1 I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T T A S K M A N A GEM EN T LEARNING GUIDE

2 Workshop Information Information Technology Services is happy to provide you with this training opportunity. We hope you enjoy it and the time you invest in participating is valuable to your work here at Massey University. Learning Outcomes Microsoft Project 2010 is a project management software program which gives you a visual way to plan projects, manage resources and collaborate with your project team. It is designed to assist with developing a plan, assigning resources to tasks, tracking projects, managing the budget and analysing workloads. In this workshop you will: Define Project Settings. Enter and Link Tasks. Understand Summary Tasks Work with Constraints and Deadlines. Gain a basic understanding of resources. Track and Report on a Project Format Face to face workshop, duration approximately 3 hours. Additional Resources Getting Started with Project Office.com Online Training Webinar RZ aspx?CTT=5&origin=HA Help For further assistance please contact ITS Service Desk on extension Feedback After this workshop please complete our online ITS Training Feedback form. Your feedback is appreciated. Hearing from you about your training experience allows us to improve the relevance and quality of this training. A digital copy of this document is available online. ITS thanks you for considering the environment before printing. 2

3 Contents Workshop Information... 2 Introduction to Project Management... 4 Store and Display Data... 5 Keyboard Shortcuts... 7 View Project... 9 Define Project Settings Exercise 1: Setup a Project Enter Tasks & Milestones Exercise 2: Enter Tasks Enter Summary Tasks Exercise 3: Enter Summary Tasks Link Tasks Exercise 4: Link Tasks Constraints and Deadlines Exercise 5: Constraints and Deadlines Manual and Auto Scheduling Work Resources Understanding Duration, Work & Units Assign Resources to Tasks Exercise 6: Assign Resources to Tasks Split Tasks Track and Manage Project Exercise 7: Track and Manage Project Reports

4 Introduction to Project Management Using Microsoft Office Project 2010 for Windows Learning Outcomes Any project has four basic steps: 1. Define the objectives The objectives for the project need to be defined and agreed with all concerned before starting to plan the project. 2. Planning the project First it has to be decided what tasks need to be done. Then when and in what sequence the tasks need to be done in. Finally it needs to be decided who is going to do the tasks. 3. Managing the Project This involves tracking the progress of the project and adjusting the plan when necessary to meet the objectives. 4. Learning The history of each project can contribute to the more successful planning of subsequent events. Microsoft Project can help with Planning, Managing and Learning. Project cannot tell you what your objectives should be. Microsoft Project is designed to be used both for task and resource management. Launch Project Launch Microsoft Project now from the start menu. 4

5 Store and Display Data Using Microsoft Project 2010 for Windows Introduction Data is stored in three spreadsheets: Task Sheet Resource Sheet Assignment Sheet Data is displayed using: Views Timescale Tables Filter Grouping Indicator Note: This section is an introduction to the terminology. The functionality is explored in more detail in other topics. Task Sheet The Task Sheet stores all information on tasks. The information on each task is stored in one row. The sheet has columns storing data such as Task Duration, Start and Finish dates, dependencies on other tasks, progress on tasks, and so on. To enable you to customise the sheet to your own requirements there are columns where you can store other text or numeric data. Resource Sheet The Resource Sheet stores all information on resources. As with the task sheet you can customise the Resource Sheet to your own requirements. Assignment Sheet The Assignment Sheet records the assignment of resources to tasks. Views Views are different ways of displaying the information. By default task information is displayed as a Gantt Chart. However this information can also be displayed in a Calendar, Pert Chart or other view. Regardless of which view you are using, any data that you enter or change is held in the underlying sheet.

6 Views, continued The default View in Project is the Gantt Chart consisting of the Entry Table (6 columns from the Task Sheet) on the left, and the time scaled Gantt chart on the right. The vertical split in the screen can be dragged to the left or the right to expose more or less chart. At the bottom of the screen is the task form. To select a different view, in the View Command tab in the Task Views group select the arrow to the right of Other Views. The Views listed in the menu can also be accessed using the View Bar at the left of the screen. If the View Bar takes up too much space on your screen, right mouse click on it. From the short cut menu select View Bar. This reduces it to a thin bar with the name of the active view on it. To re-display the View Bar, right click on it and select View Bar. Timescale Clicking on the Zoom bar changes the timescale associated with a view. You can also change the timescale by clicking the View tab and in the Zoom group, click the drop down arrow to the right of Days and then select a timescale. Many views have a Timescale across the top of the view. The scale is easily varied to show more or less detail. Tables Tables are groups of related columns from a Sheet. For example the Table called Entry, displays only information that you need when you are entering tasks. The Cost table shows only columns you need when you are working with costs. Unlike charts, tables cannot be zoomed. Project does not provide the ability to zoom the entire document (as in Word or Excel). Filter A Filter allows you to display a group of tasks that meet specified criteria (by hiding all other tasks). For example if you want to work with just critical tasks, you apply a Filter which hides all tasks other than those that are critical. Grouping Grouping allows a project manager to view tasks in groups that they define and see rolled up totals. This is especially useful when combined with custom field outline codes. Indicator The Indicator column provides instant feedback on the status of your tasks. It is visible by default, in the Gantt and Resource Sheet views. 6

7 Keyboard Shortcuts Using Microsoft Project 2010 for Windows Introduction Many of the shortcut keys that work in Excel will also work in Project, including shortcuts for; tables, charts, copying and moving, and selecting multiple tasks. Table Shortcuts In a table to: Use these keystrokes Move one cell One screen down One screen up Beginning of current row End of current row Top left cell Bottom right cell Moves the sheet across the page Select entire Sheet Select entire Column Select entire Row Go to a Task and show start of Bar on Gantt Remove Filters show all tasks Print Save File Fill Down Find Insert a new task Delete a cell/task Arrow key Page Down Page Up Home End Ctrl + Home Ctrl + End Ctrl + Page Up/Page Down Ctrl + Shift + Space Ctrl + Space Shift + Space F5 F3 Ctrl + P Ctrl + S Ctrl D Ctrl + F Insert Delete 7

8 Chart Shortcuts In a chart to Use these keystrokes Move the Chart Alt + Arrow key Zoom out Ctrl + * Zoom in Ctrl + / Go to the start/end date of the project One window right Alt + Home/End Alt + Page Down Copying and Moving Tasks You can use any of the many Windows methods to Cut, Copy and Paste. Project has the same Auto Copy feature as in Excel (i.e. using the fill handle). Pasted tasks will adopt the indentation level of the paste to location and not keep the originating indent level (i.e. the pasted task(s) become subtasks). Selecting Multiple Tasks To select adjacent tasks, click the first task and then hold down the Shift key while you click on the last cell to be included in the selection. To select two or more non-adjacent tasks select the first one, then hold the Ctrl key down while you select the others. Copying a summary task will copy all the sub-tasks as well. 8

9 View Project Using Microsoft Project 2010 for Windows Introduction Over a projects lifetime you look at the project from many different perspectives, that is why Project has so many different views, including: Timeline View Gant Chart with Timeline View Details Pane Task and Resource Tab View Tab Timeline View This view allows you to see your entire project. On the View tab in the Split View group select the Timeline checkbox. Once you have entered tasks and linked them you can drag the blue timeline bar to scroll the Gantt Chart s timescale dates. You can also drag one end to change the date range that you see in the timescale. Gant Chart with TimeLine View This is a single pane view as it only contains only the Gantt Chart. The left pane contains a table of data and the right side contains the Gantt chart. To see two views at the same time, click the View tab and turn on the Timeline. 9

10 Details Pane Instead of the Timeline you can display the Details pane below the primary pane. Click the View tab and then turn on the Details checkbox. Task and Resource Tab In the View group click the down arrow next to Gantt Chart (Task tab) or the Team Planner (Resource tab) and choose the view that you want to display. If you choose Move Views you will be able to see all built in and custom views. View Tab The Task Views group has buttons for the Gantt Chart, Task Usage, Network Diagram, and Calendar. The Resource Views tab has buttons for Team Planner, Resource Usage and the Resource Sheet. The Team Planner makes it easy to assign resources to tasks. Change Views on the Status Bar You can click one of the icons to display the Gantt Chart, Task Usage, Team Planner or Resource Sheet. Active Pane View Note When both the primary and details pane are open, Project applies the view you choose to the active pane. 10

11 Define Project Settings Using Microsoft Project 2010 for Windows Introduction There are a number of settings in Project that should be defined before capturing tasks. These include: Project Start Date Default Calendar Settings Working Calendar Settings Scheduling the project from a start date or finish date Project Start Date Set the project s start date by following the steps below: 1 On the Project tab in the Properties group select Project Information. In the Project Information dialogue box select a date from the Start Date date-picker > click OK. 2 Calendar Settings A calendar is used to specify working and non-working time for a project, including holidays. There are two aspects of the calendar that need to be setup before tasks are scheduled: Setting Calendar defaults (options) Setting up the working Calendar 11

12 Default Calendar Settings Set the Calendar defaults by following the steps below: 1 On the File tab select Options. In the Project Options window select Schedule. Set the default scheduling options for your Project. Click OK to close the Project Options window. 2 In the Project tab in the Properties group click Project Information. In the Project Information dialogue box select a date from the Start Date date-picker > click OK. Caution It is recommended that project novices and intermediate users, use the standard calendars, with as few customisations as possible (Using Exceptions for non-working days is fine). Working Calendar Settings Follow the steps below to make changes to a calendar. 1 On the Project tab in the Properties group select Change Working Time. 12

13 Working Calendar Settings, continued In the Change Working Time window there are two tabs. Work Weeks and Exceptions: Work Weeks You can set up more than one work week if you work different schedules during different times of the year (e.g. summer/winter schedule). You can t create a work week and apply it to different time periods. The [Default] work week is specified in the Calendar options. It sets week days as Working days and weekends and Nonworking days. The Start and Finish has N/A which means that the work week applies to all dates. 2 To set up a new work week select the first blank Name cell and type a name. Then select the Start and Finish dates for the new workweek. The next step is to setup the workdays and times. With the name of the workweek selected click the Details button. Click OK. 13

14 Working Calendar Settings, continued 3 In the Details for A New Workweek dialogue box you can set the working and nonworking days by selecting the appropriate radio button. 1. To select adjacent days you can click and drag. 2. To select nonadjacent days, use Ctrl + click. 3. In the From and To fields, enter the start and finish times for your work day. 4. To delete a row drag across the From and To cells and then press delete. 5. To add a new row, click the first blank From cell and enter a new From and To time. 6. Click OK. Note Project will not accept overlapping times in different rows. 4 You use Exceptions mostly for non-working time. However some working time may have exceptions, such as Public Holidays or company holidays. If an exception lasts longer than a week then it must either be nonworking time, or all the days must have the same working time. 14

15 Exercise 1: Setup a Project Using Microsoft Project 2010 for Windows Introduction These steps should be done before entering tasks in your new project. Project Start Date Set the project s start date by following the steps below: 1 Create a blank new project and save it as Massey Network Install. 2 3 Set the project start date to 16 September 2013: On the Project tab in the Properties group, select Project Information. In the Project Information dialogue box select the drop down arrow to the right of Start Date and select 16 September 2013 from the calendar. Enter the following public holidays into the calendar by clicking on the Project tab in the Properties group and selecting Change Working Time. New Year s Day 1 January Day after New Year s 2 January Waitangi Day 6 February Good Friday 18 April Easter Monday 21 April ANZAC Day 25 April Queen s Birthday 2 June Labour Day 27 October Christmas Day 25 December Boxing Day 26 December

16 Enter Tasks & Milestones Using Microsoft Project 2010 for Windows Introduction In order to use MS Project each project has to be broken down into a number of tasks. A Milestone is a significant event in a Project. Tasks The default view is the Gantt Chart and this view is useful in order to enter in the basic Task information; Task Name and Duration. Task Names Should be descriptive without being too long and should be entered more or less in the sequence they will be started. Duration Should be entered as a best guess of how much time it will take to complete a task. By default each task is given a duration of 1 day. The duration can be changed immediately or later. A bar representing each task s duration will appear in the Gantt Chart. Duration can be entered as units of Minutes (m), Hours (h), Days (d), Weeks (w) and Months (mo). In the past Project always calculated when tasks started and finished based on the dependencies you created between tasks. If you wanted to fix a task s start or finish date, you could set a date constraint on the task. Project 2010 has two scheduling modes: Auto Scheduled Makes tasks work the way they always have, with Project calculating their start and finish dates automatically. Manually Scheduled Gives you control over task dates. You may want to use this mode if you don t have all the information you need to define a task. You can enter a task name and fill in the details as they become available later. You can leave the date and duration fields blank, you can fill in specific dates, or the duration, or you can even fill in a field with a note. You can also create manually scheduled summary tasks with a high level duration. When you create tasks for the work in that summary task, you can see if you have enough time. Whether you use auto or manual scheduling, the only thing you need to do to enter a task is to type in a task name. 16

17 Enter Tasks Enter tasks by following the steps below: Ensure that the Gantt Chart is the current view, and that the Table called Entry (View > Tables > Entry) is displayed. A task can however be entered using any table. 1 2 Enter Task Names more or less in the sequence they will be started. It is easy to change the sequence at any time. Type the task s name and press Enter. Project sets the Task mode to Manually Scheduled by default. 3 The pin to the left of the task name means that the task is manually scheduled. The question mark means that the task date or duration is incomplete. If you enter a duration and Start date, Project will calculate the Finish date. If you enter the Start and Finish date Project will calculate the Duration. Once both dates are completed the question mark (?) symbol will disappear. 4 To create a new auto scheduled task, type the task name. In the Task Mode cell click the down arrow and choose Auto Scheduled. Because the task is auto scheduled, it has to have duration, start and finish date. By default each task is given a duration of 1 day. The question mark indicates that this is an estimate. It sets the start date to the Projects start date and calculates the finish date for you. The taskbar for an auto scheduled task is blue instead of the teal colour used for manually scheduled tasks. Duration can be entered as units of Minutes (m), Hours (h), Days (d), Weeks (w) and Months (mo). 17

18 Milestones A Milestone is a key point in a project. It could be the completion of an important phase in a Project, or the achievement of a particular goal. A Milestone has zero duration and cannot have resources assigned to it. Enter Milestones Enter a Milestone by following the steps below: 1 First select the task that will appear after the Milestone. 2 On the Tasks tab in the Insert group select Milestone. 3 Type the name of the Milestone and press Enter. A Milestone is represented by a diamond in the Gantt chart. 18

19 Exercise 2: Enter Tasks Using Microsoft Project 2010 for Windows Introduction In this exercise we are going to set the scheduling options and enter some tasks. Auto-schedule Set Project options so that new tasks that are created are auto scheduled: 1 On the File tab, select Options. 2 In the Project Options dialogue box click Schedule. 3 In the Scheduling options for this project, click the arrow in the drop down to the right of New tasks created and select Auto Scheduled. 4 Click OK. Enter Tasks Enter the following tasks into the Gantt Chart view. No Task Name Duration 1 Finalise Design 2 weeks 2 Order Equipment 2 days 3 Hire Wiring Contractors 1 week 4 Receive Equipment 0 days 5 Pre-install Wiring 2 weeks 6 Install PCs 4 days 7 Connect Wiring to PCs 3 days 8 Test Individual PCs 2 days 9 Connect to Network 4 days 10 Network Tests 2 days 11 Acceptance 2 days 12 Opening Celebrations 1 day 19

20 Enter Additional Tasks Add the following tasks to those that were entered above. No Task Name Duration 1 After Install PC s add Install Printers 3 days. 2 After Test Individual PCs add Test Printers 1 day. 3 After Network Tests add Test Signoff 0 days 4 After Test Signoff add Contact Clients 1 day. Attach a Note Using the notes task icon on the Task tab, in the Properties group, attach a note to the task Order Equipment: Collate and place orders for multifunction devices and PC's. A Note icon will appear in the Indicator column. You can read the note by hovering the mouse pointer over the icon. 20

21 Enter Summary Tasks Using Microsoft Project 2010 for Windows Introduction A summary task organises a task into smaller sub-tasks. A Summary task gives a rolled up aggregate for subtasks. In this topic we will: Create a summary task Hide summary tasks Use a project summary task Use the outline numbering for Work Breakdown Structure Create a Summary Task Create a summary task by following the steps bellows: 1 Click the first blank row in the task table. 2 On the Task tab in the Insert group select Summary. You now have a Summary task, with one new sub-task. Type the name for the Summary Task. In the New Task cell type the name of the subtask. 3 Note You can also use the Summary Task for several existing subtasks. This will tell you if the time scheduled for a number of tasks is long enough. Project can keep track of the duration you give a summary task, and the total duration of all the subtasks, and show you whether the work fits in the time you have. 21

22 Create a Summary Task, continued To make several existing tasks subordinate to a new summary task, select the tasks in the task table by clicking and dragging the task number. 5 6 On the Task tab click Summary. Project inserts a summary task and makes the existing tasks one level lower in the outline. 7 Now you can type a name for the New Summary Task. Note: If the duration of the summary task is less than the aggregate duration of the subtasks, then the bar below the Summary task will display in red on the Gantt Chart. Note Taking any sub-task and out-denting it, transforms it into a summary task, and all the tasks below it and to the next summary task become sub tasks of the new summary task. Hide Summary Tasks To hide summary tasks: On the Gantt Chart Tools, Format tab in the Show/Hide group, un-tick the Summary Tasks check box. 22

23 Use a Project Summary Task This is a good tool for checking project-wide values like project duration, project finish, and project total cost. This is a top level summary task with a task ID of 0. On the Gantt Chart Tools, Format tab in the Show/Hide group, tick the Project Summary Task check box. Work Breakdown Structure The Work Breakdown Structure (WBS) codes identify each task s unique place in the outline structure of the project. They can be used for reporting schedules and tracking costs. On the Gantt Chart Tools > Format tab in the Show/Hide group, tick the Outline Number check box. 23

24 Exercise 3: Enter Summary Tasks Using Microsoft Project 2010 for Windows Introduction We are going to create summary tasks and learn how to promote and demote tasks. Exercise 1 2 Create a summary task called Planning for the two tasks Finalise Design and Order Equipment. Select the two tasks Finalise Design and Order Equipment. On the Task tab in the Insert group, select Summary. Rename the new summary task to Planning. Select the tasks: Hire Wiring Contractors Receive Equipment Pre-Install wiring Install PCs Install printers Now create a summary task called Preparation for all the tasks selected above. 3 Create a new task above the task Connect Wiring to PC s and call it Test. 4 5 Outdent Test so that it is not part of the Preparation summary group. On the Task tab, in the Schedule group click Outdent Task (alt + shift + left arrow). Select the tasks: Connect Wiring to PC s Test Individual PCs Test Printers Connect to Network Network Tests Test Signoff On the Task tab, in the Schedule group click Indent Task (alt + shift + right arrow). Test is now a summary task. 24

25 Exercise, continued 6 7 Select the tasks: Contact Clients Acceptance Opening Celebrations Create a summary task for the above selected tasks called Presentation to Clients. Display a Project summary task at the top of the project and identify each task with a hierarchical code: On the Format tab, in the Show/Hide group tick Project Summary Task and Outline Number. 25

26 Link Tasks Using Microsoft Project 2010 for Windows Introduction In Project a task s Start or Finish Date is often determined by the Start or Finish date of other tasks. A task link is about one task controlling the timing of the other. A predecessor task determines when a successor task starts or finishes. A successor task depends on the start or finish of a preceding task. After you ve decided the order of your tasks, you re ready to link related tasks as predecessor and successor tasks. Note FF and SS relationships (see below) are rare, and should be avoided by novices, as they can be difficult to understand. Often these relationships can be better represented by a conventional FS relationship, and a conventional FS relationship with lead or lag times. 26

27 Link by Selection Create a Finish Start (default) link by following the steps below: 1 2 If the two tasks are adjacent click and drag from the first (predecessor) task to the second (successor) task. If the two tasks are not adjacent select the first task and then type Ctrl + Click to select the second task. On the Task tab in the Schedule group select the Link Tasks icon. Note You can also click and drag tasks in the Gantt Chart to create a Finish Start link. To unlink tasks, first select them in the Task Entry table and then in the Schedule group select the UnLink Tasks button. Creating Nondefault Links To create links other than the standard Finish Start type follow the steps below: 1 Make sure you can see the Task Form in the details pane. On the View tab in the Split View group select the Details check box. Right click the Task Form and choose Predecessors & Successors. 2 27

28 Creating Nondefault Links, continued In the Entry Table select the predecessor task In the Task Form, click the Successor Name cell, click the down arrow, and choose a successor task. In the Type cell, click the down arrow and select the type of link that will be created. 6 Click OK. Creating Nondefault Links Using steps below. To use the Task Information dialogue box to create non-default links, follow the Task Information 1 Select the Successor task in the Task Entry table. 3 On the Task tab in the Properties group click Information. 4 On the Task tab in the Properties group click Information. In the Task Information dialogue box select the Predecessor tab. 5 28

29 Creating Nondefault Links Using Task Information, continued Click the down arrow to the right of the Task Name cell and select a Predecessor task from the list. 6 7 Click the down arrow to the right of the Type cell and select the type of link to create. 8 Click OK. Lag & Lead times To provide a delay between linked tasks, enter a Lag. To provide an overlap between tasks, enter a negative lag or Lead time. 1 Select the task for which there will be a lag. In the Task Form, in the Lag cell type the duration of the lag (e.g. 2d). 2 Note 3 Click OK. You can overlap tasks (lead time), by entering a negative value in the Lag field. 29

30 Exercise 4: Link Tasks Using Microsoft Project 2010 for Windows Introduction In Project a task s Start or Finish Date is often determined by the Start or Finish date of other tasks. A task link is about one task controlling the timing of the other. A predecessor task determines when a successor task starts or finishes. A successor task depends on the start or finish of a preceding task. After you ve decided the order of your tasks, you re ready to link related tasks as predecessor and successor tasks. Exercise Assume that you cannot order the equipment before you have finalised the design. Using the link icon on the toolbar, create a link between the tasks Finalise Design and Order Equipment. We cannot hire wiring contractors until the design has been finalised. Use the click and drag method on the Gantt Chart to link from the bar for Finalise Design to Hire Wiring Contractors. Our supplier has told us there is a 4 week delivery time on the equipment that we will be ordering. Link Order Equipment and Receive Equipment and enter a lag of 4ew (4 elapsed weeks). Link Receive Equipment and Pre-Install Wiring. Change the link type to Finish- Finish. For all the remaining tasks, create links and lags that you feel are appropriate. Remember that you can have more than one link to or from a task. 30

31 Constraints and Deadlines Using Microsoft Project 2010 for Windows Introduction You can use constraints to control the start or finish dates of important tasks. You can use manually scheduled tasks or date constraints to do this. If you use manually scheduled tasks you can set both the start and finish date. If you use a date constraint then you can either set the start or the finish date, but not both. The reason why you would use a date constraint in preference to a manually scheduled task is to create a partially flexible constraint. (e.g. a task can start any time after a specific date). Microsoft Project automatically assigns the As Soon As Possible constraint when you enter a task. In order to prevent from having to micro manage a Project, you should only set constraints when necessary. Constraints limit your schedules flexibility so it s best to use the most flexible types. These include As Soon As Possible, Start No Earlier Than, Finish No Later Than. These constraints allow resources to start working on a task as soon as they are available. Inflexible types include Must Start On, Must Finish On. If there is a scheduling conflict between a constraint and a task dependency, Project will schedule the task according to the constraint. Constraints may be imposed on a task start or finish date. Note Constraints may be added unintentionally by entering a start or finish date for a task, or by dragging the task on the Gantt chart. To remove a constraint reset it back to the default As Soon As Possible. Set a Date Constraint Set a date constraint by following the steps below: 1 Select the task you want to work on. 2 On the Task tab in the Properties group click Information. 3 In the Task Information dialogue box, click the Advanced tab. 31

32 Set a Date Constraint, continued Click the down arrow to the right of Constraint type and select it from the list. Some constraint types (e.g. Start no Earlier Than) will also require a constraint date. 4 Set a Date Constraint in Task Details Form Follow the steps below to set a date constraint in the task details form: On the View tab in the Split View group choose More Views from the Details dropdown list. 1 In the More Views dialog box, double-click Task Details Form and click Apply 2 32

33 Set a Date Constraint in Task Details Form, continued 3 In the Constraint box you can choose the constraint that you want Select the date for the constraint and then click OK. 4 Multiple Task Constraints Follow the steps below to set the constraints for multiple tasks: In the Entry table right click a column heading and choose Insert Column on the shortcut menu. 1 2 In the drop down list choose Constraint Type. You can start typing the name of the field and then choose it appears in the list. You can now go and set the constraint type for a task by selecting the down arrow in the Constraint Type cell. 3 33

34 Exercise 5: Constraints and Deadlines Using Microsoft Project 2010 for Windows Introduction In this exercise we look at adding and removing a constraint. Exercise The delivery company have informed us that it will only take 2 weeks to ship the equipment to us. Change the lag between Order Equipment and Receive Equipment from 4ew to 2ew. On the View tab in the Split View group, tick the Details check box and make sure Task Form is selected. In the Gantt Chart view click on the Receive Equipment task, In the task form change the lag for the predecessor task (Order Equipment) from 4ew to 2ew. Change the start date for the Receive Equipment task to 1 day later. Notice how the constraint symbol appears in the indicator field. Remove the constraint for Receive Equipment. Open the Task Details Form in the Split View, by selecting the View tab, and in the Split View group, clicking the down arrow on the far right of the Details check box. 4 From the drop down list select More Views and then the Task Details Form. 5 In the Gantt Chart view select the Receive Equipment task. 6 In the Task Details Form change the constraint type back to As Soon As Possible and click OK. 34

35 Manual and Auto Scheduling Using Microsoft Project 2010 for Windows Introduction A Project can have a combination of manual and auto scheduled task. Switch Scheduling Mode Follow the steps below to switch the scheduling mode: 1 The Entry, Schedule and Summary tables include a Task Mode column. To switch to one of these tables, right click the all cells box at the intersection of the column heading and task ID rows and choose the one you want. Note: You can add the Task Mode field to any table by right clicking a column heading and choosing Insert Column. Then start typing the field name Task Mode. Once it displays, select it to add to the table. 2 To change the Task mode for an existing task, click the task s, Task Mode cell, click the down arrow and select the mode that you want. To change the scheduling mode for all new tasks, on the File tab, choose Options and in the Project Options dialogue box select Schedule. Click the down arrow to the right of New tasks created and choose an option. 3 35

36 Switch Scheduling Mode, continued To change the scheduling mode for new tasks, in the status bar, click New Tasks and choose the scheduling mode

37 Work Resources Using Microsoft Project 2010 for Windows Introduction A work resource like a person or piece of equipment is limited by the time it s available. You can tell Project how much a resource is available and the resource s work schedule. The Resource Sheet is the best place to do this. Create a Resource Follow the steps below to add a work resource. Step 1 Click the View tab and in the Resource View group select Resource Sheet. 2 Click the first blank Resource Name cell and type the name of the resource. You can either type in a person s last name and then first name or a generic name such as the job description. You can t use commas or square brackets in the name. In the Initials field type in the persons first and last initials or an abbreviation of the job description. Initials will display in the Gantt Chart when the resource has been assigned to a task. The Group field can represent any type of category you want (e.g. department). You can use the group field to filter the task list to tasks performed by a specific group The Maximum Units field is where you tell Project what percentage of time the resource is available for the project. (e.g. if you only work 4 hours a day this can be set to 50%). You could also tell Project that this resource consists of 3 people by setting the Maximum Units to 300%. 37

38 Create a Resource, continued Note If you assign a resource without creating it first, Project will create a resource with default values for you. To turn off this option, in the File tab, select Options and then Advanced. Under General options for this project untick the box Automatically add new resources and tasks, and click OK. Enter Resource Information You can also enter or edit resource information in the Resource Information dialog box. Follow the steps below to open the Resource Information dialog box. 1 With the Resource Sheet open, click the Resource tab and in the Properties group select Information The Resource Information dialogue box displays. 2 38

39 Understanding Duration, Work & Units Using Microsoft Project 2010 for Windows Introduction To ensure that resource assignment is done correctly it s important to understand the relationship between Duration, Work and Units. Units is the percentage or decimal amount the assigned resource works on the task. Duration is expressed in terms of the working week. Work is the actual hours or days worked. Duration Duration = 80 hours = 40 hours 50% (if you only work 4 hours a day) Work Work = Duration x Units 2 days = 5 days x 40% Units Units = Work Duration.25 = 40 hours 160 hours The percentage of time the resource works on the task is 25%. Project Calculation Rules For resource assignment Project calculates duration first, then work and lastly units. Duration Work Units Project calculates Work you input Units you input Project calculates Work you input If blank, Project uses 100% or resource Max units Duration you input Project calculates Units you input Duration you input Project calculates If blank, Project uses 100% or resource Max units Duration you input Work you input Project calculates Duration you input Project calculates If blank, Project uses 100% or resource Max units 39

40 Assign Resources to Tasks Using Microsoft Project 2010 for Windows Introduction Microsoft Project allows you to manage resources through a range from very detailed to broad. How many resources you assign, their work schedule, and availability for your project all affect how long tasks take. Use any of the methods below to assign resources. If you know the resources that you want to assign, the Task Form at the bottom of the Gantt Chart is a good way to assign a resource In the Task Entry table, select the task that you want to assign the resource to. The task form then shows information for the task that s currently selected in the top pane view. 1 2 Click the first blank Resource Name cell. 3 4 Click the down arrow and from the dropdown list choose the resource that you want to assign. To use the resource s maximum units from the resource sheet, you can leave the units cell blank and click OK. 40

41 Exercise 6: Assign Resources to Tasks Using Microsoft Project 2010 for Windows Introduction In this exercise we will learn to add and assign resources to tasks. Exercise 1 Add the following resources by clicking the View tab, and in the Resource Views group, select the resource sheet. Sharon Tate Tod Jones Joe Smith Selwyn Teal Jacinta Merck 2 Assign Sharon Tate to the task Finalise Design. 3 In the Gantt Chart view, click the Finalise Design task. Click onto the Task Form at the bottom of the Split View and click the drop down arrow to the right of Resource Name. Select Sharon Tate from the drop down box. Click OK. 4 Assign Joe Smith to the Order Equipment task. 5 Assign Tod Jones to the tasks: Hire Wiring Contractors Install PCs. 6 Have Selwyn Teal assigned to Pre-install wiring. 7 Assign Joe Smith to three tasks: Connect wiring to PC s. Test Individual PC s Connect to Network. 8 Save the file. 41

42 Split Tasks Using Microsoft Project 2010 for Windows Introduction You can split tasks to indicate periods of time when work isn t being done. Splitting means that you break the task into pieces, and then you can schedule each piece separately. The task Pre-install Wiring might be stopped, if for example the installers ran out of wire. The task could then be split into two, to indicate that no work was being done. Note Splitting tasks could complicate management of your project. Novice users may find it easier to create two separate tasks (with slightly differing names) rather than splitting an existing task. To split the Pre-Install Wiring task follow the steps below. Split Task Split a task by following the steps below. On the Task tab in the Schedule group, click Split Task The cursor changes to a split pointer. Click onto the task where you want the split. Drag the split to where you want that part of the task to resume. 4 Project splits the taskbar in two and moves the second part. The dotted line between the two pieces showes the split. 42

43 Track and Manage Project Using Microsoft Project 2010 for Windows Introduction By regularly reviewing the status of your project you can make sure that it stays on track. Project views and reports help you evaluate your project status. The project Summary Task is an easy way to keep high-level status visible. Summary Task Follow the steps below to use the Summary Task view. 1 2 The project summary task shows up with a special task ID of 0. On the Format tab select the check box for Project Summary Task. The project summary task summarizes your entire project. You can see the duration of the project and the start and finish dates. 3 You can apply different tables and look at the values in the project summary task. On the View tab, click Tables and then choose Variance. 4 In the example below, the Finish Variance is 13 days. That means the project is going to finish 13 days later than planned. 5 In the example below, If you select the cost table, then the graphic below shows that the variance is -$3240 (under budget). 43

44 Project Information Another way of viewing status is in the Project Information dialogue box. Click the Project tab and then Project Information. In the Project Information dialogue box at the bottom, click Statistics. The Project Statistics dialogue box show the Current, Baseline, Actual and Remaining values for your project. You can also see the percentage of duration and work that is complete. Status Reports To view or print Reports in Project, follow the steps below. 1 On the Project tab in the Reports group click on Reports. 2 In the Reports dialogue box, double click Overview and then double-click Project Summary. 3 If variance values for Start, Finish and Duration are greater than 0, then the project may be behind schedule. Cost variances greater than zero mean the project is over budget. If the work variance is greater than zero the project could be behind schedule. 44

45 Status Reports, continued 4 5 Another way to see status for tasks is with status indicators. In the Gantt Chart view right click a column heading and select Insert Column. Then start typing Status Select Status Indicator from the list. A clock with a check mark shows tasks that are on time. If there are tasks that aren t finished but are running late, you will see a clock with an exclamation point inside a red diamond. To draw taskbars for a baseline, go to the Format tab, click Baseline and then choose the baseline that you want to see. 6 Format Gantt Chart To format the Gantt Chart, follow the steps below. 1 To see how much slack tasks have, turn on the Slack check box. A narrow black line sticking out from the right end of a taskbar shows how much a task can delay before it delays its successors. 2 Click the Slippage down arrow and then select a baseline to show slippage with narrow black lines, from the baseline start dates to the current, scheduled start date. The length of the Slippage line shows how far tasks have slipped from the baseline start date. 45

46 Exercise 7: Track and Manage Project Using Microsoft Project 2010 for Windows Introduction In this exercise we are going to learn how to update tasks. Exercise 1 Set a baseline for the project. On the Project tab in the Schedule group, select Set Baseline and then again Set Baseline. 2 View the Tracking Gantt chart (Task tab, View group and Tracking Gantt). Note The task bars now consist of a coloured bar representing the Schedule and a grey bar representing the Baseline. Because no updating has been done, the Baseline will exactly match the Schedule, and the % complete figure at the end of each bar on the chart will be zero Update Task 2 the Finalise Design task as 100% complete. Click onto the Finalise Design task in the Gantt Entry table. On the Task tab in the Schedule group click on the 100% button. Update Task 3 Order Equipment (scheduled to take 2 days) so that 1 day has been completed but that there are still 2 days to go. Select Task 2 Order Equipment on the Task tab in the Schedule group. Click the arrow next to Mark on Track and select Update Tasks. Enter Actual dur as 1d and Remaining Dur as 2d then click OK. Task 5 Hire Wiring Contractors actually started 2 working days before it was scheduled to start, and is 50% complete. Assume you have been away for a few days and when you return you are advised that everything that was scheduled to be done by today s date has been done. Select the whole sheet and click the Mark on Track icon, then again Mark on Track. Look at the result, and then click the Undo icon. 46

47 Reports Using Microsoft Project 2010 for Windows Introduction Text based reports are easy to run and are useful for producing a checklist of upcoming assignments, or send people a quick summary of where a project stands. Unlike visual reports, text reports show data in a specific way. If you want a different perspective you have to run a different report or create a custom report with the layout that you want. Visual reports let you change them on the fly because they use Excel PivotCharts and Visio Pivot Diagrams to look at data in different ways. Text Based Reports To run a text based report, follow the steps below. 1 On the Project tab in the Reports group click Reports. Then select the report category. 2 Finally select the report that you want. 3 47

48 Visual Report To run a visual report, follow the steps below. 1 On the Project tab in the Reports group click Visual Reports. 2 In the Visual Reports dialogue box, select the visual report that you want to run. You will be able to see a preview of how the report will look, as well as choose to view the data by day, week, month, quarter or year. Click on View to run the report. 48

Using Microsoft Project 2000

Using Microsoft Project 2000 Using MS Project Personal Computer Fundamentals 1 of 45 Using Microsoft Project 2000 General Conventions All text highlighted in bold refers to menu selections. Examples would be File and Analysis. ALL

More information

Computer Training Centre University College Cork

Computer Training Centre University College Cork Computer Training Centre University College Cork Project 2013 Table of Contents What's new in Project 2013... 1 Manual scheduling... 1 Graphical Reports... 1 Trace task paths... 1 Easier view customization...

More information

OVERVIEW. Microsoft Project terms and definitions

OVERVIEW. Microsoft Project terms and definitions PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training

More information

Introduction to Microsoft Project 2010

Introduction to Microsoft Project 2010 Introduction to Microsoft Project 2010 This document provides an introduction in using Microsoft Project 2010. Microsoft Project is a project management application that contains a set of tools to help

More information

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects

More information

Microsoft Project 2013 Guide to Task and Resource Planning

Microsoft Project 2013 Guide to Task and Resource Planning Starting a Project The Microsoft Project 2013 Start screen Double click Blank Project, select a Recent project, or click Open Other Projects to work on a saved project stored on disk or on SkyDrive. To

More information

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS What is a Project... 2 The Steps involved in Setting up a Project... 3 Views... 4 How To Start a new project... 6 The Gantt Chart... 8 Outlining/Summary

More information

ELECTRO-MECHANICAL PROJECT MANAGEMENT

ELECTRO-MECHANICAL PROJECT MANAGEMENT CHAPTER-9 ELECTRO-MECHANICAL PROJECT MANAGEMENT Y K Sharma,SDE(BS-E), 9412739241(M) E-Mail ID: yogeshsharma@bsnl.co.in Page: 1 Electro-mechanical Project Management using MS Project Introduction: When

More information

Microsoft Project 2007 Level 1: Creating Project Tasks

Microsoft Project 2007 Level 1: Creating Project Tasks Microsoft Project 2007 Level 1: Creating Project Tasks By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS Regardless of job title, most of us have needed to act as a project manager, at one time or another.

More information

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0 ECDL European Computer Driving Licence Project Planning Project Management Software BCS ITQ Level 2 Using Microsoft Project 2013 Syllabus Version 1.0 This training, which has been approved by BCS, The

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: harrispe@eh.com.au Australia Software

More information

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety

More information

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan. 2 In this chapter, you will learn how to: Start Microsoft Project Standard or Professional and save a new project plan. Enter task names. Estimate and record how long each task should last. Create a milestone

More information

Project 2010 Introduction

Project 2010 Introduction Microsoft Application Series Project 2010 Introduction Best STL Courses never cancelled: guaranteed Last minute rescheduling 24 months access to Microsoft trainers 12+ months schedule UK wide delivery

More information

Microsoft Project 2013

Microsoft Project 2013 CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Project 2013 Summer 2014, Version 1.0 Table of Contents Introduction...2 Overview of the User Interface...2 Creating a

More information

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 Table of Contents ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 IMPORT A TASK LIST FROM AN EXCEL FILE INTO A NEW PROJECT PLAN... 6 Import a Task List

More information

University of Sunderland. Microsoft Project. Basic Guide

University of Sunderland. Microsoft Project. Basic Guide University of Sunderland Microsoft Project Basic Guide 21/11/2008 A Course in using Microsoft Project Garry Storer Learning Objectives 1. What project management software is, basic concepts, the tasks

More information

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project Preliminary 1. You must have Microsoft Project 2003 or higher installed to complete these procedures. 2. If necessary,

More information

Excel 2007 Basic knowledge

Excel 2007 Basic knowledge Ribbon menu The Ribbon menu system with tabs for various Excel commands. This Ribbon system replaces the traditional menus used with Excel 2003. Above the Ribbon in the upper-left corner is the Microsoft

More information

Project 2010. Quick Reference. The Assignment Equation. EPM Architects www.epmarchitects.com

Project 2010. Quick Reference. The Assignment Equation. EPM Architects www.epmarchitects.com The Assignment Equation The following equation controls the relationship between the Work, Duration, and Assignment Units for a task assignment: Or Or Work: The number of hours of real work effort spent

More information

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1 IT Training Microsoft Project Vicky Samways, IT Training Information System Services Version 2.1 Scope Learning outcomes Find out when and how to use Microsoft Project. Learn how to create a project, break

More information

Creating a New Project

Creating a New Project Creating a New Project Microsoft Project is a project management software program designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets,

More information

Project Management Dashboard Pro v5 Documentation

Project Management Dashboard Pro v5 Documentation Project Management Dashboard Pro v5 Documentation Installation There is NO installation required. It s just a macro enabled excel file that opens if you have Excel 2007, 2010, 2013 and 2016 on your Windows

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Slides Slides Slides Steps to Enter Resource Types: 1. Click View and Resource Sheet 2. In the Type column of a resource, select Work, Material, or Cost, and press Enter on your keyboard Important

More information

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project Microsoft Project 2007 Level 2: Working with Resources and Managing a Project By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS In Microsoft Project 2007 Level 1: Creating Project Tasks, the focus was

More information

Microsoft Project 2010

Microsoft Project 2010 Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window

More information

Produced by Flinders University Centre for Educational ICT. PivotTables Excel 2010

Produced by Flinders University Centre for Educational ICT. PivotTables Excel 2010 Produced by Flinders University Centre for Educational ICT PivotTables Excel 2010 CONTENTS Layout... 1 The Ribbon Bar... 2 Minimising the Ribbon Bar... 2 The File Tab... 3 What the Commands and Buttons

More information

Using MS Project in Translation Projects Management

Using MS Project in Translation Projects Management Using MS Project in Translation Projects Management When building a translation project plan, there must be taken into account: the tasks involved by the project, duration of each task, task dependencies,

More information

Project planning with MindGenius

Project planning with MindGenius Project planning with MindGenius This workshop looks at using MindGenius for planning and monitoring smaller projects. MindGenius is available free of charge on all University of Brighton staff and student

More information

Scheduling Document Creation

Scheduling Document Creation Scheduling Document Creation What is a Schedule in epm? Schedules The epm Schedule application is an integral part of the Portfolio Management suite of applications. Start and end dates for each summary

More information

1 Start a new project

1 Start a new project Project Management Quick Reference Guide for Microsoft Project 2010 Before beginning a new project, an organization must determine whether the project fits its strategic goals. Executives should classify

More information

Project Management: Intermediate Microsoft Project 2010

Project Management: Intermediate Microsoft Project 2010 Project Management: Intermediate Microsoft Project 2010 This document includes instructions for managing resources, updating project plans, and designing visual reports. Managing Resources in a Project

More information

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) CONSTRUCTION DIVISION (SCHEDULING & CONTRACTS) 1. INTRODUCTION To establish standards and consistent scheduling practices

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Document author: Produced by: Displaying a Critical Path Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

MS Project 2007 Quick Guide

MS Project 2007 Quick Guide MS Project 2007 Quick Guide 1. Setup your project Add project information Determine project start date Check / Edit the standard/base calendar Check / Edit calendar calculation options Fine-tune your configuration

More information

Introduction to MS WINDOWS XP

Introduction to MS WINDOWS XP Introduction to MS WINDOWS XP Mouse Desktop Windows Applications File handling Introduction to MS Windows XP 2 Table of Contents What is Windows XP?... 3 Windows within Windows... 3 The Desktop... 3 The

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Slides Steps to Enter Duration: 1. In the Duration column of a task, enter a value, and press Enter on your keyboard Important Points: The default time unit is days, so when you enter 5, this becomes 5

More information

Excel 2010: Create your first spreadsheet

Excel 2010: Create your first spreadsheet Excel 2010: Create your first spreadsheet Goals: After completing this course you will be able to: Create a new spreadsheet. Add, subtract, multiply, and divide in a spreadsheet. Enter and format column

More information

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows)

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows) Overview 1 Content Overview Open a project file Create a new project plan Track progress View and print reports Share a project plan Conclusion 2 Overview With you can: create new/update project plan open

More information

About the Tutorial. Audience. Prerequisites. Disclaimer & Copyright. MS Project 2013

About the Tutorial. Audience. Prerequisites. Disclaimer & Copyright. MS Project 2013 About the Tutorial MS Project, the project management software program by Microsoft, is a very handy tool for project managers that helps them develop a schedule, assign resources to tasks, track the progress,

More information

Basic Pivot Tables. To begin your pivot table, choose Data, Pivot Table and Pivot Chart Report. 1 of 18

Basic Pivot Tables. To begin your pivot table, choose Data, Pivot Table and Pivot Chart Report. 1 of 18 Basic Pivot Tables Pivot tables summarize data in a quick and easy way. In your job, you could use pivot tables to summarize actual expenses by fund type by object or total amounts. Make sure you do not

More information

Appendix A: Brief Guide to Microsoft Project 2010

Appendix A: Brief Guide to Microsoft Project 2010 1 Appendix A: Brief Guide to Microsoft Project 2010 from Revised An Introduction to Project Management, Third Edition By Kathy Schwalbe Professor, Augsburg College Department of Business Administration

More information

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 BY PAUL EASTWOOD HARRIS Eastwood Harris Pty Ltd i Copyright 1999 2010 by Eastwood Harris Pty Ltd. No part of this publication may be reproduced or used

More information

Beginning Microsoft Project

Beginning Microsoft Project Beginning Microsoft Project BEGINNING MICROSOFT PROJECT...1 WHAT IS PROJECT? WHAT IS IT USED FOR?...1 PROJECT WINDOWS... 1 Views and Tables...1 PHASE 1: PLANNING AND SETTING UP PROJECT...2 PLANNING AND

More information

Developing a Gantt and PERT Chart

Developing a Gantt and PERT Chart Developing a Gantt and PERT Chart October 2004 Edition UNITAR-executed GEF Medium-Sized Project, on behalf of UNDP Table of Contents Module 1. Creating a Gantt Chart Using MS Project... 1 Introduction...

More information

Project 2013: An introduction

Project 2013: An introduction Project 2013: An introduction TPAF Revision Information Version Date Author Changes made 1.0 February 2013 Jean Glendinning Created 2.0 November 2013 Jean Glendinning Amended elements 3.0 Feb 2014 Jean

More information

Working with sections in Word

Working with sections in Word Working with sections in Word Have you have ever wanted to create a Microsoft Word document with some pages numbered in Roman numerals and the rest in Arabic, or include a landscape page to accommodate

More information

EXCEL PIVOT TABLE David Geffen School of Medicine, UCLA Dean s Office Oct 2002

EXCEL PIVOT TABLE David Geffen School of Medicine, UCLA Dean s Office Oct 2002 EXCEL PIVOT TABLE David Geffen School of Medicine, UCLA Dean s Office Oct 2002 Table of Contents Part I Creating a Pivot Table Excel Database......3 What is a Pivot Table...... 3 Creating Pivot Tables

More information

WBS Schedule Pro. User's Guide

WBS Schedule Pro. User's Guide WBS Schedule Pro User's Guide Critical Tools, Inc. 2014 Table of Contents Overview of WBS Schedule Pro 7 What is WBS Schedule Pro? 7 What is a WBS chart? 9 What is a Network chart? 10 What's New in WBS

More information

Basic Microsoft Excel 2007

Basic Microsoft Excel 2007 Basic Microsoft Excel 2007 The biggest difference between Excel 2007 and its predecessors is the new layout. All of the old functions are still there (with some new additions), but they are now located

More information

Excel 2007 - Using Pivot Tables

Excel 2007 - Using Pivot Tables Overview A PivotTable report is an interactive table that allows you to quickly group and summarise information from a data source. You can rearrange (or pivot) the table to display different perspectives

More information

Gantt View Quick Start Guide

Gantt View Quick Start Guide Gantt View Quick Start Guide This document is intended to give you an overview of the MindGenius 4 Gantt view and its features. Topics covered in this document: Gantt Mode The Gantt View Switching Between

More information

MS Project 2000 Tutorial: Introduction

MS Project 2000 Tutorial: Introduction MS Project 2000 Tutorial: Introduction - Anjana Srikanth Stylus Systems is a Internet Technology company located in Bangalore India. One of our mottos is "a quality process creates a quality product."

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Project management deliverables (e.g. reports); WBS deliverables can be used for report timing Steps to Create a Project from an Existing Template: 1. Click File then New. 2. Select any of the featured

More information

MICROSOFT PROJECT TUTORIAL

MICROSOFT PROJECT TUTORIAL MICROSOFT PROJECT TUTORIAL INTRODUCTION Microsoft Project is a Windows-based project management software package. It provides the flexibility to help manage your project, provides assistance in every phase

More information

Getting Started with ConceptDraw PROJECT v7 for Windows

Getting Started with ConceptDraw PROJECT v7 for Windows Getting Started with ConceptDraw PROJECT v7 for Windows CS Odessa corp. Contents GETTING STARTED WITH CONCEPTDRAW PROJECT...3 CREATING PROJECTS...5 ASSIGNING RESOURCES...7 SETTING THE CALENDAR...9 MANAGING

More information

WORDPAD TUTORIAL WINDOWS 7

WORDPAD TUTORIAL WINDOWS 7 WORDPAD TUTORIAL WINDOWS 7 Quick Access bar Home Tab Triangles = More Commands Groups on the Home tab Right paragraph margin Left paragraph Margin & Indent Paragraphs Ruler Hover the mouse pointer over

More information

MS Project Tips and Tricks

MS Project Tips and Tricks MS Project Tips and Tricks ELLEN LEHNERT, MVP, PMP, MCT, MCITP CONSULTANT/INSTRUCTOR LEHNERTCS, LLC WWW.LEHNERTCS.COM ELLEN@LEHNERTCS.COM Ellen Lehnert, MVP, PMP, MCT, MCITP Background in teaching, Business

More information

Project Management Quick Reference Guide for MS Project 2010

Project Management Quick Reference Guide for MS Project 2010 Project Management Quick Reference Guide for MS Project 2010 Project 2010 offers flexibility and choice by providing tailored work management solutions for individuals, teams, and the enterprise. Besides

More information

Excel 2007 A Beginners Guide

Excel 2007 A Beginners Guide Excel 2007 A Beginners Guide Beginner Introduction The aim of this document is to introduce some basic techniques for using Excel to enter data, perform calculations and produce simple charts based on

More information

Microsoft Access 2010 handout

Microsoft Access 2010 handout Microsoft Access 2010 handout Access 2010 is a relational database program you can use to create and manage large quantities of data. You can use Access to manage anything from a home inventory to a giant

More information

Every project requires communication and collaboration and usually a lot of

Every project requires communication and collaboration and usually a lot of Collaborating on Projects with SharePoint CHAPTER 25 Every project requires communication and collaboration and usually a lot of both. With small project teams, you and your team members may interact in

More information

GUIDE TO USING MICROSOFT PROJECT 2013

GUIDE TO USING MICROSOFT PROJECT 2013 APPENDIXA GUIDE TO USING MICROSOFT PROJECT 2013 Note 1: This Appendix is used with permission from Schwalbe Publishing. It was published as a stand-alone book on May 2, 2013 and as an appendix in Kathy

More information

Handout: Word 2010 Tips and Shortcuts

Handout: Word 2010 Tips and Shortcuts Word 2010: Tips and Shortcuts Table of Contents EXPORT A CUSTOMIZED QUICK ACCESS TOOLBAR... 2 IMPORT A CUSTOMIZED QUICK ACCESS TOOLBAR... 2 USE THE FORMAT PAINTER... 3 REPEAT THE LAST ACTION... 3 SHOW

More information

Search help. More on Office.com: images templates. Here are some basic tasks that you can do in Microsoft Excel 2010.

Search help. More on Office.com: images templates. Here are some basic tasks that you can do in Microsoft Excel 2010. Page 1 of 8 Excel 2010 Home > Excel 2010 Help and How-to > Getting started with Excel Search help More on Office.com: images templates Basic tasks in Excel 2010 Here are some basic tasks that you can do

More information

Tutorials. If you have any questions, comments, or suggestions about these lessons, don't hesitate to contact us at support@kidasa.com.

Tutorials. If you have any questions, comments, or suggestions about these lessons, don't hesitate to contact us at support@kidasa.com. Tutorials The lesson schedules for these tutorials were installed when you installed Milestones Professional 2010. They can be accessed under File Open a File Lesson Chart. If you have any questions, comments,

More information

Introduction to Word 2007

Introduction to Word 2007 Introduction to Word 2007 You will notice some obvious changes immediately after starting Word 2007. For starters, the top bar has a completely new look, consisting of new features, buttons and naming

More information

Excel 2003 A Beginners Guide

Excel 2003 A Beginners Guide Excel 2003 A Beginners Guide Beginner Introduction The aim of this document is to introduce some basic techniques for using Excel to enter data, perform calculations and produce simple charts based on

More information

MS Word 2007 practical notes

MS Word 2007 practical notes MS Word 2007 practical notes Contents Opening Microsoft Word 2007 in the practical room... 4 Screen Layout... 4 The Microsoft Office Button... 4 The Ribbon... 5 Quick Access Toolbar... 5 Moving in the

More information

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start Project Management is the discipline of planning, organizing, and managing resources to complete a specific goal. Microsoft Project is software that helps you. Start your project Open Project 2010 and

More information

Project Management Courses

Project Management Courses "A well planned project will give results exactly as planned." Project Management Courses Professional Development Training has a specialised division of Project Management experts that will tailor the

More information

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2010-11 Session 6 Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 These

More information

Getting Started with ConceptDraw PROJECT v7 for OS X

Getting Started with ConceptDraw PROJECT v7 for OS X Getting Started with ConceptDraw PROJECT v7 for OS X CS Odessa corp. Contents GETTING STARTED WITH CONCEPTDRAW PROJECT...3 CREATING PROJECTS...5 ASSIGNING RESOURCES...7 SETTING THE CALENDAR...9 ADDING

More information

paragraph(s). The bottom mark is for all following lines in that paragraph. The rectangle below the marks moves both marks at the same time.

paragraph(s). The bottom mark is for all following lines in that paragraph. The rectangle below the marks moves both marks at the same time. MS Word, Part 3 & 4 Office 2007 Line Numbering Sometimes it can be helpful to have every line numbered. That way, if someone else is reviewing your document they can tell you exactly which lines they have

More information

Appendix A: Brief Guide to Microsoft Project 2013

Appendix A: Brief Guide to Microsoft Project 2013 Appendix A: Brief Guide to Microsoft Project 2013 Note: This Appendix is an update for An Introduction to Project Management, Fourth Edition, and included in the Revised Fourth Edition. It is also included

More information

Excel Pivot Tables. Blue Pecan Computer Training Ltd - Onsite Training Provider www.bluepecantraining.com :: 0800 6124105 :: info@bluepecan.co.

Excel Pivot Tables. Blue Pecan Computer Training Ltd - Onsite Training Provider www.bluepecantraining.com :: 0800 6124105 :: info@bluepecan.co. Excel Pivot Tables 1 Table of Contents Pivot Tables... 3 Preparing Data for a Pivot Table... 3 Creating a Dynamic Range for a Pivot Table... 3 Creating a Pivot Table... 4 Removing a Field... 5 Change the

More information

Appendix A: Brief Guide to Microsoft Project 2010

Appendix A: Brief Guide to Microsoft Project 2010 Appendix A: Brief Guide to Microsoft Project 2010 Excerpt from An Introduction to Project Management, Fourth Edition Provided at no charge in support of U.S. troops! Go Air Force! By Kathy Schwalbe Professor,

More information

To reuse a template that you ve recently used, click Recent Templates, click the template that you want, and then click Create.

To reuse a template that you ve recently used, click Recent Templates, click the template that you want, and then click Create. What is Excel? Applies to: Excel 2010 Excel is a spreadsheet program in the Microsoft Office system. You can use Excel to create and format workbooks (a collection of spreadsheets) in order to analyze

More information

Asta Powerproject GETTING STARTED WITH ASTA POWERPROJECT VERSION 14. astapowerproject.com. Asta Powerproject: The power behind successful projects

Asta Powerproject GETTING STARTED WITH ASTA POWERPROJECT VERSION 14. astapowerproject.com. Asta Powerproject: The power behind successful projects Asta Powerproject GETTING STARTED WITH ASTA POWERPROJECT VERSION 14 astapowerproject.com Asta Powerproject: The power behind successful projects Asta Powerproject GETTING STARTED WITH ASTA POWERPROJECT

More information

Virto SharePoint Gantt Chart App for Office 365 Release 1.0.3. User and Installation Guide

Virto SharePoint Gantt Chart App for Office 365 Release 1.0.3. User and Installation Guide Virto SharePoint Gantt Chart App for Office 365 Release 1.0.3 User and Installation Guide 2 Table of Contents OVERVIEW... 3 FEATURES LIST... 3 SYSTEM/DEVELOPER REQUIREMENTS... 3 OPERATING SYSTEM... 3 SERVER...

More information

Microsoft Project 2007 Tutorial Boston University. Boston University, Dept of Administrative Sciences, Project Management Programs (2010)

Microsoft Project 2007 Tutorial Boston University. Boston University, Dept of Administrative Sciences, Project Management Programs (2010) Microsoft Project 2007 Tutorial Boston University Boston University, Dept of Administrative Sciences, Project Management Programs (2010) 1 2 Microsoft Project 2007 Tutorial Boston University Contents Table

More information

PowerPoint 2013: Basic Skills

PowerPoint 2013: Basic Skills PowerPoint 2013: Basic Skills Information Technology September 1, 2014 1 P a g e Getting Started There are a variety of ways to start using PowerPoint software. You can click on a shortcut on your desktop

More information

Migrating to Excel 2010 from Excel 2003 - Excel - Microsoft Office 1 of 1

Migrating to Excel 2010 from Excel 2003 - Excel - Microsoft Office 1 of 1 Migrating to Excel 2010 - Excel - Microsoft Office 1 of 1 In This Guide Microsoft Excel 2010 looks very different, so we created this guide to help you minimize the learning curve. Read on to learn key

More information

EXCEL FINANCIAL USES

EXCEL FINANCIAL USES EXCEL FINANCIAL USES Table of Contents Page LESSON 1: FINANCIAL DOCUMENTS...1 Worksheet Design...1 Selecting a Template...2 Adding Data to a Template...3 Modifying Templates...3 Saving a New Workbook as

More information

Explore commands on the ribbon Each ribbon has groups, and each group has a set of related commands.

Explore commands on the ribbon Each ribbon has groups, and each group has a set of related commands. Quick Start Guide Microsoft Project 2013 looks different from previous versions, so we created this guide to help you minimize the learning curve. Quick Access Toolbar Customize this area so your favorite

More information

Introduction to Microsoft Excel 2010

Introduction to Microsoft Excel 2010 Introduction to Microsoft Excel 2010 Screen Elements Quick Access Toolbar The Ribbon Formula Bar Expand Formula Bar Button File Menu Vertical Scroll Worksheet Navigation Tabs Horizontal Scroll Bar Zoom

More information

Microsoft Excel 2010. Understanding the Basics

Microsoft Excel 2010. Understanding the Basics Microsoft Excel 2010 Understanding the Basics Table of Contents Opening Excel 2010 2 Components of Excel 2 The Ribbon 3 o Contextual Tabs 3 o Dialog Box Launcher 4 o Quick Access Toolbar 4 Key Tips 5 The

More information

BIGPOND ONLINE STORAGE USER GUIDE Issue 1.1.0-18 August 2005

BIGPOND ONLINE STORAGE USER GUIDE Issue 1.1.0-18 August 2005 BIGPOND ONLINE STORAGE USER GUIDE Issue 1.1.0-18 August 2005 PLEASE NOTE: The contents of this publication, and any associated documentation provided to you, must not be disclosed to any third party without

More information

Project Management within ManagePro

Project Management within ManagePro Project Management within ManagePro This document describes how to do the following common project management functions with ManagePro: set-up projects, define scope/requirements, assign resources, estimate

More information

Revealing the Secrets of Microsoft Project

Revealing the Secrets of Microsoft Project 2 Revealing the Secrets of Microsoft Project To know that one has a secret is to know half the secret itself. Henry Ward Beecher Topics Covered in This Chapter Recognizing the Underlying Rules of Project

More information

Lab 1 Introduction to Microsoft Project

Lab 1 Introduction to Microsoft Project Lab 1 Introduction to Microsoft Project Statement Purpose This lab provides students with the knowledge and skills to use Microsoft Project. This course takes students step-by-step through the features

More information

Access I 2010. Tables, Queries, Forms, Reports. Lourdes Day, Technology Specialist, FDLRS Sunrise

Access I 2010. Tables, Queries, Forms, Reports. Lourdes Day, Technology Specialist, FDLRS Sunrise Access I 2010 Tables, Queries, Forms, Reports Lourdes Day, Technology Specialist, FDLRS Sunrise Objectives Participants will 1. create and edit a table 2. create queries with criteria 3. create and edit

More information

Managing Projects. With. MinuteMan Project Management Software

Managing Projects. With. MinuteMan Project Management Software Managing Projects With MinuteMan Project Management Software Copyright 2011 by MinuteMan Systems Introduction This is a brief introduction to the use of Project Management Software to help you organize

More information

Microsoft Project 2013. Microsoft Project 2013. The smart way to learn. Microsoft Project 2013. one step at a time!

Microsoft Project 2013. Microsoft Project 2013. The smart way to learn. Microsoft Project 2013. one step at a time! spine = 1.32 one step at a time! Experience learning made easy and quickly teach yourself how to manage the complete project life cycle with Project 2013. With Step by Step, you set the pace building and

More information

Excel 2013 - Using Pivot Tables

Excel 2013 - Using Pivot Tables Overview A PivotTable report is an interactive table that allows you to quickly group and summarise information from a data source. You can rearrange (or pivot) the table to display different perspectives

More information

Tracking Project Progress

Tracking Project Progress L E S S O N 2 Tracking Project Progress Suggested lesson time 45-55 minutes Lesson objectives To begin tracking an active project, you will: a b c Modify the environment for tracking. You will use the

More information

Microsoft Excel 2007 Consolidate Data & Analyze with Pivot Table Windows XP

Microsoft Excel 2007 Consolidate Data & Analyze with Pivot Table Windows XP Microsoft Excel 2007 Consolidate Data & Analyze with Pivot Table Windows XP Consolidate Data in Multiple Worksheets Example data is saved under Consolidation.xlsx workbook under ProductA through ProductD

More information

Pivot Tables & Pivot Charts

Pivot Tables & Pivot Charts Pivot Tables & Pivot Charts Pivot tables... 2 Creating pivot table using the wizard...2 The pivot table toolbar...5 Analysing data in a pivot table...5 Pivot Charts... 6 Creating a pivot chart using the

More information

Primavera P6 102 Training Manual. Prepared by. Bill Pepoon, Managing Partner Construction Science, LLC

Primavera P6 102 Training Manual. Prepared by. Bill Pepoon, Managing Partner Construction Science, LLC Primavera P6 102 Training Manual Prepared by Bill Pepoon, Managing Partner Construction Science, LLC 1 Day I Introduction Setting up a new Project Activities Activity Types Activity Durations Work Breakdown

More information