Cost & Schedule Risk Assessment 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP

Size: px
Start display at page:

Download "Cost & Schedule Risk Assessment Using @Risk 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP"

Transcription

1 Cost & Schedule Risk Assessment 6.0 Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP 24 October 2012

2 What If? In Business and in Life: We always made the best possible decisions, and Implemented those decisions in the most efficient manner 2

3 BSRM Helps Clients Rank projects based on risks and opportunities Develop optimum project strategies Transform optimum project strategies into tactical plans Track project implementation; provide early warning of variances Develop meaningful dashboards and increase transparency Forecast project completion dates and costs Improve portfolio performance metrics Identify portfolio cost and schedule drivers Capture lessons learned to inform future planning Manage project and portfolio risks

4 Business Solutions & Risk Management Services Project Management Consulting Probabilistic Cost Estimation Portfolio Risk Ranking Business Analytics PM Information Systems Process & Tools for Reducing Costs and Increasing Profits Multi-Criteria Decision Analysis Cost & Schedule Risk Analysis Project Dash Boards Project Controls Earned Value Analysis

5 The Project Management Process 14/11/2012

6 Why does project management methodology matter? 14/11/2012 Varying versions exist but cartoon seems to have been documented first in John Oakland's book Total Quality Management.

7 Project Planning and Control Plan Develop Work Breakdown Structure Define resources, costs, and durations Schedule work packages using network logic Team consensus on baseline cost-loaded schedule Do Check Assess Track progress against the baseline Analyze Earned Value metrics Corrective action and change management 14/11/2012

8 The Work Breakdown Structure (WBS) A deliverables-oriented decomposition of the work to be executed by the project team to accomplish project objectives and create the desired deliverables with each descending level representing an increasingly detailed definition of the project work Deliverable: Any measurable, tangible or verifiable item that must be produced to complete a project In Practical Terms The WBS is what to deliver It is a fundamental tool to properly manage the project scope

9 Work Breakdown Structure Common language for all team members Defines and outlines scope Site Project A Project B Project C Site Prep Dewatering Excavation Restoration Site Controls Setup Build Access Road Remove and Stockpile OB Build Decon Pad 14/11/2012

10 Plan Resources and Estimate Cost and Duration Determine the Resources and Quantity of Resources Required for Work Packages Estimate the Cost of Work Packages Estimate the Duration of Work Packages

11 Assign Network Logic Shows how changes in one task impact other tasks Facilitates scheduling (and rescheduling) of people and equipment Promotes analysis of tradeoffs and potential corrective action

12 How is this project doing? COST Planned Cost Actual Cost 14/11/2012 Current Time TIME

13 Earned Value Curve EAC Management Reserve BAC COST Schedule Variance Cost Variance Planned Value Actual Cost Earned Value Current Time TIME Planned Completion Date Estimated Completion Date 14/11/2012

14 Earned value metric calculations provide holistic understanding of project progress

15 Earned Value Analysis Early warning system Early corrective action cost/schedule variance correction Scope management change orders for new scope *Source: Modified from Practice Standard for Earned Value Management 2005

16 14/11/2012 Scheduling Best Practices

17 14/11/2012 General Process for Developing Work Breakdown Structures

18 WBS Best Practices The names of the WBS elements should be easy to understand and convey meaning to all project participants and stakeholders The work packages should account for 2 to 10% of the total project budget (exceptions can occur for very large or very small projects) Activities or should not have durations beyond two project reporting periods Do not use the same task heading for activities performed by two separately responsible groups Include task and/or work packages in the WBS for work that will performed outside parties, even if they do not involve a cost (regulatory review, peer assists) Break down items such as permits, regularly scheduled field events and reports into their component activities 14/11/2012

19 Duration Estimating Best Practices Whenever possible obtain estimates from individuals who have performed similar activities in past Have people who are responsible for performing a given task provide duration estimates Make all estimates realistic. It is best to consider most likely amount of time needed, without a pessimistic or optimistic view In general assume a normal workweek and normal workday Use days as the time unit Be willing to breakdown into smaller WBS elements if there is difficulty in estimating the duration of a particular activity Do not assume that office workers will have 8 hours of uninterrupted time. Assume that office workers are 70% productive and adjust durations accordingly 14/11/2012

20 Network Scheduling Best Practices Do not link Summary Tasks PM and Oversight tasks Start when project starts and finishes when the last activity finishes Set Constraints as little as possible Instead, consider using Deadlines as they do not directly affect project scheduling dates For risk modeling you should not have any must start, must finish or similar constraints Maximize concurrency whenever possible Multiple finish to start activities off a given milestone Use of start to start logic connectors Minimize discretionary dependencies 14/11/2012

21 14/11/2012 Case Study

22 Site Background Information Former specialty petroleum manufacturing facility Objective to prepare site for sale and use as mixed commercial / residential redevelopment Project scope of work includes Removing and properly disposing of asbestos and regulated wastes from manufacturing plant Demolishing the building structure Excavating and properly disposing of soil having concentrations above residential standards Dewatering during excavation and discharging water to a publically owned treatment works Obtaining all necessary permits prior to performing field activities Business plan called for completing project by September 30, 2011 at cost of $4.6 million

23 Risk Elements included in Model Structure Probabilistic cost and duration input parameters Probabilistic resource assignments (i.e. employs RiskProjectResouceUse function) and resource unit prices Durations for Level of effort or hammock task such as project management or driven by the uncertain duration of other tasks and network logic Project risk register to address low probability high impact events (i.e., makes use of RiskProjectAddDelay function)

24 General Notes on Environmental Remediation Projects Notorious for going over budget and schedule One of the largest uncertainties is always associated with the volume of impacted material (soil, sediments) that must be addressed Another large source of uncertainty is permitting and regulatory approvals. The percentage of cost for project management higher than in other construction industries Project carrying costs can be high

25 Model Demonstration and Results 14/11/2012

26 Model Cost Results Statistic Cost Duration Fnish Date Minimum $4,220, days 8/29/2011 Maximum $6,293, days 9/13/2012 Mean $4,831, days 10/23/2011 Std Deviation $253, days 42 Days Mode $4,459, days 10/6/ % Perc $4,564, days 9/20/ % Perc $4,660, days 9/29/ % Perc $4,789, days 10/11/ % Perc $4,948, days 10/27/ % Perc $5,159, days 12/19/ /11/2012

27 14/11/2012 Greenville Site Demolition and Remediation Cost

28 14/11/2012 Greenville Site Finish Date

29 14/11/2012 Cost Tornado Diagram

30 Mar-2011 Apr-2011 May-2011 Jun-2011 Jul-2011 Aug-2011 Sep-2011 Oct-2011 Nov-2011 Dec-2011 Jan-2012 Feb-2012 Mar-2012 Cumulative Cost $Million Greenville Probabilistic Planned Value Box Plot Maximum 80 Perc% Mean 20 Perc% Minimum /11/2012

31 Cumulative Cost Trend Data for Probabilistic Earned Value Analysis 7,000,000 6,000,000 5,000,000 4,000,000 3,000,000 2,000,000 Deterministic Minimum 20 Perc% Mean 80 Perc% Maximum 1,000, /11/2012

32 Actual Results Project was completed for a cost of $ 4.9 Million and in May of 2012 Soil volume was 20% greater than planned The selected contractor had an injury even at another site which created a stop work order at this site

33 Summary Cost Schedule Risk Analysis Powerful tool for communicating potential cost and schedule outcomes Enhances ability to identify and manage cost and schedule drivers Simplifies estimating cost trends and improves net present value analysis Opens the door for probabilistic earned value analysis control chart approach CSRA should remain dynamic and re-visited throughout project life cycle

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT 6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network

More information

Basic Project Management & Planning

Basic Project Management & Planning Basic Project Management & Planning Dr. David K. Potter Director & Don Pether Chair in Engineering and Management em4a03@mcmaster.ca 1 What is Project Management? A set of principles, methods, tools, and

More information

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling

More information

Analysis One Code Desc. Transaction Amount. Fiscal Period

Analysis One Code Desc. Transaction Amount. Fiscal Period Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00

More information

Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8

Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007

More information

PROJECTS SCHEDULING AND COST CONTROLS

PROJECTS SCHEDULING AND COST CONTROLS Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to

More information

Ashley Institute of Training Schedule of VET Tuition Fees 2015

Ashley Institute of Training Schedule of VET Tuition Fees 2015 Ashley Institute of Training Schedule of VET Fees Year of Study Group ID:DECE15G1 Total Course Fees $ 12,000 29-Aug- 17-Oct- 50 14-Sep- 0.167 blended various $2,000 CHC02 Best practice 24-Oct- 12-Dec-

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost

More information

Business Idea Development Product production Services. Development Project. Software project management

Business Idea Development Product production Services. Development Project. Software project management Page 1, 1/20/2003 Ivica Crnkovic Mälardalen University Department of Computer Engineering ivica.crnkovic@mdh.se Development Project Product Lifecycle Business Idea Development Product production Services

More information

Roles: Scrum Master & Project Manager

Roles: Scrum Master & Project Manager Roles: Scrum Master & Project Manager Scrum Master: Facilitate collaborative meetings Track team performance Remove impediments (Risk, Issue) Validate team alignment to Agile framework and scope Drive

More information

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017 From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days

More information

Project Execution - PM Elements

Project Execution - PM Elements Performance Initial Release 1. Introduction to Project Tracking and Reviewing Once a project has advanced to the phase of performance, the consistent and constant flow of information on the true status

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference

More information

EXHIBIT 2-2-C PROGRESS SCHEDULES

EXHIBIT 2-2-C PROGRESS SCHEDULES EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,

More information

The principles, processes, tools and techniques of project management

The principles, processes, tools and techniques of project management Unit 34: Plan and manage a project. 341 The principles, processes, tools and techniques of project management An industrial project, big or small, must be managed effectively to ensure the project s objectives

More information

Project Management Planning

Project Management Planning The Project Plan Template The Project Plan The project plan forms the basis for all management efforts associated with the project. A project plan template is included in this document. The information

More information

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the

More information

The work breakdown structure can be illustrated in a block diagram:

The work breakdown structure can be illustrated in a block diagram: 1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Earned Value Management Tutorial Module 8: Reporting. Prepared by: Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.

More information

PROJECT MANAGEMENT PLAN <PROJECT NAME>

PROJECT MANAGEMENT PLAN <PROJECT NAME> PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome

More information

earned value management

earned value management earned value management in control of big productions an eyeon white paper october 2013 1 contents 4 ly escalation 5 linking and cost control 6 cost forecasting 6 implementation towards effective project

More information

Project Management Planning

Project Management Planning Overview of Resource Planning Every organization has a limited number of resources to perform tasks. A project manager's primary role is to find a way to successfully execute a project within these resource

More information

A Model to Develop and Use Risk Contingency Reserve

A Model to Develop and Use Risk Contingency Reserve A Model to Develop and Use Risk Contingency Reserve NK Shrivastava, PMP, RMP, ACP, CSM, SPC CEO/Consultant/Agile Coach - RefineM Agenda 1. Your Expectations from this Presentation 2. Introduction Myself

More information

Chapter 6. (PMBOK Guide)

Chapter 6. (PMBOK Guide) Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

Cost Management. How Much Will This Project Cost?

Cost Management. How Much Will This Project Cost? Cost Management How Much Will This Project Cost? Moderator Janelle Abaoag Project Insight Marketing, Public Relations Janelle.Abaoag@projectinsight.com www.projectinsight.net All participants will be on

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Create Stoplight charts using Milestones Professional

Create Stoplight charts using Milestones Professional Stoplight Charts: Ideal for At-a-Glance Project Reporting Create Stoplight charts using Milestones Professional In a report which has extensive data, how can action items be quickly highlighted and addressed?

More information

Introduction to Project Management: Principles, Techniques and Tools

Introduction to Project Management: Principles, Techniques and Tools Introduction to Project Management: Principles, Techniques and Tools 2013 Topic Agenda Time 1 Opening and Introduction 30 mins 2 Project Management - Introduction to Project Management 10 Minute Break

More information

MEASURES FOR EXCELLENCE Getting a "RUNAWAY" Software Development. Under Control. A Case Study

MEASURES FOR EXCELLENCE Getting a RUNAWAY Software Development. Under Control. A Case Study MEASURES FOR EXCELLENCE Getting a "RUNAWAY" Software Development Under Control A Case Study.J.W.E Greene QUANTITATIVE SOFTWARE MANAGEMENT LTD 7 rue Fenoux 93 Blythe Road, Paris 71 London W1 OHP Tel: 33-1-311

More information

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define

More information

Emergency Department Directors Academy Phase II. The ED is a Business: Intelligent Use of Dashboards

Emergency Department Directors Academy Phase II. The ED is a Business: Intelligent Use of Dashboards Emergency Department Directors Academy Phase II The ED is a Business: Intelligent Use of Dashboards May 2011 The ED is a Business; Intelligent Use of Dashboards Katherine Haddix-Hill, RN, MSN Acknowledge:

More information

The 10 Knowledge Areas & ITTOs

The 10 Knowledge Areas & ITTOs This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading

More information

SCHEDULE AND BUDGETING

SCHEDULE AND BUDGETING PROJECT CONTROLS The right combination of software management tools, proper initial project set-up, timely and accurate data input, continuous tracking of progress, a meaningful reporting structure, strong

More information

State of Michigan (SOM) August 2013. Department of Technology, Management & Budget

State of Michigan (SOM) August 2013. Department of Technology, Management & Budget State of Michigan (SOM) PROJECT MANAGEMENT KEY TERMS, DEFINITIONS AND ACRONYMS August 2013 Department of Technology, Management & Budget Table of Contents Table of Contents Key Terms, Definitions, and

More information

// Benchmarking Project Schedules

// Benchmarking Project Schedules // Benchmarking Project Schedules Dr. Dan Patterson, PMP CEO & President, Acumen March 2011 www.projectacumen.com Table of Contents Introduction... 4 Benchmarking Overview... 4 Uses of Schedule Benchmarking...

More information

The Plan s Journey From Scope to WBS to Schedule

The Plan s Journey From Scope to WBS to Schedule The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)

More information

From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer

From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer Date: September

More information

PROJECT TRACKING and CONTROL

PROJECT TRACKING and CONTROL PROJECT TRACKING and CONTROL 1 Outline of Project Tracking & Control 2 Project Planning & Control Context 3 Realistic and Measurable Plans Create Measurable Plans! 4 Data Sources for Project Tracking 5

More information

A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry

A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry Pranam B 1, Madhusudan G Kalibhat 2, Sudharshan KR 3 1 Student, Master of Technology (Construction

More information

A collection of Safran Project report samples for project professionals

A collection of Safran Project report samples for project professionals A collection of Safran Project report samples for project professionals Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger www.safran.com Contents Introduction... 2 About the Reports

More information

LeSueur, Jeff. Marketing Automation: Practical Steps to More Effective Direct Marketing. Copyright 2007, SAS Institute Inc., Cary, North Carolina,

LeSueur, Jeff. Marketing Automation: Practical Steps to More Effective Direct Marketing. Copyright 2007, SAS Institute Inc., Cary, North Carolina, Preface. Overview. PART 1: Marketing Financials. Chapter 1 Profit and Loss Fundamentals. Chapter 2 Profit and Loss Component Details. Chapter 3 Managing the P&L. Chapter 4 Measuring Marketing Effectiveness.

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

Percorso di Eccellenza in PROJECT MANAGEMENT. Cost estimating and estimate to completion. Ing. Locatelli Giorgio. Giorgio.locatelli@polimi.

Percorso di Eccellenza in PROJECT MANAGEMENT. Cost estimating and estimate to completion. Ing. Locatelli Giorgio. Giorgio.locatelli@polimi. Cost estimating and estimate to completion Ing. Locatelli Giorgio Giorgio.locatelli@polimi.it 0223394096 1 Cost Estimating The project s costs management evolves during the whole project life cycle and

More information

Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman

Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government

More information

output: communications management plan

output: communications management plan Q1. (50 MARKS) A. List the nine PMBOK knowledge areas and give a one sentence description of the purpose of each knowledge area along with at least one output (document etc.) and its purpose. 1.Project

More information

Procurement Planning

Procurement Planning MatriX Engineering Project Support Pinnacle Business Solutions Ltd www.pinsol.com www.matrix-eps.com Proc_Plan.doc Page 2 of 21 V_09_03 Contents 1.0 INTRODUCTION... 5 1.1 KPIS AND MEASURABLE TARGETS...

More information

PROJECT CONTROL PROCEDURE (PROJECT STANDARDS AND SPECIFICATIONS)

PROJECT CONTROL PROCEDURE (PROJECT STANDARDS AND SPECIFICATIONS) TABLE OF CONTENTS Page 1 of 18 PURPOSE 2 SCOPE 2 DEFINITION 2 ORGANIZATION AND RESPONSIBILITIES 2 Organization and Function 2 Integration of Control Functions 5 7 Introduction 7 Planning and Scheduling

More information

CENTERPOINT ENERGY TEXARKANA SERVICE AREA GAS SUPPLY RATE (GSR) JULY 2015. Small Commercial Service (SCS-1) GSR

CENTERPOINT ENERGY TEXARKANA SERVICE AREA GAS SUPPLY RATE (GSR) JULY 2015. Small Commercial Service (SCS-1) GSR JULY 2015 Area (RS-1) GSR GSR (LCS-1) Texarkana Incorporated July-15 $0.50690/Ccf $0.45450/Ccf $0.00000/Ccf $2.85090/MMBtu $17.52070/MMBtu Texarkana Unincorporated July-15 $0.56370/Ccf $0.26110/Ccf $1.66900/Ccf

More information

Module 3: The Project Planning Stage

Module 3: The Project Planning Stage Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you

More information

Guidelines: Project Schedule Project Management Office (PMO)

Guidelines: Project Schedule Project Management Office (PMO) Guidelines: Project Schedule Project Management Office (PMO) Process The project Schedule outlines the tasks and activities of the project; the duration; start and end dates for each individual task and

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

Project Management Plan for

Project Management Plan for Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...

More information

Time Management II. http://lbgeeks.com/gitc/pmtime.php. June 5, 2008. Copyright 2008, Jason Paul Kazarian. All rights reserved.

Time Management II. http://lbgeeks.com/gitc/pmtime.php. June 5, 2008. Copyright 2008, Jason Paul Kazarian. All rights reserved. Time Management II http://lbgeeks.com/gitc/pmtime.php June 5, 2008 Copyright 2008, Jason Paul Kazarian. All rights reserved. Page 1 Outline Scheduling Methods Finding the Critical Path Scheduling Documentation

More information

SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE

SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining an accurate cost loaded critical path schedule in

More information

Accident & Emergency Department Clinical Quality Indicators

Accident & Emergency Department Clinical Quality Indicators Overview This dashboard presents our performance in the new A&E clinical quality indicators. These 8 indicators will allow you to see the quality of care being delivered by our A&E department, and reflect

More information

Improve Project Team Collaboration Using Microsoft Project Online

Improve Project Team Collaboration Using Microsoft Project Online Improve Project Team Collaboration Using Microsoft Project Online Presented by Steven Vowles, PMP, CISA, MCTS Senior Program Director, Infor Consulting Services Global PMO April 29, 2016 1 Discipline!

More information

Risk Review Process Basics

Risk Review Process Basics 2011 PMOC Annual Meeting FEDERAL TRANSIT ADMINISTRATION Risk Review Process Basics Michael P. Wetherell, PE - Urban Engineers David N. Sillars, PE Sillars Consulting FEDERAL TRANSIT ADMINISTRATION 2011

More information

Acompany that consistently selects the right projects and

Acompany that consistently selects the right projects and PM.01 How to Create a World Class Project Management Organization Dr. Nick J. Lavingia, PE Acompany that consistently selects the right projects and executes them with excellence can improve return on

More information

P/T 2B: 2 nd Half of Term (8 weeks) Start: 25-AUG-2014 End: 19-OCT-2014 Start: 20-OCT-2014 End: 14-DEC-2014

P/T 2B: 2 nd Half of Term (8 weeks) Start: 25-AUG-2014 End: 19-OCT-2014 Start: 20-OCT-2014 End: 14-DEC-2014 2014-2015 SPECIAL TERM ACADEMIC CALENDAR FOR SCRANTON EDUCATION ONLINE (SEOL), MBA ONLINE, HUMAN RESOURCES ONLINE, NURSE ANESTHESIA and ERP PROGRAMS SPECIAL FALL 2014 TERM Key: P/T = Part of Term P/T Description

More information

WM'99 CONFERENCE, FEBRUARY 28 - MARCH 4, 1999

WM'99 CONFERENCE, FEBRUARY 28 - MARCH 4, 1999 ROCKY FLATS CLOSURE PROJECT: PLANNING FOR UNCERTAINTY By Larry F. Burdge Vice President, Planning and Integration Kaiser-Hill company, LLC And Joe Nolter President Project Analysis & Evaluation, Inc. ABSTRACT

More information

P/T 2B: 2 nd Half of Term (8 weeks) Start: 26-AUG-2013 End: 20-OCT-2013 Start: 21-OCT-2013 End: 15-DEC-2013

P/T 2B: 2 nd Half of Term (8 weeks) Start: 26-AUG-2013 End: 20-OCT-2013 Start: 21-OCT-2013 End: 15-DEC-2013 2013-2014 SPECIAL TERM ACADEMIC CALENDAR FOR SCRANTON EDUCATION ONLINE (SEOL), MBA ONLINE, HUMAN RESOURCES ONLINE, NURSE ANESTHESIA and ERP PROGRAMS SPECIAL FALL 2013 TERM Key: P/T = Part of Term P/T Description

More information

Project Management Certificate (IT Professionals)

Project Management Certificate (IT Professionals) Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.

More information

Portfolio Management An Inexact Science. Mark Lawry Portfolio Management Dir, GSK Milan, September 2010

Portfolio Management An Inexact Science. Mark Lawry Portfolio Management Dir, GSK Milan, September 2010 Portfolio Management An Inexact Science Mark Lawry Portfolio Management Dir, GSK Milan, September 2010 1 Portfolio Management Vision Optimizing the value delivered from the portfolio in line with strategy

More information

Project Cost Management

Project Cost Management Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please

More information

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain * TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited

More information

TECH. Tracking Progress. Project Schedule PHASE 1 STEP 1 ACTIVITY 1.1. Activity and Milestone STEP 1 STEP 2 : ACTIVITY 2.2 : ACTIVITY 1.

TECH. Tracking Progress. Project Schedule PHASE 1 STEP 1 ACTIVITY 1.1. Activity and Milestone STEP 1 STEP 2 : ACTIVITY 2.2 : ACTIVITY 1. CH03 Planning and Managing the Project * Tracking Progress * Project Personnel * Effort Estimation * Risk Management * The Project Plan * Process Models and Project Management Tracking Progress Questions

More information

Project Planning, Scheduling and Control: Assignment 2 D. U. Singer Hospital Products Corp.

Project Planning, Scheduling and Control: Assignment 2 D. U. Singer Hospital Products Corp. Project Planning, Scheduling and Control: Assignment 2 D. U. Singer Hospital Products Corp. Code for Course: MBL45-5 Assignment Number: 2 Student number: 75-163-3 Group Code Number: BOT1 Table of Contents

More information

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Unit 4: Time Management (PMBOK Guide, Chapter 6) (PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may

More information

Establishing the HKJC IT PMO. ISACA Forum. Roland Tesmer Head of IT Strategy and Planning The Hong Kong Jockey Club. 8 April 2008

Establishing the HKJC IT PMO. ISACA Forum. Roland Tesmer Head of IT Strategy and Planning The Hong Kong Jockey Club. 8 April 2008 Establishing the HKJC IT PMO ISACA Forum Roland Tesmer Head of IT Strategy and Planning The Hong Kong Jockey Club 8 April 2008 1 Introduction to HKJC IT 2 Mission Committed to One Club, One Team, One Vision,

More information

Department of Public Welfare (DPW)

Department of Public Welfare (DPW) Department of Public Welfare (DPW) Office of Income Maintenance Electronic Benefits Transfer Card Risk Management Report Out-of-State Residency Review FISCAL YEAR 2012-2013 June 2013 (March, April and

More information

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program

More information

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06 SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable

More information

Board Update. Performance Management Activities

Board Update. Performance Management Activities Board Update Performance Management Activities May 2007 Purpose of Today s Meeting Update Board Members Share Scope, Plans & Results» Benchmarking & Performance Improvement» Compliance Activities 1 Chugach

More information

NATIONAL CREDIT UNION SHARE INSURANCE FUND

NATIONAL CREDIT UNION SHARE INSURANCE FUND NATIONAL CREDIT UNION SHARE INSURANCE FUND PRELIMINARY & UNAUDITED FINANCIAL HIGHLIGHTS RENDELL L. JONES CHIEF FINANCIAL OFFICER MANAGEMENT OVERVIEW Balance Sheet Other - Insurance and Guarantee Program

More information

Jeff Haby, P.E. Director Sewer System Improvements. September 15, 2015. Agenda

Jeff Haby, P.E. Director Sewer System Improvements. September 15, 2015. Agenda SAWS Sanitary Sewer Overflow Reduction Program Jeff Haby, P.E. Director Sewer System Improvements SA Military Engineers Meeting Agenda SAWS Overview Consent Decree CD Compliance Programs Program Transition

More information

End of Life Content Report November 2014. Produced By The NHS Choices Reporting Team CH.NHSChoices-Reporting@nhs.net

End of Life Content Report November 2014. Produced By The NHS Choices Reporting Team CH.NHSChoices-Reporting@nhs.net End of Life Content Report November 2014 Produced By The NHS Choices Reporting Team CH.NHSChoices-Reporting@nhs.net End of Life Dashboard Page 1 Overall Choices Site Visits Tag cloud showing end of life

More information

CHILDREN AND YOUNG PEOPLE'S PLAN: PLANNING AND PERFORMANCE MANAGEMENT STRATEGY

CHILDREN AND YOUNG PEOPLE'S PLAN: PLANNING AND PERFORMANCE MANAGEMENT STRATEGY CHILDREN AND YOUNG PEOPLE'S PARTNERSHIP BOARD CHILDREN AND YOUNG PEOPLE'S PLAN: PLANNING AND PERFORMANCE MANAGEMENT STRATEGY 1 Introduction 1.1 The purposes of this strategy are to set out: i) the arrangements

More information

Chapter 7. (PMBOK Guide)

Chapter 7. (PMBOK Guide) Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

INTRODUCTION TO PROJECT MANAGEMENT

INTRODUCTION TO PROJECT MANAGEMENT INTRODUCTION TO PROJECT MANAGEMENT OVERVIEW The purpose of presentation is to provide leaders and team members of projects, committees or task forces with advanced techniques and practical skills for initiating,

More information

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

THE PROJECT MANAGEMENT KNOWLEDGE AREAS THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human

More information

RIIO-T1 business plan submission London Tuesday 6 September 2011

RIIO-T1 business plan submission London Tuesday 6 September 2011 RIIO-T1 business plan submission London Tuesday 6 September 2011 Cautionary statement This presentation contains certain statements that are neither reported financial results nor other historical information.

More information

Resource Management Spreadsheet Capabilities. Stuart Dixon Resource Manager

Resource Management Spreadsheet Capabilities. Stuart Dixon Resource Manager Resource Management Spreadsheet Capabilities Stuart Dixon Resource Manager Purpose Single view of resource data Shows rolling demand vs supply for 14 months, 2 months back, current month, and 11 forward

More information

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010)

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010) Software Development & Education Center Microsoft Office 2010 (Microsoft Project 2010) Mastering Microsoft Project 2010 About This Course This three-day instructor-led course provides students with the

More information

Project Integration Management

Project Integration Management Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform

More information

The purpose of this course is to provide practical assistance for defining and managing project scope.

The purpose of this course is to provide practical assistance for defining and managing project scope. Scope Definition and Scope Management Purpose - To provide practical assistance for defining and managing project scope. This course will focus on tips for creating a scope statement rather than a step-by-step

More information

Computing & Telecommunications Services Monthly Report March 2015

Computing & Telecommunications Services Monthly Report March 2015 March 215 Monthly Report Computing & Telecommunications Services Monthly Report March 215 CaTS Help Desk (937) 775-4827 1-888-775-4827 25 Library Annex helpdesk@wright.edu www.wright.edu/cats/ Last Modified

More information

PROJECT SCOPE MANAGEMENT

PROJECT SCOPE MANAGEMENT 5 PROJECT SCOPE MANAGEMENT Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully

More information

Business Plan Example. 31 July 2020

Business Plan Example. 31 July 2020 Business Plan Example 31 July Index 1. Business Overview 1.1Objectives 1.2Vision Mission and Values 1.3 Keys to Success 2. Business Management 3. Services 2.1 Company Summary 2.2 Company Ownership 2.3

More information

Project Management Concepts

Project Management Concepts Project Management Concepts Day Workshop Course PM12 PM12 - Project Management Concepts Course ID: PM12 Credits: 21 PDUs Course Duration: 3 days Course Level: Basic 3 Days 21 PDUs Course Description: In

More information

2015-16 BCOE Payroll Calendar. Monday Tuesday Wednesday Thursday Friday Jun 29 30 Jul 1 2 3. Full Force Calc

2015-16 BCOE Payroll Calendar. Monday Tuesday Wednesday Thursday Friday Jun 29 30 Jul 1 2 3. Full Force Calc July 2015 CM Period 1501075 July 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 August 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

More information

300 Scheduling and Budgeting

300 Scheduling and Budgeting Jefferson Science Associates, LLC 300 Scheduling and Budgeting Project Control System Manual Revision 7-16 - 300 Scheduling and Budgeting This chapter of the JSA Project Control System Manual describes

More information

plans based on actual cost, schedule and technical progress of work [1, 9].

plans based on actual cost, schedule and technical progress of work [1, 9]. An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan

More information

Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre

Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre Proposal To change the opening hours of the Revenues & Benefits Call Centre to 9am until 5pm Monday to Friday with effect

More information

Equipping your Forecasting Toolkit to Account for Ongoing Changes

Equipping your Forecasting Toolkit to Account for Ongoing Changes Equipping your Forecasting Toolkit to Account for Ongoing Changes Presented by: Roger Parlett Supply Chain Manager January 23, 2014 Overview Forecast Set-up Objectives of Creating a Forecast Identify Critical

More information

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control Activity Definition Input Work Breakdown Structure Scope Statement Historical Information

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information