1 Welcome Christopher R. Paolini, P.E., Sr. Vice President CME Associates, Inc Corporate Drive East Syracuse, New York (315) (315) (Fax) 1
2 Building Code of New York State Emphasis on Chapter 17 Sections Structural Tests & Special Inspections *With updates from the 2010 Building Code of New York State, which is now in effect. 2
3 Chapter 17 Structural Testing and Special Inspections I have discussed the topic of Structural Tests and Special Inspections to various groups, including CEO s, Architects, Engineers, and Contractors I have catered today s discussion to meet your needs as a Design Professional. 3
4 4
5 5 Atlantic City Garage
6 Chapter 17 Structural Testing and Special Inspections To go through Chapter 17 and all references of the Building Code of NYS, would literally take weeks to do. It is my intent today to give your staff the basic understanding of Chapter 17, so that each and everyone of you can bring that knowledge into your projects. 6
7 Chapter 17 Structural Testing and Special Inspections Section: Content: 1701 General No changes from 2007 BCNYS Definitions Some minor changes from 2007 BCNYS 1703 Approvals No changes from 2007 BCNYS 1704 Special Inspections Several changes from 2007 BCNYS. To be discussed herein. 1 BCNYS = Building Code of New York State 7
8 Chapter 17 Structural Testing and Special Inspections Don t get too worried about the thought of Special Inspections and Structural Tests. Structural Testing and Special Inspections services have been required and specified prior to The difference now is that these items are defined in the code and now are the LAW. Additionally, the Owner pays for the Structural Testing and Special Inspection services, not the Contractor. 8
9 Seminar Guidance Building Code of New York, 2007 and 2010, Chapter 17, Structural Testing and Special Inspections. DOS Technical Bulletin, Volume5- No.7, Structural Testing and Special Inspections. Oct 03. DOS Technical Bulletin, Volume 5- No.8, Inspection of Fabricators. Dec 03 ASTM E , Standard Specifications for Agencies Engaged in the Testing and/or Inspection of Materials used in Construction. ASTM C-1077 Standard Practice for laboratories Testing Concrete and Concrete Aggregates for use in Construction and Criteria for Laboratory Evaluation. 9
10 What are Special Inspections? Answer Inspection as required of the materials, installation, fabrication, erection, or placement of components and connections requiring special expertise to ensure compliance with approved construction documents and referenced standards. 10
11 Special Inspections may be Continuous, i.e. full time observation of work OR Periodic, i.e. part-time or intermittent observation of work 11
12 Definitions Approved Agency: An established and recognized agency regularly engaged in conducting tests or furnishing inspection services, when such agency has been approved. 12
13 Approved Agency To become an Approved Agency, the agency shall prove to the Code Enforcement Official that the agency: Is independent Has adequate, calibrated equipment Has experienced, certified personnel 13
14 Lets take a moment to talk about Laboratory Accreditation. Chapter 17, Table , Reinforced Concrete Construction, references ACI 318 ACI 318 references ASTM C1077, Standard Practice for Agencies Testing Concrete and Concrete Aggregates for Use in Construction 14
15 ASTM C , Under Section 11, Testing Agency Evaluation states that The testing agency shall have its facilities, equipment, personnel, and procedures evaluated at intervals of approximately 2 years by an evaluation authority to confirm its ability to perform the required tests. Two methods of evaluation, either inspection or accreditation, are acceptable.
16 16 I point these requirements out, because you, as the Design Professional, could be responsible to hire the Special Inspection Agency. If an unqualified agency is hired and something goes wrong, such as a catastrophic failure, you as the Design Professional, would get tied into the problem.
17 17 CME s approval letter for the City of Syracuse
18 Definitions Special Inspector: The special Inspector shall be a qualified person who shall demonstrate competence, to the satisfaction of the Code Enforcement Official for inspection of the particular type of construction or operation requiring special Inspection. Additionally, the qualifications outlined in Table identify the minimum qualifications of the Special Inspector. *New to 2010, the Special Inspector shall provide written documentation to the C.E.O. demonstrating their competence and relevant experience or training. 18
19 Special Inspector Qualifications Note: This table has now become Table , Minimum Qualifications for Special Inspectors. 19
20 20 Additionally, the Code Enforcement Official can approve alternate qualifications for Special Inspectors.
21 Special Inspection Section Special Inspections - Building Permit Requirement. The permit applicant shall submit a statement of special inspections prepared by the registered design professional in responsible charge as a condition for permit issuance. *New to 2010, conventional light frame construction projects will not require a statement of special inspections. 21
22 Another edit to 2010, the list of approved agency or agencies to conduct Special Inspections does not need to be listed in the Statement of Special Inspections.
23 Report Requirements Section Report Requirement A final report documenting required special inspections and correction of any discrepancies noted in the inspections shall be submitted at a point in time agreed upon by the permit applicant and the code enforcement official prior to the start of work. 23
24 Statement of Special Inspections The statement of Special Inspections SHALL: Be prepared by a registered design professional in responsible charge or if construction is not designed by an RDP, then a qualified person approved by the CEO may prepare it. Include a complete listing of materials, work, systems and components requiring Special Inspections. Outline the inspections to be performed and the frequency to perform them. New to 2010, additional requirements for special inspections or tests for seismic or wind resistance. 24
25 25
26 26 *Note, this table can be in here, but is not required to be in here.
27 27
28 28
29 29
30 30
31 Another Change from 2007 to 2010, is in Section , Mastic and Intumescent Fire-Resistant Coatings Special inspections for mastic and intumescent fire-resistant coatings applied to structural elements and decks shall be in accordance with AWCI 12-B. Special inspections shall be based on the fireresistance design as designated in the approved construction documents. 31
32 Chapter 17 Structural Testing and Special Inspections It should be noted that at the end of the project, the Special Inspector is required to submit a final report. This report must list any non-conforming test or inspection items. Non-conforming test or inspection items may inhibit the owner from getting a certificate of occupancy. Therefore, I recommend that a non-conformance list be generated periodically, say every two weeks or monthly, during the project to keep everyone on the same page regarding problem items. 32
33 33
34 CEO Responsibilities The CEO is the only one with the legal authority to enforce the Special Inspections provision of the BCNYS 34
35 The CEO SHALL: Review the submitted documents for compliance with the Special Inspection requirements Approve the Special Inspector(s) by evaluating the competence of the Special Inspector(s) Approve the Special Inspection Program submittal prior to the issuance of the Building Permit. Monitor the Special Inspection activities Review the Special Inspection Reports Perform the FINAL Inspection /Issue the Certificate of Occupancy AFTER the final Special Inspection report has been received and approved 35
36 Considerations and Questions 36
37 Chapter 17 Quiz 1. What are Special Inspections? Inspection as required of the materials, installation, fabrication, erection, or placement of components and connections requiring special expertise to ensure compliance with approved construction documents and referenced standards. 2. Who Approves the Special Inspector? The Code Enforcement Official. 3. Who hires the Special Inspector? The Owner or the Owner s Agent. 4. Does Chapter 17 provide a table for Soil Tests and Inspections? Yes. 5. Who prepares the Statement of Special Inspections? The Registered Design Professional or if an RDP does not design the construction, a qualified person approved by the CEO. 6. Name another change to Section 1704 of Chapter 17 from 2007 to
38 Any further questions? Thank you. 38
Contractor s Statement of Responsibility for Seismic-Force-Resisting Systems This form is to be filled out by the contractor.
SPECIAL INSPECTION PROCEDURE IBC CHAPTER 17 2012 EDITION When Required All projects that require a SC licensed Architect or Engineer per SC Architectural and Engineering registration law. Overview The
INDIANA DEPARTMENT OF TRANSPORTATION QUALIFIED LABORATORY AND TECHNICIAN PROGRAM
1/1/13 INDIANA DEPARTMENT OF TRANSPORTATION QUALIFIED LABORATORY AND TECHNICIAN PROGRAM The purpose of the Qualified Laboratory and Technician Program is to establish policies, procedures, and guidelines
CITY & COUNTY OF DENVER COMMUNITY PLANNING & DEVELOPMENT BUILDING PERMIT POLICY Special Inspector Qualification Michael Roach, P.E., Building Official
Reference: IBC Chapter 17, Section 1704 General: Special inspections required by IBC Chapter 17 shall be conducted by qualified persons working for an approved agency. The Building Official shall maintain
Construction Management Program
Use and Limitation: The Sponsor may use this document as a guide in preparing a construction management program for their specific project. Sponsors and Consultants are cautioned that the provision of
ACCREDITATION CRITERIA FOR SPECIAL INSPECTION AGENCIES AC291. June 2013 (Effective July 1, 2013) (Editorially revised June 4, 2015)
ACCREDITATION CRITERIA FOR SPECIAL INSPECTION AGENCIES AC291 June 2013 (Effective July 1, 2013) () (Previously issued in January 2005 as Requirements; May 2005, August 2006, May 2007, April 2008, September
SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE
Community Development Permit Services SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE PROJECT NAME PROJECT ADDRESS PERMIT NUMBER CITY RECEIVED STAMP AND INITIALS Instructions: BEFORE
STRUCTURAL TESTS AND SPECIAL INSPECTIONS
CHAPTER 17 STRUCTURAL TESTS AND SPECIAL INSPECTIONS SECTION 1701 GENERAL 1701.1 Scope. The provisions of this chapter shall apply to Class I buildings and shall govern the quality, workmanship and requirements
1 RCNY 101-06 CHAPTER 100. (a) Definitions. For the purposes of this chapter, the following terms will have the following meanings:
1 RCNY 101-06 CHAPTER 100 Subchapter A Administration 101-06 inspectors special inspection agencies. (a) Definitions. For the purposes of this chapter, the following terms will have the following meanings:
Section 1. The title of Section 101-07 of Subchapter A of Chapter 100 of Title 1 of the Rules of the City of New York is amended to read as follows:
Section 1. The title of Section 101-07 of Subchapter A of Chapter 100 of Title 1 of the Rules of the City of New York is amended to read as follows: 101-07 [Inspections and] [a] Approved [a] Agencies.
1 RCNY 101-07 CHAPTER 100
1 RCNY 101-07 CHAPTER 100 Subchapter A Administration 101-07 Approved Agencies. (a) Definitions. For the purposes of this section, all terms used herein shall have the same meanings as set forth in the
CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES
1.0 SCOPE CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES This document establishes the minimum quality program requirements for a contractor providing equipment, material, and construction
VDOT GOVERNANCE DOCUMENT
VDOT GOVERNANCE DOCUMENT Minimum Requirements for Quality Assurance and Quality Control on Design Build and Public-Private Transportation Act Projects Location and Design Division Alternate Project Delivery
FAIRFAX COUNTY, VIRGINIA. SPECIAL INSPECTIONS PROGRAM 2012 Edition (2012-SIP) Effective: July 14, 2014
FAIRFAX COUNTY, VIRGINIA SPECIAL INSPECTIONS PROGRAM 2012 Edition (2012-SIP) Effective: July 14, 2014 Publication date: July 14, 2014 Based on Virginia Uniform Statewide Building Code (2012) Edition 13
SECTION 03400 PRECAST CONCRETE STRUCTURES
SECTION 03400 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for precast concrete structures, including fabrication and erection. 1.02 REFERENCE STANDARDS A. American Society for
17 East Main Street Cuba,NewYork 14727 www.cubany.org 585-968-1560. Code Enforcement
17 East Main Street Cuba,NewYork 14727 www.cubany.org 585-968-1560 Code Enforcement Useful Information Office Information What is zoning? When Do I Need a Building Permit? When are Permits Not Required?
C. Section 014510 TESTING LABORATORY SERVICE.
SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,
STATEMENT OF WORK (SOW) On-Call Certified Welding Inspections and Nondestructive Testing
1.0 INTRODUCTION Colorado Springs Utilities (UTILITIES) is seeking qualified firms to provide verification welding inspection services, nondestructive testing services, and technical reporting to Colorado
CHAPTER 67.2 RESIDENTIAL BUILDING CODE
CHAPTER 67.2 RESIDENTIAL BUILDING CODE 1. APPLICABILITY. This Chapter shall have, along with the Code adopted hereby, the scope and applicability set out in said code except as modified by the provisions
Section 100 Contractor Quality Control Program
7/21/2014 AC 150/5370-10G Section 100 Contractor Quality Control Program 100-01 General. When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and
Placement of Manufactured Homes on Private Property
PURPOSE Placement of Manufactured Homes on Private Property To establish a procedure for permitting and inspecting a manufactured home or mobile home on private property. For the purpose of this policy,
MODEL PROGRAM FOR SPECIAL INSPECTION BASED ON IBC CHAPTER 17
MODEL PROGRAM FOR SPECIAL INSPECTION BASED ON IBC CHAPTER 17 Model Program for Special Inspection: Based on IBC Chapter 17 ISBN 1-58001-292-2 COPYRIGHT 2005, International Code Council ALL RIGHTS RESERVED.
Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS
Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS 8.1.1 PURPOSE This procedure provides guidelines related to the implementation of quality control and quality assurance
FACILITY FIRE-SUPPRESSION WATER-SERVICE PIPING 21 11 00
211100_flexheadin_01_MS_0409 5/22/09 PTC 56 Lowland Street Holliston, MA 01746 Phone: (800) 829-6975 Phone: (508) 893-9596 Fax: (508) 893-6020 E-mail: [email protected] www.flexhead.com This MANU-SPEC
PROJECT SUMMARY. Scope of work details: (If phased construction, please see plan submittal guidelines.)
APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL FIRE RESTORATION PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES) (Reproduce the following data on the building plans sheet 1 or 2) Name of
PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE
FORM A PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE The following suggested specifications are written as a guide to assist the specifier in writing his own specifications. Specific circumstances
Example Specification for Concrete using Current Building Code Requirements
Example Specification for Concrete using Current Building Code Requirements DISCLAIMER: This specification is an example that accompanies a seminar titled The P2P Initiative: Performance-based Specs for
GENERAL WELDING & FABRICATING, INC. 991 Maple Road Elma, New York 14059
QUALITY MANUAL GENERAL WELDING & FABRICATING, INC. 991 Maple Road Elma, New York 14059 Distribution: Position Location Copy # President / CEO Office 1 Operations Manager Office 2 Quality Assurance Office
Georgia Department of Transportation. Office of Materials and Research. Standard Operating Procedure (SOP) 19
Laboratory SOP 19 Revised July 1, 2003 Georgia Department of Transportation Office of Materials and Research Standard Operating Procedure (SOP) 19 This Standard Operating Procedure provides a means whereby
Implementing ISO 9000 Quality Management System
Implementing ISO 9000 Quality Management System Implementation of ISO 9000 affects the entire organization right from the start. If pursued with total dedication, it results in 'cultural transition' to
CHAPTER 4 CONCRETE TRAINING AND QUALIFICATIONPROGRAM
Concrete Training Qualification Program Topic No. 700-000-001 Effective: July 1, 2002 Construction Training and Qualification Manual Revision: March 22, 2011 Concrete Training and Qualification Program
Frequently Asked Questions
Warren County, Tennessee Building & Environmental Codes Department 201 Locust Street, Suite 6 McMinnville, TN, 37110 931.474.2633 Frequently Asked Questions What building codes are the Warren County Building
TOWN OF OHIO BUILDING PERMIT APPLICATION
DATE OF APPLICATION APPLICANT'S NAME, ADDRESS OWNER, ADDRESS PHONE:[ ] - PHONE:[ ] - E-MAIL: APPLICANT IS: OWNER [ ] CONTRACTOR [ ] PROJECT LOCATION: ROAD DIRECTIONS TAX MAP # NATURE OF WORK: [CHECK ALL
CHAPTER 2 AGGREGATE TECHNICIAN TRAINING AND QUALIFICATION PROGRAM
CHAPTER 2 AGGREGATE TECHNICIAN TRAINING AND QUALIFICATION PROGRAM 2.1 PURPOSE... 2-1 2.2 BACKGROUND.. 2-1 2.3 QUALIFICATION REQUIREMENTS BY JOB FUNCTION.. 2-1 2.3.1 Aggregate Testing Technician. 2-1 2.3.2
CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1
CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1 1 This Chapter of the FERC Engineering Guidelines has been prepared under contract with R & H Thomas, Inc. JANUARY 1993 Chapter VII Construction
NRMCA Quality Certification. Ready Mixed Concrete Quality Management System. Certification Criteria Document
NRMCA Quality Certification Ready Mixed Concrete Quality Management System Certification Criteria Document Version 1 February 2014 NRMCA Quality Certification Ready Mixed Concrete Quality Management System
Home Safe Home Inspections
Certified Radon Report My Prospective New Home, Northeast Inspection prepared for: Radon Sample Inspection Date: 11/30/2010 Inspector: David Macy ASHI #211547, Radon License #RT462 Phone: 440-740-0068
SECTION 02 8213 ASBESTOS ABATEMENT
PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 specification sections shall apply to work of this section.
NEW JERSEY ADMINISTRATIVE CODE Copyright 2015 by the New Jersey Office of Administrative Law
5:23-5.1 Title; scope; intent NEW JERSEY ADMINISTRATIVE CODE (a) This subchapter of the regulations adopted pursuant to authority of the Uniform Construction Code Act, entitled "Licensing of Code Enforcement
High Strain Dynamic Load Testing of Drilled Shafts
Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain
Acceptance Codes APPENDIX - A. Acceptance Criteria
1111 Receipt of a satisfactory Test Report from WSDOT Materials Laboratory is required indicating the lot (or lots) or batch of material meets the requirement of the specifications under which it is listed.
CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
NIST HANDBOOK 150-5 CHECKLIST CONSTRUCTION MATERIALS TESTING
NIST HANDBOOK 150-5 CHECKLIST CONSTRUCTION MATERIALS TESTING Instructions to the Assessor: This checklist addresses specific accreditation criteria prescribed in NIST Handbook 150-5, Construction Materials
SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront
PART 1 GENERAL 1.01 Work Included SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS System 402 Flush-Glazed Screw Spline Storefront A. Furnish and install aluminum architectural storefront system
ELIGIBILITY CHECKLIST:
As stated in 38-75-485 of the Omnibus Coastal Property Insurance Reform Act of 2007, the South Carolina Hurricane Damage Mitigation ( SC Safe Home ) program is established within the South Carolina Department
Responsibilities of Engineering Surveyors under ISO 9000 in Hong Kong Construction Industry
Responsibilities of Engineering Surveyors under ISO 9000 in Hong Kong Construction Industry Steve Y. W. Lam and Conrad H. W. Tang Department of Land Surveying & Geo-Informatics Hong Kong Polytechnic University,
REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION
RESIDENTIAL: REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION 2 COMPLETE SETS OF PRINTS WITH ENGINEERS STAMP ON FOUNDATION PLAN INCLUDING ELECTRICAL, PLUMBING, ETC. SITE PLAN SHOWING HOUSE LOCATION
Quality Assurance Procedures for Construction and Materials Sampling and Testing 14
Page 1 Quality Assurance Procedures for Construction and Materials Sampling and Testing 14 1. PURPOSE 1.1 To prescribe policies, procedures, and guidelines to assure the quality of materials on all Colorado
STANDARD OPERATING PROCEDURE BUILDING & SITE DEVELOPMENT
STANDARD OPERATING PROCEDURE BUILDING & SITE DEVELOPMENT Number: 340.1 Approval: Yves Khawam Effective Date: November 28, 2005 Subject: Special Inspections Page 1 of 20 1.0 PURPOSE: This document establishes
City of Beacon Building Department
City of Beacon Building Department PLEASE SUBMIT THE FOLLOWING: 1. A complete application signed by the owner. 2. An application for a certificate of Occupancy/Compliance. 3. Completed application processing
FLORIDA PRODUCT APPROVAL
FLORIDA PRODUCT APPROVAL Frequently Asked Questions January 2005 The Florida Product Approval System was implemented on October 1, 2003. Many product manufacturers and building officials are asking questions
SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
SINGLE-FAMILY EARTHQUAKE (SEISMIC) RETROFITS
CITY OF BEAVERTON Community Development Department Building Division 12725 SW Millikan Way / PO Box 4755, Beaverton, OR 97076 Phone: (503) 526-2493 Fax: (503) 526-2550 General Information (503) 526-2222
STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.
STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA October 21, 2011 888.01 General 888.02 Materials 888.03 Concrete Proportioning 888.04
Presented by: Ray Crawford ASQ Design and Construction Division
Certification for Construction Quality Managers Presented by: Ray Crawford ASQ Design and Construction Division TODAYS PRESENTATION Who We Are Quality issues in the industry Targeted uses of BOK Framework
UL Qualified Firestop Contractor Program Requirements April 2012
UL Qualified Firestop Contractor Program Requirements April 2012 For more information, please contact your local UL Field Representative INTRODUCTION: In order for a firestop systems installer/contractor
Chapter 4: Contractor Quality Control
Chapter 4: Contractor Quality Control Seattle District, NWS Last updated: 05FEB14 Chapter 4 Contractor Quality Control 1. GENERAL. Contractor is responsible for quality control and shall establish and
CONSTRUCTION MATERIAL TESTING WWW.AU.SGS.COM/INDUSTRIAL
CONSTRUCTION MATERIAL TESTING WWW.AU.SGS.COM/INDUSTRIAL Introduction For over 20 years, we have offered a full range of materials testing to suit the requirements of local, national and international civil
Document Comparison. AIA Documents A134 2009 and A131CMc 2003
Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections
5.2.7.4 CONCRETE: CONTRACTOR S QUALITY CONTROL PLAN
5.2.7.4 CONCRETE: CONTRACTOR S QUALITY CONTROL PLAN NOTE: This document is generally written in the imperative mood. The subject, "the Contractor" is implied. Also implied in this language are "shall",
INSTRUCTIONS FOR COORDINATION SECTION 06651 SOLID SURFACE FABRICATIONS
INSTRUCTIONS FOR COORDINATION SECTION 06651 SOLID SURFACE FABRICATIONS 1. Paragraph 1.02 Provide solid surface countertops at sinks locations. Provide solid surface window sills at drywall framing walls.
Inspections: Central Laboratory of the Regions
Page 1 Inspections: Central Laboratory of the Regions Protocol for Open Laboratory Review of a CDOT Materials Testing Laboratory Protocol for the Inspection of Region Materials Laboratories by the Central
JOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management
JOHN HART GENERATING STATION REPLACEMENT PROJECT Schedule 9 Quality Management SCHEDULE 9 QUALITY MANAGEMENT TABLE OF CONTENTS 1. QUALITY MANAGEMENT SYSTEM... 1 1.1 Quality Management System...1 1.2 Project
Uncovered Decks & Porches
Uncovered Decks & Porches Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed
Work Type Definition and Submittal Requirements
Work Type: Highway Materials Testing Geotechnical Laboratory Testing, Geotechnical Laboratory Testing, Standard Penetration (SPT) & Rock Coring, Cone Penetration Test, Solid Stem Auger Drilling, and Materials
Adopting Disaster Resilient Construction at the Local Level
Adopting Disaster Resilient Construction at the Local Level Sponsored by The Concrete Joint Sustainability Initiative (CJSI) Presenter Biographies August 2012 Dean Frank, P.E., LEED GA Dean Frank is Director
1 OF 7. there will be few "surprises" as the work progresses.
1 OF 7 FP-G1.94 GUIDELINES FOR SUCCESSFUL SUPERVISION OF SCHOOL DISTRICT CAPITAL CONSTRUCTION PROJECTS There is no doubt that the successful completion of any capital construction project is the result
REQUEST FOR QUALIFICATIONS/PROPOSAL (RFQ/P) FOR A ROOF CONSULTANT
REQUEST FOR QUALIFICATIONS/PROPOSAL (RFQ/P) FOR A ROOF CONSULTANT Durango School District 9 R (Owner) 201 East 12 th Street Durango, Colorado 81301 Phone (970) 247 5411, ext. 1458 PROPOSAL DUE DATE/DELIVERY
Suggested Procedures for School Boards
Suggested Procedures for School Boards The Chronology of a Project: Some of the steps described may not apply to certain types of projects, or might occur concurrently with others. As you confer with the
CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714
CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 BUILDING DIVISION (714) 961-7120 Single Family Residential New Construction, Additions & Alterations Submittal Requirements Required agency approvals
INSTRUCTIONS FOR COMPLETING APPLICATION FOR DWELLING WIND HAIL INSURANCE
INSTRUCTIONS FOR COMPLETING APPLICATION FOR DWELLING WIND HAIL INSURANCE Agent name, license number and signature are required. Insured signature is required (see page 4). Coverage should be placed in
The Florida Building Code
Setting New Standards for Safety The Florida Building Code Florida Building Commission Florida Department of Community Affairs The Florida Building Code System The Florida Building Commission Florida Building
Patio Covers / Carports
Patio Covers / Carports Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed
Home Buyer s. Helpful Information to Find and Finance Your Next Home. www.colonialnationalmortgage.com 1-800-937-6001
Home Buyer s H A N D B O O K Helpful Information to Find and Finance Your Next Home www.colonialnationalmortgage.com 1-800-937-6001 The information herein is subject to change and is not an offer to extend
Chapter 1 Manufacturing Quality Assurance (MQA) and Construction Quality Assurance (CQA) Concepts and Overview
Chapter 1 Manufacturing Quality Assurance (MQA) and Construction Quality Assurance (CQA) Concepts and Overview * 1.1 Introduction As a prelude to description of the detailed components of a waste containment
FREQUENTLY ASKED QUESTIONS: 1) Q: When is a building permit required?
FREQUENTLY ASKED QUESTIONS: These are frequently asked questions. The answers can be used as a guideline. If you are in need of further information, please call the Building Department. 1. When is a building
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.00 10 (February 2010) Change 1-05/15 ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 45 01 (January 2008) UNIFIED FACILITIES
Quality Assurance QUALITY ASSURANCE PLAN
Revision 2 Page 1 of 40 QUALITY ASSURANCE PLAN PLAN APPROVALS: Jeff Shouse Signature on File DIRECTOR OF QUALITY ASSURANCE DIRECTOR OF QUALITY ASSURANCE (signature) DATE Rodney Baltzer Signature on File
QUALITY ASSURANCE PROGRAM (QAP) City Rohnert Park
QUALITY ASSURANCE PROGRAM (QAP) City Rohnert Park The purpose of this program is to provide assurance that the materials incorporated into the construction projects are in conformance with the contract
INFORMATION BULLETIN NO.
Requirements for Plans Review Submittal, One- and Two-Family Dwellings INFORMATION BULLETIN NO. 100 (June 26, 1998, Revised March 26, 2009) City Planning & Development - Development Services City of Kansas
ACCREDITED FIRESTOP SPECIALTY CONTRACTOR PROGRAM
ACCREDITED FIRESTOP SPECIALTY CONTRACTOR PROGRAM Hilti Accredited Firestop Specialty Contractor Accreditation Guide Table of Contents 1.0 HAFSC Contractor Program Guidelines 1.1 Introduction 1.2 Accreditation
CHAPTER BUILDING CODE EFFECTIVENESS GRADING SCHEDULE: MEASURING THE COMMUNITY S COMMITMENT TO ADOPTING AND ENFORCING BUILDING CODES.
CHAPTER 11 BUILDING CODE EFFECTIVENESS GRADING SCHEDULE: MEASURING THE COMMUNITY S COMMITMENT TO ADOPTING AND ENFORCING BUILDING CODES Dennis Gage Natural Hazards Mitigation Division Insurance Services
S E E - B E R U F S G E N O S S E N S C H A F T
S E E - B E R U F S G E N O S S E N S C H A F T E M D E N B R E M E N B R E M E R H A V E N H A M B U R G K I E L W I S M A R R O S T O C K S T R A L S U N D SCHIFFSSICHERHEITSABTEILUNG International Safety
Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training
Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline
The quality and uniformity of ready mixed concrete
The New NRMCA Quality Certification Program Why should companies have a quality management system? by Karthik H. Obla and Colin L. Lobo The quality and uniformity of ready mixed concrete delivered to a
[BARLINES MANUAL OF STANDARD PRACTICE (PHILS)] Chapter One METRIC (SI), PNS BAR SIZES STANDARDS AND OTHER CRITERION
Chapter One METRIC (SI), PNS BAR SIZES STANDARDS AND OTHER CRITERION By Amadeus (Mady) Magpile, President and CEO INTRODUCTION This is first in a series of articles outlining the Manual of Standard Practice,