Forecasting Project Schedule Completion by Using Earned Value Metrics
|
|
|
- Domenic Rose
- 9 years ago
- Views:
Transcription
1 Forecasting Project Schedule Completion by Using Earned Value Metrics Ing. Stephan Vandevoorde Sr. Project Manager Fabricom Airport Systems 1
2 Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 2
3 Introduction Earned Value Management (EVM) as defined in the 2000 Edition of the PMBOK Guide: A method for integrating scope, schedule and resources, and for measuring project performance. Definition implies equal weight to both cost & schedule Reality is that most EVM metrics focus primarily on cost EVM was developed for cost measurement, not scheduling There is currently a trend to use performance indicators for predicting project duration. 3 methods are presented here. 3
4 Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 4
5 Schedule Variance (SV) SV = Earned Value - Planned Value = EV - PV Positive (+) variance: volume of work performed ahead of plan Negative (-) variance: volume of work performed behind plan SV does not measure time, it measures volume of work done versus planned on same basis (Euros) SV does not identfy work, requires drill down analysis + may be bad: work done not on critical path, offsetting tasks - may be good: work behind has float, offsetting tasks SV is zero at end of project, even when project is late Suggestions for other name: Progress Variance or Accomplishment Variance 5
6 Example - SV Early Finish Project Late Finish Project SV CV SV CV
7 Schedule Performance Index (SPI) SPI = Earned Value / Planned Value = EV / PV SPI > 1: volume of work performed ahead of plan SPI = 1: volume of work perfomred according to plan SPI < 1: volume of work performed behind plan SPI does not have a dimension SPI does not identfy work, requires drill down analysis >1 may be bad: work done not on critical path, offsetting tasks <1 may be good: work behind has float, offsetting tasks SPI equals 1 at end of project: even when project is late, the index shows a perfect schedule performance 7
8 Example - SPI Early Finish Project Late Finish Project 1,200 1,000 1,150 1,100 1,050 1,000 0,950 CPI SPI 0,975 0,950 0,925 0,900 0,875 0,850 0,825 CPI SPI 0, ,
9 Discussion of schedule metrics Strenghts of SV & SPI: provides a reliable early warning Reflects cost/schedule integration Weaknesses of SV & SPI: SV initially follows a trend, but moves towards 0, even if project is late SPI initially follows a trend, but moves towards 1, even is project is late SV & SPI does not indicate the real performance of the project At a certain point in time, the SV & SPI are no more reliable for forecasting purposes. This grey area occurs usually the last third of the project. 9
10 Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 10
11 Generic Formula EDAC = Actual Duration + Estimated Duration Work Remaining EDAC = AD + EDR EDAC = Estimated Duration at Completion AD = Actual Duration ( time now) EDR = Estimated Duration of Remaining Work The EDR is the portion to guess at best The Estimated Duration of Work Remaining is influenced by the project environment 6 types are defined 11
12 Types of EDR Estimates (1) Case 1: new EDR estimate occurs when original assumptions are no longer valid a new estimate (new schedule) needs to be developped forecasting formulas are useless in this case Case 2: EDAC as planned project will be on schedule, even when prior performance is poor f.e. we ll catch up during the testing phase can be dangereous,as unfixed problems don t fix themselves Case 3: EDR substantially higher as planned f.e. additional time is needed to fix various problems estimate in general not quantified more common as we believe 12
13 Types of EDR Estimates (2) Case 4: EDR as planned past schedule problems will not occurr in the future future progress will be according to plan Case 5: EDR will continue with current SPI trend past problems will continue in the future f.e. because of delaying corrective actions, is a realistic case Case 6: EDR will continue with current SCI trend SCI = critical ratio = CPI * SPI used when adherence to budget is critical to organization 13
14 Forecasting Methods Forecast Method Case 1 EDAC = new 2 EDAC as originally planned 3 EDAC is very high Anbari (*) Jacob (**) Lipke (***) re-schedule monitor schedule re-schedule 4 EDR according to plan EDACpv1 EDACed1 EDACes1 5 EDR will follow current SPI trend EDACpv2 EDACed2 EDACes2 6 EDR will follow current SCI trend EDACpv3 EDACed3 EDACes3 EDAC = Estimated Duration at Completion Planned Value Rate Earned Duration Earned Schedule * Earned Value Project Management Method and Extensions, Project Management Journal, Dec ** Forecasting Project Schedule Completion with EV Metrics, The Measurable News, Summer 2004 *** Further Developments in Earned Schedule, The Measurable News, Spring
15 Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 15
16 Method 1: PV Rate PV Rate = BAC / TAC PV Rate = Planned Value Rate ( /month, /week, ) TAC = Time at Completion, number of periods (months, weeks, ) BAC = Budget at Completion TV = SV / PV Rate TV= Time Variance (months, weeks, ) SV = Schedule Variance 16
17 Method 1: PV Rate EDR according to plan EDACpv1 = TAC - TV EDR with continued SPI performance EDACpv2 = TAC / SPI EDR with continued SCI performance EDACpv3 = TAC / SCI 17
18 Method 1: example Scope: TAC: install 350 TFT Monitors, 50 monitors / week 7 weeks BAC: (100 / monitor) W1 W2 W3 W4 W5 W6 W7 PV AC EV SPI 0,70 0,85 0,80 CPI 0,93 0,93 0,94 SCI 0,65 0,79 0,75 PV Rate = BAC / TAC = / 7 = / week TV = SV / PV Rate = ( ) / = -0,6 weeks EDACpv1 = TAC - TV = 7 - (-0,6) = 7,6 weeks EDACpv2 = TAC / SPI = 7 / 0,80 = 8,75 weeks EDACpv3 = TAC / SCI = 7 / 0,75 = 9,33 weeks 18
19 Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 19
20 Method 2: ED Method ED = AD * SPI ED = Earned Duration AD = Actual Duration SPI = Schedule Performance Index EDAC = AD + (TAC - ED) / P.F. EDAC= Estimated Duration at Completion TAC = Time at Completion ED = Earned Duration P.F. = Performance factor (according to different cases) 20
21 Method 2: ED Method EDR according to plan (P.F. = 1) EDACed1 = AD + (TAC - ED) / 1 = TAC + AD x (1 - SPI) EDR with continued SPI performance (P.F. = SPI) EDACed2 = AD + (TAC - ED) / SPI = TAC / SPI EDR with continued SCI performance proposed in reference: EDACed3 = TAC / SCI mathematically correct: EDACed3m = TAC / SCI + AD x (1-1/CPI) 21
22 Method 2: Extension Corrective action metric: TCSPI TCSPI = (TAC - ED) / (TAC - AD) TCSPI = To Complete Schedule Performance Index a measure of the required performance needed to bring in the project on the planned time TCSPI = (TAC - ED) / (EDAC - AD) TCSPI = To Complete Schedule Performance Index a measure of the required performance needed to bring in the project on the estimated EDAC time 22
23 Method 2: Extension What when work is not finished and planned duration is passed? Mathematically: AD > PD and SPI < 1 TAC is being replaced by AD EDACed1 = AD (2 - SPI) EDACed2 = AD / SPI EADCed3 = AD / SCI EADCed3m = AD (1-1/CPI + 1/SCI) 23
24 Method 2: example Scope: TAC: install 350 TFT Monitors, 50 monitors / week 7 weeks BAC: (100 / monitor) W1 W2 W3 W4 W5 W6 W7 PV AC EV SPI 0,70 0,85 0,80 CPI 0,93 0,93 0,94 SCI 0,65 0,79 0,75 ED = AD x SPI = 3 x 0,8 = 2,4 weeks EDACed1 = TAC + AD (1 - SPI) = (1-0,80) = 7,6 weeks EDACed2 = TAC / SPI = 7 / 0,80 = 8,75 weeks EDACed3 = TAC / SCI = 7 / 0,75 = 9,33 weeks EDACed3m = TAC / SCI + AD (1-1/CPI) = 9,14 weeks 24
25 Method 2: example Scope: TAC: install 350 TFT Monitors, 50 monitors / week 7 weeks BAC: (100 / monitor) W1 W2 W3 W4 W5 W6 W7 PV AC EV SPI 0,70 0,85 0,80 CPI 0,93 0,93 0,94 SCI 0,65 0,79 0,75 TCSPI = (TAC - ED) / (TAC - AD) = (7-2,4) / (7-3) = 1,15 TCSPI = (TAC - ED) / (EDACed1 - AD) = 1,00 TCSPI = (TAC - ED) / (EDACed2 - AD) = 0,80 TCSPI = (TAC - ED) / (EDACed3 - AD) = 0,73 TCSPI = (TAC - ED) / (EDACed3m - AD) = 0,75 25
26 Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 26
27 Method 3: Earned Schedule Idea of Earned Schedule is identical as Earned Value Instead of using cost for measuring schedule performance, we will use time Earned Schedule is determined by comparing Earned Value to the performance baseline (= planned value). The time associated with the Earned Value is found from the PV-curve. So we project the Earned Value onto the Planned Value curve 27
28 EV vs. ES - Graphical Display AC CV AC Projection of EV onto PV PV SV PV EV EV time ES AT Earned Value Earned Schedule time 28
29 ES Calulation ES = N + (EV - PV N ) / (PV N+1 - PV N ) ES = Earned Schedule N = time increment of PV that is less than current PV PV N = Planned Value at time N PV N+1 = Planned Value at time N + 1 PV N = 2 EV I M1 M2 M3 M4 M5 time ES AT = PT 29
30 ES Derived Metrics Derived metrics, similar to the classical Earned Value: SV(t) = ES - AT positive = ahead of schedule negative = lagging SPI(t) = ES / AT >1 = ahead of schedule >1 = lagging EDAC = AT + Estimated Remaining Time to Completion = AT + (TAC - ES) / P.F. 30
31 ES Forecasting EDR according to plan (P.F. = 1) EDACes1 = AD + (TAC - ES) EDR with continued SPI(t) performance EDACes2 = AD + (TAC - ES) / SPI(t) EDR with continued SPI performance EDACes3 = AD + (TAC - ES) / SCI(t) Corrective Action Metric TCSPI(t) = (TAC - ES) / (TAC - AT) 31
32 Method 3: example Scope: TAC: install 350 TFT Monitors, 50 monitors / week 7 weeks BAC: (100 / monitor) W1 W2 W3 W4 W5 W6 W7 PV AC EV N ES 0,70 1,70 2,40 SPI(t) 0,70 0,85 0,80 SCI(t) 0,65 0,79 0,75 EDACes1 = AD + (TAC - ES) = 3 + (7-2,4) = 7,6 weeks EDACes2 = AD + (TAC - ES) / SPI(t) = 8,75 weeks EDACes3 = AD + (TAC - ES) / SCI(t) = 9,33 weeks TCSPI(t) = (TAC - ES) / (TAC - AT) = (7-2,4) / (7-3) = 1,15 32
33 Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 33
34 Summary of Results Forecast Method Case 1 EDAC = new 2 EDAC as originally planned 3 EDAC is very high Anbari (*) Jacob (**) Lipke (***) re-schedule monitor schedule re-schedule 4 EDR according to plan 7,60 7,60 7,60 5 EDR will follow current SPI trend 8,75 8,75 8,75 6 EDR will follow current SCI trend 9,33 9,33 (9,14) 9,33 Planned Value Rate Earned Duration Earned Schedule All results are the same! Why? 34
35 Why are Results the Same? All methods apply the same basic parameters (EV, PV, ) All methods are based on sound analytical thought Formulas used in methods are linear, as well as the used PV in the example. If the PV is non-linear, differences between the methods could be introduced. These errors can be reduced by using smaller time increments (more reporting periods) 35
36 Non Linear PV Rate Scope: TAC: install 350 TFT Monitors, including learning curve 7 weeks BAC: (100 / monitor) W1 W2 W3 W4 W5 W6 W7 PV AC EV SPI 2,33 2,13 1,60 CPI 0,93 0,93 0,94 SCI 2,18 1,98 1,51 AT ES 1,80 4,00 4,00 SPI(t) 1,80 2,00 1,33 SCI(t) 1,68 1,87 1, PV W1 W2 W3 W4 W5 W6 W7 36
37 Results - Non Linear PV - W3 Forecast Method Case 1 EDAC = new 2 EDAC as originally planned 3 EDAC is very high Anbari (*) Jacob (**) Lipke (***) re-schedule monitor schedule re-schedule 4 EDR according to plan 6,10 5,20 6,00 5 EDR will follow current SPI trend 4,38 4,38 5,25 6 EDR will follow current SCI trend 4,65 4,65 5,39 Planned Value Rate Earned Duration Earned Schedule 37
38 Discussion Results are no longer identical, and depends on used method. The Earned Schedule method appears to forecast higher durations, compared with other methods. But most important: So far we applied the formulas to a single activity. How do the methods behave on higher WBS levels? Which method is the best? 38
39 Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level Case Study Conclusion 39
40 Case Study xxx C.I. 6 - R11/12 Scope: revamping of C.I. Island BAC: TAC: 9 months WBS: Project Level 0 juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 AC EV PV BAC 40
41 Case Study - EV Metrics juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 AC EV PV SV SPI 0,89 0,83 0,97 0,90 0,91 0,89 0,90 0,89 0,87 0,91 0,94 0,97 1, , , juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 SV CV 1,000 0,950 0,900 0,850 0,800 juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 SPI CPI 41
42 Case Study - ES Calulation juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 AC EV PV SV SPI 0,89 0,83 0,97 0,90 0,91 0,89 0,90 0,89 0,87 0,91 0,94 0,97 1,00 ###### ###### 10, , , , , , , , , , , , AT ES 0,885 1,742 2,745 3,716 4,756 5,600 5,881 6,201 6,491 7,183 7,676 8,268 9,000 PT SV(t) -0,115-0,258-0,255-0,284-0,244-0,400-1,119-1,799-2,509-2,817-3,324-3,732-4,000 SPI(t) 0,89 0,87 0,92 0,93 0,95 0,93 0,84 0,78 0,72 0,72 0,70 0,69 0,69 Example ES Calculation (period 09/02, 4th period): ES = 3 + ( ) / ( ) = 3,716 months Example ES Calculation (period 01/03, 8th period): ES = 6 + ( ) / ( ) = 6,201 months 42
43 Case Study - ES Calulation juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 AT ES 0,885 1,742 2,745 3,716 4,756 5,600 5,881 6,201 6,491 7,183 7,676 8,268 9,000 PT SV(t) -0,115-0,258-0,255-0,284-0,244-0,400-1,119-1,799-2,509-2,817-3,324-3,732-4,000 SPI(t) 0,89 0,87 0,92 0,93 0,95 0,93 0,84 0,78 0,72 0,72 0,70 0,69 0,69 Example SPI(t) Calculation (period 12/02, 7th period): SPI(t) = 5,881 / 7 = 0,84 Project is progressing at at a rate of 0,78 months for each month of actual time Example SV(t) Calculation (period 12/02, 7th period): SV(t) = 5,881-7 = - 1,119 Project lags it expected performance by 1,119 months 43
44 Case Study - SV vs. SV(t) ,0-0,5-1,0-1,5-2,0-2,5-3,0-3,5-4,0-4,5-5,0 44 Euros juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 Months SV SV(t)
45 Case Study - SPI vs. SPI(t) In this timeframe, SPI & SPI(t) correlates very well AT 11/02, or at the ca. 75% completion point, the SPI becomes unreliable 1,00 0,95 0,90 0,85 0,80 0,75 0,70 0,65 juin-02 juil-02 août-02 sept-02 oct-02 nov-02 déc-02 janv-03 févr-03 mars-03 avr-03 mai-03 juin-03 SPI SPI(t) 45
46 Case Study - EDAC P.F. = At 11/02, or at the ca. 75% completion point, the IDACes is clearly more accurate /02 07/02 08/02 09/02 10/02 11/02 12/02 01/03 02/03 03/03 04/03 05/03 06/03 EDACpv 9,08 9,34 9,06 9,33 9,48 9,84 9,78 9,98 10,19 9,82 9,55 9,27 9,00 EDACed 9,11 9,33 9,08 9,39 9,44 9,67 9,67 9,91 10,19 10,92 11,67 12,36 13,00 EDACes 9,11 9,26 9,25 9,28 9,24 9,40 10,12 10,80 11,51 11,82 12,32 12,73 13,00 PV Rate Method: correlates well at early stages, but is useless towards the end ED Method: correlates well till 75% completion point ES Method: predicts more accurate towards the final stages 46
47 Case Study - EDAC P.F. = SPI At 11/02, or at the ca. 75% completion point, the IDACes is clearly more accurate /02 07/02 08/02 09/02 10/02 11/02 12/02 01/03 02/03 03/03 04/03 05/03 06/03 EDACpv 10,17 10,80 9,26 9,96 9,88 10,13 9,96 10,15 10,38 9,91 9,59 9,28 9,00 EDACed 10,17 10,80 9,26 9,96 9,88 10,13 9,96 10,15 10,38 11,01 11,72 12,37 13,00 EDACes 10,17 10,33 9,83 9,69 9,46 9,64 10,71 11,61 12,48 12,53 12,90 13,06 13,00 PV Rate Method: correlates well at early stages, but is useless towards the end ED Method: correlates well till 75% completion point ES Method: predicts more accurate towards the final stages 47
48 Case Study - EDAC P.F. = SCI At 11/02, or at the ca. 75% completion point, the IDACes is clearly more accurate /02 07/02 08/02 09/02 10/02 11/02 12/02 01/03 02/03 03/03 04/03 05/03 06/03 EDACpv 10,14 10,52 8,13 9,87 9,51 9,79 9,73 9,62 10,07 9,57 9,08 8,93 8,72 EDACed 10,14 10,52 8,13 9,87 9,51 9,79 9,73 9,62 10,07 10,63 11,09 11,91 12,59 EDACes 10,14 10,12 9,00 9,64 9,30 9,52 10,62 11,42 12,37 12,44 12,80 13,02 13,00 PV Rate Method: correlates well at early stages, but is useless towards the end ED Method: correlates well till 75% completion point ES Method: predicts more accurate towards the final stages 48
49 Case Study - ED vs. ES AT ES PT EDACed PF=SPI EDACes PF=SPI(t) EDACed PF=SCI EDACes PF=SCI(t)
50 Discussion During early and middle project stage All methods seems to correlate well All methods produce same results within the same range During late project stage The PV Rate method is useless and meaningless (at project level, the PV is non-linear, but follows a S- curve) The ED method tends to underestimate the final duration ( remember the strange SPI behaviour, the grey area ) The ES method produces the best forecast results 50
51 Other example (presentation 2) AT PT ES EDACes spi(t) EDACed spi At M6-7, or at the ca. 70% completion point, the IDACes is clearly more accurate M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 51
52 Agenda Introduction Schedule performance indicators Schedule forecasting generic formula Method 1: Use of PV Rate (Planned Value Rate) Method 2: Use of ED (Earned Duration) Method 3: Use of ES (Earned Schedule) Discussion of different methods Forecasting at project level - Case Study Conclusion 52
53 Schedule Forecasting The use of EV metrics to forecast the schedule should happen at least on the overall project level (early warning signal): for early and middle poject stages, each method can be used for late project stage (mostly the most important period), the ES method produces clearly the best results When performance is poor, a drill-down into the lower WBS levels will help detect the troubled tasks If tasks are on the critical path, evaluation of the forecasted duration impact ca be made The use of earned duration and earned schedule metrics is NOT a replacement for scheduling tools such as PERT, CPM, Monte Carlo scheduling 53
54 Forecasting Methods At early and middle stage Forecast Method PV Rate ED ES EDR according to plan TAC - TV TAC + AD (1 - SPI) AD + (TAC - ES) EDR will follow current SPI trend TAC / SPI TAC / SPI AD + (TAC - ES) / SPI(t) EDR will follow current SCI trend TAC / SCI TAC / SCI AD + (TAC - ES) / SPI(t) At late stage Forecast Method PV Rate ED ES EDR according to plan AD + (TAC - ES) EDR will follow current SPI trend AD + (TAC - ES) / SPI(t) EDR will follow current SCI trend AD + (TAC - ES) / SPI(t) 54
55 Conclusion SPI & SV indicators are flawed and exhibit strange behaviour over the final third of the project, and are as a consequence not reliable. The use of the Earned Schedule method provides indicators SPI(t) & SV(t), which behave correctly during the project life. It has been demonstrated that the use of ES metrics provides a more reliable forecast for total project duration. Why not starting to use the earned schedule method as a standard procedure? 55
Why EVM Is Not Good for Schedule Performance Analyses (and how it could be )
Why EVM Is Not Good for Schedule Performance Analyses (and how it could be ) By Radenko Corovic, MBA Abstract Project performance researchers are unanimous that the conventional EVM (Earned Value Management)
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 [email protected]
Project Control with ProTrack
Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS
Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1
Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control
Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
TIME FORECASTING USING EARNED SCHEDULE
TIME FORECASTING USING EARNED SCHEDULE THE EUROPEAN EXPERIENCE (WITH THE HELP OF THE US) By Ing. Stephan Vandevoorde Manager Airport Systems, CofelyFabricom Director, EVM Europe Agenda The Start The beginnings
PROJECTS SCHEDULING AND COST CONTROLS
Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to
Earned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
Earned Schedule Leads to Improved Forecasting
Lipke, Walt Norman, Oklahoma, USA Earned Schedule Leads to Improved Forecasting Abstract For project cost, analysts can predict the final value with some confidence using the Independent Estimate at Completion
Assessing Schedule Performance with Earned Value
FEATURED PAPER OCTOBER 2007 Time Is Up: Assessing Schedule Performance with Earned Value By Robert Van De Velde Time drives projects. Quick and accurate evaluation of schedule performance is crucial. Quantitative
IST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
Using Earned Value Management for Improving Processes. By Cynthia K. West
Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.
Schedule Adherence a useful measure for project management
Schedule Adherence a useful measure for project management Walt Lipke PMI Oklahoma City Chapter Abstract: Earned Value Management (EVM) is a very good method of project management. However, EVM by itself
Abstract. Earned Value Management Basics
Earned Schedule: A Breakthrough Extension to Earned Value Management Kym Henderson Education Director, Project Management Institute, Sydney Australia Chapter Abstract Earned Schedule (ES) analysis is a
PROJECT MONITORING AND CONTROL USING BURNDOWN CHARTS
The 4 th edition of the Interdisciplinarity in Engineering International Conference Petru Maior University of Tîrgu Mureş, Romania, 2009 PROJECT MOITORIG AD COTROL USIG BURDOW CHARTS Attila Vajda Sysgenic
Project Cost Management
Project Cost Management Martin Pazderka [email protected] INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION Author Bill Mowery MPM, PMP Keywords Earned Value Management, Earned Schedule, Project Management, Cost
An introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Rules on using templates 1) Must reference the template used 2) Use
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
Earned value method as a tool for project control
Budownictwo i Architektura 3 (2008) 15-32 Earned value method as a tool for project control Institute of Construction, Faculty of Civil and Sanitary Engineering, Lublin University of Technology, 20-618
Introduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
INSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.
About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints
700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
performance management system that is based on Earned Schedule Management.
The aim of this presentation is to share lessons learned from using a project performance management system that is based on Earned Schedule Management. Earned Schedule Management is a new method created
Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB
Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin
Project Cost Management
Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present
Earned Schedule application to Project Management
Earned Schedule application to Project Management Walt Lipke PMI - Oklahoma City +1 405 364 1594 [email protected] www.earnedschedule.com $$ The ES idea is to determine the time at which the EV accrued
Brainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
earned value management
earned value management in control of big productions an eyeon white paper october 2013 1 contents 4 ly escalation 5 linking and cost control 6 cost forecasting 6 implementation towards effective project
Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166
Towards a Complete Earned Value Analysis Sam Sharp and Peter Hall Paper # 166 Planned vs Actual A purely accounting approach to project tracking involves the monitoring of status by simply comparing actual
Estimating Cost at Completion - Judgment & EV Information
Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number
How To Manage A Project
Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
The Two Most Useful Earned Value Metrics: the CPI and the TCPI
PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was
AACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. [email protected]
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of
L10: Budgeting and Cost Control. Olivier de Weck
ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen
Schedule Adherence. and Rework Walt Lipke, PMI Oklahoma City Chapter. PUBLISHER s CHOICE
Schedule Adherence and Rework Walt Lipke, PMI Oklahoma City Chapter Abstract. When project performance is such that the product is delivered with expected functionality at the time and price agreed between
EVM.01. Earned Value Analysis Why it Doesn't Work
EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects
Earned Value and Agile Reporting
Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
A Gentle Introduction to Earned Value Management Systems
A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP
PMP Formulae & Tips Cheat Sheet P a g e Integration Management Develop Project Charter process Project Selection Methods (>> Benefit Measurement Methods >> Economic Models -7) Present Value (PV) FV The
Simple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
Tracking Budgets and Schedules
Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is
Earned Value Management Tutorial Module 8: Reporting. Prepared by:
Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.
QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP
QUALITY AND PERFORMANCE IN PROJECTS Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS
Schedule Analysis Using Earned Value Concepts ABSTRACT
G.R. Cathcart & Erica Smith ABSTRACT Tecolote has developed a procedure to compare two schedules to determine if activities are ahead of or behind schedule. For on-going activities, we calculate the rate
Chapter 7: Project Cost Management. Munawar [email protected]
Chapter 7: Project Cost Management Munawar [email protected] Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01
PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.
Expert Reference Series of White Papers. Importance of Schedule and Cost Control
Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project
Predicting progress on your project
www.nonsuch.co [email protected] Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant
EVA (C/SCSC) and Basics of Project Control. Nathaniel Osgood 4/7/2004
EVA (C/SCSC) and Basics of Project Control Nathaniel Osgood 4/7/2004 Topics Monitoring cont d EVA (C/SCSC) Definitions and examples Forecasting Project Control General Performance-adjustments adjustments
Earned Value Management Guidelines
Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application
Schedule Compression
Schedule Compression The need to reduce the time allowed for a schedule, or a part of a schedule is routine, some of the times the need arises include: When the initial schedule is too long to meet contractual
The To Complete Performance Index
The To Complete Performance Index transforming project performance Walt Lipke 1.1 PMI - Oklahoma City Chapter 1.0 +1 405 364 1594 [email protected] www.earnedschedule.com Index 1.3 1.2 TCPI vs CPI TCPI
PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and
Project Duration Forecasting a comparison of Earned Value Management methods to Earned Schedule
Project Duration Forecasting a comparison of Earned Value Management methods to Earned Schedule Walt Lipke Member of Oklahoma City Chapter Project Management Institute (USA) Abstract: Earned Value Management
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling
Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?
Resource Loading: who and/or what needed where and when. Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded? Resource
Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional
Selftestengine..PMI-SP.270 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 5.1 PMI-SP PMI Scheduling Professional This study guides are so comprehensible that anyone can understand
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management.
SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management. Fatima Boumahdi, Rachid Chalal Abstract This paper presents an architecture for the Project Management,
Applying Fuzzy Control Chart in Earned Value Analysis: A New Application
World Applied Sciences Journal 3 (4): 684-690, 2008 ISSN 88-4952 IDOSI Publications, 2008 Applying Fuzzy Control Chart in Earned Value Analysis: A New Application Siamak Noori, Morteza Bagherpour and Abalfazl
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective
Project Time Management
Project Academy Series Project Time Management 01/22/2015 01/23/2015 Welcome and Introductions Ramaswamy Adisesh: Data Processing Manager III California Project Management Office Department of Technology
PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP
PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP Frequently Asked Questions What is the PMP credential? The PMP (Project Management Professional) credential is a globally recognized certification for
Unit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
Application of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study
2011 International Conference on Management and Service Science IPEDR vol.8 (2011) (2011) IACSIT Press, Singapore Application of Earned Value Management System on an Infrastructure Project: A Malaysian
plans based on actual cost, schedule and technical progress of work [1, 9].
An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan
PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP
PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP PROJECTS PROGRESS WELL UNTIL 70% Quick progress until 60-70% complete. Then we discover the project is in distress.
THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH
THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects
FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011
FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight Outline EVMS History at the Lab FRA EVMS Documents
A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry
A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry Pranam B 1, Madhusudan G Kalibhat 2, Sudharshan KR 3 1 Student, Master of Technology (Construction
PERCEPTION. Tracking Progress & EAC
PERCEPTION Tracking Progress & EAC 1 Maximize Efficiency Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge their competition. They can focus
Project Control. 1. Schedule Updating
Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools
Create Stoplight charts using Milestones Professional
Stoplight Charts: Ideal for At-a-Glance Project Reporting Create Stoplight charts using Milestones Professional In a report which has extensive data, how can action items be quickly highlighted and addressed?
Earned Value Analysis Exercise
Earned Value Analysis Exercise www.spmbook.com Author: Adolfo Villafiorita Revision: 2 (205-02-06) Given the following project plan: ID Task Immediate Predecessor (*) Expected Duration (days) Budget ($)
Monitoring Scrum Projects with AgileEVM and Earned Business Value (EBV) Metrics
Monitoring Scrum Projects with AgileEVM and Earned Business Value (EBV) Metrics By Dan Rawsthorne, PhD, CST Scrum is a popular project management framework for agile projects. Scrum projects are typically
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management
Project Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E
C O U R S E C E GPMCEP GLOBAL PROJECT MANAGEMENT, LLC Project Management Professional (PMP) Certification Exam Prep Global Project Management, LLC is a Global Registered Education Provider (R.E.P.) of
Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015
Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2
Towards a Multi-Dimensional Framework for Assessing the Value of. Software Projects
Towards a Multi-Dimensional Framework for Assessing the Value of Software Projects by John Richard Kopp Submitted in partial fulfillment of the requirements for the Master s degree in Software Development
DCMA DCMA-EA PAM 200.1. October 2012
DCMA Earned Value Management System (EVMS) Program Analysis Pamphlet (PAP) DCMA-EA PAM 200.1 October 2012 THE DCMA ENGINEERING AND ANALYSIS EXECUTIVE DIRECTOR IS RESPONSIBLE FOR ISSUANCE AND MAINTENANCE
Agile Project Management Controls
0 Agile Project Management Controls Issues with EVM and a Viable Alternative: Agile Project Management (PM) Tool ICEAA Conference, June 2015 San Diego, CA Blaze Smallwood, Booz Allen Hamilton Omar Mahmoud,
Chapter 6. (PMBOK Guide)
Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP
Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program
