1 PMP Test C07_ One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02. Estimate at completion (EAC) is a periodic evaluation of: A. Cost of work completed. B. Value of work performed. C. Anticipated total cost at project completion. D. What it will cost to finish the job. 03. If earned value (EV) = 350, actual cost (AC) = 400, planned value (PV) = 325, what is cost variance (CV)? A B C D Double declining balance is a form of: A. Decelerated depreciation. B. Straight line depreciation. C. Accelerated depreciation. D. Life cycle costing. 05. Analogous estimating: A. Uses bottom-up estimating techniques. B. Is used most frequently during the executing processes of the project. C. Uses top-down estimating techniques. D. Allways uses actual detailed historical costs. 06. The cost of choosing one project and giving up another is called: A. Fixed cost. B. Sunk cost. C. Net present value (NPV). D. Opportunity cost. 07. The main focus of life cycle costing is to: A. Estimate installation costs. B. Estimate the cost of operations and maintenance. C. Consider installation costs when planning the project costs. D. Consider operations and maintenance costs in making project decisions. 08. Cost performance measurement is best done through which of the following? A. Asking for a percent complete from each team member and reporting that in the monthly progress report. B. Calculating earned value and using the indexes and other calculations to report past performance and forecast future performance. Página: 1

2 C. Using the 50/50 rule and making sure the life cycle cost is less than the project cost. D. Focusing on the amount expended last month and what will be expended the following month. 09. A cost performance index (CPI) of 0.89 means: A. At this time, we expect the total project to cost 89 percent more than planned. B. When the project is completed we will have spent 89 percent more than planned. C. The project is only progressing at 89 percent of that planned. D. The project is only getting 89 cents value out of every dollar invested. 10. A project schedule performance index (SPI) of 0.76 means: A. The project is over budget. B. The project is ahead of schedule. C. The project is only progressing at 76 percent of the rate originally planned. D. The project is only progressing at 24 percent of the rate originally planned. 11. Which of the following is not needed in order to come up with a project estimate? A. WBS. B. Network diagram. C. Risks. D. Change control procedure. 12. Which of the following is an example of a parametric estimate? A. Dollars per module. B. Learning bend. C. Bottom-up. D. CPM. 13. A less rough order of magnitude estimate is made during which project management process group? A. Project planning. B. Project closing. C. Project executing. D. Project initiating. 14. How close to actual costs should a definitive budget estimate is? A. -75 percent to +25 percent. B. -10 percent to +15 percent. C. +10 percent to -25 percent. D. -15 percent to +20 percent. 15. Which factor would not be considered when choosing between two projects to undertake? A. Net present value (NPV). B. Benefit cost ratio (BCR). C. Payback period. D. Law of diminishing returns. 16. If project A has a net present value (NPV) of U.S. $30,000 and project B has an NPV of U.S. $50,000, what is the opportunity cost if project B is selected? A. $23,000. Página: 2

3 B. $30,000. C. $20,000. D. $50, Which type of cost is team training? A. Direct. B. NPV. C. Indirect. D. Fixed. 18. Project setup costs are an example of: A. Variable costs. B. Fixed costs. C. Overhead costs. D. Opportunity costs. 19. Value analysis is performed to get: A. More value from the cost analysis. B. Management to buy into the project. C. The team to buy into the project. D. A less costly way of doing the same work. 20. Who has the cost risk in a fixed price (FP) contract? A. Team. B. Buyer. C. Seller. D. Management. 21. What formula is used to calculate the EAC, when deciding that the future will be able to meet the approved plan for the project? A. AC + ETC. B. AC + (BAC - EV). C. BAC / CPI. D. AC + ((BAC EV) /CPI X SPI). 22. In calculating the project TCPI using the formula (BAC - EV) / (BAC - AC), we obtain a value of 1. 6 How should we interpret this result? A. Because the index is greater than one, the project goes well, both in cost and on time. B. The project is well on cost, because the index is greater than one C. Because the index is greater than one, the project goes well to the deadline. D. There is not enough budget to complete the work to be done. 23. Meet the project scope required to submit a photocopy machine to the customer. A model costs 10,000 and 5 years. The B model costs 16,000 and lasts 10 years. Maintenance costs of the two models are similar. Following the approach of life cycle cost, which photocopy machine you would choose. A. Model A, the criterion we should deliver the cheapest. B. Model B, because it has a cost closer to his life. C. Model A, because the project budget must be as low as possible. D. Model B, since you always have to deliver the highest quality components. Página: 3

4 24. What better expresses the difference between management reserve and contingency reserve? A. The management reserve is made for known risks and contingency reserve for unknown hazards. B. The management reserve belongs to the project manager and the contingency reserve to the project sponsor. C. The contingency reserve is made for known risks and management reserve for unknown hazards. D. The management reserve is part of the baseline and the contingency reserve is outside. 25. What better expresses the difference between a reserve and padding? A. The reserve is known and shared by the team, while the mattress is hidden by individuals. B. The reserve is estimated to detail (bottom up) and padding at high level (top down). C. Reserve is for known risks and padding for unknown risks. D. Reserve is economic and padding is temporal. Página: 4

5 PMP Test C07_01 Solution Question Area Answer 01 Cost D 02 Cost C 03 Cost D 04 Cost C 05 Cost C 06 Cost D 07 Cost D 08 Cost B 09 Cost D 10 Cost C 11 Cost D 12 Cost A 13 Cost D 14 Cost B 15 Cost D 16 Cost B 17 Cost A 18 Cost B 19 Cost D 20 Cost C 20 Cost C 21 Cost B 22 Cost D 23 Cost B 24 Cost C 25 Cost A Página: 5

Project Cost Management

Project Cost Management Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present

More information

Module 5 Cost Management PMP Exam Questions

Module 5 Cost Management PMP Exam Questions Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional

More information

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:

More information

IST 302 : Project Cost Management

IST 302 : Project Cost Management IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of

More information

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Unit 5: Cost Management (PMBOK Guide, Chapter 7) (PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for

More information

Brainstorm. What is Cost and Project Cost Management?

Brainstorm. What is Cost and Project Cost Management? Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,

More information

Chapter 7. (PMBOK Guide)

Chapter 7. (PMBOK Guide) Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

PMP Exam Preparation Answer Key

PMP Exam Preparation Answer Key Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.

More information

Using Earned Value Management for Improving Processes. By Cynthia K. West

Using Earned Value Management for Improving Processes. By Cynthia K. West Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.

More information

How To Manage Project Cost Management

How To Manage Project Cost Management Chapter 7 Project Cost Management (1) Dr. Feng-Jen Yang Objectives Understand the importance of project cost management Explain basic project cost management principles, concepts, and terms Discuss different

More information

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description

More information

Project Cost Management

Project Cost Management Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost

More information

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Rules on using templates 1) Must reference the template used 2) Use

More information

Project Cost Management. Richard Boser

Project Cost Management. Richard Boser Project Cost Management Richard Boser Project Cost Management Introduction Course Objectives Upon completing today s activities you will be knowledgeable of tools and techniques to: Allocate overall costs

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,

More information

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com Chapter 7: Project Cost Management Munawar moenawar@gmail.com Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.

More information

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue

More information

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP PMP Formulae & Tips Cheat Sheet P a g e Integration Management Develop Project Charter process Project Selection Methods (>> Benefit Measurement Methods >> Economic Models -7) Present Value (PV) FV The

More information

Project Cost Management

Project Cost Management Project Cost Management Martin Pazderka martin.pazderka@inso.tuwien.ac.at INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda

More information

An introduction to Earned Value Analysis

An introduction to Earned Value Analysis An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many

More information

Earned Value Management Guidelines

Earned Value Management Guidelines Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application

More information

Chapter 3: Project Cost Management

Chapter 3: Project Cost Management Chapter 3: Project Cost Management Learning Objectives o Understand the importance of project cost management. o Explain basic project cost management principles, concepts, and terms. o Discuss different

More information

How To Manage A Project

How To Manage A Project Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management

More information

PROJECTS SCHEDULING AND COST CONTROLS

PROJECTS SCHEDULING AND COST CONTROLS Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to

More information

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT http://www.tutorialspoint.com/pmp-exams/project_cost_management.htm Copyright tutorialspoint.com Here is a list of sample questions which would help you to understand the pattern

More information

Project Cost Control: The Way it Works By R. Max Wideman

Project Cost Control: The Way it Works By R. Max Wideman Project Cost Control: The Way it Works By R. Max Wideman 12/21/05 In a recent consulting assignment we realized that there was some lack of understanding of the whole system of project cost control, how

More information

Simple Earned Value (Using MS Project 2010)

Simple Earned Value (Using MS Project 2010) Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained

More information

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints

More information

700 Analysis and Reporting

700 Analysis and Reporting Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how

More information

Tracking Budgets and Schedules

Tracking Budgets and Schedules Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is

More information

Project Management for Scientists

Project Management for Scientists Project Management for Scientists Cost & Schedule Estimates Christoph U. Keller, c.u.keller@uu.nl Sterrekundig Instituut Utrecht Utrecht University www.astro.uu.nl/~keller Outline Resource Assignments

More information

Estimating Cost at Completion - Judgment & EV Information

Estimating Cost at Completion - Judgment & EV Information Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number

More information

Chapter 5: Project Cost Management

Chapter 5: Project Cost Management Chapter 5: Project Cost Management 1 Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource

More information

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management

More information

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

The Two Most Useful Earned Value Metrics: the CPI and the TCPI PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference

More information

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu

More information

Introduction to earn value management in Civil Engineering

Introduction to earn value management in Civil Engineering 3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.

More information

PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating:

PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating: , Fourth Edition Parallels between Cost and Time estimating: There are strong parallels between cost estimating and time estimating so you should have experienced some déjà vu when you first read it. In

More information

Net Present Value and Capital Budgeting. What to Discount

Net Present Value and Capital Budgeting. What to Discount Net Present Value and Capital Budgeting (Text reference: Chapter 7) Topics what to discount the CCA system total project cash flow vs. tax shield approach detailed CCA calculations and examples project

More information

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166 Towards a Complete Earned Value Analysis Sam Sharp and Peter Hall Paper # 166 Planned vs Actual A purely accounting approach to project tracking involves the monitoring of status by simply comparing actual

More information

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and their

More information

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA Basic 1. To calculate the payback period, we need to find the time that the project has recovered its initial investment. After two years, the

More information

Certification Exam Objectives: PK0-003

Certification Exam Objectives: PK0-003 Certification Exam Objectives: PK0-003 INTRODUCTION The CompTIA Project + examination is designed for business professionals involved with projects. This exam will certify that the successful candidate

More information

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by: Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective

More information

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and

More information

Making project management indispensable for business results. Project Management 101

Making project management indispensable for business results. Project Management 101 Making project management indispensable for business results. Project Management 101 Donald E. Moore, MBA, PMP, President of PMI NB Kelly Barter, Chapter Manager of PMI NB AGM April 28, 2011 Topics of

More information

PERCEPTION. Tracking Progress & EAC

PERCEPTION. Tracking Progress & EAC PERCEPTION Tracking Progress & EAC 1 Maximize Efficiency Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge their competition. They can focus

More information

PMI Lexicon of Project Management Terms

PMI Lexicon of Project Management Terms Project Management Institute PMI Lexicon of Project Management Terms Version 3.0 Published by: Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA Phone:

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生

專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生 專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生 講 師 介 紹 > 學 歷 台 灣 大 學 學 士 台 灣 大 學 碩 士 美 國 德 州 大 學 奧 斯 汀 校 區 工 程 專 案 管 理 博 士 中 華 民 國 土 木 工 程 大 地 工 程 水 土 保 持 工 程 專 門 技 術 人 員 高

More information

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office

More information

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761 Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity

More information

Applied Project Management ( APM )

Applied Project Management ( APM ) Applied Project Management Applied Project Management ( APM ) TRAINING PROGRAM Page 1 Of 7 APPLIED PROJECT MANAGEMENT PRO PROGRAM OVERVIEW This course provides in-depth Project Management Training and

More information

EVM.01. Earned Value Analysis Why it Doesn't Work

EVM.01. Earned Value Analysis Why it Doesn't Work EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects

More information

Project Control with ProTrack

Project Control with ProTrack Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS

More information

earned value management

earned value management earned value management in control of big productions an eyeon white paper october 2013 1 contents 4 ly escalation 5 linking and cost control 6 cost forecasting 6 implementation towards effective project

More information

COINS EVA Earned Value Analysis

COINS EVA Earned Value Analysis COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project

More information

A Gentle Introduction to Earned Value Management Systems

A Gentle Introduction to Earned Value Management Systems A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com

More information

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet Project Integration Management Processes required to ensure that the various elements of the project are properly coordinated to meet / exceed stakeholder expectations. Project Plan Development Other ning

More information

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA 1. To calculate the payback period, we need to find the time that the project has recovered its initial investment. After three years, the project

More information

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP

PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP Frequently Asked Questions What is the PMP credential? The PMP (Project Management Professional) credential is a globally recognized certification for

More information

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2

More information

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

Expert Reference Series of White Papers. Importance of Schedule and Cost Control Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project

More information

Earned Value and Agile Reporting

Earned Value and Agile Reporting Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,

More information

PMP Handouts Dr Pratul Sharma Project Management Framework

PMP Handouts Dr Pratul Sharma Project Management Framework Project Management Framework Project: a temporary endeavour undertaken to create a unique product, service or result A project is: Temporary definite start & definite end project is temporary not the result

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT 7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major

More information

11.3 BREAK-EVEN ANALYSIS. Fixed and Variable Costs

11.3 BREAK-EVEN ANALYSIS. Fixed and Variable Costs 385 356 PART FOUR Capital Budgeting a large number of NPV estimates that we summarize by calculating the average value and some measure of how spread out the different possibilities are. For example, it

More information

Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam

Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam Expert Reference Series of White Papers Tips and Techniques to Pass the PMP Exam 1-800-COURSES www.globalknowledge.com Tips and Techniques to Pass the PMP Exam Dan Stober, PMP Introduction Passing the

More information

Tracking Software Development Progress with Earned Value and Use Case Point

Tracking Software Development Progress with Earned Value and Use Case Point ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with

More information

Project Cost Management - 2 Days

Project Cost Management - 2 Days Project Cost Management - 2 Days Course Description: The Cost Management course addresses the identification, elaboration, planning, and management of the project budget. Including selected processes from

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Earned Value Management Tutorial Module 8: Reporting. Prepared by: Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.

More information

Project Cost Management.

Project Cost Management. Chapter 6 (part 2) Project Cost Management. Cost Management consists of 2 main components: - estimate costs - determine budget Objectives: Define and understand key cost management terms Understand all

More information

1 year: $ 15,000. 2 year: $ 125,000. 3 year: $ 220,000

1 year: $ 15,000. 2 year: $ 125,000. 3 year: $ 220,000 SAMPLE PMP PREPARATORY QUESTIONS AND ANSWERS 160 Free PMP Exam Prep Questions (Obtained from PM Connection: http://www.pmconnection.com/modules.php?name=web_links&l_op=viewlink&cid=9 ) http://www.bestsamplequestions.com/pmp-sample-questions/pmp-sample-questions.html

More information

Agile and Earned Value. A white paper. October 2013. Author Stephen Jones, Sellafield Ltd

Agile and Earned Value. A white paper. October 2013. Author Stephen Jones, Sellafield Ltd Agile and Earned Value A white paper October 2013 Author Stephen Jones, Sellafield Ltd This document is a whitepaper produced by the APM Planning, Monitoring and Control SIG. It represents the thoughts

More information

Program Title: Advanced Project Management Program ID: #1025924 Program Cost: $3,780 Duration: 37.5 hours. Program Description

Program Title: Advanced Project Management Program ID: #1025924 Program Cost: $3,780 Duration: 37.5 hours. Program Description Program Title: Advanced Project Management Program ID: #1025924 Program Cost: $3,780 Duration: 37.5 hours Program Description The Advance Project Management course is a training offering for professionals

More information

Which projects should the corporation undertake

Which projects should the corporation undertake Which projects should the corporation undertake Investment criteria 1. Investment into a new project generates a flow of cash and, therefore, a standard DPV rule should be the first choice under consideration.

More information

L10: Budgeting and Cost Control. Olivier de Weck

L10: Budgeting and Cost Control. Olivier de Weck ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen

More information

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 Kym.Henderson@froggy.com.au

More information

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION Author Bill Mowery MPM, PMP Keywords Earned Value Management, Earned Schedule, Project Management, Cost

More information

MC9252 SOFTWARE PROJECT MANAGEMENT UNIT I PART A

MC9252 SOFTWARE PROJECT MANAGEMENT UNIT I PART A MC9252 SOFTWARE PROJECT MANAGEMENT UNIT I PART A 1) What is a project? 2) What is software project management? 3) What are the characteristics of a project? 4) What is the different software projects and

More information

Exercise 2 Cost Management

Exercise 2 Cost Management Exercise 2 Cost Management Distribution: 12.12.2005 Deadline: 21.12.2005 Presentation: 09.01.2005 Total points possible: 20 The homework should be done in pairs of two. It is recommended to solve the problems

More information

Chapter 9 Cash Flow and Capital Budgeting

Chapter 9 Cash Flow and Capital Budgeting Chapter 9 Cash Flow and Capital Budgeting MULTIPLE CHOICE 1. Gamma Electronics is considering the purchase of testing equipment that will cost $500,000. The equipment has a 5-year lifetime with no salvage

More information

Project Cost Management

Project Cost Management Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-982-9 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-982-9 The material contained within

More information

Principles of Project Management

Principles of Project Management IPM 2012 Conference Principles of Project Management David Radkovich, PMP, EVP Subsystem Technologies david.g.radkovich.ctr@mail.mil Karen Jordan, PMP Subsystem Technologies karen.f.jordan.ctr@mail.mil

More information

AACE International Recommended Practice No. 86R 14

AACE International Recommended Practice No. 86R 14 AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment

More information

Certified Project Management Professional VS-1079

Certified Project Management Professional VS-1079 Certified Project Management Professional VS-1079 Certified Project Management Professional Certification Code VS-1079 Vskills certification for Project Management Professional assesses the candidate for

More information

Earned Value Analysis Exercise

Earned Value Analysis Exercise Earned Value Analysis Exercise www.spmbook.com Author: Adolfo Villafiorita Revision: 2 (205-02-06) Given the following project plan: ID Task Immediate Predecessor (*) Expected Duration (days) Budget ($)

More information

The To Complete Performance Index

The To Complete Performance Index The To Complete Performance Index transforming project performance Walt Lipke 1.1 PMI - Oklahoma City Chapter 1.0 +1 405 364 1594 waltlipke@cox.net www.earnedschedule.com Index 1.3 1.2 TCPI vs CPI TCPI

More information

DICTIONARY OF INFORMATION TECHNOLOGY PROJECT MANAGEMENT

DICTIONARY OF INFORMATION TECHNOLOGY PROJECT MANAGEMENT DICTIONARY OF INFORMATION TECHNOLOGY PROJECT MANAGEMENT Edited by EDMOND NG January 2002 A Activity sequencing. Identifying and documenting the relationships between project activities Activity-on-arrow

More information

Project Evolution & Estimation :cash flow forecasting, cost benefit evolution techniques, risk evolution, Cost benefit analysis

Project Evolution & Estimation :cash flow forecasting, cost benefit evolution techniques, risk evolution, Cost benefit analysis Project Evolution & Estimation :cash flow forecasting, cost benefit evolution techniques, risk evolution, Cost benefit analysis EA Cost-benefit Analysis A standard way to assess the economic benefits Two

More information

Project Prioritization

Project Prioritization Project Prioritization and Resourcing Once Size Does Not Fit all 2009 Project Management Symposium Breakout Session D Agenda 1. Overview 2. Prioritization 3. Ideas ROI VOI 4. Resourcing 5. Tips Assignment

More information

Program Title: Advanced Project Management Knowledge, Skills & Software Program ID: #1039168 Program Cost: $4,690 Duration: 52.

Program Title: Advanced Project Management Knowledge, Skills & Software Program ID: #1039168 Program Cost: $4,690 Duration: 52. Program Title: Advanced Project Management Knowledge, Skills & Software Program ID: #1039168 Program Cost: $4,690 Duration: 52.5 hours Program Description The Advance Project Management Knowledge, Skills

More information

Appendix D Glossary Of Terms

Appendix D Glossary Of Terms Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used