1 L E S S O N 2 Tracking Project Progress Suggested lesson time minutes Lesson objectives To begin tracking an active project, you will: a b c Modify the environment for tracking. You will use the Tracking Gantt Chart to modify the environment for tracking. Enter data for completed tasks. You will use the Update Tasks dialog box and the Tracking toolbar to enter data for completed tasks. Enter data for tasks in progress. You will use the Update Project dialog box and the Tracking toolbar to enter data for tasks in progress. 2-1

2 Microsoft Project 2000: Level 2 Ashbury Training a Modifying the Environment for Tracking As you enter information about a project's progress, the Gantt Chart reflects the progress of each task by displaying a thin, black bar in the center of the main task bar. The progress bar displays the completed percentage for each task. When the task is 100% complete, the progress bar extends the entire length of the task bar. The Tracking Gantt Chart displays a pair of bars for each task. The top bar of each pair represents the current schedule: red for critical and blue for noncritical. If the task is complete or in progress, Microsoft Project uses a darker color to represent the portion of the task that is complete. The bottom bar, which appears in gray, represents the original plan. The top bar changes to reflect changes in your schedule; the bottom bar doesn't change, so that you can always compare the current schedule to the original plan. Let's take a look at a project by using the Tracking Gantt Chart. Task A-1: Applying the Tracking Gantt Chart q Objective: To apply a view that best illustrates project progress. 1. Open the file C:\Student\Track Plan. A baseline plan has been set. 2. Choose View, More Views to display the More Views dialog box. 3. In the Views list box, select Tracking Gantt and click Apply. 4. Press [Alt][Home] to move to the start of the project. 5. Look at the two sets of Gantt bars. The Tracking Gantt view displays two sets of Gantt bars. The lower bars represent the baseline task dates, and the upper bars represent the current task dates. You can use this view to compare the baseline plan to the current plan. Changing the Current Date Microsoft Project uses the system date on your computer as the current date. In a project, you can view the current date line. It is a dotted vertical line marking the location of the current date. This line is displayed in the Gantt Chart, Resource Graph, and Resource Usage views. At some point, you may want to change the current date from within Microsoft Project. This allows you to analyze project data from any perspective. To change the current date: 1. Choose Project, Project Information. 2. In the Project Information dialog box, select the entry in the Current Date text box. 3. Type the date that you want to use as the current date. 4. Click OK or press [Enter]. 2-2

3 Ashbury Training Lesson 2: Tracking Project Progress Let's change the current date of a project. Task A-2: Changing the current date Tracking Gantt view is applied. 1. Choose Project, Project Information to display the Project Information dialog box. 2. Look at the Current Date text box. Microsoft Project displays today's date. 3. Change the date to 3/4/ Click OK to close the Project Information dialog box. 5. Press F5 to display the Go To dialog box. You can use this dialog box to quickly move to a specific task or date. 6. In the Date text box, type 3/4/03. Click OK. 7. Look at the line between 3/3/03 and 3/4/03. This line represents the current date, which is now in the middle of the project timeline. 2-3

4 Microsoft Project 2000: Level 2 Ashbury Training b Entering Data for Completed Tasks You have entered all of the information for each task, and you've created a baseline plan. As the project progresses, you will enter information about what happens in each task. By definition, a finished task has a % Complete value of 100. The task could have started and finished on- or off-schedule or changed duration. Tasks That Started and Finished on Schedule Microsoft Project provides you with some options for updating tasks. You can use the Tracking toolbar or the Update Tasks dialog box. To display the Tracking toolbar, choose View, Toolbars, Tracking. Figure 2-1 displays a copy of the Tracking toolbar and identifies the buttons on the toolbar. To display the Update Tasks dialog box, you can click the Update Tasks button which appears on the Tracking toolbar, or you can choose Tools, Tracking, Update Tasks. Figure 2-1: The Tracking toolbar. When a task is completed on schedule, the data in the Scheduled field are copied to the Actual field. To accomplish this, you can click the 100% Complete button on the Tracking toolbar, or enter 100% in the % Complete field of the Update Tasks dialog box. Once the percent complete is set to 100, you can change any of the Actual values and Microsoft Project will not recalculate them. Actual values that you enter are copied to the corresponding Current Start and Finish fields. Task B-1: Tracking a single task that started and finished on schedule Tracking Gantt view is applied. 1. Choose View, Toolbars, Tracking to display the Tracking toolbar. 2. Slowly drag the mouse pointer over the buttons on the Tracking toolbar to view the ScreenTips associated with each of the buttons. 3. If necessary, scroll back in the Gantt Chart to display task 3.Select task 3 (Interview Subject Matter Experts). 4. Look at the Gantt bars for task 3. The bars indicate that the task is on the critical path, a baseline has been set, and it is 0% complete. 5. On the Tracking toolbar, click the 100% Complete button to record that task 3 has been completed. A check mark appears in the Indicators column. Now, let's take a look at the Update Tasks dialog box. 6. Verify that task 3 is selected. On the Tracking toolbar, click the Update Tasks button to display the Update Tasks dialog box. 2-4

5 Ashbury Training Lesson 2: Tracking Project Progress 7. Notice that % Complete is 100% and that the Actual and Current Start and Finish dates are the same. 8. Click OK to close the Update Tasks dialog box. Practice Task 1. Mark task 4 (Search The Web) 100% complete. Tracking Multiple Tasks Now that you know how to track a single task that started and finished on schedule, let's track multiple tasks that started and finished on schedule. To save time when tracking tasks, you can update multiple tasks by selecting both tasks and clicking the appropriate button on the Tracking toolbar. Let's try it. Task B-2: Tracking multiple tasks that started and finished on schedule Tracking Gantt view is applied. Complete the Practice Task exercise at the end of Task B Drag to select tasks 6 and 7 (Create Outline and Present To Publisher). 2. Mark both tasks 100% complete. (On the Tracking toolbar, click the 100% Complete button.) 2-5

6 Microsoft Project 2000: Level 2 Ashbury Training 3. If necessary, click the Go To Selected Task button. Look at the change in the Gantt Chart. The bars that were once shaded blue to indicate a task are now solid blue to indicate the progress of the task. Also, task 5, which is a project summary task, now displays a summary progress bar underneath the summary bar. Tracking Tasks that Finished Off-Schedule For completed tasks that started or finished off-schedule, you must enter the actual date that deviated from the schedule in the Update Tasks dialog box. If the task started early or late, first enter the date the task started in the Actual Start text box. Microsoft Project moves the task to the actual start date. Then, to indicate that the task is finished, enter 100 in the % Complete text box. If the task finished early or late, then enter the date the task finished in the Actual Finish text box. Microsoft Project automatically marks any tasks with an Actual Finish date as 100% complete and sets the Remaining Dur text box to zero. If both Actual Start and Actual Finish dates differ from the schedule, enter the Actual Start date first, and then enter the Actual Finish date. If a task is behind schedule, you can update the project by rescheduling the remaining duration of the task. The easiest way to reschedule remaining duration is to click the Reschedule Work button on the Tracking toolbar. Rescheduling the remainder of a task has a different effect on tasks that have started than on tasks that have not started. If the task that you're rescheduling hasn't started, Microsoft Project moves the entire task to start on the current date. It automatically assigns a constraint of Start No Earlier Than (the current date). If the task that you're rescheduling is in progress, Microsoft Project moves the remaining duration of the task to start on the current date. It assigns a special constraint of Resume No Earlier Than (the current date). 2-6

7 Ashbury Training Lesson 2: Tracking Project Progress Task B-3: Tracking tasks that finished late Tracking Gantt view is applied. 1. Select task 8 (Revise Outline). 2. Display the Update Tasks dialog box. (On the Tracking toolbar, click the Update Tasks button.) 3. Under Actual in the Finish text box, type 2/5/03 to replace NA with a task finish date. 4. Click OK to close the Update Tasks dialog box. 5. Look at the Gantt bars for task 8. Notice how the subsequent tasks are effected. The actual finish dates have been extended. Practice Task 1. Mark task 9 (Subject Matter Experts Review) 100% complete. 2-7

8 Microsoft Project 2000: Level 2 Ashbury Training c Entering Actual Data for Tasks in Progress What's New: Use Network Diagram view A task that is in progress has an Actual Start date but no Actual Finish date and a % Complete greater than 0 and less than 100. You can indicate that a task has started by entering the start date in the Actual Start text box. Use this method if the Actual Start is different than the Planned Start. Using the Update Project Dialog Box When some aspects of a project occur as scheduled, you can use the Update Project dialog box to copy some or all of the information from the Scheduled text boxes to the Actual text boxes. In the Update Project dialog box, use the following options: If most tasks in your project are currently on schedule, select Entire Project. Enter exceptions in the Tracking table. For greater control over the tracking process, select one or more tasks and choose the Selected Tasks option. If you want Microsoft Project to calculate % Complete as a number oftasks that should be complete by the current date, select Set 0% 100% Complete. If you want Microsoft Project to enter an Actual Start value but you want to enter a value for % Complete yourself, select Set 0% or 100% Complete. An Actual Finish value is copied from the Scheduled Finish text box only if the Scheduled Finish date is earlier than the current date (as it appears in the Project Information dialog box). Task C-1: Tracking tasks that are currently in progress q Objective: To require Microsoft Project to estimate the percentage of a task that is complete. Tracking Gantt view is applied. Complete the Practice Task exercise at the end of Task B Select and look at task 12 (Write Content). This task was supposed to begin on 2/6/03 and finish on 3/7/03. Our current date is 3/4/03. Therefore, task 12 should be started and more than half completed. 2. Choose Tools, Tracking, Update Project. The Update Project dialog box appears. 2-8

9 Ashbury Training Lesson 2: Tracking Project Progress 3. Look at the dialog box. You can use this dialog box to record percentages of work completed or to reschedule uncompleted work. 4. Verify that Set 0% - 100% Complete is selected. For each of the selected tasks, a percentage of completion is automatically calculated and recorded. 5. Select Selected Tasks to indicate that this estimation be performed only on the selected tasks. 6. Click OK. 7. Look at the Gantt Chart. (You might have to scroll the Gantt Chart to the right.) Task 12 has an estimated percentage of completion recorded, and the summary task, Development Phase, has also been updated. Manually Updating an Unfinished Task In addition to automatically updating tasks in progress, you can manually enter a percent complete for an unfinished task. For example, imagine that someone who is working on a particular task has given you an estimate on the percentage of the task that is complete. To enter a percent complete for an unfinished task, display the Update Tasks dialog box and enter the appropriate percentage in the % Complete text box. Let's try it. Task C-2: Entering a percent complete for unfinished tasks q Objective: To enter your own estimate of percent completion. Tracking Gantt view is applied. 1. Select task 13 (Add Graphics). In this task, students click the Update Tasks button to see percentages complete for a task. 2. Click the Update Tasks button. 3. In the % Complete text box, type 15. If your date is different than Microsoft Project's, you can override it. 4. Click OK. 2-9

10 Microsoft Project 2000: Level 2 Ashbury Training Rescheduling Uncompleted Work At some point, you may need to reschedule uncompleted work. You can reschedule the work to start on the current date or a future date. In addition, you can have Microsoft Project reschedule the uncompleted work, or you can reschedule it yourself. To have Microsoft Project schedule uncompleted work: 1. Display the Gantt Chart, if necessary. 2. Verify that the appropriate task is selected. 3. Choose Tools, Tracking, Update Project. 4. Select Reschedule Uncompleted Work To Start After and type the appropriate date in the accompanying text box. 5. Select Selected Tasks to reschedule the selected task only. 6. Click OK. Splitting a Task When you reschedule work, a split task can result. A split task occurs when the scheduling is interrupted. For example, you may have a task that requires materials that won't be available for a few more days. You can also split a task by following the steps below: 1. On the Standard toolbar, click the Split Task button. 2. On the task's Gantt bar, click the area of the bar on the date where you want the split to occur. Drag the second part of the bar to the date on which you want the work to resume. You can split a task multiple times. If you find that you want to remove a split, drag a portion of the Gantt bar until it touches another portion. Task C-3: Rescheduling uncompleted work Tracking Gantt view is applied. 1. Look at the finish date of the project. It is 3/26/ Verify that task 13 is selected. 3. Display the Update Project dialog box. (Choose Tools, Tracking, Update Project.) 4. Select Reschedule Uncompleted Work To Start After and in the accompanying text box, type 3/6/ Select Selected Tasks. 6. Click OK. 7. Look at the Gantt Chart. A split task has been created. 2-10

11 Ashbury Training Lesson 2: Tracking Project Progress 8. Place the mouse pointer over the critical bar for task 13. The finish date is now later. 9. On the Gantt Chart, look at tasks 3 through 13. In a number of instances, the actuals for the tasks are different than the baseline plan. 10. Display the Project Statistics dialog box. 11. Look at the Actual Finish statistics versus the Baseline Finish statistics. The Current Finish date is now 3/28/03. The Variance Finish is 3.25 days. The finish date has moved forward three days. 12. Close the Project Statistics dialog box. Adding a Progress Line to a Gantt Chart If you have saved a baseline plan for your project, you can add a progress line to the Gantt Chart. A progress line connects and is a visual representation of inprogress tasks. Microsoft Project draws progress lines connecting in-progress tasks in a Gantt Chart thereby creating a graph. Peaks that point to the left represent work that is behind schedule. Peaks that point to the right represent work that is ahead of schedule. To add a progress line: 1. Choose Tools, Tracking, Progress Lines. The Progress Lines dialog box is displayed. 2. Verify that the Dates And Intervals tab is active. 3. Select Display Selected Progress Lines. 4. In the Progress Line Dates list box, click to display a drop-down arrow. 5. Click on the drop-down arrow to display a drop-down calendar, and then select a date. 6. In the Display Progress Lines In Relation To box, select Actual Plan or Baseline Plan. 7. Click OK. You can also add a progress line by using the mouse. Viewing Progress in the Network Diagram You can also view the progress of your project in the Network Diagram view. If a task is complete, its node will have an X drawn through it. If a task is in progress, its node will have a slash (\) through it. Tasks that have not yet started remain unmodified. 2-11

12 Microsoft Project 2000: Level 2 Ashbury Training Task C-4: Viewing progress in the Network Diagram Tracking Gantt view is applied. 1. Choose View, Network Diagram. 2. Choose View, Zoom to display the Zoom dialog box. 3. In the Zoom dialog box, select 50% and click OK. 4. Look at the nodes at the beginning of the project. Tasks that are complete appear with an X through them. Tasks that are in progress appear with a slash through them. 5. Return the view to Tracking Gantt. 6. Save the file as My Track Plan. 7. Close the file. Practice Task In this activity, you will track the project progress by marking tasks complete and adding lines. 1. Open the file C:\Student\Practice Tracking. 2. View the Tracking Gantt Chart and move to the start of the project. 3. Change the current date to 1/20/ Select task 1 (Paint The walls) and task 2 (Lay Carpet) and indicate that they started and finished on schedule. 5. Select task 3 (Install Partitions) and indicate that it finished late on 1/18/ Select task 4 (Install Network Cables) and indicate that it is behind schedule with only 15% completion at this point. 7. Save the file as My Practice Tracking. 8. Compare your Tracking Gantt Chart with the one in Figure Close the file. Figure 2-2: My Practice Tracking after step 7 is complete. 2-12

13 Lesson 2: Tracking Project Progress ) Wrap-up for Lesson 2 a When do you begin tracking your project? Ideally, you begin tracking your project after the planning is complete and the project is in progress. What do the two sets of bars in the Tracking Gantt Chart represent? The top bar of each pair represents the current schedule: red for critical tasks and blue for non-critical tasks. The bottom bar, which is gray, represents the original plan. b List the steps necessary to track a task that finished late. 1. Choose Tools, Tracking, Update Tasks (or click the Update Tasks button on the Tracking toolbar). 2. In the Actual Finish date text box, enter the finish date for the task. 3. Click OK. c How are completed tasks represented in the Network Diagram? Completed tasks appear with an X through them. How are tasks in progress represented? Tasks in progress appear with a slash through them. 2-13

14

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project Microsoft Project 2007 Level 2: Working with Resources and Managing a Project By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS In Microsoft Project 2007 Level 1: Creating Project Tasks, the focus was

More information

OVERVIEW. Microsoft Project terms and definitions

OVERVIEW. Microsoft Project terms and definitions PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training

More information

Project Management: Intermediate Microsoft Project 2010

Project Management: Intermediate Microsoft Project 2010 Project Management: Intermediate Microsoft Project 2010 This document includes instructions for managing resources, updating project plans, and designing visual reports. Managing Resources in a Project

More information

ELECTRO-MECHANICAL PROJECT MANAGEMENT

ELECTRO-MECHANICAL PROJECT MANAGEMENT CHAPTER-9 ELECTRO-MECHANICAL PROJECT MANAGEMENT Y K Sharma,SDE(BS-E), 9412739241(M) E-Mail ID: yogeshsharma@bsnl.co.in Page: 1 Electro-mechanical Project Management using MS Project Introduction: When

More information

Microsoft Project 2010

Microsoft Project 2010 Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

MICROSOFT PROJECT 2010 - II

MICROSOFT PROJECT 2010 - II MICROSOFT PROJECT 2010 - II Course Material This 2-day course is for intermediate and advanced users of the MS Project scheduling application who want to increase their capabilities managing projects in

More information

Scheduling Document Creation

Scheduling Document Creation Scheduling Document Creation What is a Schedule in epm? Schedules The epm Schedule application is an integral part of the Portfolio Management suite of applications. Start and end dates for each summary

More information

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS What is a Project... 2 The Steps involved in Setting up a Project... 3 Views... 4 How To Start a new project... 6 The Gantt Chart... 8 Outlining/Summary

More information

University of Sunderland. Microsoft Project. Basic Guide

University of Sunderland. Microsoft Project. Basic Guide University of Sunderland Microsoft Project Basic Guide 21/11/2008 A Course in using Microsoft Project Garry Storer Learning Objectives 1. What project management software is, basic concepts, the tasks

More information

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project Preliminary 1. You must have Microsoft Project 2003 or higher installed to complete these procedures. 2. If necessary,

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Document author: Produced by: Displaying a Critical Path Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

Lesson 6 - Managing Resources in a Project Plan

Lesson 6 - Managing Resources in a Project Plan Lesson 6 - Managing Resources in a Project Plan Lesson Objectives In this lesson, you will manage resources in a project plan. You will: Create a resource calendar. Assign resources to tasks. Assign additional

More information

Project 2010. Quick Reference. The Assignment Equation. EPM Architects www.epmarchitects.com

Project 2010. Quick Reference. The Assignment Equation. EPM Architects www.epmarchitects.com The Assignment Equation The following equation controls the relationship between the Work, Duration, and Assignment Units for a task assignment: Or Or Work: The number of hours of real work effort spent

More information

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety

More information

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0 ECDL European Computer Driving Licence Project Planning Project Management Software BCS ITQ Level 2 Using Microsoft Project 2013 Syllabus Version 1.0 This training, which has been approved by BCS, The

More information

INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9

INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9 Contents Contents INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9 IMPORT UPDATES 12 CUSTOM TEXT FIELDS MAPPING 13

More information

OmniPlan. version 2.0.1 Manual. Introduction to the Interface

OmniPlan. version 2.0.1 Manual. Introduction to the Interface OmniPlan version 2.0.1 Manual Introduction to the Interface Introduction to the Interface Toolbar Like most applications, the toolbar has buttons for commands you use frequently. Some of the buttons change

More information

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 BY PAUL EASTWOOD HARRIS Eastwood Harris Pty Ltd i Copyright 1999 2010 by Eastwood Harris Pty Ltd. No part of this publication may be reproduced or used

More information

USER MANUAL Detcon Log File Viewer

USER MANUAL Detcon Log File Viewer USER MANUAL Detcon Log File Viewer DETCON, Inc. 4055 Technology Forest Blvd., The Woodlands, Texas 77381 Ph.281.367.4100 / Fax 281.298.2868 www.detcon.com January 29, 2013 Document #4482 Revision 1.00

More information

PERCEPTION PERT-PAC Using Microsoft Project 2000

PERCEPTION PERT-PAC Using Microsoft Project 2000 PERCEPTION PERT-PAC Using Microsoft Project 2000 to Plan & Schedule A Training Tutorial (Sample Hull Block Construction) 1 This training tutorial outlines the basic features of the Microsoft Project 2000

More information

Microsoft Project 2013 Guide to Task and Resource Planning

Microsoft Project 2013 Guide to Task and Resource Planning Starting a Project The Microsoft Project 2013 Start screen Double click Blank Project, select a Recent project, or click Open Other Projects to work on a saved project stored on disk or on SkyDrive. To

More information

Analyzing Excel Data Using Pivot Tables

Analyzing Excel Data Using Pivot Tables NDUS Training and Documentation Analyzing Excel Data Using Pivot Tables Pivot Tables are interactive worksheet tables you can use to quickly and easily summarize, organize, analyze, and compare large amounts

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Slides Slides Slides Steps to Enter Resource Types: 1. Click View and Resource Sheet 2. In the Type column of a resource, select Work, Material, or Cost, and press Enter on your keyboard Important

More information

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Looking for schedule variances Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

Module A2 Item Activities, Gantt Chart and Utilization Sheet

Module A2 Item Activities, Gantt Chart and Utilization Sheet Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Module 1. Project item activities, Gantt Chart & Utilization Sheet Contents...

More information

Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet

Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Assistance PSA: Advanced Functionalities Welcome to the Advanced Functionalities

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project

More information

INTRODUCTION TO PROJECT MANAGEMENT AND MS PROJECT

INTRODUCTION TO PROJECT MANAGEMENT AND MS PROJECT LECTURE -01 TO PROJECT MANAGEMENT AND MS PROJECT 2 Objective LEARNING OBJECTIVES To learn Project Management Software and their Application to Civil Engineering Books Microsoft Office Project Step by Step

More information

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle. Planning and Managing Software Projects 2011-12 Class 10 Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

More information

HOUR 9. Formatting Worksheets to Look Great

HOUR 9. Formatting Worksheets to Look Great HOUR 9 Formatting Worksheets to Look Great Excel makes it easy to make even simple worksheets look professional. AutoFormat quickly formats your worksheet within the boundaries you select. If you want

More information

Creating a New Project

Creating a New Project Creating a New Project Microsoft Project is a project management software program designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets,

More information

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 Table of Contents ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 IMPORT A TASK LIST FROM AN EXCEL FILE INTO A NEW PROJECT PLAN... 6 Import a Task List

More information

Microsoft Project 2013

Microsoft Project 2013 CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Project 2013 Summer 2014, Version 1.0 Table of Contents Introduction...2 Overview of the User Interface...2 Creating a

More information

1. INTRODUCTION...2 2. PRODUCT...2. 2.1. Installation... 2 2.2. Documentation... 2 2.3. Website... 2. 3. workbench features...2

1. INTRODUCTION...2 2. PRODUCT...2. 2.1. Installation... 2 2.2. Documentation... 2 2.3. Website... 2. 3. workbench features...2 Table of Contents 1. INTRODUCTION...2 2. PRODUCT...2 2.1. Installation... 2 2.2. Documentation... 2 2.3. Website... 2 3. workbench features...2 3.1. Project Planning... 2 3.2. Project Tracking... 3 4.

More information

Basic Pivot Tables. To begin your pivot table, choose Data, Pivot Table and Pivot Chart Report. 1 of 18

Basic Pivot Tables. To begin your pivot table, choose Data, Pivot Table and Pivot Chart Report. 1 of 18 Basic Pivot Tables Pivot tables summarize data in a quick and easy way. In your job, you could use pivot tables to summarize actual expenses by fund type by object or total amounts. Make sure you do not

More information

Tutorials. If you have any questions, comments, or suggestions about these lessons, don't hesitate to contact us at support@kidasa.com.

Tutorials. If you have any questions, comments, or suggestions about these lessons, don't hesitate to contact us at support@kidasa.com. Tutorials The lesson schedules for these tutorials were installed when you installed Milestones Professional 2010. They can be accessed under File Open a File Lesson Chart. If you have any questions, comments,

More information

Using MS Project in Translation Projects Management

Using MS Project in Translation Projects Management Using MS Project in Translation Projects Management When building a translation project plan, there must be taken into account: the tasks involved by the project, duration of each task, task dependencies,

More information

Introduction to Microsoft Project 2010

Introduction to Microsoft Project 2010 Introduction to Microsoft Project 2010 This document provides an introduction in using Microsoft Project 2010. Microsoft Project is a project management application that contains a set of tools to help

More information

Making Visio Diagrams Come Alive with Data

Making Visio Diagrams Come Alive with Data Making Visio Diagrams Come Alive with Data An Information Commons Workshop Making Visio Diagrams Come Alive with Data Page Workshop Why Add Data to A Diagram? Here are comparisons of a flow chart with

More information

Data Visualization. Prepared by Francisco Olivera, Ph.D., Srikanth Koka Department of Civil Engineering Texas A&M University February 2004

Data Visualization. Prepared by Francisco Olivera, Ph.D., Srikanth Koka Department of Civil Engineering Texas A&M University February 2004 Data Visualization Prepared by Francisco Olivera, Ph.D., Srikanth Koka Department of Civil Engineering Texas A&M University February 2004 Contents Brief Overview of ArcMap Goals of the Exercise Computer

More information

13 Managing Devices. Your computer is an assembly of many components from different manufacturers. LESSON OBJECTIVES

13 Managing Devices. Your computer is an assembly of many components from different manufacturers. LESSON OBJECTIVES LESSON 13 Managing Devices OBJECTIVES After completing this lesson, you will be able to: 1. Open System Properties. 2. Use Device Manager. 3. Understand hardware profiles. 4. Set performance options. Estimated

More information

1. Go to your programs menu and click on Microsoft Excel.

1. Go to your programs menu and click on Microsoft Excel. Elementary Statistics Computer Assignment 1 Using Microsoft EXCEL 2003, follow the steps below. For Microsoft EXCEL 2007 instructions, go to the next page. For Microsoft 2010 and 2007 instructions with

More information

MS Project 2000 Tutorial: Introduction

MS Project 2000 Tutorial: Introduction MS Project 2000 Tutorial: Introduction - Anjana Srikanth Stylus Systems is a Internet Technology company located in Bangalore India. One of our mottos is "a quality process creates a quality product."

More information

REDUCING YOUR MICROSOFT OUTLOOK MAILBOX SIZE

REDUCING YOUR MICROSOFT OUTLOOK MAILBOX SIZE There are several ways to eliminate having too much email on the Exchange mail server. To reduce your mailbox size it is recommended that you practice the following tasks: Delete items from your Mailbox:

More information

Data Visualization. Brief Overview of ArcMap

Data Visualization. Brief Overview of ArcMap Data Visualization Prepared by Francisco Olivera, Ph.D., P.E., Srikanth Koka and Lauren Walker Department of Civil Engineering September 13, 2006 Contents: Brief Overview of ArcMap Goals of the Exercise

More information

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft

More information

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: harrispe@eh.com.au Australia Software

More information

In this example, Mrs. Smith is looking to create graphs that represent the ethnic diversity of the 24 students in her 4 th grade class.

In this example, Mrs. Smith is looking to create graphs that represent the ethnic diversity of the 24 students in her 4 th grade class. Creating a Pie Graph Step-by-step directions In this example, Mrs. Smith is looking to create graphs that represent the ethnic diversity of the 24 students in her 4 th grade class. 1. Enter Data A. Open

More information

Microsoft Project Dissected

Microsoft Project Dissected Microsoft Project Dissected by Ron Winter, PSP Schedule Analyzer Software Copyright 2012 Third Annual Construction CPM Conference Introduction Although Oracle/Primavera P6 is dominant Many contracts specify/allow

More information

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows)

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows) Overview 1 Content Overview Open a project file Create a new project plan Track progress View and print reports Share a project plan Conclusion 2 Overview With you can: create new/update project plan open

More information

1 Start a new project

1 Start a new project Project Management Quick Reference Guide for Microsoft Project 2010 Before beginning a new project, an organization must determine whether the project fits its strategic goals. Executives should classify

More information

MICROSOFT PROJECT TUTORIAL

MICROSOFT PROJECT TUTORIAL MICROSOFT PROJECT TUTORIAL INTRODUCTION Microsoft Project is a Windows-based project management software package. It provides the flexibility to help manage your project, provides assistance in every phase

More information

Microsoft Project 2007 Level 1: Creating Project Tasks

Microsoft Project 2007 Level 1: Creating Project Tasks Microsoft Project 2007 Level 1: Creating Project Tasks By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS Regardless of job title, most of us have needed to act as a project manager, at one time or another.

More information

OmniPlan for Mac Reviewer s Guide

OmniPlan for Mac Reviewer s Guide OmniPlan for Mac Reviewer s Guide 2 Overview What is OmniPlan? OmniPlan is a professional-grade project management application that's designed with the Mac in mind. It can be used to manage projects of

More information

Using Microsoft Project 2000

Using Microsoft Project 2000 Using MS Project Personal Computer Fundamentals 1 of 45 Using Microsoft Project 2000 General Conventions All text highlighted in bold refers to menu selections. Examples would be File and Analysis. ALL

More information

Microsoft Project 2010 Advanced

Microsoft Project 2010 Advanced Microsoft Project 2010 Advanced Table Of Contents SECTION 1 - REFRESH OF THE BASICS... 3 GUIDE INFORMATION... 4 Introduction... 4 How To Use This Guide... 4 Objectives... 4 Instructions... 4 PROJECT INFORMATION

More information

Project Management within ManagePro

Project Management within ManagePro Project Management within ManagePro This document describes how to do the following common project management functions with ManagePro: set-up projects, define scope/requirements, assign resources, estimate

More information

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule

More information

Before starting this section

Before starting this section Before starting this section SAVE AS YOUR EXISTING MS PROJECT FILE AS -part3-1 1.Click on View Entering Resources-1 Resource Sheet Entering Resources-2 Entering Resources-3 1.Click on the Resource

More information

NE-50413B Mastering Microsoft Project 2010

NE-50413B Mastering Microsoft Project 2010 NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need

More information

Microsoft Outlook 2007 Calendar Features

Microsoft Outlook 2007 Calendar Features Microsoft Outlook 2007 Calendar Features Participant Guide HR Training and Development For technical assistance, please call 257-1300 Copyright 2007 Microsoft Outlook 2007 Calendar Objectives After completing

More information

Project Management: Tracking Progress and Earned Value with MS Project 2003

Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain

More information

Project Management Quick Reference Guide for MS Project 2010

Project Management Quick Reference Guide for MS Project 2010 Project Management Quick Reference Guide for MS Project 2010 Project 2010 offers flexibility and choice by providing tailored work management solutions for individuals, teams, and the enterprise. Besides

More information

Workspaces Creating and Opening Pages Creating Ticker Lists Looking up Ticker Symbols Ticker Sync Groups Market Summary Snap Quote Key Statistics

Workspaces Creating and Opening Pages Creating Ticker Lists Looking up Ticker Symbols Ticker Sync Groups Market Summary Snap Quote Key Statistics Getting Started Workspaces Creating and Opening Pages Creating Ticker Lists Looking up Ticker Symbols Ticker Sync Groups Market Summary Snap Quote Key Statistics Snap Report Price Charts Comparing Price

More information

Microsoft Word Track Changes

Microsoft Word Track Changes Microsoft Word Track Changes This document is provided for your information only. You SHOULD NOT upload a document into imedris that contains tracked changes. You can choose to use track changes for your

More information

Create a Poster Using Publisher

Create a Poster Using Publisher Contents 1. Introduction 1. Starting Publisher 2. Create a Poster Template 5. Aligning your images and text 7. Apply a background 12. Add text to your poster 14. Add pictures to your poster 17. Add graphs

More information

ORACLE BUSINESS INTELLIGENCE WORKSHOP

ORACLE BUSINESS INTELLIGENCE WORKSHOP ORACLE BUSINESS INTELLIGENCE WORKSHOP Creating Interactive Dashboards and Using Oracle Business Intelligence Answers Purpose This tutorial shows you how to build, format, and customize Oracle Business

More information

The following is an overview of lessons included in the tutorial.

The following is an overview of lessons included in the tutorial. Chapter 2 Tutorial Tutorial Introduction This tutorial is designed to introduce you to some of Surfer's basic features. After you have completed the tutorial, you should be able to begin creating your

More information

WEB TRADER USER MANUAL

WEB TRADER USER MANUAL WEB TRADER USER MANUAL Web Trader... 2 Getting Started... 4 Logging In... 5 The Workspace... 6 Main menu... 7 File... 7 Instruments... 8 View... 8 Quotes View... 9 Advanced View...11 Accounts View...11

More information

WebEx Meeting Center User's Guide

WebEx Meeting Center User's Guide WebEx Meeting Center User's Guide Table of Contents Accessing WebEx... 3 Choosing the scheduler that works for you... 6 About the Quick Scheduler Page... 6 About the Advanced Scheduler... 8 Editing a scheduled

More information

How to make a line graph using Excel 2007

How to make a line graph using Excel 2007 How to make a line graph using Excel 2007 Format your data sheet Make sure you have a title and each column of data has a title. If you are entering data by hand, use time or the independent variable in

More information

Windows Movie Maker 2012

Windows Movie Maker 2012 Windows Movie Maker 2012 Open Windows Movie Maker A shortcut for Movie Maker should be on the desktop, but if it is not, you can search for the program by touching the right edge of the screen and swiping

More information

Word 2010: Mail Merge to Email with Attachments

Word 2010: Mail Merge to Email with Attachments Word 2010: Mail Merge to Email with Attachments Table of Contents TO SEE THE SECTION FOR MACROS, YOU MUST TURN ON THE DEVELOPER TAB:... 2 SET REFERENCE IN VISUAL BASIC:... 2 CREATE THE MACRO TO USE WITHIN

More information

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE Workshop Information Information Technology Services is happy to provide you with

More information

CDC UNIFIED PROCESS JOB AID

CDC UNIFIED PROCESS JOB AID Purpose The purpose of this document is to provide guidance on the practice of using Microsoft Project and to describe the practice overview, requirements, best practices, activities, and key terms related

More information

Sharing Files and Whiteboards

Sharing Files and Whiteboards Your user role in a meeting determines your level of file sharing. The type of files you can share include documents, presentations, and videos. About Sharing Files, page 1 Changing Views in a File or

More information

Microsoft Project Activity

Microsoft Project Activity Microsoft Project Activity Purpose: The goal of this activity is to lead you through the most important data entry and formatting activities in MS Project and to provide you with the fundamental knowledge

More information

Virto SharePoint Gantt Chart App for Office 365 Release 1.0.3. User and Installation Guide

Virto SharePoint Gantt Chart App for Office 365 Release 1.0.3. User and Installation Guide Virto SharePoint Gantt Chart App for Office 365 Release 1.0.3 User and Installation Guide 2 Table of Contents OVERVIEW... 3 FEATURES LIST... 3 SYSTEM/DEVELOPER REQUIREMENTS... 3 OPERATING SYSTEM... 3 SERVER...

More information

MSP How to guide session 2 (Resources & Cost)

MSP How to guide session 2 (Resources & Cost) MSP How to guide session 2 (Resources & Cost) 1. Introduction Before considering resourcing the schedule it is important to ask yourself one key question as it will require effort from the scheduler or

More information

Flash MX Image Animation

Flash MX Image Animation Flash MX Image Animation Introduction (Preparing the Stage) Movie Property Definitions: Go to the Properties panel at the bottom of the window to choose the frame rate, width, height, and background color

More information

Project 2010 Introduction

Project 2010 Introduction Microsoft Application Series Project 2010 Introduction Best STL Courses never cancelled: guaranteed Last minute rescheduling 24 months access to Microsoft trainers 12+ months schedule UK wide delivery

More information

Revealing the Secrets of Microsoft Project

Revealing the Secrets of Microsoft Project 2 Revealing the Secrets of Microsoft Project To know that one has a secret is to know half the secret itself. Henry Ward Beecher Topics Covered in This Chapter Recognizing the Underlying Rules of Project

More information

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,

More information

Instructions for creating a data entry form in Microsoft Excel

Instructions for creating a data entry form in Microsoft Excel 1 of 5 You have several options when you want to enter data manually in Excel. You can enter data in one cell, in several cells at the same time, or on more than one worksheet (worksheet/spreadsheet: The

More information

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan. 2 In this chapter, you will learn how to: Start Microsoft Project Standard or Professional and save a new project plan. Enter task names. Estimate and record how long each task should last. Create a milestone

More information

Beginning Microsoft Project

Beginning Microsoft Project Beginning Microsoft Project BEGINNING MICROSOFT PROJECT...1 WHAT IS PROJECT? WHAT IS IT USED FOR?...1 PROJECT WINDOWS... 1 Views and Tables...1 PHASE 1: PLANNING AND SETTING UP PROJECT...2 PLANNING AND

More information

Excel 2010: Create your first spreadsheet

Excel 2010: Create your first spreadsheet Excel 2010: Create your first spreadsheet Goals: After completing this course you will be able to: Create a new spreadsheet. Add, subtract, multiply, and divide in a spreadsheet. Enter and format column

More information

What's new in Project 2010

What's new in Project 2010 What's new in Project 2010 What's new in Project 2010 Microsoft Project 2010 has a shiny new interface, but that's not all. Under the hood, it contains powerful new scheduling, task management, and view

More information

Outlook Web Access. PRECEDED by v\

Outlook Web Access. PRECEDED by v\ Outlook Web Access Logging in to OWA (Outlook Web Access) from Home 1. Login page http://mail.vernonct.org/exchange 2. To avoid these steps each time you login, you can add the login page to your favorites.

More information

Sage Timesheet Web Access How To Use Timesheet

Sage Timesheet Web Access How To Use Timesheet View and Enter Hours The majority of your projects, called tasks in Timesheet Professional, have already been set up for you. Because the names of the projects are very long, your view has been changed

More information

M-Files Gantt View. User Guide. App Version: 1.1.0 Author: Joel Heinrich

M-Files Gantt View. User Guide. App Version: 1.1.0 Author: Joel Heinrich M-Files Gantt View User Guide App Version: 1.1.0 Author: Joel Heinrich Date: 02-Jan-2013 Contents 1 Introduction... 1 1.1 Requirements... 1 2 Basic Use... 1 2.1 Activation... 1 2.2 Layout... 1 2.3 Navigation...

More information

Acrobat PDF Forms - Part 2

Acrobat PDF Forms - Part 2 Acrobat PDF Forms - Part 2 PDF Form Fields In this lesson, you will be given a file named Information Request Form that can be used in either Word 2003 or Word 2007. This lesson will guide you through

More information

Using Spreadsheets, Selection Sets, and COGO Controls

Using Spreadsheets, Selection Sets, and COGO Controls Using Spreadsheets, Selection Sets, and COGO Controls Contents About this tutorial... 3 Step 1. Open the project... 3 Step 2. View spreadsheets... 4 Step 3. Create a selection set... 10 Step 4. Work with

More information

Unified Communications Using Microsoft Office Live Meeting 2007

Unified Communications Using Microsoft Office Live Meeting 2007 Unified Communications Using Microsoft Office Live Meeting 2007 Text version of online course. Contents Unified Communications... 1 About Microsoft Office Live Meeting 2007... 3 Copyright Information...

More information

Creating Fill-able Forms using Acrobat 8.0: Part 1

Creating Fill-able Forms using Acrobat 8.0: Part 1 Creating Fill-able Forms using Acrobat 8.0: Part 1 The first step in creating a fill-able form in Adobe Acrobat is to generate the form with all its formatting in a program such as Microsoft Word. Then

More information

8. COMPUTER TOOLS FOR PROJECT MANAGEMENT

8. COMPUTER TOOLS FOR PROJECT MANAGEMENT 8. COMPUTER TOOLS FOR PROJECT MANAGEMENT The project management is a complex activity that requires among others: Information intercourse referred to the project, information that is in big amounts more

More information

2) Sharing Projects Made easy by IntelliGantt s Share Wizard, there are three share options to fit the needs of your project.

2) Sharing Projects Made easy by IntelliGantt s Share Wizard, there are three share options to fit the needs of your project. Introduction TeamDirection IntelliGantt solutions allows you and the rest of your project team to collaborate on your projects together. How you would like work together is up to you. The project manager

More information

Earned Value Analysis Exercise

Earned Value Analysis Exercise Earned Value Analysis Exercise www.spmbook.com Author: Adolfo Villafiorita Revision: 2 (205-02-06) Given the following project plan: ID Task Immediate Predecessor (*) Expected Duration (days) Budget ($)

More information