UNIFIED FACILITIES GUIDE SPECIFICATIONS
|
|
|
- Cuthbert Stewart
- 9 years ago
- Views:
Transcription
1 USACE / NAVFAC / AFCEC / NASA UFGS (February 2010) Change 1-05/ Preparing Activity: USACE Superseding UFGS (January 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated July 2016 SECTION TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS SECTION QUALITY CONTROL 02/10 PART 1 GENERAL 1.1 REFERENCES 1.2 PAYMENT 1.3 SUBMITTALS PART 2 PRODUCTS PART 3 EXECUTION 3.1 GENERAL REQUIREMENTS 3.2 CONTRACTOR QUALITY CONTROL (CQC) PLAN Content of the CQC Plan Additional Requirements for Design Quality Control (DQC) Plan Acceptance of Plan Notification of Changes 3.3 COORDINATION MEETING 3.4 QUALITY CONTROL ORGANIZATION Personnel Requirements CQC System Manager CQC Personnel Additional Requirement Organizational Changes 3.5 SUBMITTALS AND DELIVERABLES 3.6 CONTROL Preparatory Phase Initial Phase Follow-up Phase Additional Preparatory and Initial Phases 3.7 TESTS Testing Procedure Testing Laboratories Capability Check Capability Recheck SECTION Page 1
2 3.7.3 Onsite Laboratory 3.8 COMPLETION INSPECTION Punch-Out Inspection Pre-Final Inspection Final Acceptance Inspection 3.9 DOCUMENTATION 3.10 SAMPLE FORMS 3.11 NOTIFICATION OF NONCOMPLIANCE ATTACHMENTS: Sample forms -- End of Section Table of Contents -- SECTION Page 2
3 USACE / NAVFAC / AFCEC / NASA UFGS (February 2010) Change 1-05/ Preparing Activity: USACE Superseding UFGS (January 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated July 2016 SECTION QUALITY CONTROL 02/10 NOTE: This guide specification covers requirements for Contractor Quality Control for construction projects or design-build construction projects. This section can be used for both design-build and design-bid-build projects. Adhere to UFC Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information. Remove information and requirements not required in respective project, whether or not brackets are present. Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR). PART 1 GENERAL 1.1 REFERENCES NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title. Use the Reference Wizard's Check Reference feature when you add a Reference Identifier (RID) outside of the Section's Reference Article to automatically SECTION Page 3
4 place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates. References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process. The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. ASTM INTERNATIONAL (ASTM) ASTM D3740 ASTM E329 (2012a) Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction (2014a) Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction U.S. ARMY CORPS OF ENGINEERS (USACE) ER (2006; Change 1) Engineering and Design -- Quality Management 1.2 PAYMENT NOTE: Select the first bracketed option for invitation for bid (IFB) solicitation, and select the second bracketed option for request for proposal (RFP) solicitation. Separate payment will not be made for providing and maintaining an effective Quality Control program. Include all associated costs in the applicable [Bid] [Pricing] Schedule item. 1.3 SUBMITTALS NOTE: Review submittal description (SD) definitions in Section SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G." Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a G to an item, if the submittal is sufficiently important or complex in context of SECTION Page 4
5 the project. For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects. Use the "S" classification only in SD-11 Closeout Submittals. The "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section SUSTAINABILITY REPORTING. Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for [Contractor Quality Control approval.] [information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section SUSTAINABILITY REPORTING. Submit the following in accordance with Section SUBMITTAL PROCEDURES: SD-01 Preconstruction Submittals Contractor Quality Control (CQC) Plan; G[, [ ]] Additional Requirements for Design Quality Control (DQC) Plan; G, DO SD-05 Design Data Discipline-Specific Checklists SD-06 Test Reports Verification Statement PART 2 PRODUCTS Not Used SECTION Page 5
6 PART 3 EXECUTION 3.1 GENERAL REQUIREMENTS NOTE: Selection of design-build construction text required. Establish and maintain an effective quality control (QC) system that complies with the Contract Clause titled "Inspection of Construction." QC consist of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. The QC system covers all construction design and construction operations, both onsite and offsite, and be keyed to the proposed construction design and construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. In this context the highest level manager responsible for the overall construction activities at the site, including quality and production is the project superintendent. The project superintendent maintains a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer. 3.2 CONTRACTOR QUALITY CONTROL (CQC) PLAN NOTE: Selection of design-build construction text required. Submit no later than [15] [30] [ ] days after receipt of notice to proceed, the Contractor Quality Control (CQC) Plan proposed to implement the requirements of the Contract Clause titled "Inspection of Construction." The Government will consider an interim plan for the first [ ] days of operation. ConstructionDesign and construction will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional work Content of the CQC Plan Include, as a minimum, the following to cover all design and construction construction operations, both onsite and offsite, including work by subcontractors, fabricators, suppliers, and purchasing agents subcontractors designers of record, consultants, architect/engineers (AE), fabricators, suppliers and purchasing agents: a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff will implement the three phase control system for all aspects of the work specified. Include a CQC System Manager that reports to the project superintendent. b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function. SECTION Page 6
7 c. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager. Furnish copies of these letters to the Contracting Officer. d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents subcontractors, designers of record, consultants, architect engineers (AE), offsite fabricators, suppliers, and purchasing agents,. These procedures must be in accordance with Section SUBMITTAL PROCEDURES. e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities approved by the Contracting Officer are required to be used.) f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation. g. Procedures for tracking constructiondesign and construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected. h. Reporting procedures, including proposed reporting formats. i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and is identified by different trades or disciplines, or it is work by the same trade in a different environment. Although each section of the specifications can generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. This list will be agreed upon during the coordination meeting. j. Coordinate scheduled work with Special Inspections required by Section SPECIAL INSPECTIONS, the Statement of Special Inspections and the Schedule of Special Inspections. Where the applicable Code issue by the Internation Code Council (ICC) calls for inspections by the Building Official, the Contractor will include the inspections in the Contractor Quality Control Plan and will perform the inspections required by the applicable ICC. The Contractor will perform these inspections using independent qualified inspectors. Include the Special Inspection Plan requirements in the CQC Plan Additional Requirements for Design Quality Control (DQC) Plan NOTE: Use this paragraph only for design-build projects. SECTION Page 7
8 The following additional requirements apply to the Design Quality Control (DQC) plan: a. Submit and maintain a Design Quality Control (DQC) Plan as an effective quality control program which assures that all services required by this contract are performed and provided in a manner that meets professional architectural and engineering quality standards. As a minimum, all documents must be technically reviewed by competent, independent reviewers identified in the DQC Plan. The same element that produced the product may not perform the independent technical review (ITR). Correct errors and deficiencies in the design documents prior to submitting them to the Government. b. Include the design schedule in the master project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period. This should be at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work. Include review and correction periods associated with each item. This should be a forward planning as well as a project monitoring tool. The schedule reflects calendar days and not dates for each activity. If the schedule is changed, submit a revised schedule reflecting the change within 7 calendar days. Include in the DQC Plan the discipline-specific checklists to be used during the design and quality control of each submittal. Submit at each design phase as part of the project documentation these completed discipline-specific checklists. ER provides some useful information in developing checklists. c. Implement the DQC Plan by a Design Quality Control Manager who has the responsibility of being cognizant of and assuring that all documents on the project have been coordinated. This individual must be a person who has verifiable engineering or architectural design experience and is a registered professional engineer or architect. Notify the Contracting Officer, in writing, of the name of the individual, and the name of an alternate person assigned to the position. The Contracting Officer will notify the Contractor in writing of the acceptance of the DQC Plan. After acceptance, any changes proposed by the Contractor are subject to the acceptance of the Contracting Officer Acceptance of Plan Acceptance of the Contractor's plan is required prior to the start of cons truction design and construction. Acceptance is conditional and will be predicated on satisfactory performance during theconstruction design andconstruction. The Government reserves the right to require the Contractor to make changes in the Constractor Quality Control(CQC) Plan and operations including removal of personnel, as necessary, to obtain the quality specified Notification of Changes After acceptance of the CQC Plan, notify the Contracting Officer in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer. SECTION Page 8
9 3.3 COORDINATION MEETING NOTE: Selection of design-build construction text required. The post award conference is conducted by the Government as soon as possible after Contract award, coordinated with issuance of the notice to proceed (NTP). Participation by the Contractor and major subcontractor representatives is mandatory. After the Preconstruction Conference, before start of construction, Postaward Conference, before start of design or construction, and prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer and discuss the Contractor's quality control system. Submit the CQC Plan a minimum of [ ] calendar days prior to the Coordination Meeting. During the meeting, a mutual understanding of the system details must be developed, including the forms for recording the CQC operations operations, design activities, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the Government, signed by both the Contractor and the Contracting Officer and will become a part of the contract file. There can be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the CQC system or procedures which can require corrective action by the Contractor. 3.4 QUALITY CONTROL ORGANIZATION NOTE: Selection of design-build construction text required Personnel Requirements The requirements for the CQC organization are a Safety and Health Manager, CQC System Manager, CQC System Manager, a Design Quality Manager, and sufficient number of additional qualified personnel to ensure safety and contract compliance. The Safety and Health Manager reports directly to a senior project (or corporate) official independent from the CQC System Manager. The Safety and Health Manager will also serve as a member of the CQC Staff Personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly will also be included as part of the CQC organization. The Contractor's CQC staff maintains a presence at the site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure contract compliance. The CQC staff will be subject to acceptance by the Contracting Officer. Provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional CQC organization. Promptly complete and furnish all letters, material submittals, shop drawing submittals, schedules and all other project documentation to the CQC organization. The CQC organization is responsible to maintain these documents and records at the site at all times, except as otherwise acceptable to the Contracting Officer. SECTION Page 9
10 3.4.2 CQC System Manager NOTE: The designer should insert desired requirements, evaluate the project to determine the level of CQC System Manager required, and select options accordingly. Identify as CQC System Manager an individual within the onsite work organization that is responsible for overall management of CQC and has the authority to act in all CQC matters for the Contractor. The CQC System Manager is required to be [a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of [ ] years construction experience on construction similar to this contract.] [a construction person with a minimum of [ ] years in related work.] This CQC System Manager is on the site at all times during construction and is employed by the prime Contractor. The CQC System Manager is [assigned no other duties] [assigned as CQC System Manager but can have duties as project superintendent in addition to quality control]. Identify in the plan an alternate to serve in the event of the CQC System Manager's absence. The requirements for the alternate are the same as the CQC System Manager CQC Personnel NOTE: Insert desired requirements if the complexity, or size of the project warrants specialized individuals in specific disciplines to perform quality control. TAB personnel must be specified when the contract specifications contain Section TESTING, ADJUSTING, AND BALANCING OF HVAC SYSTEMS. Select options accordingly. In addition to CQC personnel specified elsewhere in the contract, provide as part of the CQC organization specialized personnel to assist the CQC System Manager for the following areas: [electrical,] [mechanical,] [civil,] [structural,] [environmental,] [architectural,] [materials technician,] [submittals clerk,] [Cx Agent/LEED Specialist,] [occupied family housing coordinator]. These individuals or specialized technical companies [are directly employed by the prime Contractor and can not be employed by a supplier or subcontractor on this project] [are employees of the prime or subcontractor]; be responsible to the CQC System Manager; be physically present at the construction site during work on the specialized peronnel's areas of responsibility; have the necessary education and/or experience in accordance with the experience matrix listed herein. These individuals [ have no other duties other than quality control] [can perform other duties but need to be allowed sufficient time to perform their assigned quality control duties as described in the Quality Control Plan]. [A single person can cover more than one area provided that the single person is qualified to perform quality control activities in each designated and that workload allows.] SECTION Page 10
11 Experience Matrix Area Civil Qualifications Graduate Civil Engineer or Construction Manager with 2 years experience in the type of work being performed on this project or technician with 5 yrs related experience Mechanical Graduate Mechanical Engineer with 2 yrs experience or person with 5 years of experience supervising mechanical features of work in the field with a construction company Electrical Graduate Electrical Engineer with 2 years related experience or person 5 years of experience supervising electrical features of work in the field with a construction company Structural Graduate Civil Engineer (with Structural Track or Focus) or Construction Manager with 2 years experience or person 5 years of experience supervising structural features of work in the field with a construction company Architectural Graduate Architect with 2 years experience or person with 5 years related experience Environmental Graduate Environmental Engineer with 3 years experience Submittals Occupied Family Housing Submittal Clerk with 1 year experience Person, customer relations type, coordinator experience Concrete, Pavements and Soils Materials Technician with 2 years experience for the appropriate area Testing, Adjusting and Balancing (TAB) Personnel Specialist must be a member of AABC or an experienced technician of the firm certified by the NEBB Design Quality Control Manager Registered Architect or Professional Engineer SECTION Page 11
12 3.4.4 Additional Requirement In addition to the above experience and education requirements, the Contractor Quality Control(CQC) System Manager and Alternate CQC System Managerare required to have completed the Construction Quality Management (CQM) for Contractors course. If the CQC System Manager does not have a current certification, obtain the CQM for Contractors course certification within 90 days of award. This course is periodically offered by the Naval Facilities Engineering Command and the Army Corps of Engineers. Contact the Contracting Officer for information on the next scheduled class. The Construction Quality Management Training certificate expires after 5 years. If the CQC System Manager's certificate has expired, retake the course to remain current Organizational Changes Maintain the CQC staff at full strength at all times. When it is necessary to make changes to the CQC staff, revise the CQC Plan to reflect the changes and submit the changes to the Contracting Officer for acceptance. 3.5 SUBMITTALS AND DELIVERABLES Submittals, if needed, have to comply with the requirements in Section SUBMITTAL PROCEDURES. The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the contract requirements. When Section TOTAL BUILDING COMMISSIONING are included in the contract, the submittals required by those sections have to be coordinated with Section SUBMITTAL PROCEDURES to ensure adequate time is allowed for each type of submittal required. 3.6 CONTROL Contractor Quality Control (CQC)is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control are required to be conducted by the CQC System Manager for each definable feature of the construction work as follows: Preparatory Phase This phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes: a. A review of each paragraph of applicable specifications, reference codes, and standards. Make available during the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field. Maintain and make available in the field for use by Government personnel until final acceptance of the work. b. Review of the contract drawings. c. Check to assure that all materials and/or equipment have been tested, submitted, and approved. d. Review of provisions that have been made to provide required control SECTION Page 12
13 inspection and testing. [ e. Review Special Inspections required by Section SPECIAL INSPECTIONS, the Statement of Special Inspections and the Schedule of Special Inspections. ] [e][f]. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract. [f][g]. Examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored. [g][h]. Review of the appropriate activity hazard analysis to assure safety requirements are met. [h][i]. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work. [i][j]. Check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer. [j][k]. Discussion of the initial control phase. [k][l]. The Government need to be notified at least [ ] hours in advance of beginning the preparatory control phase. Include a meeting conducted by the CQC System Manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the definable feature. Document the results of the preparatory phase actions by separate minutes prepared by the CQC System Manager and attach to the daily CQC report. Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications Initial Phase This phase is accomplished at the beginning of a definable feature of work. Accomplish the following: a. Check work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting. b. Verify adequacy of controls to ensure full contract compliance. Verify required control inspection and testing are in conpliance with the contract. c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate. d. Resolve all differences. e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker. f. The Government need to be notified at least [ ] hours in advance of SECTION Page 13
14 beginning the initial phase for definable feature of work. Prepare separate minutes of this phase by the CQC System Manager and attach to the daily CQC report. Indicate the exact location of initial phase for definable feature of work for future reference and comparison with follow-up phases. g. The initial phase for each definable feature of work is repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met. [ h. Coordinate scheduled work with Special Inspections required by Section SPECIAL INSPECTIONS, the Statement of Special Inspections and the Schedule of Special Inspections. ]3.6.3 Follow-up Phase Perform daily checks to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. Record the checks in the CQC documentation. Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work. [Coordinate scheduled work with Special Inspections required by Section SPECIAL INSPECTIONS, the Statement of Special Inspections and the Schedule of Special Inspections.] Additional Preparatory and Initial Phases Conduct additional preparatory and initial phases on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable CQC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop. 3.7 TESTS Testing Procedure Perform specified or required tests to verify that control measures are adequate to provide a product which conforms to contract requirements. Upon request, furnish to the Government duplicate samples of test specimens for possible testing by the Government. Testing includes operation and/or acceptance tests when specified. Procure the services of a Corps of Engineers approved testing laboratory or establish an approved testing laboratory at the project site. Perform the following activities and record and provide the following data: a. Verify that testing procedures comply with contract requirements. b. Verify that facilities and testing equipment are available and comply with testing standards. c. Check test instrument calibration data against certified standards. d. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared. e. Record results of all tests taken, both passing and failing on the CQC SECTION Page 14
15 report for the date taken. Specification paragraph reference, location where tests were taken, and the sequential control number identifying the test. If approved by the Contracting Officer, actual test reports are submitted later with a reference to the test number and date taken. Provide an information copy of tests performed by an offsite or commercial test facility directly to the Contracting Officer. Failure to submit timely test reports as stated results in nonpayment for related work performed and disapproval of the test facility for this contract Testing Laboratories All testing laboratories must be validated by the USACE Material Testing Center (MTC) for the tests to be performed. Information on the USACE MTC with web-links to both a list of validated testing laboratories and for the laboratory inspection request for can be found at: Capability Check The Government reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician's testing procedures and techniques. Laboratories utilized for testing soils, concrete, asphalt, and steel is required to meet criteria detailed in ASTM D3740 and ASTM E Capability Recheck If the selected laboratory fails the capability check, the Contractor will be assessed a charge of [ ] to reimburse the Government for each succeeding recheck of the laboratory or the checking of a subsequently selected laboratory. Such costs will be deducted from the contract amount due the Contractor Onsite Laboratory The Government reserves the right to utilize the Contractor's control testing laboratory and equipment to make assurance tests, and to check the Contractor's testing procedures, techniques, and test results at no additional cost to the Government. 3.8 COMPLETION INSPECTION Punch-Out Inspection Conduct an inspection of the work by the CQC System Manager near the end of the work, or any increment of the work established by a time stated in the SPECIAL CONTRACT REQUIREMENTS Clause, "Commencement, Prosecution, and Completion of Work", or by the specifications. Prepare and include in the CQC documentation a punch list of items which do not conform to the approved drawings and specifications, as required by paragraph DOCUMENTATION. Include within the list of deficiencies the estimated date by which the deficiencies will be corrected. Make a second inspection the CQC System Manager or staff to ascertain that all deficiencies have been corrected. Once this is accomplished, notify the Government that the facility is ready for the Government Pre-Final inspection. SECTION Page 15
16 3.8.2 Pre-Final Inspection The Government will perform the pre-final inspection to verify that the facility is complete and ready to be occupied. A Government Pre-Final Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection with the customer can be scheduled. Correct any items noted on the Pre-Final inspection in a timely manner. These inspections and any deficiency corrections required by this paragraph need to be accomplished within the time slated for completion of the entire work or any particular increment of the work if the project is divided into increments by separate completion dates Final Acceptance Inspection The Contractor's Quality Control Inspection personnel, plus the superintendent or other primary management person, and the Contracting Officer's Representativeis required to be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from Base/Post Civil Facility Engineer user groups, and major commands can also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notify the Contracting Officer at least 14 days prior to the final acceptance inspection and include the Contractor's assurance that all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the contract, will be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with the contract clause titled "Inspection of Construction". 3.9 DOCUMENTATION Maintain current records providing factual evidence that required quality control activities and/or tests have been performed. Include in these records the work of subcontractors and suppliers on an acceptable form that includes, as a minimum, the following information: a. The name and area of responsibility of the Contractor/Subcontractor. b. Operating plant/equipment with hours worked, idle, or down for repair. c. Work performed each day, giving location, description, and by whom. When Network Analysis (NAS) is used, identify each phase of work performed each day by NAS activity number. d. Test and/or control activities performed with results and references to specifications/drawings requirements. Identify the control phase (Preparatory, Initial, Follow-up). List of deficiencies noted, along with corrective action. e. Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements. f. Submittals and deliverables reviewed, with contract reference, by whom, and action taken. SECTION Page 16
17 g. Offsite surveillance activities, including actions taken. h. Job safety evaluations stating what was checked, results, and instructions or corrective actions. i. Instructions given/received and conflicts in plans and/or specifications. j. Provide documentation of design quality control activities. For independent design reviews, provide, as a minimum, identification of the Independent Technical Review (ITR) team, the ITR review comments, responses and the record of resolution of the comments. k. Verification Statement. Indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. Cover both conforming and deficient features and include a statement that equipment and materials incorporated in the work and workmanship comply with the contract. Furnish the original and one copy of these records in report form to the Government daily within [ ] hours after the date covered by the report, except that reports need not be submitted for days on which no work is performed. As a minimum, prepare and submit one report for every 7 days of no work and on the last day of a no work period. All calendar days need to be accounted for throughout the life of the contract. The first report following a day of no work will be for that day only. Reports need to be signed and dated by the Contractor Quality Control(CQC) System Manager. Include copies of test reports and copies of reports prepared by all subordinate quality control personnel within the CQC System Manager Report SAMPLE FORMS NOTE: List enclosed forms. Sample forms are not a part of this guide specification and should be provided by the specifier. Sample forms enclosed at the end of this section NOTIFICATION OF NONCOMPLIANCE The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, will be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer can issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time or for excess costs or damages by the Contractor. -- End of Section -- SECTION Page 17
Chapter 4: Contractor Quality Control
Chapter 4: Contractor Quality Control Seattle District, NWS Last updated: 05FEB14 Chapter 4 Contractor Quality Control 1. GENERAL. Contractor is responsible for quality control and shall establish and
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 30 00 (August 2015) ----------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 30 00 (November 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
Module 6: QUALITY MANAGEMENT FOR CONSTRUCTION PROJECTS. Submodule 1: Introduction. Objectives: After completing this submodule, you will be able to:
Module 6: QUALITY MANAGEMENT FOR CONSTRUCTION PROJECTS Submodule 1: Introduction Objectives: After completing this submodule, you will be able to: Define the function and importance of Construction Quality
USACE NAVFAC Sample QA/QC Plan 20 selected pages (out of )
USACE NAVFAC Sample QA/QC Plan 20 selected pages (out of ) Part 1: Project Specific Quality Plan Part 2: Quality Manual Part 3: Submittal Forms Contact: First Time Quality 410 451 8006 Pat [Pick the date]
Section 100 Contractor Quality Control Program
7/21/2014 AC 150/5370-10G Section 100 Contractor Quality Control Program 100-01 General. When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and
UFGS-28 33 00.00 40 (February 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-28 33 00.00 40 (February 2014) ----------------------------------- Preparing Activity: NASA Superseding UFGS-28 33 00.00 40 (February 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (August 2008) --------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (July 2007) UNIFIED FACILITIES GUIDE SPECIFICATIONS
UFGS-02362 (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-31 31 16.20 (April 2006) Change 2-11/14 ----------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-02362 (August 2004) UNIFIED FACILITIES
UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS
USACE / NAVFAC / AFCEC / NASA UFGS-01 32 16.00 20 (February 2015) Change 2-11/15 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 32 16.00 20 (November 2009) UNIFIED FACILITIES
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-28 20 02 (November 2008) ----------------------------- Preparing Activity: USACE Superseding UFGS-13729 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
CONSTRUCTION QUALITY MANAGEMENT FOR CONTRACTORS. Student Study Guide
Control #784 Revised 2004 CONSTRUCTION QUALITY MANAGEMENT FOR CONTRACTORS Student Study Guide Produced By: U.S. Army Corps of Engineers Professional Development Support Center and U.S. Naval Facilities
Module 1: INTRODUCTION. Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION"
Module 1: INTRODUCTION Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION" Objectives: After completing this submodule, you will be able to: State
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes
UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.10 10 (February 2010) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 45 01.10 (January 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS
CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES
1.0 SCOPE CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES This document establishes the minimum quality program requirements for a contractor providing equipment, material, and construction
VDOT GOVERNANCE DOCUMENT
VDOT GOVERNANCE DOCUMENT Minimum Requirements for Quality Assurance and Quality Control on Design Build and Public-Private Transportation Act Projects Location and Design Division Alternate Project Delivery
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (February 2015) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (August 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS
ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan)
ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal Forms Part 4:
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-31 31 16.13 (November 2014) -------------------------------- Preparing Activity: USACE Superseding UFGS-31 31 16 (August 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-31 31 16.19 (February 2016) -------------------------------- Preparing Activity: NAVFAC Superseding UFGS 31 31 16.19 (August 2014) UFGS 31 31 16.20 (April 2006) UFGS
ACG Commissioning Guideline
ACG Commissioning Guideline Appendix A Sample Commissioning Specification NOTES TO APPENDIX A This appendix contains a sample Request for Proposal (RFP) for Commissioning Services as would be issued by
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-02 81 00 (February 2010) ----------------------------- Preparing Activity: USACE Superseding UFGS-02 81 00 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
Request for Proposal No. RFP02658. Project Construction Management Services. for. Capital Levy BTA IV Project: Ingraham High School Classroom Addition
Seattle Public Schools Contracting Services 2445 Third Avenue South Seattle, WA 98134 Telephone: (206) 252-0566 Fax: (206) 743-3018 [email protected] Request for Proposal No. RFP02658
Final Construction Quality Control Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut
Final Construction Quality Control Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut Revision 0 Prepared for: Olin Corporation Cleveland, Tennessee Prepared by: Sevenson Environmental
CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1
CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1 1 This Chapter of the FERC Engineering Guidelines has been prepared under contract with R & H Thomas, Inc. JANUARY 1993 Chapter VII Construction
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-27 05 14.00 10 (April 2006) -------------------------------- Preparing Activity: USACE Superseding UFGS-27 05 14.00 10 (April 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS
Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive
Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC /NASA UFGS-01 33 29 (February 2015) Change 1-11/15 ----------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 33 29 November 2014 UNIFIED FACILITIES GUIDE SPECIFICATIONS
Layton Construction Co., Inc. Quality Management Manual
Layton Construction Co., Inc QUALITY MANAGEMENT PLAN 1 Layton Construction Co., Inc. Quality Management Manual [ 2015 ] PHOENIX PHOENIX BOISE BOISE IRVINE IRVINE SALT LAKE CITY SALT ORLANDO LAKE CITY HAWAII
LETTER OF TRANSMITTAL
LETTER OF TRANSMITTAL Submittal No.:019A TO: Marlene Gaeta, Senior Engineer Construction Management Consolidated Edison Company of New York, Inc. 31-01 20 th Avenue, Building 136 2 nd Floor Astoria, New
ACIL POSITION PAPER PROCUREMENT AND EFFECTIVE PRACTICE OF CONSTRUCTION MATERIALS ENGINEERING AND TESTING SERVICES
Enhancing Public Health and Safety Through Quality Testing and Engineering ACIL POSITION PAPER PROCUREMENT AND EFFECTIVE PRACTICE OF CONSTRUCTION MATERIALS ENGINEERING AND TESTING SERVICES Construction
UFGS-16261 (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-26 29 23 (April 2006) -------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-16261 (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS
Module 5: SUBMITTALS. Objectives: After completing this module, you will be able to:
Module 5: SUBMITTALS Objectives: After completing this module, you will be able to: State the purpose of submittal procedures. Describe Government responsibilities for submittal review and/or approval.
Appendix A Contractor Quality Control Plan The Contractor Quality Control Plan is the Contractor s management plan for executing the contract.
Appendix A Contractor Quality Control Plan The Contractor Quality Control Plan is the Contractor s management plan for executing the contract. The Contractor QCP describes the way in which the Contractor
ENGINEERING AND CONSTRUCTION BULLETIN
ENGINEERING AND CONSTRUCTION BULLETIN No. 2014-13 Issuing Office: CECW-CE Issued: 22 May 2014 Expires: 22 May 2016 Subject: Contractor Performance Assessment Reporting System (CPARS) Transition Guidance
San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM
ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM 903.1 DESCRIPTION: This item shall govern the preparation and implementation of the Contractor s Construction Quality Control/Quality Assurance (QC/QA) Program for
BASE CONSTRUCTION INC
BASE CONSTRUCTION INC 14252 CULVER DRIVE A-630 IRVINE,CA 92604-0326 OFFICE:949 387-3471 Shop 714 994 9563 CELL:949 735-5292 FAX:949 786-8753 QUALITY ASSURANCE and QUALITY CONTROL MANUAL 1 TABLE OF CONTENTS
Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS
Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS 8.1.1 PURPOSE This procedure provides guidelines related to the implementation of quality control and quality assurance
STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment)
State License #CGC048773 STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment) This Agreement is made this day of, 200, by and
GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES
GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Greenburgh Central School District No. 7 ( The District ) invites proposals to perform construction management
Airport Safety and Construction Management Under The FAA
U.S. Department of Transportation Federal Aviation Administration Advisory Circular Subject: Quality Management for Federally Funded Airport Construction Projects Date: DRAFT Initiated by: AAS-100 AC No.:
INDIANA DEPARTMENT OF TRANSPORTATION QUALIFIED LABORATORY AND TECHNICIAN PROGRAM
1/1/13 INDIANA DEPARTMENT OF TRANSPORTATION QUALIFIED LABORATORY AND TECHNICIAN PROGRAM The purpose of the Qualified Laboratory and Technician Program is to establish policies, procedures, and guidelines
Building Commissioning 17900-1
SECTION 17900 BUILDING COMMISSIONING PART 1 - GENERAL 1.01 WORK DESCRIPTION: A. General: 1. The Commissioning process is a joint team effort to ensure that all mechanical equipment, controls, and systems
The Role of Construction Managers. FIDIC offers two contributions on the question of the role of a construction manager in a construction contract:
The Role of Construction Managers FIDIC offers two contributions on the question of the role of a construction manager in a construction contract: A. Notes on the use of FIDIC in the Middle East B. A Communication
Contractor s Quality Program Manual
Contractor s Quality Program Manual March 2015 ILLINOIS STATE TOLL HIGHWAY AUTHORITY The CONTRACTOR S QUALITY PROGRAM MANUAL dated March 2015 replaces the previous version dated March 2014. Major Highlight
Document Comparison. AIA Documents A134 2009 and A131CMc 2003
Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections
Attachment 5 Electrical Engineering
A. Phase 1, Preliminary Design: The CONSULTANT shall: Attachment 5 Electrical Engineering 1. Ascertain the requirements for each project through a meeting with the Capital Projects Division Manager or
Quality Assurance QUALITY ASSURANCE PLAN
Revision 2 Page 1 of 40 QUALITY ASSURANCE PLAN PLAN APPROVALS: Jeff Shouse Signature on File DIRECTOR OF QUALITY ASSURANCE DIRECTOR OF QUALITY ASSURANCE (signature) DATE Rodney Baltzer Signature on File
ACCEPTANCE CRITERIA FOR QUALITY DOCUMENTATION (AC10) June 2014
ACCEPTANCE CRITERIA FOR QUALITY DOCUMENTATION (AC10) 1.0 INTRODUCTION June 2014 1.1 Purpose: The purpose of this acceptance criteria is to establish requirements for information that is provided to ICC-ES
SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE
Community Development Permit Services SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE PROJECT NAME PROJECT ADDRESS PERMIT NUMBER CITY RECEIVED STAMP AND INITIALS Instructions: BEFORE
DAIMLER GROUP NORTH AMERICAN COMPANIES
DAIMLER GROUP NORTH AMERICAN COMPANIES General Purchasing Conditions for IT Part H Individual Software Development, Maintenance and Customization 1 Subject Matter / Scope of Performance 1.1 General The
REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER
RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February
JOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management
JOHN HART GENERATING STATION REPLACEMENT PROJECT Schedule 9 Quality Management SCHEDULE 9 QUALITY MANAGEMENT TABLE OF CONTENTS 1. QUALITY MANAGEMENT SYSTEM... 1 1.1 Quality Management System...1 1.2 Project
UNCONTROLLED COPY FOR REFERENCE ONLY
CLOVER MACHINE AND MFG. 800 MATHEW ST. #101 SANTA CLARA, CA 95050 727-3380 727-7015 fax REVISION: DATE: PAGE 1 OF 45 QUALITY POLICY MANUAL DISTRIBUTION LIST: President Purchasing Manager Vice President
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
UNIFIED FACILITIES CRITERIA (UFC) DESIGN BUILD TECHNICAL REQUIREMENTS
UFC 1-300-07A 1 March 2005 UNIFIED FACILITIES CRITERIA (UFC) DESIGN BUILD TECHNICAL REQUIREMENTS APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED UFC 1-300-07A 1 March 2005 UNIFIED FACILITIES CRITERIA
Alexandria National Cemetery SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULE
SECTION 01 32 16.13 PART 1 - GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Microsoft Project 2003 (or latest version) Bar Chart schedule demonstrating fulfillment of the contract requirements.
REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office
REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield
SCT AND MCAS MIRAMAR FOTS SOUTHERN CALIFORNIA TRACON
1-5 CONSTRUCTION SCHEDULES 1-5.1 General, Network Analysis System (NAS).- 1-5.1.1 Applicable documents.- The Publication listed below forms a part of this specification and is applicable to the extent
AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR
DB-BIM Contract No. 5890 07/14 Project No. 02-3210 AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND EVOLVE INFRASTRUCTURE SOLUTIONS, LLC, DESIGN-BUILD CONTRACTOR 1 DB-BIM Contract
CREOL EXPANSION PHASE II UCF-581 Architect/Engineer (A/E) and Construction Manager (CM) Project Fact Sheet
CREOL EXPANSION PHASE II UCF-581 Architect/Engineer (A/E) and Construction Manager (CM) Project Fact Sheet PROJECT DESCRIPTION The project consists of the design and construction of an expansion to the
INTERNAL CLAIMS AUDITOR
6650 INTERNAL CLAIMS AUDITOR The Internal Claims Auditor is an integral part of a properly designed system of internal controls. The position was created to carry out the important Board responsibility
AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder
AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder AGREEMENT made as of the day of in the year of (In words, indicate day, month and year) BETWEEN the Owner: (Name,
Mandatory Addendum to the Owner/Architect Contract For Projects Funded in Whole or in Part with State Capital Outlay Funds
Page 1 of 5 Mandatory Addendum to the Owner/Architect Contract For Projects Funded in Whole or in Part with State Capital Outlay Funds The Owner may use any form of agreement mutually agreed upon by the
QUALITY MANAGEMENT SYSTEM REVIEW AND APPROVAL TEMPLATE (DOE G 414.1-2A, Appendix A, 6-17-05)
QUALITY MANAGEMENT SYSTEM REVIEW AND APPROVAL TEMPLATE (DOE G 414.1-2A, Appendix A, 6-17-05) This review template is intended for use by the DOE for evaluating a DOE Site Office or Contractor Quality Assurance
DEPARTMENT OF THE ARMY U.S. Army Corps of Engineers Washington, DC 20314-1000. Construction CONTRACTOR SUBMITTAL PROCEDURES TABLE-OF CONTENTS
CECW-CE Regulation No. 415-1-10 Paragraph DEPARTMENT OF THE ARMY U.S. Army Corps of Engineers Washington, DC 20314-1000 Construction CONTRACTOR SUBMITTAL PROCEDURES TABLE-OF CONTENTS ER 415-1-10 30 April2012
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES A. General Information Part I: Qualifications Information The Tacoma School District is soliciting Qualifications for onsite
Construction Management Program
Use and Limitation: The Sponsor may use this document as a guide in preparing a construction management program for their specific project. Sponsors and Consultants are cautioned that the provision of
1 OF 7. there will be few "surprises" as the work progresses.
1 OF 7 FP-G1.94 GUIDELINES FOR SUCCESSFUL SUPERVISION OF SCHOOL DISTRICT CAPITAL CONSTRUCTION PROJECTS There is no doubt that the successful completion of any capital construction project is the result
Module 8: QUALITY CONTROL SYSTEM (QCS) and RESIDENT MANAGEMENT SYSTEM (RMS) Submodule 1: Introduction and Overview
Module 8: QUALITY CONTROL SYSTEM (QCS) and RESIDENT MANAGEMENT SYSTEM (RMS) Submodule 1: Introduction and Overview (Module 8 is mandatory for Contractors having Corps of Engineer contracts. It is optional
NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES. Level III Content Outline
Fire Alarm Systems Level III Content Outline The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive listing. 3.1
CORPORATE QUALITY MANUAL
Corporate Quality Manual Preface The following Corporate Quality Manual is written within the framework of ISO 9001:2008 Quality System by the employees of CyberOptics. CyberOptics recognizes the importance
1 RCNY 101-07 CHAPTER 100
1 RCNY 101-07 CHAPTER 100 Subchapter A Administration 101-07 Approved Agencies. (a) Definitions. For the purposes of this section, all terms used herein shall have the same meanings as set forth in the
Design-Build Mississippi Gate Additional Lane
Design-Build Mississippi Gate Additional Lane Buckley Air Force Base, Colorado Completion Date: December 2010 Client: United States Army Corps of Engineers Omaha District Project Reference: Jennifer McQueen,
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
Quality Assurance Program for Design-Bid-Build Projects. January 2016. 2016 by Texas Department of Transportation 512/506-5802 All Rights Reserved
Quality Assurance Program for Design-Bid-Build Projects January 2016 2016 by Texas Department of Transportation 512/506-5802 All Rights Reserved TABLE OF CONTENTS SECTION 1 - INTRODUCTION... 4 1.1 Overview...
GUIDELINES FOR AUGUST 1995
GUIDELINES FOR ELECTRICAL ENGINEERING SERVICES AUGUST 1995 PUBLISHED BY: PROFESSIONAL ENGINEERS AND GEOSCIENTISTS OF NEWFOUNDLAND & LABRADOR (PEGNL) P.O. Box 21207, St. John's, NL A1A 5B2 Telephone: (709)
ACCREDITATION CRITERIA FOR INSPECTION PROGRAMS FOR MANUFACTURERS OF METAL BUILDING SYSTEMS AC472
ACCREDITATION CRITERIA FOR INSPECTION PROGRAMS FOR MANUFACTURERS OF METAL BUILDING SYSTEMS AC472 August 2012 (Effective September 1, 2012) (Editorially revised September 4, 2013) (Editorially revised February
Session: Tue 1110 to 1225. How to Cost Load a schedule. OR Understanding the SDEF
Session: Tue 1110 to 1225 How to Cost Load a schedule for USACE s QCS/RMS OR Understanding the SDEF (understanding the SDEF) Introduction David Long Sr. Project Controls Specialist With 20+ years of Scheduling
TOWN OF LINCOLN INVITATION TO BID EMERGENCY PLANNING, DISASTER RECOVERY AND HAZARD MITIGATION GRANT PROGRAM SERVICES RFP #2015-12
TOWN OF LINCOLN INVITATION TO BID EMERGENCY PLANNING, DISASTER RECOVERY AND HAZARD MITIGATION GRANT PROGRAM SERVICES RFP #2015-12 Sealed bids are due by 10:30 am on Friday, January 30, 2015 Bid Specs are
INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006. 31-d Page 1 of 7
INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June 2006 Control Objectives Example Control Activities Audit Procedures 1. INTERNAL AUDITS Management should periodically
CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT
CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT THIS AGREEMENT made this day of Month, Year, by and between CSA CONSTRUCTION, INC., a Texas corporation whose principal
QUALITY MANAGEMENT SYSTEM REQUIREMENTS
QUALITY MANAGEMENT SYSTEM REQUIREMENTS FOR BUILDERS 2014 400 Prince George s Blvd. Upper Marlboro, MD 20774 800.638.8556 HomeInnovation.com TABLE OF CONTENTS Introduction... iii Notes... iii 1 General...1
Quality Assurance Procedures for Construction and Materials Sampling and Testing 14
Page 1 Quality Assurance Procedures for Construction and Materials Sampling and Testing 14 1. PURPOSE 1.1 To prescribe policies, procedures, and guidelines to assure the quality of materials on all Colorado
GENERAL WELDING & FABRICATING, INC. 991 Maple Road Elma, New York 14059
QUALITY MANUAL GENERAL WELDING & FABRICATING, INC. 991 Maple Road Elma, New York 14059 Distribution: Position Location Copy # President / CEO Office 1 Operations Manager Office 2 Quality Assurance Office
Copies of this document shall be classified either as Controlled or Uncontrolled, and shall be identified as such on the cover sheet.
INTRODUCTION This document describes an inspection system broken down into four separate levels. When Inspection Level IV is invoked, this system meets the requirements of former MIL-I-45208A. The primary
ACCREDITATION CRITERIA FOR FABRICATOR INSPECTION PROGRAMS FOR STRUCTURAL STEEL. AC172 February 2015 (Effective April 1, 2015)
ACCREDITATION CRITERIA FOR FABRICATOR INSPECTION PROGRAMS FOR STRUCTURAL STEEL AC172 February 2015 (Effective April 1, 2015) Requirements related to the Designated Accreditation Representative (DAR) and
CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP)
Michigan Department Of Transportation 5100B (05/13) CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Page 1 of 2 REQUISITION NUMBER DUE DATE TIME DUE MDOT PROJECT MANAGER JOB
QUALITY MANAGEMENT SYSTEM REQUIREMENTS
QUALITY MANAGEMENT SYSTEM REQUIREMENTS FOR TRADE CONTRACTORS 2014 400 Prince George s Blvd. Upper Marlboro, MD 20774 800.638.8556 HomeInnovation.com TABLE OF CONTENTS Introduction... iii Notes... iii
Construction Contract
Construction Contract Case Number: Date: Borrower Name(s): Phone #: Phone #: THIS IS A MODEL DOCUMENT FOR USE IN RENOVATION OR CONSTRUCTION LOAN TRANSACTIONS. THIS FORM IS PROVIDED AS AN EXAMPLE AND IS
AUSTIN INDEPENDENT SCHOOL DISTRICT INTERNAL AUDIT DEPARTMENT CONSTRUCTION AUDIT PROGRAM
GENERAL: Some of the Districts largest capital expenditures are from new construction, facility upgrades, and renovations. A single project can run into the millions of dollars, involving engineering,
REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES PINE TRAIL ELEMENTARY HVAC, CEILING & LIGHTING PROJECT NO. 164514
REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES FOR PINE TRAIL ELEMENTARY HVAC, CEILING & LIGHTING PROJECT NO. 164514 Contact: Mr. Tom Brown, Senior Construction Project Manager Facilities Services,
MASTER AGREEMENT CONSTRUCTION MANAGEMENT SERVICES
MASTER AGREEMENT CONSTRUCTION MANAGEMENT SERVICES This Master Agreement made this 11 day of December, 2012, by and between the St. Lucie County School Board (hereinafter referred to as the School Board
STANDARD PDCA P2-04 THIRD PARTY INSPECTIONS: QUALIFICATIONS, RESPONSIBILITIES, AND PROCEDURES
1. Scope STANDARD PDCA P2-04 THIRD PARTY INSPECTIONS: QUALIFICATIONS, RESPONSIBILITIES, AND PROCEDURES 1.1. The purpose of this standard is to establish third party inspection qualifications, responsibilities
Agreement between Owner and Architect
Agreement between Owner and Architect This AGREEMENT is made as of the - day of - in the year - BETWEEN the Owner: Drexel University - 3141 Chestnut Street - Philadelphia, Pa 19104 - - - and the Architect:
Position Classification Standard for Procurement Clerical and Technician Series, GS-1106. Table of Contents
Position Classification Standard for Procurement Clerical and Technician Series, GS-1106 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 DEFINITIONS... 3 OCCUPATIONAL INFORMATION... 3 TITLES...
