Cutter Soil Mixing Excavation and Shoring in Seattle s Pioneer Square District

Size: px
Start display at page:

Download "Cutter Soil Mixing Excavation and Shoring in Seattle s Pioneer Square District"

Transcription

1 Cutter Soil Mixing Excavation and Shoring in Seattle s Pioneer Square District Doug Lindquist 1, Ben Upsall 1, and Garry Horvitz 1 1 Hart Crowser, 1700 Westlake Avenue North, Suite 200, Seattle, WA 98109; ; Doug.Lindquist@hartcrowser.com, Ben.Upsall@hartcrowser.com, Garry.Horvitz@hartcrowser.com ABSTRACT In order to make a 13.1 m (43 ft) deep excavation, a 20.7 m (68 ft) Cutter Soil Mixing (CSM) groundwater cutoff shoring system was constructed in Seattle. The wall alignment was pre-trenched to remove obstructions and the wall was constructed using cement-bentonite slurry technology. The lower aquifer was depressurized to stabilize the base of the excavation while the upper aquifer was monitored closely for unexpected drawdown, which could result in unacceptable settlement of adjacent structures. Underpinning micropiles were installed below the perimeter footing of an adjacent 8-story building. The southern portion of the new building is supported on drilled shafts where the site s triangular shape made excavation less efficient. Permanent tie-downs were installed to resist hydrostatic uplift forces after the dewatering wells are shut off because the water pressure on the base of the foundation is greater than the building s weight. INTRODUCTION This paper presents a case history of the shoring system for the 505 First Avenue Building using Cutter Soil Mixing (CSM) technology in Seattle s historic Pioneer Square district. CSM is a relatively new technology developed in by combining the technology from two European firms, Soletanche Bachy and Bauer (Mathieu et al. 2006). This shoring system was selected for an excavation 13.1 m (43 ft) below the ground surface and 11 m (36 ft) below the groundwater table. Challenging subsurface conditions included very soft soil containing wood debris, abandoned timber piling, and numerous other obstructions. Also, a lower aquifer required depressurization to avoid blowout of the excavation base. There have been a number of excavations performed to depths greater than 25 m (82 ft) in downtown Seattle using soldier pile and tieback shoring methods with timber lagging, and numerous excavations performed to shallower depths using soil nail shoring methods. This project, however, is located south of downtown Seattle on a portion of reclaimed land where buildings are typically constructed with no more than one level below grade because of the high groundwater table. The site also had challenges: the new structure required anchoring to the subgrade soils to counteract hydrostatic uplift pressure on its foundation, an adjacent 8-story ER2010 Lindquist et al. Page 1 of 8

2 building required underpinning, new tiebacks had to be installed between and through the adjacent building s existing piles and the presence of a nearby pile supported onramp to the settlement-sensitive Alaskan Way Viaduct. A discussion of each challenge and its solution is addressed in this paper along with a description of the shoring system s performance. SITE AND SUBSURFACE CONDITIONS Site. The site is located in an area south of downtown Seattle that has been reclaimed from Elliott Bay as part of multiple historical regrading projects. The property was initially developed as a wharf on pilings for timber mill-related businesses. Fill material was deposited in the late 1880s and early 1890s and included sawdust from adjacent sawmills, wood planks and pilings, ship ballast, and burn debris from the Great Seattle Fire of Figure 1 shows the site s proximity to the historical shoreline and low tide. Figure 1. Vicinity Map Illustrating Historical Shoreline The project site is bounded to the south by the historic, 3-story Triangle Pub building and to the north by the 8-story 83 King Street building (Figure 2). Three structures were demolished prior to site development; two historic building facades were preserved. The historic west facade was removed and rebuilt in kind, while the east façade was stabilized and kept in place during construction. Soil. Subsurface conditions were based on 12 geotechnical borings extending into the bearing layer and two test pits performed within the fill. The soil conditions were generalized as 7.3 to 10.4 m (24 to 34 ft) of fill consisting of an upper crust of silty sand over wood debris, brick, silt and sand (upper aquifer) over marine silts and sands (historical beach deposits), over dense silts and silty sands (aquitard) over outwash sands (lower aquifer). Groundwater. Groundwater conditions were evaluated based on seven shallow wells and two deep wells. Prior to construction, the lower and upper aquifers had ER2010 Lindquist et al. Page 2 of 8

3 piezometric head depths averaging 1.3 m (4.2 ft) and 2.3 m (7.5 ft) below the ground surface, respectively (i.e., the lower aquifer was under pressure). Figure 2. Site Plan Illustrating Tieback Layout CSM SHORING SYSTEM AND CONTRACTOR SELECTION At the time of design, secant piles and ground freezing were the primary methods of shoring below the water table in Seattle. To coordinate details of the shoring system, underpinning, and dewatering these options were submitted to local shoring contractors to develop costs and select a shoring contractor early in the design process. The secant pile system was less costly than the soil freeze system; however, the estimates excluded the cost of delays for obstructions, which were known to exist. The contractor was selected for their alternate design-build approach consisting of cement-bentonite slurry pre-trenching and CSM cutoff wall (Parmantier and Giwosky 2009). This alternative was selected because the pre-trenching would remove the obstructions and potential delay costs. The CSM shoring system was considered superior to a secant pile wall system because of the reduced number of joints in CSM panels compared to overlapping secant piles (Brunner et al. 2006). The contractor performed cement-bentonite slurry pre-trenching with an excavator to a depth of 10.4 m (34 ft) to remove wood debris. The CSM shoring consisted of 108 overlapping panels 0.8 m thick by 2.8 m wide (2.6 ft by 9.2 ft) installed to a depth of 20.7 m (68 ft) around the 263 m (861 ft) site perimeter. While the cement/grout was still wet, soldier piles were placed through the panels on 1.7 m (5.4 ft) centers to a ER2010 Lindquist et al. Page 3 of 8

4 depth of 18.3 m (60 ft). During excavation, the panels were chipped away to expose the soldier piles and tiebacks were installed through sockets within the soldier piles. The overlapping CSM panels created a virtually water-tight shoring system. DESIGN AND CONSTRUCTION CHALLENGES Some of the design and construction challenges on this project are described here. Design Earth Pressures. The challenging subsurface conditions described previously led to the unique pre-trenching and CSM shoring. The design earth pressure diagram used to develop the tieback layout for the CSM shoring system is shown in Figure 3 along with a schematic of the soil profile. Figure 3. Design Earth Pressure Diagram and Soil Profile Dewatering and Cutoff Wall. The project required the excavation to extend 11 m (36 ft) below the static water table with limited drawdown allowed in the upper aquifer. The designers estimated that a drawdown of the lower aquifer of approximately 12.5 m (41 ft) would be required to avoid blowing out the base of the excavation and that a maximum drawdown of 1.5 m (5 ft) of the upper aquifer would be acceptable to avoid settlement of adjacent structures. Recharging the upper aquifer from the dewatering wells was considered in case the low permeability aquitard was found to be discontinuous during construction dewatering. ER2010 Lindquist et al. Page 4 of 8

5 Excavated soils had to be dewatered to facilitate transport off site. Six shallow interior wells were installed in the upper aquifer to dewater the excavated soils and two deep dewatering wells were installed outside of the site to depressurize the deep aquifer (Figure 2). One deep well was located interior to the site but was decommissioned early in construction because it was obstructing the excavation. Dewatering monitoring results are described in the Construction Monitoring section. Hydrostatic Uplift Pressure. Upon recharge of the lower aquifer, the building, which was designed to be essentially water-tight, has an unbalanced hydrostatic uplift force in excess of the building weight acting on the foundation. This required the installation of 360 tiedown micropiles to hold the building in place. Adjacent Structures. The adjacent 8-story 83 King Street building required micropile underpinning of its perimeter footing to replace existing pile support that encroached on the subject property. Piles located below the 83 King Street building and the Alaskan Way Viaduct on-ramp required accurate installation of tiebacks around existing timber foundations (Figure 2). The nearby on-ramp required tiebacks as long as 41 m (135 ft) to limit changes in soil stress near those piles. CONSTRUCTION MONITORING Construction monitoring is critical to verify that below ground construction and conditions conform to the design assumptions and that the performance is as anticipated. Site monitoring included measurement of site movement (i.e., inclinometers and optical surveys) and groundwater levels within the two aquifers. Quality assurance and quality control of the CSM wall included visual inspection of the panels during excavation as well as strength testing of the CSM soil-cement mix. Inclinometers. Three inclinometers were used to measure the lateral displacement of the CSM shoring system. The inclinometers were installed on three soldier piles at the locations shown on Figure 2. Deflection readings are shown on Figure 4, with positive deflection indicating movement into the excavation. The results indicate initial movements into the excavation followed by movements back into the soil after the top row of tiebacks were stressed. Upon further excavation, the movement went back toward the excavation. In general, these lateral movements were less than 25 mm (1 in) in either direction and were considered acceptable. Optical Monitoring. The optical monitoring plan consisted of over 200 survey points located near the top of every other soldier pile, on the buildings adjacent to the site, on the sidewalk next to the excavation, in the street, and on the adjacent Alaskan Way Viaduct on-ramp columns. The largest recorded lateral movement was approximately 4 cm (1.5 in) of movement into the soil on a pile located on the west side of the excavation. When lateral deflections of greater than about 25 mm (1 in) into the excavation were observed for any given monitoring point, the project team discussed the exceedance, visually inspected the shoring and adjacent CSM panels, and continued to monitor those deflections very closely. Deflections larger than about 50 mm (2 in) or visual signs of CSM panel or shoring system distress would ER2010 Lindquist et al. Page 5 of 8

6 likely have called for a more thorough review accompanied by corrective actions such as installation of whaler beams with additional tiebacks. There was negligible movement of many points including those on the pile-supported Alaskan Way Viaduct on-ramp columns. 0 2 Deflection (mm) Deflection (mm) Deflection (mm) Depth (m) Depth (ft) Pile E35 Pile W10 Pile W Deflection (in) Deflection (in) Deflection (in) Figure 4. Inclinometer Results Visual Inspection of CSM Panels. During excavation the condition of the CSM wall was observed visually and probed with a 13 mm (0.5 in) diameter T-probe to identify cracks, seeps, and voids or pockets of weaker-strength materials. Tieback pockets, seeps and cracks were generally filled with expanding epoxy material. The largest voids and pockets of weaker-strength material were encapsulated with a steel plate spanning between adjacent soldier piles and then backfilled. In general, the CSM wall had increased quality and consistency with depth. CSM Strength Testing. The design called for 1.4 MPa (200 psi) 28-day compressive strength of the CSM panels. Wet samples were collected from the panels following installation for laboratory testing. Approximately 95 percent of the samples exceeded the design strength. Low strength test results required one of the CSM panels to have additional grouting on the outside of the wall to improve performance in that area. Groundwater Monitoring. Groundwater monitoring was performed beginning 8 months prior to the start of depressurization of the deep aquifer, which began in February 2008, until the dewatering system was shut off in September 2009 following construction of the building to its full height and placement of exterior brick cladding. Monitoring was observed using two deep wells within the lower aquifer and seven shallow wells within the upper aquifer. Steady state pumping of 75 lpm (20 gpm) at the site resulted in a depressurization of approximately 16 m (52 ft) of water in the lower aquifer while the upper aquifer showed only 0.3 to 0.7 m (1 to 2 ft) of variation in the 7 monitoring wells, which was well within the criteria of 1.5 m (5 ft) established during design to minimize impacts to adjacent structures and ER2010 Lindquist et al. Page 6 of 8

7 utilities. Figure 5 illustrates the monitoring well data including the depressurization and recharge of the deep aquifer Groundwater Depth (Meters) Shallow Aquifer (7 wells) Deep Aquifer (2 wells) Localized Shallow Dewatering for Vault Installation Groundwater Depth (Feet) Jun-07 Aug-07 Oct-07 Dec-07 Feb-08 Apr-08 Jun-08 Aug-08 Oct-08 Dec-08 Jan-09 Mar-09 May-09 Jul-09 Sep-09 Date Figure 5. Dewatering Performance as Illustrated by Monitoring Wells DISCUSSION ON LATERAL SHORING MOVEMENTS The largest lateral movement of the shoring system was into the soil, which is not common. This is attributable to the shoring designer using total anchor design loads approximately 25 percent higher than would be inferred from the design earth pressure diagram to control intermediate stages of construction with only three tieback rows (Parmantier et al. 2009). Portions of the fill (e.g., the wood debris) also likely had a lower earth pressure than assumed in design. SHORING CONSTRUCTION COSTS The project consisted of approximately 11,300 m 2 (37,000 ft 2 ) of exposed shoring wall. The shoring contractor s design and construction costs (e.g., CSM design and installation, soldier piles, tiebacks, dewatering, micropile underpinning of north wall, facade support, etc.) were approximately $8.5 million, or $750/m 2 ($230/ft 2 ). These were the contractor s costs and do not include the owner s design team, who were the designers of record with the city and provided design and construction support. CONCLUSIONS This paper presents a case history of the successful use of CSM technology to perform a 13.1 m (43 ft) deep excavation in an area with a high water table and ER2010 Lindquist et al. Page 7 of 8

8 challenging subsurface conditions. It also demonstrates the value of retaining a specialty shoring contractor early in the design process for a unique excavation solution. The contractor-proposed pre-trenching and CSM shoring performed well and reduced risk for obstruction-related delays compared to secant pile shoring methods used in Seattle in these difficult soils. Figure 6 is a picture of the project site near the end of excavation including the temporarily supported historic east facade. Figure 6. Photo Looking North Following Final Tieback Row Installation REFERENCES Brunner, W.G., Fiorotto, R., Stötzer, E., and Schöpf, M. (2006). The Innovative CSM-Cutter Soil Mixing for Constructing Retaining and Cut-Off Walls. GeoCongress Geotechnical Engineering in the Information Technology Age, ASCE. Mathieu, F, Borel, S., and Lefebvre, L. (2006). CSM: An Innovative Solution for Mixed-In-Situ Retaining Walls, Cut-Off Walls and Soil Improvement. 10th International Conference on Piling and Deep Foundations, DFI/EFFC. Parmantier, D. and Giwosky, D. (2009). Cutter Soil Mixing Comes to Seattle. Foundation Drilling, ADSC, February 2009, Parmantier, D.M., Stow, R.F.P., and Byrne, R.J. (2009). Case Study: Cement- Bentonite Pre-Trenching and Cutter Soil Mixing (CSM) for Temporary Shoring and Groundwater Cutoff. Contemporary Topics in Ground Modification, Problem Soils, and Geo-Support, ASCE, GSP 187, ER2010 Lindquist et al. Page 8 of 8

SECTION 02200 SUPPORT OF EXCAVATION

SECTION 02200 SUPPORT OF EXCAVATION SECTION 02200 PART 1 GENERAL 1.01 DESCRIPTION A. Section including specifications for design and installation of excavation support. B. Section also includes specifications for excavation support systems

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

SECTION 02401 SHEETING, SHORING AND BRACING

SECTION 02401 SHEETING, SHORING AND BRACING SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State

More information

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76. Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA

DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76. Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76 Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA The Block 76 project includes the demolition and redevelopment of an entire city

More information

BUTE Department of Construction Management and Technology

BUTE Department of Construction Management and Technology BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):

More information

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for

More information

MILWAUKEE CITY HALL FOUNDATION RESTORATION. Project Update November 12, 2014

MILWAUKEE CITY HALL FOUNDATION RESTORATION. Project Update November 12, 2014 MILWAUKEE CITY HALL FOUNDATION RESTORATION Project Update November 12, 2014 Milwaukee City Hall Building History/Fast Facts - City Hall is a masonry and iron superstructure - Originally constructed from

More information

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet

More information

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Eric M. Klein, P. E., Rummel, Klepper & Kahl, LLP, Baltimore, Maryland Kenneth B. Andromalos, P. E., Brayman Environmental,

More information

The International Workshop on Micropiles, 2007

The International Workshop on Micropiles, 2007 MICROPILE FOUNDATION REPAIR AND UNDERPINNING, ARTS AND SCIENCE MUSEUM, UNIVERSITY OF PUERTO RICO, MAYAGUEZ Presented at: International Society of Micropiles (ISM) The International Workshop on Micropiles,

More information

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge. TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may

More information

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE ENGINEERED FOUNDATIONS Department of Public Works Jeff Hill, PE What is an engineered foundation. A Foundation Design Developed by a Trained Professional (Engineer) Types of Foundations (All of which can

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

4.11 Geologic and Soil Resources

4.11 Geologic and Soil Resources 4.11 Geologic and Soil Resources Geology and soils are evaluated as part of an environmental document because conditions in the project area can influence the type and size of a project s structure, the

More information

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation

More information

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362 California Department of Transportation Doyle Drive Test Program Deep Soil Mixing (DSM) /Cutter Soil Mixing (CSM) Testing Report By Malcolm Drilling Company, Inc. 3524 Breakwater Ave., Suite 108 Hayward,

More information

Elevating Your House. Introduction CHAPTER 5

Elevating Your House. Introduction CHAPTER 5 CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

Designed and Engineered to Perform

Designed and Engineered to Perform History EARTH CONTACT PRODUCTS, L.L.C., is a family owned company, based in Olathe, Kansas. This company was built upon Don May s U.S. Patented fourth-generation Steel Piering System that has led to the

More information

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP) SPECIFICATIONS INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP) Part 1 General 1.1 CONFORMITY Conforms to the requirements of the general conditions of the contract.

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline

More information

GOWANUS EXPRESSWAY TUNNEL PRIMER

GOWANUS EXPRESSWAY TUNNEL PRIMER GOWANUS EXPRESSWAY TUNNEL PRIMER T he New York State Department of Transportation is currently studying the replacement of the Gowanus Expressway with a tunnel. This investigation involves looking at a

More information

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe. SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price

More information

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective FHWA NATIONAL GEOTECHNICAL PROGRAM www.fhwa.dot.gov/engineering/geotech Why Geotechnical Instrumentation? Provide warning

More information

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch USE OF MICROPILES IN TEXAS BRIDGES by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch DEFINITION OF A MICROPILE A micropile is a small diameter (typically less than 12 in.), drilled and

More information

CIVL451. Soil Exploration and Characterization

CIVL451. Soil Exploration and Characterization CIVL451 Soil Exploration and Characterization 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally

More information

Anirudhan I.V. Geotechnical Solutions, Chennai

Anirudhan I.V. Geotechnical Solutions, Chennai Anirudhan I.V. Geotechnical Solutions, Chennai Often inadequate In some cases, excess In some cases, disoriented Bad investigation Once in a while good ones Depends on one type of investigation, often

More information

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located

More information

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Stephen W. Lacz 1, M. ASCE, P.E. and Richard C. Wells 2, F. ASCE, P.E. 1 Senior Professional, Trigon Kleinfelder, Inc., 313 Gallimore

More information

EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL

EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL EXAMPLE DESIGN OF CANTILEVERED WALL, GRANULAR SOIL A sheet pile wall is required to support a 2 excavation. The soil is uniform as shown in the figure. To take into account the friction between the wall

More information

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples FOUNDATION DESIGN Proportioning elements for: Transfer of seismic forces Strength and stiffness Shallow and deep foundations Elastic and plastic analysis Foundation Design 14-1 Load Path and Transfer to

More information

Severn Trent Water Ltd has undergone a massive investment programme in the River Tame catchment over the

Severn Trent Water Ltd has undergone a massive investment programme in the River Tame catchment over the Tame Urban Pollution Management Foxton Road & Sir Johns Road CSOs - collaborative working to deliver innovative solutions Severn Trent Water Ltd has undergone a massive investment programme in the River

More information

Building Condition Assessment: 109-111 North Howard Street Baltimore, Maryland

Building Condition Assessment: 109-111 North Howard Street Baltimore, Maryland KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013 How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table

More information

Construction sites are dewatered for the following purposes:

Construction sites are dewatered for the following purposes: 9. DEWATERING CONTROL OF GROUNDWATER Construction of buildings, powerhouses, dams, locks and many other structures requires excavation below the water table into water-bearing soils. Such excavations require

More information

How To Design A Foundation

How To Design A Foundation The Islamic university - Gaza Faculty of Engineering Civil Engineering Department CHAPTER (2) SITE INVESTIGATION Instructor : Dr. Jehad Hamad Definition The process of determining the layers of natural

More information

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete Tremie Concrete Underwater concrete plays an important role in the construction of offshore structures. It may be used to tie together various elements in composite action (i.e., to tie piling to the footing).

More information

load on the soil. For this article s examples, load bearing values given by the following table will be assumed.

load on the soil. For this article s examples, load bearing values given by the following table will be assumed. How Many Piers? By Gary Collins, P.E. A clear-cut guide to helical pier spacing Introduction Helical pier spacing is not an exact science. How many does it take to support a structure adequately or repair

More information

Deep Underground Basements for Major Urban Building Construction

Deep Underground Basements for Major Urban Building Construction Nicholson Construction Company 12 McClane Street Cuddy, PA 15031 Telephone: 412-221-4500 Facsimile: 412-221-3127 Deep Underground Basements for Major Urban Building Construction by Seth Pearlman, P.E.

More information

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of

More information

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER Professional Experience: Pride and Passion in the Art of Structural Engineering since 1979. Professional Registration: Professional

More information

Residential Deck Safety, Construction, and Repair

Residential Deck Safety, Construction, and Repair Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the

More information

Emergency repair of Bridge B421

Emergency repair of Bridge B421 Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)

More information

System. Stability. Security. Integrity. 150 Helical Anchor

System. Stability. Security. Integrity. 150 Helical Anchor Model 150 HELICAL ANCHOR System PN #MBHAT Stability. Security. Integrity. 150 Helical Anchor System About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair

More information

Geotechnical Building Works (GBW) Submission Requirements

Geotechnical Building Works (GBW) Submission Requirements Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.

More information

COST AND PERFORMANCE REPORT

COST AND PERFORMANCE REPORT COST AND PERFORMANCE REPORT Pump and Treat of Contaminated Groundwater at the United Chrome Superfund Site Corvallis, Oregon September 1998 Prepared by: SITE INFORMATION Identifying Information: United

More information

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering

More information

Design and Construction of Auger Cast Piles

Design and Construction of Auger Cast Piles Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com CONTENTS 1.

More information

Page & Turnbull imagining change in historic environments through design, research, and technology

Page & Turnbull imagining change in historic environments through design, research, and technology DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED

More information

Section 02415. Installation of pipe and casing for sanitary sewer by methods of augering.

Section 02415. Installation of pipe and casing for sanitary sewer by methods of augering. ITY OF PRLN UGRING PIP OR SING FOR SWRS Section 02415 UGRING PIP OR SING FOR SWRS 1.0 G N R L 1.01 STION INLUS Installation of pipe and casing for sanitary sewer by methods of augering. References to Technical

More information

Property Inspection. 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT

Property Inspection. 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT Property Inspection 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT March 2013 This document has been prepared for the benefit of Clint Marston. No liability is accepted by this company

More information

Construction Dewatering and Ground Freezing

Construction Dewatering and Ground Freezing UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Temporary Structures Construction Dewatering and Ground Freezing

More information

DIVISION 4300 STORM DRAINAGE

DIVISION 4300 STORM DRAINAGE DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES

More information

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain Effect on structures Uniform settlement - no concerns Angular distortion - causes damage due to tensile strain 1/500 - safe limit for no cracking of buildings 1/150 - potential structural damage 36 37

More information

Baton Rouge Foundation Repair

Baton Rouge Foundation Repair Baton Rouge Foundation Repair 13822 Florida Blvd Bldg 3 Baton Rouge, LA 70819 Baton Rouge Foundation Repair offers services to correct the settlement of both Slab foundations and Pier & Beam foundations

More information

UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA

UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA John R. Wolosick, P.E.,D.GE 1, Michael W. Terry, P.E. 2, W. David Kirschner 3 and Robert F. Scott Jr. P.E. 4 SYNOPSIS In

More information

Residential Foundations and Basements

Residential Foundations and Basements Residential Foundations and Basements Disclaimer All of the following information is based on the 2006 International Residential Code with Kentucky Amendments. As some information is paraphrased, article

More information

STATUS REPORT FOR THE SUBMERGED REEF BALL TM ARTIFICIAL REEF SUBMERGED BREAKWATER BEACH STABILIZATION PROJECT FOR THE GRAND CAYMAN MARRIOTT HOTEL

STATUS REPORT FOR THE SUBMERGED REEF BALL TM ARTIFICIAL REEF SUBMERGED BREAKWATER BEACH STABILIZATION PROJECT FOR THE GRAND CAYMAN MARRIOTT HOTEL STATUS REPORT FOR THE SUBMERGED REEF BALL TM ARTIFICIAL REEF SUBMERGED BREAKWATER BEACH STABILIZATION PROJECT FOR THE GRAND CAYMAN MARRIOTT HOTEL performed by Lee E. Harris, Ph.D., P.E. Consulting Coastal

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

SNC-Lavalin Inc. Montcalm Wastewater Pumping Station Upgrades - Geotechnical Report. October 2011

SNC-Lavalin Inc. Montcalm Wastewater Pumping Station Upgrades - Geotechnical Report. October 2011 SNC-Lavalin Inc. Montcalm Wastewater Pumping Station Upgrades - Geotechnical Report October 2011 SNC-Lavalin Inc Montcalm Wastewater Pumping Station Upgrades - Geotechnical Report Table of Contents 1.0

More information

4.3.5 - Breakaway Walls

4.3.5 - Breakaway Walls 4.3.5 - Breakaway Walls Elevation of a structure on a properly designed foundation reduces the potential for water damage from flooding. When the space below the lowest elevated floor is maintained free

More information

CHAPTER 4 WELL COMPLETION AND MAINTENANCE

CHAPTER 4 WELL COMPLETION AND MAINTENANCE CHAPTER 4 WELL COMPLETION AND MAINTENANCE Section 1: Disinfection. (a) Each person who repairs, modifies, works on, or otherwise affects the physical components of a well shall clean and disinfect the

More information

Guidelines For Sealing Groundwater Wells

Guidelines For Sealing Groundwater Wells Guidelines For Sealing Groundwater Wells Government of Newfoundland and Labrador Department of Environment and Conservation Water Resources Management Division Government of Newfoundland and Labrador Department

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting

Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting MnDOT Contract No. 1003249 General Project Overview This work is located along Trunk Highway (TH) 23, for State Project (SP) 7305-124.

More information

Lighthouse Engineering, L.L.C.

Lighthouse Engineering, L.L.C. Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: Office@LighthouseEng.com Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering

More information

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries Introduction Wastewater of petrochemical industries and refineries contains high amounts of emulsified aliphatic or

More information

RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS

RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS Johnson County Building Officials Association January 2008 Residential Foundation Guideline Foundation designs for one-and two-family dwellings may use

More information

School Construction Authority Architecture & Engineering

School Construction Authority Architecture & Engineering SCOPING GUIDELINES 1.0 GENERAL GUIDELINES 2.0 BUILDING ENVELOPE SCOPING GUIDELINES 3.0 CATEGORIES AND COMPONENTS: The Flood Elimination/Below Grade Capital Category may include some or all of the following

More information

Strength Determination of "Tooth-Paste" Like Sand and Gravel Washing Fines Using DMT

Strength Determination of Tooth-Paste Like Sand and Gravel Washing Fines Using DMT Strength Determination of "Tooth-Paste" Like Sand and Gravel Washing Fines Using DMT David L. Knott, P.E. and James M. Sheahan, P.E. HDR Engineering, Inc. 3 Gateway Center Pittsburgh, PA 15222-1074 Phone:

More information

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and

More information

GEOTECHNICAL INVESTIGATION CITY OF HOUSTON SURFACE WATER TRANSMISSION PROGRAM CONTRACT 74A-1 WATERLINE COH WBS NO. S-000900-0109-3 HOUSTON, TEXAS

GEOTECHNICAL INVESTIGATION CITY OF HOUSTON SURFACE WATER TRANSMISSION PROGRAM CONTRACT 74A-1 WATERLINE COH WBS NO. S-000900-0109-3 HOUSTON, TEXAS GEOTECHNICAL INVESTIGATION CITY OF HOUSTON SURFACE WATER TRANSMISSION PROGRAM CONTRACT 74A-1 WATERLINE COH WBS NO. S-000900-0109-3 HOUSTON, TEXAS Reported To: LAN, Inc. Houston, Texas by Aviles Engineering

More information

Underpinning Systems 14.1 FOUNDATION REPAIR. Helical Piles

Underpinning Systems 14.1 FOUNDATION REPAIR. Helical Piles Helical Piles Howard A. Perko Copyright 0 2009 by John Wiley & Sons, Inc. All rights reserved. C h a p t e r 14 Underpinning Systems There has been tremendous growth in the use of helical piles for underpinning

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

SECTION 411 DRILLED PIERS

SECTION 411 DRILLED PIERS Section Payment will be made under: Pay Item Foundation Excavation Foundation Excavation for Bent No. at Station Foundation Excavation for End Bent No. at Station Pay Unit Cubic Yard Lump Sum Lump Sum

More information

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN. A Solid Foundation Solution for Homeowners from Our products are made with 90% Recycled Material Down. Right. Solid. GREEN. Stop the damaging effects of foundation settling... Sinking foundations, cracked

More information

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

Comprehensive Design Example 2: Foundations for Bulk Storage Facility Comprehensive Design Example 2: Foundations for Bulk Storage Facility Problem The project consists of building several dry product storage silos near an existing rail siding in an open field presently

More information

Foundation design to Eurocode 7

Foundation design to Eurocode 7 Foundation design to Eurocode 7 Dr Andrew Bond (Geocentrix) Outline of talk Overview of Eurocode 7 New principles for geotechnical design Impact on retaining wall design Impact on pile design Benefits

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

6 RETROFITTING POST & PIER HOUSES

6 RETROFITTING POST & PIER HOUSES Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This

More information

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED

More information

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057. Lecturer: Jim Cahill

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057. Lecturer: Jim Cahill ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057 Lecturer: Jim Cahill 29 th November 2011 TABLE OF CONTENTS SUMMARY 1 MAIN BODY SECTION

More information

How to Design and Build a Fence/G traverse Bridge or Graffiti Project

How to Design and Build a Fence/G traverse Bridge or Graffiti Project Outline Project Location Project Description Project History Site Constraints Geotechnical Investigation & Soil Profile Foundation Design Process Photos Project Location Project Limits: The Grand River

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing 1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize

More information

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code LEGACY REPORT Reissued November 1, 2003 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900

More information

STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200 STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES PART 1 - GENERAL A. Description This section includes materials, testing, and installation of precast concrete

More information

DESIGNING STRUCTURES IN EXPANSIVE CLAY

DESIGNING STRUCTURES IN EXPANSIVE CLAY DESIGNING STRUCTURES IN EXPANSIVE CLAY A GUIDE FOR A RCHITECTS AND E NGINEERS Table of Contents 1. Introduction Page 1 2. Common Foundation Systems Page 2 3. Drilled Piers Page 3 a. Skin Friction Piers

More information

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage 3.3. Evaluation of Building Foundation Damage Basic Terminology: Damage: Destruction, deformation, inclination and settlement of a building foundation caused by an earthquake. Damage grade: Degree of danger

More information

COMMONLY USED RESIDENTIAL BUILDING CODES

COMMONLY USED RESIDENTIAL BUILDING CODES COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section

More information

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling

More information

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 Appendix B CONTENTS STATIC (TIEBACKS)... B-3 STATIC AXIAL (COMPRESSION/TENSION)... B-6 STATIC (LATERAL)... B-9 CAPACITY VERIFICATION

More information

Technical Assignment 2 TABLE OF CONTENTS

Technical Assignment 2 TABLE OF CONTENTS 2 TABLE OF CONTENTS Executive Summary...3 Introduction..5 Gravity Loads......6 Design Codes......7 Materials..8 Existing Structural System.. 10 Existing Floor System 15 Alternate Floor Framing Systems...17

More information

Proposed Minimum Subterranean Termite Treatment Standards

Proposed Minimum Subterranean Termite Treatment Standards Proposed Minimum Subterranean Termite Treatment Standards Introduction This document is intended to serve as a model for states considering the adoption of standards for soil application of termiticides.

More information

The Stabilizer TM. Benefits. www.griptite.com. Supplemental support system for sagging beams and floor joists within a crawl space

The Stabilizer TM. Benefits. www.griptite.com. Supplemental support system for sagging beams and floor joists within a crawl space The Stabilizer TM Supplemental support system for sagging beams and floor joists within a crawl space Pre-drilled holes in steel plate allow for connection to beam or floor joists. Benefits Levels and

More information