BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant
|
|
|
- Erica Richards
- 10 years ago
- Views:
Transcription
1 BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s as an effective Method for monitoring and managing project performance during implementation and because of its ability to assess Time, Cost and Quality in an integrated manner, EV is undoubtedly significantly superior to antecedent approaches. EVM adoption and utilization was slow at first but following endorsement by the international Project Management Institute (PMI ) as a Best Practice and inclusion in PMI s Project Management Body of Knowledge PMBOK Guide, demands to use EVM have escalated dramatically in recent years. Nevertheless many project managers and their stakeholders are still not using the Earned Value Method (EVM), and are reluctant to adopt it, or if using it are failing to obtain full benefit from EV analysis. There are three prime reasons for this poor follow-through and under-utilization. First, many people (including users) are still simply unclear what exactly EV is. Second, they are often confused by so many EVM indicators & cryptic equations. Third, EVM provides no guidance how to consistently integrate Earned Value indicator results for best effect. Thus, with inadequate project status analysis, many inappropriate conclusions are drawn, flawed recommendations made, and undesirable outcomes continue to occur. Earned Value is without a doubt the Best Practice for integrated monitoring of project implementation performance. Unfortunately, it is not very user-friendly! In preparing for PMI s Project Management Professional (PMP) exam, Earned Value is one of the most difficult topics to tackle, and the biggest obstacle to overcome. However, the following three steps outline a quick & easy approach to understanding and using Earned Value. # 1 -- Understanding Earned Value (EV) First, a clear definition of Earned Value, and what it is not. Earned Value is how much was originally budgeted to complete an activity (or milestone), regardless of when it is (or was) actually completed -- with the caveat that the Value is only Earned when the work is completed. 1 Earned Value is an indicator in monetary form, but Earned Value is NOT Real money. A picture is worth a thousand words, as the Cost vs. Work S-Curve Transform chart in Figure 1 below clearly shows. 1 NOTE: There are some applications of Earned Value -- particularly in the construction industry -- that equate Earned Value to the Percentage of Work Completed. However although such computations are easy to calculate, they tend to defeat the objective of obtaining a usable end product, or attaining an operational end objective.
2 Beyond Earned Value; Kenneth Smith, page 2 Figure 1 The S-Curve Transform The S-Curve above depicts the cumulative cost planned for the cumulative work i.e. the Planned Value -- for each increment of work over the project life. At any point in time (as depicted by the stars) the cumulative incremental Actual Cost is shown. The Earned Value is the intersect of the cost and work on the curve for the cumulative amount of work completed (shown in Figure 1 above as the Target ). The Planned Value for the time period can be read directly on the curve. Thus the S-Curve Transform chart clearly shows exactly what Earned Value is. Furthermore, the chart is useful for the entire life of the project. # 2 Key Indicator Identification, Classification, Prioritization and Performance Metric There are Four (4) primary Driver Indicators in the Earned Value Method (EVM), from which the other sixteen (16) are derived: Three (3) Monetary Indices Five (5) Monetary Values Five (5) Percentages One (1) Scheduled Date, and Two (2) Estimated Project Completion Dates each with cryptic acronynmic equations to compute the actual values such as: Cost Variance $ (CV) = EV - AC % Cost Variance = CV / EV Schedule Variance $ (SV) = EV - PV % Schedule Variance $ = SV / PV to cite only a few. While each EVM indicator is useful in its own right, attempting to assess the total impact of all sixteen -- and how best to use them -- can be bewildering.
3 Beyond Earned Value; Kenneth Smith, page 3 Fortunately, only three of the four Drivers which we have already encountered -- are the keys to understanding and utilizing Earned Value Analysis to assess current status: 1. PV = Planned Value [Also known as the Budgeted Cost of Work Scheduled, BCWS or BS ] The amount originally Planned to be Spent for the Work originally Scheduled to be Done to Date 2. AC = Actual Cost of Work Performed, ACWP or AP The amount Actually Spent for the Work Actually Done to Date Regardless Whether or Not it was Planned &/or Scheduled 3. EV = Earned Value [Also known as the Budgeted Cost of Work Performed, BCWP or BP ] The amount originally Planned to be Spent for the Work Actually Done to Date [i.e. PV: The Baseline Work Budget] The Actual Cost and Earned Value can be 1. Less than (<) 2. the Same as (=), or 3. Greater than (>) the Planned Value. The fourth driver, BAC [= Budgeted Cost at Completion, i.e. the Amount originally Planned to be Spent for the Total Project] is essential for forecasting cost and schedule under-runs or overruns. The key to knowing a project s status at any point in time during project implementation is the juxtaposition of PV, AC and EV. For example (as shown in Figure 2 below) Figure 2 Earned Value Analysis: AC and EV Compared with PV 1. Cumulative Actual Costs as of the schedule are greater than the Planned Value. This indicates a potential problem if funds are released incrementally.
4 Beyond Earned Value; Kenneth Smith, page 4 2. Cumulative Actual Costs for the work successfully completed i.e. the Earned Value -- are also greater than planned. This indicates an actual Cost Overrun. 3. However, since the Earned Value is also greater than the Planned Value as of that date, this indicates that the Project is Ahead of Schedule. Disregarding actual monetary amounts, during project implementation thirteen (13) different comparative rank-ordered PV, AC & EV Constellation combinations are possible. Six (6) of these scenarios are Good ; Four (4) are Mixed while Three (3) are Bad. Rank-ordering the actual array of Project Status scenarios for each alternative provides a new 13 point Project Performance Index. Furthermore, because they can be classified as either Good Mixed or Bad, these 13 status possibilities also systematically highlight the respective status in a tricolor traffic light system, as shown in Figure 3 below. Figure 3 Thirteen (13) Possible Project Status Constellation Combinations These constellation combinations are essentially a Rosetta Stone to quickly and easily identify, monitor and prioritize project implementation performance status. [Although the other seventeen indicators may be useful from time to time to analyze specific issues, most of the benefit to be derived from Earned Value can be obtained from these three indicators, rather than wallowing in the entire package of possible indicators. Essentially, in this case a rifle is better for determining project status than a shotgun approach.] The thirteen color-coded and rank-ordered conditions (with illustrative monetary data) are summarized in Figure 4, below. Figure 4 Integrated Project Performance Indices (PPI) for Assessing a Project s Implementation Status Condition (PSC)
5 Beyond Earned Value; Kenneth Smith, page 5 Situation # [PPI] Planned Cost PV BCWS Actual Cost AC ACWP Earned Value EV BCWP Project Status Condition: PSC 1 $100 $80 $120 Good. Work is ahead of schedule & cost savings. 2 $100 $100 $120 Good. Work is ahead of schedule & cost savings. 3 $100 $80 $100 Good. Work is on schedule, with cost savings. 4 $100 $120 $140 Good. Work is ahead of schedule, with costs savings. [But may have a cash flow problem if funds are released incrementally.] 5 $100 $120 $120 Good. Work is ahead of schedule, with costs as planned for work done. [But may have a cash flow problem if funds are released incrementally.] 6 $100 $100 $100 Ideal. Everything going according to plan On Schedule & Spending. [Extremely Rare!] 7 $100 $60 $80 Mixed Good & Bad. Saving money on the work performed; but work is behind schedule. 8 $100 $120 $100 Mixed Good & Bad. Work on schedule, but cost overrun incurred. [May have a cash flow problem if funds are released incrementally.] 9 $100 $80 $80 Mixed Good & Bad. Spending as planned; but work is behind schedule. 10 $100 $140 $120 Mixed Good & Bad. Work ahead of schedule, but a cost overrun has been incurred. [May have a cash flow problem if funds released incrementally.] 11 $100 $80 $60 Bad. Spending is slower than planned, but the Value is low indicating a cost overrun; and the work is also behind schedule. 12 $100 $100 $80 Bad. Although the spending rate is as planned, since the Value is low, there is a cost overrun; and the work is also behind schedule. 13 $100 $120 $80 Bad. Work behind schedule, cost overrun [and possible cash flow problem.] Despite the plethora of other indicators and possible analyses in the Earned Value Method, the 13 point Project Performance Index encapsulates the overall status (and over time, the project implementation trend) -- somewhat akin to Wall Street s Dow Jones Industrial Index -- for a project manager to present for stakeholder review, assessment, and redress if necessary and feasible. # 3 Computer-assisted Support System Quantitative data is essential to effectively manage project performance, but number-crunching is the bane of many project managers and their staffs. Furthermore, even given formulas appropriate for particular situations and circumstances, computing such data is not very efficient. Instead it is labor-intensive, time-consuming and prone to error. Three Quick & Easy computer-assisted tools overcome this barrier. EVA-2006 is a dedicated program that calculates all EVM indicators (and in addition to US$, another monetary indicator in a currency of your choice), and presents the results in a table for whatever further use is desired. It also displays project status in several graphics. The following format illustrates the graphic presentation for one such condition.
6 Beyond Earned Value; Kenneth Smith, page 6 Figure 5 Summary Status Chart EVA-2006 (Project Management Tool Kit # 65) The comparative graphic shown in Figure 2 is also presented in EVA-2006, together with a tri-color performance quadra-graph and a one page Executive Summary, shown in Figures 6 and 7 below. Figure 6 Summary Tri-Color Quadra-Graph Status Chart EVA-2006 (Project Management Tool Kit # 65)
7 Beyond Earned Value; Kenneth Smith, page 7 Figure 7 Executive Summary Chart EVA-2006 (Project Management Tool Kit # 65) A Project Integrated Performance Excel worksheet template computes and summarizes the project status and performance highlights i.e. the 13 point Project Performance Index, with related criteria as the basis for the assessment, plus key statistics -- the percentage of completion, schedule and cost variance. Figure 8 Project Integrated Performance Status Project Management Tool Kit #66
8 Beyond Earned Value; Kenneth Smith, page 8 Another Excel worksheet Project, Portfolio and Program System computes and summarizes the status of each project in a portfolio or program whether or not they are related -- using the Project Performance Index, as well as the overall summary status of the program or portfolio. Figure 9 Project, Portfolio and Program System Project Management Tool Kit #67 PROJECT MONITORING & EVALUATION The Project Manager s monitoring responsibility goes beyond obtaining and crunching numbers, ratios, indices and percentages derived from the Earned Value indicator drivers. The data should also be presented in an easy-to-understand format. If there is a significant variance in the Project Status Condition from the Plan [as indicated by the Project Performance Index (PPI)] i.e. one of the twelve situations other than #6 (the Ideal ) it should be readily recognized; the issues reviewed, and possible courses of action determined. The aforementioned software and Excel templates in the Project Management Toolkit both crunch numbers and present status results. The toolkit items are all "drop-in-the-data" and "read the analysis" type programs, so no knowledge of the underlying formulas -- or "number crunching" -- is necessary. Furthermore, no new collection effort is required to obtain on-going Earned Value performance data. CONCLUSION Earned Value methodology provides many different indicators for measuring project implementation performance, and they are relatively easy to compute. However, the sheer number of indicators tends to generate confusion amongst project practitioners and stakeholders. Furthermore, since each indicator analyzes the project from a different perspective, there is no consistent One Best Way to guide reviewers in the use and interpretation of these indicators during periodic project reviews. The Project Performance Index described herein, coupled with succinct graphic and computational software fulfills that need with a consistent Quick & Easy systematic approach.
9 Beyond Earned Value; Kenneth Smith, page 9 About the Author Ken Smith is a member of PMI, IPMA & asapm, and an independent project management consultant with many years of experience. He was formerly a management systems specialist, project manager and advisor with several agencies of the US Government and the international development donor community -- i.e. the World Bank Group, the Asian Development Bank and the U.S. Agency for International Development (USAID) -- for developing country government projects. Ken now conducts workshop/seminars in various aspects of project management, monitoring and evaluation. Ken developed the innovations described in this article, and the EVA-2006 software and Excel Templates for computing and displaying the indices are contained in a Project Management Toolkit -- available from [email protected] All trademarks are the property of their registered owners.
An introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
Earned Value and Agile Reporting
Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
Earned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
INSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
The Two Most Useful Earned Value Metrics: the CPI and the TCPI
PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
Chapter 7: Project Cost Management. Munawar [email protected]
Chapter 7: Project Cost Management Munawar [email protected] Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.
Brainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
Introduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
How To Manage A Project
Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management
Project Cost Management
Project Cost Management Martin Pazderka [email protected] INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP
PMP Formulae & Tips Cheat Sheet P a g e Integration Management Develop Project Charter process Project Selection Methods (>> Benefit Measurement Methods >> Economic Models -7) Present Value (PV) FV The
Project Control with ProTrack
Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS
Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1
Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control
COINS EVA Earned Value Analysis
COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project
Expert Reference Series of White Papers. Importance of Schedule and Cost Control
Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project
Project Cost Management
Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present
Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.
About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints
EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS
14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya
Estimating Cost at Completion - Judgment & EV Information
Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number
EVM.01. Earned Value Analysis Why it Doesn't Work
EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects
Using Earned Value Management for Improving Processes. By Cynthia K. West
Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.
Unit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
Simple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
IST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
AACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2
Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2 P.G. Student, Department of Civil & Environmental Engineering, NITTTR, Bhopal,
plans based on actual cost, schedule and technical progress of work [1, 9].
An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan
PERCEPTION. Tracking Progress & EAC
PERCEPTION Tracking Progress & EAC 1 Maximize Efficiency Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge their competition. They can focus
Tracking Budgets and Schedules
Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,
Chapter 3: Project Cost Management
Chapter 3: Project Cost Management Learning Objectives o Understand the importance of project cost management. o Explain basic project cost management principles, concepts, and terms. o Discuss different
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
Assessing Schedule Performance with Earned Value
FEATURED PAPER OCTOBER 2007 Time Is Up: Assessing Schedule Performance with Earned Value By Robert Van De Velde Time drives projects. Quick and accurate evaluation of schedule performance is crucial. Quantitative
Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Rules on using templates 1) Must reference the template used 2) Use
L10: Budgeting and Cost Control. Olivier de Weck
ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate
The outcome of any venture is most often affected by the ready availability of useful information on which timely decisions can be taken. For project success, the need is therefore to know where you re
Earned Value Management for Enterprise Resource Planning Implementations
Earned Value Management for Enterprise Resource Planning Implementations Venu Kotamraju Abstract ERP implementations are a special breed of projects. They are often characterized by aggressive timelines,
PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP
PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP Frequently Asked Questions What is the PMP credential? The PMP (Project Management Professional) credential is a globally recognized certification for
Tracking Software Development Progress with Earned Value and Use Case Point
ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with
Predicting progress on your project
www.nonsuch.co [email protected] Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant
Project Management: Tracking Progress and Earned Value with MS Project 2003
Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain
Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition
Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management
Project Cost Management. Richard Boser
Project Cost Management Richard Boser Project Cost Management Introduction Course Objectives Upon completing today s activities you will be knowledgeable of tools and techniques to: Allocate overall costs
Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166
Towards a Complete Earned Value Analysis Sam Sharp and Peter Hall Paper # 166 Planned vs Actual A purely accounting approach to project tracking involves the monitoring of status by simply comparing actual
PROJECT COST MANAGEMENT
PROJECT COST MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_cost_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 [email protected]
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
Basic Concepts of Earned Value Management (EVM)
Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you
Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes
Lecture Slides for Managing and Leading Software Projects Chapter 8: Measuring and Controlling Work Processes developed by Richard E. (Dick) Fairley, Ph.D. to accompany the tet Managing and Leading Software
Project Duration Forecasting a comparison of Earned Value Management methods to Earned Schedule
Project Duration Forecasting a comparison of Earned Value Management methods to Earned Schedule Walt Lipke Member of Oklahoma City Chapter Project Management Institute (USA) Abstract: Earned Value Management
Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam
Expert Reference Series of White Papers Tips and Techniques to Pass the PMP Exam 1-800-COURSES www.globalknowledge.com Tips and Techniques to Pass the PMP Exam Dan Stober, PMP Introduction Passing the
Appendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. [email protected]
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of
QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP
QUALITY AND PERFORMANCE IN PROJECTS Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS
MTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II)
MTAT.03.244 Software Economics Lecture 6: Software Cost Estimation (part II) Marlon Dumas marlon.dumas ät ut. ee Outline Review of Effort Estimation Homework Discussion on book chapter by Caper Jones Earned
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor
Earned Value Management Guidelines
Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application
Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?
Resource Loading: who and/or what needed where and when. Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded? Resource
technical tips and tricks
technical tips and tricks Earned Value Analysis Overview Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
Why EVM Is Not Good for Schedule Performance Analyses (and how it could be )
Why EVM Is Not Good for Schedule Performance Analyses (and how it could be ) By Radenko Corovic, MBA Abstract Project performance researchers are unanimous that the conventional EVM (Earned Value Management)
Application of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study
2011 International Conference on Management and Service Science IPEDR vol.8 (2011) (2011) IACSIT Press, Singapore Application of Earned Value Management System on an Infrastructure Project: A Malaysian
technical tips and tricks
technical tips and tricks Applying Earned Value Analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
Chapter 5: Project Cost Management
Chapter 5: Project Cost Management 1 Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_risk_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern
PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP
PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP PROJECTS PROGRESS WELL UNTIL 70% Quick progress until 60-70% complete. Then we discover the project is in distress.
EVA (C/SCSC) and Basics of Project Control. Nathaniel Osgood 4/7/2004
EVA (C/SCSC) and Basics of Project Control Nathaniel Osgood 4/7/2004 Topics Monitoring cont d EVA (C/SCSC) Definitions and examples Forecasting Project Control General Performance-adjustments adjustments
10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.
PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition
Basics of Cost and Schedule Control
Basics of Cost and Schedule Control Topics Monitoring and Scheduling: Two Parts of a Feedback System. Definitions Schedule Updates from Monitoring Components of Effective Monitoring Cost Control As A Management
EXAM PREP COURSE. Course Overview. Course Objectives. Course Materials Include: Our PMP Exam Prep (Fifth Edition) training program:
PMP EXAM PREP COURSE Course Overview The purpose of this course is to prepare you to pass the Project Management Professional (PMP) certification exam. The course is based on the 10 knowledge areas in
GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E
C O U R S E C E GPMCEP GLOBAL PROJECT MANAGEMENT, LLC Project Management Professional (PMP) Certification Exam Prep Global Project Management, LLC is a Global Registered Education Provider (R.E.P.) of
What is the Health of my Project?
WHITE PAPER What is the Health of my Project? The Use and Benefits of Earned Value Table of Contents How s My Project Doing?...1 Need a Solution? Earned Value to the Rescue!...1 My actual costs are less
Earned Schedule Leads to Improved Forecasting
Lipke, Walt Norman, Oklahoma, USA Earned Schedule Leads to Improved Forecasting Abstract For project cost, analysts can predict the final value with some confidence using the Independent Estimate at Completion
Project Control. 1. Schedule Updating
Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools
Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.
Project Management ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.2003 1 Project Management - Training Program - Project Scope Management
Project Prioritization
Project Prioritization and Resourcing Once Size Does Not Fit all 2009 Project Management Symposium Breakout Session D Agenda 1. Overview 2. Prioritization 3. Ideas ROI VOI 4. Resourcing 5. Tips Assignment
DEVELOPING A MODEL TO EVALUATE PROJECT PERFORMANCE: CONTRACTOR COMPANY S VIEWPOINT
DEVELOPING A MODEL TO EVALUATE PROJECT PERFORMANCE: CONTRACTOR COMPANY S VIEWPOINT Mohammad Ilbeigi M.Sc. student, School of Civil Engineering, University of Tehran, Tehran, Iran [email protected] Gholamreza
Earned value method as a tool for project control
Budownictwo i Architektura 3 (2008) 15-32 Earned value method as a tool for project control Institute of Construction, Faculty of Civil and Sanitary Engineering, Lublin University of Technology, 20-618
Earned-Value Benchmarks for Re-baselining Your Project
500 Thoreau Street Concord, MA 01742 USA +978.369.9009 [email protected] ($39.95 for 4 PDUs; $59.95 for 6 PDUs) Earned-Value Benchmarks for Re-baselining Your Project Handy benchmarks to help you re-baseline
Planning and Scheduling Your Project Using Microsoft Project 2003
Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering [email protected] Meeting Protocol Agenda Project File Project Calendar Creating
MC9252 SOFTWARE PROJECT MANAGEMENT UNIT I PART A
MC9252 SOFTWARE PROJECT MANAGEMENT UNIT I PART A 1) What is a project? 2) What is software project management? 3) What are the characteristics of a project? 4) What is the different software projects and
performance management system that is based on Earned Schedule Management.
The aim of this presentation is to share lessons learned from using a project performance management system that is based on Earned Schedule Management. Earned Schedule Management is a new method created
Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP
Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program
PMP 2013 Exam Prep. Course Overview
PMP 2013 Exam Prep Course Overview This course has been designed to prepare participants to take the Project Management Institute's Project Management Professional (PMP) Exam, 2013 edition and is based
Earned Value Management Tutorial Module 8: Reporting. Prepared by:
Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.
IMPROVING TRADITIONAL EARNED VALUE MANAGEMENT BY INCORPORATING STATISTICAL PROCESS CHARTS
IMPROVING TRADITIONAL EARNED VALUE MANAGEMENT BY INCORPORATING STATISTICAL PROCESS CHARTS Sou-Sen Leu P.O.Box 90-30, Taipei, [email protected] You-Che Lin P.O.Box 90-30, Taipei, [email protected]
Applied Project Management ( APM )
Applied Project Management Applied Project Management ( APM ) TRAINING PROGRAM Page 1 Of 7 APPLIED PROJECT MANAGEMENT PRO PROGRAM OVERVIEW This course provides in-depth Project Management Training and
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION Author Bill Mowery MPM, PMP Keywords Earned Value Management, Earned Schedule, Project Management, Cost
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling
