Project Cost Management
|
|
|
- Colleen Pope
- 10 years ago
- Views:
Transcription
1 PDHonline Course P104 (8 PDH) Project Cost Management Instructor: William J. Scott, P.E PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA Phone & Fax: An Approved Continuing Education Provider
2 PROJECT MANAGEMENT ASSOCIATES, INC 2100 Southwinds Circle Birmingham, Alabama Presents Project Cost Management Via WEB BASED LEARNING Author: William (Bill) J. Scott, PMP, PE PMA 1
3 Module 2 Project Financial Management Overview Running a project is much like running a business in essence, running a company within a company. Many of the same business management skills used to run the company apply to running the projects within that company. Project financial management is a broad category of skills necessary to ensure successful project outcome. Project financial management is more than just cost management (although cost management is of great importance). It also involves managing all aspects of the project that result in project gross margin, project income, project cash flow and ultimately the resulting financial impact on the bottom line of the company. Although project financial management overlaps portions of most of the project management knowledge areas, this course will focus specifically on project income, project cash flow and the components that affect each. Later Modules also provide more in-depth analysis on project cost management and project financial reporting. Project Revenue and Revenue Recognition 1. Project revenue is money received in exchange for project deliverables. 2. Like company revenue, project revenue can be recognized according to various methods as defined by the company. These methods must however be in accordance with GAAP. 3. Recognition of revenue is generally consistent among all projects in the company s project portfolio. There are some exceptions to this however, especially for companies that handle projects with widely variable scopes and time duration. 4. Recognition of revenue sometimes occurs prior to actual receipt of cash for goods and services supplied. 5. There must be a reasonable expectation that the client will pay for the goods and services supplied. 6. Jobs of varying scope, complexity, and risk may require different methods of revenue recognition. Examples of Revenue Recognition Methods 1. Completed Contract Basis: Revenue is recognized for the entire contract at the completion of the contract. This is typical of small projects in which it is acceptable for project costs to be financed by the company until completion of the project. 2
4 This method is almost never used for projects with values over $100,000 or durations over 6 months. An example would be the design, fabrication, and supply of a $40,000 dieselpowered back-up generator system. 2. Cash Received Basis: Revenue is recognized as cash is received in accordance with the contract payment terms. This method is typical of projects (usually small) in which progress payments are made throughout the project. An example would be monthly progress billings and payments on a construction contract. 3. Cost Incurred Basis: Revenue is recognized on a periodic basis (usually monthly) based on cost incurred to date. The cost incurred is correlated to percent completion of the project, and revenue is recognized according to the percent completion. The cost of internal labor is incurred as the labor is used. Accounting should report internal labor costs for the period. For material purchases and subcontracts, cost incurred may be figured using various methods: a. Invoices Received costs are incurred as invoices are received against the project. b. Costs Committed costs are incurred based on commitments (purchase order agreements and subcontracts). c. Estimates costs are incurred based on estimates of project completion. Risks Associated with Revenue Recognition 1. Revenue recognition according to completed contract or cash received are not very aggressive and hence offers low levels of risk to the project financial outcome. For example, there is almost no risk involved with recognizing revenue on a completed contract as there is no work left to be done, no gap remains to be filled. 2. As revenue recognition becomes more accelerated (in the case of cost incurred methods), the risk to overall project financial outcome increase. For example, a project may be 90 percent completed according to costs committed even though only 70 percent of the project deliverables have been completed. 3. The following table shows the general trend of risk versus revenue recognition: Revenue Recognition Method Completed Contract Cash Received Cost Incurred Invoices Received Cost Incurred Costs Committed Cost Incurred Estimates Risk Level Lowest Low Moderate High Highest 3
5 Project Costs During the execution phase of a project, costs are categorized as follows: 1. Cost Committed: Any costs that have been committed by the company. Issuance of a purchase order for materials is a commitment to pay for the supply of materials and is hence a committed cost. Internal labor is committed as it is posted. For subcontracts, cost committed may be a function of the commercial terms of the subcontract agreement. 2. Cost Incurred (Cost to Date): Any costs that have been posted to the project. Invoices against purchase orders are recorded as costs incurred. Internal labor is posted as it is incurred. 3. Open P.O. Cost: For costs pertaining to buy-out items, the open P.O. cost is the Cost Committed minus the Cost Incurred. 4. ETC Cost: Estimated cost to complete. Represents costs over and above committed costs that are required to move the task from the current status to completion. 5. EAC Cost: Estimated cost at completion. Represents the best estimate of the total cost of a task or project at completion of the project. EAC Cost = Cost Incurred + Open P.O. Cost + ETC Cost Cost Types and Examples 1. Direct Costs can readily be traced to cost objects. These costs are posted directly to the individual project that received the benefit of the work. Examples are: Internal labor used to execute projects Purchased materials used to make the product 2. Indirect Costs cannot readily be traced to a specific task. Therefore, these costs may be allocated proportionally to various projects. These costs vary from company to company and are usually determined by company policy. Examples are: Research and Development Depreciation of Assets SG&A a. Overhead Expenses b. Corporate Charges c. Bonuses d. Commissions e. Depreciation f. Building Rent 4
6 3. Fixed Costs costs that do not change with respect to volume or time. Examples are: SG&A Building Rent 4. Variable Costs costs that change with time, production levels, etc. Internal labor used to execute projects Purchased materials used to make the product Bonuses Commissions Depreciation Notes: 1. Costs can be classified as direct or indirect and as either fixed or variable. 2. Direct costs may also be classified as fixed or variable. Likewise, indirect costs may also be classified as fixed or variable. 3. This leads to compound categories such as direct variable costs (raw materials for example) and indirect fixed costs (building rent for example). Project Cash Flow The overriding similarity between project cash flow and company cash flow is that there are only two ways for cash to flow: in and out. There s no secret as to which is preferable here. Objectives of Cash Flow Management 1. Initiate and maintain positive cash flow throughout life cycle of project. 2. Maximize sources of cash. 3. Minimize uses of cash. 4. Minimize time lag for sources of cash. 5. Maximize time lag for uses of cash. Basic Cash Flow Management Concepts Cash In: 1. Invoicing / Payment Terms: Favorable payment terms should be negotiated in order to provide the potential for positive cash flow. An example is net 30 with interest charges for delinquent payments. No holdbacks. Partial payment up front as well as interim progress payments should be negotiated. Final payment should be tied to a specific and realizable date and or event. It should not be vague. Clauses such as payment upon successful start-up or payment upon acceptance are too fuzzy. It is too difficult to determine when the criteria have been met. 5
7 Invoicing must be according to plan. This means that the project must remain on schedule for any hope of positive cash flow. Invoices should be technically correct (according to contract requirements) to prevent delay of payments. This is especially important for large, complex projects where invoice submittals can require large amounts of back-up documentation. 2. Receivables Management: Aging analysis reports must be maintained. Delinquent payments should be flagged and forwarded from accounting to the appropriate project manager. Project manager should address the delinquent payments through the proper chain of command within the client organization. Corrective action should be taken to prevent future delinquencies. 3. Contract Change Orders: Contract change orders (adders or deducts) provide opportunities not only to improve margins but also project cash flow. Like the original contract, favorable terms and conditions should be negotiated for change orders. Adders should be invoiced separately and front-end loaded. Deducts should be applied to the original contract and back-end loaded. Change orders should be done in real time. Don t let them pile up until the end. Cash Out: 1. Internal Resource Allocation: Internal labor resources must be managed effectively. Labor costs are expensive and generally hit the project early and then again late. Allocation of labor should be allocated to the project according to plan. Variances should be noted and corrective actions taken. Labor reports must be timely and accurate to allow for proper control. 2. Contractors / Subcontractors: Subcontracts should be negotiated with favorable payment terms and conditions. Payments should be tied to specific deliverables, schedules, and quality levels. Retainage should always be applied to subcontracts. Never let your subcontractor get ahead of you on cash for work completed (Earned Value). 3. Payables Management: Payment terms should be extended to the greatest possible extent without damaging strategic relationships. Payment of vendor invoices should only be approved by the project manager or by an authority assigned by the project manager. Disputed invoices should be held pending resolution; however, resolution efforts should not be delayed simply to improve cash flow. Retainage to invoices should be applied where appropriate. 6
8 4. Contract Disputes: Dispute resolution should be attempted with project financial performance in mind. Disputes should be addressed in a timely and vigorous manner. Generally, the longer a dispute lingers without resolution, the more likely it is that the cost impact will worsen. 5. Dispute Resolution: Negotiation Negotiation of the dispute between the two parties is the first line of defense as well as the least expensive. This may be accomplished at various levels within the organizations involved (project manager to company president). Hopefully, resolution can be reached prior to the involvement of professionals. Mediation Mediation can sometimes provide help to reaching a resolution without going to binding arbitration or litigation. Arbitration Arbitration allows both parties to plead their cases to a professional arbitrator who will render a binding decision in the dispute. While more costly than both negotiation and mediation, binding arbitration is typically much less expensive than litigation. Litigation When all else fails, lawyers and court actions will produce results although at great cost to both parties. Whether the case is settled in or out of court, the legal costs can be enormous. Cash Flow / Timing of Cash 1. The project work breakdown structure (WBS), project schedule, and project budget should be used to estimate the Cash Out for various phases of the project. 2. Analysis of contract terms should be used to estimate the Cash In for various phases of the project. 3. Cash flow management should be planned by comparison of the anticipated Cash In and Cash Out values. 4. Project cash flow should be tracked and reported periodically along with other project financial information. 7
The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY
The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY From Financial Management & Accounting for the Construction Industry, CFMA. 2014 Matthew Bender and Company, Inc., a member of the LexisNexis Group.
Cash flow is the life line of a business. Many start-up
PM.02 ABC of Cash Flow Projections Mark T. Chen, PE CCE Cash flow is the life line of a business. Many start-up companies fail because of insufficient cash flow. From the perspectives of both owner and
How To Calculate Financial Performance For Construction Contractors
Understanding Construction Accounting Understanding Construction Accounting David O Brien, CPA, CGMA Member & Director of Construction Team James F. Weber, CPA, CGMA Managing Member This session is eligible
Accounting System. Page 1 of 9
Page 1 of 9 Accounting System In support of program management and Earned Value Management, the accounting system must be able to relate costs incurred to work accomplished. Not all accounting systems
Construction Economics & Finance. Module 6. Lecture-1
Construction Economics & Finance Module 6 Lecture-1 Financial management: Financial management involves planning, allocation and control of financial resources of a company. Financial management is essential
International Accounting Standard 11 Construction Contracts
International Accounting Standard 11 Construction Contracts Objective The objective of this Standard is to prescribe the accounting treatment of revenue and costs associated with construction contracts.
Accounting System Requirements
Accounting System Requirements Further information is available in the Information for Contractors Manual under Enclosure 2 The views expressed in this presentation are DCAA's views and not necessarily
School Construction Projects
The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect
Construction Contracts
STATUTORY BOARD FINANCIAL REPORTING STANDARD SB-FRS 11 Construction Contracts This version of SB-FRS 11 does not include amendments that are effective for annual periods beginning after 1 January 2015.
July 19, 2015. Sent Via Email to: XXXXX. Re: Letter Agreement for Legal Services. Dear XXXXX:
Kent H. Whitmer ([email protected]) William G. Berry ([email protected]) P.O. Box 38 129 E. Byers Ave. Hot Sulphur Springs, CO 80451 www.whitmerlawfirm.com 970.725.3460 Sent Via Email to: XXXXX
The following Accounting Standards Interpretation (ASI) relates to AS 7. ASI 29 Turnover in case of Contractors
108 Accounting Standard (AS) 7 (revised 2002) Construction Contracts Contents OBJECTIVE SCOPE Paragraph 1 DEFINITIONS 2-5 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 6-9 CONTRACT REVENUE 10-14 CONTRACT
CHAPTER 6 PROJECT CASH FLOW
CHAPTER 6 PROJECT CASH FLOW In the previous chapters, techniques for project planning, scheduling, resources management, and timecost trade off have been introduced. This chapter will deal with project
NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS
NAS 13 NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS CONTENTS Paragraphs OBJECTIVE SCOPE 1 2 DEFINITIONS 3 6 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 7 10 CONTRACT REVENUE 11 15 CONTRACT
Construction Contracts
Compiled Accounting Standard AASB 111 Construction Contracts This compiled Standard applies to annual reporting periods beginning on or after 1 January 2009 that end on or after 30 June 2009. Early application
Construction Contracts
65 Accounting Standard (AS) 7 Construction Contracts Contents OBJECTIVE SCOPE Paragraph 1 DEFINITIONS 2-5 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 6-9 CONTRACT REVENUE 10-14 CONTRACT COSTS 15-20
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. Table of Contents 1. INTRODUCTION...
Auditing Capital Projects and Project Controls. March 2013
Auditing Capital Projects and Project Controls March 2013 Internal Audit Perspective Oversight Insight Foresight Is the process operating as planned? Are controls, resources, and performance measures adequate
Contract Cash Flow & Performance Analysis. PERCEPTION Helping The Shipyard Stay On Budget
Contract Cash Flow & Performance Analysis PERCEPTION Helping The Shipyard Stay On Budget 1 Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge
International Financial Reporting. Construction Contracts IAS 11
Construction Contracts IAS 11 2 Construction contract definition Construction Contract is a contract specifically negotiated for the construction of an asset (a building, a bridge) or a combination of
February 3, 2016 12(1) CHAPTER 12
February 3, 2016 12(1) CHAPTER 12 Table of Contents Paragraph Page 12-000 Auditing Contract Termination, Delay/Disruption, and Other Price Adjustment Proposals or Claims 12-001 Contract Terminations and
Christopher Noble, Negotiating Owner-Architect Agreements: Theory and Practice (revised February 2011)
Christopher Noble, Negotiating Owner-Architect Agreements: Theory and Practice (revised February 2011) Construction projects are usually complex undertakings with numerous participants, linked by a web
CHAPTER 23. Contract Management and Administration
Date Issued: June 12, 2009 Date Last Revised: September 28, 2015 CHAPTER 23. Contract Management and Administration Table of Contents CHAPTER 23. Contract Management and Administration... 23-1 23.1 Policy...
GOVERNMENT OF MALAYSIA
GOVERNMENT OF MALAYSIA Malaysian Public Sector Accounting Standards MPSAS 11 Construction Contracts March 2015 MPSAS 11 Construction Contracts Acknowledgment The Malaysian Public Sector Accounting Standard
How To Account For Construction Contracts In Indian Accounting Standard (Indas)
Contents Indian Accounting Standard (Ind AS) 11 Construction Contracts Paragraphs OBJECTIVE SCOPE 1 2 DEFINITIONS 3 6 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 7 10 CONTRACT REVENUE 11 15 CONTRACT
PROJECT PROCUREMENT MANAGEMENT
12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,
Project Procurement Management
Project Procurement Management 1 2 Procurement Planning Procurement Planning is the process of identifying which project needs can be best met by procuring products or services outside the project organization
CHAPTER 7 COST PRINCIPLES
CHAPTER 7 COST PRINCIPLES 7101. Cost Principles. (a) Definitions. (1) Actual Costs are all direct and indirect costs which have been incurred for services rendered, supplies delivered, or construction
19.2 Applicable Terms
19.0 ACCOUNTING FOR CONSTRUCTION CONTRACTS 19.1 Introduction This chapter covers the following: a. Applicable Terms b. Applicable Standard c. Key IPSAS Provisions d. Accounting Documentation e. Accounting
City of Vallejo REQUEST FOR PROPOSAL WORKERS COMPENSATION CLAIMS AUDIT
City of Vallejo REQUEST FOR PROPOSAL WORKERS COMPENSATION CLAIMS AUDIT Date original issued: September 28, 2015 Qualifications Statements due: The City of Vallejo will consider Proposals submitted in response
Illustrative Financial Statements Prepared Using the Financial Reporting Framework for Small- and Medium-Entities
Illustrative Financial Statements Prepared Using the Financial Reporting Framework for Small- and Medium-Entities Illustrative Financial Statements This component of the toolkit contains sample financial
L.A. Tax Service, LLP 8350 MELROSE AVE. 2 ND Fl. #202 LOS ANGELES, CA 90069 TEL: (323) 658-5271 FAX: (323) 658-1114. Client Name: Dear Client,
L.A. Tax Service, LLP 8350 MELROSE AVE. 2 ND Fl. #202 LOS ANGELES, CA 90069 TEL: (323) 658-5271 FAX: (323) 658-1114 L. A. TAX SERVICE, LLP L. A. TAX SERVICE, LLP L. A. TAX SERVICE, LLP Client Name: Dear
CHAPTER 57 WORK IN PROCESS AND CONSTRUCTION IN PROCESS
CHAPTER 57 WORK IN PROCESS AND CONSTRUCTION IN PROCESS A. WORK IN PROCESS 1. Contents of Work In Process. Defense Working Capital Fund (DWCF) activities, primarily those involved in depot maintenance or
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 AMSC Number: D7549 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing
Expert Reference Series of White Papers. Importance of Schedule and Cost Control
Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project
C&I LOAN EVALUATION UNDERWRITING GUIDELINES. A Whitepaper
C&I LOAN EVALUATION & UNDERWRITING A Whitepaper C&I Lending Commercial and Industrial, or C&I Lending, has long been a cornerstone product for many successful banking institutions. Also known as working
IEC Electronics Terms and Conditions
IEC Electronics Terms and Conditions 1. General: This Purchase Order is placed subject to these terms and conditions including those within the Purchase Order. The terms of any proposal referred to in
NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION DIVISION OF ENVIRONMENTAL REMEDIATION
NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION DIVISION OF ENVIRONMENTAL REMEDIATION TECHNICAL ASSISTANCE GRANTS STATE ASSISTANCE CONTRACT RECORD KEEPING AND PAYMENT GUIDE 1.0 ACCOUNTING SYSTEM
TEXAS ASSOCIATION OF REALTORS INDEPENDENT CONTRACTOR AGREEMENT FOR SALES ASSOCIATE. Robyn Jones Homes, LLC
1 TEXAS ASSOCIATION OF REALTORS INDEPENDENT CONTRACTOR AGREEMENT FOR SALES ASSOCIATE USE OF THIS FORM BY PERSONS WHO ARE NOT MEMBERS OF THE TEXAS ASSOCIATION OF REALTORS IS NOT AUTHORIZED Texas Association
Mediation Program A Fast, Easy and Inexpensive Alternative to Litigation
SELLER BUYER INFORMATION PACKET DISPUTE RESOLUTION SYSTEM Mediation Program A Fast, Easy and Inexpensive Alternative to Litigation This mediation concerns property located at: Street Address: City: State:
In this chapter, we build on the basic knowledge of how businesses
03-Seidman.qxd 5/15/04 11:52 AM Page 41 3 An Introduction to Business Financial Statements In this chapter, we build on the basic knowledge of how businesses are financed by looking at how firms organize
Accounting for Manufacturing
Accounting for Manufacturing 1 Accounting for Manufacturing and Inventory Impairments TABLE OF CONTENTS Accounting for manufacturing 2 Production activities 2 Production cost flows 3 Accounting for production
Qcommission Sample Plans Consulting Industry
Introduction Qcommission Sample Plans Consulting Industry Companies and organizations hire consultants to strategize solutions to business, organizational, or industry -specific problems. The value in
Project Cost Management
PDHonline Course P104 (8 PDH) Project Cost Management Instructor: William J. Scott, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org
ISM Online Course Offerings
CERTIFICATION (CPSM and CPSD ) ISM Online Course Offerings 3968 Bridge Review Online Course 21 CEHs This course is designed as a review for current C.P.M. holders as part of their preparation for taking
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
NPSA GENERAL PROVISIONS
NPSA GENERAL PROVISIONS 1. Independent Contractor. A. It is understood and agreed that CONTRACTOR (including CONTRACTOR s employees) is an independent contractor and that no relationship of employer-employee
DEFENSE CONTRACT AUDIT AGENCY
DEFENSE CONTRACT AUDIT AGENCY Fundamental Building Blocks for an Acceptable Accounting System Presented by Sue Reynaga DCAA Branch Manager San Diego Branch Office August 24, 2011 Report Documentation Page
Earned value theory or earned value management
PMI Virtual Library 2010 Francisco-Javier Rodriguez Impact of Revenue Recognition Methods in Project Cost Control Through Earned Value By Francisco-Javier Rodríguez, MBA, PMP Earned value theory or earned
Earned Value Management Guidelines
Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application
How To Account For Construction Contracts In Hong Kong Kongsong Accounting Standard 11
HKAS 11 Issued October 2004Revised March 2010 Hong Kong Accounting Standard 11 Construction Contracts COPYRIGHT Copyright 2011 Hong Kong Institute of Certified Public Accountants This Hong Kong Financial
Independent Contractors. Top 10 Frequently Asked Questions
Independent Contractors Top 10 Frequently Asked Questions For many individuals, self-employment as an independent contractor can be a rewarding and satisfying career option. As is true with any employment
Stanford University Guest Lecturer, Professor s Assistant, 1999-2004 Advanced Construction Issues and Claims, Civil Engineering Department
Current Position PKR CONSULTING, INC. Founder and Chief Executive Officer, 2004 Present Provides construction consulting, dispute resolution and expert witness services to owners, contractors, subcontractors,
DoD Financial Management Regulation Volume 4, Chapter 9 January 1995 ACCOUNTS PAYABLE
CHAPTER 9 0901 GENERAL ACCOUNTS PAYABLE 090101. Purpose. This chapter provides guidance to be followed in recording and liquidating amounts payable by DoD Components. The processes described in this chapter
Make Your Working Capital Work
Make Your Working Capital Work Unlocking the value through improving processes Working capital is the amount of daily operating liquidity available with a firm i.e. for day to day operations of the firm.
Analyzing contract terms: General requirements
Analyzing contract terms: General requirements Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. About Baker Tilly > Established
Overview of Financial Solutions
Overview of Financial Solutions The Etra Advisory Group provides solutions to businesses for growth, expansion, cash flow, refinance and acquisition. We cover the world of business financing that banks
Checklist 26: How Owners Can Avoid Litigation on Construction Projects
Checklist 26: How Owners Can Avoid Litigation on Construction Projects While it is impossible to completely avoid litigation on construction projects, certain steps can be taken to minimize the potential
ComputerEase Top Ten Ways to Increase Cash Flow
TOP TEN WAYS TO INCREASE CASH FLOW Top Ten Ways to Increase Cash Flow Sep 1, 2006 12:00 PM, By David Brown, D. Brown Management ComputerEase Top Ten Ways to Increase Cash Flow Everyone knows cash flow
Review of Consultant/Professional Services Cost Accounts
Review of Consultant/Professional Services Cost Accounts 1 Table of Contents Risk Assessment Research and Planning Entrance Conference Preliminary Analytical Procedures Results from Preliminary Analytical
Preaward and Post Award Accounting System Audits. November 17, 2011 Pikes Peak NCMA Roland Wick
Preaward and Post Award Accounting System Audits November 17, 2011 Pikes Peak NCMA Roland Wick OVERVIEW This presentation will provide: 1. The basic criteria for the Preaward and Post Award accounting
Project Procurement Management
Project Procurement Management Outline Introduction Plan Purchases and Acquisitions Plan Contracting Request Seller Responses Select Sellers Contract Administration Contract Closure Introduction Procurement
Improving Accounts Payable Processes to Deliver Bottom-Line Cost Savings
VISA COMMERCIAL SOLUTIONS visa accounts payable automation white paper Improving Accounts Payable Processes to Deliver Bottom-Line Cost Savings Author: Nick Marchetti, Senior Business Leader, Visa Inc.
AGENDA FOR LUNCH SEMINAR WITH FMI AUGUST 28, 2008 12:30 PM INTRODUCTION TO GOVERNMENT CONTRACTING
AGENDA FOR LUNCH SEMINAR WITH FMI AUGUST 28, 2008 12:30 PM INTRODUCTION TO GOVERNMENT CONTRACTING 1. NICRA - What is a NICRA? - Who has a NICRA? - Do I need a NICRA? - How do I get a NICRA? 2. INDIRECT
DUE DILIGENCE DATA ROOM CHECKLIST
DUE DILIGENCE DATA ROOM CHECKLIST The following pages contain a detailed due diligence checklist that has been compiled from many years of M&A projects. While this is one of the most extensive and comprehensive
Invitation to Tender
Invitation to Tender Provision of Training in Technology Transfer and Related Areas for The Southern Africa Innovation Support Programme 1. Drawing up the tender The tender must be submitted in writing
MANAGEMENT AGREEMENT
Revised 9/19/2013 MANAGEMENT AGREEMENT In consideration of the covenants herein contained (hereinafter called "Owner") and Rudulph Real Estate, Inc. (hereinafter called "Agent"), agree as follows: 1. EMPLOYMENT:
Collaboration Agreement
Collaboration Agreement Effective as of [date] (the Effective Date ), [company], a company with a place of business at [address] ( Company ) and [university name and address] ( University ) agree as follows:
Applicability / Objective
By Rakesh Agarwal Applicability / Objective APPLICABILITY: applicable to all contracts entered into on or after 1-4-2003 and is mandatory in nature from that date. Based on AS 7 (Construction Contracts)
SOUTH CAROLINA. EXCLUSIVE RIGH`T TO REPRESENT BUYER Buyer Agency Agreement [Consult "Guidelines" (Form 201G) for guidance in completing this form]
which _ SOUTH CAROLINA EXCLUSIVE RIGH`T TO REPRESENT BUYER Buyer Agency Agreement [Consult "Guidelines" (Form 201G) for guidance in completing this form] STATE OF NORTH CAROLINA, County of Mecklenburg,
Project: Marion Public Library Drupal 7 Website. Project Proposal Terms and Conditions. Prepared On: March 27, 2013
Project: Marion Public Library Drupal 7 Website Project Proposal Terms and Conditions Prepared On: March 27, 2013 Prepared For: Marion Public Library 1095 6th Ave Marion, IA 52302 Prepared By: Droplet,
Automating payment processes to deliver bottom line cost savings in a weak economy.
VISA COMMERCIAL SOLUTIONS payables automation white paper Automating payment processes to deliver bottom line cost savings in a weak economy. Author: Nicholas Marchetti, Senior Business Leader Commercial
CHAPTER 19. Accounting for Income Taxes 6, 7, 13 2, 3, 4, 5, 6, 7, 9 14, 16, 17, 18,
CHAPTER 19 Accounting for Income Taxes ASSIGNMENT CLASSIFICATION TABLE Topics 1. Reconcile pretax financial income with taxable income. 2. Identify temporary and permanent differences. 3. Determine deferred
Consultancy Services Proposal
Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847
Introduction to SOP. Background. Background. Principles of SOP Act. Objectives of SOP Act
Introduction to SOP Background Building and Construction Industry Security of Payment (SOP) Act Objectives of Act Principles of Act Key Provisions of Act by Lim Jue Meng Jennifer Leong Ng Cher Cheng Feedback
AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME
AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME GUIDANCE NOTES FOR CONTRACTORS AND CERTIFYING ENTITIES MATERIALS PREPARED BY INTERDEPARTMENTAL AUDIT CERTIFICATE WORKING GROUP VERSION 1 APPROVED
COMMERCIAL CREDIT APPLICATION
COMMERCIAL CREDIT APPLICATION Please fill out this form completely so that we may serve you better. Business Name: Phone: : Fax: Sale Pending: Yes No Amount of Sale: Salesperson: Mailing Address: Shipping
Analyzing Cash Flows. April 2013
Analyzing Cash Flows April 2013 Overview Introductions Importance of cash flow in underwriting decisions Key attributes to calculating cash flow Where to obtain information to calculate cash flows Considerations
Revenue from contracts with customers The standard is final A comprehensive look at the new revenue model
Revenue from contracts with customers The standard is final A comprehensive look at the new revenue model No. US2014-01 (supplement) June 11, 2014 What s inside: Overview... 1 Defining the contract...
Appendix B: Work Breakdown Structure (WBS)
: Work Breakdown Structure (WBS) B.1. Introduction The WBS and WBS dictionary are effective management processes for planning, organizing, and administering NASA programs and projects. In accordance with
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program 458 برنامج إدارة العقود الھندسية وعقود التشييد المتكامل معتمد عالميا 10 October
(INSERT NAME OF FIRM)
MASTER AGREEMENT FOR CONSULTING SERVICES (INSERT NAME OF FIRM) THIS AGREEMENT is made and entered into as of the day of by and between South Tahoe Public Utility District, hereinafter referred to as "DISTRICT"
Understanding Financial Statements. For Your Business
Understanding Financial Statements For Your Business Disclaimer The information provided is for informational purposes only, does not constitute legal advice or create an attorney-client relationship,
Agriculture & Business Management Notes...
Agriculture & Business Management Notes... Farm Machinery & Equipment -- Buy, Lease or Custom Hire Quick Notes... Selecting the best method to acquire machinery services presents a complex economic problem.
The Insurance Coverage Law Information Center
The following article is from National Underwriter s latest online resource, FC&S Legal: The Insurance Coverage Law Information Center. The Insurance Coverage Law Information Center LIABILITY CLAIMS COSTS
DEMO Version. Owner and Contractor OCNMP103
Page 1 of 12 AGREEMENT made as of the in the year of (In words, indicate day, month and year) day of BETWEEN the Owner: (Name, address and other information) DEMO Version and the Contractor: (Name, address
SMACNA Participant Workbook Cash Flow. October 2013
SMACNA Participant Workbook Cash Flow October 2013 MANAGING THE LIFEBLOOD OF CONTRACTING CASH FLOW MAXIM CONSUTING GROUP OVERVIEW AGENDA Do you have a cash flow problem? Best Practices that improve cash
Guidelines for Outside Counsel New York University, NYU Langone Medical Center and Affiliates
NEW YORK UNIVERSITY Guidelines for Outside Counsel New York University, NYU Langone Medical Center and Affiliates Purpose and Goals New York University s Senior Vice President and General Counsel, assisted
Two Sample Engagement Letters (with optional notices)
NOTE: This material is intended as only an example which you may use in developing your own form. It is not considered legal advice and as always, you will need to do your own research to make your own
Introducing Project Procurement Management
12 Introducing Project Procurement Management CERTIFICATION OBJECTIVES 12.01 Planning for Purchases 12.02 Completing Procurement Planning 12.03 Examining the Results of Procurement Planning 12.04 Preparing
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. and Rod C. Carter, CCP, PSP Table
1 Supplement: IAS 11 Construction contracts
1 Supplement: IAS 11 Construction contracts Introduction In this section we introduce construction contracts. We will look at the required treatments and disclosures under IAS 11. Make sure that you work