1 PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 specification sections shall apply to work of this section SCOPE OF WORK A. Asbestos Removal Contractor shall be responsible for, but not limited to, the following: 1. Submission and approval of required notification prior to commencement of work. 2. Removal of all asbestos material within the asbestos removal limit line. 3. Contractor shall inspect facility and insure that all asbestos material has been removed in accordance with the specifications. 4. Furnish all labor, materials, services, insurance and equipment necessary to carry out the removal operation in accordance with applicable regulations and codes. 5. Be responsible for obtaining approval for a waste disposal site and transportation of waste to waste disposal facility. Waste disposal facility must have a valid NYS DEC or Regulatory Waste Authority permit. Waste transporter shall have a valid NYS DEC, Division of Solid & Hazardous Materials, Part 364 Waste Transporter Permit. 6. Post all applicable regulations at the job site. 7. Maintain the required log of all persons entering work area. 8. Provide Owner with Close-Out Report and Record Drawings containing all information pertaining to the removal and disposal of asbestos containing materials (quantity and location). 9. Provide Owner with record drawing of asbestos removal including location, quantity and type of asbestos removed REGULATIONS AND CODES A. All work of this contract shall comply with all applicable Federal, State, Local and Municipal regulations including, but not limited to: 1. Toxic Substances Control Act (TSCA) Title II Asbestos Hazard Emergency Response Act (AHERA) (October 22, 1986) and most recent amendments/editions. 2. Environmental Protection Agency (EPA) Final Rule Act (AHERA) 40 CFR Part 763 Subpart E (October 30, 1987) and most recent amendments/editions. 3. Environmental Protection Agency (EPA) Worker Protection Rule 40 CFR Part 763 Subpart G, (February 25, 1987) and most recent amendments/editions. 4. National Emission Standards for Hazardous Air Pollutants (NESHAPS) 40 CFR 61 Subpart A - General Provisions and most recent amendments/editions. 5. National Emission Standards for Hazardous Air Pollutants 40 CFR 61 Subpart M - Asbestos Provisions and most recent amendments/editions. 6. Summary of Occupational Safety and Health Administration (OSHA) 29 CFR General Industry Standard. 7. Occupational Safety and Health Administration (OSHA) 29 CFR General Industry Standard. 8. Occupational Safety and Health Administration (OSHA) 29 CFR Construction Standard and 29 CFR Construction Standard "Excursion Limit" (Amended September 14, 1988). 9. Occupational Safety and Health Administration (OSHA) 29 CFR , Subpart I and Appendix A3, Respiratory Protection Standard. 10. New York State Department of Environmental Conservation (DEC): 6 NYCRR Part Waste Transporter Permits. 11. New York State Department of Labor (DOL): Industrial Code Rule No. 56 as amended March 21, 2007, Guidance Document 2.0 released January 24, 2009; include current amendments. PAGE NO. 1
2 12. Fire Code of New York, 2010 Including Technical Bulletins issued by the New York State Department of State. 13. Existing Building Code of New York State 2010, Including Technical Bulletins issued by New York State Department of State. 14. Building Code of New York State 2010, Including Technical Bulletins issued by New York State Department of State. 15. New York State Department of Labor (DOL), Title 10, Part DEFINITIONS A. See NYSDOL Industrial Code Rule No. 56. B. See Chapter 2 of the Fire Code, Existing Building Code & Building Code of New York State for other definitions CONTRACTOR LIABILITY A. It is understood and agreed that the handling, removal and disposition of asbestos or asbestos products involves certain health risks which require specific safety measures. Owner and Consultant (Architect/Engineer) shall not be responsible for safety measures on the job, including measures for the protection of employees or other contractors or subcontractors, nor for the protection of the general public. Such responsibility for safety is and shall remain that of Contractor. Therefore, except for claims and damages arising for negligent acts, errors or omissions of Consultant. Contractor agrees to hold harmless, defend and indemnify Owner and Consultant from all claims, suits, expenses, or damages arising from or alleged to arise from exposure to or inhalation of asbestos or asbestos fibers CONTRACTOR REQUIREMENTS A. During all Asbestos Abatement (Phase II) Activities the Asbestos Abatement Contractor shall have a "Contractor Supervisor" on site. If the Contractor Supervisor is not on site during Asbestos Abatement activities, work shall stop and shall not commence until the Contractor Supervisor has returned to the project site. B. The Contractor Supervisor shall have a minimum of five (5) year experience as a project (contractor) supervisor, the experience shall be similar in scope, size and complexity. C. The Project Supervisor shall be capable of communicating in english and the native language of the asbestos abatement work crew (handlers/ workers) NOTICES AND PERMITS A. Comply with the standards referenced in Part 1 of this section. B. Contractor to submit DOSH 465 from "Non-Friable Asbestos or Asbestos Material Roofing Project(s)". C. Required notification to be based on removal in excess of 260 lf. or 160sq. ft. Contractor shall be responsible for all initial, renewal, amended and emergency notifications and related fees associated with notification of asbestos project. Contractor shall provide copy of Asbestos Project Notification to Environmental Consultant and Designated Owner's Representative. D. Should the contractor discover a material that he suspects is an asbestos containing material and believes the material shall be tested. He shall stop all work and contact the Environmental Consultant and the Architect. The Owner's Environmental Consultant with permission of the Owner will collect the required samples and complete the analysis of said material. Samples and analysis by the contractor or other consultant other than that of the Owner's will not be accepted ENVIRONMENTAL CONSULTANT A. An Environmental Consultant will be employed by the Owner and shall represent the Owner in all matters pertaining to the work performed in accordance with these specifications and requirements. PAGE NO. 2
3 B. The Environmental Consultant is authorized by the Owner to oversee all removal work, to interpret procedures and to enforce all provisions of the contract documents and NYS Code Rule 56 pertaining to the removal of asbestos containing insulation. C. The Environmental Consultant is authorized to stop work if, in his opinion, there is a substantial non-conformance with the contract documents and NYS Code Rule 56 and/or a situation presenting a health hazard to workers or to the Owner's employees. D. The Environmental Consultant shall attend project meetings as well as schedule meetings as required to expedite the Asbestos Removal Work and act as the Owner's liaison in all matters involving the work. E. The Environmental Consultants role in health and safety matters does not alleviate the Contractor's obligation to comply with all applicable health and safety regulations promulgated by the local state or federal government. F. The Environmental Consultant shall perform air sampling during the removal project. The Contractor shall cooperate fully with the Consultant and shall ensure the cooperation of his workers during collection of personal air samples. The collection, if any, of personal air samples does not relieve the Contractor of his responsibility to collect personal air sampling of his asbestos workers. Contractor shall monitor at least 25% of his employees SUBMITTALS A. See Section Submittal Procedures, for submittal process. B. "Submit" means to forward and electronic copy to the Designer of Record and the Environmental Consultant for review. C. Submittals shall be forwarded a minimum of ten (10) days prior to the Anticipated Commencement of the Asbestos Abatement Work and any resubmissions shall be expedited. D. Prior to commencement of work: 1. Submit copy of required notifications per the standards referenced in Part 1 of this section. 2. Submit Work Plan: A written work plan that describes the asbestos abatement methods to be used including the type of decontamination units, the decontamination locations and Contractor's worker protection plan shall be submitted to the Asbestos Designer of Record and to the Environmental Consultant prior to abatement activities. 3. Submit satisfactory proof to Asbestos Designer of Record and Environmental Consultant that all required permits, site location and arrangements for transport and disposal of asbestos containing or contaminated materials, supplies and the like have been obtained, including: a. One current copy of each Contractor's asbestos handler' s license and one copy of each employee's asbestos handler' s certificate. In addition to the asbestos handlers licenses, the Asbestos Abatement Contractor shall submit each employees "OSHA 10" card. Should Handlers' or Supervisor's documentation expire during the duration of the project the Asbestos Contractor shall submit replacement documents. b. Copy of waste hauler' s NYSDEC permit and one copy of NYSDEC Certificate of Approval for the ACM waste disposal site. c. Submit a written description and scale drawings for the construction of decontamination enclosure systems and for isolation of the work areas in compliance with this specification and applicable regulations. Show all equipment locations and exhaust locations. d. Submit documentation indicating that all employees have had instruction on the hazards of asbestos exposure, on use of fitting of respirators, on protective dress, on use of showers, on entry and exit from work areas and on all aspects of work procedures and protective measures. e. Submit location and installation method of air exhaust (negative air) system. f. Submit documentation certifying that all workers employed in asbestos related aspects of the job have had medical examinations as prescribed by the OSHA regulations and have been found fit to perform work while wearing a respirator. This PAGE NO. 3
4 certification is to be signed by a physician indicating that he has reviewed the relevant medical records and that they support the certification. Medical records are not to be submitted and will not be accepted. g. The Contractor and Owner shall agree in writing on the condition of the building and fixtures and background level, prior to commencement of the work. h. Contractor shall submit copy of his daily log. i. Submit manufacturer's certification that vacuums, ventilation equipment and other equipment required to contain airborne fibers, conform to ANSI Z9.2. j. The Contractor shall establish a manifest system that accounts for all asbestos waste. The manifest system shall be described in writing and will be subject to the approval of the Environmental Consultant. Copies of the written description and any receipts generated during the handling and disposal process shall be provided to the Owner. The Contractor must be able to demonstrate custody over all asbestos waste from the time it is removed from the work area until it is deposited at the landfill. The Asbestos Disposal Manifests completed by all Parties shall be submitted to the Owner within (45) days after the abatement has been completed and the Asbestos material debris has been removed from the site (for each phase of work). k. Submit schedule of removal. 4. Prior to Final Payment: a. Submit closeout package to include: 1) Copy of Notifications. 2) Copy of Contractor Asbestos License and Employees involved in the project. Certificates and Documentation as indicated in C.6. 3) Copy of Haulers Permit. 4) Copies of Daily Work Area Entry Logs. 5) Copies of Lab Reports on Personal Air Monitoring. 6) Copies of Asbestos Disposal Manifests completed by all Parties, for each phase of work as applicable. 7) Copy of Record Drawing indicating locations type, and quantities of ACBM removed. PART 2 PRODUCTS - NOT USED PART 3 EXECUTION 3.01 ASBESTOS-CONTAINING MATERIAL HANDLING AND REMOVAL PROCEDURES A. Comply with the standards referenced in Part 1 of this Section. B. Removal of existing fixed items or built-in furnishings and equipment as necessary to access areas scheduled for abatement. C. The contractor is responsible for providing adequate lighting of the work area to be abated. Minimum lighting levels in work area shall be 10 foot candles. D. Asbestos Contractor shall have appropriate type & quantity of Equipment on site in the event that the primary equipment malfunctions. E. Remove and dispose of all asbestos containing materials as noted within the designated work areas on the Contract Drawings CLEANUP PROCEDURES A. Comply with the standards referenced in Part 1 of this section AIR SAMPLING, MONITORING AND ANALYSIS A. Air Monitoring Tests: The Owner shall employ the services of an independent testing laboratory to perform air sample monitoring tests. The laboratory shall use the methods described in standards referenced in Part 1 of this section, except the clearance test shall be TEM Method (Transmission Electron Microscope) and PCM Method (Phase Contrast Microscopy). PAGE NO. 4
5 B. The Contractor shall be responsible for all costs associated with additional air sampling and analysis should the work area not pass initial clearance and sampling DISPOSAL OF ASBESTOS-CONTAINING MATERIAL AND RELATED DEBRIS A. Transport the asbestos-containing waste, related debris, and waste water to the approved disposal site. Comply with the standards referenced in Part 1 of this section. B. The Asbestos Abatement Contractor shall return a fully executed waste shipment record to the owner within 35 days after Asbestos waste has left the project site. If project is completed in phases, the waste shipment record shall be returned within thirty five days after ACM Waste for each phase is removed from the project site RESTORATION A. Remove temporary decontamination facilities and restore area designated for these facilities to its original condition or better RECORD KEEPING A. In addition to required record keeping, Contractor shall retain: 1. Entry and exit log. 2. Results of personal monitoring samples. Worker's medical exams. B. Provide Owner with Close-Out Report containing all records and documentation on the removal and disposal of asbestos containing materials. END OF SECTION PAGE NO. 5
Asbestos Management Plan EC 45 Page 1
Name: Asbestos and ACBM (asbestos containing building material) Management Plan Areas Affected: All buildings that contain asbestos and ACBM on campus Effective Date: 1/1/09 Reviewed/Revised: 12/15/12
More informationUniversity of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS
Page 1 of 5 The inhalation of asbestos fibers in excess amounts can lead to chronic lung disease. Our knowledge of these health effects comes from studies of workers exposed routinely to high concentrations
More informationASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM September 2015 Asbestos Management Program Table of Contents I. Purpose II. III. IV. Definitions Identification of Asbestos Asbestos Sampling V. Notification and Labeling VI.
More informationSyracuse University s Guidelines for Work Involving Materials Containing Trace Asbestos (Asbestos at a Concentration Less than 1%)
Syracuse University s Guidelines for Work Involving Materials Containing Trace Asbestos (Asbestos at a Concentration Less than 1%) I. Asbestos Survey Requirements Prior to performing any construction,
More informationDepartment of Environmental Health & Safety. Asbestos Management Program
Department of Environmental Health & Safety Asbestos Management Program Issued by: Nathan Rath Date Effective: December 2010 OHIO University Asbestos Management Program Table of Contents Section/Title
More informationAsbestos Management Program
Asbestos Management Program Department of Environmental Health & Safety Department of Facilities Management Rev. 4/2/09 OHIO University Asbestos Management Program Table of Contents Section/Title Page_
More informationASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS
ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS 1.0 GENERAL 1.1 SUMMARY A. The following procedures apply to the project manual and drawings for asbestos in
More informationEXHIBIT A SCOPE OF SERVICES
EXHIBIT A SCOPE OF SERVICES 1.0 INTRODUCTION Asbestos consulting services are required for Item/Segment No. 227775-1, SR-7 (US 441) from Fillmore Street to South of Stirling Road, Hollywood, Broward County,
More informationOGS LIMITED ASBESTOS & LEAD SURVEY REPORT
our people and our passion in every project OGS LIMITED ASBESTOS & LEAD SURVEY REPORT Building 44 Willard Drug Treatment Center 7116 County Road 132 Willard, NY Prepared for: NYSOGS 33 rd Floor, Corning
More informationAddendum 1 Clarifications
Addendum 1 Clarifications Asbestos 1. Clarifications CONTRACTOR is instructed to incorporate standard abatement procedures as mandated by the Federal OSHA Construction Industry Standard; 29 CFR 1926.1101,
More informationNorth Carolina State University. Asbestos Management Plan
North Carolina State University 1.0 Introduction Purpose The purpose of this plan is to establish the polices and procedures to be used at North Carolina State University (NCSU) in the management of building
More informationLEGAL REVIEW & UPDATE
LEGAL REVIEW & UPDATE There are lots of laws and regulations designed to protect workers, the general public, and the environment. However, not everyone follows the laws. Many people deliberately break
More informationAsbestos Abatement Management Program. Facilities Operations and Development Environmental Health & Safety
Asbestos Abatement Management Program Facilities Operations and Development Environmental Health & Safety November 7, 2012 INTRODUCTIONS David Kos (EHS) Director of Environmental Affairs David Kehl (EHS)
More informationAsbestos Management Program (EHS Program Manager 7.5)
Asbestos Management Program (EHS Program Manager 7.5) 1.0 Introduction The Weill Cornell Medicine (WCM) Asbestos Management Program protects the WCM community from the health hazards related to asbestos
More informationALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVERSITY. MANAGING ASBESTOS at EINSTEIN. Prepared by: Department of Environmental Health and Safety
ALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVERSITY Prepared by: Department of Environmental Health and Safety Revised: August, 2013 ALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVERSITY DEPARTMETN
More informationWellesley College Asbestos Management Program
Wellesley College Asbestos Management Program Table of Contents Page Policy 2 Impacts of Asbestos Containing Materials (ACM)... 3 Compliance... 3 Objectives... 4 Operational Controls Standard Operating
More informationASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate
More informationAsbestos abatement Sampling & Analysis. Abatement Project Supervision
Asbestos abatement Sampling & Analysis Abatement Project Supervision TOPICS FOR DISCUSSION Air Sampling PERSONNEL AREA Analysis PCM Analysis TEM Analysis TYPES OF SAMPLING Two types of air sampling are
More informationUNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY
Revision No.: 1 Page 1 of 6 I. PURPOSE This procedure establishes the process to conduct asbestos work as it applies to Operation and Maintenance activities, including emergencies. II. PERSONNEL AFFECTED
More informationCharacteristics/Applications
Facilities Operations and Development Environmental Health & Safety 1314 Kinnear Rd. Columbus, Ohio 43212 Phone (614) 292-1284 Fax (614) 292-6404 http://fod.osu.edu The Ohio State University Asbestos Management
More informationASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015
ASBESTOS CONTAINING MATERIALS OPERATIONS & MAINTENANCE PLAN 2015 Prepared For: (School Name) PREPARED BY: DIOCESE OF JOLIET ENVIRONMENTAL OFFICE FOR ANY ENVIRONMENTAL RELATED EMERGENCY CONTACT: RICHARD
More information100 North Senate Avenue, Indianapolis, IN 46204 Phone: (317) 308-3103 Toll Free: (800) 451-6027
GUIDANCE OLQ GENERAL ID #003-02-SW INDIANA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT OFFICE OF LAND QUALITY ASBESTOS HANDLING AND DISPOSAL REQUIREMENTS www.idem.in.gov Mitchell E. Daniels, Jr. Thomas W. Easterly
More informationCOMPLIANCE WITH THIS PUBLICATION IS MANDATORY
BY ORDER OF THE COMMANDER 56TH FIGHTER WING (AETC) AIR FORCE INSTRUCTION 32-1052 LUKE AIR FORCE BASE Supplement 1 5 NOVEMBER 2008 Civil Engineering FACILITY ASBESTOS MANAGEMENT COMPLIANCE WITH THIS PUBLICATION
More informationAsbestos Management & Abatement
Asbestos Management & Abatement Latest revised date: October 29, 2012 Page 1 of 18 1.0 LEGAL & LEGISLATIVE REQUIREMENTS This standard provides guidance to meeting the minimum requirements of the Act &
More informationWashington University Asbestos Operations and Maintenance Plan
1. Purpose Washington University Asbestos Operations and Maintenance Plan 1.1. The purpose of this Asbestos Operations and Maintenance (O&M) Plan is to minimize the potential for exposure to airborne asbestos
More informationASBESTOS OPERATIONS AND MAINTENANCE PLAN
UNIVERSITY OF FLORIDA ASBESTOS OPERATIONS AND MAINTENANCE PLAN Administered by: Environmental Health and Safety Building 179 PO Box 112190 Gainesville, Florida 32611 Introduction The following document
More information2. 40 CFR Part 763; The Asbestos Hazard Emergency Response Act (AHERA), EPA Worker Protection Rule, February 25, 1987.
Penn State University Environmental Health and Safety Asbestos Management Program I. Introduction Over the past several decades the hazards of asbestos exposure have become well known. With this influx
More informationASBESTOS MANAGEMENT PLAN
ASBESTOS MANAGEMENT PLAN SAN JOSE STATE UNIVERSITY Environmental Health & Occupational Safety Asbestos Management Plan 1.0 Introduction 2.0 Policy 3.0 Responsibilities 4.0 Contract Administration 5.0 In-House
More informationSPECIFICATION DIVISION 2 NUMBER SECTION DESCRIPTION DIVISION 02 EXISTING CONDITIONS SECTION 028214 ASBESTOS REMEDIATION FLOOR TILE AND MASTIC
ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION
More informationASBESTOS MANAGEMENT INTRODUCTION
SECTION: II. General Hygiene/ Safety Chapter: 7. Asbestos Management Revision Date: 12/05/2013 Review Date: ASBESTOS MANAGEMENT INTRODUCTION PURPOSE This policy has been developed to ensure that hazardous
More informationCONNECTICUT STATUTES : (4)
CONNECTICUT STATUTES : (4) TITLE 20 PROFESSIONAL AND OCCUPATIONAL LICENSING, CERTIFICATION, TITLE PROTECTION AND REGISTRATION. EXAMINING BOARDS CHAPTER 400K INDUSTRIAL HYGIENE AND SAFETY INSPECTOR TITLE
More informationASBESTOS and LEAD-BASED PAINT INVESTIGATION TOWN OF ST. PAUL WILLIS BUILDING ST. PAUL, VIRGINIA
ASBESTOS and LEAD-BASED PAINT INVESTIGATION TOWN OF ST. PAUL WILLIS BUILDING ST. PAUL, VIRGINIA May 22, 2013 Robert R. Jones, Ph.D., REM, AHERA Asbestos Inspector, 5/22/13 Signature Date Asbestos Virginia
More informationTRAINING CENTER LOCATION: 10 COLVIN AVE, ALBANY, NY
ASBESTOS INITIAL COURSES JAN. FEB. MARCH APRIL MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. Worker/Handler 7-10 10-13 11-14 14-17 9-12 11-14 4 days $500.00 Supervisor/Contractor 9-13 12-16 7-11 9-13 10-14 12-16
More informationNew York State Department of Health Center for Environmental Health Bureau of Occupational Health
New York State Department of Health Center for Environmental Health Bureau of Occupational Health Kevin Malone, Section Chief Asbestos Safety Training Program Flanigan Square Troy NY, 12180 518-402-7940
More informationLoss Control TIPS Technical Information Paper Series
Loss Control TIPS Technical Information Paper Series Innovative Safety and Health Solutions SM Asbestos-Containing Material (ACM) In Buildings The presence of asbestos in buildings, particularly those
More informationDRAFT Analysis of Brownfields Cleanup Alternatives City of Olympia Isthmus Properties 505/529 4 th Avenue West
DRAFT Analysis of Brownfields Cleanup Alternatives City of Olympia Isthmus Properties 505/529 4 th Avenue West December 2013 Prepared by: Kip Summers, P.E. City of Olympia Table of Contents Introduction...
More informationWASTE SERVICES & DISPOSAL AGREEMENT. By: By: Name: Name: Title: Title:
WASTE SERVICES & DISPOSAL AGREEMENT COMPANY: CUSTOMER: By: By: Name: Name: Date Date Title: Title: Effective Date of Agreement: Initial Term: Contract No. This Waste & Disposal Services Agreement, consisting
More informationThe Richard Stockton University ASBESTOS MANAGEMENT PLAN
The Richard Stockton University ASBESTOS MANAGEMENT PLAN January 2015 Asbestos Management Plan Table of Contents I. Introduction II. III. IV. Definitions Identification of Asbestos Notification and Labeling
More informationAsbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material
Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace
More informationJune 27, 2013. Project GSA1570019. Rhonda Rance U.S. General Services Administration 450 Golden Gate Avenue, Floor 4 San Francisco, California 94102
June 27, 2013 Project GSA1570019 Rhonda Rance U.S. General Services Administration 450 Golden Gate Avenue, Floor 4 San Francisco, California 94102 Subject: Determination of Asbestos Conditions Former USDA
More informationSPECIFICATIONS FOR ASBESTOS-CONTAINING MATERIALS SUNY PURCHASE COLLEGE BEECHWOOD RESIDENCE 3031 PURCHASE STREET PURCHASE, NEW YORK 10577 FOR
SPECIFICATIONS FOR ASBESTOS-CONTAINING MATERIALS AT SUNY PURCHASE COLLEGE BEECHWOOD RESIDENCE 3031 PURCHASE STREET PURCHASE, NEW YORK 10577 FOR SUNY PURCHASE COLLEGE 735 ANDERSON HILL ROAD PURCHASE, NEW
More informationFRED GRAHAM'S ASBESTOS SAFETY PROGRAM EXPERT WITNESS SUPPORT SERVICES
FRED GRAHAM'S ASBESTOS SAFETY PROGRAM EXPERT WITNESS SUPPORT SERVICES QUALIFICATIONS If your asbestos lawsuit requires the services of a asbestos safety program expert witness to determine if the property
More informationSpecifications for Asbestos Abatement
Specifications for Asbestos Abatement Virginia Department of Health Henry/Martinsville Health Department 295 Commonwealth Boulevard Martinsville, Virginia Prepared for City of Martinsville, Virginia 300
More informationDIVISION 248 ASBESTOS REQUIREMENTS. Asbestos Emission Standards and Procedural Requirements 340-248-0250. Asbestos Abatement Project Exemptions
DIVISION 248 ASBESTOS REQUIREMENTS Asbestos Emission Standards and Procedural Requirements 340-248-0250 Asbestos Abatement Project Exemptions (1) Any person who conducts or provides for the conduct of
More informationBritish Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT
BCIT Safety Manual Contents 1. Purpose... 3 2. Definitions... 3 2.1 Asbestos... 3 2.2 Asbestos Containing Material (ACM)... 3 2.3 Friable Material... 3 2.4 Low Risk Work Activity... 3 2.5 Moderate Risk
More informationTraining Course Catalog
Training Course Catalog Asbestos, Lead Paint, Mold, OSHA Chem Scope, Inc. 15 Moulthrop Street, North Haven CT 06473 203-865-5605 Fax 203-498-1610 www.chem-scope.com chem.scope@snet.net Table of Contents
More informationAsbestos NESHAP ISSUES AND QUESTIONS
Asbestos NESHAP ISSUES AND QUESTIONS FIRE-DAMAGED BUILDINGS HOW DOES THE NESHAP APPLY? After the Fire Is Out Building condition can vary widely from smoke damage to complete destruction with variations
More informationASBESTOS, DEMOLITION OR RENOVATION, SANDBLASTING, AND GRINDING STANDARDS
ASBESTOS, DEMOLITION OR RENOVATION, SANDBLASTING, AND GRINDING STANDARDS The purpose of City Code 11-4-2150-11-4-2190 is to reduce the potential risk of harm to the public's health, safety and welfare
More informationUI Procedures for Asbestos Management
UI Procedures for Asbestos Management The University of Iowa Rev.12/12/2012 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing
More informationAsbestos Abatement Work Plan for the Carter Carburetor Superfund Site
for the Prepared for: ACF Industries LLC 101 Clark Street St. Charles, Missouri 63301 Prepared by: AMEC Environment & Infrastructure, Inc. 15933 Clayton Road, Suite 215 Ballwin, Missouri 63011 Project
More informationAsbestos Survey. for. Commercial Building TCA Building T-187, Pasco Airport Pasco, Washington. May 1, 2014. Project #A2014/0406.
Asbestos Survey for Commercial Building TCA Building T-187, Pasco Airport Pasco, Washington May 1, 2014 Project #A2014/0406 prepared for: Port of Pasco PO Box 769 Pasco, WA 99301 prepared by: Blue Mountain
More informationAsbestos Inspection Project Procedure
EOSMS 402 Date: 01/13/2014 Page 1 of 6 1) Purpose This document is intended to specify the scope of services required of Asbestos Contractor in asbestos inspection projects at Kennesaw State University
More informationasbestos management SECTION 21 SECTION CONTENTS ADDITIONAL READING Asbestos Management / Page1 / SECTION 21 TULANE UNIVERSITY
SECTION 21 asbestos management TULANE UNIVERSITY ENVIRONMENTAL HEALTH AND SAFETY POLICIES AND PROCEDURES MANUAL REVISION DATE: 9/1/03 Return to Table of Contents, EH&S Policies & Procedures Manual SECTION
More informationQuestions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project
Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project The Watergate Community is currently in the process with the fire suppression and interior renovations
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-02 82 16.00 20 (August 2011) ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-02 82 16.00 20 (February 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More information130 LIBERTY STREET ASBESTOS ABATEMENT PLAN
130 LIBERTY STREET ASBESTOS ABATEMENT PLAN Prepared for: GILBANE BUILDING COMPANY 125 MAIDEN LANE NEW YORK, NEW YORK Prepared by: WESTON SOLUTIONS 205 CAMPUS DRIVE EDISON, NEW JERSEY 08837 NYS Certified
More informationARKANSAS POLLUTION CONTROL and ECOLOGY COMMISSION REGULATION NO. 21 ARKANSAS ASBESTOS ABATEMENT REGULATION
Pollution Control and Ecology Commission # 014.00-021 ARKANSAS POLLUTION CONTROL and ECOLOGY COMMISSION REGULATION NO. 21 ARKANSAS ASBESTOS ABATEMENT REGULATION Adopted by the PC&E Commission September
More information(A) All asbestos-containing waste material shall be deposited as soon as is practical by the waste generator at:
3745-20-05 Standard for asbestos waste handling. [Comment: For dates of non-regulatory government publications, publications of recognized organizations and associations, federal rules, and federal statutory
More informationSUBPART 6 - ASBESTOS SOURCES 2105.60 ASBESTOS ABATEMENT CONTRACTOR LICENSES
SUBPART 6 - ASBESTOS SOURCES 2105.60 ASBESTOS ABATEMENT CONTRACTOR LICENSES a. General. In addition to the accreditation and permit requirements under 2105.61 and 2105.62, respectively, of this Article,
More informationANALYSIS OF BROWNFIELDS CLEANUP ALTERNATIVES FAIRFIELD HILLS CAMPUS HAZARDOUS SUBSTANCES REMOVAL DANBURY HALL AND EIGHT SINGLE FAMILY HOMES
ANALYSIS OF BROWNFIELDS CLEANUP ALTERNATIVES FAIRFIELD HILLS CAMPUS HAZARDOUS SUBSTANCES REMOVAL DANBURY HALL AND EIGHT SINGLE FAMILY HOMES UNITED STATES ENVIRONMENTAL PROTECTION AGENCY BROWNFIELDS CLEANUP
More informationHobart and William Smith Colleges. Environmental, Health and Safety Program
Hobart and William Smith Colleges Geneva, New York Environmental, Health and Safety Program Copies of the EHS Program: 1. Human Resources Office 2. Office of the President (Provost) 3. Campus Safety Office
More informationLEAD MANAGEMENT PROGRAM
Page: 1 of 7 1.0 Purpose and Applicability 1.1 It is the policy of the University of Pennsylvania in coordination with the Office of Environmental Health and Radiation Safety to provide the University
More informationThe Vermont Department of Health When is Asbestos a Public Health Threat? Town Health Officers (THO) Training
When is Asbestos a Public Health Threat? Town Health Officers (THO) Training Asbestos and Lead Regulatory Program 2013 When is Asbestos a Public Health Threat? Town Health Officer (THO) Training August
More informationDivision of Public Health Administrative Manual
PURPOSE To establish a protocol for the development of a written Division of Public Health Hazard Communications Program at each applicable office or laboratory workplace and to assure that employees are
More informationTHE RICHARD STOCKTON UNIVERSITY OF NEW JERSEY ASBESTOS ABATEMENT CONTINGENCY PLAN. February 2015
THE RICHARD STOCKTON UNIVERSITY OF NEW JERSEY ASBESTOS ABATEMENT CONTINGENCY PLAN February 2015 Risk Management and Environmental Health and Safety Office RMEHS ASBESTOS ABATEMENT CONTINGENCY PLAN Table
More informationDraft ABCA : USEPA 2015 Brownfields Cleanup Grant Application for Former Hudepohl Brewery Site by Port of Greater Cincinnati Development Authority
Analysis of Brownfield Cleanup Alternatives (ABCA) for Hudepohl Brewery Site Introduction & History The Port of Greater Cincinnati Development Authority (Port Authority) has developed a draft proposal
More informationASBESTOS. CSEA / Local 1000 AFSCME / AFL-CIO. 143 Washington Avenue, Albany, New York 12210. Danny Donohue, President
S A F E T Y & H E A L T H ASBESTOS QUESTIONS AND ANSWERS FOR BUILDING OCCUPANTS CSEA / Local 1000 AFSCME / AFL-CIO 143 Washington Avenue, Albany, New York 12210 Danny Donohue, President : CSEA OCCUPATIONAL
More information2012 OPEN ENROLLMENT SCHEDULE Environmental, Health & Safety Training State & Federal EPA Accredited Programs
2012 OPEN ENROLLMENT SCHEDULE Environmental, Health & Safety Training State & Federal EPA Accredited Programs ASBESTOS Abatement Worker/Supervisor Air Sampling Technician (NYS) Allied Trades (NYS) NIOSH
More informationPROTECTING TRIBAL CHILDREN & COMMUNITY MEMBERS FROM ASBESTOS-IN-SCHOOL HAZARDS
PROTECTING TRIBAL CHILDREN & COMMUNITY MEMBERS FROM ASBESTOS-IN-SCHOOL HAZARDS PROTECTING TRIBAL CHILDREN & COMMUNITY MEMBERS FROM ASBESTOS-IN-SCHOOL HAZARDS 19 th Annual Tribal EPA Environmental Conference.
More informationTAMPA ELECTRIC COMPANY ENERGY SUPPLY ASBESTOS AWARENESS PROGRAM
ASBESTOS AWARENESS PROGRAM TABLE OF CONTENTS TITLE PAGE # PURPOSE / INTRODUCTION 1 RESPONSIBILITY 2 EMPLOYEE TRAINING AND DOCUMENTATION 2-4 MEDICAL SURVEILLANCE 4 UNPLANNED DISTRUBANCE OF ASBESTOS CONTAINING
More informationApproved by: UBC ACT Committee
The University of British Columbia Asbestos Safety Policy Prepared by: Russell R. English Policy Approved by: UBC ACT Committee Issue Date: April 1, 2004 Replaces: March, 1989 I-B-05 1.0 Policy: This policy
More informationOriginal Date of Issue: 12/08
POLICIES AND PROCEDURES ASBESTOS PROGRAM DEPARTMENT: ENVIRONMENTAL HEALTH AND SAFETY SUBJECT: ASBESTOS PROGRAM Original Date of Issue: 12/08 REVIEWED: 12/08 04/09 01/2012 REVISED: 12/08 04/09 01/2012 l.
More informationAdministrative Procedure. Asbestos
Administrative Procedure FT107 Asbestos Board Received: January 30, 2012 Review Date: February 2015 Accountability: 1. Frequency of Reports As needed 2. Severity Threshold As needed (eg. Ministry of Labour
More informationAsbestos Management POLICY
Asbestos Management POLICY All Asbestos Containment Material (ACM) removal activities shall comply with applicable federal, state, and local regulations. Areas of responsibility of Facilities Management
More informationBRIEFING TO THE UN STAFF
BRIEFING TO THE UN STAFF Topics History, Properties and Uses of Asbestos Important Definitions Regulatory Overview Asbestos Abatement Procedures History And Use What is Asbestos? Asbestos is a mineral
More informationUNOFFICIAL. 1. Owner: Delaware Department of Transportation (DelDOT) WEBSITE
SECTION 01013 - SUMMARY OF THE WORK - ASBESTOS ABATEMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationAsbestos Licensure Law. Code of West Virginia Chapter 16, Article 32 (As amended by the 1993 Legislative Session)
Asbestos Licensure Law Code of West Virginia Chapter 16, Article 32 (As amended by the 1993 Legislative Session) Be it enacted by the Legislature of West Virginia: That chapter sixteen of the code of West
More informationBOSTON COLLEGE OFFICE OF ENVIRONMENTAL HEALTH & SAFETY ASBESTOS MANAGEMENT PROGRAM
BOSTON COLLEGE OFFICE OF ENVIRONMENTAL HEALTH & SAFETY ASBESTOS MANAGEMENT PROGRAM Prepared: May, 1999 Revised: February, 2004 Reviewed: September, 2004 Table of Contents Section Title Page # 1.0 Program
More informationMARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore MD 21230 410-537-3000 1-800-633-6101 www.mde.state.md.
MARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore MD 21230 410-537-3000 1-800-633-6101 www.mde.state.md.us/asbestos Martin O Malley Governor Robert M. Summers, Ph.D. Secretary
More informationWest Virginia Accreditation Standards for Asbestos, Lead and Radon Training
West Virginia Accreditation Standards for Asbestos, Lead and Radon Training West Virginia Bureau for Public Health Office Of Environmental Health Services Radiation, Toxics and Indoor Air Division Certification
More informationASBESTOS AWARENESS TRAINING
ALBERT EINSTEIN COLLEGE of MEDICINE of YESHIVA UNIVRESITY Substance: Asbestos CAS Registry Number: 1332-21-4 ASBESTOS AWARENESS TRAINING Synonyms: chrysotile, amosite (cummingtonite-grunerite), actinolite,
More informationASBESTOS/LEAD SURVEY AND CONSULTING AGREEMENT BY AND BETWEEN NEW YORK UNIVERSITY / NYU HOSPITALS CENTER - OWNER - AND - CONSULTANT - --------- PROJECT
APPENDIX A ASBESTOS/LEAD SURVEY AND CONSULTING AGREEMENT BY AND BETWEEN NEW YORK UNIVERSITY / NYU HOSPITALS CENTER - OWNER - AND - CONSULTANT - --------- PROJECT DATED AS OF ASBESTOS/LEAD SURVEY AND CONSULTING
More informationARTICLE 18. ASBESTOS MANAGEMENT NOTE: IC 13-1 and IC 13-7 were repealed by P.L.1-1996, SECTION 99, effective July 1, 1996.
ARTICLE 18. ASBESTOS MANAGEMENT NOTE: IC 13-1 and IC 13-7 were repealed by P.L.1-1996, SECTION 99, effective July 1, 1996. Rule 1. Asbestos Management Personnel; Licensing 326 IAC 18-1-1 Applicability
More informationCONTAINS ASBESTOS FIBERS
ASBESTOS Rules and Regulations Controlling Exposure DANGER CONTAINS ASBESTOS FIBERS AVOID CREATING DUST CANCER AND LUNG DISEASE HAZARD This booklet was prepared and published by Division of Field and Legal
More informationLoss Control TIPS Technical Information Paper Series
Loss Control TIPS Technical Information Paper Series Innovative Safety and Health Solutions SM An Overview of OSHA s Laboratory Standard: 29 CFR 1910.1450 Introduction The Occupational Safety and Health
More informationREMOVAL OF ASBESTOS-CONTAINING MASTIC. The Sherman School 2 Route 37 East Sherman, Connecticut 06784
REMOVAL OF ASBESTOS-CONTAINING MASTIC at The Sherman School 2 Route 37 East Sherman, Connecticut 06784 OWNER: Town of Sherman 9 Route 39 North P.O. Box 39 Sherman, Connecticut 06784 (860)355-1139 State
More informationMount Sinai Pediatric Environmental Health Specialty Unit WTC Asbestos Fact Sheet
This fact sheet answers frequently asked health questions (FAQs) about asbestos. It is part of a series of fact sheets describing potential health risks to children from exposures related to the World
More informationIWU PHYSICAL PLANT SAFETY PROGRAM. Toxic and Hazardous Substances, Title 29 Code of Federal Regulations (CFR) Part 1910.1001, Subpart Z Asbestos
STANDARDS Toxic and Hazardous Substances, Title 29 Code of Federal Regulations (CFR) Part 1910.1001, Subpart Z Asbestos 1. INTRODUCTION IWU has a responsibility to provide a safe environment for students,
More informationEVALUATION OF MSHA S HANDLING OF INSPECTIONS AT THE W.R. GRACE & COMPANY MINE IN LIBBY, MONTANA MINE SAFETY AND HEALTH ADMINISTRATION
EVALUATION OF MSHA S HANDLING OF INSPECTIONS AT THE W.R. GRACE & COMPANY MINE IN LIBBY, MONTANA MINE SAFETY AND HEALTH ADMINISTRATION REPORT NO.: 2E-06-620-0002 REPORT ISSUED: March 22, 2001 TABLE OF CONTENTS
More informationGUIDANCE DOCUMENT (redline version 2.0, released 01/30/09) on amended Industrial Code Rule 56(ASBESTOS) Page 1 of 88
1 1. 2 (b ) Purpose and Intent. This Section indicates that these regulations include those who supervise and employ persons employed in all aspects of an asbestos project. Does this statement include
More informationSPECIFICATION DIVISION 2 NUMBER SECTION DESCRIPTION DIVISION 02 EXISTING CONDITIONS SECTION 028215 ASBESTOS REMEDIATION ROOFING MATERIAL
ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION
More informationAsbestos in Soil Who Knew? A Consulting Perspective 1 st Annual Southeast Brownfields Association
Asbestos in Soil Who Knew? A Consulting Perspective 1 st Annual Southeast Brownfields Association Presented by: Russell E. Stauffer, PE AMEC Environment & Infrastructure, Inc. October 30, 2014 75 East
More informationthe risks of removing asbestos containing drywall October 29, 2011
Summary of recent research about the risks of removing asbestos containing drywall joint compound during residential renovation Presented by David Redmond October 9, 011 Some background information about
More informationASBESTOS MANAGEMENT PROGRAM RISK MANAGEMENT AND SAFETY 2014 Page 1
ASBESTOSS MANAGEMENT PROGRAM RISK MANAGEMENT AND SAFETY 2014 1 TABLE OF CONTENTS 1.0 INTRODUCTION 4 1.1 Policy 4 1.2 Purpose 4 1.3 Scope and Application 4 2.0 EMERGENCY CONTACT INFORMATION 4 2.1 Asbestos
More informationGuidelines of Best Management Practices for the Operation of Post Consumer (Tear 0ff) Asphalt Shingle Recycling Facilities
Guidelines of Best Management Practices for the Operation of Post Consumer (Tear 0ff) Asphalt Shingle Recycling Facilities The purpose of this document is to provide potential recyclers/processors with
More informationASBESTOS MANAGEMENT AND OPERATING PLAN FOR MCCONNELL AIR FORCE BASE
ASBESTOS MANAGEMENT AND OPERATING PLAN FOR MCCONNELL AIR FORCE BASE LAST UPDATE 2003 TABLE OF CONTENTS TABLE OF CONTENTS... 1 GLOSSARY OF TERMS... 4 LIST OF ACRONYMS... 7 LIST OF REFERENCES... 9 1.0 INTRODUCTION...
More informationOREGON STATUTES : (3) OREGON REVISED STATUTES: CHAPTER 654: OCCUPATIONAL SAFETY AND HEALTH
OREGON STATUTES : (3) OREGON REVISED STATUTES: CHAPTER 654: OCCUPATIONAL SAFETY AND HEALTH TITLE 36: PUBLIC HEALTH AND SAFETY CHAPTER 431: STATE AND LOCAL ADMINISTRATION AND ENFORCEMENT OF HEATLH LAWS
More informationASBESTOS CONTROL PLAN
ASBESTOS CONTROL PLAN POLICY It is the long term plan of Emily Carr University to have an asbestos free workplace. In the interim, The University plans to manage asbestos hazards based on prioritization
More informationAHERA 3-Year Asbestos Re-Inspection
AHERA 3-Year Asbestos Re-Inspection Denver 940 Fillmore Street Denver, Colorado 80206 Report Date: November 20, 2013 OEI Project No. 13.159 Prepared For: John Lewis Denver 940 Fillmore Street Denver, CO