Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build
|
|
|
- Gabriel Matthews
- 10 years ago
- Views:
Transcription
1 Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build John H. Moore Nuclear Power Division Paris, France March 11, 2014 (OECD Workshop) International Atomic Energy Agency
2 Exciting Times! International Atomic Energy Agency
3 Barakah-Unit 1, UAE July Concrete pouring after approval of PSAR. Unit 2 followed May The United Arab Emirates is the first country to start the construction of its first nuclear power plant in 27 years, since construction was started on China's first plant in 1985.
4 Sanmen, China Jan 29, 2013 AP-1000 Containment vessel top head placement; Sanmen, China
5 VC Summer Unit 2, USA March 10/11, 2013 First concrete pour of a new NPP in North America in three decades. Followed closely followed by concrete pours at Vogtle Unit 3 (and later by Summer 3 and Vogtle4)
6 Other recent starts (2013 and 2014) Belarus; China (3); South Korea; Argentina.
7 Current status 18 Construction Starts 80 Under Construction Europe-Western Europe-Central & East Asia-Middle East & South Asia-Far East America-North America-Latin Source: PRIS 05-Mar-2014
8 NPP Guidance Nuclear Facility Guidance Safety Requirements MANAGEMENT SYSTEM GUIDANCE
9 GS-G-3.5 Mgmt System for Nuclear Installations - Appendix V Construction Things to do: Define roles and interfaces; Grade requirements based on safety significance; Have well defined processes; Define handover and responsibility transfer processes; Plan activities;
10 GS-G-3.5 Mgmt System for Nuclear Installations - Appendix V Construction Things to do (continued): Have kick off meetings; Control design information; Maintain cleanliness; Maintain control of material; Prevent damage during storage and handling; Verify construction work.
11 Verification of Construction Work Need to have: Methods/schedules for verification that specify levels of inspection & verification required; Suppliers must verify all procurement requirements have been satisfied; Construction activities should follow inspection and test plans (ITPs) approved by organization (Owner);
12 Verification of Construction Work ITPs should have appropriate hold / witness points for owner to verify acceptability; Plan to be prepared to ensure design and regulatory requirements met; Process required to verify construction activities; Verification normally documented via check sheets or similar means to record that SSCs have been constructed and installed to specified requirements.
13 Example quality issues (Sanman, China) RCP impeller : Irregularities welded without documentation; Squib Valve : Manufacturer used components and subcontractor without proper equipment qualification.
14 BEST PRACTICE PUBLICATIONS
15 Project Management in NPP Construction Construction management Preparatory phase; Construction phase (after concrete pouring); Commissioning phase; Main issues and lessons learned Selection of local suppliers; Bulk material management; Worker turnover; Construction equipment; Massive movements of people and material; Public perception; Construction phase closure activities; Country specific lessons learned
16 Construction Technologies for New NPPs Goal: Achieving optimum construction schedule for future NPP construction projects. Content: Comprehensive descriptions of all construction methods; Advantages / disadvantages; Best practices; Lessons learned.
17 Some sample beneficial technologies Early engineering / front end planning; Site construction management support systems Modularization and open top construction; Advanced welding; 4 season construction.
18 Early Engineering Reduce Site Manpower by 40% Previous Design Process Basic Design Detailed Design Construction Construction Engineering Front-Loaded Construction Engineering Basic Design Requirements from Construction Engineering Detailed Design Inputs from Plant Design (BOQ, Composite Design, etc.) Construction Construction Engineering Source : From Hitachi construction experience
19 Issues with a Gen 3+ project design changes by end of 2013; Lead time for nuclear side design change approvals from one month to six months; Engineering completion behind schedule; Insufficient support for regulatory review from off-shore team. Should improve for nth of a kind
20 Site construction management support 建 設 工 程 3D-model linked to schedule
21 6D construction schedules 3D model + Quantities + Resources + Time = 6D database Develop detailed construction schedule by area based on quantities and labour resources; Simulate schedule with 3D-model. 3D-model by construction area Quantities based on 3D-model Schedule loaded with quantities and resources Assign labour resource
22 Modularization Upper Drywell Module RPV RCCV Top Slab Stator (650 ton) (900 ton) (550 ton) (420 ton) RCCV Lower Liner Module Upper Condenser Module 630 ton) (270 ton) RPV Pedestal Module Base Mat Module HPU Module Lower Condensor Unit (410 ton) (460 ton) (270 ton) (260 ton)
23 Sep 27, 2010 Unit 1 CA01 lifting.
24 Man Power (arb.) Manpower Peak Reduction Effort - Construction & Module Experience- 4 Based on previous ABWR (Conventional Method) 3 Level-off Manpower Peak 2 1 Manpower Distribution Construction Progress Based on Latest ABWR (month)
25 Advanced Welding Techniques Quality welding is crucial and time consuming; Advanced Techniques Metal Arc Welding; Gas Tungsten Arc Welding; Submerged Arc Welding; Automatic welding equipment is very effective; Maintains high quality; Improves work environment in narrow spaces.
26 Automatic Welding Machine Automatic Welding Machine for RCCV Liner Automatic Welding for Large Bore Piping Automatic Welding for Small Bore Piping (CRD piping)
27 Four season construction Provides factory-like environment for construction during winter; Secures environment for: Welding; Concrete pouring & curing; Protection from equipment; Allows around the clock work.
28 冬 期 稼 働 率 [%] Four season construction Buildings with the All-Weather Structure (Steel and Temporary cover) Movable Temporary Roof Improvement of Work Productivity during winter 個 別 養 生 耐 候 工 法 全 天 候 耐 候 工 法
29 CONSTRUCTION READINESS REVIEW SERVICE
30 REVIEW SERVICES Phase 1 Phase 2 Phase 3 NPP site review mission IPPAS mission INSSERV mission SCART mission Pre- OSART mission ISSAS mission EPREV mission INIR mission Milestone 1 Milestone 2 NPP construction review mission INIR mission Milestone 3 30
31 Construction Readiness Reviews Focus is on a specific NPP construction project (new build or refurbishment), not the overall programme. Must have design chosen and construction preparations underway at a very detailed level. Guidelines finalized and published. Service available now!
32 REVIEW SERVICES Phase 1 (commit to programme) Phase 2 (invite bids) Phase 3 (commission and operate) NPP site review mission IPPAS mission Stage 1 Construction INSSERV Preparation. mission SCART mission Pre- OSART ISSAS mission Stage 2 EPREV Construction Execution. mission INIR mission INIR mission NPP construction review mission INIR mission Milestone 1 Milestone 2 Milestone 3 32
33 Construction readiness reviews Areas Reviewed: Project Management; Engineering Readiness; Procurement / Material / Supply Chain Readiness; Quality Management and Records; Human Resources and Training; Construction Readiness; Construction Installation Completion Assurance; Targeted Reviews (as requested by customer).
34 Project management area Scope control; Front end planning; Risk management; Project oversight; Project scheduling; Contract & Estmating; procurement Metrics; strategies; Alignment; Change control; Community support; Delay/suspension provisions. Roles & responsibilities;
35 Engineering readiness area Documentation; Feedback incorporation; Design change process; Planning; Configuration mgmt, controlled docs & records; Computer & cyber security; Review of previous work (if delayed project); Eng. Programmes; Eng. quality (Ph2 review).
36 Procurement / material / supply chain readiness Equip./material availability; Procurement procedures and plans; Packaging, warehousing, & transport; Material inspection; Risk management; Quality assurance / quality surveillance.
37 Quality management and records Quality assurance & controls; Independent assessments; Non-conformance / corrective action programmes; Construction experience; Quality surveillance and construction inspection; Controlled documentation and records.
38 Human resources and training Hiring, development, and training; Personnel qualification; Human performance; Health and safety training; Personnel availability; First line supervision and management.
39 Construction readiness Site infrastructure requirements; Regulatory requirements; Tools availability; Construction sequencing; Security and safeguards requirements; Construction execution plans and procedures; Safety management; Environmental management; New construction practices / technologies.
40 Construction completion assurance Process defined; Walkdown processes; Hold points; Open item tracking; Labelling and control of boundaries; Inaccessible items; Interim maintenance during construction.
41 Targeted reviews (upon request) Completed activities and expenditures; Detailed as-experienced schedule review; Variance review; Significant events of interest; Corrective action review; Other areas.
42 E-LEARNING
43 Construction e-learning module Part of a series targeted at newcomer countries, at both senior leader and project team member levels. Topics covered in Construction Module: What makes nuclear construction unique; Important considerations for projects and programmes; How to achieve excellence; Key site considerations. Now available!
44 SOME LESSONS LEARNED
45 Elements needed for successful NPP Health, environment and safety Communicate with regulator and public as early as possible and as much as possible; Quality Quality surveillance of sub-contractors (engineering, construction etc.) should start early; Cover both domestic and foreign vendors; Schedule Level 2 for management; monitor at level 3; Ensure sufficient resources, support contractors; Financial Risk funding needed. Only 25 % NPP projects in China were completed with planned budget.
46 Project management lessons Clearly define roles of Owner and EPC contractor ; Set up PM organization early; Ensure Owner has appropriate contingency funding and risk allocated for unforeseens; Perform surveillance of quality during manufacturing; Need strong site centred PM for EPC and Suppliers;
47 Project management lessons (cont. d) Off-site team should support fully, but not manage site team; Include incentives for on/off site team; Authorized to proceed (ATP) for long lead items equally important with first concrete pour date (FCD); Lead time typically 3 years between ATP and FCD in recommended (China).
48 Thank you for your attention! Follow Nuclear Energy on
Lessons Learned from past NPP Construction Technology/Management
Lessons Learned from past NPP Construction Technology/Management 19 March 2014 Ki Sig Kang Nuclear Power Division International Atomic Energy Agency Trend in Construction Starts Rabidly changed the No.
UAE Nuclear Power Programme : Status and Update
UAE Nuclear Power Programme : Status and Update Technical Meeting on Topical Issues in the Development of Nuclear Power Infrastructure Vienna, 3 rd Feb 2015 Hamad Alkaabi Permanent Representative of the
Hitachi s Involvement in Nuclear Power Plant Construction in Japan
Hitachi s Involvement in Nuclear Power Plant Construction in Japan 48 Hitachi s Involvement in Nuclear Power Plant Construction in Japan Naoki Kajiyama Kenji Hamamura Koichi Murayama OVERVIEW: To protect
Advanced Construction Methods for New Nuclear Power Plants
Advanced Construction Methods for New Nuclear Power Plants A. Introduction Relative to coal fired and natural gas fired power plants, nuclear power plants are more expensive to build but less expensive
Olkiluoto 3 Experience
Olkiluoto 3 Experience CNRA International Workshop on New Reactor Siting, Licensing and Construction Experience Hosted by the State Office for Nuclear Safety Prague, Czech Republic 15-17 September 2010
Westinghouse AP1000 PWR and the Growing Market for New Nuclear Power Plants
Westinghouse AP1000 PWR and the Growing Market for New Nuclear Power Plants Westinghouse Electric Company & The Nuclear Fuel Cycle Royal Commission - South Australia November 4, 2015 1 AP1000 is a trademark
Building New Generation Nuclear Plants Worldwide : AREVA's Experience
Building New Generation Nuclear Plants Worldwide : AREVA's Experience Philippe Guay Senior Vice President, New Builds Offers AREVA 37 th WNA Symposium 12-14 September 2012 LONDON Projects status The value
The ABWR Project at Shimane-3, Japan
CASE STUDIES ON PROJECT AND LOGISTICS MANAGEMENT IN NUCLEAR NEW BUILT The ABWR Project at Shimane-3, Japan Sang-Baik Kim, Jan-Horst Keppler OECD Nuclear Energy Agency, Nuclear Development Division OECD
1.040 Project Management
MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Fred Moavenzadeh Spring 2009
The World Nuclear Supply
The World Nuclear Supply Chain An Overview Greg KASER Staff Director NEA International WPNE Workshop Paris 11 March 2014 Outline of Presentation 1. About WNA 2. Value of: New construction Early dismantlement
Olkiluoto 3 Project. AREVA Suppliers Day Warsaw October 4, 2011
Olkiluoto 3 Project AREVA Suppliers Day Warsaw October 4, 2011 Virginie MOUCQUOT-LAIHO AREVA OL3 Project Management Office & Communications Manager AREVA Reactor & Services - New Builds EPR Project Fleet
The ACR : Advanced Design Features for a Short Construction Schedule
Transactions of the 17 th International Conference on Structural Mechanics in Reactor Technology (SMiRT 17) Prague, Czech Republic, August 17 22, 2003 Paper # S01-3 The ACR : Advanced Design Features for
Engineering, Procurement and Construction (EPC) Projects
Engineering, Procurement and Construction (EPC) Projects Opportunities for Improvements through automation Presented by Robert N. Fox Summary Clarify distinctions between EPC and AEC State EPC Challenges
Auditing Capital Projects and Project Controls. March 2013
Auditing Capital Projects and Project Controls March 2013 Internal Audit Perspective Oversight Insight Foresight Is the process operating as planned? Are controls, resources, and performance measures adequate
Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3
/01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,
Russian approach to organization of international cooperation in the field of nuclear infrastructure (NI)
STATE NUCLEAR ENERGY CORPORATION ROSATOM Russian approach to organization of international cooperation in the field of nuclear infrastructure (NI) A. E. Sitnikov Rosatom/ Rosenergoatom Russia Atomex-Asia
AP1000 Technology: Passive & Proven
AP1000 Technology: Passive & Proven The Right Fit for Brazil Jeff Benjamin Senior Vice President Nuclear Power Plants (NPP) AP1000 is a trademark or registered trademark of Westinghouse Electric Company
Accenture Management Consulting. Open Roles
Accenture Management Consulting Open Roles Who are we? Accenture s Consulting workforce is involved in business consulting, process design work and the application of technologies to business. Management
Ensuring Quality Going Down the Supply Chain
Ensuring Quality Going Down the Supply Chain (Including Vendor Qualification) What is the Role of Operators, Vendors and Regulators? April 21, 2015 DAE-HEE LEE Contents Nuclear Quality Issues The Role
C-41 (May 13) Procurement Engineering and Supply Chain Guidelines in Support of Operation and Maintenance of Nuclear Facilities
C-41 (May 13) Procurement Engineering and Supply Chain Guidelines in Support of Operation and Maintenance of Nuclear Facilities FOREWORD One of the IAEA s statutory objectives is to seek to accelerate
CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS
CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS Presented by W.J. (Chris) Zhang University of Saskatchewan Saskatoon, Canada Email: [email protected] Outline 1. Modularization in NPP 2. Comparison
ROK s Assistance Programs for New comers
ROK s Assistance Programs for New comers TM on Topical Issues in the Development of Nuclear Power Infrastructure, 3-6 February 2015 Kyo Hwang Technology Policy & Strategy Department Korea Hydro & Nuclear
Planning, Organisation and Control of Resources in Construction and the Built Environment
Unit 7: Planning, Organisation and Control of Resources in Construction and the Built Environment NQF Level 3: Guided learning hours: 60 BTEC National Unit abstract A successful project requires careful
Best Practices and Approaches to Supply Chain Management
Best Practices and Approaches to Supply Chain Management ATOMEX Forum 2012 Moscow 12.12. 14.12.2012 AF-Consult Switzerland Ltd Jan Kocourek 1 Objectives Provide information available regarding both the
ENEC Management System and Quality Assurance Program
ENEC Management System and Quality Assurance Program Shami S. Dua Quality Assurance Director IAEA TM on Management System Grading 23-27 January 2012, Vienna, Austria Safety moment ENEC Management System
VENDOR PREQUALIFICATION QUESTIONNAIRE
FM/PR/PM11/03 VENDOR PREQUALIFICATION Project. Doc. : LOCATION: Page. : 1 of 9 Company Name: Company Address: 1. Invitation to Pre qualify Pyramid E&C hereby invites your company to participate in a pre
DOE O 226.1A, IMPLEMENTATION OF DEPARTMENT OF ENERGY OVERSIGHT POLICY CONTRACTOR ASSURANCE SYSTEMS CRITERIA ATTACHMENT 1, APPENDIX A
DOE O 226.1A, IMPLEMENTATION OF DEPARTMENT OF ENERGY OVERSIGHT POLICY CONTRACTOR ASSURANCE SYSTEMS CRITERIA ATTACHMENT 1, APPENDIX A DEFINITIONS Assurance systems encompass all aspects of the processes
Financing Nuclear Power Projects: Challenges and IAEA Assistance in Capacity Building
Financing Nuclear Power Projects: Challenges and Assistance in Capacity Building International Framework for Nuclear Energy Cooperation Finance Workshop London, 9-10 May 2012 Nadira Barkatullah International
Introduction to Social Compliance & Its Business Benefits
Proposal for Conducting Seminar on Introduction to Social Compliance & Its Business Benefits Submitted to: Environment Agency, Abu Dhabi Table of Contents Summary..02 Seminar Objectives 02 Content Outline..02
Technical Meeting on Fire Protection Approaches and Experiences in Nuclear Power Plants
Technical Meeting on Fire Protection Approaches and Experiences in Nuclear Power Plants IAEA Headquarters Vienna, Austria 27 29 May 2015 Ref. No.: I2-TM-50054 Information Sheet A. Introduction The lessons
Vogtle. Twelfth Semi-annual Vogtle Construction Monitoring Report. units 3 & 4. February 2015 Docket No. 29849
Vogtle units 3 & 4 Twelfth Semi-annual Vogtle Construction Monitoring Report February 2015 Docket No. 29849 The CA05 wall module is lifted into the Vogtle Unit 3 containment vessel Vogtle Units 3 and
R000. Revision Summary Revision Number Date Description of Revisions R000 Feb. 18, 2011 Initial issue of the document.
2 of 34 Revision Summary Revision Number Date Description of Revisions Initial issue of the document. Table of Contents Item Description Page 1. Introduction and Purpose... 5 2. Project Management Approach...
IAEA Safety Standards for Regulatory Activities
Safety Standards for Regulatory Activities April 2010 Gustavo Caruso Regulatory Activities Section Division of Nuclear Installation Safety International Atomic Energy Agency Content Safety Standards and
Materials Management:
Materials Management: Damodara U. Kini, P.E. OFTEN OVERLOOKED AS A COST SOLUTION, SUCCESSFULLY MANAGING MATERIALS CAN LEAD TO GREATER SAVINGS. Damodara U. Kini is procurement manager at Raytheon, Engineers
REPORT 2016/035 INTERNAL AUDIT DIVISION
INTERNAL AUDIT DIVISION REPORT 2016/035 Audit of the use of consultants and individual contractors in the United Nations Stabilization Mission in Haiti Overall results relating to the effective hiring
POWER & RENEWABLE ENERGY SERVICES
POWER & RENEWABLE ENERGY SERVICES Nuclea Siting - Assistance to permitting Environmental Impact Assessment Safety and environmental audits Construction code compliance and design review Supplier Technical
MISSION REPORT ON THE INTEGRATED NUCLEAR INFRASTRUCTURE REVIEW (INIR)
MISSION REPORT ON THE INTEGRATED NUCLEAR INFRASTRUCTURE REVIEW (INIR) Counterpart: Ministry of Economy 18 to 22 March 2013 Warsaw, Poland CONTENTS 1. EXECUTIVE SUMMARY... 3 2. INTRODUCTION... 5 3. OBJECTIVES
How to successfully manage your mega-project
BUILDING, CONSTRUCTION & REAL ESTATE How to successfully manage your mega-project Part II Stakeholder communication and project controls integration kpmg.com 2 Building, Construction & Real Estate How
MANAGEMENT SYSTEM FOR A NUCLEAR FACILITY
GUIDE YVL A.3 / 2 June 2014 MANAGEMENT SYSTEM FOR A NUCLEAR FACILITY 1 Introduction 5 2 Scope of application 6 3 Management system 6 3.1 Planning, implementation, maintenance, and improvement of the management
POWER & RENEWABLE ENERGY SERVICES
POWER & RENEWABLE ENERGY SERVICES Siting - Assistance to permitting Environmental Impact Assessment Safety and environmental audits Construction code compliance and design review Supplier Technical Assessment
Experience and Qualifications of PROCESS PLANTS CORPORATION
Experience and Qualifications of PROCESS PLANTS CORPORATION Table of Contents Section 1. Project Services pg 3-20 Engineering Services Project management Design engineering Design management Construction
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
QUALITY ASSURANCE GUIDE FOR PROJECT MANAGEMENT
NOT MEASUREMENT SENSITIVE DOE G 413.3-2 6-27-08 QUALITY ASSURANCE GUIDE FOR PROJECT MANAGEMENT [This Guide describes suggested non-mandatory approaches for meeting requirements. Guides are not requirements
Capacity Building and Human Resource Development for Nuclear Power Programmes
Technical Meeting on COOPERATION FOR HUMAN RESOURCE DEVELOPMENT (HRD) AMONG EMBARKING AND EXPERIENCED COUNTRIES Vienna, 04 06 June, 2013 Capacity Building and Human Resource Development for Nuclear Power
& Start-up Directory
& Start-up Directory INTEGRATED SERVICE SOLUTIONS Index C H A P T E R 1 INTRODUCTION 4 C H A P T E R 2 COMMISSIONING & START UP SERVICE 5 2.1 Standard Implementation Path 6 2.2 The Home Office Phase 7
Quality Management Plan
6500m HOV Project Stage 1: A-4500 HOV Document Control No.: 0000000 3-November-2009 WOODS HOLE OCEANOGRAPHIC INSTITUTION WOODS HOLE, MA 02543 Document Control Sheet Date Originator Description 07-28-09
Global Nuclear Power Developments Asia Leads The Way
Global Nuclear Power Developments Asia Leads The Way Edward Kee Nuclear Energy Asia 2010 - Hong Kong (1400 1430) Global Nuclear Power Developments - Asia Leads The Way What is the competitive global position
https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework
All interested parties Direct Dial: 020 7901 1849 Email: [email protected] Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance
PROJECT AND PORTFOLIO MANAGEMENT - NUCLEAR
Page 1 of 5 PROJECT AND PORTFOLIO MANAGEMENT - NUCLEAR 1.0 PURPOSE This evidence provides an overview of the nuclear operations project portfolio and other related project work. The project portfolio includes
The Role of Nuclear Knowledge Management
The Role of Nuclear Knowledge Management A. Introduction The Agency has been a focal point for nuclear knowledge and information since its establishment in 1957. Nuclear knowledge management (NKM) came
Engineering Procurement Construction Quality Plan
Engineering Procurement Construction Quality Plan Index 1 Introduction... 4 1.1 Project Background... 4 1.2 Document Purpose... 4 1.3 Change Control... 4 1.4 Contract... 4 1.5 Quality system... 4 1.6 Distribution...
Nuclear Consultancy & Engineering Services
Insert a caption to go with the photograph in here ITER, France Wednesday, 14 December 2011 Nuclear Consultancy & Engineering Services T H E N U C L E A R A T K I N S A S S Y S T E M A L L I A N C E CONSTRUCTION
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM 2015 Business Plan Chapter 3, Water Facilities Focus Area, Goal Number 4 June 2011 CAPITAL IMPROVEMENT PROGRAM
PROCUREMENT OF MAINTENANCE SERVICES AND HEALTH AND SAFETY AT WORK
63 PROCUREMENT OF MAINTENANCE SERVICES AND HEALTH AND SAFETY AT WORK 1. Introduction Outsourcing has been an increasing trend in modern work organisations throughout many years now. A report and a fact
September 20, 2011 SUBJECT: NRC INSPECTION REPORT NO. 99901387/2011-202 AND NOTICE OF NONCONFORMANCE
Mr. David Barry, President Nuclear Division, Shaw Power Group 128 South Tryon Street Suite 400 Charlotte, NC 28202 September 20, 2011 SUBJECT: NRC INSPECTION REPORT NO. 99901387/2011-202 AND NOTICE OF
The Comprehensive Coatings Service Provider to Industry
Coating Systems Excellent Engineering Solutions The Comprehensive Coatings Service Provider to Industry 2 Coating Systems Weir Coatings specialises in the application of high performance protective linings
QUALITY MANAGEMENT SYSTEM REVIEW AND APPROVAL TEMPLATE (DOE G 414.1-2A, Appendix A, 6-17-05)
QUALITY MANAGEMENT SYSTEM REVIEW AND APPROVAL TEMPLATE (DOE G 414.1-2A, Appendix A, 6-17-05) This review template is intended for use by the DOE for evaluating a DOE Site Office or Contractor Quality Assurance
Quality Assurance QUALITY ASSURANCE PLAN
Revision 2 Page 1 of 40 QUALITY ASSURANCE PLAN PLAN APPROVALS: Jeff Shouse Signature on File DIRECTOR OF QUALITY ASSURANCE DIRECTOR OF QUALITY ASSURANCE (signature) DATE Rodney Baltzer Signature on File
AREVA: supply chain network principles and company s vision
AREVA: supply chain network principles and company s vision Virginie MOUCQUOT-LAIHO AREVA Finland Communications Director & Vice Country Manager Oulu, Finland 18.09.2012 1 AREVA & nuclear industry The
Industry Solutions Oil and Gas Engineering Document Control and Project Collaboration Solutions for Oil and Gas
Industry Solutions Oil and Gas Engineering Document Control and Project Collaboration Solutions for Oil and Gas Industry Solutions Managing the complexity of major capital projects in today s oil and gas
Long term operation integrated processes for delivering extended asset performance
Long term operation integrated processes for delivering extended asset performance 15 04 2015 Agenda 1. Introduction 2. Long term operation process for delivery 3. Business planning and key assumptions
Join the UK Nuclear Renaissance. Procurement & Quality Process
Join the UK Nuclear Renaissance Procurement & Quality Process 1 AREVA NP UK Supplier Day, March 16th Birmingham EPR is a trademark of the AREVA Group 1 The Process: AREVA Supply Chain Strategy Didier David
TOSHIBA s Nuclear Energy Activities
December 12, 2010 IGARASHI, Yasuharu Toshiba Corporation, Executive Officer Corporate Senior Vice President President & CEO, Power Systems Company Export Control No. PSN-2010-1406 Document No. G3-1109
AP1000 European 18. Human Factors Engineering Design Control Document
18.2 Human Factors Engineering Program Management The purpose of this section is to describe the goals of the AP1000 human factors engineering program, the technical program to accomplish these goals,
NOT PROTECTIVELY MARKED
Title of document ONR GUIDE Supply Chain Management Arrangements for the Procurement of Nuclear Safety Related Items or Services Document Type: Unique Document ID and Revision No: Nuclear Safety Technical
Executive Development Workshop. A Systems Approach to Inventory Management
Executive Development Workshop A Systems Approach to Inventory Management OVERVIEW Inventory management is important from the view point that it enables to address two important issues - maintaining adequate
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling
Qualification of In-service Inspections of NPP Primary Circuit Components
Qualification of In-service Inspections of NPP Primary Circuit Components ABSTRACT Matija Vavrouš, Marko Budimir INETEC Institute for nuclear technology Dolenica 28, 10250 Zagreb, Croatia [email protected],
WORK SCOPE. Domains in which we work:
WORK SCOPE Engineering consulting, technical office, assistance and supervision in industrial works. We specialize in structures, civil works and industrial equipment. Domains in which we work: Industrial
Cyber Security and the Canadian Nuclear Industry a Canadian Regulatory Perspective
Cyber Security and the Canadian Nuclear Industry a Canadian Regulatory Perspective Terry Jamieson Vice-President Technical Support Branch Canadian Nuclear Safety Commission August 11, 2015 www.nuclearsafety.gc.ca
SUPPLIER QUALITY MANAGEMENT SYSTEM QUESTIONNAIRE
Company Name Street Address City, State, Zip code Phone Number Fax Company Website Email Address ORGANIZATION NAME PHONE NUMBER EMAIL ADDRESS President/CEO General Manager Engineering Manager Production
ABSTRACT. The Guidelines Section F is related to the Purchasing requirements of NSQ100 (Chapter 7.4). Summary
Page 1 / 9 ABSTRACT This document is the Section F to NSQ-100 Guidelines. Its objective is to help to the understanding of NSQ-100 requirements through some examples or recommendations and descriptions
NZQA registered unit standard 25872 version 2 Page 1 of 5. Develop and implement a project plan to deliver on an Infrastructure works contract
Page 1 of 5 Title Develop and implement a project plan to deliver on an Infrastructure works contract Level 5 Credits 15 Purpose People credited with this unit standard are able to: explain relationship
MSD Supply Chain Programme Strategy Workshop
MSD Supply Chain Programme Strategy Workshop Day 2 APPENDIX Accenture Development Partnerships Benchmarking MSD s Current Operating Supply Chain Capability 1.0 Planning 2.0 Procurement 3.0 Delivery 4.0
How to successfully manage your mega-project. Part III Continuously improve your chances for project success. kpmg.com
How to successfully manage your mega-project Part III Continuously improve your chances for project success kpmg.com 2 Building, Construction & Real Estate Mega-project keys to success Early planning and
JOINT INTEGRITY MANAGEMENT SOLUTIONS
JOINT INTEGRITY MANAGEMENT SOLUTIONS Joint Integrity Management Solutions Some 30 years after developing the technology behind hydraulic bolt tensioning, Hydratight continues to push the boundaries with
Part 1 General and Administrative Information. Part 3 Applicant s Environmental Report Combined License Stage
Part 16 South Carolina Electric and Gas V. C. Summer Nuclear Station, Units 2 & 3 COL Application COLA Table of Contents Navigation Page Part 1 General and Administrative Information Part 2 Final Safety
ALL PRODUCTS MFG & SUPPLY
ALL PRODUCTS MFG & SUPPLY 618 ANDERSON DRIVE ROMEOVILLE, IL 60446 PHONE: 877-255-8700 FAX: 877-255-8701 WWW. APGASKET.COM QUALITY MANAGEMENT SYSTEM MANUAL DATE: 11/20/12 REVISION 9.1 UNCONTROLLED COPY
AREVA, an unparalleled experience in building nuclear reactors
AREVA, an unparalleled experience in building nuclear reactors Frank APEL Senior Vice President Sales Central Europe and Nordic Countries AREVA, International Commercial Organisation 9 th Annual European
Earned Value Management Tutorial Module 8: Reporting. Prepared by:
Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.
APPENDIX B SUPPLEMENTAL INSPECTION PROGRAM A. OBJECTIVES AND PHILOSOPHY OF THE SUPPLEMENTAL INSPECTION PROGRAM
APPENDIX B SUPPLEMENTAL INSPECTION PROGRAM A. OBJECTIVES AND PHILOSOPHY OF THE SUPPLEMENTAL INSPECTION PROGRAM The supplemental inspection program is designed to support the NRC s goals of maintaining
Quality Management System
LH Sleightholme Ltd, Westfield Works, Helperthorpe, Malton, North Yorkshire YO17 8TQ Quality Management System MANUAL ISO 9001:2008 This Quality Management System Manual has been issued on the authority
PM in construction industry
PM in construction industry Construction 2. Lepel BME Department of Construction Technology and Management 19-03-2014 PM in general Project integration Project plan development Project plan execution Integrated
INSPECTION AND CONSTRUCTION MANAGEMENT CAPABILITIES
INSPECTION AND CONSTRUCTION MANAGEMENT CAPABILITIES 9601 JONES ROAD, SUITE 242 HOUSTON, TEXAS 77065 (832) 678-2210 FAX (832) 678-2310 Table of Contents SECTION 1 - CORPORATE OVERVIEW... 3 SECTION 2 - RESPONSIBILITIES
Introduction Building project management
Introduction Building project management Construction management 2. (BMEEPEKT601-BMEEPEKK601) 10-02-2011 Introduction Lecturers: Adrienn Lepel PhD István Vidovszky PhD Guest lecturers Requirements Two
Rev: Issue 4 Rev 4 Quality Manual AOP0101 Date: 10/07/13. Quality Manual. CBT Technology, Inc. 358 North Street Randolph, MA 02368
Quality Manual CBT Technology, Inc. 358 North Street Randolph, MA 02368 Issue 4 Revision 4 Note: updates are in italics Page 1 of 18 1.0 Scope and Exclusions Scope This Quality Manual contains policies
Bogue Machine Company, Inc. Business Instruction
Bogue Machine Company, Inc. Business Instruction Document Title: Supplier Quality Control Requirements Document Number: Revision: Document Owner: Mark Bogue Backup Owner: Craig Bogue Parent Document: PURP-004,
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
AS9100 Quality Manual
Origination Date: August 14, 2009 Document Identifier: Quality Manual Revision Date: 8/5/2015 Revision Level: Q AS 9100 UNCONTROLLED IF PRINTED Page 1 of 17 1 Scope Advanced Companies (Advanced) has established
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
CHARACTERISTICS OF SUCCESSFUL MEGAPROJECTS
Chapter Six CHARACTERISTICS OF SUCCESSFUL MEGAPROJECTS Bibliographic Information: Committee to Assess the Policies and Practices of the Department of Energy to Design, Manage, and Procure Environmental
Quality Assurance Manual ISO 9001:2000. Uncontrolled copy
ISO 9001:2000 Uncontrolled copy Approved by: Hugue Meloche, Eng. Page 1 of 24 Intellectual Property This document, prepared by Meloche Group Inc. for its company in the Valleyfield region, remains the
Title: Rio Tinto management system
Standard Rio Tinto management system December 2014 Group Title: Rio Tinto management system Document No: HSEC-B-01 Standard Function: Health, Safety, Environment and Communities (HSEC) No. of pages: 23
3.03 College Board Advanced Placement Test means the Advanced Placement test administered by the College Board and Educational Testing Service.
Arkansas Department of Education Rules for Advanced Placement and International Baccalaureate Diploma Incentive Program And Rules Governing Advanced Placement Courses in the Four Core Areas in Arkansas
COMPARISON OF ELECTRICITY GENERATION COST OF NPP WITH ALTERNATES IN PAKISTAN
COMPARISON OF ELECTRICITY GENERATION COST OF NPP WITH ALTERNATES IN PAKISTAN IAEA INPRO dialogue forum 8 toward nuclear energy system sustainability: economics, resource availability and institutional