2 Basic Bank Permitting Process Submit Prospectus to IRT. If approved then: Conduct site visit with IRT. If approved then: Develop and submit a Banking Instrument and Restoration Plan to the IRT. If approved then: Record deed restrictions on property. Construct mitigation site. Monitor for 7 years.
3 Monitoring Requirements for Mitigation Sites 7 years of monitoring not all parameters measured yearly Vegetation Hydraulic Stream surveys Photo documentation Baseline conditions (water quality, fish, bugs) Annual reporting Restrictive covenants required
4 Standard Credit Release Schedule Action Percent Release Approval of Banking Instrument 15 Initial In-Stream Modifications 15 Initial Vegetation Restoration/Tree Planting 10 Success Criteria Met Year 1 5 Success Criteria Met Year 2 5 Success Criteria Met Year 3 10 Success Criteria Met Year 4 10 Success Criteria Met Year 5 5 Success Criteria Met Year 6 5 Final Success Criteria Met Year 7 20 TOTAL 100
5 Project Location
6 Bank Summary Bank is located in Dawson County, GA Bank sponsor is Cochrans Creek Partners, LLC Banking instrument approved in April 2008 Restored stream length = 16,000 LF Restored wetland acreage = 12 Acres Stream credits generated ~ 240,000 Current market price ~ $70-$90 per credit
7 Landowner Segments
8 LLC Structure LLC is comprised of four separate landowners. Wildlands negotiated profit sharing of LLC based on estimated pro-rata share of stream credits. Credit totals were estimated per landowner segment based on USACE Savannah District SOP. Process was more about lawyers than about bank height ratios. Business of Banking.
9 Site Overview
10 Riparian Buffer and Bank Erosion
11 Restoration Plan
12 Bank Erosion
13 Service Area
14 Service Areas Based on 8-digit HUC codes. Primary Service Area 8-digit HUC where bank is located. Secondary Service Area 8-digit HUCs adjacent to primary and within the same major river basin. Individual permit applicants must purchase credits within a bank s primary service area. Nationwide permit applicants can purchase credits from a bank s primary or secondary service area.
15 Site Specific Wetland Mitigation
16 Site Specific Wetland Mitigation Restoration 12 acres of ditched and drained wetlands. Wetland mitigation was sold separately for an Individual Permit. Deed recorded as separate parcel from the mitigation bank.
17 Standard Operating Procedures (SOPs) Establish a method for calculating mitigation credits (proposed mitigation) and debits (impacts) Provides predictability and consistency for the development, review and approval of plans.
18 Standard Operating Procedures Calculated using a variety of factors which include: Streams Stream type Priority area Existing condition Duration Dominant impact scaling factor Linear feet of impact Wetlands Dominant effect Duration of effect Existing condition Lost kind Preventability Rarity ranking Impacted area
19 Mitigation Costs Wetlands Purchased From Mitigation Bank Type Of Impact Credits/Acre* Mitigation Cost ** Wetland Fill 9.1 $68,200 Road Crossing 9.1 $68,200 Clearing 7.1 $53,250 *Assumes a riverine pristine wetland ** Assumes $7,500 per wetland credit
20 Mitigation Costs Streams Purchased from Mitigation Bank Type Of Impact Credits/Foot* Mitigation Cost/Foot** Pipe 5.0 $375 Road Crossing 5.0 $375 Clearing 2.0 $150 *Assumes a perennial stream ** Assumes $75 per stream credit
21 Stream Mitigation Credit Comparison Type Of Impact Credits/Foot Mitigation Approach Credits/Foot Pipe 5.0 Road Crossing 5.0 Clearing 2.0 Restoration 15.0 Enhancement 10.0 Preservation 2.0 Average mitigation ratio is approximately 1:3
22 New Mitigation Rule Guidelines If Compensation is Required 1. Mitigation Bank 2. In Lieu-Fees 3. Permittee Responsible Mitigation using a watershed approach 4. Permittee Responsible Mitigation on-site 5. Permittee Responsible Mitigation off-site
23 New Mitigation Rule Requirements 1. Long term maintenance 2. Financial assurances 3. Watershed approach
24 Questions?
The West Virginia Stream and Wetland Valuation Metric
The West Virginia Stream and Wetland Valuation Metric Background As indicated in the U.S. Army Corps of Engineer s (USACE) regulations [33 CFR 332.8(b)], the district engineer will establish an Interagency
Alternative (Flexible) Mitigation Options Proposed Rule - Revised
Alternative (Flexible) Mitigation Options Proposed Rule - Revised NC Association of Environmental Professionals June 9, 2011 Background Purposes Update rules due to required changes from statutes Put all
2008 Compensatory Mitigation Rule: Overview and Highlights. Jenny Thomas U.S. Environmental Protection Agency Wetlands Division July 2014
2008 Compensatory Mitigation Rule: Overview and Highlights Jenny Thomas U.S. Environmental Protection Agency Wetlands Division July 2014 Outline Background Rule goals Rule structure 8 sections Highlight
A Cost Analysis of Stream Compensatory Mitigation Projects in the Southern Appalachian Region 1
A Cost Analysis of Stream Compensatory Mitigation Projects in the Southern Appalachian Region 1 J. Bonham 2 and K. Stephenson Abstract Recently the US Army Corps of Engineers (the Corps) has increased
Chapter 3 SENSITIVE AREAS AND VEGETATED CORRIDORS
Chapter 3 3.01 General Provisions 3.01.1 Introduction 3.01.2 Application and Interpretation of Chapter 3.01.3 Unbuildable Lots 3.01.4 Other Permits 3.01.5 Prohibited Activities 3.02 Service Provider Letter
Ecological Mitigation Strategies
Greg McGowan Director of Ecological Services Types, Risks, and Relative Costs of Ecological Mitigation LFR Inc. www.lfr.com [email protected] 2004 2004 2006 The Road to Success Understand & Quantify
Chagrin River Watershed Partners, Inc. Cost Analysis of Low Impact Development Best Management Practices
Chagrin River Watershed Partners, Inc. Cost Analysis of Low Impact Development Best Management Practices Amy H. Brennan (440) 975-3870 www.crwp.org [email protected] Chagrin River Watershed Partners Formed
Coldwater Heritage Partnership Implementation Grant Final Report Morrison Run Watershed Restoration Project Western Pennsylvania Conservancy Project Summary The goal of the Morrison Run Watershed Restoration
Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed. Summary Report 2002
Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed Summary Report 2002 DOE/BP-00005268-5 November 2002 This Document should be cited as follows: "Restoring Anadromous Fish Habitat in Big Canyon
Upper Des Plaines River & Tributaries, IL & WI Feasibility Study
Upper Des Plaines River & Tributaries, IL & WI Feasibility Study Jeffrey Zuercher Project Manager Chicago District February 19, 2014 Study Partnership: US Army Corps of Engineers Agenda Background Study
Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013.
Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013 Rationale Underground infrastructure may be at risk from valley, streambank
33 CFR PART 332 COMPENSATORY MITIGATION FOR LOSSES OF AQUATIC RESOURCES. Authority: 33 U.S.C. 401 et seq. ; 33 U.S.C. 1344; and Pub. L. 108 136.
33 CFR PART 332 COMPENSATORY MITIGATION FOR LOSSES OF AQUATIC RESOURCES Authority: 33 U.S.C. 401 et seq. ; 33 U.S.C. 1344; and Pub. L. 108 136. Source: 73 FR 19670, Apr. 10, 2008, unless otherwise noted.
1.7.0 Floodplain Modification Criteria
1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:
Leveraging Ohio s Clean Water SRF Program to Fund Stream and Wetland Restoration and Protection Projects
Leveraging Ohio s Clean Water SRF Program to Fund Stream and Wetland Restoration and Protection Projects Association of State Wetland Managers 2014 State/Tribal/Federal Coordination Meeting Shepherdstown,
Emergency Streambank Restoration/Stabilization. Kentucky Division of Water Water Quality Certification May 2010 Educational Assistance
Emergency Streambank Restoration/Stabilization Kentucky Division of Water Water Quality Certification May 2010 Educational Assistance Due to the severity of the recent rains and flooding occurrences, the
Urban Stream Restoration Defining the Full Benefits of a Project. Warren C. High MACTEC Engineering and Consulting
Urban Stream Restoration Defining the Full Benefits of a Project Warren C. High MACTEC Engineering and Consulting Economics in the Decision Process Return on Investment Willingness to Pay Municipal Growth
MULTI-AGENCY COMPENSATORY MITIGATION PLAN CHECKLIST 1
MULTI-AGENCY COMPENSATORY MITIGATION PLAN CHECKLIST 1 Mitigation Goals and Objectives o Describe functions lost at impact site o Describe functions to be gained at mitigation site o Describe overall watershed
Conservation Tax Credit Regulations Chapter 391-1-6 A-1 RULES OF GEORGIA DEPARTMENT OF NATURAL RESOURCES CHAPTER 391-1-6
Conservation Tax Credit Regulations Chapter 391-1-6 A-1 RULES OF GEORGIA DEPARTMENT OF NATURAL RESOURCES CHAPTER 391-1-6 GEORGIA CONSERVATION TAX CREDIT PROGRAM TABLE OF CONTENTS 391-1-6-.01 Purpose and
INNOVATION IN FLOW RESTORATION AND WATER BANKING CASE STUDY: DUNGENESS WATER EXCHANGE
INNOVATION IN FLOW RESTORATION AND WATER BANKING CASE STUDY: DUNGENESS WATER EXCHANGE Amanda Cronin Washington Water Trust AWRA- Washington State Conference September 26, 2013 WASHINGTON WATER TRUST Washington
LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN
1 AUGUST 2011 LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN KEY ELEMENTS OF THE PLAN: 1. Replace the existing unsafe Ragged Mountain dam with a new dam and raise the reservoir pool level initially
3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN
3.4 DRAINAGE PLAN This section describes the existing onsite drainage characteristics and improvements proposed within this Specific Plan. Following this description, drainage plan development standards
Appendix A. Lists of Accomplishments and Project Costs. UMRWD 10 Year Plan Update. Appendix A UPPER MINNESOTA RIVER WATERSHED DISTRICT
UPPER MINNESOTA RIVER WATERSHED DISTRICT Lists of Accomplishments and Project Costs 10 Year Plan Update UMRWD 10 Year Plan Update Page A 1 UMRWD LIST OF ACCOMPLISHMENTS Since its inception in 1967, the
5.14 Floodplains and Drainage/Hydrology
I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA April 17, 2013 Goal To develop a basic understanding of PA Department of Environmental Protection (DEP) and US Army Corps of Engineers
PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY
PIPELINE ROUTING PERMIT For A NATURAL GAS PIPELINE IN DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PUC DOCKET No. G002/GP-05-1706 In accordance with the requirements
How To Amend A Stormwater Ordinance
Regulatory Alternatives to Address Stormwater Management and Flooding in the Marlboro Street Study Area Alternative 1: Amend Existing Local Regulations This proposed alternative provides an incremental
Prepared By: Eric Chamberlain
Prepared By: Eric Chamberlain Drainage 101 So, What s a Municipal Drain??? It is a Drainage System either open ditch or enclosed pipe system or any other water control structure Petitioned for by landowners
Chapter 22A Forest Conservation Law
Chapter 22A Forest Conservation Law 2014 1 Table of Contents Table of Contents Article I - General... 4 Sec. 22A-1. Short title... 4 Sec. 22A-2. Findings and purpose... 4 Sec. 22A-3. Definitions... 4 Sec.
Sims Bayou Federal Flood Damage Reduction Project
Sims Bayou Federal Flood Damage Reduction Project A. Gene Rushing, Jr., P.E., PMP HCFCD Project Manager January 15, 2014 Harris County s Watersheds Historical Flooding in Harris County 1929 1935 HCFCD
Saving Constituents Money on Flood Insurance Under FEMA s Community Rating System (CRS)
Saving Constituents Money on Flood Insurance Under FEMA s Community Rating System (CRS) Today s Discussion 1. FEMA s Flood Insurance Program: A Brief Overview 2. Flood Insurance Rates: Are they rising?
IMPROVING SOUTH FORK PEACHTREE CREEK WATERSHED USING THE TRIPLE BOTTOM LINE DEKALB COUNTY, GEORGIA
IMPROVING SOUTH FORK PEACHTREE CREEK WATERSHED USING THE TRIPLE BOTTOM LINE DEKALB COUNTY, GEORGIA David Chastant AUTHORS:DeKalb County, 330 West Ponce De Leon Ave, Decatur, Georgia 30030 REFERENCE:Proceedings
Carlton Fields Memorandum
Carlton Fields Memorandum TO: FROM: RE: DAN WEEDE FRED RUSHING RIPARIAN BUFFER DATE: JULY 26, 2013 BACKGROUND Both the state of Georgia and the city of Atlanta 1 have certain guidelines that must be followed
Chehalis River Basin Flood Damage Reduction 2013-2015 Capital Budget Approved by Legislature in June 2013
Chehalis River Basin Flood Damage Reduction 2013-2015 Capital Budget Approved by Legislature in June 2013 1. Design alternatives for large capital flood projects (basinlevel water retention and Interstate
A Developer s Guide: Watershed-Wise Development
A Developer s Guide: Watershed-Wise Development Environmental Protection What is a watershed? It does not matter how far away you build from a creek, lake, or the ocean, you are in a watershed. Another
Rhode Island NRCS received approximately $2.4 million in ARRA funds to implement four floodplain easement projects.
American Recovery and Reinvestment Act (ARRA) Emergency Watershed Protection Program Floodplain Easements Rhode Island Natural Resources Conservation Service Rhode Island NRCS received approximately $2.4
WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE
WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE May 24, 2005 Table of Contents Introduction...3 Definitions...3 Types of Wetland Restorations...4 Re-Contouring...4 Engineered...4 Water
Clean Water Services. Ecosystems Services Case Study: Tualatin River, Washington
Viewed broadly, the concept of ecosystem services describes the many resources and services provided by nature. Typically, traditional planning and development practices do not adequately represent the
Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
HCP Team Meeting. November 18, 2015. icfi.com
HCP Team Meeting November 18, 2015 icfi.com 1 Welcome and Introductions Where are we in the HCP process Hydrology modeling update Native fish survey Fish translocation Finalize covered activities Next
RE: Docket # COE 2010 0035; ZRIN 0710 ZA05 Submitted via email to [email protected] and Rulemaking Portal at www.regulations.gov.
April 18, 2011 U.S. Army Corps of Engineers Attn: CECW CO R 441 G Street, N.W. Washington, DC 20314 1000 RE: Docket # COE 2010 0035; ZRIN 0710 ZA05 Submitted via email to [email protected] and Rulemaking
Remaining Wetland Acreage 1,500,000 915,960 584,040-39%
NEW JERSEY Original Wetland Acreage Remaining Wetland Acreage Acreage Lost % Lost 1,500,000 915,960 584,040-39% New Jersey Wetlands: Nearly 99 percent of New Jersey s wetlands are palustrine or estuarine.
The Teton Creek Restoration Project Summary:
The Teton Creek Restoration Project Summary: The Teton Creek Restoration Project area extends for approximately one mile upstream from the Cemetery Road Bridge and includes the Aspen Pointe, The Aspens
A. Describe the existing drainage patterns on-site as shown on Map I, including any potential flooding and erosion problems.
19. STORMWATER MANAGEMENT A. Describe the existing drainage patterns on-site as shown on Map I, including any potential flooding and erosion problems. The majority of the approximately ±500 acre Property
United States Depmiment of the Interior Bureau of Reclamation Western Colorado Area Office Grand Junction, Colorado
WCAO-GJ-FONSI -14-01 United States Depmiment of the Interior Bureau of Reclamation Western Colorado Area Office Grand Junction, Colorado FINDING OF NO SIGNIFICANT IMPACT SPURLIN MESA LATERAL OF THE CRAWFORD
The History and Status of Wetland Mitigation Banking and Water Quality Trading
The History and Status of Wetland Mitigation Banking and Water Quality Trading Palmer Hough and Lynda Hall U.S. EPA Office of Wetlands, Oceans & Watersheds Overview Part I: Mitigation Banking Part II:
Conservation Banking Incentives for Stewardship
Conservation Banking Incentives for Stewardship Ecological Services Office Jacksonville, Florida Erin Gawera 904-731-3121 [email protected] What is a Conservation Bank? Conservation Banks are permanently
Water Quality and Water Usage Surveys
Appendix 1 Water Quality and Water Usage Surveys This appendix contains copies of the Water Quality Survey and the Lake Usage Survey that we used to complete the watershedbased community assessments. We
DECISION DOCUMENT NATIONWIDE PERMIT 27
DECISION DOCUMENT NATIONWIDE PERMIT 27 This document discusses the factors considered by the Corps of Engineers (Corps) during the issuance process for this Nationwide Permit (NWP). This document contains:
THE DUNGENESS WATER EXCHANGE. Washington Water Trust March 13, 2013 Sequim Realtors
THE DUNGENESS WATER EXCHANGE Washington Water Trust March 13, 2013 Sequim Realtors PRESENTATION OVERVIEW Who is the Washington Water Trust? What is the Dungeness Water Exchange? How does the Exchange provide
SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST
This checklist may be used by applicants for encroachment permits, and contractors in development of Site- Specific BMP Plans for projects. plan reviewers will use this checklist to review the Site-Specific
Section 4 General Strategies and Tools
Section 4 General Strategies and Tools Key planning issues for WRIA 35 have been identified in Sections 5 and 6 in the areas of water supply, instream flow, water quality, and aquatic habitat. General
Series 2016A-2 (Green Bonds) Final Proceeds Allocation April 2016
Series 2016A-2 (Green Bonds) Final Proceeds Allocation April 2016 James L. McIntire Washington State Treasurer Summary The State of Washington offered green bonds to investors in September 2015, with approximately
Lower Raritan Watershed Management Area Stormwater & Flooding Subcommittee Strategy Worksheet LRSW-S3C1
Strategy Name: Reduce Existing Potential for Flood Damages LRSW-S3C1. Develop and implement a program to: Minimize flood damages through the use of structural measures. Minimize flood damages through the
- POLICY - Disaster Recovery Assistance Program
August 29, 2013 - POLICY - Disaster Recovery Assistance Program Overview Disasters and emergency legislative funding occur frequently and usually unpredictably. These characteristics require a standard
ANGORA FIRE RESTORATION PROJECT
ANGORA FIRE RESTORATION PROJECT U.S. Forest Service LAKE TAHOE BASIN MANAGEMENT UNIT Duncan Leao Vegetation Management Planner Richard Vacirca Forest Aquatics Biologist 3 PHASES OF FIRE REHAB Phase I Rehab:
State of New Jersey Approved Wetlands Mitigation Banks
State of New Jersey Approved Wetlands Mitigation Banks as of 4/27/15 The table below lists each Watershed Management Area (WMA) HUC 8 with its corresponding mitigation bank(s). To receive more information
Section 19. Basin-wide Mitigation Action Plans
Section 19. Basin-wide Mitigation Action Plans This Mitigation Plan identifies twelve specific hazards that could affect the Basin. Section 20 of this Plan set forth mitigation action plans to be carried
CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE
1008 STORM DRAINAGE (3/24/05) 1008.01 PURPOSE To minimize the amount of stormwater runoff resulting from development utilizing nonstructural controls where possible, maintain and improve water quality,
Wildlife Habitat Conservation and Management Program
Wildlife Habitat Conservation and Management Program Manual for Counties and Cities Oregon Department of Fish and Wildlife 2015 Table of Contents 1. Introduction Purpose of the habitat program Objective
King County, Washington Policies and Practice for the Use of Eminent Domain For Flood Risk Reduction
King County, Washington Policies and Practice for the Use of Eminent Domain For Flood Risk Reduction Introduction Eminent domain refers to the power possessed by the state over all property within the
Mission Canyon Residential Design Guidelines Workshop. Table Focus: Environmental Issues and Concerns
Mission Canyon Residential Design Guidelines Workshop Table Focus: Environmental Issues and Concerns Grading How is Grading Regulated in Santa Barbara County? The technical aspects of grading are regulated
Multi-purpose Drainage Management (MDM) Plans
Multi-purpose Drainage Management (MDM) Plans August 13, 2015 Chuck Brandel, PE Civil Engineer, ISG Joe Mutschler, PE Faribault County SWCD AGENDA 1. Multi-purpose Drainage Management (MDM) Plans 2. Examples
FLOOD PROTECTION BENEFITS
IV. (340 points) Flood Protection Benefits A. Existing and potential urban development in the floodplain (50) 1. Describe the existing and potential urban development at the site and the nature of the
PUBLIC NOTICE Application for Permit
PUBLIC NOTICE Application for Permit 30-Day Notice Issue Date: June 20, 2016 Expiration Date: July 20, 2016 US Army Corps of Engineers No: NWP-2010-535 Oregon Department of State Lands No: 58311-RF Interested
Chapter 9. Selected Watershed Initiatives in the Great Basin Region
Chapter 9 Selected Watershed Initiatives in the Great Basin Region The Great Basin contains vast areas of sparsely populated desert lands. Lacking an ocean drainage, the Great Basin is a hydrologic sink
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Elba Liquefaction Company, L.L.C. Southern LNG Company, L.L.C. Elba Express Company, L.L.C. Docket No. PF13-3-000 NOTICE OF INTENT TO PREPARE
U.S. ARMY CORPS OF ENGINEERS, SAVANNAH DISTRICT MODEL DECLARATION OF CONSERVATION COVENANTS AND RESTRICTIONS
Updated October 2013 U.S. ARMY CORPS OF ENGINEERS, SAVANNAH DISTRICT MODEL DECLARATION OF CONSERVATION COVENANTS AND RESTRICTIONS The following Model Declaration of Conservation Covenants and Restrictions
SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST
This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)
General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title]
General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title] Purpose These rules set forth the conditions under which a person may, without an individual removal-fill permit
Environmental Case Study Decatur, Georgia, DeKalb County A Suburban Creek Resists Channelization
Introduction A visual examination of Doolittle Creek in a highly developed suburban county in Georgia yielded telltale signs of a creek whose original streambed had been altered. Examination of official
Green Infrastructure Maintenance Management at MSDGC. Leslie Schehl, PE, MBA, PMP June 24, 2015
Green Infrastructure Maintenance Management at MSDGC Leslie Schehl, PE, MBA, PMP June 24, 2015 Presentation Overview Background Asset List SCM and the Asset Management Lifecycle Accomplishments To Do List
Executive Summary Minnesota Nutrient Reduction Strategy
Executive Summary The (NRS) will guide the state in reducing excess nutrients in waters so that in-state and downstream water quality goals are ultimately met. Nutrient impacts are widespread. Excessive
Green Spaces to Improve Waterways and Communities
Green Spaces to Improve Waterways and Communities Thomas M. Evans, ASLA LEED AP Green Infrastructure Design Services Director Cleveland, Ohio Northern Michigan Green Infrastructure Conference June 4, 2015
Michigan Wetlands. Department of Environmental Quality
Department of Environmental Quality Wetlands are a significant component of Michigan s landscape, covering roughly 5.5 million acres, or 15 percent of the land area of the state. This represents about
Tres Rios del Norte Feasibility Study
Tres Rios del Norte Feasibility Study Santa Cruz River Pima County, Arizona February 2011 Study Area: 18 Miles of Santa Cruz River (Prince to Sanders), portions of City of Tucson, Town of Marana, and unincorporated
Final Report. Dixie Creek Restoration Project. Funded by Plumas Watershed Forum
Final Report Dixie Creek Restoration Project Funded by Plumas Watershed Forum Plumas Corporation January 2009 1 Background FR-CRM staff presented this project to the Dixie Valley Landowners Association
Stream Buffer Variance Application Stream Buffer Protection Ordinance
Report Stream Buffer Variance Application Stream Buffer Protection Ordinance Prepared for Gwinnett County Department of Planning & Development 75 Langley Drive Lawrenceville, GA 30045 August 2005 Prepared
Weed Survey and Mapping
Weed Survey and Mapping The primary objective of weed surveying and mapping is to accurately identify and delineate land with populations of invasive plants or noxious weeds. These surveys allow land managers
FILING REQUIREMENTS EXCERPTS FROM THE ZONING ORDINANCE SOLAR ENERGY SYSTEMS
County of San Diego, Planning & Development Services APPLICANT S GUIDE FOR A SOLAR ENERGY SYSTEM ZONING DIVISION These guidelines provide information on how to apply for a Solar Energy System. Review the