Earned value analysis in project management: Survey and research potential
|
|
|
- Briana McKenzie
- 10 years ago
- Views:
Transcription
1 Earned value analysis in project management: Survey and research potential Milind Padalkar, Saji Gopinath* Quantitative Methods & Operations Management Indian Institute of Kozhikode, Kerala, India Abstract: Earned Value Analysis is a recommended technique for monitoring and controlling project execution. Yet, despite four decades of institutional backing and sustained advocacy, its adoption still remains limited. It draws loyal adherents as well as opponents, and an ongoing debate about its practical utility. Empirical studies of its effectiveness or adaptation for different situations are sparse; and the claims, objections do not appear to be reconciled. In this paper, we survey academic and practitioner literature on Earned Value Management and its extensions, and attempt to reconcile the debate by juxtaposing the claims and counterclaims against parallel research streams in project management. We suggest an integrative schema to ground the technique amidst the various bodies of research opinions in order to elicit future directions. Keywords: Earned Value Management, Project management, Literature survey Introduction Despite many decades of practice and academic attention, project performance remains problematic. Empirical evidence suggests that projects do not generally achieve the required scope, are often late, and perform badly on quality of deliverables as well as on cost budgets. According to a recent Standish Group survey report, 61% of the projects either failed or were challenged to meet success criteria; and 74% faced schedule overruns (Standish 2013). Earned Value Analysis (EVA) is a classical technique to monitor and control project performance. It owes its genesis to US Department of Defense (DOD), which formalized Cost/Schedule Control Systems Criteria (C/SCSC) in 1967, and mandated that defense contractors must use it and report progress in specified formats. C/SCSC was updated to Earned Value Management System (EVMS) in 1997 by Electronic Industry Association through ANSI/EIA-748 standard. At this time, the acronyms used by C/SCSC such as BCWS, ACWP, and BCWP, were simplified to PV (Planned Value), AC (Actual Cost), and EV (Earned Value) respectively. As EVMS was more flexible, DOD and US Federal agencies adopted it replacing C/SCSC (Fleming and Koppelman 2005). Subsequently, Project Management Institute adopted it as a standard: i) Calling it Earned Value Management (EVM), the technique was included in its Guide to the Project Management Body of Knowledge (PMBOK ) 2000 edition as one of the standard methods of controlling performance, and ii) Included EVM in PMP its flagship certification program as part of the Project Integration Management knowledge area, and under Monitoring and Controlling Process Group. These initiatives have led to high level of awareness 1
2 about EVM among the practicing project managers as confirmed by several studies (Kim et al. 2003; Besner and Hobbs 2006). Yet, despite these attempts, EVM remains underutilized by the private industry (Kim et al. 2003; Besner and Hobbs 2006; Marshall et al. 2008; Kwak and Anbari 2012; De Marco and Narbaev 2013; Singh et al. 2014). EVM integrates three key project performance criteria: scope, time and cost (Anbari 2003). EVM is fundamentally deterministic (Kim and Reinschmidt 2009), i.e. it is grounded in the assumption that the project scope, master schedules and cost budgets are completely determined and fixed from start. Throughout its history, EVM has enjoyed strong advocacy from its proponents many of whom were involved with DOD programs. On the other hand, several scholars and practitioners contest its practicality from an implementation point of view, and question its structural rigidity. In response, proponents have attempted to address the objections by suggesting extensions. In parallel, a separate line of empirical research has focused on key success factors to explain project outcomes. Some of these factors are also the pre-requisites for successful EVM adoption, and thus lend support to the objections. Finally, yet another stream of research recognizes the innate indeterminacy of the project phenomena and studies them through uncertainty or complexity lenses. The research under these lenses rejects determinism, negating the basic plank of EVM. Thus, multiple research streams bear on the EVM debate. Given these developments, it would be pertinent to ask what sort of future awaits EVM outside the US DOD and Federal government-mandated projects. We note that most objections to EVM question its applicability and cost/benefits, but not its usefulness. It would be instructive to examine the evolution and the current state of this debate; and what implications it might have on EVM as well as future research potential in this area. We review available literature on EVM and offer a perspective on the different strands of debate along with contextual findings from parallel research streams. We propose a schematic to integrate the views from different scholars and attempt to derive future directions for research. This paper is organized as follows. We provide a brief description of EVM concepts and technique, followed by a summary of the cross-currents in the debate to propose an integrative schema for situating the various viewpoints. Next, we discuss the implications and future possibilities for EVM research before concluding with the limitations of our study. Earned Value Management EVM integrates project scope, time and cost through periodic measurements of actual cost and work completion. It views project progress in terms of cost as a function of time against a firm baseline set up at the start of the project. When the project is originally planned, it is divided into Work Breakdown Structure (WBS) and further sub-divided into work packages. These work packages are assessed for cost estimates and scheduled in a time sequence. Taken together, WBS, master schedule and cost budgets form the baseline, represented as a graph of planned costs over time. This is the planned value (PV). It simply tells how the costs will flow over time as planned. During the project execution, actual costs (AC) and the quantum of work completed are periodically noted. The work completion is pro-rated to equivalent monetary value based on the budgetary costs for the work packages completed (work-in-progress packages are assessed on % completion). This is the earned value (EV). These three numbers, i.e. PV, AC and EV drive the operation of EVM. In essence, (EV AC) measures cost performance and (EV PV) measures 2
3 schedule performance. By measuring at periodic intervals, EVM focuses on the flow rates of actual cost and completion against the planned cost and completion. PV, EV and AC make it possible to compute cost and time variances, as well as extrapolate how much cost and time would be required for project completion (Figure 1). Simple calculations based on these three numbers yield several ratios for project control. Of these, three ratios can be regarded as important: Cost Performance Index (CPI), Schedule Performance Index (SPI), and Cost Estimate at Completion (CEAC). By giving historical and forward information about the project, EVM becomes a tool for monitoring and course corrections. CPI = EV/AC SPI = EV/PV CEAC = AC + (BAC EV)/CPI Image source: Figure 1: PV, AC and EV Our purpose is not to give an exhaustive description of EVM, as several excellent papers exist (Fleming and Koppelman 2000; 2005; 2009; Anbari 2003), but to examine its utility as a control technique. Towards this, we now turn to review the debate that surrounds EVM. Cross-currents in EVM literature DOD contractors were clearly the early adopters of the technique can be seen as the era of C/SCSC, which listed 35 requirements widely seen to be excessive and over-specified, requiring a lot of paperwork (Abba 1997). Hence, C/SCSC was not enthusiastically received by DOD contractors, and the private industry almost completely ignored it. EVM fared better as a control technique for a number of reasons. First, it dropped some of the cumbersome aspects of C/SCSC and made it more flexible. Second, several US Federal Government Agencies such as NASA and Department of Energy adopted EVM, and began to push for its adoption by the private industry. Third, Project Management Institute accepted it as a standard for project control and included it in PMBOK and PMP certifications. Fourth, a small body of advocates emerged from the practitioners who had used it on DOD projects. From late 90 s, private firms began to use EVM. However, it does not appear to enjoy widespread usage. A survey on project management tools revealed that EVM was underutilized (Besner and Hobbs 2006). Surveys from construction industry show poor adoption (Beatham et al. 2004; Chan and Chan 2004). When used, an evidence of positive relationship with project performance is seen (Marshall et al. 2008). Based on a review of available EVM literature, we note two facts: i) adoption levels of EVM remain low (Kim et al. 2003; Besner and Hobbs 2006; Rozenes et al. 2006; Marshall et al. 3
4 2008; De Marco and Narbaev 2013; Singh et al. 2014), and ii) the literature is largely anecdotal in nature, with very few empirical studies on post-adoption experience (Kim et al. 2003; Marshall et al. 2008). Therefore, much of the available literature can be regarded as representing views, claims and counterclaims of scholars and practitioners based on their studies and/or experience. Thus, it is possible to group the various articles in two categories: Protagonist literature and Objectionist literature. By objectionist we mean challenging the orthodoxy with objective arguments, anecdotal evidence or data. We observe that the objectionist literature challenges the assumptions of determinism and measurability of EVM variables; however, we do not find studies that evaluate or question EVM s theoretical base. There is a third stream that seeks to extend EVM to overcome the objections. Separately, project management literature has a long-standing empirical stream informing on success/failure factors linked to project outcomes. Some of these variables e.g. scope instability, control systems maturity, etc. overlap with the objectionist claims. Thus the empirical research stream has a bearing on the debate between protagonist and objectionist literatures. Finally, a recent trend is to view the project phenomena through non-deterministic lenses of uncertainty and complexity (Svejvig and Andersen 2015). Since EVM is anchored in a deterministic paradigm, this line of research would appear to question the fundamental basis of EVM. Table 1 lists these five streams of research. Table 1 Research streams related to EVM Category Description of research stream Research orientation Protagonist Support and advocacy of EVM Deterministic and method-centric Objectionist Challenges EVM on the basis of utility, practicality, reliability Empirical or logical negation of assumptions Extensionist Extensions to EVM to overcome objections Bridge between the two schools Empiricist Searches explanatory factors for outcomes Empirical Non-determinist Holds that phenomena are inherently nondeterministic Models phenomena to gain further insights and to obtain tractability We proceed with a review of research in the first four categories. As the non-determinist research does not relate to our enquiry, we do not include it in our review and analysis. For our survey, we focus on journal articles on the grounds that non-journal writings are normally not peer-reviewed, often lack the requisite academic rigor, and are generally anchored to a methods-orientation that is non-contestable. We note that though several conference papers on EVM exist, these are generally not subjected to rigorous peer-level scrutiny. Hence we exclude conference papers unless they happen to be well-cited and presented in top conferences such as POMS or DSI. Review of protagonist literature on EVM Clearly, US Government Agencies and Project Management Institute are the main protagonists. By publishing the standards and mandating or recommending their adoption makes EVM the de jure method of project control. EVM has spawned a number of loyal adherents that include practitioners, consultants and academia. Protagonist writings on EVM tend to be articles in journals, business media, monographs and topic-focused books. There are two broad themes in protagonist journal writings: i) articles in the nature of explanation of EVM and elaboration of key parameters, and ii) articles on EVM as a tool to control future adverse events. 4
5 Under the first theme, Abba (1997; 2000) provides background on the historical events leading to the EVM standard, and discusses A-12 program cancellation to underline its capability to issue early alerts for a potential failure. Christensen (1998) reviews literature to report costs and benefits of EVM. Anbari (2003) gives a comprehensive description of EVM illustrating the use of its various parameters. He also provides extensions to EVM by describing more ratios and their potential utility, while remaining firmly anchored in the deterministic paradigm. Raby (2000) provides easy description of EVM for lay users. In an HBR article, Fleming and Koppelman (2003) describe EVM and argue Cost Performance Index (CPI) as a key parameter that predicts the final cost at completion with reliable accuracy much earlier in the project. Cioffi (2006) contests the usefulness of acronyms used in EVM and claims that simplified, intuitive acronyms can improve the adoption behavior among practitioners. Kuehn (2007) uses the metaphor of flight path to give a detailed description of EVM and illustrates it with an example. Fleming and Koppelman (2009) illustrate the importance of CPI and its ability to forecast via another parameter called TCPI. A study by Marshall et al (2008) finds moderate evidence of EVM as a predictor of project outcomes. The second theme examines the forecasting ability of the technique, posting that early stability of the indices imparts early alert capability. Christensen and Heise (1993) study 155 completed DOD projects to find stable CPI beyond 20 percent complete point. Lipke (2002) shows that the reciprocals of CPI and SPI are log-normally distributed; and hence amenable to statistical reliability techniques. Christensen and Templin (2002) analyze 240 DOD contracts to show that stability of CPI from 20 percent complete point is a good predictor of cost estimate at completion. Working on his master s degree thesis, Mitchell (2007) studies 181 completed DOD projects to show that cumulative CPI stabilized at or before 50 percent complete point. Vandevoorde and Vanhoucke (2006) describe EVM to forecast project schedule performance. Review of objectionist literature on EVM The objectionist literature is small and mostly comes from defense projects or the construction industry. Cooper (2003) points to the fact that complex projects often involve unanticipated rework, making them unsuitable for EVM. Rozenes et al., (2006) question the hierarchical nature of work breakdown structure (WBS), on which EVM is based, and claim that most common success factors include clear goals and effective control mechanisms, which are generally weak in practice. These deficiencies could explain the low adoption of EVM by the private industry. Putz et al., (2006) describe a NASA case study pointing out problems in setting up baselines, lack of baseline validation, and weaknesses in cost estimates. Lukas (2007) lists ten pitfalls for EVM usage including incomplete requirements or their documentation, WBS-Schedule-Budget integration issues, inapplicability/resistance to WBS, ineffective change processes, inadequate costing systems etc. De Marco and Narbaev (2013) describe the stumbling blocks for EVM such as level of detail in plans/schedules and measurement reliability especially assessment of work package completion. They observe that SPI tends to 1 as the project nears completion, and hence it is not useful predictor beyond a 60 percent complete point. It appears that the authors are unaware of the concept of Earned Schedule introduced by Lipke (2003). Singh et al. (2014) criticize EVM as a reactive and lagging technique in context of renovation construction industry. They claim that it does not reveal the causes of delays or budget overruns and hence does not advise the future plan of action. EVM is also not suitable when changes to budgets, scope or schedules occur. As such changes are endemic, agile methods have been developed to address 5
6 them through iterative processes and non-linear feedback loops. Adapting EVM for Agile methods has been discussed in few conference proceedings (Cabri and Griffiths 2006; Sulaiman et al. 2006). However, EVM s applicability for Agile methods is yet to be rigorously established. Contrasting the above against protagonist research, we observe that neither of the protagonist themes attempts to engage the objections raised by researchers. Review of extensionist literature on EVM Literature to bridge the above cross-currents is very sparse, and offers concrete opportunity for future work in this stream. Bauch and Chung (2001) suggest a modified technique using Shewhart statistical control charts to dynamically monitor time-cost-scope parameters. Pajares and Lopez-Paredes (2011) offer a revised method to integrate risk management with EVM. Kim et al (2003) propose an implementation methodology for EVM based on a four-factor model of EVM acceptance. Lipke et al. (2009) suggest statistical inference techniques to fix confidence intervals for parameters. To overcome the anomalous behavior of SPI (tending to 1 towards completion) cited in the objectionist literature, Lipke (2003; 2004; 2006) proposes the concept of Earned Schedule (ES), involving mapping EV back to time by referencing the baseline. Using simulation, ES is shown to be a better indicator of schedule at completion than traditional EVM methods (Vanhoucke and Vandevoorde, 2007; Lipke, 2009). Kim and Reinschmidt (2009) use Bayesian inference on beta-s curve and show that the method delivers narrower intervals compared to earned schedule or the traditional method. It can be seen that the extensionist approach is centered on using statistical techniques to study instability of the EVM indicators. It does not address the underlying causes for instability. Empiricist literature Unclear scope, Requirement Changes, Infeasible WBS Objectionist literature Rework Poor costing or Control systems Empiricist literature Weak scheduling, Weak metrics Changes to budgets Scope or schedules Scope (Requirements) Planning (WBS, Scheduling) Budgeting (Estimation, Costing) Control System (Standards, Metrics, Assessment, Corrective actions, Change control) Components required for EVM Advocacy EVM Index stability, New indices Methods to Implement Protagonist literature Extensionist literature Figure 2: Integrated view of multiple lines of research enquiry Review of empiricist project management literature Project management literature offers considerable quantum of empirical research on success or failure factors to explain the project outcomes. Recall that creating a firm baseline is a fundamental requirement for EVM. It stands to reason that any project variable that interacts 6
7 with the baseline components would influence EVM. The empirical research on project management identifies several factors related to project failures such as fixed schedules with no iterative processes, ineffective change management, weak requirements, high complexity, erroneous estimation or metrics, insufficient planning, unclear or shifting goals, etc., showing that actual project environment is anything but deterministic (Whittaker 1999; Cooke-Davis 2002; Kappelman et al. 2006; Nelson 2007; Chua 2009). These factors induce instability in scope, requirements, and estimates and adversely affect the necessary conditions for EVM. Taking an integral view of these four streams of research, we note that the protagonist writings have continued to advocate the technique, taking little cognizance of the objections raised from various quarters (Figure 2), despite such objections being grounded in empirical reality. The extensionist research has remained peripheral to main concerns about lack of robustness of scope, requirements, and estimates. Discussion A timeline view of the four research streams (Figure 3) indicates that they run contemporaneously. Interestingly, the objections to EVM do not seem to be engaged by EVM researchers, hence the debate on its applicability remains open and relevant. EVM is powerful because it is a simple, yet an elegant technique, deriving from basic costing principles. By requiring a baseline, it forces an integrated view of work completion and cost flow over time. Without such a technique, the three parameters of scope, schedule and cost are often monitored independently (Rozenes et al., 2006). We observe that it is well subscribed on government projects, since compliance is a necessary pre-requisite of doing business with the government. However, its adoption in that sector does not testify to execution efficiency. Recall that many objections to EVM relate to excessive paperwork and difficulty of hard measurements. Empiricist E7 E1 E2 E3 E4 E5 E6 X9 X3 X8 X1 X2 X4 X5 X6 X7 X10 Extensionist Objectionist O6 O1 O2 O3 O4 O5 Protagonist S1 S3 S4 S5 A4 S2 A6 A1 A2 A3 A5 A7 A8 A9 A S: Stability-related, A: Advocacy-related, O: Objectionist, X: Extensionist, E: Empiricist Figure 3: Timeline view of the different research streams Year E1 Hughes (1986) O4 De Marco & Narbaev (2013) A1 Abba (1997) X1 Bauch & Cheung (2001) E2 Whittaker (1999) O5 Singh et al. (2014) A2 Christensen (1998) X2 Kim et al. (2003) E3 Cooke-Davis (2002) O6 Putz et al. (2006) A3 Abba (2000) X3 Lipke(2003) E4 Kappelman et al. (2006) S1 Christensen & Heise (1993) A4 Raby (2000) X4 Lipke (2004) E5 Nelson (2007) S2 Lipke (2002) A5 Anbari (2003) X5 Lipke (2006) E6 Cerpa & Verner (2009) S3 Christensen & Templin (2002) A6 Fleming & Koppelman (2003) X6 Vanhoucke & Vandevoorde (2007) E7 Chua (2009) S4 Vandevoorde & Vanhoucke (2006) A7 Cioffi (2006) X7 Kim & Reinschmidt (2009) O1 Cooper (2003) S5 Mitchell (2007) A8 Kuehn (2007) X8 Lipke et al., (2009) O2 Rozenes et al. (2006) A9 Marshall et al. (2008) X9 Lipke (2009) O3 Lukas (2007) A10 Fleming & Koppelman (2009) X10 Pajares & Lopez-Paredes (2011) 7
8 Whether the extra cost of compliance is recovered from incremental efficiencies, preemption of budgetary overruns or from the government clients is not clear. But, despite persistent advocacy, there is no evidence of its widespread adoption within the private industry. Empirical studies on EVM usage are very sparse, with one study (Marshall et al. 2008) showing only a moderate relationship (R 2 = ) between EVM adoption and project performance. We believe that the simplicity of the technique is exactly what reduces its applicability. Because it is grounded in costing principles, it can operate only if the baseline costs and the project plan are fully detailed at project initiation. This implies that project goals, requirements, scope, work breakdown structures, work package definitions, estimates, master schedules, and cost budgets must be firm at the project set-up. There is considerable empirical evidence that information about these elements either does not exist, or is incomplete at the project set-up. Thus, the project baseline is approximate and includes unknown error. EVM literature provides little guidance on project set-up strategies when one or more of these elements are insufficiently informed. Even assuming that the baseline is accurate and detailed, changes in scope, schedule or cost budgets can occur due to endogenous or exogenous events. Empiricist surveys report that such changes are common and consistently rank high in the list of factors critical to project performance. EVM literature does not inform on how the technique should be adapted when changes happen. A typology of changes and how they can be flexibly accommodated within EVM would be useful for the practitioners. Another commonly reported problem relates to inadequacy of the measurement systems. Even with perfect project set-up, measurement errors cannot be avoided. Established costing systems can measure AC with fair accuracy, but EV measures remain fuzzy. To compute EV, one must measure completion of work packages. This requires subjective judgment for in-progress work packages. To overcome the problem of errors of judgment, 50/50 rule has been suggested. This however leads to EV being overstated or understated by an average 25% of each work package baseline. When EV is aggregated over work package differing in size, it is not possible to specify the error in total EV. Objectionist literature points this out, and the extensionist stream appears to have engaged this issue by looking at statistical inference methods (Lipke et al. 2009). But such research investigates confidence intervals on CPI and not EV. This problem possibly merits attention from other research streams such as work measurement. EVM serves two main purposes. First, it tells the project manager where the project is, by connecting work completion, costs incurred and time taken. Second, it supplies the arithmetic to predict the cost and time parameters at completion. Arguably, anything that offers an ability to predict future outcomes should be much valued, and it is no surprise that it is the dominant theme in all protagonist writings. Moreover, the objectionist papers do not explicitly challenge EVM s prediction ability while questioning its practicability. It is puzzling that a technique offers a very useful feature which is not contested, and yet gets ignored in practice. Since empirical evidence about EVM remains very sparse, we offer a couple of conjectures to explain its low adoption. First, we note that the arithmetic to calculate the predicted values of parameters follows the method of linear extrapolation using CPI, which is simply the rate at which actual cost inflow converts to productive cost outflow. For true predictive ability, CPI must achieve a constant value, which explains the search for stable CPI in protagonist literature. There is no reason to believe that actual cost will convert to productive work at a constant rate. Indeed the graphs illustrating EVM generally show different S-curves for AC and EV. If the two cost flows are differently non-linear, EVM loses its ability to predict because CPI becomes a function of time. 8
9 Second, deriving the shapes of cost functions is not possible because it requires a precise understanding of causal model of work and costs. Costing logic is rarely possessed of such an understanding (Lebas 1995). By forcing linearity on patently non-linear phenomena, EVM does much disservice to its claim of prediction accuracy. Even so, EVM remains one of the few techniques that generate progress data from which it is possible to learn the function shapes. Such data, coupled with prior knowledge could be used to make statistically robust inferences about the cost functions. We note a few initial attempts towards this end in the extensionist literature (Lipke et al. 2009; Pajares and Lopez-Paredes 2011), which use confidence interval-based methods. However, the computed confidence intervals are likely to be too broad in the early stages to be of much practical use. Also, these methods assume that underlying variables follow normal distributions; but there is no reason to assume such normality (Lipke 2002). Other methods such as Bayesian inference or stochastic models could deliver narrower, robust intervals, and have been attempted with encouraging results (Kim and Reinschmidt 2009). With better grasp of function shapes, Monte Carlo methods and/or systems dynamics could deliver further insights into the behavior of costs. Such methods have already been used to deliver useful insights (Lipke 2009; Vanhoucke and Vandevoorde 2007), and could advance the extensionist enquiry to act as an effective bridge between the protagonist and the objectionist schools and may aid the adoption of EVM. To conclude, our paper surveys the cross-currents in EVM literature and finds the debate to be disengaged, with no early signs of greater adoption by practitioners. We also find the research on EVM to be sparse, both in terms of empirical findings and conceptual models. Our paper contributes to the literature by integrating the dispersed research streams into a framework, and by positing multiple lines of future research. We acknowledge the limitations of our work. First, due to dispersed nature of research, our findings are limited by the papers we could find for our review. Second, due to acute paucity of empirical studies, we are forced to offer conjectural explanations. Such explanations may stand altered if more empirical data were available. Despite these limitations, we hope that our contribution offers utility for future researchers. Bibliography Abba, W. (1997). Earned Value Management-Reconciling Government and Commercial Practices. Program Manager, 26, Abba, W. (2000). How Earned Value Got to Primetime: A Short Look Back and A Glance Ahead. In Project Management Institute Seminars and Symposium in Houston, TX. Anbari, F.(2003).Earned value project management method & extensions. Project Management Journal, 34(4), Bauch, G., & Chung, C. (2001). A Statistical Project Control Tool for Engineering Managers. Project Management Journal, 32(2), Beatham, S., Anumba, C., Thorpe, T., & Hedges, I. (2004). KPIs: a critical appraisal of their use in construction. Benchmarking: An International Journal, 11(1), Besner, C., & Hobbs, B. (2006). The perceived value and potential contribution to project management practices to project success. Project Management Journal, 37(3), Cabri, A., & Griffiths, M. (2006, July). Earned Value and Agile Reporting. AGILE, 6, Chan, A. P., & Chan, A. P. (2004). Key performance indicators for measuring construction success. Benchmarking: an international journal, 11(2), Christensen, D. (1998). The costs and benefits of the earned value management process. Journal of Parametrics, 18(2), Christensen, D., & Heise, S. (1993). Cost performance index stability. National Contract Management Journal, 25(1),
10 Christensen, D., & Templin, C. (2002). EAC evaluation methods: do they still work. Acquisition Review Quarterly, 9(1), Chua, A. (2009). Exhuming it projects from their graves: an analysis of eight failure cases and their risk factors. Journal of Computer Information Systems, 49(3). Cioffi, D. (2006). Designing project management: A scientific notation and an improved formalism for earned value calculations. International Journal of Project Management, 24(2), Cooke-Davies, T. (2002). The real success factors on projects. International Journal of Project Management, 20(3), Cooper, K. What s your project s real price tag. Harvard Business Review. 81(12), De Marco, A., & Narbaev, T. (2013). Earned value-based performance monitoring of facility construction projects. Journal of Facilities Management, 11(1), Fleming, Q., & Koppelman, J. (2000; 2005). Earned value project management. Project Management Institute. Fleming, Q. & Koppelman, J. (2003). What s your project s real price tag. Harvard Business Review, 81(9), Fleming, Q., & Koppelman, J. (2009). The two most useful earned value metrics: The CPI and the TCPI. Cost Engineering, 51(3), Kappelman, L., McKeeman, R., & Zhang, L. (2006). Early warning signs of IT project failure: The dominant dozen. Information systems management, 23(4), Kim, B., & Reinschmidt, K. (2009). Probabilistic forecasting of project duration using Bayesian inference and the beta distribution. Journal of Construction Engineering and Management, 135(3), Kim, E., Wells Jr, W., & Duffey, M. (2003). A model for effective implementation of Earned Value Management methodology. International Journal of Project Management, 21(5), Kuehn, U. EVM. 05 Earned Value Analysis Why am I forced to do it? AACE International Transactions. Kwak, Y., & Anbari, F. (2012). History, practices, and future of earned value management in government: Perspectives from NASA. Project Management Journal, 43(1), Lebas, M. (1995). Performance measurement and performance management. International Journal of Production Economics, 41(1), Lipke, W. (2002). A study of the normality of earned value management indicators. The Measurable News,4,1-6. Lipke, W. (2003). Schedule is different. The Measurable News, 31(4), Lipke, W. (2004). Connecting earned value to the schedule. The Measurable News, 1, Lipke, W. (2006). Applying earned schedule to critical path analysis and more. The Measurable News, Lipke, W. (2009). Project duration forecasting A comparison of earned value management methods to earned schedule. The Measurable News, (2), Lipke, W.,Zwikael, O.,Henderson, K. & Anbari, F.(2009).Prediction of project outcome:application of statistical methods to earned value management. International Journal of Project Management, 27(4), Lukas, M. EVM. 01 Earned Value Analysis Why it Doesn't Work AACE International Transactions. Marshall, R., Ruiz, P., & Bredillet, C. (2008). Earned value management insights using inferential statistics. International Journal of Managing Projects in Business, 1(2), Mitchell, R. (2007).Historical Review of Cost Performance Index Stability.Naval Postgraduate School Monterey CA. Nelson, R. (2007). IT project management: infamous failures, classic mistakes, and best practices. MIS Quarterly Executive, 6(2) Pajares, J., & Lopez-Paredes, A. (2011). An extension of the EVM analysis for project monitoring: The Cost Control Index and the Schedule Control Index. International Journal of Project Management, 29(5), Putz, P.,Maluf, D.Bell,D.,Gurram,M.,Hsu,J., Patel, H., & Swanson, K.(2007, March). Earned value management at NASA: An integrated, lightweight solution. In Aerospace Conference, 2007 IEEE (pp. 1-8). Raby, M. (2000). Project management via earned value. Work study, 49(1), Rozenes, S., Vitner, G., & Spraggett, S. (2006). Project control: literature review. Project Management Journal, 37(4), Singh, Y., Abdelhamid, T., Mrozowski, T., & El-Gafy, M. (2014). Investigation of Contemporary Performance Measurement Systems for Renovation Projects. Journal of Construction Engineering, Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), Vandevoorde, S., & Vanhoucke, M. (2006). A comparison of different project duration forecasting methods using earned value metrics. International Journal of Project Management, 24(4), Vanhoucke, M., & Vandevoorde, S. (2007). A simulation and evaluation of earned value metrics to forecast the project duration. Journal of the Operational Research Society, 58(10),
An introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 [email protected]
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION Author Bill Mowery MPM, PMP Keywords Earned Value Management, Earned Schedule, Project Management, Cost
Earned Schedule Leads to Improved Forecasting
Lipke, Walt Norman, Oklahoma, USA Earned Schedule Leads to Improved Forecasting Abstract For project cost, analysts can predict the final value with some confidence using the Independent Estimate at Completion
Earned Value and Agile Reporting
Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,
Project Control with ProTrack
Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS
Applying Fuzzy Control Chart in Earned Value Analysis: A New Application
World Applied Sciences Journal 3 (4): 684-690, 2008 ISSN 88-4952 IDOSI Publications, 2008 Applying Fuzzy Control Chart in Earned Value Analysis: A New Application Siamak Noori, Morteza Bagherpour and Abalfazl
Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1
Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control
Assessing Schedule Performance with Earned Value
FEATURED PAPER OCTOBER 2007 Time Is Up: Assessing Schedule Performance with Earned Value By Robert Van De Velde Time drives projects. Quick and accurate evaluation of schedule performance is crucial. Quantitative
Agile and Earned Value. A white paper. October 2013. Author Stephen Jones, Sellafield Ltd
Agile and Earned Value A white paper October 2013 Author Stephen Jones, Sellafield Ltd This document is a whitepaper produced by the APM Planning, Monitoring and Control SIG. It represents the thoughts
EVM.01. Earned Value Analysis Why it Doesn't Work
EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects
Estimating Cost at Completion - Judgment & EV Information
Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number
The Two Most Useful Earned Value Metrics: the CPI and the TCPI
PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was
How To Manage A Project
Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you
Why EVM Is Not Good for Schedule Performance Analyses (and how it could be )
Why EVM Is Not Good for Schedule Performance Analyses (and how it could be ) By Radenko Corovic, MBA Abstract Project performance researchers are unanimous that the conventional EVM (Earned Value Management)
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
Introduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
Earned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
Abstract. Earned Value Management Basics
Earned Schedule: A Breakthrough Extension to Earned Value Management Kym Henderson Education Director, Project Management Institute, Sydney Australia Chapter Abstract Earned Schedule (ES) analysis is a
AACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
Project Cost Management
Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
Project Cost Control: The Way it Works By R. Max Wideman
Project Cost Control: The Way it Works By R. Max Wideman 12/21/05 In a recent consulting assignment we realized that there was some lack of understanding of the whole system of project cost control, how
EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS
14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya
PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and
Earned value method as a tool for project control
Budownictwo i Architektura 3 (2008) 15-32 Earned value method as a tool for project control Institute of Construction, Faculty of Civil and Sanitary Engineering, Lublin University of Technology, 20-618
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Rules on using templates 1) Must reference the template used 2) Use
SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT
1 PMSC Quarterly Meeting, February 1 2, 2011, Fort Worth, Texas SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT Increasing the Probability Program of Success (PoPS)by Connect the dots between
Predicting progress on your project
www.nonsuch.co [email protected] Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant
Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman
Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government
INSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
Unit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
What is the Health of my Project?
WHITE PAPER What is the Health of my Project? The Use and Benefits of Earned Value Table of Contents How s My Project Doing?...1 Need a Solution? Earned Value to the Rescue!...1 My actual costs are less
Forecasting Project Schedule Completion by Using Earned Value Metrics
Forecasting Project Schedule Completion by Using Earned Value Metrics Ing. Stephan Vandevoorde Sr. Project Manager Fabricom Airport Systems [email protected] 1 Agenda Introduction Schedule performance indicators
Appendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
Since 1985, the Test Program Set (TPS) development
Applying Management Reserve to Software Project Management Walter H. Lipke Oklahoma City Air Logistics Center, Directorate of Aircraft Maintenance, Software Division Today s standard of practice for managing
plans based on actual cost, schedule and technical progress of work [1, 9].
An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan
Brainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.
Project Management ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.2003 1 Project Management - Training Program - Project Scope Management
700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
IMPROVING TRADITIONAL EARNED VALUE MANAGEMENT BY INCORPORATING STATISTICAL PROCESS CHARTS
IMPROVING TRADITIONAL EARNED VALUE MANAGEMENT BY INCORPORATING STATISTICAL PROCESS CHARTS Sou-Sen Leu P.O.Box 90-30, Taipei, [email protected] You-Che Lin P.O.Box 90-30, Taipei, [email protected]
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP
PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP PROJECTS PROGRESS WELL UNTIL 70% Quick progress until 60-70% complete. Then we discover the project is in distress.
Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
Young Hoon Kwak Associate Professor School of Business The George Washington University
Project Management in Government: An Introduction to Earned Value Management (EVM) Improving Performance Series Young Hoon Kwak Associate Professor School of Business The George Washington University Frank
David S. Christensen, Ph.D.
The Costs and Benefits LESSONS of the Earned LEARNED Value Management Process THE COSTS AND BENEFITS OF THE EARNED VALUE MANAGEMENT PROCESS David S. Christensen, Ph.D. Up to now assessments of the earned
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s
New Tools for Project Managers: Evolution of S-Curve and Earned Value Formalism
New Tools for Project Managers: Evolution of S-Curve and Earned Value Formalism A Presentation at the Third Caribbean & Latin American Conference On Project Management, 21 23 May 2003 Denis F. Cioffi,
Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. [email protected]
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective
EARNED VALUE ANALYSIS IN THE CONTROL OF PROJECTS: SUCCESS OR FAILURE?
EARNED VALUE ANALYSIS IN THE CONTROL OF PROJECTS: SUCCESS OR FAILURE? Ricardo Viana Vargas, MSc, IPMA-B, PMP Professor Getulio Vargas Foundation (FGV) Brazil Professor Fundação Instituto de Administração
// Benchmarking Project Schedules
// Benchmarking Project Schedules Dr. Dan Patterson, PMP CEO & President, Acumen March 2011 www.projectacumen.com Table of Contents Introduction... 4 Benchmarking Overview... 4 Uses of Schedule Benchmarking...
Schedule Adherence a useful measure for project management
Schedule Adherence a useful measure for project management Walt Lipke PMI Oklahoma City Chapter Abstract: Earned Value Management (EVM) is a very good method of project management. However, EVM by itself
USING THE EARNED VALUE COST MANAGEMENT REPORT TO EVALUATE THE CONTRACTOR'S ESTIMATE AT COMPLETION. David S. Christensen, Ph.D.
USING THE EARNED VALUE COST MANAGEMENT REPORT TO EVALUATE THE CONTRACTOR'S ESTIMATE AT COMPLETION David S. Christensen, Ph.D. College of Business Southern Utah University 351 West, Center Street Cedar
IST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
Project Duration Forecasting a comparison of Earned Value Management methods to Earned Schedule
Project Duration Forecasting a comparison of Earned Value Management methods to Earned Schedule Walt Lipke Member of Oklahoma City Chapter Project Management Institute (USA) Abstract: Earned Value Management
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance R. Scott Brunton, PMP, PMI-RMP/SP, EVP Principal Solutions Consultant Lewis Fowler, LLC www.lewisfowler.com Welcome to the
COINS EVA Earned Value Analysis
COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project
ON THE USE OF SCHEDULE RISK ANALYSIS
OVERVIEW ARTICLE KEYWORDS f schedule risk analysis f Monte-Carlo simulation f change impact analysis r A B S T R A C T The purpose of this paper is to give an overview on the existing literature and recent
Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP
PMP Formulae & Tips Cheat Sheet P a g e Integration Management Develop Project Charter process Project Selection Methods (>> Benefit Measurement Methods >> Economic Models -7) Present Value (PV) FV The
PMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
PROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_cost_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern
(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
TIME FORECASTING USING EARNED SCHEDULE
TIME FORECASTING USING EARNED SCHEDULE THE EUROPEAN EXPERIENCE (WITH THE HELP OF THE US) By Ing. Stephan Vandevoorde Manager Airport Systems, CofelyFabricom Director, EVM Europe Agenda The Start The beginnings
L10: Budgeting and Cost Control. Olivier de Weck
ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen
Simple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
Expert Reference Series of White Papers. Importance of Schedule and Cost Control
Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project
Program and Project Management Practices in the Federal Civilian Agencies
Progress through partnership National Defense Industry Association, Civilian Agencies Industry Working Group Program and Project Management Practices in the Federal Civilian Agencies White Paper Lawrence
Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.
About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints
The To Complete Performance Index
The To Complete Performance Index transforming project performance Walt Lipke 1.1 PMI - Oklahoma City Chapter 1.0 +1 405 364 1594 [email protected] www.earnedschedule.com Index 1.3 1.2 TCPI vs CPI TCPI
Schedule Adherence. and Rework Walt Lipke, PMI Oklahoma City Chapter. PUBLISHER s CHOICE
Schedule Adherence and Rework Walt Lipke, PMI Oklahoma City Chapter Abstract. When project performance is such that the product is delivered with expected functionality at the time and price agreed between
Tracking Software Development Progress with Earned Value and Use Case Point
ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with
PROJECT MANAGEMENT USING DYNAMIC SCHEDULING: BASELINE SCHEDULING, RISK ANALYSIS & PROJECT CONTROL By Mario Vanhoucke
THE MEASURABLE NEWS 2013.02 PROJECT MANAGEMENT USING DYNAMIC SCHEDULING: BASELINE SCHEDULING, RISK ANALYSIS & PROJECT CONTROL By Mario Vanhoucke ABSTRACT The purpose of this article is to give the reader
A Comparison of System Dynamics (SD) and Discrete Event Simulation (DES) Al Sweetser Overview.
A Comparison of System Dynamics (SD) and Discrete Event Simulation (DES) Al Sweetser Andersen Consultng 1600 K Street, N.W., Washington, DC 20006-2873 (202) 862-8080 (voice), (202) 785-4689 (fax) [email protected]
PERCEPTION. Tracking Progress & EAC
PERCEPTION Tracking Progress & EAC 1 Maximize Efficiency Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge their competition. They can focus
Project Cost Management
Project Cost Management Martin Pazderka [email protected] INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda
QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP
QUALITY AND PERFORMANCE IN PROJECTS Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS
How to successfully manage your mega-project
BUILDING, CONSTRUCTION & REAL ESTATE How to successfully manage your mega-project Part II Stakeholder communication and project controls integration kpmg.com 2 Building, Construction & Real Estate How
MTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II)
MTAT.03.244 Software Economics Lecture 6: Software Cost Estimation (part II) Marlon Dumas marlon.dumas ät ut. ee Outline Review of Effort Estimation Homework Discussion on book chapter by Caper Jones Earned
A collection of Safran Project report samples for project professionals
A collection of Safran Project report samples for project professionals Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger www.safran.com Contents Introduction... 2 About the Reports
THE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
Agile Project Management Controls
0 Agile Project Management Controls Issues with EVM and a Viable Alternative: Agile Project Management (PM) Tool ICEAA Conference, June 2015 San Diego, CA Blaze Smallwood, Booz Allen Hamilton Omar Mahmoud,
Basic Concepts of Earned Value Management (EVM)
Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data
Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2
Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2 P.G. Student, Department of Civil & Environmental Engineering, NITTTR, Bhopal,
THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH
THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects
COST PERFORMANCE INDEX STABILITY 1. David S. Christensen Scott R. Heise INTRODUCTION
COST PERFORMANCE INDEX STABILITY 1 David S. Christensen Scott R. Heise INTRODUCTION The Cost Performance Index (CPI) is a key indicator used to analyze cost and schedule performance data reported by defense
Earned Value for Agile Development by John Rusk, Optimation Ltd, 2009, The DACS
Earned Value for Agile Development by John Rusk, Optimation Ltd, 2009, The DACS It s life, Jim, but not as we know it. [attributed to Mr Spock] Just as the Star Trek crew found life in very different forms,
PROJECTS SCHEDULING AND COST CONTROLS
Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to
Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166
Towards a Complete Earned Value Analysis Sam Sharp and Peter Hall Paper # 166 Planned vs Actual A purely accounting approach to project tracking involves the monitoring of status by simply comparing actual