execution Plan Define how you want to reach your objectives Aggressive/cooperative Involvement/Control of legal counsel Use of consultants Speed or Amount of Settlement Basis of settlement

12 Define Tasks Detail the deliverables and the work required to get them Driven off scope of work but more detailed Answer Why is this a claim? What is affected? What aspects of work being done are insured/not insured? What was done about it? What did/will it cost? How does the money get recovered? Know what documentation is needed to support the answers

13 Responsibility Matrix Identify the resources required to fulfill the needs of the Tasks identified Multi-stream response Field (physical assets) Field/Corporate (production/sales impacts) Corporate (finance impacts) Establish Roles and Accountability matrix Lines of communication, reporting and responsibility Document Management Stewardship

14 Develop a timeline Take the tasks and develop a logical sequence Define cause Define scope of damage/repairs Identify and define duration for insured scope and uninsured scope. Calculate the anticipated time lag between repair being complete and progression of the claim process. Add in outside factors Interim payments what process and trigger points? Extended duration/deferred or non-essential work Claim closeout process Project a target closure date

15 Schedule Example 0 Incident Conduct Cause and Origin Cause and Origin (Prove Trigger) Develop Scope of Damage Scope of Damage Complete Develop repair plan Develop repair estimate Demolition Demolition Complete Construction Construction complete Start-up Begin collecting invoices Receive last invoice Collect proof of payment Submit invoices to adjuster Invoices in for review Negotiate payment Adjuster recommends Payment Process payment Payment received proof signed Develop model for business loss Track production impacts provide business model for review Review business model Agree BI loss Adjuster recommends Payment (BI) Process payment (BI) Payment received and proof signed Claim Closed

16 Risk Management Will not anticipate all problems Gives tool to bring in management help Manage expectations both internally and externally Manage resources internally and externally Requires revisiting plan often Revise as required

17 Execute Plan Execute the prepared plan in relation to the insurance claim scope Periodically revisit and revise as project proceeds Reporting progress Managing expectations Develop and manage relationships QA/QC Close out / lessons learned

18 Benefits of Project Management Approach Defined goalposts Defined completion Clear communication of expectations and accomplishments Internally and externally Reduced misunderstandings Less confrontational More efficient resolution Less time revisiting ideas and needs More rapid conclusion of claim Better auditability and justification of claim amounts

19 Thank you Lloyd Kortbeek, P.Eng, CIP Lloyd is the president and founder of E2I2 Consulting Inc, an engineering firm specialized in dealing with industrial claims. His firm provides investigation services related to cause and origin, claim support services related to the preparation and evaluation of claims, insurance claims in particular, and input and evaluation related to optimizing operation and maintenance methods. Mike Roper, CIP Mike is the president of Energy Insurance Consultants/EIC Claim Management. The company specializes in supporting clients in the management of their Property, Business Interruption, OEE, Liability and Pollution claims as well as pre-loss policy wording review and theoretical claim scenario analysis.

BDO Consulting. Insurance Claim Services. Logo

BDO Consulting. Insurance Claim Services. Logo BDO Consulting Insurance Claim Services Business interruption and property damage claim preparation is our core business exclusively servicing policyholders. We utilize a comprehensive and detailed approach

More information

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement

More information

Quick Reference Guide Interactive PDF Project Management Processes for a Project

Quick Reference Guide Interactive PDF Project Management Processes for a Project Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process

More information

EMERGENCY PREPAREDNESS PLAN Business Continuity Plan

EMERGENCY PREPAREDNESS PLAN Business Continuity Plan EMERGENCY PREPAREDNESS PLAN Business Continuity Plan GIS Bankers Insurance Group Powered by DISASTER PREPAREDNESS Implementation Small Business Guide to Business Continuity Planning Surviving a Catastrophic

More information

GETTING (BACK TO) BUSINESS INTERRUPTION INSURANCE. Section 1: Lost property and lost earnings are treated separately

GETTING (BACK TO) BUSINESS INTERRUPTION INSURANCE. Section 1: Lost property and lost earnings are treated separately GETTING (BACK TO) BUSINESS INTERRUPTION INSURANCE Section 1: Lost property and lost earnings are treated separately Business interruption insurance (also known as business income protection, profit protection,

More information

Series 4 Human Resource Management Unit 4.4 Team Development. EPO Training 2000 to date Gord Gibben, PMP

Series 4 Human Resource Management Unit 4.4 Team Development. EPO Training 2000 to date Gord Gibben, PMP Series 4 Human Resource Management Unit 4.4 Team Development Unit 4.4 Team Development Learning Objectives Team Development stages Team Charter Team Development Quiz Recommended Reading Unit 4.4 Learning

More information

The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004)

The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004) The Project Management Knowledge Areas as defined by PMI (PMBOK, 2004) is the processes required to ensure that the various elements of the project are properly coordinated. the processes required to ensure

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane samlane@aol.com Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,

More information

LGS Project Management Methodology

LGS Project Management Methodology Page: 32 LGS Project Management Methodoy The LGS project management methodoy is integral to our overall delivery methodoy. Based on inpro, one of the LGS inspiration series documents, our methodoy is compliant

More information

THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini)

THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) PAGE 1 THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) Ing. Guido Mattu More than 25 years experience in Engineering and Project Management activities

More information

CONTRACT MANAGEMENT FRAMEWORK

CONTRACT MANAGEMENT FRAMEWORK CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...

More information

Client information note Assessment process Management systems service outline

Client information note Assessment process Management systems service outline Client information note Assessment process Management systems service outline Overview The accreditation requirements define that there are four elements to the assessment process: assessment of the system

More information

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs HUMAN RESOURCE MANAGEMENT Organizational planning Staff Acquisition Project interfaces such as organizational interfaces, technical interfaces and interpersonal interfaces. Staffing requirements Staffing

More information

GENERAL RECORDS SCHEDULE 1.1: Financial Management and Reporting Records

GENERAL RECORDS SCHEDULE 1.1: Financial Management and Reporting Records GENERAL RECORDS SCHEDULE 1.1: Financial Management and Reporting Records This schedule covers records created by Federal agencies in carrying out the work of financial management: procuring goods and services,

More information

Chapter 1 Introduction to Contract Management and Administration

Chapter 1 Introduction to Contract Management and Administration Chapter 1 Introduction to Contract Management and Administration Definitions What is Contract Management? Contract management is the process that ensures both parties to a contract fully understand their

More information

Ken Ross. Professional Experience. Insurance Claims Consulting

Ken Ross. Professional Experience. Insurance Claims Consulting Ken Ross Associate Director Navigant Consulting (PI) LLC * Direct: 713-646-5036 Fax: 713-646-5001 ken.ross@navigantconsulting.com Professional History Navigant Consulting, Inc. 2008 to present Echelon

More information

5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter

5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter Develop Project Charter Develop Preliminary Project Scope Statement Develop Project Management Plan Scope Planning PROCESS GROUP: INITIATION 4.1 The project charter serves as the input document for the

More information

Construction Management Standards of Practice

Construction Management Standards of Practice Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388

More information

ID Task Name Time Pred

ID Task Name Time Pred 0 UC Modernization Project Plan 1115 d 1 1 Phase I - Business Case Development and Competitive Procurement 205 d 2 1.1 Complete Initial Feasibility Study 55 d 3 1.2 Prepare and Issue LBR 30 d 2 4 1.3 Competitive

More information

Project Integration Management

Project Integration Management Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform

More information

PHASE 8: IMPLEMENTATION PHASE

PHASE 8: IMPLEMENTATION PHASE PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter 1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process

More information

Project Management Simple Answers to Simple Questions

Project Management Simple Answers to Simple Questions Project Management Simple Answers to Simple Questions Originally I wrote this for one of my clients in 1991. The idea was to develop a brochure to promote project management in one of the client's departments.

More information

Get experience on your side. Contractors and Consultants. Environmental Package Insurance

Get experience on your side. Contractors and Consultants. Environmental Package Insurance Get experience on your side Contractors and Consultants Environmental Package Insurance Contractors and Consultants Why you should choose ENCON's Environmental Package Insurance As a contractor or consultant,

More information

Input, Output and Tools of all Processes

Input, Output and Tools of all Processes 1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) Marc.Conrad@luton.ac.uk 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /

More information

Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas)

Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas) Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas) Nutek, Inc. 3829 Quarton Road, Suite 102 Bloomfield Hills, Michigan 48302, USA. Phone: 248-540-4827, Email: Support@Nutek-us.com

More information

Project Management Plan for

Project Management Plan for Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...

More information

PIMA COUNTY PROJECT TRACKING REPORT

PIMA COUNTY PROJECT TRACKING REPORT PIMA COUNTY PROJECT TRACKING REPORT [DEPARTMENT NAME] [PROJECT NAME] Revision Date: [03/18/09] The Project Tracking Report document will provide a single source document where the Project Charter can continue

More information

Project Procurement Management

Project Procurement Management Project Procurement Management Outline Introduction Plan Purchases and Acquisitions Plan Contracting Request Seller Responses Select Sellers Contract Administration Contract Closure Introduction Procurement

More information

ATTACHMENT 3 TO AIU3 HOSTED VOIP SERVICE REQUEST FOR PROPOSAL (December 10, 2010)

ATTACHMENT 3 TO AIU3 HOSTED VOIP SERVICE REQUEST FOR PROPOSAL (December 10, 2010) ATTACHMENT 3 TO AIU3 HOSTED VOIP SERVICE REQUEST FOR PROPOSAL (December 10, 2010) AlleghenyCONNECT Existing Vendor Pricing Worksheet for Configuration Changes NOC VOIP Support Statement of Work Presented

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS USACE / NAVFAC / AFCEC / NASA UFGS-01 32 16.00 20 (February 2015) Change 2-11/15 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 32 16.00 20 (November 2009) UNIFIED FACILITIES

More information

DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM

DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM 2015 Business Plan Chapter 3, Water Facilities Focus Area, Goal Number 4 June 2011 CAPITAL IMPROVEMENT PROGRAM

More information

Certification Preparation Course LATVIKON (R.E.P.)Centre

Certification Preparation Course LATVIKON (R.E.P.)Centre PMP Certification Preparation Course LATVIKON (R.E.P.)Centre ABOUT THIS COURSE Your ability as a project manager to demonstrate best practices in Project Management both on the job and through professional

More information

Certificate In Project Management (CIPM)

Certificate In Project Management (CIPM) Conceptualize Plan Plan & Deliver Organize Implement Control Change if Required Integrate Deliver & Closeout Knowledge Leverage Certificate In Project Management (CIPM) Course Overview The Certificate

More information

Time Management. Herb Pollard III

Time Management. Herb Pollard III Time Management A Small Business Perspective Herb Pollard III Project Manager for Time Management - Pollard PMI Slide 1 Introduction: Time Management - Pollard PMI Slide 2 Project Phases and the Areas

More information

PMP Project Management Professional Study Guide, Third Edition

PMP Project Management Professional Study Guide, Third Edition PMP Project Management Professional Study Guide, Third Edition Joseph Phillips McGraw-Hill is an independent entity from the Project Management Institute, Inc. and is not affiliated with the Project Management

More information

Appendix 3: Project Management Substation Guidelines (General Process Flow Template)

Appendix 3: Project Management Substation Guidelines (General Process Flow Template) 365 Appendix 3: Project Management Substation Guidelines (General Process Flow Template) Checkpoint Methodology The schedule is issued prior to the go decision. It covers the duration of the project. It

More information

Issue Paper & Initial Straw Proposal. Settlement Timeline Bridge

Issue Paper & Initial Straw Proposal. Settlement Timeline Bridge Issue Paper & Initial Straw Proposal Settlement Timeline Bridge March 11, 2010 Settlement Timeline Bridge 1 Introduction Prepared for Discussion on a Stakeholder Call March 18, 2010 The CAISO has settlement

More information

Managing IT Projects. Chapter 2 The PMI Framework

Managing IT Projects. Chapter 2 The PMI Framework Managing IT Projects Chapter 2 The PMI Framework The PMI Framework The Project Management Institute,USA is an internationally acclaimed organization Devoted to Creation & sharing of knowledge in the area

More information

The ITS Project Management Framework

The ITS Project Management Framework The ITS Project Management Framework Information Technology Services Project Management Framework v1.0 1 Table of Contents Introduction 3 Why Create a Project Management Framework? 4 Projects versus Operational

More information

Project Execution, Monitoring and Control (IS PM 8. Lecture; 2012 Spring)

Project Execution, Monitoring and Control (IS PM 8. Lecture; 2012 Spring) Project Execution, Monitoring and Control Topics of the lecture as follows: PDCA cycle Project execution processes by PMBOK Project monitoring and controlling processes by PMBOK Project monitoring and

More information

Texas Department of Transportation

Texas Department of Transportation Consultant Errors & Omissions Correction and Collection Procedures July 2014 July 2014 Consultant Errors & Omissions Correction and Collection Procedures 1.0 Consultant Contract Administration... 2 2.0

More information

PUTTING OUT THE FIRE Preparing Successful Property and Business Interruption Insurance Claims. Presented by Chris Brophy and Tony Moraes

PUTTING OUT THE FIRE Preparing Successful Property and Business Interruption Insurance Claims. Presented by Chris Brophy and Tony Moraes PUTTING OUT THE FIRE Preparing Successful Property and Business Interruption Insurance Claims Presented by Chris Brophy and Tony Moraes February 5, 2015 Presenters Chris Brophy New York / 212.651.7180

More information

Playing The Project Management Game

Playing The Project Management Game Playing The Project Management Game Tools and Techniques to Win the Game Dean Athanassiades, PMP Nancy Stetson, PMP Version 2003-12-02 (c) Dean Athanassiades 2003 1 Presenters Dean Athanassiades, PMP Philips

More information

THE NEW REALITY OF RISK CYBER RISK: TRENDS AND SOLUTIONS

THE NEW REALITY OF RISK CYBER RISK: TRENDS AND SOLUTIONS THE NEW REALITY OF RISK CYBER RISK: TRENDS AND SOLUTIONS Read the Marsh Risk Management Research Briefing: Cyber Risks Extend Beyond Data and Privacy Exposures To access the report, visit www.marsh.com.

More information

CONTRACT MANAGEMENT COURSES

CONTRACT MANAGEMENT COURSES CONTRACT MANAGEMENT COURSES Principles and Practices Administration of Commercial Contracts Commercial Applications Risk Management in the Sourcing Environment TM Principles and Practices Identify contract

More information

Project Procurement Management

Project Procurement Management Project Procurement Management 1 2 Procurement Planning Procurement Planning is the process of identifying which project needs can be best met by procuring products or services outside the project organization

More information

Frequently Asked Questions in Project Management

Frequently Asked Questions in Project Management Frequently Asked Questions in Project Management 1. Question: What is Project Management? Answer: Project Management is the collection and application of skills, knowledge, processes, and activities to

More information

Frequently Asked Questions (Including Definitions)

Frequently Asked Questions (Including Definitions) My Business Income Consultation from Chubb Frequently Asked Questions (Including Definitions) Frequently Asked Questions How To Use The Tool Click on the question that you would like to have answered.

More information

Insurance. Insurance. My home is insured. What should I do first?

Insurance. Insurance. My home is insured. What should I do first? Insurance This chapter has information for people with insurance queries who experienced loss because of the February 2009 Victorian bushfires. It also has information on financial and other help. My home

More information

SCHEDULE 3 Generalist Claims 2015

SCHEDULE 3 Generalist Claims 2015 SCHEDULE 3 Generalist Claims 2015 Nominal Insurer And Schedule 3 (Claims) Page: 1 of 23 Contents Overview... 3 1. Scope of Services... 4 1.1 Claims Services... 4 1.2 Claims Process... 5 1.3 Assessment

More information

The 10 Knowledge Areas & ITTOs

The 10 Knowledge Areas & ITTOs This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading

More information

A Guide To The Project Management Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition

A Guide To The Project Management Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition A Guide To The Project Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition Major Changes The adoption of the verb-noun format for process names Amplification as to Enterprise

More information

THE COMPLETE PROJECT MANAGEMENT METHODOLOGY AND TOOLKIT

THE COMPLETE PROJECT MANAGEMENT METHODOLOGY AND TOOLKIT THE COMPLETE PROJECT MANAGEMENT METHODOLOGY AND TOOLKIT GERARD M. HILL CRC Press Taylor & Francis Group Boca Raton London New York CRC Press is an imprint of the Taylor & Francis Croup, an informa business

More information

Applying the Theory of the Firm to Examine a Technology Startup at the Investment Stage

Applying the Theory of the Firm to Examine a Technology Startup at the Investment Stage Applying the Theory of the Firm to Examine a Technology Startup at the Investment Stage There is nothing more practical than a good theory. Kurt Lewin Psychologist and author The investment stage of a

More information

Supporting the Perfect Order: Collaborative S&OP and VMI

Supporting the Perfect Order: Collaborative S&OP and VMI Supporting the Perfect Order: Collaborative S&OP and VMI October 30, 2012 Frankfurt, Germany Gary Neights Director, Product Management The Multi-Echelon Supply Chain Plan Your Supplier s Suppliers Your

More information

PRACTICE ADVISORIES FOR INTERNAL AUDIT

PRACTICE ADVISORIES FOR INTERNAL AUDIT Société Française de Réalisation, d'etudes et de Conseil Economics and Public Management Department PRACTICE ADVISORIES FOR INTERNAL AUDIT Tehnical Assistance to the Ministry of Finance for Development

More information

Network Rail Infrastructure Projects Joint Relationship Management Plan

Network Rail Infrastructure Projects Joint Relationship Management Plan Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf

More information

4 b) Where to Record Revenue. 4 5 c) When to Record Revenue. 6-11 Recognition of Unrestricted Revenue Recognition of Restricted Revenue Sources

4 b) Where to Record Revenue. 4 5 c) When to Record Revenue. 6-11 Recognition of Unrestricted Revenue Recognition of Restricted Revenue Sources Revenue Recognition Policy Guidelines These guidelines are organized within the following sections: Pages I. Purpose 1 II. Responsibilities 1 III. Definitions 2-3 IV. Major Sources of Revenue and Normal

More information

Recognition of Prior Learning (RPL) Kit. BSB51407 Diploma of Project Management

Recognition of Prior Learning (RPL) Kit. BSB51407 Diploma of Project Management Recognition of Prior Learning (RPL) Kit BSB51407 Diploma of Project Management Applicant: Date: Diploma of Project Management RPL Kit 1 Applicant declaration: I have completed the following RPL application

More information

Pandemic Influenza Planning for Colleges and Universities

Pandemic Influenza Planning for Colleges and Universities Pandemic Influenza Planning for Colleges and Universities Richard Hernandez, Dr.P.H., RRT Dean, Allied Health Sciences Trident Technical College Charleston, SC Colleges and Universities Pandemic Influenza

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

Why Nonprofits Need Nonprofit Accounting Software

Why Nonprofits Need Nonprofit Accounting Software Why Nonprofits Need Nonprofit Accounting Software % CONTENTS Executive Summary... 3 The Benefits of a Nonprofit Accounting System... 4 Unique Regulations and Standards for Unique Solutions... 4 Supporting

More information

Best Practices in Model Development and Maintenance Adam Rose (adam.rose@xpsolutions.com), Product Manager, XP Solutions

Best Practices in Model Development and Maintenance Adam Rose (adam.rose@xpsolutions.com), Product Manager, XP Solutions Best Practices in Model Development and Maintenance Adam Rose (adam.rose@xpsolutions.com), Product Manager, XP Solutions adopted from Best practices for software development projects Mike Perks (mperks@us.ibm.com),

More information

Project Management Professional (PMP)

Project Management Professional (PMP) Project Management Professional (PMP) Duration: 5 days Course Objectives: PMI s Project Management Professional (PMP) credential is the most important industry-recognized certification for project managers.

More information

Metro Business Continuity and Disaster Recovery Plan Response to vendor questions RFP10-1629

Metro Business Continuity and Disaster Recovery Plan Response to vendor questions RFP10-1629 April 14, 2010 Q1. How does Metro define its plan? What type of plan does Metro want to create? Should it focus on the facility, process, and/or department? Is it intended for use during incident management

More information

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM)

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM) AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM) February 2010 Version 1.12 Copyright: Australian Institute of Project Management Document

More information

Governance in the Project Management World Published January 2013.

Governance in the Project Management World Published January 2013. Governance in the Project Management World Published January 2013. 12/6/12 Executive Summary This paper examines "governance", its potential role in project management and the governance environment in

More information

Project Management Institute. Construction. Extension to. A Guide to the Project Management Body of Knowledge. PMBOK Guide 2000 Edition.

Project Management Institute. Construction. Extension to. A Guide to the Project Management Body of Knowledge. PMBOK Guide 2000 Edition. Project Management Institute Construction Extension to A Guide to the Project Management Body of Knowledge PMBOK Guide 2000 Edition Provisional Construction Extension to A Guide to the Project Management

More information

CDC UNIFIED PROCESS PRACTICES GUIDE

CDC UNIFIED PROCESS PRACTICES GUIDE Purpose The purpose of this document is to provide guidance on the practice called Project Close-Out and to describe the practice overview, requirements, best practices, activities, and key terms related

More information

Project Management Competency Standards

Project Management Competency Standards BSB01 Business Services Training Package Project Management Competency Standards CONTENTS BSBPM401A Apply scope management techniques...3 BSBPM402A Apply time management techniques...8 BSBPM403A Apply

More information

Module 7: Change Management

Module 7: Change Management Module 7: Change Module 7: Change Integrating Project with Change They think by installing this system they will end my services let us see if they will ever manage to get it done What is the purpose of

More information

Claims Reporting Procedure

Claims Reporting Procedure Claims Reporting Procedure This document includes:- An introduction to the claims reporting process Your Belmont contacts The life of your claim A review of the Ministry of Justice Reforms Introduction

More information

Project Charter Updated

Project Charter Updated Enterprise IT Service Management Pilot Proof of Concept Project Charter Updated Prepared By: M. Riley & J. Foster Date of Publication: March 13, 2006 Date Last Revised: April 25, 2007 PMO CH1, 8/01 Document

More information

Risk Management Division Municipal Manager Anchorage: Performance. Value. Results.

Risk Management Division Municipal Manager Anchorage: Performance. Value. Results. Risk Management Division Anchorage: Performance. Value. Results. Purpose Minimize the financial impact and loss of Human resources, from known and unknown events and accidents. Core Services Process auto

More information

Overview TECHIS60851. Manage information security business resilience activities

Overview TECHIS60851. Manage information security business resilience activities Overview Information security business resilience encompasses business continuity and disaster recovery from information security threats. As well as addressing the consequences of a major security incident,

More information

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

THE PROJECT MANAGEMENT KNOWLEDGE AREAS THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human

More information

Project Cost Management

Project Cost Management PDHonline Course P104 (8 PDH) Project Cost Management Instructor: William J. Scott, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org

More information

Business-critical Insurance

Business-critical Insurance Business-critical Insurance Identifying those insurances that support the business and its strategy Guide 2015 Contents Introduction... 4 Categories of insurance... 5 Determining which insurance covers

More information

Del O'Roark, Loss Prevention Consultant, Lawyers Mutual Insurance Co. of Ky.

Del O'Roark, Loss Prevention Consultant, Lawyers Mutual Insurance Co. of Ky. So You've Been Accused of Legal Malpractice? Well, Don't Just Do Something - Sit There! Del O'Roark, Loss Prevention Consultant, Lawyers Mutual Insurance Co. of Ky. KBA Bench & Bar, Vol. 58 No. 1, Winter

More information

DRAFT Revised Guide to the National CDEM Plan 2015 July 2015

DRAFT Revised Guide to the National CDEM Plan 2015 July 2015 19. Planning Summary Planning involves the proactive coordination of CDEM Group and agency activities in the medium to long term, with the intention of achieving a unified effort that works towards a common

More information

Subject Area 1 Project Initiation and Management

Subject Area 1 Project Initiation and Management DRII/BCI Professional Practice Narrative: Establish the need for a Business Continuity Plan (BCP), including obtaining management support and organizing and managing the BCP project to completion. (This

More information

Big Data Support Services. Service Definition

Big Data Support Services. Service Definition 1 3 Big Data Support Services Service Definition BIG DATA SUPPORT SERVICES Service Description The Big Data Support Services are part of the Cognizant Information Management service family. Providing a

More information

Lesson 10: IT Project and Program Management

Lesson 10: IT Project and Program Management Lesson 10: IT Project and Program Management Lesson 10 Objectives Identify resources for technical data Identify project management fundamentals Identify project management skills Identify the five project

More information

Organization. Project Name. Project Overview Plan Version # Date

Organization. Project Name. Project Overview Plan Version # Date Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents

More information

Louisiana: Bulletin No. 06-06 Commercial and Homeowners Insurance Disclosure Forms. Bulletin No. 06-06 and disclosure forms attached there-in

Louisiana: Bulletin No. 06-06 Commercial and Homeowners Insurance Disclosure Forms. Bulletin No. 06-06 and disclosure forms attached there-in market bulletin From Director, Worldwide Markets (extn 6863) Date 26 January 2007 Reference Subject Subject areas Attachments Action points Y3963 Louisiana: Bulletin No. 06-06 Commercial and Homeowners

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

Environmental Negotiation Primer

Environmental Negotiation Primer June 2002 Page 1 of 6 Naval School, Civil Engineer Corps Officer (CECOS) Issue Discussion Whether you are negotiating the subtle, yet important, specific input and results of a human health risk assessment

More information

Consultancy Services Proposal

Consultancy Services Proposal Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847

More information

Introduction and Background

Introduction and Background Introduction and Background The Community College League of California is a nonprofit public benefit corporation whose voluntary membership consists of the 72 local community college districts in California.

More information

Project Closeout Module 1 Construction Closeout Checklist

Project Closeout Module 1 Construction Closeout Checklist Project Closeout Module 1 Construction Closeout Checklist August 5, 2005 1 OAR Challenge How to Close the Project (Drain the Swamp) And Protect District Assets from Contractors (Alligators) 2 Project Closeout

More information

**READ YOUR INSURANCE POLICY FOR COMPLETE POLICY TERMS AND CONDITIONS**

**READ YOUR INSURANCE POLICY FOR COMPLETE POLICY TERMS AND CONDITIONS** HOMEOWNERS HO P 002 06 11 IMPORTANT INFORMATION REQUIRED BY THE LOUISIANA DEPARTMENT OF INSURANCE Homeowners Insurance Policy Coverage Disclosure Summary This form is promulgated pursuant to LSA-R.S. 22:1332

More information

July 2013 Report No. 13-042

July 2013 Report No. 13-042 John Keel, CPA State Auditor An Audit Report on Selected State Contracts at the Texas Education Agency Report No. 13-042 An Audit Report on Selected State Contracts at the Texas Education Agency Overall

More information

GASB Statement 49 Accounting and Financial Reporting for Pollution Remediation Obligations Implementation Issues in a Question and Answer Format

GASB Statement 49 Accounting and Financial Reporting for Pollution Remediation Obligations Implementation Issues in a Question and Answer Format GASB Statement 49 addresses accounting and financial reporting standards for pollution (including contamination) remediation obligations, which are obligations to address the current or potential detrimental

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

ESKITP6036 IT Disaster Recovery Level 5 Role

ESKITP6036 IT Disaster Recovery Level 5 Role Overview This sub-discipline is about the competencies required in order to manage all aspect of Disaster Recovery (DR), as it applies to IT within an organisation. ESKITP6036 1 Performance criteria You

More information

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010

Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010 Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning

More information

Key Issues in Loss Mitigation - Catastrophic Events / Commercial Property Insurance

Key Issues in Loss Mitigation - Catastrophic Events / Commercial Property Insurance Key Issues in Loss Mitigation - Catastrophic Events / Commercial Property Insurance Area Business Disaster Recovery Symposium Myrtle Beach Convention Center January 31, 2014 James W. Errico 1 Brief Bio

More information