UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA

Size: px
Start display at page:

Download "UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA"

Transcription

1 UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA John R. Wolosick, P.E.,D.GE 1, Michael W. Terry, P.E. 2, W. David Kirschner 3 and Robert F. Scott Jr. P.E. 4 SYNOPSIS In late 2011, the general contractor was erecting a U-shaped building for a planned 10 storey new student housing building in North Carolina USA using tunnelform concrete construction methods. In September, the general contractor had reached the 8 th level of the East Wing of the structure and had completed foundations and begun placing slabs-on-grade for the West Wing. When settlement of more than 100 mm (4 inches) was observed in the East tower, concrete construction was halted. Micropiles were chosen to stabilize the rapidly settling foundation. Low-headroom installation was required for the East Wing while open headroom conditions were available at the West Wing. Due to a schedule requirement of opening the student housing in August 2012, a very rapid construction schedule for the underpinning was required. Health and safety issues were of paramount concern due to the intense schedule, heavy resource load, and a requirement to work adjacent to interior and utility trade contractors. Approximately 1,035 micropiles, drilled to bedrock, were installed in a 10 week schedule using up to 8 drill rigs and 2 work shifts without a safety incident. An artist s rendition of the proposed building is shown on Figure 1. Figure 1. Artist s rendition of student housing building 1 Director of Engineering, Hayward Baker Inc., 515 Nine North Court, Alpharetta, GA, 30004,USA , jrwolosick@haywardbaker.com 2 Senior Vice President, Hayward Baker Inc., 515 Nine North Court, Alpharetta, GA, 30004,USA , mwterry@haywardbaker.com 3 Area Manager - Carolinas, Hayward Baker Inc., 208 Little Santee Road, Colfax, NC, 27235,USA , wdkirschner@haywardbaker.com 4 Senior Engineer, Hayward Baker Inc., 4979 Lebanon Pike, Old Hickory, TN, 37138,USA , rscott@haywardbaker.com 1

2 PROJECT BACKGROUND In September, 2011, Hayward Baker was requested to make a site visit to discuss possible remedial deep foundation techniques to address the differential settlements observed at the site. During the walk through, the general contractor stated that they had not noticed the settlement until a thunderstorm had flooded the first floor. Ponded water was observed on the slabs up to 100 mm (4 inches) deep at the midpoint of the East Wing (near points 5 and 6 shown on Figure 3). The tunnel-formed construction used for the structure seemed to accommodate the settlements and showed little to no cracking at the time. A settlement survey was performed and measured 25 to 50 mm (1 to 2 inches) at each end of the East Wing and 100 mm (4 inches) at the midpoint of the East Wing. However, the survey was repeated on a regular basis and showed a rapid rate of settlement. A system of micropile underpinning was selected for the foundation repair and the load test program began immediately while the underpinning plans were prepared by the structural engineer. GEOLOGIC SETTING The project is located in the Piedmont physiographic province. The Piedmont is characterized by residual soils weathered from parent bedrock. The parent rocks are typically gneisses and schists with some granitic intrusions. The rocks typically lie in northeast trending belts and have a thick residual soil cover known as saprolite. The residual soils have formed as the result of chemical weathering of the parent rock. The degree of weathering varies based on mineral composition and the degree of natural fracturing and jointing. Therefore the soils are typically highly variable in density and consistency and often contain areas of partially weathered rock (PWR) at variable depths and thickness. The predominant soil type is either a sandy silt or silty sand, typically containing mica, with some clay fraction closer to the ground surface. GEOTECHNICAL INVESTIGATION Fourteen borings were drilled to initially investigate the subsurface conditions in An additional fourteen borings were also drilled during the remedial work at the site. The remedial borings showed similar conditions to the initial investigation. The groundwater table was at a depth of about 3.6 m (12 feet). The original geotechnical report identified a deeply weathered and soft soil profile over much of the site. Depth to PWR averaged about 65 feet but was measured as deep as 90 feet. Up to 11 feet of PWR was encountered by the borings. See Figure 2 for a boring log (Boring T-12) from the initial investigation near the center of the site. 2

3 ORIGINAL FOUNDATION CONSTRUCTION The original geotechnical report, recognizing potential excessive settlement of shallow foundations, recommended driven 305 mm (12 inch) square concrete piles (citing high steel prices in 2007) or auger-cast piles. Aggregate piers were recommended by the geotechnical engineering report only for the adjacent 7 storey parking garage. For construction, however, aggregate pier foundations were selected for both structures, the student housing structure and the parking garage. The authors are not aware of any foundation issues at the parking garage. However, after the installation of the aggregate piers, the student housing building suffered significant settlements during construction, prior to completion of the building. When the settlements exceeded 114 mm (4 ½ inches), concrete construction was halted and a remedial design for micropiles was initiated. Figure 2. Boring T-12 from the center of the site 3

4 STUDENT HOUSING BUILDING DETAILS The site for the student housing building was gently sloping and required cuts of about 1.8 m (6 feet) and fills of about 3.6 m (12 feet). The structure was U-shaped as shown on Figure 5. The building occupied approximately one square city block. Tunnel-form construction, which allows the casting of the reinforced concrete walls and slabs simultaneously, was used. Only wall footings were utilized, with no individual column footings due to this design. The concrete tunnel-form frame for the East Wing of the structure had been completed to the 8 th level out of the planned 11 storeys before concrete construction was halted due to the observed settlements. An extensive settlement monitoring program was set up for the structure in early September, 2011, after significant settlement were observed. The locations of the observation points for the East Wing and the results from the monitoring are shown on Figures 3 and 4. The settlement monitoring indicated that the structure was settling rapidly and did not indicate slowing of the rate of settlement. Figure 3. Settlement point monitoring locations for the East Wing 4

5 Figure 4. Settlement monitoring of East Wing starting in early September The West Wing slab foundation had been placed, but elevated work had not yet begun. Therefore, the micropile installation for the East Wing had to be constructed in limited headroom and access conditions as shown on Figures 8 and 9. The West Wing micropile installation was performed in open headroom (Figure 10). ORIGINAL FOUNDATION INSTALLATION DETAILS The aggregate pier design for the student housing building included approximately 1,050 piers, 0.77 m (30 inch) in diameter (not installed by the authors company). The aggregate piers varied in length from m (12-28 feet). The piers were spaced as shown on Figure 5. Spread footing foundations rested on top of the aggregate piers. The footings were apparently designed for allowable bearing pressures of 287 and 335 kpa (6,000 and 7,000 psf). 5

6 Figure 5. Initial foundation treatment with aggregate piers PROJECT HEALTH AND SAFETY All projects require a strong commitment to health and safety. This project specifically presented several unique safety challenges. Implementing an effective Health and Safety Plan (HSP) was critical due to the intense and quick build up of resources on the project, and around the clock operations. Senior management (offsite) was required to perform independent safety inspections of the site on a weekly basis. Additionally, the crew was incentivized to report safety concerns and near miss incidents which helped foster the existing company culture that shows how safety ownership belongs to everyone. The overall Health and Safety Plan included both daily and weekly reviews, safety inspections and toolbox talks. A daily task analysis was completed each morning and required the crew to actively engage in discussing their work task, hazards present and safe work procedures to mitigate these hazards. The general contractor assisted in communication and logistical planning through trade meetings to keep safety as the first priority throughout the project. Policies adopted to promote safety on the project involved: mandatory spotters for all equipment movement, signage and barricades to 6

7 inform other trades of ongoing activities and active monitoring of all fall protection and open hole issues. The total safety effort yielded a project which was completed without any OSHA recordable incidents. MICROPILE UNDERPINNING Small diameter, 100 mm (4 inch) maximum outside diameter, 9 12 mm ( inch) thick wall steel pipe micropiles were used for the underpinning of the student housing building. Design loads for the piles were 445 and 667 kn (50 and 75 tons). The piles were drilled using water flush into the underlying PWR or to refusal using disposable drill bits and then fully grouted from the bottom-up. About 20 percent of the micropiles encountered the aggregate piers during drilling, which presented caving conditions in the borehole. The piles were advanced rapidly through the piers into the residual soils, which then tended to stabilize the hole by caking the aggregates with sandy silt. Typical socket depths into the PWR were 3 to 4.5 m (10 to 15 feet). The piles drilled for the East Wing were installed in limited access and headroom. A typical micropile layout for the southeast side of the East Wing is shown on Figure 6. Figure 6. Micropile locations in southeast corner of East Wing 7

8 Other micropile layouts throughout the building were similar. The micropiles were installed through holes cored or drilled through the existing spread footing foundations. The micropiles were attached to the existing footings by non-shrink grout and weld beads were added onto the micropile pipe where the micropiles extended through the roughened holes made in the footings. MICROPILE LOAD TESTING Two compression micropile load tests were conducted, one at the East Wing and another at the West Wing. Although the production piles were designed for two different loads, only testing of the higher loading condition was performed. The higher loading condition was a design load of 667 kn, (75 tons, 150 kips) and a test load of 1,334 kn (150 tons, 300 kips) as shown. The pile design required a minimum socket into PWR of about 4.5 m (15 feet) or refusal on bedrock. As shown on Figure 7, the test piles performed well, with deflections of 11.5 mm (0.45 inches) measured at design load. The piles exhibited some lateral movements as the load was applied, which slightly skews the deflection results. The East Wing pile test was discontinued slightly early due to safety concerns about the leaning test pile. Figure 7. Micropile compression load test results 8

9 Figure 8. East Wing restricted access conditions Figure 9. East Wing micropile drilling in low headroom 9

10 Figure 10. West Wing micropile drilling in open headroom FOOTING CONNECTION DETAILS AND LOAD TESTING Eight inch diameter holes were cored or percussion drilled through the existing spread footing foundations to accommodate the micropiles. Rotary coring utilized diamond coring bits and percussion drilling used down-the-hole hammers. The diamond cored holes were roughened using a scabbling apparatus. A photo of a typical roughened core hole is shown on Figure 11. Initially in the design, it was understood that a 900 mm (3 feet) thick footing was the thinnest available for bonding of the micropiles. A working bond stress of 1,140 kpa (165 psi) was therefore initially selected for design. However, later it was determined that some footings were only 600 mm (2 feet) thick. Since the connection detail was key to the design, it was decided to increase the working bond value to 1,725 kpa (250 psi) using non-shrink grout and to prove this value with testing on site. Tension load tests were conducted on non-production pieces of micropile pipe, including weld beads around the perimeter of the pipe, bonded to the footing with non-shrink grout for both cored/roughened and percussion drilled holes. The tests were done at an adjacent tower crane foundation at the West Wing. Figure 12 illustrates the connection test setup. Results from the coring and drilling tests were almost identical and are shown on Figure 13. The connection tests netted a maximum bond stress of 3,450 kpa (500 psi) versus the required bond stress of 1,725 kpa (250 psi). 10

11 Figure 11. Photo of roughened core hole through existing footing Figure 12. Micropile pipe to footing connection test set-up 11

12 Connection Test Percussion Drill Load Test Load (Kips) Elongation (Inches) Design Load = 150 Kips Average Deflection Rebound Curve Design Load Ave Defl. Minus Elastic Rebound Curve Minus Elastic Figure 13. Percussion drill connection load test results RESULTS As shown on Figure 14, the settlement was arrested successfully after micropile installation as load was transferred to the piles by the structure. The foundation remediation project was completed in only 10 weeks, with approximately 1,035 micropiles installed. Construction of the student housing building was then resumed. A recent photo of the construction is shown on Figure 15. CONCLUSIONS After an aggregate pier foundation installation failed to perform adequately, drilled and grouted micropiles were successfully installed to underpin a large structure that had settled severely. This intense, resource loaded and aggressive schedule project was completed without a safety incident. Drilled footing connections using nonshrink grout worked very well to attach the building to the micropiles with minimal disruption to the existing structure. 12

13 Figure 14. East Wing settlement data indicating no further settlement of the building after underpinning Figure 15. Recent photo of the student housing building construction 13

14 ACKNOWLEDGEMENTS The original geotechnical report was written by GeoTechnologies. Ed Hearn, P.E. was the on-site geotechnical engineer for GeoTechnologies during the remediation work. The general contractor was a Joint Venture of Brasfield & Gorrie General Contractors / Clancy & Theys Construction Company. Jarrett Frazier was the project manager for the general contractor. Tom Finn and Stephen Edwards were the superintendents for the micropile/underpinning work for Hayward Baker. Satoshi Mitsumori was the field engineer for Hayward Baker. Martin Cuadra, P.E. with Uzun & Case was the structural engineer for the remedial work. Sandy Triplett helped prepare this paper. REFERENCES 1. Sowers, G.F. and Richardson, T.L., Residual Soils of the Piedmont and Blue Ridge, Transportation Research Record No. 919, National Academy Press, Washington, DC, 1985, pp Preliminary Report of Subsurface Investigation, Ten Storey Building and Parking Deck, North Carolina, GeoTechnologies, Inc., November 30, 2007, 53 pages. 14

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

The International Workshop on Micropiles, 2007

The International Workshop on Micropiles, 2007 MICROPILE FOUNDATION REPAIR AND UNDERPINNING, ARTS AND SCIENCE MUSEUM, UNIVERSITY OF PUERTO RICO, MAYAGUEZ Presented at: International Society of Micropiles (ISM) The International Workshop on Micropiles,

More information

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Stephen W. Lacz 1, M. ASCE, P.E. and Richard C. Wells 2, F. ASCE, P.E. 1 Senior Professional, Trigon Kleinfelder, Inc., 313 Gallimore

More information

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch USE OF MICROPILES IN TEXAS BRIDGES by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch DEFINITION OF A MICROPILE A micropile is a small diameter (typically less than 12 in.), drilled and

More information

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for

More information

load on the soil. For this article s examples, load bearing values given by the following table will be assumed.

load on the soil. For this article s examples, load bearing values given by the following table will be assumed. How Many Piers? By Gary Collins, P.E. A clear-cut guide to helical pier spacing Introduction Helical pier spacing is not an exact science. How many does it take to support a structure adequately or repair

More information

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge. TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may

More information

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet

More information

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations from New construction foundations don t have to be a headache. The CHANCE Helical Pier Foundation System gives you the performance of concrete without the drawbacks and liabilities of driven piles and

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples Prof. V.S.Raju (Formerly: Director, IIT Delhi & Professor and Dean, IIT Madras) Email: rajuvs_b@yahoo.com

More information

Chapter 9 Remedial Measures

Chapter 9 Remedial Measures [This is an annotated version of a chapter from the US Army Corps of Engineers book, Foundations in Expansive Soils. This book is in the public domain. This document is consists of an abbreviated and annotated

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE ENGINEERED FOUNDATIONS Department of Public Works Jeff Hill, PE What is an engineered foundation. A Foundation Design Developed by a Trained Professional (Engineer) Types of Foundations (All of which can

More information

Lighthouse Engineering, L.L.C.

Lighthouse Engineering, L.L.C. Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: Office@LighthouseEng.com Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

Pent Up Load and Its Effect on Load Test Evaluation

Pent Up Load and Its Effect on Load Test Evaluation Nicholson Construction Company 12 McClane Street Cuddy, PA 15031 Telephone: 412-221-4500 Facsimile: 412-221-3127 Pent Up Load and Its Effect on Load Test Evaluation by T.D. Richards Jr., P.E. Nicholson

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline

More information

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED

More information

MICROPILE FOUNDATIONS IN KARST: STATIC AND DYNAMIC TESTING VARIABILITY

MICROPILE FOUNDATIONS IN KARST: STATIC AND DYNAMIC TESTING VARIABILITY MICROPILE FOUNDATIONS IN KARST: STATIC AND DYNAMIC TESTING VARIABILITY Jesús Gómez, Ph.D., P.E Allen Cadden, P.E. O. Christopher Webster, P.E. Schnabel Engineering, Inc. Schnabel Engineering, Inc. Schnabel

More information

Equivalent CPT Method for Calculating Shallow Foundation Settlements in the Piedmont Residual Soils Based on the DMT Constrained Modulus Approach.

Equivalent CPT Method for Calculating Shallow Foundation Settlements in the Piedmont Residual Soils Based on the DMT Constrained Modulus Approach. Equivalent CPT Method for Calculating Shallow Foundation Settlements in the Piedmont Residual Soils Based on the DMT Constrained Modulus Approach. Paul W. Mayne, PhD, P.E., Professor, Geosystems Engineering

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

ENCE 4610 Foundation Analysis and Design

ENCE 4610 Foundation Analysis and Design This image cannot currently be displayed. ENCE 4610 Foundation Analysis and Design Shallow Foundations Total and Differential Settlement Schmertmann s Method This image cannot currently be displayed. Strength

More information

Emergency repair of Bridge B421

Emergency repair of Bridge B421 Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)

More information

Paper - 4 - The relation of Micropile Diameters in case of Pressure casting and non-pressure casting (30)

Paper - 4 - The relation of Micropile Diameters in case of Pressure casting and non-pressure casting (30) Paper - 4 - Elarabi, H.; Abbas A., The relation of Micropile Diameters in case of Pressure casting and non-pressure casting,magnt Research Report (ISSN. 1444-8939), Vol.2 (2) Accepted for publication The

More information

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load

More information

How to Design and Build a Fence/G traverse Bridge or Graffiti Project

How to Design and Build a Fence/G traverse Bridge or Graffiti Project Outline Project Location Project Description Project History Site Constraints Geotechnical Investigation & Soil Profile Foundation Design Process Photos Project Location Project Limits: The Grand River

More information

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 Appendix B CONTENTS STATIC (TIEBACKS)... B-3 STATIC AXIAL (COMPRESSION/TENSION)... B-6 STATIC (LATERAL)... B-9 CAPACITY VERIFICATION

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

MILWAUKEE CITY HALL FOUNDATION RESTORATION. Project Update November 12, 2014

MILWAUKEE CITY HALL FOUNDATION RESTORATION. Project Update November 12, 2014 MILWAUKEE CITY HALL FOUNDATION RESTORATION Project Update November 12, 2014 Milwaukee City Hall Building History/Fast Facts - City Hall is a masonry and iron superstructure - Originally constructed from

More information

CIVL451. Soil Exploration and Characterization

CIVL451. Soil Exploration and Characterization CIVL451 Soil Exploration and Characterization 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally

More information

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Eric M. Klein, P. E., Rummel, Klepper & Kahl, LLP, Baltimore, Maryland Kenneth B. Andromalos, P. E., Brayman Environmental,

More information

DAMAGE TO FOUNDATIONS FROM EXPANSIVE SOILS

DAMAGE TO FOUNDATIONS FROM EXPANSIVE SOILS DAMAGE TO FOUNDATIONS FROM EXPANSIVE SOILS J. David Rogers, Robert Olshansky, and Robert B. Rogers Expansive soils in many parts of the United States pose a significant hazard to foundations for light

More information

Settlement of Foundations on Expansive Clays Due to Moisture Demand of Trees CIGMAT 2008

Settlement of Foundations on Expansive Clays Due to Moisture Demand of Trees CIGMAT 2008 Settlement of Foundations on Expansive Clays Due to Moisture Demand of Trees CIGMAT 2008 Kenneth E. Tand, P.E. Practicing Geotechnical Engineer FRIEND OR FOE Trees are our friends. They extract carbon

More information

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com

HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com, 2011 TO: Mr. REF: CONDITION OF PROPERTY SURVEY Dear Mr. : At your request,

More information

GLOSSARY OF TERMINOLOGY

GLOSSARY OF TERMINOLOGY GLOSSARY OF TERMINOLOGY AUTHORIZED PILE LENGTHS - (a.k.a. Authorized Pile Lengths letter) Official letter stating Engineer's recommended length of concrete piles to be cast for construction of foundation.

More information

ATLAS RESISTANCE Pier Foundation Systems

ATLAS RESISTANCE Pier Foundation Systems ATLAS RESISTANCE Pier Foundation Systems Foundation Repair Systems for Civil Construction Applications: Residential, Commercial, Industrial Atlas Resistance Piers have been used to restore and/or stabilize

More information

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective FHWA NATIONAL GEOTECHNICAL PROGRAM www.fhwa.dot.gov/engineering/geotech Why Geotechnical Instrumentation? Provide warning

More information

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code LEGACY REPORT Reissued November 1, 2003 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900

More information

WORK SCOPE. Domains in which we work:

WORK SCOPE. Domains in which we work: WORK SCOPE Engineering consulting, technical office, assistance and supervision in industrial works. We specialize in structures, civil works and industrial equipment. Domains in which we work: Industrial

More information

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013 How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table

More information

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE 9.1 INTRODUCTION An important reason that composite piles have not gained wide acceptance in the civil engineering practice is the lack of a long

More information

Cold Weather Concrete Practices

Cold Weather Concrete Practices Cold Weather Concrete Practices The Information below is an outline of common practice for residential foundation placement and winter construction utilize Edmonton and surrounding Area. Conditions in

More information

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA FHWA Hollow Bar Soil Nail (HBSN) Test Program Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA Outline Introduction and motivation Installation methods for testing Testing and

More information

PROFESSIONAL ENGINEERING INSPECTIONS, INC.

PROFESSIONAL ENGINEERING INSPECTIONS, INC. PROFESSIONAL ENGINEERING INSPECTIONS, INC. P. O. BOX 271492 HOUSTON, TEXAS 77277 Registered Engineering Firm #1503 http://www.profengineering.com (713) 664-1264 July 8, 2004 Mr. Simple Samson 2831 Octoberfest

More information

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built

More information

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 CONTENTS 1.0 INTRODUCTION 2.0 OVERVIEW OF SPT APPROACH TO DEVEOPMENTS/WORKS IN THE VICINITY OF

More information

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA STRUCTURAL ASSESSMENT FOR Full Metal Jacket Building 0 Prince Street, Prepared by: ALPHA CORPORATION (Alpha) 1850 S. Loudoun Street, Suite 200 Winchester, VA 22601 540-723-0704 September 22, 2010 J. Michael

More information

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER Professional Experience: Pride and Passion in the Art of Structural Engineering since 1979. Professional Registration: Professional

More information

Foundation Underpinning Process and Relationship with Groundwater in West- Central Florida

Foundation Underpinning Process and Relationship with Groundwater in West- Central Florida Foundation Underpinning Process and Relationship with Groundwater in West- Central Florida Ahmed Said, PhD, PE Principal Engineering Consultant, Sinkhole Geotech, Inc. e-mail: admin@sinkholegeotech.com

More information

High Capacity Helical Piles Limited Access Projects

High Capacity Helical Piles Limited Access Projects High Capacity Helical Piles Limited Access Projects Tel 403 228-1767 Canada, USA, Russia Brendan ODonoghue 519 830-6113 Presentation Summary 1. Helical piles Background on large diameter shafts and helices

More information

SECTION 3 ONM & J STRUCTURAL ANALYSIS

SECTION 3 ONM & J STRUCTURAL ANALYSIS Historic Boynton Beach High School Existing Building Assessment City of Boynton Beach February 10, 2011 SECTION 3 ONM & J STRUCTURAL ANALYSIS STRUCTURAL ENGINEERS SPECIAL INSPECTORS STRUCTURAL CONDITION

More information

System. Stability. Security. Integrity. 150 Helical Anchor

System. Stability. Security. Integrity. 150 Helical Anchor Model 150 HELICAL ANCHOR System PN #MBHAT Stability. Security. Integrity. 150 Helical Anchor System About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair

More information

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT 1.0 SOIL IMPROVEMENT 1.1 General Soil Investigation Information are provided in Part B1 annex as a guide to the Contractor for his consideration

More information

October 30, 2014. Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR. Report of Findings, Structural Investigation, Benton, Arkansas, Dear Mr.

October 30, 2014. Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR. Report of Findings, Structural Investigation, Benton, Arkansas, Dear Mr. 117 S. Market St. Benton, AR 72015 * 501-315-2626 * Fax 501-315-0024 October 30, 2014 Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR Re: Report of Findings,, Benton, Arkansas, Dear Mr. Vick: This

More information

Baton Rouge Foundation Repair

Baton Rouge Foundation Repair Baton Rouge Foundation Repair 13822 Florida Blvd Bldg 3 Baton Rouge, LA 70819 Baton Rouge Foundation Repair offers services to correct the settlement of both Slab foundations and Pier & Beam foundations

More information

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

5/1/2013. Topics. The challenge is to better maintain native characteristics of soils during and after construction

5/1/2013. Topics. The challenge is to better maintain native characteristics of soils during and after construction PIN Foundations Topics Applications Design and Construction Flow Control Credits www.pinfoundations.com Copyright 2008, Pin Foundations, Inc. Curtis Hinman WSU Extension Faculty, Watershed Ecologist chinman@wsu.edu

More information

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN. A Solid Foundation Solution for Homeowners from Our products are made with 90% Recycled Material Down. Right. Solid. GREEN. Stop the damaging effects of foundation settling... Sinking foundations, cracked

More information

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with

More information

FOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012

FOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012 FOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012 Building and Housing has published technical guidance for foundation repairs and reconstruction for residential properties in green zone Foundation Technical

More information

Step 11 Static Load Testing

Step 11 Static Load Testing Step 11 Static Load Testing Test loading is the most definitive method of determining load capacity of a pile. Testing a pile to failure provides valuable information to the design engineer and is recommended

More information

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma Bart B. Barrett, B.S., P.E.1 Kerry S. Lee, M.B.A., P.E., M. ASCE2 Erik L. Nelson, Ph.D., P.E., M. ASCE3

More information

Steve Brinkman Alain Pinel Realtors 167 S San Antonio Road Los Altos, CA 94022 RE: Foundation Inspection for 162 Del Monte Ave. Los Altos, CA 94022

Steve Brinkman Alain Pinel Realtors 167 S San Antonio Road Los Altos, CA 94022 RE: Foundation Inspection for 162 Del Monte Ave. Los Altos, CA 94022 M G C O N S T R U C T O R S & E N G I N E E R S, I N C. I N S P E C T O R S E N G I N E E R S B U I L D E R S C A L I F O R N I A E N G I N E E R I N G A N D B U I L D I N G L I C E N S E A / B 6 4 2 0

More information

Spotting Structural Problems in a Home

Spotting Structural Problems in a Home Home Inspector s Guide To Spotting Structural Problems in a Home Greg Madsen and Richard McGarry McGarry and Madsen Inspection Here s some suggestions for giving your next potential house purchase a careful

More information

DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76. Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA

DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76. Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76 Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA The Block 76 project includes the demolition and redevelopment of an entire city

More information

product manual HS-4210 HS-4210_MAN_09.08 Digital Static Cone Penetrometer

product manual HS-4210 HS-4210_MAN_09.08 Digital Static Cone Penetrometer HS-4210_MAN_09.08 product manual HS-4210 Digital Static Cone Penetrometer Introduction This Manual covers the measurement of bearing capacity using the Humboldt Digital Static Cone Penetrometer (DSCP).

More information

Structural Assessment Report

Structural Assessment Report Report Dallas Township Elementary School Dallas, Pennsylvania (JBCI Project No. 144911) 1655 Suburban Station Building 1617 John F. Kennedy Boulevard Philadelphia PA 19103 215 665 0497 5 Sandwood Drive

More information

National Archives and Record Administration

National Archives and Record Administration National Archives and Record Administration Installation of Self-Closing Flood Barriers and Loading Dock Turntable Removal and Structural Slab Repairs ! 2010 Baltimore Washington Chapter Outstanding Repair

More information

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage 3.3. Evaluation of Building Foundation Damage Basic Terminology: Damage: Destruction, deformation, inclination and settlement of a building foundation caused by an earthquake. Damage grade: Degree of danger

More information

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:! In-situ Testing! Insitu Testing! Insitu testing is used for two reasons:! To allow the determination of shear strength or penetration resistance or permeability of soils that would be difficult or impossible

More information

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR If you listen to the hype, it sounds like there must be 20 or 30 different types of piers out there. Company A says they have an

More information

SERVICES 2015 ISO 18001

SERVICES 2015 ISO 18001 SERVICES 2015 A family business with a solid foundation of experience, we handle all aspects of site investigation.... Phase 1 Environmental Studies Phase 2 Intrusive Investigations Phase 3 Remediation

More information

Re: Damages to Alaska Building from Legislative Information Office Construction

Re: Damages to Alaska Building from Legislative Information Office Construction 510 L Street Suite 200 Anchorage, AK 99501-1949 (907) 274-22362236 Phone (907) 274-25202520 Fax www.bbfm.com July 22, 2015 Jim Gottstein Alaska Building 406 G Street, Suite 206 Anchorage, AK 99501 Re:

More information

Proposed Minimum Subterranean Termite Treatment Standards

Proposed Minimum Subterranean Termite Treatment Standards Proposed Minimum Subterranean Termite Treatment Standards Introduction This document is intended to serve as a model for states considering the adoption of standards for soil application of termiticides.

More information

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E. MICROPILES SUBJECT TO LATERAL LOADING Dr. Jesús Gómez, P.E. Micropile Design and Construction Seminar Las Vegas, NV April 3-4, 2008 Outline When are micropiles subject to lateral load? How do we analyze

More information

2010-2011 Contractor of the Year

2010-2011 Contractor of the Year U.S. Army Corps of Engineers: Little Calumet River Stage VII Steel Sheet Piling Installation Hammond, Indiana Thatcher worked two rigs concurrently one on the north side and one on the south. The United

More information

Technical Assignment 2 TABLE OF CONTENTS

Technical Assignment 2 TABLE OF CONTENTS 2 TABLE OF CONTENTS Executive Summary...3 Introduction..5 Gravity Loads......6 Design Codes......7 Materials..8 Existing Structural System.. 10 Existing Floor System 15 Alternate Floor Framing Systems...17

More information

PART E SPECIFICATIONS

PART E SPECIFICATIONS PART E SPECIFICATIONS Page 1 of 5 PART E - SPECIFICATIONS GENERAL E1. APPLICABLE SPECIFICATIONS, STANDARD DETAILS AND DRAWINGS E1.1 The City of Winnipeg Works and Operations Division Standard Construction

More information

DUDERSTADT FOUNDATION & CONSTRUCTION, LLC.

DUDERSTADT FOUNDATION & CONSTRUCTION, LLC. DUDERSTADT FOUNDATION & CONSTRUCTION, LLC. Drilling since 1916 2215 Belknap Place Phone (210) 824-3800 San Antonio, TX 78212-1904 Fax (210) 824-9525 www.duderstadtfoundation.com ABOUT THE COVER: Drilled

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

STATIC PILE LOAD TEST MANUAL. GEOTECHNICAL CONTROL PROCEDURE GCP-18 Revision #4

STATIC PILE LOAD TEST MANUAL. GEOTECHNICAL CONTROL PROCEDURE GCP-18 Revision #4 STATIC PILE LOAD TEST MANUAL GEOTECHNICAL CONTROL PROCEDURE GCP-18 Revision #4 AUGUST 2015 GEOTECHNICAL CONTROL PROCEDURE: STATIC PILE LOAD TEST MANUAL GCP-18 Revision #4 STATE OF NEW YORK DEPARTMENT

More information

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598 Lessons Learned from Large Diameter Sanitary Sewer Pipe Bursting Project: Conversion of Abandoned Gravity Sewer Main Into Upsized Sanitary Force Main South San Francisco, CA Kent Von Aspern,* Collins Orton**

More information

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

Comprehensive Design Example 2: Foundations for Bulk Storage Facility Comprehensive Design Example 2: Foundations for Bulk Storage Facility Problem The project consists of building several dry product storage silos near an existing rail siding in an open field presently

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks

More information

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and

More information

Structural Foundation System

Structural Foundation System Structural Foundation System SLABTEK, a technological advancement in foundation designs for residential and lightweight commercial structures SlabTek is a patent allowed process for concrete foundations

More information

Lighthouse Engineering, L.L.C.

Lighthouse Engineering, L.L.C. Wednesday, August 20, 2014 Lighthouse Engineering, L.L.C. Michael Gandy, P.E. Registered Professional Engineer (TX: 95672) Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website:

More information

An Automatic Kunzelstab Penetration Test

An Automatic Kunzelstab Penetration Test An Automatic Kunzelstab Penetration Test Yongyuth Sirisriphet 1, Kitidech Santichaianant 2 1 Graduated student: Faculty of Industrial Education in and Technology. King Mongkut's University of Technology

More information

Designed and Engineered to Perform

Designed and Engineered to Perform History EARTH CONTACT PRODUCTS, L.L.C., is a family owned company, based in Olathe, Kansas. This company was built upon Don May s U.S. Patented fourth-generation Steel Piering System that has led to the

More information

Now That s IDEAL. Now That s IDEAL. LISTEN. RESEARCH. DESIGN. DELIVER.

Now That s IDEAL. Now That s IDEAL. LISTEN. RESEARCH. DESIGN. DELIVER. The Leading Edge SM At IDEAL, we try not to complicate things. We discover needs and problems, then work out solutions. It takes real teamwork to accomplish truly great things. That s you and us, working

More information

How To Design A Foundation

How To Design A Foundation The Islamic university - Gaza Faculty of Engineering Civil Engineering Department CHAPTER (2) SITE INVESTIGATION Instructor : Dr. Jehad Hamad Definition The process of determining the layers of natural

More information

Strength Determination of "Tooth-Paste" Like Sand and Gravel Washing Fines Using DMT

Strength Determination of Tooth-Paste Like Sand and Gravel Washing Fines Using DMT Strength Determination of "Tooth-Paste" Like Sand and Gravel Washing Fines Using DMT David L. Knott, P.E. and James M. Sheahan, P.E. HDR Engineering, Inc. 3 Gateway Center Pittsburgh, PA 15222-1074 Phone:

More information

6 RETROFITTING POST & PIER HOUSES

6 RETROFITTING POST & PIER HOUSES Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This

More information

HCD DSA OSHPD 1 2 1/AC AC SS SS/CC 1 2 3 4 2013 CALIFORNIA BUILDING CODE 141

HCD DSA OSHPD 1 2 1/AC AC SS SS/CC 1 2 3 4 2013 CALIFORNIA BUILDING CODE 141 CALIFORNIA BUILDING CODE MATRIX ADOPTION TABLE CHAPTER 1 SOILS AND FOUNDATIONS (Matrix Adoption Tables are non-regulatory, intended only as an aid to the user. See Chapter 1 for state agency authority

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information