Brief Introduction to Earned Value Management (EVM)
|
|
|
- Samson Bradford
- 10 years ago
- Views:
Transcription
1 Brief Introduction to Earned Value Management (EVM) 12/25/06 EVM Introduction 1 12/25/06 EVM Introduction 1
2 Outline Introduction to the basic rationale and elements of EVM Issues of actually implementing an EVM tracking scheme Background materials 12/25/06 EVM Introduction 2 12/25/06 EVM Introduction 2
3 The Problem A successful program manager says: We completed the project we promised to deliver in the time we promised and with the budget we asked for. The standard source of information about the status of the project is the status of the budget, which only tells you how quickly and how completely you are spending the money you have. What you really want to track is how quickly and how completely you are accomplishing the work you promised to do. The coupling of money spent to work done or schedule consumed is loose and nonlinear. Also, the expenditure track is a one-dimensional projection of a two-dimensional problem. (behind) (under) Budget Variance 12/25/06 EVM Introduction 3 Schedule Variance 12/25/06 EVM Introduction 3 (over) (ahead)
4 Why You Need to Know Both Cost and Schedule Variances Project A is in good shape, under budget and ahead of schedule. Project B is over budget, but if we realize Budget (under) Variance it is ahead of schedule, we can slow the effort to save money. Project D s cost variance looks D A better than A s, but if we (behind) (ahead) realize it is behind schedule, Schedule we can spend more to catch up. Variance Project C looks just like B if we only look at the cost variance, but C B we can t slow down to save money. (over) And it looks just like D if we only look at schedule, but we can t spend more to catch up. It s time to rescope! 12/25/06 EVM Introduction 4 12/25/06 EVM Introduction 4
5 So What Do We Have to Work With? 1. DEFINE THE WORK AND ORGANIZE TEAMS CONTRACT BUDGET BASE MANAGEMENT RESERVE (MR) 2. SCHEDULE THE WORK 3. ALLOCATE BUDGETS $ Each chunk of work corresponds to a chunk of budget and a chunk of schedule. BASELINE TIME 12/25/06 EVM Introduction 5 12/25/06 EVM Introduction 5
6 The Basic Idea For each chunk of work, define its value as the budget assigned to it. When you complete that chunk of work, you have earned its value. The total earned value to date gives you a point on the ($,time) graph the Budgeted Cost of Work Performed (BCWP). You could compare this to the actual amount of work that you were supposed to have completed by this point in the schedule, as measured by its budgeted cost the Budgeted Cost of Work Scheduled (BCWS), another point on the ($,time) graph. You could also compare it to the actual amount spent to complete the chunks of work done to date the Actual Cost of Work Performed (ACWP), a third point on the ($,time) graph. Look at what information these comparisons give about the status of the project. 12/25/06 EVM Introduction 6 12/25/06 EVM Introduction 6
7 Budgeted Cost of Work Scheduled (BCWS) Month 1 BCWS = $1,000 Month 2 BCWS = $1,000 Month 3 BCWS = $1,000 Total Budget = $5,000 to be spent over 5 months We plan to deploy 1 stand each month at an estimated cost of $1,000. BCWS each month = $1,000 Month 4 BCWS = $1,000 Month 5 BCWS = $1,000 Each Each dollar dollar of of BCWS BCWS represents a specific dollar dollar of of work work scope. scope. BCWS BCWS is is aggregated and and summed as as the the performance measurement baseline. 12/25/06 EVM Introduction 7 12/25/06 EVM Introduction 7
8 Budgeted Cost of Work Performed (BCWP) We re at the end of the second month, but only 1 stand is complete. Value of work performed = $1,000 You You earn earn value value the the same same way way as as it it was was budgeted in in the the baseline. 12/25/06 EVM Introduction 8 12/25/06 EVM Introduction 8
9 Schedule Variance (SV) BUDGET BASED BC WS BC WP Of the work we scheduled to have done, how much did we budget for it to cost? Of the work we actually performed, how much did we budget for it to cost? SCHEDULE VARIANCE is is the the difference between work work scheduled and and work work performed (expressed in in terms terms of of budget budget dollars) dollars) formula: SV SV $ = BCWP --BCWS example: SV SV = BCWP BCWP --BCWS BCWS = $1,000 $1, $2,000 $2,000 SV= SV= -$1,000 (negative = behind behind schedule) 12/25/06 EVM Introduction 9 12/25/06 EVM Introduction 9
10 Schedule Variance (SV) 5,000 $ sv BCWS the baseline BCWP earned value TIME 5 months 12/25/06 EVM Introduction 10 12/25/06 EVM Introduction 10
11 Actual Cost of Work Performed (ACWP) Labor came to $1,300, and materials cost $1,100. That first stand cost $2,400! actual expenditures vs. vs. budget 12/25/06 EVM Introduction 11 12/25/06 EVM Introduction 11
12 Cost Variance (CV) BC WP AC WP PERFORMANCE BASED Of the work we actually performed, how much did we budget for it to cost? Of the work we actually performed, how much did it actually cost? COST VARIANCE is is the the difference between budgeted cost cost and and actual actual cost cost formula: CV CV $ = BCWP --ACWP example: CV CV = BCWP BCWP --ACWP ACWP = $1,000 $1, $2,400 $2,400 CV= CV= -$1,400 (negative = cost cost overrun) 12/25/06 EVM Introduction 12 12/25/06 EVM Introduction 12
13 Cost Variance (CV) 5,000 ACWP actual cost cv $ BCWP earned value TIME 5 months 12/25/06 EVM Introduction 13 12/25/06 EVM Introduction 13
14 Note That We Can Isolate Schedule and Cost Variances 5,000 BCWS $ ACWP sv cv BCWP TIME 5 months schedule variance = BCWP - BCWS = negative number cost variance = BCWP - ACWP = negative number behind behind schedule, schedule, over over cost cost 12/25/06 EVM Introduction 14 12/25/06 EVM Introduction 14
15 Where are the significant problems? By tracking and sorting on variances, we can isolate the troublesome WBS elements. sorted by CV ($) WBS DESCRIPTION Proj Ofcr %Comp %Spent CPI CV CV CV % VAC VAC PCC Zepka COMMUNICATIONS Tideman G&A GEN & ADMIN SYS ENGINEERING Price I & A Troop PROJ MANAGEMENT Brown FUNC INTEGRA Price MANAGEMENT DATA Simmons SENSORS Smith SPARES Blair SYSTEM TEST Hall ENG DATA Novak MR MGT RESERVE UB UNDIST BUDGET COM COST OF MONEY DATA DISPLAY Troop OV OVERHEAD TEST FACILITIES Smart COMP PROGRAMS Pino PCC TEST Bond ADPE Zepka AUX EQUIP Tideman /25/06 EVM Introduction 15 12/25/06 EVM Introduction 15
16 Performance Indices We can also get a sense of the overall performance of the project by tracking performance indices. GOOD BAD COST COST PERF PERF INDEX INDEX (CPI) (CPI) = BCWP BCWP ACWP ACWP SCHED SCHED PERF PERF INDEX INDEX (SPI) (SPI) = BCWP BCWP BCWS BCWS CPI SPI TIME 12/25/06 EVM Introduction 16 12/25/06 EVM Introduction 16
17 Budget at Completion (BAC) The most important markers of the overall performance of the project look at predictions of the variances at the end. These require several quantities, the first being the Budget at Completion. sum of all BCWS = BAC $5,000 $5,000 $ $ $ $ $ $ $ time $ When When all all work work has has been been phased, phased, the the cumulative cumulative BCWS BCWS = BAC BAC e.g., e.g., $5,000 $5,000 = $5,000 $5,000 12/25/06 EVM Introduction 17 12/25/06 EVM Introduction 17
18 What will be the final cost? Estimate at Completion (EAC) defined as actual cost to date + estimated cost of work remaining usually develop comprehensive EAC at least annually reported by WBS in cost performance report should examine on monthly basis consider the following in EAC generation: performance to date impact of approved corrective action plans known/anticipated downstream problems best estimate of the cost to complete remaining work also called latest revised estimate (LRE), indicated final cost, etc. ACWP + ETC = EAC 12/25/06 EVM Introduction 18 12/25/06 EVM Introduction 18
19 Getting the Estimate at Completion Just a few little glitches. We should be able to do the complete job.ack let s see, for about $7,500 12/25/06 EVM Introduction 19 12/25/06 EVM Introduction 19
20 Determining EAC via Statistics Common EAC Formulae: EAC = BAC/CPI = ACWPcum + Budgeted Cost of Work Remaining CPI3 = ACWPcum + Budgeted Cost of Work Remaining.8(CPI) +.2(SPI) = ACWPcum + Budgeted Cost of Work Remaining CPI * SPI 12/25/06 EVM Introduction 20 12/25/06 EVM Introduction 20
21 Other methods of EAC calculation Grass Roots or formal EAC detailed build-up from the lowest level detail hours, rates, bill of material, etc. Average of statistical formulae Show range of EACs (optimistic, most probable, pessimistic) Complete schedule risk analysis for remaining work, estimate work remaining 12/25/06 EVM Introduction 21 12/25/06 EVM Introduction 21
22 Variance at Completion (VAC) B AC E AC what the total job is supposed to cost what the total job is expected to cost VARIANCE AT AT COMPLETION is is the the difference between what what the the total total job job is is supposed to to cost cost and and what what the the total total job job is is now now expected to to cost. cost. FORMULA: VAC = BAC --EAC Example: VAC VAC = $5, $7,500 VAC VAC = -- $2,500 (negative = overrun) 12/25/06 EVM Introduction 22 12/25/06 EVM Introduction 22
23 Variance at Completion (VAC) VAC = Budget at Completion - Estimate at Completion = BAC - EAC EAC VAC BAC $ TIME 12/25/06 EVM Introduction 23 12/25/06 EVM Introduction 23
24 VAC is Particularly Important for Government Contracts Variance at Completion vs. Contractor Loss Positive VAC: EAC < BAC underrun contractor gain Negative VAC: EAC > BAC share area contractor partial loss EAC > ceiling overrun contractor loss (100%) Government develops top level EAC for comparison Government will limit progress payments if EAC is greater than ceiling Government needs forecast of fund requirements May still have time to change the final outcome 12/25/06 EVM Introduction 24 12/25/06 EVM Introduction 24
25 Probably the Biggest Selling Point for EVM A survey of over 800 military programs showed that no program ever improved performance better than the following EAC calculation: EAC = BAC/CPI, at the 15%-complete point in the program. Thus, there is strong empirical evidence that EVM translates early information into essential guidance for program re-baselining. 12/25/06 EVM Introduction 25 12/25/06 EVM Introduction 25
26 EVM Analyses There are a wide variety of indicators to play with in EVM. Term Symbol Formula Checklist Actions Percent Complete % Done BCWP BAC Ratio of work accomplished in terms of the total amount of work to do. Cost Performance Index or Performance Factor CPI or PF BCWP ACWP Ratio of work accomplished against money spent (an efficiency rating: Work Done for Resources Expended) To Complete Performance Index or Verification Factor TCPI or VF BAC - BCWP EAC - ACWP Ratio of work remaining against money remaining (Efficiency which must be achieved to complete the remaining work with the expected remaining money) Schedule Performance Index SPI BCWP BCWS Ratio of work accomplished against what should have been done (Efficiency Rating: Work done as compared to what should have been done) Schedule Correlation SC or S/C PCUM SV Ratio of Schedule Variance (SV) in terms of average amount of work accomplished (in weeks or months). It indicates a correlation to program true schedule condition Independent Estimate At Completion IEAC 1) 2) ACWP + BAC PF BAC - BCWP.8CPI +.2SPI Calculation of a projected Estimate At Completion to compare with the CAM's Estimate At Completion: 1) Ration of total work to be done against experienced cost efficiency 2) Sunk costs added to a ratio of remaining work against weighted cost and schedule efficiencies Average Performance P CUM BCWPcum Duration (wks or mos) Since ACWP Began Average rate at which work has been accomplished since work began Average Expected Performance To Finish P TO GO BCWPcum Duration (wks or mos) From Time Now to Manager's Stated Completion Date Average rate at which work must be accomplished in the future to finish on the date the CAM has forecasted for completion of the work. 12/25/06 EVM Introduction 26 12/25/06 EVM Introduction 26
27 EVM Analyses There are a wide variety of analytic techniques to play with in EVM. Sort on significant variances eliminate almost complete, just starting, etc. Graph and analyze trends Look at comparative data e.g. cumulative performance vs. projected performance Examine written analysis by contractor does it answer why? adequacy of corrective action plans Analysis of schedule trends, critical path Analysis of EAC realism what are the drivers? what can we do do about them? 12/25/06 EVM Introduction 27 12/25/06 EVM Introduction 27
28 Graphical EVM Analyses Percent of Dollars MEGA HERZ ELEC & VEN Cost/Schedule Variance F C-0050 MOH-2 RDPR FPI POP: 01 MAR SEP MAY JUN JUL AUG SEP OCT NOV DEC JAN -6% -7% 0% -11% Overall cost and schedule trend BCWS BCWP ACWP CV SV Cost Drivers, Cause COST VARIANCE SCHEDULE VARIANCE Dollars In Millions At Completion KTR PO PMB: 20.4 % COMP: 32.9 MR: 0.4 KTR MR LRE: 0.0 PO MR LRE: 0.0 CURRENT FUNDING: 10.0 PO EPC: 24.0 PROJ FUNDING: 23.0 AS OF: JAN 93 OPR: MR B. TECH PROGRAM: Mohawk Vehicle Element: 3600 Dollars In Millions 8.0 MEGA HERZ ELEC & VEN F C-0050 RDPR FPI Estimates at Completion 1992 APR MAY JUN JUL AUG SEP OCT NOV DEC EAC realism 1993 JAN Name: PCC 7.0 graphs show show overall overall trend... are are you you getting better, better, or or worse? BAC LRE CUM CPI /25/06 EVM Introduction 28 12/25/06 EVM Introduction 28
29 Example: Using Performance Efficiencies (1) Will the contractor come in on budget? COST PERFORMANCE INDEX: CPI = cost efficiency for work performed to date (The value of work accomplished for each dollar spent) WORK BCWP ACCOMPLISHED $1000 = ACWP = ACTUALS = $2400 =.42 Compare the CPI to the TCPI-BAC: HISTORY TCPI(BAC) = Efficiency necessary to complete on budget WORK = BAC-BCWP = REMAINING = $ $1000 BAC-ACWP BUDGET $ $2400 REMAINING = $4000 $2600 FUTURE = /25/06 EVM Introduction 29 12/25/06 EVM Introduction 29
30 Example: Using Performance Efficiencies (2) SCHEDULE PERFORMANCE INDEX: SPI = schedule efficiency with which work has been accomplished (The rate at which work is being accomplished) WORK = BCWP = ACCOMPLISHED = $1000 =.50 BCWS WORK $2000 SCHEDULED 12/25/06 EVM Introduction 30 12/25/06 EVM Introduction 30
31 Example: Using Performance Efficiencies (3) IS THE CONTRACTOR'S EAC (LRE) REASONABLE? Compare the CPI to the TCPI-LRE TCPI(LRE) = Efficiency necessary to complete at the contractor s estimate WORK BAC-BCWP = REMAINING $ $1000 = $4000 = 1.00 LRE-ACWP ESTIMATE $ $2400 $4000 REMAINING = = Cumulative performance to date (CPI) =.42 reasonable? Contractor has been performing at 42% efficiency, but expects to complete remaining work at 100% efficiency! 12/25/06 EVM Introduction 31 12/25/06 EVM Introduction 31
32 Outline Introduction to the basic rationale and elements of EVM Issues of actually implementing an EVM tracking scheme Background materials 12/25/06 EVM Introduction 32 12/25/06 EVM Introduction 32
33 Getting at the Value SELECTED PSWBS ELEMENTS Product Development SOFTWARE INTEGRATION PROGRAM Master Planning SELECTED REPORTING ELEMENTS Ada Products Software Tools Standards CWBS EXTENSION Ada Study Ada Conversion Ada Approach FUNCTIONAL ORGANIZATION CPCI #1 MOS CPCI #2 MOLE CPCI #3 MAC VP/GM Marketing Engineering Operations Software Engineering Hardware Engineering Ada Applications Secure Systems LAN Applications Control Account Control Account Control Account Control Account Control Account Control Account Responsibility Matrix Control Account BCWS BCWP ACWP BAC EAC Planning Packages Work Packages OBS DATA SUMMARIZATION W B S D A T A S U M M A R I Z A T I O N 12/25/06 EVM Introduction 33 12/25/06 EVM Introduction 33
34 Control Account Elements Work Packages Detailed, short-span tasks, or material items, required to accomplish the CA objectives, typically in the near term Planning Packages Future work that has not been detail planned as work packages. They are always scheduled to occur in the future. Work Packages Planning Packages Task 1 Task 2 Task 3 Task 4 Task 5 Work Packages have budgets and schedules. 12/25/06 EVM Introduction 34 12/25/06 EVM Introduction 34
35 Work Packages Development of Control Account Plans MAY break down the control account budget into smaller work packages Work Package subset of control account reasonably short in duration Work Pkg #1 Work Pkg #2 Work Pkg #3 single element of cost (e.g., labor) single technique for earning value consistent with detail schedules has same characteristics as control account scope of work milestone completion criteria single performing organization start and end dates CONTROL ACCOUNT PLAN $ $ $ $ $ $ $ $ $ 12/25/06 EVM Introduction 35 12/25/06 EVM Introduction 35
36 Work Package Characteristics Work packages are discrete and measurable. Work packages yield products or accomplishments, such as design drawing package conduct design review install stand Often done in rolling wave detailed plans made for near term work packages planning packages are for future work and are not detailed CAMs periodically plan another increment of work packages 12/25/06 EVM Introduction 36 12/25/06 EVM Introduction 36
37 Ways of Earning Value Should be a quantitative and discrete way to measure the work Discrete physical, tangible end product Apportioned discrete, dependent on another discrete work package example: quality assurance planned as historical estimating factor (e.g., 7%) Level of Effort no tangible end product basis of measurement: time when clock starts ticking, you automatically accumulate earned value no schedule variance example: management personnel May tie in with success criteria or technical measure e.g., successful completion of a specific test, reliability growth curve 12/25/06 EVM Introduction 37 12/25/06 EVM Introduction 37
38 Methods for Assigning Earned Value Method How Value is Earned 0/100 no EV at opening, 100% EV at close of WP 50/50 50% EV at opening, 50% EV at close of WP Units Completed Equivalent Units Weighted Milestone Percent Complete same budget value for identical units planned unit standards, allows partial credit each milestone weighted based on planned resources ideal to have a milestone each month subjective (least desirable) 12/25/06 EVM Introduction 38 12/25/06 EVM Introduction 38
39 Suggested for LWA 0/50/100 measurement Typical work package length is 80 hours. Work package status is reported at status meetings, held every two weeks. May just be that 50% of work packages are reported at weekly status meetings. EV is 0% (of budget for work package) if it has not yet been started, or is only now starting. EV is 50% if work is underway. EV is 100% if work is complete. If work package is at 50% two status meetings in a row, it is flagged as a potential issue. Avoids subjectivity of % done ; compromises on granularity of tracking, frequency of reporting Puts the onus on doing the WPs right, up front. 12/25/06 EVM Introduction 39 12/25/06 EVM Introduction 39
40 Outline Introduction to the basic rationale and elements of EVM Issues of actually implementing an EVM tracking scheme Background materials 12/25/06 EVM Introduction 40 12/25/06 EVM Introduction 40
41 A Spectrum of Implementation Where Small Companies Commercial or Defense Larger Companies Government Organic Foreign Countries Major Defense Contractors When as desired corporate policy, enterprise wide FFP contracts? DoD Non-Major Contracts (>12 months) <$6M* >$6M DoD Major Contracts >$70M RDT&E >$300M Prod Reports streamlined, no paper? tailored to needs C/SSR CPR Core EV Principles Tailored Applications ANSI/EIA (32 criteria) *with judgment 12/25/06 EVM Introduction 41 12/25/06 EVM Introduction 41
42 Earned Value Management: History PERT and PERT/Cost Milestone Charts And Rate-of-Expenditure Curves Dollars Spent Vs Estimates Of Percent Complete (DD 1097) Earned Value Concept (MINUTEMAN) Cost Accomplishment Concept (TITAN III) AF Cost/schedule Planning And Control Specification (C/SPCS) DOD Cost/Schedule Control Systems Criteria (C/SCSC) (DODI ) DOD -Revised DODI and Issued the Joint Implementation Guide (JIG) NASA Marshall Space Flight Center C/SPC DOE Performance Measurement System (PMS) DOD Revised the C/SCSC JIG DOD Revised the C/SCSC JIG National Security Agency Earned Value NASA Goddard Space Flight Center PMS FAA & NASA Lewis Research Center PMS NASA Johnson Space Flight Center PMS DOD Revised DOD C/SCSC JIG NASA Marshall SFC Revised PMS (MMI C, 44 Criteria) 1989 Australian DOD DODI Canadian DOD PMS 1991 DODI replaces DODI National Oceanic And Atmospheric Administration (NOAA) PMS 1993 Swedish FMV C/SCSC 1994 Internal Revenue Service (IRS) C/SCSC 1994 Federal Bureau Of Investigation (FBI) C/SCSC 1996 DODR R replaces DODI C/SCSC revised from 35 to 32 criteria 1996 Revised JIG Renamed Earned Value Management Implementation Guide (EVMIG) 1997 EVMIG Revised 1998 MIL-STD 881B replaced by MIL HDBK /25/06 EVM Introduction 42 12/25/06 EVM Introduction 42
43 EVM Resources Books Earned Value Quentin W. Fleming & Joel M. Koppleman Cost/Schedule Control Systems Criteria Quentin W. Fleming Project Performance Measurement Robert R. Kemps Visualizing Project Management Kevin Forsberg, Ph.D., Hal Mooz and Howard Cotterman Software Artemis Views Artemis Management Systems Contact: Patrick Perugini (303) Web: Cobra Welcom Software Contact: Diana Melton (281) Web: Software [continued] Dekker TRAKKER Dekker Ltd. Contact: Ron Barry (909) Web: MicroFrame Project Manager (MPM) MicroFrame Technologies, Inc. Contact: Carl Amacker (415) Web: Internet Project Management Institute US DoD Earned Value Earned Value Bibliography 12/25/06 EVM Introduction 43 12/25/06 EVM Introduction 43
L10: Budgeting and Cost Control. Olivier de Weck
ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen
700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
An introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
Earned Value Management Tutorial Module 8: Reporting. Prepared by:
Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.
Appendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
INSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1
Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control
Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP
Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program
Basic Concepts of Earned Value Management (EVM)
Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data
Estimating Cost at Completion - Judgment & EV Information
Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number
Earned Value and Agile Reporting
Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,
Earned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH
THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects
DCMA DCMA-EA PAM 200.1. October 2012
DCMA Earned Value Management System (EVMS) Program Analysis Pamphlet (PAP) DCMA-EA PAM 200.1 October 2012 THE DCMA ENGINEERING AND ANALYSIS EXECUTIVE DIRECTOR IS RESPONSIBLE FOR ISSUANCE AND MAINTENANCE
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
Simple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
PROJECTS SCHEDULING AND COST CONTROLS
Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to
Introduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
Project Execution - PM Elements
Performance Initial Release 1. Introduction to Project Tracking and Reviewing Once a project has advanced to the phase of performance, the consistent and constant flow of information on the true status
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective
Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 [email protected]
Brainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
How To Manage A Project
Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management
Earned Value Management Best Practices
Division of Information Technology Investment Management Enterprise Architecture & Strategy Group Office of Information Services Earned Value Management Best Practices Version 2.2 Last Modified: 19 November
EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS
14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya
Using Earned Value Management for Improving Processes. By Cynthia K. West
Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.
Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. [email protected]
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of
USING THE EARNED VALUE COST MANAGEMENT REPORT TO EVALUATE THE CONTRACTOR'S ESTIMATE AT COMPLETION. David S. Christensen, Ph.D.
USING THE EARNED VALUE COST MANAGEMENT REPORT TO EVALUATE THE CONTRACTOR'S ESTIMATE AT COMPLETION David S. Christensen, Ph.D. College of Business Southern Utah University 351 West, Center Street Cedar
Chapter 7: Project Cost Management. Munawar [email protected]
Chapter 7: Project Cost Management Munawar [email protected] Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor
EVM.01. Earned Value Analysis Why it Doesn't Work
EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects
A Gentle Introduction to Earned Value Management Systems
A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT
1 PMSC Quarterly Meeting, February 1 2, 2011, Fort Worth, Texas SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT Increasing the Probability Program of Success (PoPS)by Connect the dots between
PERCEPTION. Tracking Progress & EAC
PERCEPTION Tracking Progress & EAC 1 Maximize Efficiency Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge their competition. They can focus
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
AACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
Percorso di Eccellenza in PROJECT MANAGEMENT. Cost estimating and estimate to completion. Ing. Locatelli Giorgio. Giorgio.locatelli@polimi.
Cost estimating and estimate to completion Ing. Locatelli Giorgio [email protected] 0223394096 1 Cost Estimating The project s costs management evolves during the whole project life cycle and
Contract Cash Flow & Performance Analysis. PERCEPTION Helping The Shipyard Stay On Budget
Contract Cash Flow & Performance Analysis PERCEPTION Helping The Shipyard Stay On Budget 1 Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 AMSC Number: D7549 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing
FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office
Basics of Cost and Schedule Control
Basics of Cost and Schedule Control Topics Monitoring and Scheduling: Two Parts of a Feedback System. Definitions Schedule Updates from Monitoring Components of Effective Monitoring Cost Control As A Management
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Rules on using templates 1) Must reference the template used 2) Use
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you
Project Cost Management
Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present
Tracking Software Development Progress with Earned Value and Use Case Point
ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with
plans based on actual cost, schedule and technical progress of work [1, 9].
An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Earned Value Management System (EVMS) and. Project Analysis Standard Operating Procedure (EPASOP)
Earned Value Management System (EVMS) and Project Analysis Standard Operating Procedure (EPASOP) Issued by Office of Acquisition and Project Management MA-63 March 12, 2014 DEPARTMENT OF ENERGY Office
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.
About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints
Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman
Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government
earned value management
earned value management in control of big productions an eyeon white paper october 2013 1 contents 4 ly escalation 5 linking and cost control 6 cost forecasting 6 implementation towards effective project
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION Author Bill Mowery MPM, PMP Keywords Earned Value Management, Earned Schedule, Project Management, Cost
COINS EVA Earned Value Analysis
COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project
Unit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
IST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN?
1 IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN? Presented at The Nexus of Agile Software Development and Earned Value Management, OSD-PARCA, February 19 20, 2015 Institute for Defense Analysis, Alexandria,
Create Stoplight charts using Milestones Professional
Stoplight Charts: Ideal for At-a-Glance Project Reporting Create Stoplight charts using Milestones Professional In a report which has extensive data, how can action items be quickly highlighted and addressed?
Since 1985, the Test Program Set (TPS) development
Applying Management Reserve to Software Project Management Walter H. Lipke Oklahoma City Air Logistics Center, Directorate of Aircraft Maintenance, Software Division Today s standard of practice for managing
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
Agile Project Management Controls
0 Agile Project Management Controls Issues with EVM and a Viable Alternative: Agile Project Management (PM) Tool ICEAA Conference, June 2015 San Diego, CA Blaze Smallwood, Booz Allen Hamilton Omar Mahmoud,
The Two Most Useful Earned Value Metrics: the CPI and the TCPI
PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was
Earned Value Management Guidelines
Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application
MTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II)
MTAT.03.244 Software Economics Lecture 6: Software Cost Estimation (part II) Marlon Dumas marlon.dumas ät ut. ee Outline Review of Effort Estimation Homework Discussion on book chapter by Caper Jones Earned
Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP
PMP Formulae & Tips Cheat Sheet P a g e Integration Management Develop Project Charter process Project Selection Methods (>> Benefit Measurement Methods >> Economic Models -7) Present Value (PV) FV The
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s
Tracking Budgets and Schedules
Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is
Earned Value Management System Description
LCLS Project Management Document # 1.1-015 Project Management Revision 3.0 Earned Value Management System Description Patricia Mast (LCLS Project Controls Manager) Signature Date Mark Reichanadter (LCLS
Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes
Lecture Slides for Managing and Leading Software Projects Chapter 8: Measuring and Controlling Work Processes developed by Richard E. (Dick) Fairley, Ph.D. to accompany the tet Managing and Leading Software
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance R. Scott Brunton, PMP, PMI-RMP/SP, EVP Principal Solutions Consultant Lewis Fowler, LLC www.lewisfowler.com Welcome to the
Project Cost Management
Project Cost Management Martin Pazderka [email protected] INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda
Project Management: Tracking Progress and Earned Value with MS Project 2003
Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain
COST PERFORMANCE INDEX STABILITY 1. David S. Christensen Scott R. Heise INTRODUCTION
COST PERFORMANCE INDEX STABILITY 1 David S. Christensen Scott R. Heise INTRODUCTION The Cost Performance Index (CPI) is a key indicator used to analyze cost and schedule performance data reported by defense
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,
Forecasting Project Schedule Completion by Using Earned Value Metrics
Forecasting Project Schedule Completion by Using Earned Value Metrics Ing. Stephan Vandevoorde Sr. Project Manager Fabricom Airport Systems [email protected] 1 Agenda Introduction Schedule performance indicators
Cost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP
Cost & Schedule Risk Assessment Using @Risk 6.0 Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP 24 October 2012 What If? In Business and in Life: We always made the best possible decisions, and Implemented
Accounting System. Page 1 of 9
Page 1 of 9 Accounting System In support of program management and Earned Value Management, the accounting system must be able to relate costs incurred to work accomplished. Not all accounting systems
Project Cost Management through Earned Value Performance Management - EVPM
Project Cost Management through Earned Value Performance Management - EVPM Author: Dr. Raf M. Dua This paper was originally presented by Dr. Raf M. Dua to the Australian Institute of Project Management
Earned Value Management Systems Application Guide
National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide January 27, 2015 Revision 2 National Defense Industrial Association (NDIA)
Brillig Systems Making Projects Successful
Metrics for Successful Automation Project Management Most automation engineers spend their days controlling manufacturing processes, but spend little or no time controlling their project schedule and budget.
Financial Management and Program Management: Integration and Intersections
American Society of Military Comptrollers Professional Development Institute May 26 29, 2015 Financial Management and Program Management: Integration and Intersections D e b r a E. H a h n D e b b i e.
What is the Health of my Project?
WHITE PAPER What is the Health of my Project? The Use and Benefits of Earned Value Table of Contents How s My Project Doing?...1 Need a Solution? Earned Value to the Rescue!...1 My actual costs are less
New Tools for Project Managers: Evolution of S-Curve and Earned Value Formalism
New Tools for Project Managers: Evolution of S-Curve and Earned Value Formalism A Presentation at the Third Caribbean & Latin American Conference On Project Management, 21 23 May 2003 Denis F. Cioffi,
Assessing Schedule Performance with Earned Value
FEATURED PAPER OCTOBER 2007 Time Is Up: Assessing Schedule Performance with Earned Value By Robert Van De Velde Time drives projects. Quick and accurate evaluation of schedule performance is crucial. Quantitative
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network
CVR/IT Consulting LLC
2011 CVR/IT Consulting LLC All Rights Reserved 1 www.cvr-it.com [email protected] Overview Easy Earned Value CVR/IT Consulting LLC 2011 CVR/IT Consulting LLC All Rights Reserved 2 Introduction Earned Value
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling
Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition
Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management
Predicting progress on your project
www.nonsuch.co [email protected] Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant
Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01
PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.
Over Target Baseline and Over Target Schedule Guide
Over Target Baseline and Over Target Schedule Guide OUSD AT&L (PARCA) December 5, 2012 1 Table of Contents Section Page No. Introduction 4 Chapter 1. What is Formal Reprogramming? 5 1.1 Formal Reprogramming
Project Cost Management. Richard Boser
Project Cost Management Richard Boser Project Cost Management Introduction Course Objectives Upon completing today s activities you will be knowledgeable of tools and techniques to: Allocate overall costs
Project Management System Description (PMSD)
Project Management System Description (PMSD) Revision 3 Project Management System Description (PMSD) Revision 3 February 2016 Prepared by: Date: Steve Langish Planning & Control Division Approved by: Date:
Applied Project Management ( APM )
Applied Project Management Applied Project Management ( APM ) TRAINING PROGRAM Page 1 Of 7 APPLIED PROJECT MANAGEMENT PRO PROGRAM OVERVIEW This course provides in-depth Project Management Training and
