1 1/1/13 INDIANA DEPARTMENT OF TRANSPORTATION QUALIFIED LABORATORY AND TECHNICIAN PROGRAM The purpose of the Qualified Laboratory and Technician Program is to establish policies, procedures, and guidelines to assure that quality materials and construction practices are incorporated into all Department contracts. The Qualified Laboratory and Technician Program applies to all personnel conducting acceptance sampling and testing procedures. The primary objective of the Qualified Laboratory and Technician Program is to establish programs that assure the Acceptance Personnel are capable of conducting the appropriate sampling and testing procedures correctly. Obtaining this objective will assure that maximum quality control and superior highway materials are incorporated into the completed highway infrastructure. To accomplish the goals of the program, the Department will provide the following: 1. The Department Office of Materials Management Laboratory will maintain AASHTO Accreditation. 2. The Office of Materials Management Laboratory will conduct on-site inspections in the District laboratories to assure the performance of the test equipment and the qualification of the District Laboratory technicians. 3. The Office of Materials Management Laboratory will conduct on-site inspections in the District Production laboratories to assure the performance of the test equipment and the laboratories capability to conduct the testing. 4. The Office of Materials Management Laboratory will maintain a sample proficiency program with the District and Production laboratories to ensure uniformity of test results. 5. The Department will give written examinations to assess the knowledge of each sampling and testing procedure. 6. The Department will review proficiencies for each of the sampling and testing procedures. 7. The Department will maintain the related programs consisting of the Independent Assurance Program, the Certified Aggregate Producer Program (ITM 211), the Certified Hot Mix Asphalt Producer Program (ITM 583), the Certified Precast Concrete Producer Program (ITM 813), the Certified Precast Prestressed Concrete Producer Program (ITM 814), and their respective audit programs. The Indiana Qualified Laboratory and Technician Program has been developed in accordance with the provisions of Federal Regulations 23 CFR 637, Subpart B, entitled Quality Assurance Procedures for Construction. 1 of 7
2 Terminology AASHTO. American Association of State Highway and Transportation Officials Acceptance Program. The procedures of the Department for the determination of the quality and conformity to the contract specifications Acceptance Personnel. Representatives of the Department, Contractor, Producer, Consultant, or Local Public Agency who conduct contract specific sampling or testing of materials or products for compliance with the contract requirements. Personnel include Project Engineers, Project Supervisors, technicians, and seasonal employees. ACI. American Concrete Institute ASTM. American Society for Testing and Materials Certified Technicians. Industry representatives who have successfully completed the requirements of the Aggregate, Hot Mix Asphalt, Concrete, or ACI Level I Concrete Training Programs Independent Assurance Program. The verification of the sampling and testing procedures used in the acceptance program which are conducted by a Department technician but are not used as part of the acceptance of any contract materials or products. Laboratory Proficiency Samples. Homogeneous samples prepared by the Office of Materials Management that are distributed and tested by multiple laboratories. The test results are compared to assure the laboratories are obtaining similar results. Materials Services Section. Section within the Office of Materials Management responsible for providing technical and quality control guidance for maintaining the Office of Materials Management AASHTO Accreditation and District Testing functions Qualified Laboratories. Laboratories that have demonstrated the capability of conducting standard practices for material testing as determined by AASHTO, ASTM, or the Department Qualified Technicians. Individuals who have successfully completed the requirements of the Indiana Department of Transportation Qualified Laboratory and Technician Program Proficiency Test. Testing by the technician to demonstrate proficiency in sampling materials and conducting tests Written Examination. The initial portion of the Qualified Technician Program required for acceptance sampling and testing procedures. 2 of 7
3 Qualified Laboratory and Technician Program Panel The State Materials Engineer will chair a Qualified Laboratory and Technician Program Panel which is responsible for the development of the program, the approval of the program and guidelines, the development of training criteria, the development of the written examination, the development of proficiency testing guidelines, the development of a database for each technician, and the de-qualification or other appropriate actions regarding laboratories or personnel. The panel will consist of the State Materials Engineer Materials Services Engineer, State Construction Engineer, a District Testing Engineer, and a District Construction Engineer. Qualified Laboratory Program The Department Qualified Laboratory Program consists of maintaining AASHTO Accreditation of the Office of Materials Management Laboratory, the developing and maintaining laboratory inspections and laboratory sample exchanges with the District Testing laboratories and District Production laboratories, and the developing and maintaining laboratory inspections for laboratories meeting the requirements of the Certified Aggregate Producer Program, the Certified Hot Mix Asphalt Producer Program, the Certified Precast Concrete Producer Program, or the the Certified Precast Prestressed Concrete Producer Program. The AASHTO Materials Reference Laboratory (AMRL) provides technical support and administrative coordination for the AASHTO Accreditation Program. AMRL provides laboratory assessment, quality system evaluations, and proficiency testing samples for laboratories testing soils, asphalt binders, emulsified asphalt, hot mix asphalt, paint, and aggregates. Similar services are offered by the Cement and Concrete Reference Laboratory (CCRL) for laboratories testing hydraulic cement, pozzolons, portland cement concrete, reinforcing steel, and masonry units. The AASHTO Accreditation Program requires that all laboratories participate in the on-site inspection program. The Office of Materials Management is assessed by AMRL and CCRL on a frequency of approximately 24 months. The assessment includes an on-site inspection and a Quality System review. The assessors evaluate the apparatus and procedures used to conduct physical tests to determine if the laboratory Quality System is consistent with that specified by the Quality System Manual. At the completion of the inspection, the assessor summarizes the findings and notes any deficiencies regarding corrective action. The laboratory is required to provide AMRL or CCRL with satisfactory evidence that all deficiencies have been corrected within 90 days of the issuance of the final report. The AASHTO Accreditation Program requires that all laboratories participate in the applicable proficiency sample proficiency program. The Office of Materials Management participates in all applicable sample proficiencies offered by AMRL and CCRL. When laboratory test results are beyond two standard deviations of the grand average values, the laboratory is required to determine the reason for the discrepancy and report the corrective action taken within 60 days of the issuance of the final report. 3 of 7
4 The Department on-site inspection program requires that an Office of Materials Management representative audit the District and Production laboratories annually. The laboratories are required to present all testing equipment to assess their dimensional and functional requirements. The laboratories are required to conduct all of the tests being done at that particular facility. The equipment and procedural presentations are evaluated and documented. When deficiencies are noted, a review of the deviation from the test method will be made to include a discussion of possible corrective actions. Each laboratory is required to maintain a Quality Control System manual and to document that all equipment has been calibrated and verification records are maintained. The Materials Services Section will audit the Department laboratories for performance graded binder, emulsified asphalt, hot mix asphalt, soil, portland cement concrete, and aggregates. All documentation of the audits is retained in the Materials Services Section. The Office of Materials Management will fabricate laboratory proficiency samples for distribution to the District and Production laboratories. The District and Production laboratories will be supplied with directives on testing procedures, data documentation, and any other required information for the proficiency samples. The Production laboratories are required to have technicians qualified under this Program conduct all laboratory sample proficiency testing. The Materials Services Section will analyze the results of the laboratory proficiency for program compliance. All laboratory proficiency sample program documentation will be retained by the Materials Services Section. Industry laboratories which have been approved by the Department under the requirements of the Certified Aggregate Producer Program or the Certified Hot Mix Asphalt Producer Program are initially qualified to conduct sampling and testing for acceptance of materials. Continual evaluation of the quality conformance of the laboratories will be done by the Department during the annual Certified Aggregate or Certified Hot Mix Asphalt Plant audits. Any deficiencies noted during these reviews will be administered by the appropriate program and resolved within 10 days. Industry laboratories which have been approved by the Department as Geotechnical Consultants are initially qualified to conduct sampling and testing for acceptance of B Borrow or structure backfill. Continual evaluation of the quality conformance of the laboratories is done by assessments and proficiency sample programs by AMRL. Deficiencies from the assessment of the laboratory test procedures or deficiencies of the proficiency samples are required to be corrected. Industry laboratories which have been approved by the Department under the requirements of the Certified Precast Concrete Producer Program are initially qualified to conduct sampling and testing for acceptance of materials by the American Concrete Pipe Association (ACPA), the National Precast Concrete Association (NPCA) or Precast/Prestressed Concrete Institute (PCI) Certification Programs. Continual evaluation of the quality conformance of the laboratories is done by the ACPA or NPCA during the annual audits. Any deficiencies noted during these reviews is administered by the appropriate program and resolved within 30 days. 4 of 7
5 Acceptance Personnel The Qualified Technician Program is applicable to Department Construction, Department Testing, Contractor, Producer, Consultant, or Local Public Agency technicians. Representatives include Project Engineers, Project Supervisors, technicians, and seasonal employees that are involved in the acceptance process for any contract. The Contractor, Producer, Local Public Agency, or Consultant is responsible for providing adequate training to their employees, coordinating with the Districts to schedule the written examinations, and notifying the respective District Testing Engineer when personnel need proficiency testing. Certified Aggregate Technicians, and Certified Asphalt Technicians are not required to take the written exam to become a Qualified Technician. Proficiency testing is required and will be evaluated by the Independent Assurance Program. Industry representatives, other than Certified Technicians, who conduct sampling and testing used for acceptance of materials or products are required to complete the written examination and proficiency testing as described in the Qualified Technician Program. Qualified Technician Program The Qualified Technician Program is maintained for aggregates, hot mix asphalt, portland cement concrete, soils, and special testing. Technician qualification requires an initial written examination and subsequent proficiency testing at least once every three years. Acceptance Personnel are required to be qualified in each area designated by the requirement of their job duties. For Department employees, voluntary classroom training is provided prior to the written examinations. The written examinations or proficiency testing will detail the applicable AASHTO, ASTM, or Indiana Test Method requirements and will include the procedures for the sampling, testing, frequencies, and documentation of test results. Written examinations are provided to the Acceptance Personnel when requested. If a failure of the written examination occurs, a re-examination will be allowed; however, the exam may not be taken within 24 hours of the original examination. The Acceptance Personnel will be given the opportunity to review applicable test requirements prior to the re-examination. If a failure of the re-examination occurs, the Department will forward the results to the appropriate District Testing Engineer or District Construction Engineer for subsequent actions in accordance with the Non-Conforming Examination requirements, stated hereafter. The individual will not be allowed to conduct contract acceptance sampling or testing for those specified procedures that were failed. 5 of 7
6 Written examinations are conducted as required for all Acceptance Personnel who have not been reviewed for proficiency within a three year period, new employees, or those individuals needing qualifications in additional testing areas. The date recorded to designate the beginning of the three year period for the written examination will be January 1 st of the year that the individual passed the examination. Proficiency testing will only be given after the Acceptance Personnel have passed the written examination. Proficiency testing and the evaluation of equipment applicable to either sampling or testing procedures is to be monitored through the Independent Assurance Program at least once every three years. A procedural checklist will be followed to ensure uniformity during the proficiency test, and the results will be documented. Acceptance Personnel are responsible for keeping their proficiency requirements current. If a failure of the proficiency test occurs, a re-test will be given immediately after a review of the applicable test procedures. If a failure of the re-test for proficiency occurs, the Department will forward the results to the appropriate District Testing Engineer or District Construction Engineer for subsequent actions in accordance with the Non-Conforming Proficiency requirements, stated hereafter. The individual will not be allowed to conduct contract acceptance sampling or testing for those specified procedures that were failed. The District Testing Engineers and the District Construction Engineers are responsible for the administration of the written examinations and the applicable proficiency testing for all Acceptance Personnel. The Office of Materials Management is responsible for developing and maintaining a database system of all individuals who have successfully completed the written examinations and proficiency testing for each required specified sampling or testing procedure. Non-Conforming Examinations or Proficiency If a Department employee fails the follow-up examination or proficiency, the individual will not be allowed to conduct sampling or testing used for contract acceptance. If a Non-Department employee fails the follow-up examination or proficiency test, the individual will not be allowed to conduct sampling or testing procedures used for contract acceptance. Applicable training to the satisfaction of the Qualified Laboratory and Technician Program Panel will be demonstrated and subsequent passing the written examination and proficiency test will be required for the individual to become a Qualified Technician. Unqualified Personnel Conducting Acceptance Sampling or Testing If a Department employee knowingly conducts acceptance sampling or testing and has not been qualified in accordance with the Qualified Laboratory and Technician Program, the individual may be subject to disciplinary actions as deemed appropriate by the Qualified Laboratory and Technician Program Panel and the Human Resources Division. 6 of 7
7 If a Non-Department employee knowingly conducts acceptance sampling or testing and has not been qualified in accordance with the Qualified Laboratory and Technician Program, the individual s employer and the Department Contract Administration Division will be notified. 7 of 7
Quality Assurance Procedures for Construction and Materials Sampling and Testing 14
Page 1 Quality Assurance Procedures for Construction and Materials Sampling and Testing 14 1. PURPOSE 1.1 To prescribe policies, procedures, and guidelines to assure the quality of materials on all Colorado
Quality Assurance Program for Design-Bid-Build Projects. January 2016. 2016 by Texas Department of Transportation 512/506-5802 All Rights Reserved
Quality Assurance Program for Design-Bid-Build Projects January 2016 2016 by Texas Department of Transportation 512/506-5802 All Rights Reserved TABLE OF CONTENTS SECTION 1 - INTRODUCTION... 4 1.1 Overview...
Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS
Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS 8.1.1 PURPOSE This procedure provides guidelines related to the implementation of quality control and quality assurance
QUALITY ASSURANCE PROGRAM (QAP) City Rohnert Park
QUALITY ASSURANCE PROGRAM (QAP) City Rohnert Park The purpose of this program is to provide assurance that the materials incorporated into the construction projects are in conformance with the contract
The ABA Certification Program. Procedures Manual for the Certification of Construction Materials Testing Laboratories
The ABA Certification Program Procedures Manual for the Certification of Construction Materials Testing Laboratories January 2015 Foreword Around the world, certification has become a definitive requirement
Section 100 Contractor Quality Control Program
7/21/2014 AC 150/5370-10G Section 100 Contractor Quality Control Program 100-01 General. When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and
CHAPTER 2 AGGREGATE TECHNICIAN TRAINING AND QUALIFICATION PROGRAM
CHAPTER 2 AGGREGATE TECHNICIAN TRAINING AND QUALIFICATION PROGRAM 2.1 PURPOSE... 2-1 2.2 BACKGROUND.. 2-1 2.3 QUALIFICATION REQUIREMENTS BY JOB FUNCTION.. 2-1 2.3.1 Aggregate Testing Technician. 2-1 2.3.2
Section 5.6 QUALITY CONTROL PROGRAM
5.6.1 PURPOSE Section 5.6 QUALITY CONTROL PROGRAM This document describes activities for personnel who are involved with the Florida Department of Transportation s (Department) Quality Control (QC) Program,
5.2.7.4 CONCRETE: CONTRACTOR S QUALITY CONTROL PLAN
5.2.7.4 CONCRETE: CONTRACTOR S QUALITY CONTROL PLAN NOTE: This document is generally written in the imperative mood. The subject, "the Contractor" is implied. Also implied in this language are "shall",
Inspections: Central Laboratory of the Regions
Page 1 Inspections: Central Laboratory of the Regions Protocol for Open Laboratory Review of a CDOT Materials Testing Laboratory Protocol for the Inspection of Region Materials Laboratories by the Central
CITY & COUNTY OF DENVER COMMUNITY PLANNING & DEVELOPMENT BUILDING PERMIT POLICY Special Inspector Qualification Michael Roach, P.E., Building Official
Reference: IBC Chapter 17, Section 1704 General: Special inspections required by IBC Chapter 17 shall be conducted by qualified persons working for an approved agency. The Building Official shall maintain
Building Code of New York State
Welcome Christopher R. Paolini, P.E., Sr. Vice President CME Associates, Inc. 6035 Corporate Drive East Syracuse, New York 13057 (315) 701-0522 (315) 701-0526 (Fax) [email protected] 1 Building
C. Section 014510 TESTING LABORATORY SERVICE.
SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,
Quality Assurance Program. June 2005 2005 by Texas Department of Transportation (512) 416-2055 all rights reserved
Quality Assurance Program June 2005 2005 by Texas Department of Transportation (512) 416-2055 all rights reserved Quality Assurance Program June 2005 Manual Notices Manual Notice 2005-1To: Users of the
Construction Management Program
Use and Limitation: The Sponsor may use this document as a guide in preparing a construction management program for their specific project. Sponsors and Consultants are cautioned that the provision of
Project Procedures Guide. Sampling Frequencies for Materials Testing and Inspection
Project Procedures Guide Sampling Frequencies for Materials Testing and Inspection PREFACE This Project Procedures Guide is intended for use as a resource in determining reasonable sampling frequencies
VDOT GOVERNANCE DOCUMENT
VDOT GOVERNANCE DOCUMENT Minimum Requirements for Quality Assurance and Quality Control on Design Build and Public-Private Transportation Act Projects Location and Design Division Alternate Project Delivery
CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES
1.0 SCOPE CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES This document establishes the minimum quality program requirements for a contractor providing equipment, material, and construction
CONSTRUCTION INSPECTOR CERTIFICATION PROGRAM
CONSTRUCTION INSPECTOR CERTIFICATION PROGRAM COLORADO DEPARTMENT OF TRANSPORTATION COURSE CATALOG 2011 October 27, 2010 Table of Contents CHIEF ENGINEERS POLICY MEMO #25... 2 CERTIFICATION: BASIC HIGHWAY
Georgia Department of Transportation. Office of Materials and Research. Standard Operating Procedure (SOP) 19
Laboratory SOP 19 Revised July 1, 2003 Georgia Department of Transportation Office of Materials and Research Standard Operating Procedure (SOP) 19 This Standard Operating Procedure provides a means whereby
SECTION 03400 PRECAST CONCRETE STRUCTURES
SECTION 03400 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for precast concrete structures, including fabrication and erection. 1.02 REFERENCE STANDARDS A. American Society for
Contractor s Statement of Responsibility for Seismic-Force-Resisting Systems This form is to be filled out by the contractor.
SPECIAL INSPECTION PROCEDURE IBC CHAPTER 17 2012 EDITION When Required All projects that require a SC licensed Architect or Engineer per SC Architectural and Engineering registration law. Overview The
Work Type Definition and Submittal Requirements
Work Type: Highway Materials Testing Geotechnical Laboratory Testing, Geotechnical Laboratory Testing, Standard Penetration (SPT) & Rock Coring, Cone Penetration Test, Solid Stem Auger Drilling, and Materials
DMS - 7310 REINFORCED CONCRETE PIPE AND MACHINE-MADE PRECAST CONCRETE BOX CULVERT FABRICATION AND PLANT QUALIFICATION
DMS - 7310 REINFORCED CONCRETE PIPE AND MACHINE-MADE PRECAST CONCRETE BOX CULVERT FABRICATION EFFECTIVE DATE: APRIL 2012 7310.1. Description. This specification will govern for the fabrication of machine-made
Example Specification for Concrete using Current Building Code Requirements
Example Specification for Concrete using Current Building Code Requirements DISCLAIMER: This specification is an example that accompanies a seminar titled The P2P Initiative: Performance-based Specs for
STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.
STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA October 21, 2011 888.01 General 888.02 Materials 888.03 Concrete Proportioning 888.04
NIST HANDBOOK 150-5 CHECKLIST CONSTRUCTION MATERIALS TESTING
NIST HANDBOOK 150-5 CHECKLIST CONSTRUCTION MATERIALS TESTING Instructions to the Assessor: This checklist addresses specific accreditation criteria prescribed in NIST Handbook 150-5, Construction Materials
1 RCNY 101-06 CHAPTER 100. (a) Definitions. For the purposes of this chapter, the following terms will have the following meanings:
1 RCNY 101-06 CHAPTER 100 Subchapter A Administration 101-06 inspectors special inspection agencies. (a) Definitions. For the purposes of this chapter, the following terms will have the following meanings:
Table of Contents. Introduction and Purpose... 3. Technician Certification Programs... 4
November 2015 Table of Contents Introduction and Purpose... 3 Technician Certification Programs... 4 Program Administration... 4 Required Experience... 5 Training Programs... 6 Waivers for Experience...
NRMCA Quality Certification. Ready Mixed Concrete Quality Management System. Certification Criteria Document
NRMCA Quality Certification Ready Mixed Concrete Quality Management System Certification Criteria Document Version 1 February 2014 NRMCA Quality Certification Ready Mixed Concrete Quality Management System
Contractor s Quality Program Manual
Contractor s Quality Program Manual March 2015 ILLINOIS STATE TOLL HIGHWAY AUTHORITY The CONTRACTOR S QUALITY PROGRAM MANUAL dated March 2015 replaces the previous version dated March 2014. Major Highlight
THERMAL INSULATION MATERIALS
NIST HANDBOOK 150-15 2006 Edition National Voluntary Laboratory Accreditation Program THERMAL INSULATION MATERIALS Lawrence I. Knab National Voluntary Laboratory Accreditation Program Standards Services
SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
AMERICAN CONCRETE INSTITUTE. Certification Policies for Concrete Field Testing Technician B Grade I
AMERICAN CONCRETE INSTITUTE Certification Policies for Concrete Field Testing Technician B Grade I Approved by the ACI Board of Direction October 29, 1992 Last revised by the Certification Programs Committee
QUALITY ASSURANCE PROGRAM
QUALITY ASSURANCE PROGRAM (Revised December, 2009) TABLE OF CONTENTS I. Overview..1 II. III. IV. Roles and Responsibilities...5 Laboratory Certification Program 7 Technician Certification Program...10
NEW YORK CITY DEPARTMENT OF DESIGN + CONSTRUCTION
NEW YORK CITY DEPARTMENT OF DESIGN + CONSTRUCTION April 2015 QUALITY ASSURANCE AND CONSTRUCTION SAFETY Operations Manual Bill de Blasio, Mayor Dr. Feniosky Peña-Mora, Commissioner Kevin F. Donnelly, Deputy
CHAPTER 2 AGGREGATE TECHNICIAN TRAINING AND QUALIFICATION PROGRAM
Topic No. 700-000-001 Construction Training and Qualification Manual Effective: July 1, 2002 Aggregate Technician Training and Qualification Program Revised: DRAFT May 6September 3, 2008 CHAPTER 2 AGGREGATE
Adopting Disaster Resilient Construction at the Local Level
Adopting Disaster Resilient Construction at the Local Level Sponsored by The Concrete Joint Sustainability Initiative (CJSI) Presenter Biographies August 2012 Dean Frank, P.E., LEED GA Dean Frank is Director
CHAPTER 4 CONCRETE TRAINING AND QUALIFICATIONPROGRAM
Concrete Training Qualification Program Topic No. 700-000-001 Effective: July 1, 2002 Construction Training and Qualification Manual Revision: March 22, 2011 Concrete Training and Qualification Program
MID-ATLANTIC REGION TECHNICIAN CERTIFICATION PROGRAM. Maryland State Highway Administration Technician Certification Renewal Policy January 2006
MID-ATLANTIC REGION TECHNICIAN CERTIFICATION PROGRAM Technician Certification Renewal Policy Mid-Atlantic Region Technician Certification Program Technician Certification Renewal Policy Table of Contents
CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1
CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1 1 This Chapter of the FERC Engineering Guidelines has been prepared under contract with R & H Thomas, Inc. JANUARY 1993 Chapter VII Construction
UL Qualified Firestop Contractor Program Requirements April 2012
UL Qualified Firestop Contractor Program Requirements April 2012 For more information, please contact your local UL Field Representative INTRODUCTION: In order for a firestop systems installer/contractor
Chapter 4: Contractor Quality Control
Chapter 4: Contractor Quality Control Seattle District, NWS Last updated: 05FEB14 Chapter 4 Contractor Quality Control 1. GENERAL. Contractor is responsible for quality control and shall establish and
Quality Management Plan
September 8, 2015 NYNJ LINK DEVELOPER LLC Revision 0 Developer s Maintenance and Control Facility Elizabeth, NJ Parsons Project No.: 648109 & 449252 This page intentionally left blank. This page intentionally
Laboratory and Technician Certification. by Nabil Kamel, M.A.Sc., P.Eng. CCIL Program Manager
Laboratory and Technician Certification by Nabil Kamel, M.A.Sc., P.Eng. CCIL Program Manager Laboratory and Technician Certification Table of contents What is lab certification? Why lab certification?
1 RCNY 101-07 CHAPTER 100
1 RCNY 101-07 CHAPTER 100 Subchapter A Administration 101-07 Approved Agencies. (a) Definitions. For the purposes of this section, all terms used herein shall have the same meanings as set forth in the
Acceptance Codes APPENDIX - A. Acceptance Criteria
1111 Receipt of a satisfactory Test Report from WSDOT Materials Laboratory is required indicating the lot (or lots) or batch of material meets the requirement of the specifications under which it is listed.
Section 1. The title of Section 101-07 of Subchapter A of Chapter 100 of Title 1 of the Rules of the City of New York is amended to read as follows:
Section 1. The title of Section 101-07 of Subchapter A of Chapter 100 of Title 1 of the Rules of the City of New York is amended to read as follows: 101-07 [Inspections and] [a] Approved [a] Agencies.
MATERIALS CERTIFICATION SCHOOLS
MATERIALS CERTIFICATION SCHOOLS 2011, Virginia Department of Transportation Registration Process Online Registration Enrollment and payment for all personnel in the Materials Certification Schools may
LOCAL PUBLIC AGENCY (LPA) QUALITY ASSURANCE PROGRAM
Certified LPA Field Tested Materials LOCAL PUBLIC AGENCY (LPA) QUALITY ASSURANCE PROGRAM (Revised February 2015) TABLE OF CONTENTS I. Overview..1 II. III. IV. Roles and Responsibilities...5 Laboratory
ADMINISTRATIVE MANUAL FOR CONSTRUCTION TECHNICIAN TRAINING AND CERTIFICATION LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
ADMINISTRATIVE MANUAL FOR CONSTRUCTION TECHNICIAN TRAINING AND CERTIFICATION LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT Louisiana Transportation Research Center Louisiana Department of Transportation
MID-ATLANTIC REGION TECHNICIAN CERTIFICATION PROGRAM
MID-ATLANTIC REGION TECHNICIAN CERTIFICATION PROGRAM Maryland State Highway Administration Technician Certification Program Training / Testing Information January, 2015 Table of Contents Introduction..
ACCEPTANCE CRITERIA FOR QUALITY DOCUMENTATION (AC10) June 2014
ACCEPTANCE CRITERIA FOR QUALITY DOCUMENTATION (AC10) 1.0 INTRODUCTION June 2014 1.1 Purpose: The purpose of this acceptance criteria is to establish requirements for information that is provided to ICC-ES
Office of Construction and Innovative Contracting Technical Certification Unit. Technical Certification Handbook 2016
Office of Construction and Innovative Contracting Technical Certification Unit Technical Certification Handbook 2016 Updated September 2015 For Your Information REGISTRATION Registration opens October
Standard for GDOT Hot Mix Asphalt Technician Training and Qualification Program. Developed from AASHTO DESIGNATION: R 25-00.
Standard for Developed from AASHTO DESIGNATION: R 25-00 Table of Contents 1. SCOPE AND LIMITATION 2. REFERENCE DOCUMENTS 3. INTRODUCTION 4. PROGRAM ORGANIZATIONAL STRUCTURE AND MANAGEMENT 5. TRAINING AND
SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE
Community Development Permit Services SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE PROJECT NAME PROJECT ADDRESS PERMIT NUMBER CITY RECEIVED STAMP AND INITIALS Instructions: BEFORE
The quality and uniformity of ready mixed concrete
The New NRMCA Quality Certification Program Why should companies have a quality management system? by Karthik H. Obla and Colin L. Lobo The quality and uniformity of ready mixed concrete delivered to a
MATERIALS CERTIFICATION SCHOOLS
MATERIALS CERTIFICATION SCHOOLS Registration Process Online Registration Enrollment and payment for all personnel in the Materials Certification Schools must be done online through the VDOT University
NorthEast Transportation Training and Certification Program (NETTCP) Course Registration Form
(NETTCP) Course Registration Form Interim Certification (Cost $300 members / $425 non-members) HMA Plant Technician* HMA Paving Inspector* Soils & Aggregate Inspector* Soils & Aggregate Lab Technician*
2. Performance Test Schedule and Certificates. 2.1 Definitions
2. Performance Test Schedule and Certificates 2.1 Definitions 2.1.1 Unit shall mean the complete Power Station Assembly/Unit as defined in the Agreement (which consists of equipment provided by Contractor
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
The IP3 accreditation process. Bob Hart Chief Assessor September 2008
Pr The IP3 accreditation process Bob Hart Chief Assessor September 2008 Stages of assessment 1. Association responds to the guidelines in the form of a self evaluation 2. Consultation on Panel membership
EVALUATION AND ACCREDITATION OF SUPPLIER TEST FACILITIES GP 10
EVALUATION AND ACCREDITATION OF SUPPLIER TEST FACILITIES GP 10 EVALUATION AND ACCREDITATION OF TESTING FACILITIES USED BY SUPPLIER OF MATERIALS TO GENERAL MOTORS PREFACE TO GP-10 General Motors expects
Pennsylvania Asphalt Improvement Network (PASIN) Hot Mix Asphalt Industry Baseline Assessment Report. December 2006
Pennsylvania Asphalt Improvement Network (PASIN) Hot Mix Asphalt Industry Baseline Assessment Report December 2006 Table of Contents INTRODUCTION... 4 SECTION 1: EXECUTIVE SUMMARY... 4 1. Methodology...4
Concrete Technician Certification Program
Concrete Technician Certification Program FIELD TECHNICIANS Initial Certification Requirements, Recertification Requirements and Application Procedures Publication 536 November 2013 Pennsylvania Department
NVLAP Assessor Training. Assessor Qualification & Training Requirements
NVLAP Assessor Training Assessor Qualification & Training Requirements References ISO/IEC 17011: Conformity assessment General requirements for accreditation bodies accrediting conformity assessment bodies
MATERIALS CERTIFICATION SCHOOLS 2016
MATERIALS CERTIFICATION SCHOOLS 2016 2014, Virginia Department of Transportation Registration Process Online Registration Enrollment and payment for all personnel in the Materials Certification Schools
QUALITY ASSURANCE MANUAL JPM OF MISSISSIPPI, INC.
QUALITY ASSURANCE MANUAL JPM OF MISSISSIPPI, INC. Hattiesburg, MS Revision E 01/19/11 Revised to ISO 9001:2008 on July 9, 2009 JPM OF MISSISSIPPI, INC. MANAGEMENT QUALITY POLICY It is the goal of JPM of
Section 000 Organization of an Engineering District (Construction)
Table of Contents 1. General Policies and Provisions... 000-1 2. District Executive... 000-2 3. Assistant District Executive Design... 000-3 4. Assistant District Executive Maintenance... 000-4 5. Assistant
How DCMA Helps To Ensure Good Measurements
How DCMA Helps To Ensure Good Measurements Speaker/Author: Robert Field Defense Contract Management Agency 605 Stewart Avenue Garden City, New York 11530 Email: [email protected] Phone: (516) 228-5886;
Quality Assurance QUALITY ASSURANCE PLAN
Revision 2 Page 1 of 40 QUALITY ASSURANCE PLAN PLAN APPROVALS: Jeff Shouse Signature on File DIRECTOR OF QUALITY ASSURANCE DIRECTOR OF QUALITY ASSURANCE (signature) DATE Rodney Baltzer Signature on File
Quality Manual Printed copy valid for 24 hours from time of printing unless stamped CONTROLLED COPY in red. Page
Quality Manual Page 1 of 20 Change Log Document Revision Date Description of Change 15/04/09 Initial Release Page 2 of 20 1.0 Scope and Exclusions Scope This Quality Manual contains policies that have
6 QUALITY CONTROL PROCEDURES
6 QUALITY CONTROL PROCEDURES Producer Personnel Management Representative Certified Asphalt Technicians Qualified Technicians Reference Publications Field Laboratory Test Equipment Calibration Diary Materials
NRC INSPECTION MANUAL INSPECTION PROCEDURE 88045
NRC INSPECTION MANUAL INSPECTION PROCEDURE 88045 NMSS/FCSS EFFLUENT CONTROL AND ENVIRONMENTAL PROTECTION PROGRAM APPLICABILITY: 2600 88045-01 INSPECTION OBJECTIVES The objectives of this procedure are
QUALITY MANAGEMENT SYSTEM REQUIREMENTS
QUALITY MANAGEMENT SYSTEM REQUIREMENTS FOR TRADE CONTRACTORS 2014 400 Prince George s Blvd. Upper Marlboro, MD 20774 800.638.8556 HomeInnovation.com TABLE OF CONTENTS Introduction... iii Notes... iii
DESIGN-BUILD QUALITY MANAGEMENT PLAN OUTLINE
DESIGN-BUILD QUALITY MANAGEMENT PLAN OUTLINE DESIGN-BUILD PROJECT In developing its own QMP, the Design-Builder is encouraged to follow the organization and format of this QMP Outline. The Design-Builder
UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.00 10 (February 2010) Change 1-05/15 ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 45 01 (January 2008) UNIFIED FACILITIES
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
MATERIALS DIVISION MEMORANDUM
MATERIALS DIVISION MEMORANDUM GENERAL SUBJECT: Precast Concrete SPECIFIC SUBJECT: Quality Control Plan Review Check list; Approved list Nos. 26 and 34; Precast Repair Manual NUMBER: MD 286-06 DATE: December
Quality Management System for Ready Mixed Concrete Companies
Quality Management System for Ready Mixed Concrete Companies Parts A and B prepared by: William C. Twitty, Jr., P.E. Part C Developed by the NRMCA P2P Steering Committee Reviewed and Approved by the NRMCA
NC SBI QUALITY ASSURANCE PROGRAM
NC SBI QUALITY ASSURANCE PROGRAM for the SBI Reviewed by: Deputy Assistant Director Bill Weis Date: Approved by: Assistant Director Jerry Richardson Date: Originating Unit: SBI Effective Date: July 25,
RTP s NUCLEAR QUALITY ASSURANCE PROGRAM
RTP s NUCLEAR QUALITY ASSURANCE PROGRAM RTP operates under one quality program, whether you purchase products that are commercial grade, nuclear safety-related or industrial safety compliant (IEC 61508).
Quality Management Plan
6500m HOV Project Stage 1: A-4500 HOV Document Control No.: 0000000 3-November-2009 WOODS HOLE OCEANOGRAPHIC INSTITUTION WOODS HOLE, MA 02543 Document Control Sheet Date Originator Description 07-28-09
Chapter 22. Lump Sum Project Guidelines
Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11
CONCRETE MANUAL BASED ON THE 2015 IBC AND ACI 318-14 CONCRETE QUALITY AND FIELD PRACTICES GERALD B. NEVILLE, P.E.
CONCRETE MANUAL BASED ON THE 2015 IBC AND ACI 318-14 CONCRETE QUALITY AND FIELD PRACTICES GERALD B. NEVILLE, P.E. Concrete Manual: Based on the 2015 IBC and ACI 318-14 ISBN: 978-1-60983-618-4 Cover Design:
Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES
SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work
Guide Specification Precast Concrete Products
Guide Specification Precast Concrete Products This specificaton should be used only by qualified professionals who are competent to evaluate the significance and limiations of the specification and who
Certification. Septic Tank Contractors
Certification I. Certification Required Chapter 290-5-26-.17 provides for certification and de-certification of septic tank contractors, inspection personnel, pumpers, soil scientists and maintenance personnel.
ACIL POSITION PAPER PROCUREMENT AND EFFECTIVE PRACTICE OF CONSTRUCTION MATERIALS ENGINEERING AND TESTING SERVICES
Enhancing Public Health and Safety Through Quality Testing and Engineering ACIL POSITION PAPER PROCUREMENT AND EFFECTIVE PRACTICE OF CONSTRUCTION MATERIALS ENGINEERING AND TESTING SERVICES Construction