1 Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant Te Papa Museum, Wellington

2 A bit about me 25 years experience in project, programme and portfolio management in various countries. For the past 12 years, based in Wellington and servicing customers and clients in NZ and Australia and nearby. I have three children under 13 and when I have time, I enjoy music, reading, fruit trees, cricket, theatre, travel, wine, politics and etymology (the history and study of words). I m a regular presenter at the annual Project Management Conference in NZ and occasionally in Australia: Eddie Obeng Project Types The Zombies of Project Management The Zombies of Programme and Portfolio Management So You think you re ready to be a Consultant? 2

3 Today s session On a Friday afternoon You ve been out partying last night You ve just had lunch Your eyelids are heavy You will fall asleep This is going to be great session, don t you think? 3

4 Predicting progress on your project What are our options? 4

5 Horoscope? Imagine a Scorpio Project Manager! Or a Libran sponsor! 5

6 Crystal Ball? 6

7 Tarot Cards? 7

8 Superstition? 8

9 Mood? 9

10 What is Earned Value Management? Earned Value Management (EVM) is a management methodology for integrating scope, schedule and resources for objectively measuring project performance and progress and for forecasting project outcome It is an industry standard way to: measure a project s progress, forecast its completion date and final cost, and provide schedule and budget variances along the way. 10

11 Earned Value Management In English, please! Okay, think about going to a friend s bbq in a different city to your own Scope driving to a different city to catch up with friends and have a bbq Schedule the time you are due at your friend s place along with an estimated duration of the journey Resources your time, effort and costs involved in the journey However, at some point in the journey, you might find yourself or your partner asking these questions Are we on schedule? Are we running a bit late? What will we do? Are we running a bit too fast? What will we do? Will we get there on time? Will we be late? How late? With Earned Value Management, we can answer these questions confidently and more 11

12 Point in time So, Earned Value Management is about a point in time calculation. In other words, it s about what the future looks like based on performance to this point in time. It s not a fixed prediction but rather a prediction at this point of time that still allows, hopefully, for time to intervene and in some cases wilfully and positively change the final prediction. Today, I will be taking you through the Change Management lifecycle to ensure that I help effect some change in your approach and understanding of Earned Value Management. The first step is Awareness and so I hope I ve just made you aware of Earned Value and what it purports to do. 12

13 Change Management : ADKAR Change Management Unfreeze Move Refreeze Current State Transition State Future State 13 A D K A R Awareness of the need for change Desire to participate and support the change (WIIFM) Knowledge on how to change Ability to implement required skills and behaviours Reinforcement to sustain the change

14 Earned Value What s the problem we re trying to fix here? What s in it for you and your organisation? 14

15 What s the problem? 70% of projects are: Over budget Behind schedule 52% of all projects finish at 189% of their initial budget And some, after huge investments of time and money, are simply never completed! Source: The Standish Group 15

16 Have we done what we said we d do? % complete estimating % of Budget spent % of work done % of time elapsed subjective, incomplete draws false conclusions 16

17 What s More Important Knowing where you are on schedule? Knowing where you are on budget? Knowing where you are on work accomplished? It s difficult to judge one of the three over the other, so in fact all three are equally important. 17

18 EVM Integrates All Three elements It compares the PLANNED amount of work with what has actually been COMPLETED, to determine if COST, SCHEDULE, and WORK ACCOMPLISHED are progressing as planned. Work is Earned or credited as it is completed. By integrating three measurements, it provides consistent, numerical indicators with which you can evaluate and compare projects. 18

19 The challenging questions that EVM answers Are we delivering more or less work than planned? When is the project likely to be completed? Are we currently over or under budget? What is the remaining work likely to cost? What is the entire project likely to cost? How much will we be over or under budget at the end of the project? What is driving the significant cost and/or schedule variances? 19

20 Earned Value is Needed because. it provides an Early Warning Indicator (EWI) for prompt corrective action when there is still time to intervene timely change requests if required There is often a need to roll up progress of many tasks into an overall project status There is a need for a uniform unit of measure (dollars or work-hours). 20

21 Change Management : ADKAR Change Management Unfreeze Move Refreeze Current State Transition State Future State 21 A D K A R Awareness of the need for change Desire to participate and support the change (WIIFM) Knowledge on how to change Ability to implement required skills and behaviours Reinforcement to sustain the change

22 What do I need to get started? You will need a Work Breakdown Structure (WBS)/ Product Breakdown Structure (PBS) It needs to be deliverable or product oriented If it s not in the WBS/PBS, then it is out-of-scope Each descending level represents more detail Full (and accurate) definition is key Defined deliverables/products Timeframe for delivery of deliverables/products Total cost (direct and indirect) to deliver deliverables/products Let s look at an example 22

23 A sample schedule (with a WBS/PBS embedded) 23

24 Requirements of Earned Value Proper PBS/WBS Design Baseline Budget Baseline Schedule Work measurement by work-hours, dollars, units, etc. Good Project Scheduling Practices involving the following: A baselined schedule with costs (as mentioned above) The recording of actual progress on effort and costs The recording of estimates to completion for effort and costs 24

25 Earned Value Terminology Let s learn the terminology. We ll start with the first two: PV Planned Value (Formerly known as BCWS - Budgeted Cost of Work Scheduled) Planned Value is the authorised, time-phased budget assigned to accomplish the scheduled work. At any given point on a time line, PV describes how much of the project work was planned to be performed BAC Budget at Completion The sum of all budgets established for the work to be performed. The project BAC is the sum of all the work package BACs Please note. At the start of a project, before any progress has been made and after budgets have been set and baselined, the PV and BAC are normally identical 25

26 What does it look like? Please note that the PV and BAC are identical at the start of the project before any work commences or any costs are incurred 26

27 It s getting too theoretical. It s Lego time!! 27

28 Grab your worksheet You will build a wall You have 4 minutes You have 100 bricks. 28 You will earn $10 per minute per person and $1 per brick laid

29 [what happened with the audience] I asked them to build a wall like the one displayed here except it was to be 10 bricks wide and 10 bricks high. I promised them 4 minutes and emphasised it wasn t a race and then I abruptly asked them to stop immediately after 2 minutes had passed and to record how many bricks they had laid in their incomplete wall. This number of bricks is significant. 29

30 Work these out PV Planned Value (Formerly known as BCWS - Budgeted Cost of Work Scheduled) Planned Value is the authorised, time-phased budget assigned to accomplish the scheduled work. At any given point on a time line, PV describes how much of the project work was planned to be performed BAC Budget at Completion The sum of all budgets established for the work to be performed. The project BAC is the sum of all the work package BACs Assuming there are 2 builders working on this and based on the assumptions outlined in Slide 28, the answers and workings are: PV = 100 $1 [$100] plus 2 $10/minute for 4 minutes [$80] = $180 BAC = same as above = $180 30

31 The Answer sheet Calculation 2 person teams 3 person teams Planned Value PV $180 $220 Planned Value PV 2 $90 $110 Budget At Completion $180 $220 Cost per brick laid $1.80 $2.20 Note the use of PV with a little 2. This denotes the Planned Value at 2 minutes into the 4 minute estimated duration of the task. This is significant as we use the PV 2 value from here on as we are interested in measuring Earned Value at this point of time, namely 2 minutes into our 4 minute task. Please also note the cost per brick laid. This is significant later on. 31

32 Earned Value Terminology Okay, another two: AC Actual Cost (Formerly known as ACWP - Actual Cost of Work Performed) The realised cost incurred for the work performed on an activity during a specific time period. This can be reported for cumulative to date or for a specific reporting period. EV Earned Value (Formerly known as BCWP Budgeted Cost of Work Performed) The measure of the work performed, expressed in terms of the budget authorised for that work. Earned Value can be reported for cumulative to date or for a specific reporting period. Assuming there are 2 builders working on this and based on the assumptions outlined in Slide 28, and that only 60 bricks have been laid, the answers and workings are on the next slide 32

33 The Answer sheet Category 2 person teams 3 person teams Planned Value PV $180 $220 Planned Value PV 2 $90 $110 Budget At Completion - BAC $180 $220 No. of bricks built = B B B 60 Actual Cost AC (B *$1 ) + Cost of Effort to Date $100 Earned Value EV B * Cost of Bricks Laid $108 33

34 What does it look like? Please note that the EV and the AC are often different values unless we are strictly on target wit progress. 34

35 Some Derived Metrics SV: Schedule Variance (BCWP-BCWS) or (EV PV 2 ) A comparison of amount of work performed during a given period of time/earned value to what was scheduled to be performed/planned value. A negative variance means the project is behind schedule CV: Cost Variance (BCWP-ACWP) or (EV AC) A comparison of the budgeted cost of work performed /earned value with actual cost. A negative variance means the project is over budget. 35

36 The Answer sheet Category 2 person teams 3 person 2 person Planned Value PV $180 $220 $180 Planned Value PV 2 $90 $110 $90 Budget At Completion - BAC $180 $220 $180 No. of bricks built = B B B 60 Actual Cost AC (B *$1 ) + Cost of Effort to Date $100 Earned Value EV B * Cost of Bricks Laid $108 Schedule Variation SV EV - PV 2 $108 - $90 = $18 Cost Variation - CV EV - AC $108 - $100 = $8 36

37 Some More Derived Metrics SPI: Schedule Performance Index SPI=BCWP/BCWS or SPI = EV/PV 2 SPI <1 means project is behind schedule CPI: Cost Performance Index CPI= BCWP/ACWP or CPI = EV/AC CPI <1 means project is over budget CSI: Cost Schedule Index (CSI=CPI x SPI) The further CSI is from 1.0, the less likely project recovery becomes. 37

38 38 The Answer sheet Category 2 person teams 3 person 2 person Planned Value PV 2 $90 $110 $90 Actual Cost AC (B *$1 ) + Cost of Effort to Date $100 Earned Value EV B * Cost of Bricks Laid $108 Schedule Variation SV EV - PV $108 - $90 = $18 Cost Variation - CV EV - AC $108 - $100 = $8 Schedule Performance Index SPI EV/PV 2 $108/$90 = 1.2 Cost Performance Index CPI EV/AC $108/ $100 = 1.08 Cost Schedule Index - CSI CPI x CSI 1.2 * 1.08 = 1.296

39 Making Projections Once a project is 10% complete, the overrun at completion will not be less than the current overrun. Once a project is 20% complete, the CPI does not vary from its current value by more than 10%. The CPI and SPI are statistically accurate indicators of final cost results. Source: Defense Acquisition University 39

40 Today s Challenges Today s executives must achieve critical outcomes, respond rapidly to business changes, and make strategic project decisions earlier than ever in the project life cycle all with increased visibility into the decision-making process. Need for accurate and consistent status information Numerous complex (and interrelated) projects with many activities with many dependencies Project managers are asked to reduce project costs while improving forecasting and to compress schedules while increasing schedule accuracy. 40

41 CPI / SPI charting 41

42 Any shortcomings with Earned Value? Yes, sometimes quantifying/measuring work progress can be difficult. Think about the challenges that Agile project management might throw up. How might you tackle that? Is there value in Earned Value Management for projects using the Agile approach? The time required for data measurement, input, and manipulation can be considerable. You will need to be cognizant of effort curves and ensure you have that built into your baseline Front loaded, back loaded, turtle, double peak, etc. It mustn t be the SOLE arbitrator in making decisions about projets within a portfolio. This is just one perspective in decision making don t forget benefits, strategic alignment, risk etc. 42

43 Change Management : ADKAR Change Management Unfreeze Move Refreeze Current State Transition State Future State 43 A D K A R Awareness of the need for change Desire to participate and support the change (WIIFM) Knowledge on how to change Ability to implement required skills and behaviours Reinforcement to sustain the change

44 So, Is This Stuff New? It s been around since the sixties. It was also known as Cost/Schedule Control Systems Criteria (C/SCSC) 44

45 Do I have to create this from scratch each time? So where do I get one? Buy a prepackaged application. (Lots of them around) Make your own in Microsoft Excel Use Microsoft Project, or Microsoft Project Server Most PMIS (Project Management Information System) applications systems will Earned Value built into their views, reports and tables 45

46 Earned Value Reports & Views 46

47 Earned Value - Tables 47

48 In summary Need to get beyond misleading measures of progress. Earned Value Management will help reduce guesswork in: measuring performance forecasting 48

49 One Final Caveat a positive one Past Performance is Not Necessarily Indicative of Future Results How? If we are using Earned Value, we have time to intervene and help Shape the Future of our project s results 49

50 Change Management : ADKAR Change Management Unfreeze Move Refreeze Current State Transition State Future State 50 A D K A R Awareness of the need for change Desire to participate and support the change (WIIFM) Knowledge on how to change Ability to implement required skills and behaviours Reinforcement to sustain the change

51 Best of luck! Thanks for your attendance For more information or if you have any questions, please contact me on Phone: Website:

Brainstorm. What is Cost and Project Cost Management?

Brainstorm. What is Cost and Project Cost Management? Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,

More information

An introduction to Earned Value Analysis

An introduction to Earned Value Analysis An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many

More information

MTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II)

MTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II) MTAT.03.244 Software Economics Lecture 6: Software Cost Estimation (part II) Marlon Dumas marlon.dumas ät ut. ee Outline Review of Effort Estimation Homework Discussion on book chapter by Caper Jones Earned

More information

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com Chapter 7: Project Cost Management Munawar moenawar@gmail.com Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost

More information

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description

More information

COINS EVA Earned Value Analysis

COINS EVA Earned Value Analysis COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project

More information

Introduction to earn value management in Civil Engineering

Introduction to earn value management in Civil Engineering 3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.

More information

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu

More information

Simple Earned Value (Using MS Project 2010)

Simple Earned Value (Using MS Project 2010) Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained

More information

700 Analysis and Reporting

700 Analysis and Reporting Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference

More information

AACE International Recommended Practice No. 86R 14

AACE International Recommended Practice No. 86R 14 AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment

More information

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Rules on using templates 1) Must reference the template used 2) Use

More information

Using Earned Value Management for Improving Processes. By Cynthia K. West

Using Earned Value Management for Improving Processes. By Cynthia K. West Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.

More information

IST 302 : Project Cost Management

IST 302 : Project Cost Management IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue

More information

Appendix D Glossary Of Terms

Appendix D Glossary Of Terms Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

Chapter 7. (PMBOK Guide)

Chapter 7. (PMBOK Guide) Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

Earned Value and Agile Reporting

Earned Value and Agile Reporting Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,

More information

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management

More information

Chapter 3: Project Cost Management

Chapter 3: Project Cost Management Chapter 3: Project Cost Management Learning Objectives o Understand the importance of project cost management. o Explain basic project cost management principles, concepts, and terms. o Discuss different

More information

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints

More information

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office

More information

Planning and Scheduling Your Project Using Microsoft Project 2003

Planning and Scheduling Your Project Using Microsoft Project 2003 Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering sridhar@sastratechnologies.in Meeting Protocol Agenda Project File Project Calendar Creating

More information

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin

More information

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by: Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective

More information

Earned Value Analysis Exercise

Earned Value Analysis Exercise Earned Value Analysis Exercise www.spmbook.com Author: Adolfo Villafiorita Revision: 2 (205-02-06) Given the following project plan: ID Task Immediate Predecessor (*) Expected Duration (days) Budget ($)

More information

Basics of Cost and Schedule Control

Basics of Cost and Schedule Control Basics of Cost and Schedule Control Topics Monitoring and Scheduling: Two Parts of a Feedback System. Definitions Schedule Updates from Monitoring Components of Effective Monitoring Cost Control As A Management

More information

A Gentle Introduction to Earned Value Management Systems

A Gentle Introduction to Earned Value Management Systems A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com

More information

Chapter 5: Project Cost Management

Chapter 5: Project Cost Management Chapter 5: Project Cost Management 1 Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource

More information

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS 14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya

More information

Project Cost Management

Project Cost Management Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present

More information

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of

More information

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 Kym.Henderson@froggy.com.au

More information

Project Cost Management

Project Cost Management Project Cost Management Martin Pazderka martin.pazderka@inso.tuwien.ac.at INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda

More information

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor

More information

Earned Value Management Guidelines

Earned Value Management Guidelines Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application

More information

Project Management: Tracking Progress and Earned Value with MS Project 2003

Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain

More information

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION Author Bill Mowery MPM, PMP Keywords Earned Value Management, Earned Schedule, Project Management, Cost

More information

Project Management Glossary

Project Management Glossary Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project

More information

QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP

QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP QUALITY AND PERFORMANCE IN PROJECTS Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS

More information

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program

More information

Agile and Earned Value. A white paper. October 2013. Author Stephen Jones, Sellafield Ltd

Agile and Earned Value. A white paper. October 2013. Author Stephen Jones, Sellafield Ltd Agile and Earned Value A white paper October 2013 Author Stephen Jones, Sellafield Ltd This document is a whitepaper produced by the APM Planning, Monitoring and Control SIG. It represents the thoughts

More information

CLARITY PPM TIPS, TRICKS, and TERMINOLOGY

CLARITY PPM TIPS, TRICKS, and TERMINOLOGY CLARITY PPM TIPS, TRICKS, and TERMINOLOGY Clarity PPM Knowledge Sharing Series Helping the Clarity PPM Community Members Benefit from Best Practice TABLE OF CONTENTS 1 OVERVIEW... 3 2 OVERVIEW PAGE...

More information

How To Manage A Project

How To Manage A Project Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management

More information

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

The Two Most Useful Earned Value Metrics: the CPI and the TCPI PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was

More information

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Estimating Cost at Completion - Judgment & EV Information

Estimating Cost at Completion - Judgment & EV Information Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number

More information

Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes

Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes Lecture Slides for Managing and Leading Software Projects Chapter 8: Measuring and Controlling Work Processes developed by Richard E. (Dick) Fairley, Ph.D. to accompany the tet Managing and Leading Software

More information

Earned Value Management System Description

Earned Value Management System Description LCLS Project Management Document # 1.1-015 Project Management Revision 3.0 Earned Value Management System Description Patricia Mast (LCLS Project Controls Manager) Signature Date Mark Reichanadter (LCLS

More information

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Unit 5: Cost Management (PMBOK Guide, Chapter 7) (PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for

More information

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:

More information

Basic Concepts of Earned Value Management (EVM)

Basic Concepts of Earned Value Management (EVM) Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data

More information

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects

More information

Project Control with ProTrack

Project Control with ProTrack Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS

More information

CVR/IT Consulting LLC

CVR/IT Consulting LLC 2011 CVR/IT Consulting LLC All Rights Reserved 1 www.cvr-it.com info@cvr-it.com Overview Easy Earned Value CVR/IT Consulting LLC 2011 CVR/IT Consulting LLC All Rights Reserved 2 Introduction Earned Value

More information

Tracking Budgets and Schedules

Tracking Budgets and Schedules Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is

More information

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Earned Value Management Tutorial Module 8: Reporting. Prepared by: Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.

More information

Tracking Software Development Progress with Earned Value and Use Case Point

Tracking Software Development Progress with Earned Value and Use Case Point ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with

More information

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s

More information

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10. PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition

More information

Earned Value Management Best Practices

Earned Value Management Best Practices Division of Information Technology Investment Management Enterprise Architecture & Strategy Group Office of Information Services Earned Value Management Best Practices Version 2.2 Last Modified: 19 November

More information

What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate

What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate The outcome of any venture is most often affected by the ready availability of useful information on which timely decisions can be taken. For project success, the need is therefore to know where you re

More information

Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?

Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded? Resource Loading: who and/or what needed where and when. Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded? Resource

More information

Project Management System Description (PMSD)

Project Management System Description (PMSD) Project Management System Description (PMSD) Revision 3 Project Management System Description (PMSD) Revision 3 February 2016 Prepared by: Date: Steve Langish Planning & Control Division Approved by: Date:

More information

PERCEPTION. Tracking Progress & EAC

PERCEPTION. Tracking Progress & EAC PERCEPTION Tracking Progress & EAC 1 Maximize Efficiency Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge their competition. They can focus

More information

Application of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study

Application of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study 2011 International Conference on Management and Service Science IPEDR vol.8 (2011) (2011) IACSIT Press, Singapore Application of Earned Value Management System on an Infrastructure Project: A Malaysian

More information

CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT

CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT PREPARED BY James E Aksel, PMP jim@projectpmo.com http://www.msprojectdblog.com http://www.projectpmo.com Page 1 of 19 Table

More information

PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP

PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP PROJECTS PROGRESS WELL UNTIL 70% Quick progress until 60-70% complete. Then we discover the project is in distress.

More information

L10: Budgeting and Cost Control. Olivier de Weck

L10: Budgeting and Cost Control. Olivier de Weck ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen

More information

plans based on actual cost, schedule and technical progress of work [1, 9].

plans based on actual cost, schedule and technical progress of work [1, 9]. An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan

More information

PROJECT SCHEDULING AND TRACKING

PROJECT SCHEDULING AND TRACKING PROJECT SCHEDULING AND TRACKING PROJECT SCHEDULING AND TRACKING Software project scheduling is an activity that distributes estimated effort across the planned project duration by allocating the effort

More information

Earned Value Management

Earned Value Management Earned Value Management Program and Project Management Enablement April 2010 Contact: jjacobi@scottmadden.com cmlyons@scottmadden.com What is Earned Value Management and Why Do I Need It? Complex projects

More information

Project Cost Management

Project Cost Management Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please

More information

EVM.01. Earned Value Analysis Why it Doesn't Work

EVM.01. Earned Value Analysis Why it Doesn't Work EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects

More information

Slides copyright 1996, 2001, 2005, 2009, 2014 by Roger S. Pressman. For non-profit educational use only

Slides copyright 1996, 2001, 2005, 2009, 2014 by Roger S. Pressman. For non-profit educational use only Chapter 34 Project Scheduling Slide Set to accompany Software Engineering: A Practitioner s Approach, 8/e by Roger S. Pressman and Bruce R. Maxim Slides copyright 1996, 2001, 2005, 2009, 2014 by Roger

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Earned Value Analysis Overview Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

Analysis and Application of Earned Value Management in Software Development

Analysis and Application of Earned Value Management in Software Development Analysis and Application of Earned Value Management in Software Development Frank Tsui School of Computing and Software Engineering Southern Polytechnic State University, Marietta, Georgia, USA 30060 Abstract

More information

PROJECT RESOURCES CONTROL

PROJECT RESOURCES CONTROL PROJECT RESOURCES CONTROL PRESENTATION TO PI TEAM MASTER S FORUM Roy A. Maizel Science Mission Directorate NASA Headquarters July 29, 2011 Understanding the Environment NASA is in the discretionary part

More information

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management

More information

Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01

Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01 PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.

More information

What is the Health of my Project?

What is the Health of my Project? WHITE PAPER What is the Health of my Project? The Use and Benefits of Earned Value Table of Contents How s My Project Doing?...1 Need a Solution? Earned Value to the Rescue!...1 My actual costs are less

More information

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166 Towards a Complete Earned Value Analysis Sam Sharp and Peter Hall Paper # 166 Planned vs Actual A purely accounting approach to project tracking involves the monitoring of status by simply comparing actual

More information

Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam

Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam Expert Reference Series of White Papers Tips and Techniques to Pass the PMP Exam 1-800-COURSES www.globalknowledge.com Tips and Techniques to Pass the PMP Exam Dan Stober, PMP Introduction Passing the

More information

Using Earned Value Management Concepts to Improve Commercial Project Performance

Using Earned Value Management Concepts to Improve Commercial Project Performance Using Earned Value Management Concepts to Improve Commercial Project Performance R. Scott Brunton, PMP, PMI-RMP/SP, EVP Principal Solutions Consultant Lewis Fowler, LLC www.lewisfowler.com Welcome to the

More information

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

Expert Reference Series of White Papers. Importance of Schedule and Cost Control Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project

More information

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by: Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you

More information

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761 Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity

More information

Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman

Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

PROJECT TRACKING and CONTROL

PROJECT TRACKING and CONTROL PROJECT TRACKING and CONTROL 1 Outline of Project Tracking & Control 2 Project Planning & Control Context 3 Realistic and Measurable Plans Create Measurable Plans! 4 Data Sources for Project Tracking 5

More information

performance management system that is based on Earned Schedule Management.

performance management system that is based on Earned Schedule Management. The aim of this presentation is to share lessons learned from using a project performance management system that is based on Earned Schedule Management. Earned Schedule Management is a new method created

More information

Module 5 Cost Management PMP Exam Questions

Module 5 Cost Management PMP Exam Questions Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional

More information

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet Project Integration Management Processes required to ensure that the various elements of the project are properly coordinated to meet / exceed stakeholder expectations. Project Plan Development Other ning

More information

Assessing Schedule Performance with Earned Value

Assessing Schedule Performance with Earned Value FEATURED PAPER OCTOBER 2007 Time Is Up: Assessing Schedule Performance with Earned Value By Robert Van De Velde Time drives projects. Quick and accurate evaluation of schedule performance is crucial. Quantitative

More information

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling

More information

Applied Software Project Management

Applied Software Project Management Applied Software Project Management Project Schedules http://www.stellman-greene.com 1 What is a project schedule? The project schedule is a calendar that links the tasks to be done with the resources

More information