MS Project Tutorial for Senior Design Using Microsoft Project to manage projects
|
|
|
- Nelson Randall
- 10 years ago
- Views:
Transcription
1 MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects in an informal way: they have a deadline to meet, and they monitor progress of the project as it moves along. However, computer resources are available for managing team projects more formally. This tutorial will introduce you to Microsoft Project, a software package that helps to plan and track projects. You will walk through instructions for project planning, and then for project tracking and finally communicating progress. In managing projects, there are essentially two steps: project planning, and project tracking. Projects consist of several tasks, each of a certain duration, that are to be carried out in a certain sequence. Project planning happens at the start of a project; at this stage the team identifies the tasks involved, estimates task duration, and guesses at task sequence. As the project progresses, some of this may change: task sequences may have to be altered, and tasks may take longer or shorter than originally planned. Project tracking involves recording these various changes, and making appropriate changes to the proposed schedule; tracking must take places throughout the life of the project. Tutorial Objectives: Become familiar with features of MS project and project management Opening and saving files Linking tasks Defining tasks Organizing projects Tracking project completion Understanding milestones and comments Using MS project to communicate Initial Steps: To launch Project, double-click on the Microsoft Project icon. When the Welcome! message box is displayed, click on the button next to Start a New Project. The various parts of the Project screen are as follows: Below the menu bar is the tool bar. This contains a number of buttons that can be clicked to carry out certain common operations. Below the toolbar, to the left side of the screen is the Task Table. This looks like a spreadsheet, with information about each task in a row. To the right of the Task Table is the Gantt Chart. Using horizontal bars, the Gantt Chart graphically represents the task schedule.
2 Project Planning: Project planning involves identifying the tasks involved, their durations, and the relationships among the tasks. Microsoft Project then automatically computes the total project duration and other related information. To enter information about a task, click on an empty cell in the Task Table, type in the name of the task, and press enter. The task name appears in the cell, and a default duration of one day is assigned. To change the default duration, click on the cell in question, type in the correct duration, and press enter. 1. Enter the list of tasks shown below together with their duration: To insert a new task, select in the Task Table the row above which the new task is to be inserted. Choose the Insert Insert Task menu item to insert a blank row in the Task Table. Type in the name of the new task and its duration. 2. Add two new tasks: Project start at the head of the list, and Project finish at the end of the list. Assign them both durations of 0 days. A special kind of task is the milestone. This is usually has a duration of one or zero days, and is used to indicate an event rather than a task. To create a milestone, double-click on its cell in the Task Table. In the resulting Task Information dialog box, choose the Advanced tab and click on the box next to Mark Task as Milestone. 3. Project start and Project finish are milestones in the project we are working on. Mark them as such. You can create hierarchies of tasks: main tasks and their subtasks. To create a hierarchy with a main task and its subtasks, list the subtasks immediately below the main task. Highlight the subtasks, and click on the demote button,, in the toolbar. The highlighted subtasks are indented, and the main task is shown in bold. This action can be reversed by highlighting a subtask and clicking on the promote button, toolbar. To hide the subtasks under a main task, click on the collapse button, toolbar; reverse this action using the expand button,., in the, in the
3 4. Insert a new task labeled Study phase above Conduct survey and make it the main task containing the subtasks Conduct survey, Collect secondary data, and Analyze data. The Task Table should look as follows: To identify the sequence of tasks, double-click on each task in turn, and designate predecessor tasks: those that logically precede the current task. In the Task Information dialog box, choose the Predecessors tab. As shown in the graphic below, first click on a blank cell under Task Name, then click on the drop button indicated, and from the drop list select the predecessor task. As links are created between tasks, the Gantt Chart will change to reflect these links.
4 5. Set the predecessors for each task as shown in the graphic below. (The number refers to the ID number of the predecessor task; for instance, task ID 1 is Project Start. To change the timescale of the Gantt Chart, choose Format Timescale... In the resulting Timescale dialog box, set the major and minor scale units as follows: 6. The Gantt Chart should look as follows: To change the appearance of the Gantt Chart, choose Format Gantt Chart Wizard... To display critical tasks, for example: in Step 2, choose Critical Path, and click Next. In Step 9, choose Dates, and click Next. Keep clicking Next in the remaining steps, until you get to click on Format It. Click Exit to close the Wizard. The chart should appear as follows:
5 The red bars indicate that these tasks are critical: they must be completed on time if the project is not to be delayed beyond the target date. The default relationship between a predecessor and a successor task is as follows: when the predecessor Finishes the successor Starts (FS). This may not be what is desired. Instead, for instance, five days after the predecessor Starts, you may wish to Start the successor (SS, with 5 days lag time). To change the relationship between two linked tasks, double-click on the successor task in the Task Table. In the Task Information dialog box, choose the Predecessors tab. Click on Type cell of the target predecessor. Click on the button with the downward arrow that appears under Predecessors. From the list that drops down, choose the appropriate relationship. In the Lag cell of the predecessor, type in the desired lag time, and press enter. Lag time is the number of days between the finish or start of the predecessor and the finish or start of the successor task; it can be a positive number or a negative number. 7. Set Write proposal to start 5 days after Analyze results starts. Note how the duration of the entire project is reduced. The project has been fast-tracked. Once the initial project schedule has been determined, it has to be recorded as the baseline plan; future adjustments to the schedule will be compared to this baseline. To do this, choose Tools Tracking Save Baseline... In the resulting dialog box, choose Baseline and Entire Project, and click the OK button. (In this dialog box, you can also save upto five different interim project schedules.) The current view (whatever is on the screen) can be either printed (choose File Print Preview and then print) or copied and pasted into a Microsoft Word document: To copy the Chart, first highlight all the tasks that must be included in the picture to be copied. Then, click on the button in the toolbar. In the resulting dialog box, choose For Printer for high-resolution pictures. You can now switch to the other application and paste the picture.
6 To save the project information, use File Save As for the first time, and File Save for later times. To exit Microsoft Project, use File Exit. Project Tracking: To track projects in Microsoft Project, a distinction is drawn between planned, actual, and scheduled information about tasks. Planned task dates (start, finish, duration) are those that are assigned in the initial schedule that is created. As the project progresses, actual dates are recorded; these may or may not be different from the planned dates. In response to changing circumstances, the project may have to be rescheduled; this new information is recorded as scheduled dates. The three different types of information make it possible to keep track of how a project is progressing with regard to the initial plan. Enter the actual completion data for tasks that are already complete or under way. To do this, click on each task that is complete, and select Tools Tracking Update Tasks... In the Update Task dialog box, type the percentage of work completed or the actual finish date. For this exercise, Identify site finished on 3/13/03; Meet Residents and Collect secondary data are 100% complete; Conduct survey is only 60% complete. Note that there is a bar through each task showing how much is complete. If the project is on schedule, then all tasks finishing before today's date should have a bar extending their whole length. Tasks currently under way should have a bar extending till the current date. Clearly there is a problem with Conduct survey; it is behind schedule. We must adjust our schedule to allow for the slippage. Here is how it can be done: Increase the time allotted to the task so that 60% of the task represents the number of days till today's date. Click on the task Conduct survey, and choose the Tools Tracking Update Tasks... menu item. In the Update Task dialog box, increase the Remaining Duration to 10, and click OK. The task is now going to take longer, but the completion bar is still short of today's date. Choose the Tools Tracking Update Tasks... menu item again, and in the Update Task dialog box, change the % Complete back to 60%. Now, the schedule is approximately as we want it:
7 Choose a different view to get a better sense of how the project has changed. Choose View More Views... In the More Views dialog box, choose Tracking Gantt Chart (this is the last in the list), and click on Apply. (You will have to change the Timescale as described earlier.) The Gantt Chart now looks as follows: The gray bars are the baseline schedule; the upper bars are the current schedule. The impact of the work slippage is now clearly visible. Communicating Progress: Now that you can manage your schedule with MS project, you need to use it as a communication tool with your group members, customer and instructors. Preview the project before you print it with the print preview icon. You can edit the print view by clicking on page setup at the top menu in the print preview screen. Click the legend subheading and then click none to remove the legend and make more space on the page. To print the document click the Print button in the preview screen, and adjust the dates for printing to 3/4/03 to 5/22/03. Print the project. Other communication with MS project might include adding it to your web site. You can save the file as an HTML document from the save as command. You may also screen capture a portion of your project schedule to add to reports or presentations.
8 This ends the tutorial. Microsoft Project allows much more powerful planning and tracking of projects including the resources consumed in completing tasks. It also allows charts and reports to be very highly customized.
Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010 This document provides an introduction in using Microsoft Project 2010. Microsoft Project is a project management application that contains a set of tools to help
OVERVIEW. Microsoft Project terms and definitions
PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training
ELECTRO-MECHANICAL PROJECT MANAGEMENT
CHAPTER-9 ELECTRO-MECHANICAL PROJECT MANAGEMENT Y K Sharma,SDE(BS-E), 9412739241(M) E-Mail ID: [email protected] Page: 1 Electro-mechanical Project Management using MS Project Introduction: When
Microsoft Project 2010
Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window
Microsoft Project 2007 Level 2: Working with Resources and Managing a Project
Microsoft Project 2007 Level 2: Working with Resources and Managing a Project By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS In Microsoft Project 2007 Level 1: Creating Project Tasks, the focus was
University of Sunderland. Microsoft Project. Basic Guide
University of Sunderland Microsoft Project Basic Guide 21/11/2008 A Course in using Microsoft Project Garry Storer Learning Objectives 1. What project management software is, basic concepts, the tasks
technical tips and tricks
technical tips and tricks Document author: Produced by: Displaying a Critical Path Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado
CS 587 Software Project Management Instructor: Dr. Atef Bader MS Project Tutorial MS Project in Labs: Available in Siegal Hall Lab in Main Campus Available in Room 210 Rice Campus Prepared by Milton Hurtado
Microsoft Project 2013
CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Project 2013 Summer 2014, Version 1.0 Table of Contents Introduction...2 Overview of the User Interface...2 Creating a
How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows)
Overview 1 Content Overview Open a project file Create a new project plan Track progress View and print reports Share a project plan Conclusion 2 Overview With you can: create new/update project plan open
Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by
Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones
FastTrack Schedule 10. Tutorials Manual. Copyright 2010, AEC Software, Inc. All rights reserved.
FastTrack Schedule 10 Tutorials Manual FastTrack Schedule Documentation Version 10.0.0 by Carol S. Williamson AEC Software, Inc. With FastTrack Schedule 10, the new version of the award-winning project
Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems
Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems Computer Lab # 1 Time Management (with Microsoft Project 2007) Lab Manual (with master s
USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS
P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: [email protected] Australia Software
Creating a New Project
Creating a New Project Microsoft Project is a project management software program designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets,
Using Microsoft Project 2000
Using MS Project Personal Computer Fundamentals 1 of 45 Using Microsoft Project 2000 General Conventions All text highlighted in bold refers to menu selections. Examples would be File and Analysis. ALL
IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1
IT Training Microsoft Project Vicky Samways, IT Training Information System Services Version 2.1 Scope Learning outcomes Find out when and how to use Microsoft Project. Learn how to create a project, break
Using MS Project in Translation Projects Management
Using MS Project in Translation Projects Management When building a translation project plan, there must be taken into account: the tasks involved by the project, duration of each task, task dependencies,
T12. Excel and Microsoft Project. Introduction LEARNING OUTCOMES
P L U G - I N T12 Creating LEARNING OUTCOMES Gantt Charts with Excel and Microsoft Project 1. Explain a Gantt Chart. 2. Describe the main steps involved in creating a Gantt Chart using Excel. 3. Describe
Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.
2 In this chapter, you will learn how to: Start Microsoft Project Standard or Professional and save a new project plan. Enter task names. Estimate and record how long each task should last. Create a milestone
INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS
INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS What is a Project... 2 The Steps involved in Setting up a Project... 3 Views... 4 How To Start a new project... 6 The Gantt Chart... 8 Outlining/Summary
Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa
Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety
Planning and Managing Projects with Microsoft Project Professional 2013
Project management deliverables (e.g. reports); WBS deliverables can be used for report timing Steps to Create a Project from an Existing Template: 1. Click File then New. 2. Select any of the featured
I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE
I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE Workshop Information Information Technology Services is happy to provide you with
MS Project 2007 Quick Guide
MS Project 2007 Quick Guide 1. Setup your project Add project information Determine project start date Check / Edit the standard/base calendar Check / Edit calendar calculation options Fine-tune your configuration
Microsoft Project 2013 Guide to Task and Resource Planning
Starting a Project The Microsoft Project 2013 Start screen Double click Blank Project, select a Recent project, or click Open Other Projects to work on a saved project stored on disk or on SkyDrive. To
How to use Microsoft Project? Basic Training to Help You during the BYI challenge
How to use Microsoft Project? Basic Training to Help You during the BYI challenge Table of Contents I. Main Concepts 1. Overview of Microsoft Project 2. Explanation of the main concepts II. How to : Create
WBS Schedule Pro. User's Guide
WBS Schedule Pro User's Guide Critical Tools, Inc. 2014 Table of Contents Overview of WBS Schedule Pro 7 What is WBS Schedule Pro? 7 What is a WBS chart? 9 What is a Network chart? 10 What's New in WBS
Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project
Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project Preliminary 1. You must have Microsoft Project 2003 or higher installed to complete these procedures. 2. If necessary,
technical tips and tricks
technical tips and tricks Looking for schedule variances Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0
ECDL European Computer Driving Licence Project Planning Project Management Software BCS ITQ Level 2 Using Microsoft Project 2013 Syllabus Version 1.0 This training, which has been approved by BCS, The
MS Project 2000 Tutorial: Introduction
MS Project 2000 Tutorial: Introduction - Anjana Srikanth Stylus Systems is a Internet Technology company located in Bangalore India. One of our mottos is "a quality process creates a quality product."
Computer Training Centre University College Cork
Computer Training Centre University College Cork Project 2013 Table of Contents What's new in Project 2013... 1 Manual scheduling... 1 Graphical Reports... 1 Trace task paths... 1 Easier view customization...
Microsoft Project 2007 Level 1: Creating Project Tasks
Microsoft Project 2007 Level 1: Creating Project Tasks By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS Regardless of job title, most of us have needed to act as a project manager, at one time or another.
Beginning Microsoft Project
Beginning Microsoft Project BEGINNING MICROSOFT PROJECT...1 WHAT IS PROJECT? WHAT IS IT USED FOR?...1 PROJECT WINDOWS... 1 Views and Tables...1 PHASE 1: PLANNING AND SETTING UP PROJECT...2 PLANNING AND
Lab 1 Introduction to Microsoft Project
Lab 1 Introduction to Microsoft Project Statement Purpose This lab provides students with the knowledge and skills to use Microsoft Project. This course takes students step-by-step through the features
Laboratory 1 Initiating a Project
Laboratory 1 Initiating a Project Outline What is a project? What is project management? Initiating a project. Getting Starting with Project 2007? What Is a Project? A project is an activity that has a
Project Initiation and Revision Training Manual. Table of Contents
for Engineering and Construction v.4.1 Project Initiation and Revision Training Class Conducted by Evans Technology June 2005 Table of Contents Introduction to Primavera... 3 Project Management (P3eC)...
Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.
Planning and Managing Software Projects 2011-12 Class 10 Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Developing a Gantt and PERT Chart
Developing a Gantt and PERT Chart October 2004 Edition UNITAR-executed GEF Medium-Sized Project, on behalf of UNDP Table of Contents Module 1. Creating a Gantt Chart Using MS Project... 1 Introduction...
Planning and Scheduling Your Project Using Microsoft Project 2003
Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering [email protected] Meeting Protocol Agenda Project File Project Calendar Creating
Planning and Managing Projects with Microsoft Project Professional 2013
Slides Steps to Enter Duration: 1. In the Duration column of a task, enter a value, and press Enter on your keyboard Important Points: The default time unit is days, so when you enter 5, this becomes 5
Revealing the Secrets of Microsoft Project
2 Revealing the Secrets of Microsoft Project To know that one has a secret is to know half the secret itself. Henry Ward Beecher Topics Covered in This Chapter Recognizing the Underlying Rules of Project
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL INTRODUCTION Microsoft Project is a Windows-based project management software package. It provides the flexibility to help manage your project, provides assistance in every phase
What is a Mail Merge?
NDUS Training and Documentation What is a Mail Merge? A mail merge is generally used to personalize form letters, to produce mailing labels and for mass mailings. A mail merge can be very helpful if you
Microsoft Office 2010
Access Tutorial 1 Creating a Database Microsoft Office 2010 Objectives Learn basic database concepts and terms Explore the Microsoft Access window and Backstage view Create a blank database Create and
Pivot Tables & Pivot Charts
Pivot Tables & Pivot Charts Pivot tables... 2 Creating pivot table using the wizard...2 The pivot table toolbar...5 Analysing data in a pivot table...5 Pivot Charts... 6 Creating a pivot chart using the
PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS
PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 BY PAUL EASTWOOD HARRIS Eastwood Harris Pty Ltd i Copyright 1999 2010 by Eastwood Harris Pty Ltd. No part of this publication may be reproduced or used
Project 2010 Introduction
Microsoft Application Series Project 2010 Introduction Best STL Courses never cancelled: guaranteed Last minute rescheduling 24 months access to Microsoft trainers 12+ months schedule UK wide delivery
Microsoft Access 2010 handout
Microsoft Access 2010 handout Access 2010 is a relational database program you can use to create and manage large quantities of data. You can use Access to manage anything from a home inventory to a giant
Sample Table. Columns. Column 1 Column 2 Column 3 Row 1 Cell 1 Cell 2 Cell 3 Row 2 Cell 4 Cell 5 Cell 6 Row 3 Cell 7 Cell 8 Cell 9.
Working with Tables in Microsoft Word The purpose of this document is to lead you through the steps of creating, editing and deleting tables and parts of tables. This document follows a tutorial format
Open Workbench. User Guide. v2.0.00
Open Workbench User Guide v2.0.00 This documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation ) is for your informational
PERCEPTION PERT-PAC Using Microsoft Project 2000
PERCEPTION PERT-PAC Using Microsoft Project 2000 to Plan & Schedule A Training Tutorial (Sample Hull Block Construction) 1 This training tutorial outlines the basic features of the Microsoft Project 2000
Getting Started with Access 2007
Getting Started with Access 2007 1 A database is an organized collection of information about a subject. Examples of databases include an address book, the telephone book, or a filing cabinet full of documents
Appendix A: Brief Guide to Microsoft Project 2010
1 Appendix A: Brief Guide to Microsoft Project 2010 from Revised An Introduction to Project Management, Third Edition By Kathy Schwalbe Professor, Augsburg College Department of Business Administration
Project Management Quick Reference Guide for MS Project 2010
Project Management Quick Reference Guide for MS Project 2010 Project 2010 offers flexibility and choice by providing tailored work management solutions for individuals, teams, and the enterprise. Besides
Lesson 07: MS ACCESS - Handout. Introduction to database (30 mins)
Lesson 07: MS ACCESS - Handout Handout Introduction to database (30 mins) Microsoft Access is a database application. A database is a collection of related information put together in database objects.
Basic Pivot Tables. To begin your pivot table, choose Data, Pivot Table and Pivot Chart Report. 1 of 18
Basic Pivot Tables Pivot tables summarize data in a quick and easy way. In your job, you could use pivot tables to summarize actual expenses by fund type by object or total amounts. Make sure you do not
Scheduling Document Creation
Scheduling Document Creation What is a Schedule in epm? Schedules The epm Schedule application is an integral part of the Portfolio Management suite of applications. Start and end dates for each summary
Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)
Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) CONSTRUCTION DIVISION (SCHEDULING & CONTRACTS) 1. INTRODUCTION To establish standards and consistent scheduling practices
Word 2007: Basics Learning Guide
Word 2007: Basics Learning Guide Exploring Word At first glance, the new Word 2007 interface may seem a bit unsettling, with fat bands called Ribbons replacing cascading text menus and task bars. This
Creating a Database in Access
Creating a Database in Access Microsoft Access is a database application. A database is collection of records and files organized for a particular purpose. For example, you could use a database to store
TILOS GETTING STARTED & EXERCISES
TILOS GETTING STARTED & EXERCISES 1. Release 2010-03 TILOS 7.0 Created by Linear project GmbH Training Support Software Development For further information please contact: ----------------------------------------------------------------------------------------------
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
Virto SharePoint Gantt Chart App for Office 365 Release 1.0.3. User and Installation Guide
Virto SharePoint Gantt Chart App for Office 365 Release 1.0.3 User and Installation Guide 2 Table of Contents OVERVIEW... 3 FEATURES LIST... 3 SYSTEM/DEVELOPER REQUIREMENTS... 3 OPERATING SYSTEM... 3 SERVER...
Mail Merge Creating Mailing Labels 3/23/2011
Creating Mailing Labels in Microsoft Word Address data in a Microsoft Excel file can be turned into mailing labels in Microsoft Word through a mail merge process. First, obtain or create an Excel spreadsheet
Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet
Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Assistance PSA: Advanced Functionalities Welcome to the Advanced Functionalities
Mac Outlook Calendar/Scheduler and Tasks
Introduction Schedule an event and/or meeting. Schedule all-day and recurring events. Assign tasks to another user and use special shortcut keys. Contents Introduction Contents Calendar View Edit an appointment
POS Connector Installation and Setup Guide
POS Connector Installation and Setup Guide Contents About POS Connector for Small Business Accounting... 1 What is POS Connector?... 1 How does POS Connector work?... 1 Is POS Connector easy to install
To export data formatted for Avery labels -
Information used to create labels in the Client Data System (CDS) can be exported out of CDS and used to create labels in Microsoft Word, making it possible to customize the font style, size, and color.
Microsoft Project 2007 Tutorial Boston University. Boston University, Dept of Administrative Sciences, Project Management Programs (2010)
Microsoft Project 2007 Tutorial Boston University Boston University, Dept of Administrative Sciences, Project Management Programs (2010) 1 2 Microsoft Project 2007 Tutorial Boston University Contents Table
Creating Web Pages With Dreamweaver MX 2004
Creating Web Pages With Dreamweaver MX 2004 1 Introduction Learning Goal: By the end of the session, participants will have an understanding of: What Dreamweaver is, and How it can be used to create basic
Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start
Project Management is the discipline of planning, organizing, and managing resources to complete a specific goal. Microsoft Project is software that helps you. Start your project Open Project 2010 and
Step Sheet: Creating a Data Table and Charts
Step Sheet: Creating a Data Table and Charts Using Microsoft Excel Spreadsheets with Data This step sheet will help you build a data table and convert the data into histograms and circle graphs for your
ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5
Table of Contents ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 IMPORT A TASK LIST FROM AN EXCEL FILE INTO A NEW PROJECT PLAN... 6 Import a Task List
5. Creating a Gantt Chart
5. Creating a Gantt Chart Whilst the network diagram is a useful way to describe how tasks are linked to each other, the Gantt chart is used to display the schedule of a project. The Gantt chart is the
INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9
Contents Contents INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9 IMPORT UPDATES 12 CUSTOM TEXT FIELDS MAPPING 13
Handout: Word 2010 Tips and Shortcuts
Word 2010: Tips and Shortcuts Table of Contents EXPORT A CUSTOMIZED QUICK ACCESS TOOLBAR... 2 IMPORT A CUSTOMIZED QUICK ACCESS TOOLBAR... 2 USE THE FORMAT PAINTER... 3 REPEAT THE LAST ACTION... 3 SHOW
Aras Corporation. 2005 Aras Corporation. All rights reserved. Notice of Rights. Notice of Liability
Aras Corporation 2005 Aras Corporation. All rights reserved Notice of Rights All rights reserved. Aras Corporation (Aras) owns this document. No part of this document may be reproduced or transmitted in
Microsoft Excel Basics
COMMUNITY TECHNICAL SUPPORT Microsoft Excel Basics Introduction to Excel Click on the program icon in Launcher or the Microsoft Office Shortcut Bar. A worksheet is a grid, made up of columns, which are
Creating Electronic Portfolios using Microsoft Word and Excel
Step-by-Step Creating Electronic Portfolios using Microsoft Word and Excel The Reflective Portfolio document will include the following: A Cover Page for the portfolio - Include a Picture or graphic A
How To Manage A Project With Project Management On M Project Software On A Pc Or Macbook 2.5 (Windows)
Project management M project tutorial Part 1: Project beginning and the Gantt chart Purpose Project management by using Microsoft Project software Introduction Project management is a process of organizing,
Every project requires communication and collaboration and usually a lot of
Collaborating on Projects with SharePoint CHAPTER 25 Every project requires communication and collaboration and usually a lot of both. With small project teams, you and your team members may interact in
Excel Pivot Tables. Blue Pecan Computer Training Ltd - Onsite Training Provider www.bluepecantraining.com :: 0800 6124105 :: [email protected].
Excel Pivot Tables 1 Table of Contents Pivot Tables... 3 Preparing Data for a Pivot Table... 3 Creating a Dynamic Range for a Pivot Table... 3 Creating a Pivot Table... 4 Removing a Field... 5 Change the
Introduction to Microsoft Access 2007
Introduction to Microsoft Access 2007 Introduction A database is a collection of information that's related. Access allows you to manage your information in one database file. Within Access there are four
Intro to Excel spreadsheets
Intro to Excel spreadsheets What are the objectives of this document? The objectives of document are: 1. Familiarize you with what a spreadsheet is, how it works, and what its capabilities are; 2. Using
Microsoft Project Activity
Microsoft Project Activity Purpose: The goal of this activity is to lead you through the most important data entry and formatting activities in MS Project and to provide you with the fundamental knowledge
ACCESS 2007 BASICS. Best Practices in MS Access. Information Technology. MS Access 2007 Users Guide. IT Training & Development (818) 677-1700
Information Technology MS Access 2007 Users Guide ACCESS 2007 BASICS Best Practices in MS Access IT Training & Development (818) 677-1700 Email: [email protected] Website: www.csun.edu/it/training Access
4.0 - Using the Microsoft Project Plan
4.0 - Using the Microsoft Project Plan 153 4.0 - Using the Microsoft Project Plan 1.0 Introduction to PM 2.0 Plan Project 21 2.1 22 2.2 23 2.3 Prepare Estimates Develop WBS Develop Schedules 3.0 Manage
Getting Started with Excel 2008. Table of Contents
Table of Contents Elements of An Excel Document... 2 Resizing and Hiding Columns and Rows... 3 Using Panes to Create Spreadsheet Headers... 3 Using the AutoFill Command... 4 Using AutoFill for Sequences...
1. INTRODUCTION...2 2. PRODUCT...2. 2.1. Installation... 2 2.2. Documentation... 2 2.3. Website... 2. 3. workbench features...2
Table of Contents 1. INTRODUCTION...2 2. PRODUCT...2 2.1. Installation... 2 2.2. Documentation... 2 2.3. Website... 2 3. workbench features...2 3.1. Project Planning... 2 3.2. Project Tracking... 3 4.
MERLIN. The Quick Start Guide to professional project management. 2013 ProjectWizards GmbH, Melle, Germany. All rights reserved.
MERLIN The Quick Start Guide to professional project management 2013 ProjectWizards GmbH, Melle, Germany. All rights reserved. INTRODUCTION Welcome to the quick start guide to Merlin! Thank you for choosing
Avery Wizard: Using the wizard with Microsoft Word. This is a simple step-by-step guide showing how to use the Avery wizard in word
Avery Wizard: Using the wizard with Microsoft Word This is a simple step-by-step guide showing how to use the Avery wizard in word Open up a blank document in Microsoft Word and click the Avery Tab at
Open Workbench Warrior. Beginner's Guide to Open Workbench
Open Workbench Warrior Beginner's Guide to Open Workbench Table of Contents Introduction...3 Open Workbench Functionality...3 Project Planning...3 Project Tracking and Management...3 Sample Project...3
As in the example above, a Budget created on the computer typically has:
Activity Card Create a How will you ensure that your expenses do not exceed what you planned to invest or spend? You can create a budget to plan your expenditures and earnings. As a family, you can plan
Advanced Presentation Features and Animation
There are three features that you should remember as you work within PowerPoint 2007: the Microsoft Office Button, the Quick Access Toolbar, and the Ribbon. The function of these features will be more
Review on Using Packages to Enhance the Teaching of Critical Path Networks
Review on Using Packages to Enhance the Teaching of Critical Path Networks Harry S Ku Abstract The aim of this paper is to review a published paper, Using computer software packages to enhance the teaching
Microsoft Outlook 2013 Part 1: Introduction to Outlook
CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Outlook 2013 Part 1: Introduction to Outlook Fall 2014, Version 1.0 Table of Contents Introduction...3 Starting Outlook...3
Snap 9 Professional s Scanning Module
Miami s Quick Start Guide for Using Snap 9 Professional s Scanning Module to Create a Scannable Paper Survey Miami s Survey Solutions Snap 9 Professional Scanning Module Overview The Snap Scanning Module
Basic Formatting of a Microsoft Word. Document for Word 2003 and 2007. Center for Writing Excellence
Basic Formatting 1 Basic Formatting of a Microsoft Word Document for Word 2003 and 2007 Center for Writing Excellence Updated April 2009 Basic Formatting 2 Table of Contents GENERAL FORMATTING INFORMATION...