FILING REQUIREMENTS EXCERPTS FROM THE ZONING ORDINANCE SOLAR ENERGY SYSTEMS
|
|
|
- Norah Fowler
- 10 years ago
- Views:
Transcription
1 County of San Diego, Planning & Development Services APPLICANT S GUIDE FOR A SOLAR ENERGY SYSTEM ZONING DIVISION These guidelines provide information on how to apply for a Solar Energy System. Review the attached Zoning Ordinance excerpts to determine where and under what restrictions this use is allowed. Please be sure to read ALL of the information in this Guide and application package forms. OPTIONAL: Contact Planning & Development Services (PDS) to set-up a pre-application meeting to determine the processing requirements and to discuss project specifics with various departments prior to formally submitting an application. To schedule a pre-application meeting, contact PDS Zoning at (858) Note: There is a fee for a pre-application meeting. FILING REQUIREMENTS Photovoltaic Solar Energy Systems for Onsite Use: Allowed as an accessory use in all zones upon approval of a building permit unless the property is subject to a Special Area Designator or is governed by a Discretionary Permit. (Please refer to Page 5) Photovoltaic Solar Energy Systems for Offsite Use (project area less than 10 acres): Allowed in all zones upon approval of an Administrative Permit Photovoltaic Solar Energy Systems for Offsite Use (project area 10 acres or more): Allowed in all zones upon approval of a Major Use Permit Solar Energy Systems for Offsite Use: Allowed in all zones as Major Impact Service and Utility upon approval of a Major Use Permit. Please refer to the Administrative Permit or Major Use Permit cover sheets for information on the application filing requirements for a Solar Energy System. Please follow link: /zoning/zoningpermits.html Section 1110: DEFINITIONS EXCERPTS FROM THE ZONING ORDINANCE SOLAR ENERGY SYSTEMS Photovoltaic Solar Energy System: A type of solar energy system that converts solar energy into a usable form of electricity using Photovoltaic Solar Cells. Solar Energy System, Onsite Use: A solar energy conversion system consistent with the requirements of section 6954 for onsite energy use. The energy generated is predominately used onsite. Solar Energy System, Offsite Use: A solar energy conversion system consistent with the requirements of section 6954 for offsite energy use. The energy generated is predominately used offsite. Section 6954(a): SOLAR ENERGY SYSTEMS, ONSITE USE 1. A photovoltaic solar energy system for onsite use shall be allowed as an accessory use to all Agricultural, Civic, Commercial, Industrial and Residential use types in all zones in accordance with the following requirements: PDS-316 (Rev. 11/2014) PAGE 1 of 5
2 i. Setback. A System shall meet all of the main building setback requirements of the zone or comply with Section 4835.f. (See Page 4 for Height and Setback Requirements) ii. iii. iv. Height. A System shall meet the height limit of the height designator of the zone, except when allowed to extend not more than 5 feet above the highest point of the roof, in accordance with Section 4620.i. Solar Panel Description. The panel manufacturer and model shall be specified as part of the building permit. Special Area Regulations: Photovoltaic solar energy systems for onsite use subject to a Special Area Designator must comply with the applicable Special Area Regulations provisions of Sections 5000 through Section 6954(b)(1): PHOTOVOLTAIC SOLAR ENERGY SYSTEMS, OFFSITE USE ADMINISTRATIVE PERMIT PROCESS AND REQUIRED FINDINGS 1. A photovoltaic solar energy system for offsite use with a project area of less than 10 acres shall be allowed with an Administrative Permit in all zones in accordance with the Administrative Permit Procedure commencing at Section The following findings must be made prior to approval of an Administrative Permit: (a.) That the location, size, design, and operating characteristics of the proposed use will be compatible with adjacent uses, residents, buildings, or structures, with consideration given to: i. Harmony in scale, bulk, coverage and density; ii. The availability of public facilities, services and utilities; iii. The harmful effect, if any, upon desirable neighborhood character; iv. The generation of traffic and the capacity and physical character of surrounding streets; v. The suitability of the site for the type and intensity of use or development which is proposed; and to vi. Any other relevant impact of the proposed use; and (b.) (c.) (d.) That the impacts, as described in paragraph "b.1.(a.)" of this section, and the location of the proposed use will be consistent with the San Diego County General Plan; and That the requirements of the California Environmental Quality Act have been complied with; and That the applicant has provided the County with an owner consent letter demonstrating to the satisfaction of the Director that the operator of the Solar Energy System is authorized to use the property for a Solar Energy System, unless the operator owns the land upon which the Solar Energy System will be located. Section 6954(b)(2): PHOTOVOLTAIC SOLAR ENERGY SYSTEMS, OFFSITE USE MAJOR USE PERMIT PROCESS AND REQUIRED FINDINGS 2. A photovoltaic solar energy system for offsite use with a project area of 10 acres or more, or a combination of parcels with a combined area of 10 acres or more is a Major Impact Service and PDS-316 (Rev. 11/2014) PAGE 2 of 5
3 Utility in all zones and shall require a Major Use Permit permitted in accordance with the use permit procedure commencing at section Section 6954(b)(3): SOLAR ENERGY SYSTEMS, OFFSITE USE MAJOR USE PERMIT PROCESS AND REQUIRED FINDINGS 3. All other types of a solar energy systems or solar power plants including concentrating solar power plants, parabolic troughs, concentrating linear fresnel reflectors, stirling solar dish, or a solar power tower are a Major Impact Service and Utility in all zones and shall require approval of a Major Use Permit in accordance with section 7350 and the following requirements on any parcel of land: (a.) (b.) (c.) Setback. A system or plant shall meet all of the setback requirements of the zone. (See Page 4 for Height and Setback Requirements) Height. A system or plant of more than 200 feet in height is required to comply with Federal Aviation Administration safety height requirements. Visual. The following measures shall be followed in order to minimize the visual impact of the project: i. Removal of existing vegetation shall be minimized. ii. iii. iv. Internal roads shall be graded for minimal size and disruption. Any accessory buildings shall be painted or otherwise visually treated to blend with the surroundings. A structure shall be non-reflective in all areas possible to blend with the surroundings. (d.) Security. The operator shall provide a security in the form and amount determined by the Director to ensure removal of the Solar Energy System. The security shall be provided to PDS prior to building permit issuance. Once the Solar Energy System has been removed from the property pursuant to a demolition permit to the satisfaction of the Director, the security may be released to the operator of the Solar Energy System. HEIGHT AND SETBACK REQUIREMENTS Front Yard Setback: Interior Side Exterior Side Permitted but shall not exceed 30 inches above grade and must maintain 3 foot setback from property line. Permitted but shall not exceed 12 feet in height and must maintain 3 foot setback from property line. Permitted but shall not exceed 30 inches above grade and must maintain 3 foot setback from property line. Rear Permitted but shall not exceed 12 feet in height and must maintain 3 foot setback from property line. Solar Panels shall not cover more than 50 percent of the required yard in combination with all structures in the rear yard setback. PDS-316 (Rev. 11/2014) PAGE 3 of 5
4 Main Building Envelope: Roof Mounted Panels on Main Building: Roof Mounted Panels within Interior Side/ Rear Permitted but shall not exceed the allowed maximum height by the height designator. Permitted but shall not extend more than 5 feet above the highest point of the roof. (Section 4620.i) Permitted but shall not exceed 12 feet in total height (accessory building including solar panels). (Section 4835.f) MISC. INFORMATION Building Permit: Building Permits will be required to ensure that all solar energy systems meet current Uniform Building Code. Applicants should contact PDS Building at (858) or toll-free at (888) for Code standards and requirements. Department of Environmental Health If a proposed solar energy system is proposed to be sited near a septic system or is proposed to use a well for water, please contact the Department of Environmental Health (DEH) to identify DEH requirements. Special Area Designator If the project site contains a Special Area Designator (J, B, D, or S) and has no approved Site Plan or Use Permit, a waiver of the Site Plan review requirements may be required prior to the issuance of a building permit for a solar energy system or a Site Plan would be required. FOR PROJECTS REQUIRING A DISCRETIONARY PERMIT: Environmental Review: The deposit collected for the environmental review portion of the application covers review of an Application for an Environmental Initial Study (AEIS) for compliance with the California Environmental Quality Act (CEQA). If any environmental issues are identified or an additional study is needed after the initial review by PDS staff, the applicant may need to submit additional forms/studies and an additional deposit. Service Availability Letters To show that there are adequate public facilities to serve the Solar Energy System, the applicant must include Service Availability Letter from the fire district (PDS-399F), water district (PDS-399W), and sewer district (PDS-399S) if the project will be served by a public sewer district. The applicant completes the top of the form and then has the service agency complete the bottom portion. Once the forms are completed by the service agency, they should be submitted with the remainder of the application. Please PDS-316 (Rev. 11/2014) PAGE 4 of 5
5 be aware that service agencies may have requirements and improvements that need to be met and completed before the Solar Energy System can open for business. Stormwater Regulations Applicants for Solar Energy Systems do have to prepare a Stormwater Management Plan as part of the Administrative and Major Use Permit process, and please be aware that operation of a solar energy system must comply with all applicable stormwater regulations at all times. In addition, building permit plans must demonstrate how stormwater regulations will be met. The activities at a solar energy system are subject to enforcement under permits from the San Diego Regional Water Quality Control Board (RWQCB) and the County of San Diego Watershed Protection, Stormwater Management, and Discharge Control Ordinance (Ordinance No. 9926) and all other applicable ordinances and standards. This includes requirements for Low Impact Development (LID) /docs/lid- Handbook.pdf materials and wastes control, erosion control, and sediment control on the project site. Projects that involve areas greater than one acre require that the property owner keep additional and updated information on-site concerning stormwater runoff. Previously Approved Discretionary Projects If the subject parcel has an approved discretionary permit, then any proposed solar energy system shall be in compliance with that particular discretionary permit. A County of San Diego Planner shall verify that the proposed project is consistent with the approved plot plan and that all pre-building permit conditions of the approved discretionary permit have been satisfied. PDS-316 (Rev. 11/2014) PAGE 5 of 5
County of San Diego, Planning & Development Services SECOND DWELLING UNIT
County of San Diego, Planning & Development Services ZONING DIVISION The Zoning Ordinance, Section 6156.x, allows the addition of a second dwelling unit to those properties zoned to allow the Family Residential
SOLAR ENERGY FACILITIES ZONING AMENDMENTS
SOLAR ENERGY FACILITIES ZONING AMENDMENTS 1. In Section 10, Special Regulations, of the Zoning Bylaw, insert a new Section 10.06, to be entitled Solar Energy Facilities and to read as follows: SECTION
VILLAGE OF PLEASANT PRAIRIE COMMERCIAL COMMUNICATION PERMIT
VILLAGE OF PLEASANT PRAIRIE COMMERCIAL COMMUNICATION PERMIT CLASS 1 COLLOCATION New Commercial Communication Structure Substantial Modification Please check one of the following: CLASS 2 COLLOCATION OTHER
December 2014. 1.0 Purpose
Model As-of-Right Zoning Bylaw: Allowing Use of Large-Scale Ground-Mounted Solar Photovoltaic Installations Prepared by: Department of Energy Resources Massachusetts Executive Office of Environmental Affairs
d. Building permits may only be approved if consistent with the approved development plan and land division for all units with common walls.
Section 20.920.060 Tier 2 Infill Standards. In addition to the Tier 1 standards and incentives, Tier 2 infill parcels and land divisions and the subsequent development on those Tier 2 infill parcels shall
Answers to Commonly Asked Questions
County of San Diego, Planning & Development Services FIRESTORM POLICY AND GUIDANCE DOCUMENT BUILDING DIVISION Answers to Commonly Asked Questions The County of San Diego understands the confusion and frustration
CHAPTER 23 Wireless Communication Facilities
CHAPTER 23 Wireless Communication Facilities Section 23.1 Purpose It is the general purpose and intent of this Section to comply with the requirements of the Federal Telecommunications Act of 1996, as
9. Does the County of San Diego keep home plans on file for existing homes?
County of San Diego, Planning & Development Services FIRESTORM POLICY DOCUMENT BUILDING DIVISION FIRE REBUILD Answers to Commonly Asked Questions The County of San Diego understands the confusion and frustration
Edgecombe County Solar Energy Development Ordinance
1. Purpose The purpose of this ordinance is to facilitate the construction, installation, and operation of Solar Energy Systems (SESs) in Edgecombe County in a manner that promotes economic development
Residential Accessory Buildings
City of Republic Residential Accessory Buildings REVISION DATE: FEBRUARY 2012 Buildings less than 120 square feet (120 sq. ft.) do not require a building permit unless they: are built on a permanent concrete
INTRODUCTION TO ZONING DISTRICT REGULATIONS
INTRODUCTION TO ZONING DISTRICT REGULATIONS Classification of Zoning Districts Zoning districts in Dorchester County are categorized as Suburban Urban, Suburban Transition, or Rural. These districts are
TOWN OF MONSON CERTIFICATIONS-SPECIAL TOWN MEETING MAY 11, 2015
TOWN OF MONSON CERTIFICATIONS-SPECIAL TOWN MEETING MAY 11, 2015 ARTICLE 8: The Town voted by 2/3 vote to amend its Zoning Bylaws by deleting the current Section 6.14 Wireless Communications Facilities
DATE STAMP RECEIVED BY OFFICE OF PLANNING
Applicants must appear in person to file an application. Applications by mail or courier will not be accepted. APPLICATION FOR A SPECIAL ADMINISTRATIVE PERMIT (SAP) File No.: FOR CELL TOWERS (new or increase
BOROUGH OF OAKLAND COUNTY OF BERGEN STATE OF NEW JERSEY ORDINANCE 13-CODE-685
BOROUGH OF OAKLAND COUNTY OF BERGEN STATE OF NEW JERSEY ORDINANCE 13-CODE-685 AN ORDINANCE TO AMEND, SUPPLEMENT AND REVISE THE CODE OF THE BOROUGH OF OAKLAND, LAND USE, CHAPTER 59 ENTITLED LAND USE AND
PLANNED DEVELOPMENT PERMIT
FILE NO. LOCATION OF PROPERTY ZONING DISTRICT ZONING FILE NUMBER GENERAL PLAN DESIGNATION PROPOSED USE PLANNED DEVELOPMENT PERMIT PDA05-095-01 Southwest corner of Silver Creek Valley Road and Silver Creek
How To Amend A Stormwater Ordinance
Regulatory Alternatives to Address Stormwater Management and Flooding in the Marlboro Street Study Area Alternative 1: Amend Existing Local Regulations This proposed alternative provides an incremental
Division 51-4.400. Yard, Lot, and Space Regulations.
Division 51-4.400. Yard, Lot, and Space Regulations. SEC. 51-4.401. MINIMUM FRONT YARD. (a) General provisions. (1) Required front yards must be open and unobstructed except for fences. Except as otherwise
Definition of Tower from the Bradley County Zoning Resolution
Definition of Tower from the Bradley County Zoning Resolution 43. TOWER. Any outdoor structure designed and constructed to support one (1) or more transmitting or receiving devices for telephone, radio
BLOCK 400 PLANNED COMMUNITY DISTRICT
BLOCK 400 PLANNED COMMUNITY DISTRICT Newport Center December 1983 Newport Beach, California Ordinance 88-119 Adopted December 12, 1988 Amendment No. 672 Resolution No. 95-115 Adopted October 9, 1995 Amendment
HIGHLIGHTS: Heights in Residential Zoning Districts
HIGHLIGHTS: Heights in Residential Zoning Districts Charlotte-Mecklenburg Planning Commission March 7, 2011 PROJECT BACKGROUND 1. A rezoning petition (#2008-32) was initiated by the Myers Park Neighborhood
BOARD OF ADJUSTMENT STAFF REPORT. BOA File No. 3786 1515 West Avenue- Multifamily Building
MIAMI BEACH PLANNING DEPARTMENT FROM: DATE: RE: BOARD OF ADJUSTMENT STAFF REPORT Thomas R. Mooney, AIC~ Planning Director December 4, 2015 Meeting BOA File No. 3786 1515 West Avenue- Multifamily Building
DELAWARE TOWNSHIP ORDINANCE #2011-06LU
DELAWARE TOWNSHIP ORDINANCE #2011-06LU AN ORDINANCE SUPPLEMENTING AND AMENDING THE LAND USE ORDINANCE OF THE TOWNSHIP OF DELAWARE BY PERMITTING SOLAR ENERGY SYSTEMS. #2011-06LU WHEREAS, it is the purpose
HARDWICK TOWNSHIP WARREN COUNTY, NEW JERSEY
HARDWICK TOWNSHIP WARREN COUNTY, NEW JERSEY AN ORDINANCE TO AMEND CHAPTER XIII OF THE REVISED GENERAL ORDINANCES BEING THE LAND DEVELOPMENT ORDINANCE OF THE TOWNSHIP OF HARDWICK TOWNSHIP IN ORDER TO ADOPT
City Code of ANN ARBOR, MICHIGAN Chapter 55 Zoning
ARTICLE II. USE REGULATIONS 5:10.2. R1A, R1B, R1C, R1D single family dwelling district (1) Intent. (a) These single family residential districts are designed to provide an environment of predominantly
Industrial Suburban District Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations
16.20.110 - Industrial Suburban District ( IS ) Figure REFERENCE Typical Buildings in the IS District Figure REFERENCE Site Plan of a typical development in the IS District Sections: 16.20.110.1 Composition
Planning and Zoning Commission Johnston, Iowa June 29, 2015
ITEM NO. 15-19 Planning and Zoning Commission Johnston, Iowa June 29, 2015 SUBJECT: Consider recommending approval of the Final Plat for Crosshaven Plat 6 subdividing 28.28 acres into 47 single family
Sec. 44-615. Home occupation.
Sec. 44-615. Home occupation. Purpose: A home occupation may be located in any residential district, recognizing that certain residential and nonresidential uses can co-exist in the same structure. It
Chapter 7 ZONING PLAN
Chapter 7 ZONING PLAN Introduction This Chapter opens with a general description of a zoning plan. It is followed by a brief explanation of the relationship between this Growth Management Plan and the
3.1.8 Utilities and Service Systems
3.1.8 Utilities and Service Systems This section discusses potential impacts to utilities and service systems, including water, wastewater, and solid waste hauling and disposal, resulting from the implementation
Michael & Christina Harland (PLN020078)
LYNNE MOUNDAY ZONING ADMINISTRATOR COUNTY OF MONTEREY STATE OF CALIFORNIA RESOLUTION NO. 020078 A. P. # 009-451-011-000 In the matter of the application of Michael & Christina Harland (PLN020078) FINDINGS
2 February 12, 2014 Public Hearing
2 February 12, 2014 Public Hearing APPLICANT & PROPERTY OWNER: MATTHEW ALVES REQUEST: Conditional Use Permit (Home Occupation / firearm sales and gunsmithing) ADDRESS / DESCRIPTION: 2445 Brush Creek Lane
Building Permit Application Packet. BUILDING CODES Adopted by La Plata County For Enforcement In The Unincorporated Areas Of La Plata County
Building Permit Application Packet The purpose of Building Codes is to establish the minimum requirements to safe guard the public health, safety and general welfare through structural strength, means
Article 20. Nonconformities
Article 20. Nonconformities 20.1 PURPOSE 20.2 GENERAL STANDARDS OF APPLICABILITY 20.3 NONCONFORMING USE 20.4 NONCONFORMING STRUCTURES 20.5 NONCONFORMING LOTS OF RECORD 20.6 NONCONFORMING SIGNS 20.1 PURPOSE
DALLAS COUNTY, IOWA CHAPTER 48 SMALL WIND ENERGY CONVERSION SYSTEMS ORDINANCE FOR THE UNINCOPORATED AREA OF DALLAS COUNTY, IOWA
TITLE V PROPERTY AND LAND USE SMALL WIND ENERGY CONVERSION SYSTEMS ORDINANCE FOR THE UNINCOPORATED AREA OF DALLAS COUNTY, IOWA 48.01 INTENT 48.05 APPLICATION REQUIRED 48.02 DEFINITIONS 48.06 APPEALS 48.03
WESTFIELD-WASHINGTON ADVISORY PLAN COMMISSION December 7, 2015 1512-SPP-24 & 1512-ODP-24
Petition Number: Subject Site Address: Petitioner: Request: East side of Oak Road, north of 151 st Street Langston Development Co. Primary Plat and Overall Development Plan amendment review for Mapleridge
CHAPTER 5 - "R1" SINGLE-FAMILY RESIDENTIAL DISTRICT
CHAPTER 5 - "R1" SINGLE-FAMILY RESIDENTIAL DISTRICT Section 5-1. Regulations: The regulations set forth in this chapter, or set forth elsewhere in this ordinance when referred to in this chapter, are the
ARTICLE 22. AKB ARTHUR K. BOLTON PARKWAY OVERLAY ZONE
ARTICLE 22. AKB ARTHUR K. BOLTON PARKWAY OVERLAY ZONE Sec. 2201. Purpose. AKB is an overlay zone which governs the development of property located along the Arthur K. Bolton Parkway (Georgia Highway 16
Application No.: 14.074 Steve Rush, representing Rocky Mountain Power Rocky Mountain Power Project Location: approximately 1600 N. 6800 E.
Planning Commission Staff Report Planning and Development Services Croydon Substation Conditional Use Permit Public Meeting August 28, 2014 Application No.: 14.074 Applicant: Steve Rush, representing Rocky
ORDINANCE NO. 2013 -
ORDINANCE NO. 2013 - AN ORDINANCE OF BREVARD COUNTY, FLORIDA AMENDING CHAPTER 62, LAND DEVELOPMENT REGULATIONS SECTION 62-2891, LOT DRAINAGE, AND CHAPTER 22 BUILDINGS AND BUILDING REGULATIONS, SECTION
Submit a copy of your license issued by the Department of Social and Health Services.
Skamania County Community Development Department Building/Fire Marshal Environmental Health Planning Skamania County Courthouse Annex Post Office Box 1009 Stevenson, Washington 98648 Phone: 509-427-3900
Assisted Living & Memory Care
SACRAMENTO ASSISTED LIVING & MEMORY CARE 8685 GREENBACK LANE SACRAMENTO CALIFORNIA APN 261-0210-005 DESIGN REVIEW NARRATIVE PROPOSAL Rood Investments proposes to develop a 92,816 square foot Assisted Living
Rezoning case no. RZ15-08: Adam Development Properties, LP
PLANNING AND ZONING COMMISSION STAFF REPORT June 4, 2015 Rezoning case no. RZ15-08: Adam Development Properties, LP CASE DESCRIPTION: LOCATION: a request to amend the development plan of a previously-approved
B. Improve the appearance and character of areas surrounding new development.
Chapter 4.3: Landscape Regulations Sections: 4.301 Purposes 4.302 Applicability 4.303 General Provisions 4.304 Landscape Maintenance 4.301 Purposes The purposes of these regulations are to: A. Promote
PRELIMINARY PROJECT REVIEW PROCESS
CITY OF CYPRESS 5275 Orange Avenue Cypress, California 90630 (714) 229-6720 PRELIMINARY PROJECT REVIEW PROCESS 1. Discuss project with Planning staff to determine zoning regulations, unusual characteristics
Building Permits Permit Counter
Building Permits Permit Counter APPLICATION CHECKLIST SUBMITTAL REQUIREMENTS: 1. Completed signed and notarized Development Services Department Permit Application, submit to Permit Counter. 2. Copy of
LAND USE CODE CHAPTER 18.68 GENERAL REGULATIONS
CHAPTER 18.68 GENERAL REGULATIONS SECTIONS: 18.68.010 Fences. 18.68.020 Vision Clearance Area. 18.68.030 Access. 18.68.040 Yard Requirements. 18.68.050 Special Setback Requirements. 18.68.070 Land Surveys.
D3 April 8, 2015 Public Hearing
D3 April 8, 2015 Public Hearing APPLICANT AND PROPERTY OWNER: ASSEMBLY OF YAH, INC. STAFF PLANNER: Kevin Kemp REQUEST: Conditional Use Permit (Religious Facility - church) ADDRESS / DESCRIPTION: 5151 Locke
Cellular Antenna Towers for Cellular Telecommunications Service or Personal Communications Services
ARTICLE XV CELL TOWER REGULATIONS Cellular Antenna Towers for Cellular Telecommunications Service or Personal Communications Services Sect. 1500 Purpose The purposes of these regulations are: to provide
City of Mandeville. Guidelines for Construction and Development
City of Mandeville Guidelines for Construction and Development 1 Application for Permitting Requirements The following items must accompany any application for a permit for the construction of single family
SANTA BARBARA COUNTY COMPREHENSIVE PLAN LOMPOC AREA
SANTA BARBARA COUNTY COMPREHENSIVE PLAN LOMPOC AREA A. LAND USE ELEMENT INTERPRETIVE GUIDELINES B. COMMUNITY BENEFITS C. COUNTY ACTION ITEMS Adopted by the Board of Supervisors November 9, 1999 A. Santa
TREE PERMIT APPLICATION Private Property- Section 10.52.120 MBMC COMMUNITY DEVELOPMENT DEPARTMENT
Permit No.: TREE PERMIT APPLICATION Private Property- Section 10.52.120 MBMC COMMUNITY DEVELOPMENT DEPARTMENT City Hall 1400 Highland Avenue Manhattan Beach, CA 90266-4795 Telephone (310) 802-5500 FAX
Kirkland Zoning Code 113.25
Kirkland Zoning Code 113.25 Chapter 113 COTTAGE, CARRIAGE AND TWO/THREE-UNIT HOMES Sections: 113.05 User Guide 113.10 Voluntary Provisions and Intent 113.15 Housing Types Defined 113.20 Applicable Use
A. Permitted uses. The following uses are permitted by right in the C-2 zone, subject to the limitations specified:
1 of 8 4/6/2015 1:11 PM Sacramento City Code Up Previous Next Main Collapse Search Print No Frames Title 17 PLANNING AND DEVELOPMENT CODE Division II ZONING DISTRICTS AND LAND USE REGULATIONS Chapter 17.216
PLANNING COMMISSION COUNTY OF MONTEREY, STATE OF CALIFORNIA
PLANNING COMMISSION COUNTY OF MONTEREY, STATE OF CALIFORNIA In the matter of the application of Pebble Beach Company (PLN020290) RESOLUTION NO. 02074 A.P. # 008-411-018-000-M FINDINGS AND DECISION for
Solar Siting in New Jersey
Solar Siting in New Jersey Background Document Sustainable Jersey 7/1/2012 This document is intended to frame the issues around siting of large commercial solar siting as a prelude to developing best practices
New Home Construction Packet
New Home Construction Packet Congratulations! You are building a new home in Meyerland. This packet of information was assembled to assist you with the process. It contains all the forms that you will
EXHIBIT B. Color-Keyed Legend for Tracking Categories of Proposed Ordinance Amendments
Color-Keyed Legend for Tracking Categories of Proposed Ordinance Amendments Clean-up/Housekeeping- correcting errors, omissions, internal inconsistencies; provide additional clarity for interpretation;
SPECIAL USE PERMIT 22-01. JCSA Groundwater Treatment Facility Staff Report for the November 5, 2001, Planning Commission Public Hearing
SPECIAL USE PERMIT 22-01. JCSA Groundwater Treatment Facility Staff Report for the November 5, 2001, Planning Commission Public Hearing This report is prepared by the James City County Planning Division
REGULATIONS FOR CELLULAR ANTENNA TOWERS AND CELLULAR TELECOMMUNICATIONS SERVICES
REGULATIONS FOR CELLULAR ANTENNA TOWERS AND CELLULAR TELECOMMUNICATIONS SERVICES Joint City-County Planning Commission of Barren County, Kentucky 126 East Public Square City Hall Glasgow, KY 42141 A. PURPOSE:
City of Douglas Commercial Building Permit Site Application
City of Douglas Commercial Building Permit Site Application *Complete the following information including a complete site plan and floor plan. *Incomplete information may result in delay and/or rejection
Neighborhood Planning Guide To Zoning
City of Austin Neighborhood Planning Guide To Zoning City of Austin Planning & Development Review Department 505 Barton Springs Road One Texas Center Austin, TX 78704 June 2014 DISCLAIMER: This Guide is
TOWN BOARD OF THE TOWN OF NORTH SALEM WESTCHESTER COUNTY, NEW YORK LOCAL LAW # OF THE YEAR 2012
TOWN BOARD OF THE TOWN OF NORTH SALEM WESTCHESTER COUNTY, NEW YORK LOCAL LAW # OF THE YEAR 2012 CHAPTER 250, ZONING ORDINANCE AMENDMENTS - PD-CCRC DISTRICT Section 1. Purpose: The purpose of this Local
SITE DEVELOPMENT PLAN CHECKLIST. Project Name: Site Plan No.:
SITE DEVELOPMENT PLAN CHECKLIST 5/12/05 Rev.3/14/06 Project Name: Site Plan No.: REVIEW CRITERIA Plans: A site development plan (signed and sealed) shall be on a 24 x 36 sheet at a scale that is no smaller
CHECKLIST FOR TELECOMMUNICATION TOWER CO-LOCATION APPLICATIONS. Conditional Use Permit Approved by Board of Supervisors Date of approval:
CHECKLIST FOR TELECOMMUNICATION TOWER CO-LOCATION APPLICATIONS Conditional Use Permit Approved by Board of Supervisors Date of approval: Site Plan Approval: Date of approval: Fees: $4,000 Licensed Co-location
5. Environmental Analysis
5.11 The potential for adverse impacts on utilities and service systems was evaluated based on information concerning current service levels and the ability of the service providers to accommodate the
Model Subdivision and Land Development (SALDO) Subdivision/ Land Development Presentation Overview. Why Subdivision and Land Development Regulations?
Model Subdivision and Land Development (SALDO) Subdivision/ Land Development Presentation Overview Purpose of Subdivision/ Land Development Ordinances (SALDO) Municipalities Planning Code Process Design
Division S-37. PD Subdistrict 37.
Division S-37. PD Subdistrict 37. SEC. S-37.101. LEGISLATIVE HISTORY. PD Subdistrict 37 was established by Ordinance No. 24204, passed by the Dallas City Council on March 8, 2000. Ordinance No. 24204 amended
The Metropolitan Planning Commission. DATE: May 19, 2015
TO: FROM: The Metropolitan Planning Commission MPC Staff DATE: May 19, 2015 SUBJECT: Petition of LLC, Owner Harold Yellin, Agent PIN: 2-0015-01-002 & 003 Lot Size:.85 Acres (approximately) Aldermanic District:
Stormwater Design Guidelines Frequently Asked Questions:
525 Golden Gate, 11th Floor San Francisco, CA 94102 T 415.551.4694 F 415.934.5728 TTY 415.554.3488 Stormwater Design Guidelines Frequently Asked Questions: A. GENERAL INQUIRIES... 2 1. What projects are
COASTAL DEVELOPMENT PERMIT
COASTAL DEVELOPMENT PERMIT ZONE CODE SECTIONS 12.20.2 prior to LCP certification. The MASTER LAND USE APPLICATION INSTRUCTION SHEET 500' RADIUS should also be followed, except that a 100-foot radius map
PLANNING DIVISION STAFF REPORT February 23, 2015. Summary. Background Information PREPARED FOR THE PLAN COMMISSION. Legistar File ID # 36810
PLANNING DIVISION STAFF REPORT PREPARED FOR THE PLAN COMMISSION Project Address: Application Type: Legistar File ID # 36810 Prepared By: Summary Conditional Use Timothy M. Parks, Planning Division Report
Fernbrook Home Owners Association [HOA] Policy Memorandum No. 3
Fernbrook Home Owners Association [HOA] Policy Memorandum No. 3 ARCHITECTURAL DESIGN GUIDELINES Adopted by the Board This policy memo's objective is to guide homeowners, residents and members of the Architectural
The Board of Zoning Appeals shall have the duty and power to:
Section 21-09.03. (a) Establishment and Jurisdiction. The for the City of South Bend, Indiana, is hereby re-established in accordance with Indiana Code 36-7-4-900 et seq. The for the City of South Bend,
FILE NO.: Z-8403. LOCATION: Located on the Northeast and Southeast corners of West 12 th Street and Dennison Street
FILE NO.: Z-8403 NAME: Glason Short-form POD LOCATION: Located on the Northeast and Southeast corners of West 12 th Street and Dennison Street DEVELOPER: Dennis Glason c/o the Law Office of Simmons S.
COUNTY OF EL DORADO DEVELOPMENT SERVICES ZONING ADMINISTRATOR STAFF REPORT SPECIAL USE PERMIT
COUNTY OF EL DORADO DEVELOPMENT SERVICES ZONING ADMINISTRATOR STAFF REPORT Agenda of: January 20, 2010 Item No.: Staff: 4.a. Aaron Mount SPECIAL USE PERMIT FILE NUMBER: APPLICANTS: REQUEST: LOCATION: S08-0030/Birt
Floodplain Development Land Use Review
COMMUNITY DEVELOPMENT DEPARTMENT Planning Division P.O. Box 490 333 Broadalbin Street SW Albany, OR 97321 Phone 541-917-7550 Fax 541-791-0150 www.cityofalbany.net Floodplain Development Land Use Review
8.24.010. Chapter 8.24
8.24.010 Chapter 8.24 CULTIVATION AND POSSESSION OF MEDICAL MARIJUANA Sections: 8.24.010 Findings. 8.24.020 Purpose and Intent. 8.24.030 Definitions. 8.24.040 Cultivation of Medical Marijuana 8.24.050
Single Family Residential Building Permit Questions & Answers
Single Family Residential Building Permit Questions & Answers Prepared by Dept. of Public Works Revised 07/01/13 200 East Park Street Edwardsville, IL 62025 (618) 692-7535 (618) 692-7505(Fax) Hours: Monday
NON-RESIDENTIAL BUILDING PERMIT PROCEDURES
TOWAMENCIN TOWNSHIP NON-RESIDENTIAL BUILDING PERMIT PROCEDURES PART I Location of Property Address, Zoning District, Parcel Number and Lot & Block must be provided on all applications. PARTS II thru VIII
TENT AND STAGE CUSTOMER ASSISTANCE GUIDE
TENT AND STAGE CUSTOMER ASSISTANCE GUIDE Charles County Government Department of Planning & Growth Management P.O. Box 2150 La Plata, MD 20646 (301) 645 0692 / (301) 870 3935 Fax: (301) 645 0575 Web Site:
CITY OF BELOIT REPORT TO THE BELOIT LANDMARKS COMMISSION
CITY OF BELOIT REPORT TO THE BELOIT LANDMARKS COMMISSION Meeting Date: May 19, 2009 Agenda Item: 5 File Number: COA-2009-09 Applicant: Lisa Anderson-Levy & Robert Levy Existing Zoning: R-1B, Single-Family
CHAPTER 3 MANUFACTURED AND MOBILE HOMES
16-3-1 HOT SPRINGS CODE 16-3-3 CHAPTER 3 16-3-1. Short title. This ordinance may be referred to as the Hot Springs Manufactured Home Ordinance. 16-3-2. Definitions. For the purpose of this ordinance, the
CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL
CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL This manual applies to all development projects within Pitkin County. A Construction Management Plan (CMP) shall be submitted for all projects in Pitkin
sdci Seattle Permits Tip Tree Protection Regulations in Seattle CATEGORIES OF TREES AFFECTED IDENTIFYING TREE TYPES ON YOUR PROPERTY
sdci Seattle Department of Construction and Inspections Tip 242 Seattle Permits part of a multi-departmental City of Seattle series on getting a permit Updated May 12, 2011 Tree Protection Regulations
Mission Canyon Residential Design Guidelines Workshop. Table Focus: Environmental Issues and Concerns
Mission Canyon Residential Design Guidelines Workshop Table Focus: Environmental Issues and Concerns Grading How is Grading Regulated in Santa Barbara County? The technical aspects of grading are regulated
Commercial Construction Permit Application
THIS IS NOT A CONSTRUCTION PERMIT DO NOT START CONSTRUCTION UNTIL PERMIT IS ISSUED City of Lincoln Commercial Construction Permit Application Rev. 4-14 Page 1 Commercial Permit Application THIS IS NOT
5 March 12, 2014 Public Hearing
5 March 12, 2014 Public Hearing APPLICANT: MOORE FARM, L.L.L.P. PROPERTY OWNER: MOORE FARM L.L.L.P. STAFF PLANNER: Kevin Kemp REQUEST: Change of Zoning (B-1A Limited Community Business to Conditional B-2
GUIDELINES FOR PLAN CHECK AND PERMIT REQUIREMENTS FOR SOLAR ENERGY SYSTEMS
INFORMATION BULLETIN / PUBLIC GENERAL INFORMATION REFERENCE NO.: LAMC 91.1301, 93.690 Effective: 01-01-2014 DOCUMENT NO.: P/GI 2014-027 Revised: 11-07-2014 Previously Issued As: P/GI 2011-027 GUIDELINES