1 PROGRESS OF PROJECTS IN CRIS Last updated on 21/09/2015 (A) STATUS OF PROJECTS AT A GLANCE S. Project Group Project Status No. 1. Freight Operations FOIS Phase-II (TMS More than 99.9% RR s booked Information Expansion) through TMS. System (FOIS) IREPG E-Payment facility extended to a total of 878 customers, covering 79.23% of all RRs. Automatic Sanction of DE is awaited. Board has Identification of constituted a committee to finalize the Railway Wagons specifications of RFID tags. using RFID 2. Passenger Reservation Systems (PRS) 3. Unreserved Ticketing System (UTS) PRS Expansion 3,285 locations, 11,941 PRS terminals; 5.47 crore passengers booked, earning ` crore in August WAP & SMS Gateway for PRS and NTES Website Next Generation E- ticketing (NGeT) DR System for PRS Unreserved Ticketing System Automatic Ticket Vending Machines and their Expansion across Zonal Railways Capacity enhancement and Disaster Recovery System for UTS The SMS Gateway for sending alerts to passengers in case of status change in the PRS tickets has been launched. Approx 1.5 lakh messages being sent daily. Number of maximum concurrent sessions on nget.irctc.co.in were 1,48,552 on 13 th August, Data replication is continuing from all PRS centres to PRS DR centre at Secunderabad. Secondary DR links have been setup in SR and are ready for drill. Being developed on Railtel network for other Railway. UTS is implemented in 5829 locations, Crore passengers booked, earning ` crore during August, ATVMs is working out of 2170 commissioned over NR, NWR, WR, CR, ER, SER, ECoR, SR and SCR over major suburban / non-suburban stations. UTS server capacity enhanced; DR for connected client is set up for all Zonal Railways. Set up for thin clients / ATVMs is in progress. 1 of 23

2 S. No. Project Group Project Status 4. Control Office Application (COA) 5. Crew Management System (CMS) 6. Integrated (a) Coaching Management System (ICMS) (b) National Train Enquiry System (NTES) Unreserved Ticketing System through Mobile at Mumbai and Chennai suburban region Data warehouse for UTS 7. IR Web Portal Indian Railway Web Portal 8. Material Management The pilot project has been inaugurated by MR on 27/12/2014 at Dadar suburban station, Mumbai with Windows & Android Application. Tickets are printed through existing ATVMs at stations. Hon ble MR inaugurated mobile paperless tickets for Chennai area on 22/04/2015. For the purpose of UTS Data warehouse, the replication of data of all Railways has been completed. Data model for Data Warehouse is prepared. ETL mapping and data validation are in progress. COA Application is running in all 77 division / area Control Offices. CMS Implemented in 383 lobbies. 51,444 crews being booked daily. Modules are COIS, PAM and COIS are in operation. PAM (Punctuality), Coaching Maintenance Management and Coaching (CMM) pilot is running in three pilot Maintenance Module depots namely, BCT/WR, NDLS/NR (CMM) Pilot and LKO/NR. NTES web NTES application is running at interface enquiry.indianrail.gov.in. Windows and Android Apps are available for concurrent areas to NTES. 39 Railway websites are hosted on the IR Web-Portal. SMS and Web-based Complaint Management System operational. Booking of Retiring Rooms is available for 483 stations through station terminals and the Internet. E-procurement System (EPS) Material Management Information System (MMIS) E-Tendering module working on all the Zonal Rlys, Production Units and other units of IR. More than 8.07 lakh tenders published through the E- Procurement System. Over `6984 Cr. worth of scrap material auctioned through E-Auction system. MOU for Implementation of ERP based integrated MMIS on Indian Railways signed by CRIS and Northern Railway. 2 of 23

3 S. Project Group Project Status No. 9. Asset Management Locomotive Design & development of LMS - Management System ROAMS has been started. Table (LMS) - Diesel structure for loco failure & loco Locos (pilot project) holding functionalities has been prepared. Detailed Estimate of LMS rollout sent to Rly.Bd. Loco Master Data Management functionality developed. Punctuality Module design is being prepared. Freight Management Module (FMM) for Freight Stock (pilot project) Detailed Estimate for FMM rollout is prepared. FMM - ROAMS-YARD is under development. The following forms have been developed: o Build Rake. o Fit/DVS/ROH/POH Marking. o Wagon parameter entry. o BPC created and printed for CC rake. Software for Pilot Phase completed in July 2014 in Locomotive Asset 2 sheds. Mgt (SLAM) - Electric Loco WISE Phase-II (Workshop Management System launched at Raipur Work shop, Lower Parel, Charbagh and Lallaguda. System) HMIS Advice from Board regarding restructuring of project is awaited. ERP in ICF MOU for Operations and Maintenance Contract with ICF for Rs crore has been signed. Rail Wheel Plant Bela, Patna Bihar ERP Project for DLW Varanasi MOU has been signed for setting up of integrated ICT systems at RWP- BELA. DPR and Budget estimate submitted in May, 2014 MOU signed for planning and setting up ERP project at DLW Varanasi. Infrastructure planning & Data Center design in progress. User requirement 3 of 23

4 S. No. Project Group Project Status 10. Parcel Management System (PMS) Rail Coach Factory, Rae Bareli Expansion of Hand Held Terminals for TTEs Replacement of HW at Central Site CRIS. Pilot project of HHT for TTEs 11 Human Resource HRMS Management System (HRMS) 12 IT Infrastructure DR Data Centre at Secunderabad. 13 GIS Map & Geospatial Database for Indian Railway assets (GIS) 14 Software Aided Timetable Management System 15 Civil Engineering Projects GIS Map & Geospatial Database for Indian Railway assets (GIS) SATSaNg / TTMS Implementation of Track Management System(TMS) on balance divisions of IR Indian Railway Projects Sanction and Management (IRPSM). Railway Land Management System-pilot project specification completed. MOU has been signed for setting up of integrated ICT systems at RCF, RBL. Tender for setting up datacentre has been floated on Dt Tender document prepared and likely to be finalized & issued shortly Tender document prepared; awaiting sanction of Detailed Estimate for finalization and floating. Pilot project has been completed on 11 pair of trains. Revised approach being finalized with Board. Racks for DR System will be hosted in Railtel datacenter in Secunderabad. Detailed Part Estimate for Rs Crore has been sanctioned for implementation of Station Navigation System (SNIS). Scope of work being finalized in consultation with Engg dept of NR. Version 3.5 has been released for testing. Version 3.6 is under development. The system successfully implemented in 28 divisions of IR. Continuous support provided to users of the implemented modules. i) Works programme processing and sanctioning module implemented and running on entire Indian Railways. ii) IRPSM Phase II detail estimate not yet sanctioned by Rly Board. iii) No funds since Jan.13, excess expenditure of `16 lakhs incurred i) Various reports related to earning from various sources have been developed and are under testing. ii) Detailed estimate not yet 4 of 23

5 S. No. Project Group Project Status for 1 division (ADI). sanctioned by the Railway Board. 16 Security Application RPF Security Management System (RSMS) on IR All India RPF Security Helpline for passengers 17 Electrical Project EEMS Electrical Energy Management System TDMS Traction Distribution and Management System Revenue Estimate for O&M activities of RPF Security Management System (RSMS) amounting to Rs lacs, has been sent to Railway Board for onward action after having been concurred by Northern Railway finance. Railway Board had decided to launch a Manual RPF Security Helpline in Northern Railways in the month of February 2014 and to extend it to other Railways as well. The order however did not mention anything about the future course of action for IT enabled RPF Security Helpline Project sanctioned as Plan Head 17 Project in The EEMS website and Application for manual Data entry forms for various Energy Data Modules were designed, developed and deployed on test bed environment. 2. Rail Saver Website is available at 3. PO has been issued to M/s HCL Technologies Ltd. for Pilot demonstration of Energy Efficient Technology on IT platform through 500 AMR Meters on Installation and Commissioning of IT Hardware (Rack, Servers and SAN etc.)for Pilot demonstration of Energy Efficient Technology on IT platform through 500 AMR Meters project has been completed. 1. The revised detailed estimate for four Divisions of Indian Railways is prepared and sent to Northern Railway for sanction as advised by Railway Board. 2. TDMS pilot Application has been deployed on public URL 5 of 23

6 S. No. Project Group Project Status 18 SECROADS E Working AMC 19 Communication Networks Enhancement of Case Monitoring System Implementation of Network Security Infrastructure at 05 PRS/UTS data centres and Railways Internet Data centre (RIDC) at CRIS and implementation of IPSec over Unified Ticketing Network (UTN) SMMS: Signalling maintenance management systems (Pilot Phase to be implemented on BHD-SNP section of Delhi Division and UMP (Ex)-RPJ (Ex) section of UMB division.) Real-time Train Information System (RTIS) Upgradation of Network Management System (NMS) for Unified Ticketing Network and FOIS Network. 3. Presentation of TDMS project has been given to CEE/NR, CEDE/NR & Sr. DEE of NR Northern Railway on The system is under remote support from 1 st Aprl 2014 through resource posted at CRIS HQ office. Test Bed implementation of proposed enhancement for extension of software upto GM s level has been done for 4 zonal Railways viz. SCR, ECR, NWR and ECoR. Integration with PAMS and MR Cell RFMS has been done. O&M support is provided to already implemented modules. Detailed estimate has been sanctioned by Railway Board on and MoU to be signed with NR. System installed, log analysis etc. being carried out Detail estimate has been sanctioned by Railway Board. Development under progress. Railway Board has decided to hold the work till allotment of S-MSS bandwidth by ISRO. Project was delayed due to unavailability of funds. Out of 16, Funds / commitment received from only 12 Zonal Railways. 6 of 23

7 (B) PROJECT STATUS 1 FREIGHT OPERATIONS INFORMATION SYSTEM (FOIS) IREPG E-Payment facility for 10 new customers was commissioned during August The E-payment facility has been provided to a total of 878 customers. In addition, facility of 50 existing customers was also extended due to expiry of LC/BG. A total of ` crores (`208 crores per day) of freight payment was done through E-payment during August 2015 which is around % of the total freight. 2 PASSENGER RESERVATION SYSTEM PRS is working at 3,285 locations with 11,941 PRS terminals. On an average, 5.47 crore passengers are being booked in PRS with average Passenger Earnings of ` crores during August In the corresponding period of August 2014, total 5.57 crore passengers were booked from 11,199 PRS Terminals at 3,109 Locations resulting in total earnings of ` crore. WAP & SMS Gateway for PRS and NTES Website The SMS Gateway project for sending SMS alerts to passengers in case of status change in the PRS tickets, as compared to the initial booking status (For ex. W/L to RAC, RAC to Confirm, W/L to Confirm) was launched by Hon ble Minister of State for Railways on The Pre-Chart SMS alerts are being sent once a day, beginning from 5 days before the journey date and also after post charting (which is done approx. 3-4 hours before train departure). The post chart SMS alerts convey the actual Berth No., Coach No. and RAC Seat No. for those passengers whose final Charting status has changed as compared to the initial booked status. In case of any ticket upgradation or seat re-allotment SMS alerts are being sent. On an average approximately 1.5 lac SMS alerts are being sent on daily basis. Next Generation E-ticketing (NGeT) Number of maximum concurrent users on nget.irctc.co.in as on 13 th August, 2015 had been 1,48,552. Ticket Booking Statistic Maximum bookings per day was registered on 1 st August, 2015 Maximum bookings during the period of hrs was recorded on 26 th August, 2015 Maximum bookings during the period of hrs was recorded on 7 th August, 2015 Maximum bookings during the period of hrs was recorded on 13 th August, ,34,295 27,263 61,575 1,10,529 7 of 23

8 Maximum bookings per minute was recorded on 15 th August, 2015 Maximum bookings per sec. was recorded on 27 th August, , Average transaction response time for user to book ticket on NGeT excluding payment is sec. Following Security Audits of NGET system was conducted by STQC: Web Applications Security assessment VA of Network Devices and Servers The auditing report was satisfactory. Application changes have been done as per requirement of IRCTC/Railways A. E-Ticketing New Requirement Travel Agent Booking & Booking through web services enabled on NGET i. Changes done to allow booking in Tatkal & Premium Tatkal quota and Dynamic train without ID Card. ii. Implement STQC security recommendations. Enhancement :- i. User Interface Changes: Update messages in Hindi & English on static link wrt auto cancellation/refund in case of train cancellation Remove Tab IRCTC Deals from NGET login page Add link for AGENT user manual on Login Page New Tab on home page "E-Wheelschair" Message update wrt Suvidha Train on payment page ii. Change Google analytics sample rate from 80 to 0.75 iii. Dynamic page creation for Bank Transaction charge iv. User type 4 should be consider as General User and other should be treated as Agent in booking Issue Fixed i. Printing issue of passenger details on ERS ii. At booking time if some PRS exception is coming, the actual message is getting suppressed. 8 of 23

9 B. Dashboard New Requirement i. RDS Hour wise / Minute wise Report Enhancement i. Case: TDR filed against fully WL PNR and PNR drop after Charting Changes done not to display the TDR details if refund has been granted through drop WL scheduler ii. Remove check for at least one small letter in Username from all reports iii. Refund Batch changes for Bank Id int to Long for RDS refund because it is 20 digit long iv. I-ticket printing through the dashboard application should not be allowed for i- ticket booked through user of type 51. Details should not be displayed in the list & search filter. v. Make changes in TDR batch for stopping CR registration request against PNR whose train is cancelled. vi. Drop WL scheduler: separate status should be defined for Seized PNR & Allotment done in diff TDRC. And once the status is defined, these PNRs should not be pickup for cancellation through the WL scheduler Issue Fixed i. Changes have been done to fix Wrong Chart status updated against PNR through scheduler ii. SOME CASES NOT REGISTER/REPUDIATED BY ECRS system iii. Changes done to update chart status on NGET DB multiple times as per SMS file received from PRS iv. Current PNR amount NOT pick in SQL and check has been build to avoid C. Dashboard Travel Agent Admin (New Requirement Closed):- Following Functionalities have been developed:- a) User Management b) Profile Section Management c) RDS Management d) Agent Complaint Management 9 of 23

10 D. Agent Interface New Functionality :- i. Functionality has been developed for checking Ticket/PNR details, TDR status & Cancel Ticket status by Agent & Sub-Agent. And also option to cancel ticket/pnr has been provided. ii. Functionality has been developed for Master Agent to Manage Sub-Agent (User Management) iii. Functionality has been developed for password management of Agents & Sub- Agent iv. Following Reports have been designed:- Daily Transaction report :- Booking Report, Cancellation Report, TDR Report & Failed Transaction Report RDS Daily Accounting report DR System for PRS Data replication is continuing from all PRS centres to PRS DR centre at Secunderabad. Secondary DR links have been setup in SR and are ready for drill. Being developed on Railtel network for other Railway. 3 UNRESERVED TICKETING SYSTEM Unreserved Ticketing System A total of crore passengers were served, resulting in total earning of ` crore during the month of August 2015 as compared to crore passengers and ` crore earnings during August 2014, thereby showing an increase of 4.48% and decrease of 3.61% in total passengers served and earnings respectively. On an average, UTS served 1.97 crore passengers and earned `50.51 crore each day in August At present UTS is functioning at 5829 locations and running at Counters. Automatic Ticket Vending Machines and their Expansion across Zonal Railways 1924 ATVMs is working out of 2170 commissioned over NR, NWR, WR, CR, ER, SER, ECoR, SR and SCR over major suburban / non-suburban stations. 10 of 23

11 Capacity enhancement and Disaster Recovery System for UTS UTS server capacity enhanced; DR for connected client is set up for all Zonal Railways. Set up for thin clients / ATVMs is in progress. Unreserved Ticketing System through Mobile at Mumbai and Chennai suburban region (as pilot for one year) The pilot project has been inaugurated by MR on 27/12/2014 at Dadar suburban station, Mumbai with Windows & Android Application. Tickets are printed through existing ATVMs at stations. Hon ble MR inaugurated mobile paperless tickets for Chennai area on 22/04/ COMPUTERIZED CONTROL CHARTING COA Application is running in all the 77 divisions/area Control Offices of the Indian Railways. Integration between COA and FOIS, adjoining COA, NTES and ICMS is completed in all 68 divisional control offices. New Time table schedules were created in ICMS application, and the data was successfully transferred to the COA application to ensure updated time table availability with the section controllers. 5 CREW MANAGEMENT SYSTEM (CMS) Number of lobbies commissioned 383 Daily call served through CMS system at present Nearly 51,444 Crew Bio data in CMS system 1,01,888 Total lobbies commissioned are 383 ( ) 380 Lobbies, 2 training schools at UDZ & MLY) and 1 as CMS/CRIS/NDLS-HQ. Last lobby created : SR / MDU / MVN on (a) INTEGRATED COACHING MANAGEMENT SYSTEM (ICMS) The ICMS application is hosted on central server located in CRIS, Chanakyapuri accessed over FOISNET. It is a browser based application and can be run from any client on FOISNET. Approx clients are running on FOISNET on thin clients/pcs. This has three applications as Punctuality Analysis and Monitoring (PAM), Coaching Operations Information System (COIS), Coach Maintenance Management (CMM) pilot. First two modules of application are already deployed over IR, third module Coaching Maintenance Management (CMM) pilot was made Go-live at three pilot depots namely, BCT/WR, NDLS/NR and LKO/NR. The CMM application is built on the core of an EAM software MAXIMO. Apart from this the Central Application has been made available to all Zonal Railway HQs on It has modules on Passenger complaints, Contracts 11 of 23

12 monitoring, Machinery & Plant, Coach Condemnation, Pit charts, Special drives, Project tracking, Trial monitoring, Budget trains and Documentation. ICMS infrastructure was set up in and asset has become overdue replacement as servers are running 9 th year. Sanction of the Detailed estimate has been received. Five new reports have been implemented for CMM in various depots. Detailed estimate for rollout of CMM project has been sanctioned by Railway Board. 6(b) National Train Enquiry System The National Train Enquiry System (NTES) is meant for providing updated arrival/departure information of passenger trains to the public through internet website ( and nationwide rail enquiry number 139. Recently, new web interface alongwith mobile interface has been launched. NTES is the core application feeding information to all interfaces. A Mobile App & Desktop App for Window 8.0 platform has been developed and launched. A mobile Application for Android has also been launched. New version (v1.2) of NTES mobile app has been released on for Android and Windows with security features- encryption/decryption. 7 IR WEB PORTAL i. Complaint Management System (CMS) The Web Complaint Management System (Web CMS) can be accessed through the IR Portal home page, complaint and suggestions section. It can also be directly accessed through the URL, Divisional Work Flow has been made online so that divisional level escalation can be configured. The SMS based Complaint Management System is also operational. ii. Cloak Room Application: This application is operational at New Delhi Station (Ajmeri Gate and Paharganj). During the month of August 2015, no booking has been taken place. Total Package Booked Total Package Delivered Total Earning : Nil : Nil : Nil 12 of 23

13 Retiring Room: Retiring Room Application is now running at 483 stations through Terminals. At 483 stations booking for Retiring Rooms can be made on the Internet. 2015: Earnings from booking of Retiring Rooms during the month of August Booked on Terminals: Rooms Booked : 39,683 Net Earnings : `1,02,47,259/- Booked on Internet: Rooms Booked : 20,142 Net Earnings : `91,94,954/- Portal websites feel. All the 39 Websites have been migrated with standardized and uniform look & 8 MATERIAL MANAGEMENT E- PROCUREMENT SYSTEM (EPS) Implementation of E-Procurement System on all 16 Zonal Railways, 7 Production Units (viz. RCF, ICF, DLW, CLW, DMW, RWF and RCF/RBL) and RDSO, RAILTEL, Core/ALD and Metro Railway, Kolkata completed. More than 8.07 Lakh tenders have been uploaded by different Railways. 28,951 vendors have been registered on the system. 24,985 tenders issued through the system in August, 2015, and 548 vendors enrolled. E-Auction module software has been implemented in CR, ER, ECR, ECoR, NR, NCR, NER, NFR, NWR, SR, SCR, SER, SECR, SWR, WR, WCR Including 4 PUs RCF, ICF, DLW, RWF. Over `6984 crore worth of material auctioned through E-Auction system. Extension of E-Procurement System to Depots, Divisions and other units The detailed estimate has been sanctioned by Railway Board on MOU between NR and CRIS has been finalized on IREPS has been extended to 262 Depots/Divisions in Zonal Railway. MATERIAL MANAGEMENT INFORMATION SYSTEM Detailed estimate of Rs crore has been sanctioned. Local Purchase of immis being rolled out in 262 out of 300 Depots/Divisions in Zonal Railway and PUs. 13 of 23

14 9 ASSET MANAGEMENT LOCO SHED MANAGEMENT SYSTEM (LMS) Design & development of LMS - ROAMS has been started. Table structure for loco failure & loco holding functionalities has been prepared. Detailed Estimate of LMS rollout sent to Rly.Bd. Loco Master Data Management functionality developed. Punctuality Module design is being prepared. FREIGHT MAINTENANCE MANAGEMENT MODULE (FMM) Detailed Estimate for FMM rollout is prepared. FMM - ROAMS-YARD is under development. The following forms have been developed: o Build Rake. o Fit/DVS/ROH/POH Marking. o Wagon parameter entry. o BPC created and printed for CC rake. SOFTWARE FOR LOCOMOTIVE ASSET MANAGEMENT (SLAM) Pilot Phase completed in July Meetings held with GZB & TKD on 18/ for SLAM enhancement. Meetings held with GZB & TKD on 18/ for SLAM enhancement. Development & training setup installed and commissioned on Proposal for extending 4 sheds in SLAM i.e. BRC, BL, AJNI & BZA: Tender finalized and PO issued An estimate for 1 year AMC and ATS support for SLAM central server is prepared at an estimated cost of `1.02 cr. WORKSHOP MANAGEMENT SYSTEM (WISE PHASE II ) LOWER PAREL: Coaches Sub-orders & Assy. orders had been created by all the sections. Work Orders are released and job allocation, job assignment, FNIP and technical completion were carried out by almost all users. CHARBAGH: All rolling stocks after different schedules of DSL, DEMU were turned out through WISE. Data for leave module is under preparation. Casual Leave data of all the secs/shops were near completion. Booking of material through WISE has been started by DSL shop partially. Around 2500nos drawings and documents have been uploaded manually and approx 40,000 drawing are to be batch uploaded. Working closely with stores Management for quickly implementing IMMIS. Non Stock Requisitions were being prepared in Wise system for material procurement. RAIPUR: Gang wise attendance reportsare being generated through WISE for use in Incentive Report. Attendance marking is regular in all Shops. Problems encountered in Body I & Body II are being rectified. 14 of 23

15 Lalaguda: Training has being given to staff inside the workshop to mark attendance, generate stock and non-stock indents and IR sheets. Generation of indents has being done at the respective shops. Online attendance marking system has being implemented at EDP Center, CTR, Millwright, Trimming, Tinsmith and Corrosion shops.material consumption pattern has been generated for CB & UF Store. LILUAH: The issues like coach roll out, coach stages, berthing, intershop items like DV has been fixed. Some more TCs has been configured to production system.network problems in YD, SSE/CORD/MR, MR/BL are fixed. Proposal for upgradation of BSNL leased line has been approved by CWM and is awaiting DyGM s approval. Data entries in yard, MR BL, AB- L,MR/AB are done regularly. HMIS APPLICATION FOR RAILWAY HOSPITALS A Committee has been formed in Board to scrutinize all aspects of the application. TURNKEY IMPLEMENTATION OF ERP AT ICF, CHENNAI MOU for Operations and Maintenance Contract with ICF for Rs crore has been signed between FA&CAO/ICF and GGM/ERP/CRIS. Pending implementation issues are being corrected. Supplementary O&M MOU for with the revised estimate has been vetted by FA&CAO/ICF. Necessary communication from ICF is awaited to sign it. Integrated ICT System project at RWP-BELA, PATNA/ BIHAR An MOU has been signed on for setting up of integrated ICT system at RWP-BELA, Patna, Bihar. DPR for the project is finalized and expected to be submitted shortly. Sl No Description Status 1 Hiring of Man Power Already hired from NIELIT and working on the Project. However, most of the staff hired have resigned and left CRIS. GM/CC or GM/HRD has been requested to arrange moiré staff. 2 Accommodation Hiring Not required and hired leased accommodation vacated on 31/08/ Training (Level I &II) Training completed. 4 User requirement specifications DPR along with Functional requirement specifications approved by Bela 5 Tender document A common tender document for all 3 PUs (DLW, RWP/Bela & RCF/RBL) 15 of 23

16 for Application software is with Finance & Procurement for vetting/ verification of terms and conditions. 6 Project report DPR along with Functional requirement specifications approved by Bela. 7. Detailed estimate The detailed estimate to the tune of Rs Crores has been vetted by FA&CAO/WPO/Patna and approved by CME/WPO to go ahead for floating the tender. ipas Implementation:- Salaries are being generated from ipas system in RWP/Bela and other Accounting functions are also being done through ipas system. CAO/Bela has also desired CRIS to implement MMIS at RWP/Bela expeditiously. ERP Project-DLW An MOU was signed on 14/02/2013 for planning and setting up ERP project at DLW/Varanasi. DPR has been signed-off by CME/DLW on 31/03/2015. S Description Status No 1 Hiring of Man Power Already hired from NIELIT and working on the Project. However, most of the staff hired have resigned and left CRIS. GM/CC or GM/HRD has been requested to arrange moiré staff. 2 Logistics and Procurement of Desktop PCs 20 nos All-in PC supplied to DLW/ Varanasi and under commissioning. 3 Training (ERP) Will be provided as part of common tender of ERP application software. 4 User requirement Completed and signed off. specifications 5 Functional requirement Completed and signed off specifications 6 Project report The DPR along with all technical specification of all the modules have been finalized and signed off on 31/03/ Tender document i) A common tender document for all 3 PUs (DLW, RWP/Bela & RCF/RBL) is finalized and is with Finance for vetting and procurement branch for verification of terms and conditions for floating open tender. ii) Another tender document for common data center at CRIS New Delhi is under final stage of preparation. 8. Detailed estimate Detailed estimate to the tune of Rs Crores has been vetted by FA&CAO and sanctioned by CME/DLW on 19/03/ of 23

17 Integrated ICT System project at Rail Coach Factory at Rae Bareily Work of setting up of Network has been awarded. Work of setting up of data-centre has been awarded and work is in an advanced stage. Gate Attendance devices have been received & part commissioned. Complete review of project has been done with CME & CPM/RBL. Further review has also be done with CDE/IT who has recently taken over. All pending issues were discussed. RBL would be confirming the next sequence of action to be taken. 10 PARCEL MANAGEMENT PARCEL MANAGEMENT SYSTEM (PMS) Parcel Management System was inaugurated by Shri Suresh Prabhu, Hon ble Minister for Railways on at Mumbai in which GM/Central Railway, Sh. S K Sood and GM/Western Railway, Shri Hemant Kumar were also present in this occasion. Commissioning of PMS terminals completed in NDLS-BCT corridor. Commissioning in progress at remaining corridors NDLS-MAS, HWH-CSTM, HWH-MAS. Expansion of Hand Held Terminals for TTEs Tender document prepared and likely to be finalized & issued shortly. Detailed Estimates have been sent to CAO/PTS, NR on 24/09/2014 for sanction. Replacement of HW at Central Site CRIS Tender document prepared; awaiting sanction of Detailed Estimate for finalization and floating. Detailed Estimates have been sent to CAO/PTS, NR on 24/09/2014 sanction. for Pilot project of Hand Held Terminals for TTEs. Pilot project has been completed on 11 pair of trains. Rs Lacs for project cost and Rs. 217 Lacs for maintenance are yet to be released although all bills issued to concern Railways for release of funds. 11 HUMAN RESOURCES MANAGEMENT SYSTEM Revised approach being finalized with Board. 12. IT INFRASTRUCTURE Disaster Recovery Data Centre at Secunderabad After the Scrutiny of Technical Bids, Financial bids have been opened and are 17 of 23

18 under consideration of TC. Offers received exceed the estimate, case is under evaluation. In the meantime, rack will be placed in Railtel datacenter in Secunderabad. 13. GIS Map & Geospatial Database for Indian Railway assets (GIS) Detailed Part Estimate for Rs Crore has been sanctioned. MoU and DE for further work being finalized in consultation with nodal agency i.e. NR Civil Engg Dept. 14 SATSaNg / TIME TABLE MANAGEMENT SYSTEM Version 3.5 has been released for testing. Version 3.6 is under development. 15 CIVIL ENGINEERING PROJECTS TRACK MANAGEMENT SYSTEM: Scope of Work Design, Development, implementation and hand holding support for Track Management System. Design and development of Rail-Road Crossing GAD Approval System. Design and development of On-line Monitoring of Railway s Private Siding Projects. Design and development of Way Leave/Easement Right Application Monitoring System. Activities performed during the month (Track Management System): Complete stores module is under process of enhancement for clear identification of material location: a. New module has been developed for changing the class of material from Second hand to Unserviceable/ Scrap. b. Ledger/Material Balance report has been enhanced. c. Ledger adjustment module has been enhanced. d. ART module has been developed for users of Track Depot. OMS: Module has been enhanced for integration of new file format generated by new OMS machine commissioned in Ahmedabad Division. Railway Affecting Works: Design of Railway Affecting Works has been completed during the month. Land Module: Enhancement/ modification have been done during the month for restricting the uploading of voluminous files. Reports: Various reports have been enhanced and 12 reports have been developed in pdf formats as well during the month. Indian Railway Projects Sanctions and Management (IRPSM) Scope of Work Design, Development, implementation and hand holding support for Indian Railways Projects Sanction and Management (IRPSM). 18 of 23

19 Activities performed during the month: A new report was created to view item wise details of each Rate Reference uploaded for proposals related with Track Renewal plan head. A utility was provided to print the Unit Rate Reference report in PDF format containing details of item wise breakup along with sub estimate of other departments. Short listing of Proposals screen was modified to let the Drop Down List of Budget Year increment automatically whenever budget year changes. Facility was provided in Filling of outlay for I1 works screen to fill the Pink Book No for each work, along with allocation wise outlay. Facility was provided in Filling of outlay for I1 works screen to choose the correct allocations in place of existing one and insert new allocations for each work, whose details were provided in latest Pink Book. Provided the support for the queries raised from Railway Board, Zonal Railways, Divisions and Workshops through , phone and letters. Railway Land Management System-pilot project for 1 division (ADI) i) Various reports related to earnings from various sources have been developed and are under testing. ii) Detail Estimate not yet sanctioned by Railway Board. 16 Security Applications RPF Security Management System (RSMS) on IR Application running in Production environment since March Module wise application progress during the month is as follows: Control Room Messaging (CRM), Special Intelligence Bureau (SIB) and Crime Records and Registers (CRR) Modules, Miscellaneous Crimes (MC) and Monthly Crime Review (MCR All are working in live environment and no major problem reported during the month. Revenue Estimate amounting to Rs lacs for O&M activities of RPF Security Management System (RSMS) has been sent to Railway Board for onward action after having been concurred by Northern Railway finance. All India RPF Security Helpline for passengers Railway Board had decided to launch a Manual RPF Security Helpline in Northern Railways in the month of February Railway Board through an order subsequently decided to extend the manual RPF Helpline as initiated in Northern Railway to other Railways as well. The order however did not mention anything about the future course of action for IT enabled RPF Security Helpline Project sanctioned as Plan Head 17 Project in of 23

20 17 Electrical Projects EEMS Electrical Energy Management System Scope of Work is development of Website for Centre of Excellence (COE) and Pilot demonstration of Energy Efficient Technology on IT platform. a. The EEMS website and Application for manual Data entry forms for various Energy Data Modules were designed, developed and deployed on test bed environment. b. Rail Saver Website has been now secured and available on public network through secure URL c. Tender for Pilot demonstration of Energy Efficient Technology on IT platform through 500 AMR Meters has been opened on and Technical evaluation of the Tender is completed and PO has been issued on TDMS Traction Distribution and Management System The scope of Pilot project is to design, develop and implement the system on two divisions of Central Rly / Western Rly. Current Status: The revised detailed estimate for four Divisions sent to Railway Board / CEE(NR) /CEE(WR) for sanction. Railways Electrical Network Masters have been designed and being tested. Jurisdiction Master being tested. Existing Railways Network data of TMS has been ported into TDMS Database. 18 OAEW Projects SECROADS E Working AMC Scope of Work Operation and Maintenance support of the SECROADS including minor modifications to the application software. The system is under remote support from 1 st April 2014 through resource posted at CRIS HQ office. Work undertaken during the month: Created new reports in LAP/LHAP/Leave encashment applications showing in a particular time frame. Grade wise list of sanctioned application List of sanctioned applications based on Gazetted and non-gazetted officer in a particular time frame. Created a new replica of File movement and tracking application on one of the clustered server by replacing old one to resolve replication and consistency issues. Searching issue in Manual file tracking system application by creating new indexes after deleting old one has been fixed. Changes made in Print preview page of LAP application, added details of extension and cancellation also. Changes made in Proprietary Article Certificate approving conditions of Non- Stock Indent application. Reduced disk utilization of ICM server by deleting old logs and running DB optimization commands. 20 of 23

21 Case Monitoring System for OSD/PRI, Railway Board Scope of Work Design, Development and implementation of Case Monitoring System for OSD/PRI to be implemented in Railway Board and its replication to Zonal Railways as part of enhancement. Activities performed during the month: Operation and Maintenance (O&M) support has been provided to the application modules already implemented for the users of Railway Board & Zonal Railways. 19 Communication Networks : - i. Network Security Infrastructure Name of Project / Work Implementation of Network Security Infrastructure at 05 PRS/UTS data centres and Railways Internet Data centre (RIDC) at CRIS and implementation of IPSec over Unified Ticketing Network (UTN) Year of Sanction 2012 Pink Book Item No. (if any) Total sanctioned Cost of Project Item No. 152 of pink book Item No. 160 of pink book Crores CRIS Portion of Cost Current Status of Project (in bullet pionts) Major achievements till date (in Bullet points) Issues pending with Rlys/Rly Board a) CRIS portion : crores b) Railway Establishment charges : lakh Total detail estimate cost : crores Detail estimate has been sanctioned by Railway Board and MoU to be signed with NR. System installed, log analysis etc. being carried out. Signing of MoU and Fund transfer by N. Rly. ii SMMS Signalling maintenance management systems Name of Project / Work Year of Sanction 2013 SMMS: Signalling maintenance management systems (Pilot Phase to be implemented on BHD-SNP section of Delhi Division and UMP (Ex)-RPJ (Ex) section of UMB division.) Pink Book Item No. (if any) Item No. 167 of pink book Total sanctioned Cost of Project 3.0 Crores 21 of 23

22 Current Status of Project (in bullet points) Detailed estimates awaiting sanction Future planning Detailed estimates along with User requirement specifications, Software requirement specifications and solution architecture are being prepared. Detail estimate has been sent to to NR for sanction. Detail estimate has been sanctioned by Railway Board. Development under progress. All India Roll Out iii. Real-time Train Information System (RTIS) Name of Project / Work Year of Sanction 2012 Real-time Train Information System (RTIS) Pink Book Item No. (if any) Item No. 456 of NCR pink book Total sanctioned Cost of Project Crores CRIS Portion of Cost Current Status of Project (in bullet pionts) Major achievements till date (in Bullet points) Issues pending with Rlys/Rly Board Detailed estimates awaiting sanction Future planning 52.3 Crores Signing of MoU is pending with IRPMU and funds are awaited. Technical specifications for the loco-equipment have been finalized and sent to IRPMU. Tender for procurement of loco equipment is to be done by IRPMU. Revised cost estimate has also been sent to IRPMU. Railway Board has decided to wait till allotment of S-MSS bandwidth by ISRO 1) RTIS trials conducted successfully in Chennai region of S. Rly. 2) Tech. Specs for Loco unit finalized and sent to IRPMU for procurement. 3) Tech. Specs of some other backend subsystems completed Allotment of S-MSS bandwidth by ISRO Revised cost estimate sanction awaited from IRPMU PAN India Rollout iv Upgradation of Network Management System (NMS) for Unified Ticketing Network and FOIS Network. Name of Project / Work Year of Sanction 2012 Total sanctioned Cost of Project Upgradation of Network Management System (NMS) for Unified Ticketing Network and FOIS Network Crores 22 of 23

23 Amount Received till March crores (Approx.) Current Status of Project (in bullet pionts) Major achievements till date (in Bullet points) Issues pending with Rlys/Rly Board Project is delayed due to unavailability of funds. Out of 16 Railways, Funds/commitment received from only 12 Zonal Railways. However, a tender process has already been initiated for addressing the composite requirement of FOIS and UTN Network. Bids received on 12 Feb for consolidated tender for upgradation of NMS for UTN & FOIS Network. Evaluation report for Pre- Qualification (PQ) has been prepared and forwarded to Tender Committee. Tenchinal evaluation is in progress. Earlier Project was delayed due to unavailability of funds. Out of 16, Funds/commitment received from only 12 Zonal Railways. Fund transfer from remaining Zonal Railways 23 of 23

Government of India (Bharat Sarkar) Ministry of Railways (Rail Mantralaya) (Railway Board) No. E(MPP)96/1/15Pt.II Dated: 31.05.

Government of India (Bharat Sarkar) Ministry of Railways (Rail Mantralaya) (Railway Board) No. E(MPP)96/1/15Pt.II Dated: 31.05. Government of India (Bharat Sarkar) Ministry of Railways (Rail Mantralaya) (Railway Board) No. E(MPP)96/1/15Pt.II Dated: 31.05.2012 Shri R.K. Prasahar, CPO/Central Railway, Mumbai Shri, Arjun Tabiyar,

More information

Online Reservation System Using QR Code based Android Application System

Online Reservation System Using QR Code based Android Application System International Journal of Scientific and Research Publications, Volume 4, Issue 12, December 2014 1 Online Reservation System Using QR Code based Android Application System Mrs. Omprakash Yadav *, Ryan

More information

A QR Code Based Processing for Dynamic and Transparent Seat Allocation

A QR Code Based Processing for Dynamic and Transparent Seat Allocation International Journal of Scientific and Research Publications, Volume 3, Issue 10, October 2013 1 A QR Code Based Processing for Dynamic and Transparent Seat Allocation Mehul Yadav *, Sumedh Kurundkar

More information

allowed. Request for inclusion and consideration of ISO 2008:9001 quality certification. CMMI Level 5 : 10 Marks CMMI Level 3 : 07 marks ISO: 05

allowed. Request for inclusion and consideration of ISO 2008:9001 quality certification. CMMI Level 5 : 10 Marks CMMI Level 3 : 07 marks ISO: 05 Corrigendum for the Tender for Web Based Project Monitoring Tool & MIS System Bidders Clarification Sl. Clause /Page no Tender Clause Clarification Sought Clarification No. 1 Page No:4 No consortium Consortium

More information

Chapter 1 Unreserved Ticketing System in Indian Railways

Chapter 1 Unreserved Ticketing System in Indian Railways Chapter 1 Unreserved Ticketing System in Indian Railways 1.1 Highlights Chapter 1 Unreserved Ticketing System in Indian Railways Indian Railways did not have any structured mechanism for resolving delays

More information

RULES AND REGULATIONS. Do s for the Service providers

RULES AND REGULATIONS. Do s for the Service providers 1 RULES AND REGULATIONS Mandates for Registration Do s for the Service providers Registration as an RSP (Retail Service Provider) in IRCTC is issued for booking of E- Tickets only (except RTSA agents,

More information

REAL ESTATE PORTAL SOLUTION. Ver 1.11

REAL ESTATE PORTAL SOLUTION. Ver 1.11 REAL ESTATE PORTAL SOLUTION DEVELOPER CONSUMER AGENTS Ver 1.11 Techzone Real Estate Portal Solutions end to end property system platform - Ver1.11 Page 1 Index of the documents Chapter page No. Introduction

More information

Common Patient Portal (ors.gov.in)

Common Patient Portal (ors.gov.in) Common Patient Portal (ors.gov.in) ON-BOARING MANUAL FOR HOSPITALS National Informatics Centre July 2015 (version 1.0) Target Audience As part of the Digital India program of Government of India, Hon ble

More information

Help Document for utsonmobile - Android Phone (Paperless Ticket)

Help Document for utsonmobile - Android Phone (Paperless Ticket) Help Document for utsonmobile - Android Phone (Paperless Ticket) Unreserved Ticketing System is the predominant ticketing system on Indian Railways in terms of the number of passengers it serves. As of

More information

Integrated Challan cum Return (ICR) - Scope of Work for ICR Platform

Integrated Challan cum Return (ICR) - Scope of Work for ICR Platform Integrated Challan cum Return (ICR) - Scope of Work for ICR Platform 1. Proposed System Modules: a) User Portal b) ICR Management Platform c) Integration with Bankers Core Banking platform d) Messaging

More information

Global Enterprise Business Management Platform Interactive, Intelligent with Controls to Ensure Profit

Global Enterprise Business Management Platform Interactive, Intelligent with Controls to Ensure Profit Global Enterprise Business Platform Interactive, Intelligent with Controls to Ensure Profit Sales and Sales Force Customer Relationship Supply Chain Stores & Purchase Production Product Data Scheduling

More information

Transport Department Government of Uttar Pradesh

Transport Department Government of Uttar Pradesh Transport Department Government of Uttar Pradesh Intelligent Transport Management System (ITMS) Uttar Pradesh State Road Transport Corporation (UPSRTC) Capital cost Rs. 38.25 crores 50% ACA Grant by MoRTH,

More information

Indian Railways Embrace e-procurement Solutions to

Indian Railways Embrace e-procurement Solutions to Travel, Transportation & Logistics Indian Railways Embrace e-procurement Solutions to Improve Efficiency and Enhance Performance Client Brief The Indian Railways (IR) is Asia's largest and the world's

More information

MINISTRY OF RAILWAYS

MINISTRY OF RAILWAYS MINISTRY OF RAILWAYS CHAPTER: IX Konkan Railway Corporation Limited Financial Accounting module of ERP Highlights: There was inordinate delay in development and implementation of Railway Application Package

More information

Part-II Of Tender For FOIS EDW Solution

Part-II Of Tender For FOIS EDW Solution Part-II Of Tender For FOIS EDW Solution 2013 Centre for Railway Information Systems, ChanakyaPuri, New Delhi-110021 IT Wing of Indian Railways Table of Content Chapter Title Page 1 Key Dates 5 2 Project

More information

ATTACHMENT III Tender No. 10000265-HD-48009. Laboratory Information Management System (LIMS)

ATTACHMENT III Tender No. 10000265-HD-48009. Laboratory Information Management System (LIMS) Objective: ATTACHMENT III Tender No. 10000265-HD-48009 Laboratory Information Management System (LIMS) HPCL Mumbai refinery is looking for LIMS system to automate the Refinery Laboratory operation and

More information

REQUEST FOR PROPOSAL SUPPLY, INSTALLATION AND CUSTOMIZATION OF HELPDESK SOFTWARE. Tender No. ECIL / CSD / 10-3053 dated 27.05.2011

REQUEST FOR PROPOSAL SUPPLY, INSTALLATION AND CUSTOMIZATION OF HELPDESK SOFTWARE. Tender No. ECIL / CSD / 10-3053 dated 27.05.2011 REQUEST FOR PROPOSAL FOR SUPPLY, INSTALLATION AND CUSTOMIZATION OF HELPDESK SOFTWARE Tender No. ECIL / CSD / 10-3053 dated 27.05.2011 ELECTRONICS CORPORATION OF INDIA LTD ( A Government of India Enterprise

More information

The Indian Railways attempt to modernize its reservation systems. Since the railway has become the best modes of. Research Article December 2013

The Indian Railways attempt to modernize its reservation systems. Since the railway has become the best modes of. Research Article December 2013 Next Generation E-ticketing System Abdul Mateen Ansari 1 Aftab Alam 2 Mohammed Mujahid.Barga 3 Department of Information System Department of Computer Science Department of Computer Science King Khalid

More information

State Health Society, Bihar Pariwar Kalyan Bhawan, Sheikhpura, Patna-14

State Health Society, Bihar Pariwar Kalyan Bhawan, Sheikhpura, Patna-14 fcgkj ljdkj lllllljdkj State Health Society, Bihar Pariwar Kalyan Bhawan, Sheikhpura, Patna-14 NOTICE INVITING TENDER From Companies/Agencies for Hiring Four Dedicated Servers (1 Linux Application Server

More information

Rail Safety Worker. Competency Management Briefing. 27 Feb 12

Rail Safety Worker. Competency Management Briefing. 27 Feb 12 Rail Safety Worker Competency Management Briefing 27 Feb 12 Objectives for the Presentation 01 Introduction 02 Rail Safety Work 03 Approach to Competency Management 04 2012 Project Timeline 05 Pegasus

More information

Web-Based Rail Reservation (Internet Ticketing)*

Web-Based Rail Reservation (Internet Ticketing)* Web-Based CHAPTER Rail 14 Reservation (Internet Ticketing) 173 Web-Based Rail Reservation (Internet Ticketing)* Sanjay Aggarwal General Manager (Operations), New Delhi sanjay@irctc.co.in ABSTRACT Indian

More information

Invitation for Expression of Interest for providing software development services

Invitation for Expression of Interest for providing software development services PASCHIMANCHAL UNNAYAN PARSHAD under Department of Paschimanchal Unnayan Affairs, Government of West Bengal Ailakundi (Behind S.B.S.T.C. Garage), Kenduadihi, Bankura, West Bengal 722102 e-mail: pupbankura@gmail.com

More information

For windows erver, Which edition of Windows server 2008 is required ( i. e. Web / Standard / Enterprise )?? Kindly suggest.

For windows erver, Which edition of Windows server 2008 is required ( i. e. Web / Standard / Enterprise )?? Kindly suggest. Clarifications/Responses for Notice Inviting Tender From Companies/Agencies for Hiring Four Dedicated Servers (3 - Linux & 1 - Windows) Sr. No. Page No. Clause in Tender Clarification/Suggestion Sought

More information

Help Document for utsonmobile - Android Phone

Help Document for utsonmobile - Android Phone Help Document for utsonmobile - Android Phone Unreserved Ticketing System is the predominant ticketing system on Indian Railways in terms of the number of passengers it serves. As of now, the passengers

More information

Help Document for utsonmobile - Android Phone

Help Document for utsonmobile - Android Phone Help Document for utsonmobile - Android Phone Indian Railway is introducing the facility of booking unreserved suburban tickets on smartphones. The application has been developed in-house by Centre for

More information

Impact Factor :3.029 E- ISSN - 2349-6746 ISSN -2349-6738

Impact Factor :3.029 E- ISSN - 2349-6746 ISSN -2349-6738 IMPLICATIONS OF ONLINE RAILWAY TICKET BOOKING D.Anbupriya* Dr.S.Subadra** *Ph.D Research Scholar Arignar Anna Government Arts College, Namakkal, India. **Assistant Professor & Research Guide, Arignar Anna

More information

ENTERPRISE RESOURCE PLANNING (ERP)

ENTERPRISE RESOURCE PLANNING (ERP) CHAPTER 15 ENTERPRISE RESOURCE PLANNING (ERP) Page: 1 ERP Project of BSNL Contents 1. What is ERP? 2. Why ERP at BSNL 3. ERP Project Current Status 4. ERP implementation approach 5. ERP implementation

More information

RFP For Operationalization of National Contact Center for ECI on Outsourced Model

RFP For Operationalization of National Contact Center for ECI on Outsourced Model 1 Please provide Bifurcation of agents in Voice, Email, SMS, Web chat alongwith the volume and the average handle time The bifurcation details shall be provided during the Project Preparatory Phase. The

More information

Tender No. CWC/RO-CNI/H&T-MDU I & II (Adhoc) /2015-16/ Date: 09.01.2016. Tender notice

Tender No. CWC/RO-CNI/H&T-MDU I & II (Adhoc) /2015-16/ Date: 09.01.2016. Tender notice CENTRAL WAREHOUSING CORPORATION (A GOVT. OF INDIA UNDERTAKING) Regional Office : No.4 North Avenue,Srinagar Colony,Saidapet, Chennai 15. Phone : 22201216/0350 Fax. 22200068. E-Mail :rmmdrs.cwhc@nic.in

More information

EMPLOYEES STATE INSURANCE CORPORATION (ESIC) Welcome to Pre Bid conference 12-10-2015

EMPLOYEES STATE INSURANCE CORPORATION (ESIC) Welcome to Pre Bid conference 12-10-2015 EMPLOYEES STATE INSURANCE CORPORATION (ESIC) Welcome to Pre Bid conference 12-10-2015 ESI ACT, 1948 The Employees State Insurance Act - Promulgated by the Parliament in the year 1948. The Scheme was introduced

More information

CENTRAL WAREHOUSING CORPORATION (A GOVT. OF INDIA UNDERTAKING) REGIONAL OFFICE: CHENNAI.

CENTRAL WAREHOUSING CORPORATION (A GOVT. OF INDIA UNDERTAKING) REGIONAL OFFICE: CHENNAI. CENTRAL WAREHOUSING CORPORATION (A GOVT. OF INDIA UNDERTAKING) REGIONAL OFFICE: CHENNAI. E-TENDER DOCUMENT FOR APPOINTMENT OF REGULAR H&T CONTRACTOR AT CW, CHROMEPET, CHENNAI. DATE FOR DOWNLOADING TENDER

More information

Technical Requirem ent

Technical Requirem ent Reasoned document for draft Functional Requirement of system of Centralized coach Monitoring system (CCMS) for air conditioned LHB EOG coaches of ndian railway. SL. No. Clause Title Clau se No Technical

More information

Track Forever GPS Tracking Control Center Specification

Track Forever GPS Tracking Control Center Specification Track Forever GPS Tracking Control Center Specification Invincible People, Invincible Technologies & Invincible Solutions We develop solutions that reach beyond physical boundaries using state of the art

More information

Challan Generation Steps

Challan Generation Steps IT Rollout Challan Generation Steps INTRODUCTION : IT ENABLEMENT IN ESIC INSTITUTIONS In order to provide hassle-free services to the stakeholders, ESIC is implementing an IT Roll Out Plan named Project

More information

Online Railway Reservation. Intel Easy Steps 1 2012 Intel Corporation All rights reserved.

Online Railway Reservation. Intel Easy Steps 1 2012 Intel Corporation All rights reserved. Online Railway Reservation Intel Easy Steps 1 2012 Intel Corporation Online Railway Reservation Introducing Online Railway Reservation System Technology has transformed many aspects of life in the 21st

More information

Company Profile Excelanto Technologies

Company Profile Excelanto Technologies WELCOME Company Profile Excelanto Technologies is a Software development company that specializes in Windows and Web Based development activities, client server solutions and Corporate Website development

More information

Global Asset Tracking & Identification System

Global Asset Tracking & Identification System ` Global Asset Tracking & Identification System 2 About GATIS Solutions Global Asset Tracking & Identification Systems GATIS is a robust, secure and comprehensive Auto-ID system, with a logistic and asset

More information

INTRODUCTION SAHAJ ACCOUNTING

INTRODUCTION SAHAJ ACCOUNTING INTRODUCTION Welcome to SAHAJ ACCOUNTING software, not just accounting, complete business solutions. Whether you plan to manage your personal accounts or the finances of your business, you can use SAHAJ

More information

Supply Chain Management- Indian Railways

Supply Chain Management- Indian Railways Supply Chain Management- Indian Railways Divya Gangwar, and Navin Kumar Abstract Indian Railways is one of the biggest organisation of Government of India employing nearly 14 lakh persons and having annual

More information

HUMAN RESOURCES DEPARTMENT. HR-TAD/M2/Rec/2013 12 th September 2013 RECRUITMENT OF CLERKS AND OFFICERS

HUMAN RESOURCES DEPARTMENT. HR-TAD/M2/Rec/2013 12 th September 2013 RECRUITMENT OF CLERKS AND OFFICERS BANKING PARTNER Regd. Office: Aluva, Kerala HUMAN RESOURCES DEPARTMENT HR-TAD/M2/Rec/2013 12 th September 2013 RECRUITMENT OF CLERKS AND OFFICERS Federal Bank, a leading Private Sector Bank having pan

More information

VENDOR ENROLMENT HELP MANUAL MATERIALS, COMPONENTS & SERVICES

VENDOR ENROLMENT HELP MANUAL MATERIALS, COMPONENTS & SERVICES VENDOR ENROLMENT HELP MANUAL For MATERIALS, COMPONENTS & SERVICES Page 0 OFB eprocurement System Vendor Enrolment Module This module affects all users who wish to enroll as a Vendor. Through this enrolment,

More information

23. I.T. SECTIONS (HARDWARE AND SOFTWARE)

23. I.T. SECTIONS (HARDWARE AND SOFTWARE) 23. I.T. SECTIONS (HARDWARE AND SOFTWARE) 23.1 Main functions: The I.T. Sections (H&S) look after the following works: (i) Providing Secretarial assistance and support to the following Committees: (a)

More information

Indian Railways: Fast-Tracking to Success with Technology from SAP

Indian Railways: Fast-Tracking to Success with Technology from SAP 2014 SAP AG or an SAP affiliate company. All rights reserved. Indian Railways: Fast-Tracking to Success with Technology from SAP Indian Railways Industry Public sector Products and Services Rail transportation

More information

Refund Rules and TDR Filing w.e.f. 12-NOVEMBER-2015

Refund Rules and TDR Filing w.e.f. 12-NOVEMBER-2015 Refund Rules and TDR Filing w.e.f. 12-NOVEMBER-2015 Authority:- Railway Board letter No.TCII/2003/2015/Refund Policy/1 dated 06-Nov-2015 The Gazette Of India Notification Dated 04-Nov-2015. Ticket Booking/cancellation

More information

Expression of Interest (EOI) For. End to End Solution For Enterprise Data Warehouse Solution In Punjab National Bank

Expression of Interest (EOI) For. End to End Solution For Enterprise Data Warehouse Solution In Punjab National Bank Expression of Interest (EOI) For End to End Solution For Enterprise Data Warehouse Solution In Punjab National Bank PUNJAB NATIONAL BANK INFORMATION TECHNOLOGY DIVISION HEAD OFFICE, 5 SANSAD MARG, NEW

More information

miletone as suggested below:

miletone as suggested below: Response to Queries by Bidders for Tender "RFP for Design, Development, Hosting and Maintenance of Website/Portal for MMRC for 2 years." Sr. No. Clause Ref. No. Original Clause Query Proposal by Bidder

More information

City of Coral Gables

City of Coral Gables City of Coral Gables Information Technology Department IT TECHNICAL SUPPORT DIVISION Infrastructure Upgrade Plan Systems, Applications, Network, and Telecommunications Infrastructure OVERVIEW Last revision:

More information

NOTICE INVITING e-quotation

NOTICE INVITING e-quotation NOTICE INVITING e-quotation O/O EXECUTIVE DIRECTOR FLIGHT INSPECTION UNIT SAFDARJUBG AIRPORT NEW DELHI-110003 Ref.No: AAI/FIU/Aircraft/Insurance/2015-16/ DATE: 05/08/2015 Subject: Insurance of AAI Fleet

More information

DREAM IT PROJECTS M-SUBURBAN TRAIN TICKET SYSTEM. www.dreamitprojects.com DREAM IT Projects Contact: 9870699963 9870645416. Page 1

DREAM IT PROJECTS M-SUBURBAN TRAIN TICKET SYSTEM. www.dreamitprojects.com DREAM IT Projects Contact: 9870699963 9870645416. Page 1 DREAM IT PROJECTS M-SUBURBAN TRAIN TICKET SYSTEM www.dreamitprojects.com DREAM IT Projects Contact: 9870699963 9870645416 Page 1 Contents 1. Abstract... 3 2. Overview... 3 3. Current Scenario... 4 4. Proposed

More information

Invitation for Expression of interest : e-maintenance management system

Invitation for Expression of interest : e-maintenance management system Invitation for Expression of interest : e-maintenance management system Introduction 1. The maintenance responsibility in the IAF spans across a diverse range of aircraft, associated equipment, support

More information

PRELIMINARY GUIDELINES E-PROCUREMENT MODULE OF NIC

PRELIMINARY GUIDELINES E-PROCUREMENT MODULE OF NIC PRELIMINARY GUIDELINES E-PROCUREMENT MODULE OF NIC As per the Office Memorandum (OM)no. 10/3/2012-PPC dated 30 th March, 2012, issued by the Department of Expenditure, all Ministries / Departments of the

More information

Railways Budget 2015-16: Detailed Analysis

Railways Budget 2015-16: Detailed Analysis Railways Budget 2015-16: Detailed Analysis The Minister of Railways, Mr. Suresh Prabhu, presented the Railways Budget 2015-16 to Parliament on February 26, 2015. In his address, he assessed the performance

More information

CRM Login ADMIN PANEL. URL - www.fulloncrm.com. Login page Details: 1. Login Page :

CRM Login ADMIN PANEL. URL - www.fulloncrm.com. Login page Details: 1. Login Page : CRM Login ADMIN PANEL URL - www.fulloncrm.com Login page Details: 1. Login Page : Enter your Login Credential and click on login then it will open your panel. 2. Admin Dashboard : Your Admin dashboard

More information

e-procurement on Indian Railways Sanjay Aggarwal & V K Srivatsava

e-procurement on Indian Railways Sanjay Aggarwal & V K Srivatsava e-procurement on Indian Railways Sanjay Aggarwal & V K Srivatsava Case Studies on e-governance in India 2012-2013 Page i e-procurement on Indian Railways Sanjay Aggarwal & V K Srivatsava Case Studies on

More information

2 2 & 2 3 3 3 4 / / EMD

2 2 & 2 3 3 3 4 / / EMD Contents Website... 2 Live Tenders... 2 Registration & Digital Signatures... 2 Participation in the Tender... 3 Login... 3 Online Request for the Tender... 3 Download Documents... 4 Upload files Technical

More information

LEARNING SOLUTIONS website milner.com/learning email training@milner.com phone 800 875 5042

LEARNING SOLUTIONS website milner.com/learning email training@milner.com phone 800 875 5042 Course 6451B: Planning, Deploying and Managing Microsoft System Center Configuration Manager 2007 Length: 3 Days Published: June 29, 2012 Language(s): English Audience(s): IT Professionals Level: 300 Technology:

More information

NOTICE INVITING PROPOSAL

NOTICE INVITING PROPOSAL NOTICE INVITING PROPOSAL Sl. Pg. 1 1. CIDCO of Maharashtra Limited through the process of e-tendering invites On-line Proposal from single business entities fulfilling the eligibility criteria for PMIC

More information

Project Manager 1 Post == Experience 10-12 years in Project Management in reputed company, Salary Rs.1,20,000/-

Project Manager 1 Post == Experience 10-12 years in Project Management in reputed company, Salary Rs.1,20,000/- Project Manager 1 Post == Experience 10-12 years in Project Management in reputed company, Salary Rs.1,20,000/- Senior Soft ware Developer 2 Posts Junior Soft ware Developer 4 Posts Database Administrator

More information

System Administration Training Guide. S100 Installation and Site Management

System Administration Training Guide. S100 Installation and Site Management System Administration Training Guide S100 Installation and Site Management Table of contents System Requirements for Acumatica ERP 4.2... 5 Learning Objects:... 5 Web Browser... 5 Server Software... 5

More information

TCIL/16/12/07/2015(WI) 22 nd July 2015. NIT for Pre-bid Tie-up for Disaster Management EoI

TCIL/16/12/07/2015(WI) 22 nd July 2015. NIT for Pre-bid Tie-up for Disaster Management EoI TCIL/16/12/07/2015(WI) 22 nd July 2015 NIT for Pre-bid Tie-up for Disaster Management EoI Telecommunications Consultants India Ltd., (TCIL), is a Government of India Enterprise under Ministry of Communications,

More information

Government of Rajasthan Directorate of Horticulture, Rajasthan, Jaipur. Expression of Interest

Government of Rajasthan Directorate of Horticulture, Rajasthan, Jaipur. Expression of Interest Government of Rajasthan Directorate of Horticulture, Rajasthan, Jaipur No. DH/MIS/Solar/Web/2012-13/7058 Dated: 18.02.13 Expression of Interest The Directorate of Horticulture/ RHDS intends to invite offers

More information

Table of Contents INTRODUCTION... 2 HOME... 3. Dashboard... 5 Reminders... 8 Announcements... 12 Preferences... 13 Recent Items... 15 REQUESTS...

Table of Contents INTRODUCTION... 2 HOME... 3. Dashboard... 5 Reminders... 8 Announcements... 12 Preferences... 13 Recent Items... 15 REQUESTS... Table of Contents INTRODUCTION... 2 HOME... 3 Dashboard... 5 Reminders... 8 Announcements... 12 Preferences... 13 Recent Items... 15 REQUESTS... 16 Request List View... 17 Requests based on Filters...

More information

e-procurement in Indian Railways Sanjay Aggarwal V. K. Srivastava

e-procurement in Indian Railways Sanjay Aggarwal V. K. Srivastava e-procurement in Indian Railways Sanjay Aggarwal V. K. Srivastava Case Studies on e-governance in India 2012-2013 e-procurement in Indian Railways Sanjay Aggarwal V. K. Srivastava Case Studies on e-governance

More information

Amendment 1 - Annexure 5 (C) Technical Criteria

Amendment 1 - Annexure 5 (C) Technical Criteria 1 - Annexure 5 (C) Technical Criteria S. Eligibility Criteria Documents required Complied Y/N Formatted: Heading 2, Indent: Left: 0", Hanging: 0.4" C) Technical Criteria (Experience and other Technical

More information

Undertakings and other Organisations

Undertakings and other Organisations Undertakings and other Organisations CONTAINER CORPORATION OF INDIA LTD. (CONCOR): Container Corporation of India Ltd. (CONCOR) was set up in November 1989 with the prime objective of developing multi-modal

More information

Software Requirements Specification for a Management Information System at NIT Calicut

Software Requirements Specification for a Management Information System at NIT Calicut Software Requirements Specification for a Management Information System at NIT Calicut National Institute of Technology, Calicut (NIT Calicut) is one of the leading research and academic institutes in

More information

BANARAS HINDU UNIVERSITY VARANASI

BANARAS HINDU UNIVERSITY VARANASI BANARAS HINDU UNIVERSITY VARANASI [Website : www.bhu.ac.in] EXPRESSION of INTEREST (EoI) FOR UNIVERSITY MANAGEMENT SYSTEM LAST DATE FOR RECEIPT OF EoI : 15 th March, 2010 DATE & TIME OF EoI Presentation

More information

Last Updated on 11/06/2008. www.jobprotech.com

Last Updated on 11/06/2008. www.jobprotech.com Last Updated on 11/06/2008 www.jobprotech.com Copyright JobPro Technology, 2008 How to Use this Guide This manual is designed as a reference for JobPro customers. It is not intended to be a replacement

More information

MDM SMS Based Monitoring System USER MANUAL

MDM SMS Based Monitoring System USER MANUAL Page #:1 of MDM SMS Based Monitoring System USER MANUAL 1 Page #:2 of Contents 1. Introduction... 3 1.1 Purpose... 3 1.2 Scope... 3 1.3 Getting Started... 3 2. MDM Scheme... 5 2.1 Master... 6 2.1.1 MDM

More information

Say Goodbye to paper work computerize your Schools & Colleges..!! Presented by- Manav Technologies

Say Goodbye to paper work computerize your Schools & Colleges..!! Presented by- Manav Technologies Say Goodbye to paper work computerize your Schools & Colleges..!! Presented by- Manav Technologies Manav Technologies is Chhattisgarh based Online Services provider.manav Technologies is striving to become

More information

Management System. Product FOX-CAMMS. www.foxindia.net. FOX Group

Management System. Product FOX-CAMMS. www.foxindia.net. FOX Group FOX/Br-018A/CAMMS/Rev6 18.05.12 www.foxindia.net FOX Group Fox Controls Pvt. Ltd. Fox Automation. Fox Solutions. Fox Singapore Pte. Ltd. Product FOX-CAMMS Centralized Asset Maintenance Management System

More information

Corrigendum to RFP for Selection of Managed Service Provider for eprocurement System

Corrigendum to RFP for Selection of Managed Service Provider for eprocurement System Corrigendum to RFP for Selection of Managed Service Provider for eprocurement System Reference is made to RFP Ref. No.: DSD/HR/e-procurement/2013/1 Dated 15/07/2013. Following corrections/alterations in

More information

Organise Your Business

Organise Your Business Organise Your Business Second CRM On Demand Customer Relationships A Functional Introduction Presentation January, 2013 Organise Your Business Second CRM On Demand Customer Relationships Designed for Small

More information

NMS300 Network Management System

NMS300 Network Management System NMS300 Network Management System User Manual June 2013 202-11289-01 350 East Plumeria Drive San Jose, CA 95134 USA Support Thank you for purchasing this NETGEAR product. After installing your device, locate

More information

PRELIMINARY GUIDELINES E-PROCUREMENT MODULE OF NIC

PRELIMINARY GUIDELINES E-PROCUREMENT MODULE OF NIC PRELIMINARY GUIDELINES E-PROCUREMENT MODULE OF NIC As per the Office Memorandum (OM) no. 10/3/2012-PPC dated 30 th March, 2012 and all subsequent OMs, issued by the of Expenditure, all Ministries / s of

More information

INVITATION FOR EXPRESSION OF INTEREST SYSTEM INTEGRATOR- SUPPLY AND IMPLEMENTATION OF ERP BASED CGLMS

INVITATION FOR EXPRESSION OF INTEREST SYSTEM INTEGRATOR- SUPPLY AND IMPLEMENTATION OF ERP BASED CGLMS 1 INVITATION FOR EXPRESSION OF INTEREST SYSTEM INTEGRATOR- SUPPLY AND IMPLEMENTATION OF ERP BASED CGLMS Purpose of the EOI 1. Headquarters, Indian Coast Guard, invites Expression of Interest from vendors

More information

Standupmitra Portal User Manual

Standupmitra Portal User Manual Stand-Up India scheme and web based interactive portal (www.standupmitra.in) were launched by the Hon ble Prime Minister on April 05, 2016. Under the guidance of Dept. of Financial Services, Ministry of

More information

Self Help Guide. (Home WiFi) Contents

Self Help Guide. (Home WiFi) Contents Self Help Guide (Home WiFi) Contents 1. Having issue! Refer to relevant topic... 2 a. Connection not working... 2 i. CPE / WiFi Router customers... 2 ii. Ethernet / Wireline customers... 3 b. Manage Password...

More information

HINDUSTAN AERONAUTICS LIMITED (BANGALORE COMPLEX) FACILITIES MANAGEMENT DIVISION BANGALORE- 560 017 E-TENDER NOTICE FM/NEP/INT/27/14-15 Date: 29.01.

HINDUSTAN AERONAUTICS LIMITED (BANGALORE COMPLEX) FACILITIES MANAGEMENT DIVISION BANGALORE- 560 017 E-TENDER NOTICE FM/NEP/INT/27/14-15 Date: 29.01. HINDUSTAN AERONAUTICS LIMITED (BANGALORE COMPLEX) FACILITIES MANAGEMENT DIVISION BANGALORE- 560 017 E-TENDER NOTICE FM/NEP/INT/27/14-15 Date: 29.01.15 Online E-tenders are invited in Two-Bid System for

More information

Introduction to Hosted Desktop Services (HDS)

Introduction to Hosted Desktop Services (HDS) Introduction to Hosted Desktop Services (HDS) Powerdial Services Ltd Introduction to Hosted Desktop Service Overview 2014 Hosted Desktops What are they? It s your computer but hosted in the Cloud It s

More information

Tecknodreams Software Consulting Pvt. Ltd. Managing IT Services in an Insurance Company

Tecknodreams Software Consulting Pvt. Ltd. Managing IT Services in an Insurance Company Tecknodreams Software Consulting Pvt. Ltd. Managing IT Services in an Insurance Company Company Profile This Insurance Company is a specialist in Health Insurance and provides quality service at the best

More information

A Guide to New Features in Propalms OneGate 4.0

A Guide to New Features in Propalms OneGate 4.0 A Guide to New Features in Propalms OneGate 4.0 Propalms Ltd. Published April 2013 Overview This document covers the new features, enhancements and changes introduced in Propalms OneGate 4.0 Server (previously

More information

Hardware. Maintenance

Hardware. Maintenance Government Services available through the portal 1. The scope of the work is limited to the portal and its integration with service provider applications. It doesn't include any work on the service provider

More information

An Integrated Business Management Solution

An Integrated Business Management Solution An Integrated Business Management Solution www.exactllyerp.com exactllyerp An Integrated Business Management Solution MEETS ALL YOUR CORE BUSINESS NEEDS SIMPLE TO LEARN AND USE DRIVES VALUE FOR YOUR BUSINESS

More information

Financial Advice Budget II General Accounts (1) (2) (3) (4) (5) (6) 1. 2. 3. 4. 5. 6. 7. 8.

Financial Advice Budget II General Accounts (1) (2) (3) (4) (5) (6) 1. 2. 3. 4. 5. 6. 7. 8. APPENDIX II (See para 129) GENERAL LIST OF IMPORTANT ITEMS OF WORK REQUIRED TO BE DONE BY AN ACCOUNTS OFFICER ON HIS POSTING AS INCHARGE OF A BRANCH/SECTION OF AN ACCOUNTS OFFICE 1. An Accounts Officer

More information

Invitation of Bid Proposals for.net Migration of APEDA website, its online applications and Setting up APEDA itrack System

Invitation of Bid Proposals for.net Migration of APEDA website, its online applications and Setting up APEDA itrack System Invitation of Bid Proposals for.net Migration of APEDA website, its online applications and Setting up APEDA itrack System 1. Introduction APEDA is a pioneer in using information technology for its internal

More information

Corporate Online Travel Solutions. by Thomas Cook (India) Ltd.

Corporate Online Travel Solutions. by Thomas Cook (India) Ltd. Corporate Online Travel Solutions by Thomas Cook (India) Ltd. Dear Corporate, Welcome! And on behalf of the Thomas Cook (India) Ltd., I warmly invite you aboard an exciting journey of travel! In 1841,

More information

NOTICE INVITING e-tender NOTICE (3 BOT -3 Envelopes Open Tender) (Bid Invitation No. 1000011060)

NOTICE INVITING e-tender NOTICE (3 BOT -3 Envelopes Open Tender) (Bid Invitation No. 1000011060) Ref: AAI /VNS/AGM (E-E)/e-NIT-9/2015-16/ Date: 19/08/2015 NOTICE INVITING e-tender NOTICE (3 BOT -3 Envelopes Open Tender) (Bid Invitation No. 1000011060) 1. Item rate(s) tenders are invited through, the

More information

ASSAM POWER GENERATION CORPORATION LIMITED

ASSAM POWER GENERATION CORPORATION LIMITED ASSAM POWER GENERATION CORPORATION LIMITED Notice Inviting Expression of Interest for Consultancy in connection of Assam Power Sector Investment Program financed by ADB NIT No. NIT/PMU/05 of 2014-15 Director

More information

National Small Industries Corporation Ltd NSIC Bhawan, Okhla Industrial Estate, Phase III New Delhi-20 Telephone: 011-26927059

National Small Industries Corporation Ltd NSIC Bhawan, Okhla Industrial Estate, Phase III New Delhi-20 Telephone: 011-26927059 National Small Industries Corporation Ltd NSIC Bhawan, Okhla Industrial Estate, Phase III New Delhi-20 Telephone: 011-26927059 NOTICE INVITING TENDER FOR DESIGN, DEVELOPMENT, IMPLEMENTATION AND TESTING

More information

TENDER DOCOUMENT. For

TENDER DOCOUMENT. For TENDER DOCOUMENT For Hosting of Live Video Streaming or Webcasting Products and applications on Keonics mainframe infrastructure under Linux platform on revenue sharing model KARNATAKA STATE ELECTRONICS

More information

nexvortex SIP Trunking Implementation & Planning Guide V1.5

nexvortex SIP Trunking Implementation & Planning Guide V1.5 nexvortex SIP Trunking Implementation & Planning Guide V1.5 510 S PRING S TREET H ERNDON VA 20170 +1 855.639.8888 Introduction Welcome to nexvortex! This document is intended for nexvortex Customers and

More information

GPS/GSM/ GPRS/ Web Based Real Time Vehicle Tracking System RFP

GPS/GSM/ GPRS/ Web Based Real Time Vehicle Tracking System RFP Introduction We are looking for a web based real time vehicle tracking software system to be used with all popular GPS/GSM/GPRS based tracking devices. We intend to provide GPS Tracking/ fleet management

More information

Progress by Partnership. State Wide E-Procurement Implementation

Progress by Partnership. State Wide E-Procurement Implementation Progress by Partnership 1 State Wide E-Procurement Implementation Contents Selecting the Platform and Model Snapshot of progress so far Implementation Challenges Way forward 3 Selecting the e-procurement

More information

Chapter 11 Training Requirements

Chapter 11 Training Requirements Chapter 11 Training Requirements 11.1 Computer Training Keeping in view the large scale computerization in the IR, the Committee discussed at length the present status of availability of computer trained

More information

Secure, Compliant and Flexible Cloud Services

Secure, Compliant and Flexible Cloud Services www.ricohidc.com Secure, Compliant and Flexible Cloud Services Key to continuous success is EVOLUTION RICOH CLOUD SERVICES - Next Generation Cloud Services Our ISO 27001 certified datacenters provide wide

More information

Maharashtra State e-governance Policy 2011 e-governance Policy of Maharashtra - 2011 Government of Maharashtra Directorate of Information Technology General Administration Department 7th Floor, Mantralaya,

More information

Integral Party Plan Software. Implementation Options 2015

Integral Party Plan Software. Implementation Options 2015 Integral Party Plan Software Implementation Options 2015 Party Plan Solutions Overview Party Plan Solutions is a software development and business consulting firm dedicated to serving direct selling companies

More information

TENDER DOCUMENT FOR EXPRESSION OF INTREST FOR STORE AND ASSET MANAGEMENT SOFTWARE AIIMS PATNA

TENDER DOCUMENT FOR EXPRESSION OF INTREST FOR STORE AND ASSET MANAGEMENT SOFTWARE AIIMS PATNA Govt. of India ALL INDIA INSTITUTE OF MEDICAL SCIENCES, PATNA (An Autonomous body under MoHFW, Govt. of India) TENDER NO: AIIMS/Pat/Tender/EOI/Store & asset Mgt Software/2014 DATED: 14.07.2014 TENDER DOCUMENT

More information

Distribution Training Guide. D110 Sales Order Management: Basic

Distribution Training Guide. D110 Sales Order Management: Basic Distribution Training Guide D110 Sales Order Management: Basic Certification Course Prerequisites The combined D110 Sales Order Management certification course consists of a hands- on guide that will walk

More information