INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS

Size: px
Start display at page:

Download "INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS"

Transcription

1 INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS What is a Project... 2 The Steps involved in Setting up a Project... 3 Views... 4 How To Start a new project... 6 The Gantt Chart... 8 Outlining/Summary tasks Assigning Task Relationships Task Calendars Resources Resource Costs Calendars Scheduling with Resources Resource Overallocations Deadlines and Task Constraints Setting A Baseline Tracking Applying Filters & Sorting Data Printing and Reports Previewing and Printing Reports

2 WHAT IS A PROJECT A project is a well-defined sequence of events with an identifiable beginning and ending. A project is different from a process in that there is always a point when the project is complete and the goal has been met. The Need for Project Management Project Management is the planning, organising and managing of tasks and resources to accomplish a defined objective, usually with the constraint of time and cost. Project Management helps you to answer: How long the project will take. The impact on the overall project if a task is delayed. Which tasks are critical? Are sufficient resources allocated to the project to complete on time? The resource costs of the project. Is the project on schedule? Project Management can be broken down into three phases: Creating the project plan Identifying the tasks to be completed and organising the resources available to complete the tasks. Managing the project Ensuring that the allocated resources complete the defined tasks on schedule and within budget Progress reporting Producing reports on project progress. 2

3 THE STEPS INVOLVED IN SETTING UP A PROJECT 1. Set a schedule Create a workday and holiday schedule. 2. Define the project goals and determine what needs to be done. 3. Determine the sequence of tasks. Break the project into phases and subdivide phases into tasks. Identify Project Milestones. Estimate the duration of each task. Which tasks can be completed before others? Which tasks can be completed at the same time? Define task constraints. 4. Assign resources: Who is needed for each task? What equipment is needed for each task? What facilities are necessary? 5. Review the plan Verify the accuracy and completeness. Circulate the plan for review. 6. Additional Planning Issues Budget and cost constraints. Who else needs project status information? What are the consequences of missing deadlines? Critical Path Method (CPM) This refers to a mathematical model that takes into account the relationships between tasks, their duration and any constraints regarding the availability of resources to identify which tasks are critical. A task is critical when its delay could effect the end date of the project. Program Evaluation Review Technique (PERT) A PERT chart, sometimes called a network chart, refers to the graphic representation of how the tasks are linked to one another. This chart is useful when it is more important to focus on the relationships between tasks rather than the time schedule. Gantt Chart Henry L Gantt developed a graphic charting system to depict activities across a time scale. The Gantt chart can be used in Microsoft Project to build a project as well as track and report it. 3

4 VIEWS A view is a format in which you enter and display information. The Gantt Chart view is the default view. It is made up of the Entry table on the left, used to enter task information and the Gantt chart on the right. Views fall into three categories: Sheet views Chart and Graph views Form views Views are displayed in single or combination format. A combination view displays any two single views together. Changing Views Project comes with 24 predefined views. You can use the View Menu to change views or the View bar located on the left side of the project window. The View Bar lists eight of the most commonly used view which are described below: 4

5 View Name Calendar Description A monthly calendar showing tasks and their duration's. Use this view to show the tasks scheduled in a specific week or range of months. Gantt Chart A list of tasks and related information and a chart showing tasks and their duration's over time. This is the most commonly used view to enter and schedule a list of tasks. Network Diagram A network diagram showing all tasks and task dependencies. Use this chart to create and fine-tune your schedule in a flowchart format. Task Usage A list of tasks showing assigned resources grouped under each task. Use this view to see which resources are assigned to specific tasks and to view resource work contours. Tracking Gantt Resource Graph A list of task and related information and a chart showing baseline and scheduled Gantt bars for each task. Use this view to compare the baseline and schedule with the actual schedule. A graph showing resource allocation cost or work. Use this view to display information about a single resource or group of resources over time. Resource Sheet A list of resources and related information. Use this view to enter and edit resource information in a spreadsheet like format. Resource Usage A list of resources showing task assignments grouped under each resource. use this view to show cost or work allocation information over time for each resource per assignment and to set resource work contours. More Views Opens the More Views dialog box which displays a list of every view available. 5

6 HOW TO START A NEW PROJECT There are three activities that need to be completed before you enter individual project tasks: 1. Setting the Project Properties 2. Entering project working times and non working times 3. Setting the file properties The Project Properties If you don't enter a project start date or finish date, Microsoft Project automatically uses the current date as the start date. 1. From the Project Menu select Project Information 2. Enter a start date To enter a start date Type the date on which you want to start your project in the Start date box. To enter a finish date Click Project Finish Date in the Schedule from box, and then type a finish date from which to schedule your project in the Finish date box. Tip: If your plans change, you can change your project information at any time by clicking Project Information on the Project menu. Project uses the Current Date to calculate variances between baseline data and scheduled data unless there is a date in the Status Date field. The Calendar setting is used to change the Base calendar that Project uses to calculate how long the project will take to complete. 6

7 Setting File Properties This is an optional activity but is useful because the options you enter can be used in header and footer details for printing and reporting Choose File, Properties The properties dialog box is displayed Enter text into the headings that you might wan to use later. You should a least enter the Title and Author. Entering the project working times This involves setting the options and working times in the standard calendar that all other calendars use as a default. Choose Tools, Change Working Time Make sure that Standard project calendar is selected in the For drop down list. The default work times are 8am to Noon and 1pm to 5pm Monday to Friday, Fifty-two weeks of the year. Eight working hours per day with an hour for lunch. Change these settings to reflect you Organisations requirements. You do this by clicking the Details button to enter the working hours for the organisation as shown. Click the Exceptions tab to enter the non-working time for the company. EG: Public holidays. Click on the Options button to make any changes to the Calendar options. Important to set these as you need to tell how many hours in the working day, week and month. 7

8 These should be in sync with your Standard Calendar. The most important calendar options are those that define a workday, week and month. Microsoft Project makes all its duration and other time calculations based on minutes and then uses the values entered in the calendar options to convert the minutes into day, week and month units. It is important that you tell project how to define these time intervals. THE GANTT CHART The first view that you see when you enter Project is the Gantt Chart. When you first enter tasks they all appear left aligned in the Gantt chart. This is because no task relationships have yet been established between the tasks. To Enter Tasks and Durations The Gantt Chart consists of a table on the left and a bar chart on the right. Type the name of the task in the Name column Type the duration of the task in the Duration column. Tasks are measured in terms of how long they will take, Project accepts: m h d w mo for minutes for hours for days for weeks for months If you are unsure about the time it will take to complete a task enter a? after the duration and Project marks this as an estimated duration. Overtype the duration again to remove the question mark. 8

9 Applying Elapsed Duration Elapsed duration is a type of duration that you can use when the activity or task continues around the clock, irrespective of the workday hours. For example, a ship carrying parts to a manufacturing plant doesn t stop sailing at the end of the day. If it takes 14 hours for the ship to sail from one port to another you can enter 14eh, where the e indicates elapsed duration. Milestones Tasks with duration of Zero are set as milestones. Milestones usually represent the completion of an event, phase or other measurable goal within the project. When duration is entered as zero the Gantt bar changes to a diamond shaped marker. Critical Tasks A critical task is defined as a task, which if delayed, will delay the end date and time of the project. Critical tasks are shown as a red bar on the Gantt Chart. Non Critical Tasks A non-critical task is defined as a task, which if delayed, will not have an affect on the project end date. To Widen the Task Column If the name of the task is too long to display in the Name column: Move the mouse until it is on the vertical line between the Name and Duration titles. The mouse pointer will change to a double-headed arrow. Drag the mouse to the right to increase the column width or double click when the double-headed arrow appears and the column width is automatically resized to best fit the contents Moving Around the Table The vertical scroll bar can be used to view up and down through the task list. To go to a specific task or different date press F5 and enter the required date or task number. The keyboard direction arrows can also be used to move to specific tasks. Ctrl+Home will move you to the first task on the list. 9

10 Recurring Tasks A recurring task is a task that occurs repeatedly within a project. This could be a weekly meeting, a status report or regular inspections. Instead of typing the task repeatedly within a schedule a recurring task needs only be entered once. A recurring task can be set to repeat daily, weekly, monthly or yearly 1 Click in the task name for the task that you want the recurring task to appear above. 2 Select Insert, Recurring Task. 3 Fill in the appropriate details OUTLINING/SUMMARY TASKS Projects can be broken down into manageable portions by either using outlining to split tasks into logical groups, or you can create sub-projects, which can be set up as different tiles but linked to the main project. Sub-Projects are detailed as a separate section later in this manual. When you create your project you will have Phases, known as summary tasks and the tasks needed to complete those phases, known as subordinate tasks. Summary tasks are descriptive headings, subordinate tasks are details. A summary task is completed only when all the subordinate tasks have been completed. Icon Outdent Description Outdents a task to a higher level. Indent Show Subtasks Indents a task to a lower level. Indenting creates a summary task above. Expands a summary task. Hide Subtasks Collapses a summary task. Show Select the outline level that you want to display or select the top option to show all tasks. 10

11 You can have up to 65,000 levels on outline mode. When you use the Edit Cut or Edit Copy commands to move a summary task, all of its subordinate tasks are moved with the summary task. If you want to move only the summary task, promote the subtasks first. Summary Task Summarises the cost, work and schedule information of the other tasks showing the total duration between the starting point of the earliest task and the finish of the latest task for the five subordinate tasks. Subtasks Any tasks that have been demoted below a summary task. Formatting an Outline The Tools, Options, View tab allows you to control how the outline is displayed on the Task sheet. If a check appears in the box, the option is turned on. Click in the required box to turn the option on or off. Show Summary Tasks Indent Name Show Outline Number Show Outline Symbol Project Summary Task The display of summary tasks can be turned on or off Name indented to reflect their outline levels. Outline numbers are used to represent the task s position within the outline. The numbering system used is similar to the numbers used in legal documents or procedure manuals. Shows a + symbol if there are tasks that are not being displayed below the current outline level. Shows a symbol to indicate all levels are displayed. Inserts a Task a task with an ID of 0 and the name of the project at the top of the task list. 11

12 Reorganising Summary Tasks When you move a summary task Microsoft Project moves all of its subordinate tasks To Move a Summary Task Select the row containing the summary task by clicking on the row number preceding the name of the task. Select Edit, Cut. Select the row where you want to move the summary task to. Select Edit, Paste Collapsing and Expanding an Outline One of the most useful features of outlining is that you can collapse or expand summary tasks to hide or display their subordinate tasks to control the amount of detail that displays on the screen or for printing the project. When collapsed, the tasks still exist in your project. Collapsing and expanding only affects the tasks you see on your computer screen. To Collapse Part of an Outline Select the summary task or tasks that you want to collapse. Click on the Collapse button or double click on the ID number of the summary task. To Expand Part of an Outline Select the summary task or task that you want to expand. Click on the Expand button or double click on ID number of the summary task. To Expand the Outline for the Entire Project Click on the Show All subtasks button 12

13 ASSIGNING TASK RELATIONSHIPS Microsoft Project lets you set up task relationships so that you can make one task s start or finish date dependant upon another task s start or finish date. A task that must be started or finished before another task can begin is called a predecessor task. A task that can only start or finish after another task has finished is called the successor task. Task Relationships FS SS FF Finish to Start Start to Start Finish to Finish Task A Task B Task A Task B Task A Task B Linking Tasks with a Finish to Start Relationship Select the tasks to be linked and choose Edit, Link Tasks or click on the Link button on the standard toolbar. This links the tasks with a finish to start relationship. Lead and Lag You may wish to build in lead and lag times into your plan. In a finish to start relationship, an overlap between tasks is called a lead-time and a gap or time delay between two tasks is called a lag. Lead times are entered as negative numbers. To Enter Task Relationships in the Task Form Fields To display the Task form quickly, double click on the horizontal split bar on the vertical scroll bar. Select the task to which you want to assign a predecessor on the Gantt Chart. Click the Predecessor ID field at the bottom of the Task Form. Type the predecessor task ID number. 13

14 If you want a task relationship other than finish to start, type the abbreviation in the Type field. If you want to add a lead or lag time, enter it in the Lag field. If you want a one day gap between one task starting and one task finishing enter 1d. If you want a one day overlap between two tasks enter 1d. TASK CALENDARS By default, your tasks are scheduled by the project calendar. Task calendars define unique or specific exceptions for scheduling individual tasks, such as machinery that runs during nonworking time. Create a calendar for a task 1 On the Tools menu, click Change Working Time. 2 Click New. 3 In the Name box, type a name for your new calendar. 4 To begin with a default calendar, click Create new base calendar. To create a new base calendar based on an existing calendar, click Make a copy of, and then click the calendar name in the calendar box. 5 Click OK 6 Make the required changes to the calendar: To change the calendar on specific days. Click the Details button and select the days on which you wish to make the change. To select nonadjacent days, hold down CTRL and click the days. To select adjacent days, hold down SHIFT and click the first and last day for the calendar change. Under Set selected date(s) to, click Use Default, Nonworking time, or Nondefault working time. 14

15 To Assign a Calendar to a Task 1 On the View menu, click Gantt Chart. 2 In the Task Name field, double click the task to which you want to assign a calendar. 3 Click the Advanced tab. 4 In the Calendar box, click the calendar you want to use for the task. 5 Select the Scheduling ignores resource calendars check box to have the task calendar ignore all resource calendars if applicable. If you choose to have Microsoft Project ignore resource calendars, a task will be scheduled even if resources assigned to the task have nonworking time set in their resource calendar. Assign a calendar to a recurring or summary recurring task In the Task Name field, double click the recurring or summary recurring task to which you want to assign a calendar. Click Recurring Task Information In the Recurring Task Information dialog box, click the calendar you want to assign to the recurring task in the Calendar box. Select the Scheduling ignores resource calendars check box to have the task calendar override all resource calendars if applicable. The duration of a task is based on the combination of the standard, resource, or task calendar assigned. 15

16 RESOURCES A resource can be any item, place or person necessary to completing the task. A task might require a single resource or multiple resources to be completed. Resource names can be generic or specific in their description. For example a resource that performs administrative duties could be called Admin Assistant or Pat Robins. How you name your resources depends on the project and the scheduler's preference but whatever method you choose make sure you are consistent. For example, the resource John is only one resource, whilst the resource Mechanic could be one person or a team. When a resource is assigned to a task a single unit or 100% is entered into the Max units field. This can be changed if you are entering a team as a single entry. You can enter a value of less than 100% if you wish. You can assign a single unit, partial unit or multiple units of a resource to a task but you shouldn't assign more units of a resource than you have available in the project. Material Resources Material resources are materials consumed in the completion of a task as opposed to equipment used to complete a task. Entering Resources You can enter resources in several different locations. The two most common locations are the Assign Resources dialog box and the Resource Sheet. Assign Resource Dialog Box Click on the Assign Resources button and the Assign Resources Dialog box appears. Type the name of the resource in the name box and press Enter to move to the next row. Type the next name in the next row and repeat until you have entered all the required resources. Click Close. 16

17 The Resource Sheet The Resource sheet can be used for entering information about more than one resource quickly. This method can be used if you know the names of the majority of resources you are going to use before you start assigning resources to tasks. 1 Click the Resource Sheet Icon on the View Bar 2 Enter the name of the resource in the name field and then any additional resource information as required. Note, the resource sheet can be customised by changing the column headings, inserting and deleting columns or changing the order of the columns The default Resource Sheet has the following column headings: Name Type Material Label Initials Group Max. Units Std Rate Ovt Rate Cost/Use Accrue At Base Calendar Code The name of the resource. The type of resource Work or Material The unit of measurement for a material resource: tons, pounds, items, gross etc. The abbreviated name for the resource. A name that is useful for grouping resources that can be used for sorting and filtering. The total number of resource units available. Standard wage, salary or rate for the resource. Overtime rate for the resource. Cost amount per use of each resource unit. Accrual method for costs; start, end or prorated. Choose a calendar from the Calendars available. An identification code, such as an accounting code that you might want to use for sorting, filtering or reporting. 17

18 Assigning Work Resources 1 Select the task you want to assign a resource or resources to. 2 Click on the Assign Resources button and the assign resources dialog box appears 3 Select the required resource and click assign. 100% of that resource is assigned by default. You can change the percentage assignment, if you wish, in the Units field. Note you can select more than one resource by clicking and dragging over the required resource names or by holding down the CTRL key whilst you click on each required resource to make multiple selections You can assign one resource to more than one task by selecting all of the required tasks before you click on the assign button on the Resource Assignment dialog box. Assigning Material Resources Assigning Variable Material Consumption Variable material consumption is used when material consumption is increased as the task duration changes. They are assigned at an amount per time. For example, if you were assigning fuel for a generator the amount of fuel used would be dependant upon the length of time the generator was need for. If the generator uses an average of 2 litres per hour then when the fuel was assigned to a task you would enter 2/h in the units field for the fuel. The suffixes /m /h /d/ /w or /mon can be used to indicate time usage. Assigning Fixed Material Consumption This method assumes that the amount consumed is not related to the duration of the task. For example, you may have ordered a fixed amount of Topsoil for a landscaping project which is not dependant upon how long it will take to distribute the topsoil. When you assign a fixed amount of material to a task you just enter the number of units that will be consumed on the task. 18

19 The Resource Information Dialog Box (General) Double click on any resource name and the Resource Assignment dialog box appears You can use this box to enter the following additional resource information: Workgroup Available From and To dates Type in the box to specify the address for the resource. Select an option from the Workgroup box to specify the workgroup communication method used for the resource. Click From and then type dates in the From and To boxes to specify a range of dates that the resource is available for the project. If a resource is assigned to tasks outside of these dates, then Microsoft Project indicates that the resource is overallocated. 19

20 RESOURCE COSTS There are two types of costs in MS Project, resource costs and fixed costs. Each resource or task can have a cost associated with it. Resource costs can be accrued in several ways. They can be prorated by the hour or accrued at the end or the start of the task and an hourly rate might change during the duration of the project. A resource might also have a different hourly rate for different types of work. The resource sheet can be used to enter basic cost information. To enter additional resource cost information use the Costs tab in the Resource Information Dialog box. The Resource Information Dialog Box (Costs) Using variable resource rates you can track changes over time in a project. Variable resource rates are time stamped so that new rates are applied to the project at the appropriate time. You can enter up to 25 different resource rate changes in each of the five cost rate tables to support increases or decreases to the resource cost rates. By default, resources are assigned to tasks using the cost rate from table A. You can change the table in the Assignment Information dialog box. Rate changes can be entered as either a percentage or a number. The new rate is calculated by adding the old rate plus the percentage of the old rate. A negative percentage calculates a decrease from the old rate. 20

21 The Assignment Information Box 1 Select the Task Usage view form the view bar. 2 Double click on the Resource name that you want to change the cost table allocation and the Assignment Information Box appears. 3 Click the Cost Rate Table down arrow and select the appropriate table CALENDARS Calendars define the working and non-working time for the project and for each resource assigned in the project. As a change is made in the calendar Project automatically reschedules all tasks affected by the change. There are two types of calendars, base calendars and resource calendars. Base calendars define the working day for the project or a set of resources. Resource calendars define the working days and working hours for a specific resource. The default base calendar is called Standard. When a resource is added to a project a copy of the standard calendar is copied to create a resource calendar for each resource. Project comes with two other base calendars; the 24 hour and Nightshift calendars. You can also create new base calendars for groups of resources. Project has some default calendar options such as default start time and hours per day. These options are used to assign dates to tasks when no date or time is specified. If changes are made to the default calendar options then the base calendar will need to be updated with those changes. If the calendar options and base calendar do not reflect the same basic information then you might get a conflict between task and resource assignments. 21

22 The Calendar Options To view or change the default settings for the calendar options: 1. Select Tools, Options. 2. Click the Calendar Tab. 3. The default calendar options are displayed. The Base Calendar Base calendars specify the basic working days, hours and holidays for the entire project or for a group of resources. The standard Project calendar is set as follows: Monday to Friday, 08:00-17:00, one hour for lunch, no holidays. Tools, Change Working Time, allows you to modify the base calendar. You can select from the list of current calendars or create a new Base Calendar To Edit A Base Calendar 1 To change a day for the entire calendar, select one or more day titles across the top of the calendar. 2 To change a specific day or days click and highlight the required days below the day titles. 3 To specify a day as a working day click the required day and click on working option button. 4 To specify a day as non working click the required day and click on non working option button. To Edit a Resource Calendar Resource Calendars are used to track the availability of individual resources. Because a resource calendar begins as a copy of the base calendar assigned to the resource, only exceptions for that particular resource should be entered into the resource calendar. Changes to a resource calendar might include holidays, training or meetings. A resource calendar for equipment might include scheduled maintenance or downtime for cleaning. Resource calendars are edited in the same way as base calendars. Resource calendars are available in the Tools, Change Working Time dialog box or on the Working Time tab in the Resource Information dialog box. 22

23 Creating a New Base Calendar 1 Select Tools, Change Working Time 2 Click New. 3 The create new base calendar dialog box appears. Type the name of the calendar in the Name field. 4 You can either create a new base calendar or make a copy of the existing base calendar. 5 Click OK 6 A new calendar appears for the name you specified. Make the appropriate changes Assigning Resources to different Base Calendars Base Calendars can be assigned to resources on the Resource Sheet or in the Change Working Time tab in the Resource information dialog box. If changes have been made to a resource calendar and then a new base calendar is assigned, the resource calendar changes remain in effect. SCHEDULING WITH RESOURCES Effort Driven Scheduling When you assign or remove people from a task, Microsoft Project will extend or shorten the duration of the task to accommodate the additional or fewer resources applied to the task but it will not change the total work for the task. This is called effort-driven scheduling and is the default Microsoft Project uses to make resource assignments. As resources are added to a task, the total work on the task stays the same. The amount of work distributed to the resources assigned to the task, however, will change Effort-driven scheduling applies only to resources being added to or removed from a task. It does not apply to Microsoft Project's calculation rules when changing work, duration, and unit values for resources already assigned to tasks. When working with effort-driven scheduling, keep the following in mind: 23

24 The effort-driven calculations will apply only after the first resource is assigned to the task. Once a resource is applied, the work value will not change as new resources are assigned to or removed from the same task The effort-driven calculations will not be applied to multiple resources that are assigned at the same time and that are the first assignments on a task. After this initial assignment of multiple resources, however, the work value will not change as new resources are assigned to or removed from the same task. If the assigned task type is Fixed Units, then assigning additional resources will shorten the duration of the task. If the assigned task type is Fixed Duration, then assigning additional resources will decrease the individual unit values for resources. If the assigned task type is Fixed Work, then assigning additional resources will shorten the duration of the task Summary tasks and inserted projects cannot have the effort-driven setting turned on. Note: Previous versions of Microsoft Project behave as if effort-driven scheduling is turned off. Adding assignments in these earlier versions increased work, but did not alter the duration of the task To Turn off Effort Driven Scheduling As you assign or remove people from a task, Microsoft Project by default decreases or increases the duration of the task, but will not change the total work on the task. You may want to change this behaviour to more accurately reflect what happens on a particular task when resources are added or removed. For example, you may want to see the total work increase as you add more people to a particular task. 1 On the View Bar, click Gantt Chart. 2 In the Task Name field, double click the tasks for which you want to turn off effort-driven scheduling. 3 Click the advanced tab 4 Clear the Effort driven check box Tip You can turn off effort-driven scheduling for all tasks you create. On the Tools menu, click Options, click the Schedule tab, and then clear the New tasks are effort driven check box. 24

25 Task Types The task type Fixed Unit is the default task type in Project. When resources are added or removed from a fixed unit task the duration of the task is generally affected. However, designating a task as effort-driven or adding or removing resources determines the true effect on the tasks duration. Example Task X has a duration of 2 weeks, an initial resource assignment of one unit of Resource A, and total work of 80 Hours. The following table describes how a Fixed unit task accommodates resource and scheduling method changes after the initial assignments: Fixed Unit - Effort Driven Duration Units Work Add one unit of same Resource A 1 Week 200% Resource A 40 Hours Each 80 Hours Total Add one unit of different resource B 1 Week 100% Resource A 100% Resource B 40 Hours 40 Hours 80 Hours Total Fixed Unit - Without Effort Driven Duration Units Work Add one unit of same Resource A 1 Week 200% Resource A 80 Hours Each 160 Hours Total Add one unit of different resource B 2 Weeks 100% Resource A 100% Resource B 80 Hours 80 Hours 160 Hours Total 25

26 Modifying a Fixed Duration Task If a task has a fixed duration then the duration remains the same when resources are added or removed. The resource units or the total hours are affected on a fixed duration task depending on the scheduling method as illustrated below. Example Task X has a duration of 2 weeks, an initial resource assignment of one unit of Resource A, and total work of 80 Hours. The following table describes how a Fixed unit task accommodates resource and scheduling method changes after the initial assignments Fixed Duration - Effort Driven Duration Units Work Add one unit of same Resource A 2 Weeks 200% Resource A Add one unit of different resource B 2 Weeks 50% Resource A 50% Resource B 80 Hours Each 160 Hours Total 40 Hours 40 Hours 80 Hours Total Fixed Duration - Without Effort Driven Duration Units Work Add one unit of same Resource A 1 Week 200% Resource A 80 Hours Each 160 Hours Total Add one unit of different resource B 2 Weeks each Modifying a Fixed Work Task 100% Resource A 100% Resource B 80 Hours 80 Hours 160 Hours Total If a task has the task type Fixed Work, the total work for the task remains the same when resources are added or removed. The duration and the resource units are affected on a Fixed Work task. A Fixed Work task must be effort driven. 26

27 Example Task X has a duration of 2 weeks, an initial resource assignment of one unit of Resource A, and total work of 80 Hours. The following table describes how a Fixed unit task accommodates resource and scheduling method changes after the initial assignments: Fixed Work - Effort Driven Duration Units Work Add one unit of same Resource A 1 Week 200% Resource A 40 Hours Each 80 Hours Total Add one unit of different resource B How to Change the Task Type 1 Weeks 100% Resource A 100% Resource B 40 Hours 40 Hours 80 Hours Total 1 Select View, More View and apply the Task Entry View. 2 The Gantt Chart is displayed in the top pane and the task form in the bottom pane. 3 Select the task that you want to change and click on the down arrow beside Task Type on the Task Form. 4 Select the appropriate Task Type. RESOURCE OVERALLOCATIONS A resource conflict occurs when a resource is scheduled to perform more work than the resource can accomplish in the available working time. Viewing Resource Workloads and Task Assignments Viewing resource workload helps to identify to what extent a resource is overallocated or underallocated. When a Resource is overallocated the resource text is highlighted in red and in a resource view a levelling indicator is displayed. Use the Resource Usage view and Resource Allocation view to identify and resolve resource overallocations. The resource management toolbar provides tools for resolving resource overallocation as well as assigning resources. The following table describes the buttons on the Resource Management toolbar. 27

28 Button Resource Allocation View Task Entry View Description Displays the Resource Allocation view with the Resource Usage View in the top pane and the levelling Gantt in the bottom Displays the Task Entry view which consists of the Gantt Chart view in the top pane and the Task Form view in the bottom pane. Go To Next Overallocation Moves to the next overallocation Assign Resources Opens the Assign Resources dialog box. Share Resources Update Resource Pool Address Book Resource Details Using Resource Leveling Help Displays the Share Resources dialog box where resources can be made available to other projects. Updates the project resource pool. Displays the address book for locating resources. Displays the Properties dialog box for the selected resource. Filters for a resource's task with the Using Resource filter. Displays a set of procedures for leveling resources. Leveling Resource Conflicts Leveling is a strategy used to resolve resource overallocations by delaying or splitting tasks. Project examines overallocations by looking at task dependencies, slack time, dates, priorities, and constraints and determines if a task can be delayed or split to resolve a resource conflict. To Display the Resource Leveling Dialog Box From the Tools menu, select Level Resources There are three setting areas in the Resource Leveling dialog box: Leveling Calculations Area Leveling Range Resolving Overallocations Area 28

29 Leveling Calculations Area Project can be set to manually or automatically perform leveling and search for overallocations based on a time period. Manual Automatic Look for overallocations on a... Basis performs leveling only when the Level Now button is clicked. performs leveling as changes are made to the schedule. tasks are considered overallocated if the total assigned work exceeds the total work hours for the specified block of time. Leveling Range Entire Project - level the entire project range which is the default Specified Date Range - tasks that occur in the specified date range. Resolving Overallocations Leveling Order ID Only Standard Priority Standard checks tasks in ascending order by task ID number checks tasks in order of predecessor dependencies, slack times, dates, priority and then constraints checks task priority order first, predecessor dependencies, slack times, dates and then constraints Level Only Within Available Slack levels only those tasks that will not affect the project finish date. Leveling can adjust individual assignments on a task Leveling can create splits in remaining work levels a resource independent of any other resource working on a task. interrupts tasks by creating splits in the remaining work on tasks or resource assignments. 29

30 The Leveling Gantt View From the View menu, more views, levelling Gannt Bars that represent changes made to tasks and resource assignments during leveling are displayed in this view. Green Gantt bars indicate the scheduled start and finish dates for a task before leveling occurred. Blue Gantt bars represent the newly scheduled start and finish dates for tasks after leveling occurred. The olive lines indicate delay and the aqua lines indicate slack. To Remove the last leveling operation To remove the last leveling operation click go to Tools Menu, Level Resources, clear Leveling. You can do this for the entire project or just the selected tasks. Manually Resolve Resource Overallocations Using Project to perform leveling operations might not always be enough to completely resolve all the resource conflicts in a project. Some suggestions for manual leveling are as follows: Increase the maximum units of the resource Reschedule the task that has created the overallocation Add overtime Adjust dependencies or constraints Remove the resource if it isn't important to the task Replace the resource with another resource Make calendar adjustments to extend the working days and hours for the project or resource. Decrease the amount of work assigned to the resource. DEADLINES AND TASK CONSTRAINTS When a task is first entered into Project the task start date is the project start date. After tasks are linked and resources are assigned Project sets start and finish dates based on task dependencies and resource availability. This is the most effective way of scheduling because it incorporates flexibility. But, the projects need to reflect real life constraints. A constraint is a restriction imposed on the start or finish date. Constraints can be applied to a task by using the Advanced Tab on the Task Information dialog box. 30

31 Flexible Constraints Constraint Description Flexible For As Soon As Possible As Late As Possible Finish No Earlier Than Starts the task as soon as possible based on other constraints and dependencies. Starts the task as late as possible based on other constraints and dependencies. Finish the task on or after an entered date All projects All projects Projects scheduled from a start date. Start No Earlier Than Starts the task on or after an entered date. Projects scheduled from a start date. Finish No Later Than Start No Later Then Inflexible Constraints Finishes the task on or before an entered date Starts the task on or before an entered date. Projects scheduled from a finish date Projects scheduled from a finish date. Inflexible constraints are tied to a particular date and should be used less often because they take flexibility away from the schedule. The following table describes the types of constraints and when they are inflexible: Constraint Description Inflexible For Finish No Earlier Than Finishes the task on or after an entered date. Projects scheduled with a finish date. Start No Earlier Than Starts the task on or after an entered date. Projects scheduled from a finish date. Finish No Later Than Start No Later Then Finishes the task on or before an entered date Starts the task on or before an entered date. Projects scheduled from a start date Projects scheduled from a start date. Must Finish On Finishes the task on an entered date All Projects Must Start On Starts the task on an entered date All Projects 31

32 To Apply a Constraint 1 Select the task and double click on the task to display the Task Information dialog box. 2 Click the Advanced tab. 3 Click the Type down arrow and select the required constraint 4 Click the date down arrow and select the required date. 5 Click OK and a constraint indicator icon is displayed in the Indicator field to the left of the Task Name. Note: Project can move the start date beyond its constraint date. On the Tools menu, click Options. Click the schedule tab and then clear the Tasks will always Honour Their Constraint Dates check box. Task links will now take precedence over constraints. This means that if a constraint is set and there is no way you are going to meet that date then you can leave the constraint information in the project for documentation. When a Constraint Creates a Conflict When task constraints are set, conflicts occur that can affect the project finish date or task dependency. When a conflict occurs, the Planning Wizard appears and warns that a conflict or a potential conflict will exist if the constraint is applied. For example, if you are about to apply a Must Start on constrain the system see this as an inflexible constraint and warns you that you have three choices: Cancel and no constraint will be set. Continue, but a Start No Earlier constraint will be set Continue and a Must Start On constraint will be set. Setting a Deadline Rather than setting an inflexible constraint which might have a negative effect on the scheduling you can apply a Deadline date. A Deadline date is a date that you want or need the task completed by. Setting a Deadline does not affect the task scheduling in any way but Project places a downward pointing arrow on the Gantt Chart to indicate the Deadline and an indicator when the deadline is exceeded 32

33 To Set a Deadline Double click on the Task to display the Task Information Form. Select the Advanced Tab and Enter a Deadline Date. Troubleshooting If a project is being scheduled from a start date then entering a start date for a task or dragging the Gantt bar automatically sets a Start No Earlier Than constraint. If a finish date is entered, a Finish No Earlier Than constraint is automatically set. If a project is being scheduled from a fish date, entering a s start date for a task or dragging the Gantt bar automatically sets a Start No Later Than constraint. If a finish date is entered, a Finish No Later Than constraint is automatically set SETTING A BASELINE Once a project schedule has been created and the resource and task conflicts have been resolved the current schedule represents the best estimate of how the project should proceed and what resources it will take. Before the first task begins a baseline should be set. Setting the baseline is a critical step in the scheduling process. As a project progresses, the start times, finish times and resource assignments will change. A baseline is useful for comparing the planned schedule with later versions of the schedule to see what changes have occurred. To save a baseline When a baseline is set the data in the scheduled fields is copied over to the baseline fields. If a baseline is saved before the schedule planning is finished, a new baseline can be saved over the existing baseline. Select Tools, Tracking, Set Baseline Click OK. 33

34 Creating Interim Plans An interim plan is generally saved at certain stages in the project. These plans can then be compared to the baseline plan and the current schedule. The data saved in an interim plan includes the start and finish dates and any split dates but resource or assignment data is saved. 1 Select Tool, Tracking, Save Baseline. 2 Select Save Interim Plan option. The Copy and Into boxes are active. 3 Click the Copy down arrow and select the date fields to be copied. Usually the Start/Finish Fields. 4 Click the Into down arrow and select the date field to which you wish to copy. If this is the first interim plan for the project select Start1/Finish1. Each interim plan set after that goes to the subsequent Start/Finish number. 5 In the For area make sure the Entire Project is selected although you can set an interim plan for specific tasks if you wish. 6 Click OK. 34

OVERVIEW. Microsoft Project terms and definitions

OVERVIEW. Microsoft Project terms and definitions PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training

More information

ELECTRO-MECHANICAL PROJECT MANAGEMENT

ELECTRO-MECHANICAL PROJECT MANAGEMENT CHAPTER-9 ELECTRO-MECHANICAL PROJECT MANAGEMENT Y K Sharma,SDE(BS-E), 9412739241(M) E-Mail ID: yogeshsharma@bsnl.co.in Page: 1 Electro-mechanical Project Management using MS Project Introduction: When

More information

Microsoft Project 2013 Guide to Task and Resource Planning

Microsoft Project 2013 Guide to Task and Resource Planning Starting a Project The Microsoft Project 2013 Start screen Double click Blank Project, select a Recent project, or click Open Other Projects to work on a saved project stored on disk or on SkyDrive. To

More information

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects

More information

Planning and Scheduling Your Project Using Microsoft Project 2003

Planning and Scheduling Your Project Using Microsoft Project 2003 Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering sridhar@sastratechnologies.in Meeting Protocol Agenda Project File Project Calendar Creating

More information

Computer Training Centre University College Cork

Computer Training Centre University College Cork Computer Training Centre University College Cork Project 2013 Table of Contents What's new in Project 2013... 1 Manual scheduling... 1 Graphical Reports... 1 Trace task paths... 1 Easier view customization...

More information

MS Project 2000 Tutorial: Introduction

MS Project 2000 Tutorial: Introduction MS Project 2000 Tutorial: Introduction - Anjana Srikanth Stylus Systems is a Internet Technology company located in Bangalore India. One of our mottos is "a quality process creates a quality product."

More information

Lesson 6 - Managing Resources in a Project Plan

Lesson 6 - Managing Resources in a Project Plan Lesson 6 - Managing Resources in a Project Plan Lesson Objectives In this lesson, you will manage resources in a project plan. You will: Create a resource calendar. Assign resources to tasks. Assign additional

More information

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows)

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows) Overview 1 Content Overview Open a project file Create a new project plan Track progress View and print reports Share a project plan Conclusion 2 Overview With you can: create new/update project plan open

More information

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: harrispe@eh.com.au Australia Software

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Slides Slides Slides Steps to Enter Resource Types: 1. Click View and Resource Sheet 2. In the Type column of a resource, select Work, Material, or Cost, and press Enter on your keyboard Important

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

University of Sunderland. Microsoft Project. Basic Guide

University of Sunderland. Microsoft Project. Basic Guide University of Sunderland Microsoft Project Basic Guide 21/11/2008 A Course in using Microsoft Project Garry Storer Learning Objectives 1. What project management software is, basic concepts, the tasks

More information

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety

More information

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE Workshop Information Information Technology Services is happy to provide you with

More information

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project Microsoft Project 2007 Level 2: Working with Resources and Managing a Project By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS In Microsoft Project 2007 Level 1: Creating Project Tasks, the focus was

More information

Using MS Project in Translation Projects Management

Using MS Project in Translation Projects Management Using MS Project in Translation Projects Management When building a translation project plan, there must be taken into account: the tasks involved by the project, duration of each task, task dependencies,

More information

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 Table of Contents ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 IMPORT A TASK LIST FROM AN EXCEL FILE INTO A NEW PROJECT PLAN... 6 Import a Task List

More information

Microsoft Project 2007 Level 1: Creating Project Tasks

Microsoft Project 2007 Level 1: Creating Project Tasks Microsoft Project 2007 Level 1: Creating Project Tasks By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS Regardless of job title, most of us have needed to act as a project manager, at one time or another.

More information

MICROSOFT PROJECT 2010 - II

MICROSOFT PROJECT 2010 - II MICROSOFT PROJECT 2010 - II Course Material This 2-day course is for intermediate and advanced users of the MS Project scheduling application who want to increase their capabilities managing projects in

More information

Introduction to Microsoft Project 2010

Introduction to Microsoft Project 2010 Introduction to Microsoft Project 2010 This document provides an introduction in using Microsoft Project 2010. Microsoft Project is a project management application that contains a set of tools to help

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Document author: Produced by: Displaying a Critical Path Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project Preliminary 1. You must have Microsoft Project 2003 or higher installed to complete these procedures. 2. If necessary,

More information

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan. 2 In this chapter, you will learn how to: Start Microsoft Project Standard or Professional and save a new project plan. Enter task names. Estimate and record how long each task should last. Create a milestone

More information

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1 IT Training Microsoft Project Vicky Samways, IT Training Information System Services Version 2.1 Scope Learning outcomes Find out when and how to use Microsoft Project. Learn how to create a project, break

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Looking for schedule variances Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

MS Project 2007 Quick Guide

MS Project 2007 Quick Guide MS Project 2007 Quick Guide 1. Setup your project Add project information Determine project start date Check / Edit the standard/base calendar Check / Edit calendar calculation options Fine-tune your configuration

More information

Microsoft Project 2010 Advanced

Microsoft Project 2010 Advanced Microsoft Project 2010 Advanced Table Of Contents SECTION 1 - REFRESH OF THE BASICS... 3 GUIDE INFORMATION... 4 Introduction... 4 How To Use This Guide... 4 Objectives... 4 Instructions... 4 PROJECT INFORMATION

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Project management deliverables (e.g. reports); WBS deliverables can be used for report timing Steps to Create a Project from an Existing Template: 1. Click File then New. 2. Select any of the featured

More information

Project 2010 Introduction

Project 2010 Introduction Microsoft Application Series Project 2010 Introduction Best STL Courses never cancelled: guaranteed Last minute rescheduling 24 months access to Microsoft trainers 12+ months schedule UK wide delivery

More information

EXCEL 2007. Using Excel for Data Query & Management. Information Technology. MS Office Excel 2007 Users Guide. IT Training & Development

EXCEL 2007. Using Excel for Data Query & Management. Information Technology. MS Office Excel 2007 Users Guide. IT Training & Development Information Technology MS Office Excel 2007 Users Guide EXCEL 2007 Using Excel for Data Query & Management IT Training & Development (818) 677-1700 Training@csun.edu http://www.csun.edu/training TABLE

More information

Microsoft Project 70-178 Exam Study Guide

Microsoft Project 70-178 Exam Study Guide Microsoft Project 70-178 Exam Study Guide Prepared by The Versatile Company for MPUG. www.versatilecompany.com The Versatile Company, 2012. About this Study Guide This guide was developed based upon the

More information

Creating a New Project

Creating a New Project Creating a New Project Microsoft Project is a project management software program designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets,

More information

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0 ECDL European Computer Driving Licence Project Planning Project Management Software BCS ITQ Level 2 Using Microsoft Project 2013 Syllabus Version 1.0 This training, which has been approved by BCS, The

More information

PERCEPTION PERT-PAC Using Microsoft Project 2000

PERCEPTION PERT-PAC Using Microsoft Project 2000 PERCEPTION PERT-PAC Using Microsoft Project 2000 to Plan & Schedule A Training Tutorial (Sample Hull Block Construction) 1 This training tutorial outlines the basic features of the Microsoft Project 2000

More information

Using Microsoft Project 2000

Using Microsoft Project 2000 Using MS Project Personal Computer Fundamentals 1 of 45 Using Microsoft Project 2000 General Conventions All text highlighted in bold refers to menu selections. Examples would be File and Analysis. ALL

More information

Resource Allocation in MS Project

Resource Allocation in MS Project Resource Allocation in MS Project Calendars The project calendar determines the working days and hours available to your project, In addition each resource can have their unique calendars to mark time

More information

Tracking Project Progress

Tracking Project Progress L E S S O N 2 Tracking Project Progress Suggested lesson time 45-55 minutes Lesson objectives To begin tracking an active project, you will: a b c Modify the environment for tracking. You will use the

More information

Beginning Microsoft Project

Beginning Microsoft Project Beginning Microsoft Project BEGINNING MICROSOFT PROJECT...1 WHAT IS PROJECT? WHAT IS IT USED FOR?...1 PROJECT WINDOWS... 1 Views and Tables...1 PHASE 1: PLANNING AND SETTING UP PROJECT...2 PLANNING AND

More information

MICROSOFT PROJECT TUTORIAL

MICROSOFT PROJECT TUTORIAL MICROSOFT PROJECT TUTORIAL INTRODUCTION Microsoft Project is a Windows-based project management software package. It provides the flexibility to help manage your project, provides assistance in every phase

More information

Ohio University Computer Services Center August, 2002 Crystal Reports Introduction Quick Reference Guide

Ohio University Computer Services Center August, 2002 Crystal Reports Introduction Quick Reference Guide Open Crystal Reports From the Windows Start menu choose Programs and then Crystal Reports. Creating a Blank Report Ohio University Computer Services Center August, 2002 Crystal Reports Introduction Quick

More information

Session 6. Microsoft Project. Emanuele Della Valle. http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza

Session 6. Microsoft Project. Emanuele Della Valle. http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza Session 6 Microsoft Project Emanuele Della Valle http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza Credits 2 This slides are largely based on CEFRIEL s slides for PMI Certification and Prof.

More information

8. COMPUTER TOOLS FOR PROJECT MANAGEMENT

8. COMPUTER TOOLS FOR PROJECT MANAGEMENT 8. COMPUTER TOOLS FOR PROJECT MANAGEMENT The project management is a complex activity that requires among others: Information intercourse referred to the project, information that is in big amounts more

More information

Project 2013: An introduction

Project 2013: An introduction Project 2013: An introduction TPAF Revision Information Version Date Author Changes made 1.0 February 2013 Jean Glendinning Created 2.0 November 2013 Jean Glendinning Amended elements 3.0 Feb 2014 Jean

More information

Microsoft Project 2007 Tutorial Boston University. Boston University, Dept of Administrative Sciences, Project Management Programs (2010)

Microsoft Project 2007 Tutorial Boston University. Boston University, Dept of Administrative Sciences, Project Management Programs (2010) Microsoft Project 2007 Tutorial Boston University Boston University, Dept of Administrative Sciences, Project Management Programs (2010) 1 2 Microsoft Project 2007 Tutorial Boston University Contents Table

More information

Project 2010. Quick Reference. The Assignment Equation. EPM Architects www.epmarchitects.com

Project 2010. Quick Reference. The Assignment Equation. EPM Architects www.epmarchitects.com The Assignment Equation The following equation controls the relationship between the Work, Duration, and Assignment Units for a task assignment: Or Or Work: The number of hours of real work effort spent

More information

Microsoft Project 2010

Microsoft Project 2010 Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window

More information

Project Management: Intermediate Microsoft Project 2010

Project Management: Intermediate Microsoft Project 2010 Project Management: Intermediate Microsoft Project 2010 This document includes instructions for managing resources, updating project plans, and designing visual reports. Managing Resources in a Project

More information

Developing a Gantt and PERT Chart

Developing a Gantt and PERT Chart Developing a Gantt and PERT Chart October 2004 Edition UNITAR-executed GEF Medium-Sized Project, on behalf of UNDP Table of Contents Module 1. Creating a Gantt Chart Using MS Project... 1 Introduction...

More information

Tutorials. If you have any questions, comments, or suggestions about these lessons, don't hesitate to contact us at support@kidasa.com.

Tutorials. If you have any questions, comments, or suggestions about these lessons, don't hesitate to contact us at support@kidasa.com. Tutorials The lesson schedules for these tutorials were installed when you installed Milestones Professional 2010. They can be accessed under File Open a File Lesson Chart. If you have any questions, comments,

More information

Project Management Courses

Project Management Courses "A well planned project will give results exactly as planned." Project Management Courses Professional Development Training has a specialised division of Project Management experts that will tailor the

More information

Project planning with MindGenius

Project planning with MindGenius Project planning with MindGenius This workshop looks at using MindGenius for planning and monitoring smaller projects. MindGenius is available free of charge on all University of Brighton staff and student

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Slides Steps to Enter Duration: 1. In the Duration column of a task, enter a value, and press Enter on your keyboard Important Points: The default time unit is days, so when you enter 5, this becomes 5

More information

Business Objects Version 5 : Introduction

Business Objects Version 5 : Introduction Business Objects Version 5 : Introduction Page 1 TABLE OF CONTENTS Introduction About Business Objects Changing Your Password Retrieving Pre-Defined Reports Formatting Your Report Using the Slice and Dice

More information

MSP How to guide session 2 (Resources & Cost)

MSP How to guide session 2 (Resources & Cost) MSP How to guide session 2 (Resources & Cost) 1. Introduction Before considering resourcing the schedule it is important to ask yourself one key question as it will require effort from the scheduler or

More information

Getting Started with Excel 2008. Table of Contents

Getting Started with Excel 2008. Table of Contents Table of Contents Elements of An Excel Document... 2 Resizing and Hiding Columns and Rows... 3 Using Panes to Create Spreadsheet Headers... 3 Using the AutoFill Command... 4 Using AutoFill for Sequences...

More information

Revealing the Secrets of Microsoft Project

Revealing the Secrets of Microsoft Project 2 Revealing the Secrets of Microsoft Project To know that one has a secret is to know half the secret itself. Henry Ward Beecher Topics Covered in This Chapter Recognizing the Underlying Rules of Project

More information

Scheduling Document Creation

Scheduling Document Creation Scheduling Document Creation What is a Schedule in epm? Schedules The epm Schedule application is an integral part of the Portfolio Management suite of applications. Start and end dates for each summary

More information

Microsoft Project 2013. Microsoft Project 2013. The smart way to learn. Microsoft Project 2013. one step at a time!

Microsoft Project 2013. Microsoft Project 2013. The smart way to learn. Microsoft Project 2013. one step at a time! spine = 1.32 one step at a time! Experience learning made easy and quickly teach yourself how to manage the complete project life cycle with Project 2013. With Step by Step, you set the pace building and

More information

Open Workbench. User Guide. v2.0.00

Open Workbench. User Guide. v2.0.00 Open Workbench User Guide v2.0.00 This documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation ) is for your informational

More information

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 BY PAUL EASTWOOD HARRIS Eastwood Harris Pty Ltd i Copyright 1999 2010 by Eastwood Harris Pty Ltd. No part of this publication may be reproduced or used

More information

1 Start a new project

1 Start a new project Project Management Quick Reference Guide for Microsoft Project 2010 Before beginning a new project, an organization must determine whether the project fits its strategic goals. Executives should classify

More information

ECDL / ICDL Project Planning Syllabus Version 1.0

ECDL / ICDL Project Planning Syllabus Version 1.0 ECDL / ICDL Project Planning Syllabus Version 1.0 Purpose This document details the syllabus for ECDL / ICDL Project Planning. The syllabus describes, through learning outcomes, the knowledge and skills

More information

itaskx itaskx - MS Project compatible project management tool for Mac OS X MANUAL

itaskx itaskx - MS Project compatible project management tool for Mac OS X MANUAL itaskx itaskx - MS Project compatible project management tool for Mac OS X MANUAL itaskx Index 1.0 itaskx Brief Instruction 1.1 Tasks 1.1.1 1.1.2 1.1.3 1.1.4 1.1.5 1.1.6 1.1.7 1.1.8 1.1.9 1.2 Resources

More information

FastTrack Schedule 10. Tutorials Manual. Copyright 2010, AEC Software, Inc. All rights reserved.

FastTrack Schedule 10. Tutorials Manual. Copyright 2010, AEC Software, Inc. All rights reserved. FastTrack Schedule 10 Tutorials Manual FastTrack Schedule Documentation Version 10.0.0 by Carol S. Williamson AEC Software, Inc. With FastTrack Schedule 10, the new version of the award-winning project

More information

Making Visio Diagrams Come Alive with Data

Making Visio Diagrams Come Alive with Data Making Visio Diagrams Come Alive with Data An Information Commons Workshop Making Visio Diagrams Come Alive with Data Page Workshop Why Add Data to A Diagram? Here are comparisons of a flow chart with

More information

MICROSOFT OFFICE PROJECT - SYLLABUS

MICROSOFT OFFICE PROJECT - SYLLABUS MICROSOFT OFFICE PROJECT - SYLLABUS Sessions Session 1 Description 1. INTRODUCTION a. Introduction to CADFORUM and PPM b. Project c. Examples of project d. Project Triangle e. Project Management f. Life

More information

Excel 2010: Create your first spreadsheet

Excel 2010: Create your first spreadsheet Excel 2010: Create your first spreadsheet Goals: After completing this course you will be able to: Create a new spreadsheet. Add, subtract, multiply, and divide in a spreadsheet. Enter and format column

More information

SYSTEM ANALYSIS AND COMPUTER PROJECT MANAGEMENT Developing Engine Technology

SYSTEM ANALYSIS AND COMPUTER PROJECT MANAGEMENT Developing Engine Technology ROZWÓJ POTENCJAŁU I OFERTY DYDAKTYCZNEJ POLITECHNIKI WROCŁAWSKIEJ Wrocław University of Technology Advanced Informatics and Control Konrad Jackowski, Robert Burduk SYSTEM ANALYSIS AND COMPUTER PROJECT

More information

EXCEL PIVOT TABLE David Geffen School of Medicine, UCLA Dean s Office Oct 2002

EXCEL PIVOT TABLE David Geffen School of Medicine, UCLA Dean s Office Oct 2002 EXCEL PIVOT TABLE David Geffen School of Medicine, UCLA Dean s Office Oct 2002 Table of Contents Part I Creating a Pivot Table Excel Database......3 What is a Pivot Table...... 3 Creating Pivot Tables

More information

Excel 2003 Tutorial I

Excel 2003 Tutorial I This tutorial was adapted from a tutorial by see its complete version at http://www.fgcu.edu/support/office2000/excel/index.html Excel 2003 Tutorial I Spreadsheet Basics Screen Layout Title bar Menu bar

More information

T12. Excel and Microsoft Project. Introduction LEARNING OUTCOMES

T12. Excel and Microsoft Project. Introduction LEARNING OUTCOMES P L U G - I N T12 Creating LEARNING OUTCOMES Gantt Charts with Excel and Microsoft Project 1. Explain a Gantt Chart. 2. Describe the main steps involved in creating a Gantt Chart using Excel. 3. Describe

More information

MERLIN. The Quick Start Guide to professional project management. 2013 ProjectWizards GmbH, Melle, Germany. All rights reserved.

MERLIN. The Quick Start Guide to professional project management. 2013 ProjectWizards GmbH, Melle, Germany. All rights reserved. MERLIN The Quick Start Guide to professional project management 2013 ProjectWizards GmbH, Melle, Germany. All rights reserved. INTRODUCTION Welcome to the quick start guide to Merlin! Thank you for choosing

More information

Microsoft Project Server 2010 Project Manager s Guide for Project Web App

Microsoft Project Server 2010 Project Manager s Guide for Project Web App Microsoft Project Server 2010 Project Manager s Guide for Project Web App Copyright This document is provided as-is. Information and views expressed in this document, including URL and other Internet Web

More information

MICROSOFT PROJECT SOFTWARE FOR THE PROJECT SCHEDULING

MICROSOFT PROJECT SOFTWARE FOR THE PROJECT SCHEDULING MICROSOFT PROJECT SOFTWRE FOR THE PROJECT SCHEDULING ŠÁRK ČEMERKOVÁ Silesian University in Opava School of usiness dministration in Karviná Department of Mathematical Methods in Economics Czech Republic

More information

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle. Planning and Managing Software Projects 2011-12 Class 10 Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

More information

Before starting this section

Before starting this section Before starting this section SAVE AS YOUR EXISTING MS PROJECT FILE AS -part3-1 1.Click on View Entering Resources-1 Resource Sheet Entering Resources-2 Entering Resources-3 1.Click on the Resource

More information

Managing Projects. With. MinuteMan Project Management Software

Managing Projects. With. MinuteMan Project Management Software Managing Projects With MinuteMan Project Management Software Copyright 2011 by MinuteMan Systems Introduction This is a brief introduction to the use of Project Management Software to help you organize

More information

Basic Excel Handbook

Basic Excel Handbook 2 5 2 7 1 1 0 4 3 9 8 1 Basic Excel Handbook Version 3.6 May 6, 2008 Contents Contents... 1 Part I: Background Information...3 About This Handbook... 4 Excel Terminology... 5 Excel Terminology (cont.)...

More information

Time & Attendance Manager Basics

Time & Attendance Manager Basics Time & Attendance Manager Basics Handout Manual V03261272136EZ18CMB2 2012 ADP, Inc. ADP s Trademarks The ADP Logo, ADP Workforce Now, and ezlabormanager are registered trademarks of ADP, Inc. In the Business

More information

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft

More information

Introduction to Microsoft Access XP

Introduction to Microsoft Access XP Introduction to Microsoft Access XP Access is the database management system in Microsoft Office. A database is an organized collection of facts about a particular subject. An address book or a library

More information

Enterprise Interface User Guide

Enterprise Interface User Guide Enterprise Interface User Guide http://www.scientia.com Email: support@scientia.com Ref: 3094 ISO 9001:2000 / TickIT certified Copyright Scientia Ltd 2010 This document is the exclusive property of Scientia

More information

WORK PROGRAM GUIDELINES

WORK PROGRAM GUIDELINES Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment

More information

PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE. In An. Established Project Environment PAUL EASTWOOD HARRIS

PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE. In An. Established Project Environment PAUL EASTWOOD HARRIS PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE Planning and Progressing a Single Project Schedule With and Without Resources In An Established Project Environment BY PAUL EASTWOOD HARRIS Eastwood

More information

Microsoft Project 2013

Microsoft Project 2013 CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Project 2013 Summer 2014, Version 1.0 Table of Contents Introduction...2 Overview of the User Interface...2 Creating a

More information

WBS Schedule Pro. User's Guide

WBS Schedule Pro. User's Guide WBS Schedule Pro User's Guide Critical Tools, Inc. 2014 Table of Contents Overview of WBS Schedule Pro 7 What is WBS Schedule Pro? 7 What is a WBS chart? 9 What is a Network chart? 10 What's New in WBS

More information

Basic Microsoft Excel 2007

Basic Microsoft Excel 2007 Basic Microsoft Excel 2007 The biggest difference between Excel 2007 and its predecessors is the new layout. All of the old functions are still there (with some new additions), but they are now located

More information

Microsoft Project Activity

Microsoft Project Activity Microsoft Project Activity Purpose: The goal of this activity is to lead you through the most important data entry and formatting activities in MS Project and to provide you with the fundamental knowledge

More information

MS Project Tips and Tricks

MS Project Tips and Tricks MS Project Tips and Tricks ELLEN LEHNERT, MVP, PMP, MCT, MCITP CONSULTANT/INSTRUCTOR LEHNERTCS, LLC WWW.LEHNERTCS.COM ELLEN@LEHNERTCS.COM Ellen Lehnert, MVP, PMP, MCT, MCITP Background in teaching, Business

More information

Microsoft Access 2010 handout

Microsoft Access 2010 handout Microsoft Access 2010 handout Access 2010 is a relational database program you can use to create and manage large quantities of data. You can use Access to manage anything from a home inventory to a giant

More information

ECDL / ICDL Project Planning Project Management Software Level 2. Syllabus Version 1.0 (UK)

ECDL / ICDL Project Planning Project Management Software Level 2. Syllabus Version 1.0 (UK) ECDL / ICDL Project Planning Project Management Software Level 2 Syllabus Version 1.0 (UK) Purpose This document details the syllabus for ECDL / ICDL Project Planning. The syllabus describes, through learning

More information

In this session, we will explain some of the basics of word processing. 1. Start Microsoft Word 11. Edit the Document cut & move

In this session, we will explain some of the basics of word processing. 1. Start Microsoft Word 11. Edit the Document cut & move WORD PROCESSING In this session, we will explain some of the basics of word processing. The following are the outlines: 1. Start Microsoft Word 11. Edit the Document cut & move 2. Describe the Word Screen

More information

Appendix A: Brief Guide to Microsoft Project 2010

Appendix A: Brief Guide to Microsoft Project 2010 1 Appendix A: Brief Guide to Microsoft Project 2010 from Revised An Introduction to Project Management, Third Edition By Kathy Schwalbe Professor, Augsburg College Department of Business Administration

More information

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2010-11 Session 6 Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 These

More information

OmniPlan. version 2.0.1 Manual. Introduction to the Interface

OmniPlan. version 2.0.1 Manual. Introduction to the Interface OmniPlan version 2.0.1 Manual Introduction to the Interface Introduction to the Interface Toolbar Like most applications, the toolbar has buttons for commands you use frequently. Some of the buttons change

More information

Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project

Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project Project Example Overview Microsoft Project, in addition to scheduling calculations,

More information

Project Management: Tracking Progress and Earned Value with MS Project 2003

Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain

More information

Resource Management with Microsoft Project Professional 2010

Resource Management with Microsoft Project Professional 2010 Resource Management with Microsoft Project Professional 2010 Greg Bailey Founder & CEO SharkPro Software greg.bailey@sharkprosoftware.com 1 Copyright 2011 SharkPro Software Corporation Microsoft Project

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project

More information