1 UHIN STANDARDS COMMITTEE Version 2.3 Change Management Specification The UHIN Change Management Specification is compatible with all HIPAA requirements. Purpose: The purpose of this Specification is to detail a formal process by which change to the UHIN community network is implemented. Changes can come in the form of National Standards, commercial/governmental payer or provider needs, Board of Directors or Executive Committee directives. Goal: The goal for this Specification is to detail the process for managing change to the UHINet II (gateway) and UHIN branded products. This will allow UHIN members to meet deadlines together (as much as possible) using a coordinated approach for the benefit of the UHIN community. Responsibility: The Change Management Subcommittee will be responsible for managing the development methodology and implementation procedure which adheres to this Specification. In order to meet this responsibility the committee will need to meet on an on-going basis to develop community test plans for all changes. This committee will coordinate the necessary resources for each community organization to implement test plans. UHIN Staff is responsible to coordinate with vendors for the implementation of the change management process. Authority: Change Management Committee must have participation, from member organizations, representing Standards and Technical interests. Participants will be developing the change management process and are expected to have sufficient knowledge to create the project plans. The organization representative(s) must have the authority to influence the commitment of resources for the testing portion of the change management process. Representatives must be able to communicate with the appropriate internal authorities for resource allocation for development, testing and implementation. Change management has responsibility to report to the UHIN Standards Committee the changes and request the commitment of resources from the Executive Committee/Board. Applicability: This Specification applies to all changes that are required within the UHIN community for implementation of Electronic Data Interchange for all health care related data. Items addressed by this Specification include but are not limited to the following: Utah Health Information Network Transactor (UHINT) Utah Health Information Network Net (UHINet II) Clinical Health Information Exchange Hub UHINSpeedi UHINTracker UHIN e-lite Written documentation for products and services o Design documentation (i.e. scope, functional and technical) o UHINet Connectivity Documents Technical Reference Manual (TRM) for UHINet II o UHINet Web Portal User Manual o UHINT User Manual o UHINSpeedi User Manual o UHINTracker User Manual o UHIN e-lite User Manual o Other documents as developed/approved 1

2 Processes for timelines, monitoring, testing and implementing change in UHIN network systems in compliance and accordance with UHIN Standards and Specifications. Formal process for converting the current systems/processes from test to production. TIME LINE FOR SCHEDULED CHANGES TO UHINET AND UHINT Figure 1 UHINet and UHINT release time charts. October Release 2 nd Tuesday Gather changes, scope and functional documentation for October release Change Management Prioritizes Changes and creates test plans Forward work to Standards for approval UHIN Staff UHIN Staff Negotiate w/ vendor for changes UHIN Staff α-test β-test RELEASE 2 nd Tuesday April Release 2 nd Tuesdsay Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep OCT May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar APR UHINet and UHINT Products 1. UHIN has two scheduled major releases per year; one in April and one in October. 2. Non routine changes will have to be approved by Executive/Board and incorporated to the prioritization process for changes. 3. The Change Management Subcommittee coordinates the way in which changes, updates and testing are completed for UHINet and UHIN branded products. 4. Change Management will meet as necessary prior to the beta testing time period to develop the community test plan. 2

3 Figure 2 UHINSpeedi Change Schedule May Release 2 nd Tuesday Gather changes, scope and functional documentation for November release Change Management Prioritizes Standards approval Negotiate Changes α-test β-test RELEASE 2 nd Tuesday Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May November Release 2 nd Tuesday Additional System Updates Elysium Changes (Axolotl) As of August 25 th, 2009, monthly releases will occur when needed during this preproduction period. Once we are in full production this will be revisited. e-lite Changes (Axolotl) As of August 25 th, 2009, monthly releases will occur when needed on Wednesday mornings (2:00am 5:00am). Once we are in full production this will be revisited. Programming Error Fixes As of August 25 th, 2009, Programming Error Fixes shall occur on the 2 nd and 4 th Tuesday of the month. There is a caveat that an update on the 4 th Tuesday will be done only if needed and is not an end of the month date. Appendix B provides the schedule for all system and application updates. 3

4 Process Flow for Change Requests 4

5 Details of process flow for requested changes to the UHIN community network 1. All requests are taken by UHIN staff and determined whether they are programming/service problems or new services. 2. Requests for changes will be taken to the Standards Committee for review in regard to Standards or Specification work (Standards/Specifications will follow the Standards process flow) Budget constraints Time or resource constraints If a change request requires additional funding or based on investigation cannot be incorporated into the request list those requests will be forwarded to the Executive/Board for approval. 3. Those that do not require Executive/Board approval or have obtained approval will then be provided to the Change Management for prioritization 4. The Change Management Committee prioritizes the list of change requests and sends list back to the Standards Committee for final approval. 5. Standards Committee approves, comments or renegotiates with Change Management on list of changes 6. The approved list is sent forward to UHIN Project Team for negotiations with vendors 7. UHIN Project Team provides the completed negotiated list to Change Management and the Standards Committee. Those items that are not negotiated for will be kept in queue by the Change Management Subcommittee for the next release date or for inclusion into the UHIN budget process. 8. Change Management Subcommittee creates implementation plans for the roll out which includes but is not limited to Type of testing Testing partner coordination Defined timelines for testing Defined Timelines for release. 9. Changes will follow the detailed implementation plan process. 10. Change Management Signs off on completed changes. 11. Notification is sent to the community. 5

6 1. Development of new apps/version releases. There are may be times when testing new applications and version releases will occur outside of the normal release schedule. The Change Management Subcommittee is committed to following the Routine release schedule as often as possible. When a change or new product is released outside of the routine time line then the Change Management Subcommittee will expect that the application will be tested/accepted in the following manner and documented in the implementation plan. UHIN offers unique environments for Alpha and Beta testing of new applications or version releases. Please see Appendix A for an explanation of these environments. Quality Assurance Product Service testing in the Peruvian environment 2-3 week time frame 1. Unit testing will be done primarily by UHIN Staff and community members when requested. This stage of testing should be based on each requirement within the technical Specification. This testing is done to ensure that the specific requirements of the negotiated changes have been completed and has not impacted the existing programming. UHIN staff, by policy set by the Executive Committee, is not allowed to have PHI therefore some community members may be requested to participate. 2. Load testing may be completed by Community members, but is not required. 3. UHIN Staff will not test connectivity items. Product/Service testing in the Solitude environment 2-3 week time frame 1. UHIN Community Quality Unit Testing. This stage of testing is to verify the product functionality. This testing is completed by the UHIN Community This stage of testing should be based on completion of the plan created by Change Management. 2. Regression/User Acceptance Testing. This stage of testing is a front to back test of the modified applications and systems. This testing is the final test to ensure that any change did not disrupt another portion of the software. This include but is not limited to New feature Critical existing features Load testing Testing bug fixes Communication pathways This testing is coordinated by Change Management Subcommittee with key stakeholders. This testing coordination will be incorporated into the testing plan. It is assumed that the stakeholders will be available for testing based on scheduled release dates and the Change Management timeline. In the event issues that were in the Specification were not met the application or version/upgrade will be returned to Strategic partner/vendor for re-programming. 2. Testing Plan The testing plan will be created by the Change Management to address the specific testing types and activities which will include but not be limited to types of testing, testing timelines and notification issues. The timelines for testing will, as much a possible, follow the guidelines outlined in the UHINet and UHIN Branded Products release time charts in Figure 1 above. 6

7 3. Testing Sign Off UHIN Change Test Results and Sign Off Description of Change Change No Product/Service: Date: Detailed Description of Changes to be tested: (attach additional pages if needed) Testing Plan: (attach additional pages if needed) Testing Partners for this test plan Contact Name Organization TPN/Environment Contact Name Organization TPN/Environment Contact Name Organization TPN/Environment Contact Name Organization TPN/Environment Environments requiring Test: UHIN Internal Staging Prestaging Mirrored Production UHIN Internal Staging Development Production Testing Results: 7

8 For Test Sign Off or Return to Vendor for additional fixes: Tested/Approved By: Disagree Comment Tested/Approved By: Disagree Comment Tested/Approved By: Disagree Comment Tested/Approved By: Disagree Comment Tested/Approved By: Disagree Comment Tested/Approved By: Disagree Comment 8

9 Documentation 1. All documentation distributed by UHIN will accurately reflect what the current process is or incorporates. 2. UHIN Committees will be given draft copies for comment and review. 3. Final documents will be available and distributed through the UHIN web site or UHIN list serves. 4. Implementation Issues: 1. Any contractual negotiations will be completed by UHIN Management as needed. 2. The Executive Director may re-prioritize the implementation of changes based on (1) budgetary constraints and (2) usefulness of the implementation to the majority of UHIN Subscribers. 3. UHINet and UHIN branded products will meet all deadlines set in approved Standards and Specifications. Implementation Date: History: (MM/DD/YY) Original A* 1 A 2 A3 A 4 ORIGINATION DATE 01/01/04 05/24/07 08/27/09 APPROVAL DATE 5/12/04 2/6/ /02/09 EFFECTIVE DATE 6/12/04 3/6/ /02/10 * A = Amendment 9

10 Appendix A UHINet Environments 10

11 UHIN Testing Environment Request for the chie UHIN understands that we currently have two servers, a test server and one for production. If we understand correctly currently the demo and production environments both reside on the production server and test on the test server. We prefer to keep the test and production environments on separate servers and isolated from each other as much as possible. We do not want the risk of test and production data becoming inadvertently mixed. Having test and production on separate servers is the method that the UHIN community has asked for in the past and is accustomed to having. As background, below is a description of the environments currently in use for the administrative network, UHINet II. UHINet II Testing Environments The UHINet II testing environments and process are the result of requests directly from the UHIN community. UHINet II Environments Production Testing User Testing for Production Environment UHIN Prestaging UHIN Staff Testing (new updates) Development Community QA Testing (new updates) Production Production Environment Mirrored Environments Software from our strategic partner RelayHealth is first loaded in the UHIN Prestaging test environment where Beta testing is performed by UHIN. All software updates first goes here for both major and interim releases. After the software passes testing in UHIN Prestaging it moves to the Development environment where community members as needed can also test the most recently released software. Once UHIN is satisfied that the software has passed all testing and is ready for production it is moved simultaneously to the Production Testing test environment and to Production which is the production environment. Production Testing is a test environment that is an exact mirror of production. Production Testing is available for UHIN members to test their own software and connections against an environment that is exactly like production but without affecting production. The test environments UHIN and Production Testing are virtual environments residing on the same server. Development and Production each have their own separate physical servers. 11

12 Document Revision History Ver /21/2009 Initial version. 12

13 Appendix B Change Management and System Change Schedule System Architecture Changes (DirectPointe) Emergency right away High Risk As per Medium Risk Low Risk Currently 2 nd and 4 th Tuesday - change to 1 st and 3 rd Tuesday of the Month beginning UHINet Router programming changes (RelayHealth) April and October 2 nd Tuesday UHINT Application Changes (RelayHealth) April and October 2 nd Tuesday UHINSpeedi - Application Changes (All Health) May and November 2 nd Tuesday Elysium Changes (Axolotl) Monthly Releases when needed Change times/dates will be determined by utilization patters (off times) e-lite Changes (Axolotl) Monthly Releases when needed Wednesday mornings (2:00 5:00am) Programming Error Fixes 2 nd and 4 th Tuesday of Month caveat on 4 th only if needed and not the end of the month date. 13

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

Analysis One Code Desc. Transaction Amount. Fiscal Period

Analysis One Code Desc. Transaction Amount. Fiscal Period Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00

More information

Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8

Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007

More information

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017 From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days

More information

Supervisor Instructions for Approving Web Time Entry

Supervisor Instructions for Approving Web Time Entry Supervisor Instructions for Approving Web Time Entry Time Approval Deadlines by Category Local 2110 Members members submit time by NOON on Monday of the pay week. Time should be approved no later than

More information

P/T 2B: 2 nd Half of Term (8 weeks) Start: 25-AUG-2014 End: 19-OCT-2014 Start: 20-OCT-2014 End: 14-DEC-2014

P/T 2B: 2 nd Half of Term (8 weeks) Start: 25-AUG-2014 End: 19-OCT-2014 Start: 20-OCT-2014 End: 14-DEC-2014 2014-2015 SPECIAL TERM ACADEMIC CALENDAR FOR SCRANTON EDUCATION ONLINE (SEOL), MBA ONLINE, HUMAN RESOURCES ONLINE, NURSE ANESTHESIA and ERP PROGRAMS SPECIAL FALL 2014 TERM Key: P/T = Part of Term P/T Description

More information

P/T 2B: 2 nd Half of Term (8 weeks) Start: 26-AUG-2013 End: 20-OCT-2013 Start: 21-OCT-2013 End: 15-DEC-2013

P/T 2B: 2 nd Half of Term (8 weeks) Start: 26-AUG-2013 End: 20-OCT-2013 Start: 21-OCT-2013 End: 15-DEC-2013 2013-2014 SPECIAL TERM ACADEMIC CALENDAR FOR SCRANTON EDUCATION ONLINE (SEOL), MBA ONLINE, HUMAN RESOURCES ONLINE, NURSE ANESTHESIA and ERP PROGRAMS SPECIAL FALL 2013 TERM Key: P/T = Part of Term P/T Description

More information

P/T 2B: 2 nd Half of Term (8 weeks) Start: 24-AUG-2015 End: 18-OCT-2015 Start: 19-OCT-2015 End: 13-DEC-2015

P/T 2B: 2 nd Half of Term (8 weeks) Start: 24-AUG-2015 End: 18-OCT-2015 Start: 19-OCT-2015 End: 13-DEC-2015 2015-2016 SPECIAL TERM ACADEMIC CALENDAR For Scranton Education Online (SEOL), Masters of Business Administration Online, Masters of Accountancy Online, Health Administration Online, Health Informatics

More information

Committee of the Whole. January 22, 2014

Committee of the Whole. January 22, 2014 Committee of the Whole January 22, 2014 Drivers for 2003 IT Outsourcing Cost savings - privatization model ($2- $3MM/year) Cost avoidance Data center lease with County expiring ($3.5MM) Disaster recovery

More information

2015-16 BCOE Payroll Calendar. Monday Tuesday Wednesday Thursday Friday Jun 29 30 Jul 1 2 3. Full Force Calc

2015-16 BCOE Payroll Calendar. Monday Tuesday Wednesday Thursday Friday Jun 29 30 Jul 1 2 3. Full Force Calc July 2015 CM Period 1501075 July 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 August 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

More information

Ashley Institute of Training Schedule of VET Tuition Fees 2015

Ashley Institute of Training Schedule of VET Tuition Fees 2015 Ashley Institute of Training Schedule of VET Fees Year of Study Group ID:DECE15G1 Total Course Fees $ 12,000 29-Aug- 17-Oct- 50 14-Sep- 0.167 blended various $2,000 CHC02 Best practice 24-Oct- 12-Dec-

More information

CENTERPOINT ENERGY TEXARKANA SERVICE AREA GAS SUPPLY RATE (GSR) JULY 2015. Small Commercial Service (SCS-1) GSR

CENTERPOINT ENERGY TEXARKANA SERVICE AREA GAS SUPPLY RATE (GSR) JULY 2015. Small Commercial Service (SCS-1) GSR JULY 2015 Area (RS-1) GSR GSR (LCS-1) Texarkana Incorporated July-15 $0.50690/Ccf $0.45450/Ccf $0.00000/Ccf $2.85090/MMBtu $17.52070/MMBtu Texarkana Unincorporated July-15 $0.56370/Ccf $0.26110/Ccf $1.66900/Ccf

More information

Computing & Telecommunications Services Monthly Report March 2015

Computing & Telecommunications Services Monthly Report March 2015 March 215 Monthly Report Computing & Telecommunications Services Monthly Report March 215 CaTS Help Desk (937) 775-4827 1-888-775-4827 25 Library Annex helpdesk@wright.edu www.wright.edu/cats/ Last Modified

More information

In accordance with risk management best practices, below describes the standard process for enterprise risk management (ERM), including:

In accordance with risk management best practices, below describes the standard process for enterprise risk management (ERM), including: Enterprise Risk Management Process and Procedures Scope In accordance with risk management best practices, below describes the standard process for enterprise risk management (ERM), including: Risk identification

More information

Bb Upgrade Timeline. Oct Nov Dec Jan 2011 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan 2012. PDFmyURL.com

Bb Upgrade Timeline. Oct Nov Dec Jan 2011 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan 2012. PDFmyURL.com Bb Upgrade Timeline Oct Nov Dec Jan 2011 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan 2012 Technology Create a training plan for Bb early adopters and mentors Conduct Transitioning to Bb 9.1 training

More information

Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre

Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre Proposal To change the opening hours of the Revenues & Benefits Call Centre to 9am until 5pm Monday to Friday with effect

More information

JISC data.bris project & EPSRC Platform project: progress against workplan (October 2012)

JISC data.bris project & EPSRC Platform project: progress against workplan (October 2012) Project Name : data.bris DBSG/5/2 JISC data.bris project & EPSRC Platform project: progress against workplan (October 2012) WORKPACKAGES Month: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Oct 11 Nov Dec

More information

NASDAQ DUBAI TRADING AND SETTLEMENT CALENDAR 2015. 1. On US Federal Reserve Holidays, no settlements will take place for USD.

NASDAQ DUBAI TRADING AND SETTLEMENT CALENDAR 2015. 1. On US Federal Reserve Holidays, no settlements will take place for USD. NASDAQ Dubai Circular No. : 65/14 Date of Issue : December 22 nd 2014 Date of Expiry : Upon issue of replacement Circular NASDAQ DUBAI TRADING AND SETTLEMENT CALENDAR 2015 Issued pursuant to the NASDAQ

More information

Oregon s Experience Accepting Online Credit and Debit Payments

Oregon s Experience Accepting Online Credit and Debit Payments Oregon s Experience Accepting Online Credit and Debit Payments Statistical Charts and Examples Page 1 of 8 How Oregon s Case Validation Works Semi-Technical Speak As part of their process, a vendor using

More information

ACCESS Nursing Programs Session 1 Center Valley Campus Only 8 Weeks Academic Calendar 8 Weeks

ACCESS Nursing Programs Session 1 Center Valley Campus Only 8 Weeks Academic Calendar 8 Weeks Session 1 Academic Calendar August 24, 2015 to October 17, 2015 Tuesday / Thursday, 5:30 pm to 8:30 pm M/W T/TH T/W TH S Saturday lab as scheduled Classes Begin 24-Aug 25-Aug 25-Aug 27-Aug 29-Aug NU205

More information

ACCESS Nursing Programs Session 1 Center Valley Campus Only 8 Weeks Academic Calendar 8 Weeks

ACCESS Nursing Programs Session 1 Center Valley Campus Only 8 Weeks Academic Calendar 8 Weeks Session 1 Academic Calendar August 24, 2015 to October 17, 2015 Tuesday / Thursday, 5:30 pm to 8:30 pm M/W T/TH T/W TH S Saturday lab as scheduled Classes Begin 24-Aug 25-Aug 25-Aug 27-Aug 29-Aug NU205

More information

CPSC ITDS/RAM Pilot System: PGA Message Set

CPSC ITDS/RAM Pilot System: PGA Message Set CPSC ITDS/RAM Pilot System: PGA Message Set Electronic Certificate Filing Test March 27, 2015 This presentation has not been reviewed or approved by the Commission and may not reflect its views CPSC Background

More information

Important Dates Calendar 2014-2015 FALL

Important Dates Calendar 2014-2015 FALL Important Dates Calendar 204-205 FALL Rev. 6-8-4 st 8 H st 0 2nd 0 st 5 2nd 5 3rd 5 LSC Advanced Registration Begins May 27 May 27 May 27 May 27 May 27 May 27 May 27 May 27 May 27 Returning Students Advanced

More information

Managing Projects with Practical Software & Systems Measurement PSM

Managing Projects with Practical Software & Systems Measurement PSM Managing Projects with Practical Software & Systems Measurement PSM Mauricio Aguiar PSM Qualified Instructor TI Métricas Ltda. Av. Rio Branco 181/1910 Rio de Janeiro, RJ Brazil 20040-007 www.metricas.com.br

More information

5/29/2015. Auditing IT Contracts From Afar. Disclaimer. Agenda

5/29/2015. Auditing IT Contracts From Afar. Disclaimer. Agenda Auditing IT Contracts From Afar Ensuring Compliance Michael Carr, JD, CISSP, CIPP Director, Enterprise IT Architecture & Chief Information Security Officer University of Kentucky June 2015 Disclaimer The

More information

CAFIS REPORT 2015.10

CAFIS REPORT 2015.10 CAFIS REPORT 2015.10 INDEX Message CAFIS Inbound 03-06 07-08 CAFIS Arch 09-10 CAFIS Brain 11-12 CAFIS Global 13-14 What We Do 15-16 About CAFIS 17-18 Services for Member Stores 19-34 Services for Card

More information

Detailed guidance for employers

Detailed guidance for employers April 2015 3 Detailed guidance for employers Appendix A: Pay reference periods This document accompanies: Detailed guidance no. 3 Assessing the workforce Pay reference period calendars where the definition

More information

Deep Security Intrusion Detection & Prevention (IDS/IPS) Coverage Statistics and Comparison

Deep Security Intrusion Detection & Prevention (IDS/IPS) Coverage Statistics and Comparison Deep Security Intrusion Detection & Prevention (IDS/IPS) Trend Micro, Incorporated A technical brief summarizing vulnerability coverage provided by Deep Security. The document also outlines a comparison

More information

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the

More information

DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE

DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Executive Summary The project will document campus requirements for IAM functionality and select and procure one or more technology

More information

Department of Public Welfare (DPW)

Department of Public Welfare (DPW) Department of Public Welfare (DPW) Office of Income Maintenance Electronic Benefits Transfer Card Risk Management Report Out-of-State Residency Review FISCAL YEAR 2012-2013 June 2013 (March, April and

More information

Financial Operating Procedure: Budget Monitoring

Financial Operating Procedure: Budget Monitoring Financial Operating Procedure: Budget Monitoring Original Created: Jan 2010 Last Updated: Jan 2010 1 Index 1 Scope of Procedure...3 2 Aim of Procedure...3 3 Roles & Responsibilities...3 Appendix A Timetable...7

More information

RIIO-T1 business plan submission London Tuesday 6 September 2011

RIIO-T1 business plan submission London Tuesday 6 September 2011 RIIO-T1 business plan submission London Tuesday 6 September 2011 Cautionary statement This presentation contains certain statements that are neither reported financial results nor other historical information.

More information

Retail Market IT Services Service Level Agreement

Retail Market IT Services Service Level Agreement Electric Reliability Council of Texas Retail Market IT Services Service Level Agreement Summary: Availability targets and related service information for the IT services provided by ERCOT that facilitate

More information

South Dakota Board of Regents. Web Time Entry. Student. Training Manual & User s Guide

South Dakota Board of Regents. Web Time Entry. Student. Training Manual & User s Guide South Dakota Board of Regents Web Time Entry Student Training Manual & User s Guide Web Time Entry Self Service Web Time Entry is a web-based time entry system designed to improve accuracy and eliminate

More information

Implementing Capacity Management within SIAM (Service Integration & Management) Amrit Bhattacharya

Implementing Capacity Management within SIAM (Service Integration & Management) Amrit Bhattacharya Implementing Capacity Management within SIAM (Service Integration & Management) Amrit Bhattacharya amrit.bhattacharya@accenture.com amrit_infi@yahoo.co.in https://no.linkedin.com/pub/amrit-bhattacharya/16/2a1/586

More information

Deep Security/Intrusion Defense Firewall - IDS/IPS Coverage Statistics and Comparison

Deep Security/Intrusion Defense Firewall - IDS/IPS Coverage Statistics and Comparison Deep Security/Intrusion Defense Firewall - IDS/IPS Trend Micro, Incorporated A technical brief summarizing vulnerability coverage provided by Deep Security and Intrusion Defense Firewall. The document

More information

Government proposals to reform vocational qualifications for 16-19 year olds in England

Government proposals to reform vocational qualifications for 16-19 year olds in England Government proposals to reform vocational qualifications for 16-19 year olds in England A consultation published by the Department for Education (DfE) on 7 th March 2013 What reforms does the consultation

More information

Annexure B: Planning, Budgeting and Performance Management Programme

Annexure B: Planning, Budgeting and Performance Management Programme Annexure B:, Budgeting Programme The following are key activities that need take place in more detail than Time frame Nature Period referred Start Finish 2012/09/01 /08/31 /or September /09/01 /09/26 August

More information

CABINET 9 th February 2006. Report of the Director of Partnerships and Customer Services

CABINET 9 th February 2006. Report of the Director of Partnerships and Customer Services CABINET 9 th February 2006 Report of the Director of Partnerships and Customer Services ITEM 11 CRM DEVELOPMENT Purpose of the Report To seek approval to the replacement for the Council s Customer Relationship

More information

Reverse Transfer on a National Scale: Why? How?

Reverse Transfer on a National Scale: Why? How? Reverse Transfer on a National Scale: Why? How? Registrars and Provosts Meeting Charleston, West Virginia March 11, 2015 3/17/2015 1 What is reverse transfer? 3/17/2015 2 It s a big issue 3/17/2015 3 How

More information

Homeland Security Grants Management Louisiana Emergency Preparedness Association (LEPA)

Homeland Security Grants Management Louisiana Emergency Preparedness Association (LEPA) Homeland Security Grants Management Louisiana Emergency Preparedness Association (LEPA) An LEM Basic Credentialing Course 1 Objectives Using local government management systems perform: Homeland security

More information

Manchester City Council Report for Information. Managing Attendance (Real Time Absence Reporting)

Manchester City Council Report for Information. Managing Attendance (Real Time Absence Reporting) Manchester City Council Report for Information Report to: Subject: Overview and Scrutiny Human Resources Subgroup - 25 January 2011 Managing Attendance (Real Time Absence Reporting) Report of: Assistant

More information

Managing Open Source Code Best Practices

Managing Open Source Code Best Practices Managing Open Source Code Best Practices September 24, 2008 Agenda Welcome and Introduction Eran Strod Open Source Best Practices Hal Hearst Questions & Answers Next Steps About Black Duck Software Accelerate

More information

The principles, processes, tools and techniques of project management

The principles, processes, tools and techniques of project management Unit 34: Plan and manage a project. 341 The principles, processes, tools and techniques of project management An industrial project, big or small, must be managed effectively to ensure the project s objectives

More information

1. Introduction. 2. User Instructions. 2.1 Set-up

1. Introduction. 2. User Instructions. 2.1 Set-up 1. Introduction The Lead Generation Plan & Budget Template allows the user to quickly generate a Lead Generation Plan and Budget. Up to 10 Lead Generation Categories, typically email, telemarketing, advertising,

More information

Resource Management Spreadsheet Capabilities. Stuart Dixon Resource Manager

Resource Management Spreadsheet Capabilities. Stuart Dixon Resource Manager Resource Management Spreadsheet Capabilities Stuart Dixon Resource Manager Purpose Single view of resource data Shows rolling demand vs supply for 14 months, 2 months back, current month, and 11 forward

More information

Roles: Scrum Master & Project Manager

Roles: Scrum Master & Project Manager Roles: Scrum Master & Project Manager Scrum Master: Facilitate collaborative meetings Track team performance Remove impediments (Risk, Issue) Validate team alignment to Agile framework and scope Drive

More information

Human Resources Management System Pay Entry Calendar

Human Resources Management System Pay Entry Calendar Human Resources Management System Pay Entry Calendar http://www1.umn.edu/ohr/payroll/calendars/index.html Important Information The system is unavailable for entry, due to maintenance, during the following

More information

UR Financials Project

UR Financials Project UR Financials Project Demo Days February 2015 Agenda UR Financials Project Update January Close Progress Reporting Enhancements Training Update Workday Releases Communications Saving Filters Demonstration

More information

Project Update December 2, 2008 2008 Innovation Grant Program

Project Update December 2, 2008 2008 Innovation Grant Program Tri-University Vulnerability Scanning/Management Solution Project Update December 2, 2008 2008 Innovation Grant Program 1 Project Summary This grant application is part of a previous project report presented

More information

Academic Calendars. Term I (20081) Term II (20082) Term III (20083) Weekend College. International Student Admission Deadlines

Academic Calendars. Term I (20081) Term II (20082) Term III (20083) Weekend College. International Student Admission Deadlines Academic Calendars Term I (20081) Term II (20082) Academic Calendars Term III (20083) Weekend College International Student Admission Deadlines Final Examination Schedule Broward Community College Catalog

More information

Choosing a Cell Phone Plan-Verizon

Choosing a Cell Phone Plan-Verizon Choosing a Cell Phone Plan-Verizon Investigating Linear Equations I n 2008, Verizon offered the following cell phone plans to consumers. (Source: www.verizon.com) Verizon: Nationwide Basic Monthly Anytime

More information

2013 2014 University-Wide Academic Calendar

2013 2014 University-Wide Academic Calendar 2013 2014 University-Wide Academic Calendar Guide to Abbreviations UGD = Undergraduate Day GS = Graduate Schools LAW = School of Law CPS = College of Professional Studies Aug 26 Monday LAW: Fall semester

More information

City & County of San Francisco Permit & Project Tracking System

City & County of San Francisco Permit & Project Tracking System City & County of San Francisco Permit & Project Tracking System PPTS Sneak Preview March 20, 2013 Welcome & Opening Statements AGENDA 1. Opening Statements Department Directors 2. Project Background 3.

More information

HOW POWER FITS INTO YOUR E-RATE PROJECT

HOW POWER FITS INTO YOUR E-RATE PROJECT HOW POWER FITS INTO YOUR E-RATE PROJECT A BACKGROUND ON E-RATE Remember the days when schools were filled with chalkboards, paper workbooks, hardbound encyclopedias and rotary phones? Today, the landscape

More information

Consumer ID Theft Total Costs

Consumer ID Theft Total Costs Billions Consumer and Business Identity Theft Statistics Business identity (ID) theft is a growing crime and is a growing concern for state filing offices. Similar to consumer ID theft, after initially

More information

GTA Board of Directors September 4, 2014

GTA Board of Directors September 4, 2014 GTA Board of Directors September 4, 2014 Our Strategic Vision Our Mission A transparent, integrated enterprise where technology decisions are made with the citizen in mind To provide technology leadership

More information

CQC Compliance Monitoring Framework

CQC Compliance Monitoring Framework At Care Group Level CQC Compliance Monitoring Framework 1. Utilising cascade training, Clinical Managers to ensure the staff within their Care Group are aware of the regulations, how to ensure compliance,

More information

One Newport s Performance Management Framework 2014/15

One Newport s Performance Management Framework 2014/15 One Newport s Performance Management Framework 2014/15 1) Introduction One Newport s Performance Management Framework (PMF) sets out One Newport s vision for how it plans to manage performance and delivery

More information

Pennsylvania Home And Community Based Services (HCBS) Waiver Settings Transition Plan

Pennsylvania Home And Community Based Services (HCBS) Waiver Settings Transition Plan Section 1: Identification - Pennsylvania will use its statewide transition plan as a way to determine its compliance with CMS s rule on HCBS. Pennsylvania will determine the current level of what state

More information

PROJECT: DLS Website Redesign STATUS REPORT May-June 2015

PROJECT: DLS Website Redesign STATUS REPORT May-June 2015 PROJECT: DLS Website Redesign STATUS REPORT May-June 2015 Key Project Roles Project Sponsor: Karen Johnson Executive Director, DLS Project Advisor: Vanessa Salway Program Manager: Project Manager: Steve

More information

2014 2015 University-Wide Academic Calendar

2014 2015 University-Wide Academic Calendar 2014 2015 University-Wide Academic Calendar Guide to Abbreviations UGD = Undergraduate Day GS = Graduate Schools LAW = School of Law CPS = College of Professional Studies Sunday Monday Tuesday Wednesday

More information

Employers Compliance with the Health Insurance Act Annual Report 2015

Employers Compliance with the Health Insurance Act Annual Report 2015 Employers Compliance with the Health Insurance Act Annual Report 2015 ea Health Council Health Council: Employers Compliance with the Health Insurance Act 1970 Annual Report 2015 Contact us: If you would

More information

Effective patient booking for NHSScotland. Best practice in the booking and management of patient appointments

Effective patient booking for NHSScotland. Best practice in the booking and management of patient appointments Effective patient booking for NHSScotland Best practice in the booking and management of patient appointments Crown copyright 2012 The Scottish Government St Andrew s House Edinburgh EH1 3DG Contents Background...

More information

Accident & Emergency Department Clinical Quality Indicators

Accident & Emergency Department Clinical Quality Indicators Overview This dashboard presents our performance in the new A&E clinical quality indicators. These 8 indicators will allow you to see the quality of care being delivered by our A&E department, and reflect

More information

GOVERNING BODY MEETING held in public 29 July 2015 Agenda Item 4.4

GOVERNING BODY MEETING held in public 29 July 2015 Agenda Item 4.4 GOVERNING BODY MEETING held in public 29 July 2015 Agenda Item 4.4 APPENDIX A Strategic Planning Process 2016/17 Strategic Planning Process 2016/17 Interlocking processes 5 Year strategic process: reviewed

More information

PROJECT: Online Shop STATUS REPORT September 2015

PROJECT: Online Shop STATUS REPORT September 2015 PROJECT: Online Shop STATUS REPORT September Key Project Roles Project Sponsor: Paul Dowler Project Director: Program Manager: Project Manager: Ryan Giltrap Solution Coordinator: Ivan Saric Business Analyst:

More information

Sage ERP MAS 90, 200, 200 SQL, and Sage ERP MAS 500. Supported Versions

Sage ERP MAS 90, 200, 200 SQL, and Sage ERP MAS 500. Supported Versions Sage ERP MAS 90, 200, 200 SQL, and Sage ERP MAS 500 Supported Versions Current Document: 2012... Page 1 Earlier Documents: 2011... Page 2 2010... Page 3 2009... Page 4 2008... Page 5 Sage ERP MAS 90, 200,

More information

2016 Examina on dates

2016 Examina on dates Please note the following informa on: The following exams are available throughout the year: Please click on the exam for which you wish to see the dates. When you have finished, you can select to return

More information

VA Medical Device Protection Program (MDPP)

VA Medical Device Protection Program (MDPP) VA Medical Device Protection Program (MDPP) Presented to National Institute for Standards and Technology (NIST) Health Security Conference May 11, 2011 Table of Contents Introduction MDPP Timeline and

More information

City of Minneapolis RCA Provision of IT Services. Committee of the Whole February 11, 2015

City of Minneapolis RCA Provision of IT Services. Committee of the Whole February 11, 2015 City of Minneapolis RCA Provision of IT Services Committee of the Whole February 11, 2015 Background IT Services contract with Unisys signed 12/2002 Unisys contract renegotiated in 2007 Reduced cost, added

More information

The Impact of Medicare Part D on the Percent Gross Margin Earned by Texas Independent Pharmacies for Dual Eligible Beneficiary Claims

The Impact of Medicare Part D on the Percent Gross Margin Earned by Texas Independent Pharmacies for Dual Eligible Beneficiary Claims The Impact of Medicare Part D on the Percent Gross Margin Earned by Texas Independent Pharmacies for Dual Eligible Beneficiary Claims Angela Winegar, M.S., Marvin Shepherd, Ph.D., Ken Lawson, Ph.D., and

More information

Start Your. Business Business Plan

Start Your. Business Business Plan Start Your Waste Recycling Business A TECHNICAL STEP-BY-STEP-GUIDE OF HOW TO START A COMMUNITY-BASED WASTE RECYCLING BUSINESS Start Your Waste Recycling Business Business Plan INTERNATIONAL LABOUR OFFICE

More information

2015 Examination dates

2015 Examination dates Please note the following information: The following exams are available throughout the year: BULATS Paper-based: Please click on the exam for which you wish to see the dates. When you have finished, you

More information

Infographics in the Classroom: Using Data Visualization to Engage in Scientific Practices

Infographics in the Classroom: Using Data Visualization to Engage in Scientific Practices Infographics in the Classroom: Using Data Visualization to Engage in Scientific Practices Activity 4: Graphing and Interpreting Data In Activity 4, the class will compare different ways to graph the exact

More information

Guidelines for Virtual Transportation Management Center Development. National Rural ITS Meeting August 27, 2014

Guidelines for Virtual Transportation Management Center Development. National Rural ITS Meeting August 27, 2014 Guidelines for Virtual Transportation Management Center Development National Rural ITS Meeting August 27, 2014 1 Project Purpose Overview To develop a guidebook that provides technical guidance on planning

More information

Change Management Advisory Council. September, 2010

Change Management Advisory Council. September, 2010 Change Management Advisory Council September, 2010 Agenda 8:00-8:20: 8:20-8:40: 8:40-9:00: 9:00-9:30: Introduce team; share role of Advisory Council and discussion questions Discuss program overview and

More information

HEALTH INSURANCE EXCHANGES: FEDERAL DEADLINES AND STATE DECISIONS

HEALTH INSURANCE EXCHANGES: FEDERAL DEADLINES AND STATE DECISIONS HEALTH INSURANCE EXCHANGES: FEDERAL DEADLINES AND STATE DECISIONS Annual Meeting: Council of State Governments West July 21, 2012 BOB CAREY RLCAREY CONSULTING AGENDA 1 The Basics: Health Insurance Exchanges

More information

PROJECTS SCHEDULING AND COST CONTROLS

PROJECTS SCHEDULING AND COST CONTROLS Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to

More information

Cost effective methods of test environment management. Prabhu Meruga Director - Solution Engineering 16 th July SCQAA Irvine, CA

Cost effective methods of test environment management. Prabhu Meruga Director - Solution Engineering 16 th July SCQAA Irvine, CA Cost effective methods of test environment management Prabhu Meruga Director - Solution Engineering 16 th July SCQAA Irvine, CA 2013 Agenda Basic complexity Dynamic needs for test environments Traditional

More information

OPERATIONS SERVICE UPDATE

OPERATIONS SERVICE UPDATE OPERATIONS SERVICE UPDATE EXECUTIVE SUMMARY Policy Processing At the June 24 Citizens Board of Governors meeting, Staff committed to achieving year end policy processing service goals by September 1, 24.

More information

FY 2015 Schedule at a Glance

FY 2015 Schedule at a Glance Coaching and Mentoring for Excellence Oct 21 23, 2014 $2,950 Residential Coaching and Mentoring for Excellence Apr 7 9, 2015 $2,400 Non-residential Coaching and Mentoring for Excellence May 27 29, 2015

More information

NHS BLOOD AND TRANSPLANT MARCH 2009 RESPONDING EFFECTIVELY TO BLOOD DONOR FEEDBACK

NHS BLOOD AND TRANSPLANT MARCH 2009 RESPONDING EFFECTIVELY TO BLOOD DONOR FEEDBACK 09/26 NHS BLOOD AND TRANSPLANT MARCH 2009 RESPONDING EFFECTIVELY TO BLOOD DONOR FEEDBACK EXECUTIVE SUMMARY From April 2009 an NHS wide common approach to complaint handling comes in to effect. This provides

More information

OPTIMIZING THE USE OF VHA s FEE BASIS CLAIMS SYSTEM (FBCS)

OPTIMIZING THE USE OF VHA s FEE BASIS CLAIMS SYSTEM (FBCS) VA-CASE VISN 11 VA Center for Applied Systems Engineering OPTIMIZING THE USE OF VHA s FEE BASIS CLAIMS SYSTEM (FBCS) The Fee Basis Claims System (FBCS) Optimization initiative aims to improve, standardize,

More information

Agenda and Materials Dec 11, 2012. ITS Executive Steering Committee (ITESC)

Agenda and Materials Dec 11, 2012. ITS Executive Steering Committee (ITESC) Agenda and Materials Dec 11, 2012 ITS Executive Steering Committee (ITESC) 1 2 Agenda Academic Technology Committee Update C. Scheidenhelm, B. Montes Sakai Migration Plans C. Scheidenhelm, B. Montes Disaster

More information

PowerSteering Product Roadmap Your Success Is Our Bottom Line

PowerSteering Product Roadmap Your Success Is Our Bottom Line Drive strategy. Accelerate results. cloud-based program & portfolio management software PowerSteering Product Roadmap Your Success Is Our Bottom Line Jay Hoskins Director of Product Management PowerSteering

More information

Duke Maestro Care and Clinical Research: 1 st Town Hall Meeting

Duke Maestro Care and Clinical Research: 1 st Town Hall Meeting 6// Duke Maestro Care and Clinical Research: st Town Hall Meeting Dean Nancy Andrews, MD, PhD Dr. Iain Sanderson, Chief Research and Academic Information Officer. Dr. Mark Stacy, Vice Dean for Clinical

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost

More information

A!Team!Cymru!EIS!Report:!Growing!Exploitation!of!Small! OfCice!Routers!Creating!Serious!Risks!

A!Team!Cymru!EIS!Report:!Growing!Exploitation!of!Small! OfCice!Routers!Creating!Serious!Risks! ATeamCymruEISReport:GrowingExploitationofSmall OfCiceRoutersCreatingSeriousRisks PoweredbyTeamCymru sthreatintelligencegroup Page 1of 14www.team-cymru.com www.team-cymru.com Threat'Intelligence'Group EXECUTIVE

More information

DHS BUDGET REQU~ST FOR FY 2015-2016

DHS BUDGET REQU~ST FOR FY 2015-2016 DHS BUDGET REQU~ST FOR FY 2015-2016 ($ Amounts in Thousands) Page # of Governor's Executive Budget: APPROPRIATION: Pp. C1.8, E30.5, E30.16, E30.17 Payment to Federal Govt. - Medicare Drug Progr~m l. SUMMARY

More information

Walton Centre. Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt. Monitoring & Audit

Walton Centre. Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt. Monitoring & Audit Page 1 Walton Centre Monitoring & Audit Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt Page 2 Table of Contents Section Contents 1 Introduction 2 Responsibilities Within This

More information

Council, 6 February 2014. IT Report. Executive summary and recommendations. Introduction

Council, 6 February 2014. IT Report. Executive summary and recommendations. Introduction Council, 6 February 2014 IT Report Executive summary and recommendations Introduction The report sets out the main activities of the IT Department since the last meeting of Council. It includes statistical

More information

Marsha Ingram, Head of Corporate Affairs

Marsha Ingram, Head of Corporate Affairs Date of Board meeting: 26 th November 2008 Subject: Annual Cycle of Board Business Trust Board lead: Marsha Ingram, Head of Corporate Affairs Presented by: Marsha Ingram, Head of Corporate Affairs Aim

More information

2015 2016 University-Wide Academic Calendar

2015 2016 University-Wide Academic Calendar 2015 2016 University-Wide Academic Calendar Guide to Abbreviations UGD = Undergraduate day GS = Graduate schools LAW = School of Law CPS = College of Professional Studies SEM = Semeter programs (undergraduate

More information

EMR UPDATE ON TIME AND ON BUDGET CLINICAL TRANSFORMATION IMPLEMENTATION PLAN

EMR UPDATE ON TIME AND ON BUDGET CLINICAL TRANSFORMATION IMPLEMENTATION PLAN EMR UPDATE ON TIME AND ON BUDGET CLINICAL TRANSFORMATION IMPLEMENTATION PLAN Testing and Build Stability View Only Scanning Interfaces Training Innovative Technology EMR UPDATE COMMUNICATION PLAN Essential

More information

MANAGEMENT INFORMATION REPORT Department for Business Innovations & Skills (BIS)

MANAGEMENT INFORMATION REPORT Department for Business Innovations & Skills (BIS) MANAGEMENT INFORMATION REPORT Department for Business Innovations & Skills (BIS) Version 3.2 9/1/215 Clyde & Co 4 th Floor, Collingwood House, 3 Collingwood Street, Newcastle, NE1 1JW T: 191 229 223 F:

More information

www.pwc.com/bigdecisions Are you prepared to make the decisions that matter most? Decision making in healthcare

www.pwc.com/bigdecisions Are you prepared to make the decisions that matter most? Decision making in healthcare www.pwc.com/bigdecisions Are you prepared to make the decisions that matter most? Decision making in healthcare Results from PwC s Global Data & Analytics Survey 2014 healthcare Patient data. Precision

More information