Bridge Geotechnical Considerations and Designing for Scour PART II Christopher Byrum, Ph.D., P.E. Geotechnical Soil and Materials Engineers, Inc.
|
|
- Aileen Lynch
- 7 years ago
- Views:
Transcription
1 Bridge Geotechnical Considerations and Designing for Scour PART II Christopher Byrum, Ph.D., P.E. Geotechnical Soil and Materials Engineers, Inc. Brian Barkdoll, PhD, PE Scour Michigan Technological University Geotechnical Evaluations for Bid Bridge Design USGS Topo And Bedrock Topo to estimate Depth to Rock 1
2 USDA Soil Survey For Marsh Limits Peat Marshes Detailed Soil Survey: All New Alignments Obtain Data from Existing Bridge Plans/Files 1. Existing Test Holes 2. Bridge Deck Cross Section (between beams) 3. Existing Utilities Type and Location 4. Construction History Files Issues 5. Design History Files Issues Review All This Stuff and: 1. Summarize Key Site Conditions 2. Decide if New Test Holes are Needed 3. Make the Field Geotechnical Evaluation Plans 2
3 Big Drill Rig = Deep Holes Small Truck Drill Rig Small All-Terrain Drilling Rig Remote Control for Safety 3
4 MDOT SKID drill rig mounted to Pontoon Boat SKID drill rig Set Inside a Cofferdam using a Crane 4
5 Weak Cohesive Soils- Thin Wall Shelby Tube Low Disturbance Very Weak Cohesive Soils- In-Situ Vane Shear Strength Testing 5
6 Soft-Soil Evaluation m Elev. m SPT, bpf Moisture Percent Torvane Field Vane For Design Strength, kpa Geotechnical Evaluation Case Study A Very Difficult Test Hole Existing Piers Settled and Cracked, Vibration Related I-696 over Rouge River- Bridge Widening 6
7 Pier Settled and Railing Crushed Crushed Column Big Crack 7
8 8
9 9
10 Typical Test Hole Frequency BRIDGES 1. One per substructure Unit (<50-ft wide) 2. Two per Unit ( ft wide) 3. Three per Unit ( ) APPROACHES 1. Fill over Marsh (50-ft Spacing, muck rods) 2. Fill over Good Dirt (250-ft Spacing) Artesian Drilling Protocol: 1. Do not poke a hole into the artesian within the proposed cofferdam limits. 2. Do not poke a hole into the artesian where you cant seal it (Barge Test Hole performed in the middle of a River). 10
11 Artesian Drilling Protocol: 3. Use Special Drill Rigs with ability to grout and drive casing (Water Well Rigs). 4. Do poke a few holes into the Artesian in select areas that can be sealed and measure: A. the static head and flow rate. B. the cover soil type/thickness. C. the artesian soil type and thickness. D. depth to hard bottom below the artesian soil. Artesian conditions were close to the Ground Surface and intense at this site Flow out of SB5 Casing Soil Sampling Deep Test Holes with SPT Testing: SPT Needed for Soil Strength Design Info. Sewer Trench and Sheet Piling Designs. Global Staility Analayses for Embankments and Walls. Shelby Tube or Vane Shear Tests Very Weak Soil Deposits. Drill Rigs get 75 to 150 linear feet of sampling per day. SCOUR Do Particle Size Gradation (Sieve/Hydrometer) tests/plots Define Layers and Gradation to 8 meters below footing Sometimes we get Channel Surface/Bed Samples (The Armor) 11
12 Initial Questions/Data Before Setting the Geo Scope 1. Are we trying to save the existing pavement? No = No Coring Required, just thickness and type data. Yes = Get Core Samples of Existing Pavement and Samples of Existing Base Materials for Gradation Analyses. 2. Are there new/relocated utilities? Data for Shoring/Dewatering 3. Unusual Existing Utilities needing special attention? Yes = Special Stuff May Be Needed. 4. Weak Soils/Swamps with Major Grade Increases/Widening? Yes = Deeper Borings and Special Stuff. 5. Do we need Retaining Walls or New Traffic Signal Poles? Yes = Deeper Borings and Special Stuff Initial Questions/Data Before Setting the Geo Scope 1. Are we trying to save the existing pavement? No = No Coring Required, just thickness and type data. Yes = Get Core Samples of Existing Pavement and Samples of Existing Base Materials for Gradation Analyses. 2. Are there new/relocated utilities? Data for Shoring/Dewatering 3. Unusual Existing Utilities needing special attention? Yes = Special Stuff May Be Needed. 4. Weak Soils/Swamps with Major Grade Increases/Widening? Yes = Deeper Borings and Special Stuff. 5. Do we need Retaining Walls or New Traffic Signal Poles? Yes = Deeper Borings and Special Stuff 12
13 Widening Widening GAS PEAT Marl Fiber SEWER Core Embank WATER Initial Questions/Data Before Setting the Geo Scope 1. Are we trying to save the existing pavement? No = No Coring Required, just thickness and type data. Yes = Get Core Samples of Existing Pavement and Samples of Existing Base Materials for Gradation Analyses. 2. Are there new/relocated utilities? Data for Shoring/Dewatering 3. Unusual Existing Utilities needing special attention? Yes = Special Stuff May Be Needed. 4. Weak Soils/Swamps with Major Grade Increases/Widening? Yes = Deeper Borings and Special Stuff. 5. Do we need Retaining Walls or New Traffic Signal Poles? Yes = Deeper Borings and Special Stuff 13
14 Initial Questions/Data Before Setting the Geo Scope 1. Are we trying to save the existing pavement? No = No Coring Required, just thickness and type data. Yes = Get Core Samples of Existing Pavement and Samples of Existing Base Materials for Gradation Analyses. 2. Are there new/relocated utilities? Data for Shoring/Dewatering 3. Unusual Existing Utilities needing special attention? Yes = Special Stuff May Be Needed. 4. Weak Soils/Swamps with Major Grade Increases/Widening? Yes = Deeper Borings and Special Stuff. 5. Do we need Retaining Walls or New Traffic Signal Poles? Yes = Deeper Borings and Special Stuff SWAMPS: Embankment Widening Example On-Going Slope Movements 14
15 Test Locations Muck Rod Tests Deep Soil Borings: Sheet Pile and Pavement Design SPT 0 50 SPT
16 CONTINUOUS GEOGRID #2 The Anchors GWT GEOGRID #3 CONTINUOUS GEOGRID #1 Placement of EPS and Geogrid behind sheeting. View from Northwest of the Wall 16
17 View from North Hillside, Looking South View of Final Product, Looking West GEOTECHNICAL ENGINEERING PROCESS 40 ft. Abutment A Approach Embankment Pier 1 N or E Abutment B Pier 2 Pier 3 R.R. Existing Ground Superstructure-Beams, Deck, Joints, Railing. Substructures-Footings, Columns and Walls 17
18 State Route M-63 over CSX Railroad St. Joseph, Michigan PHASE I: PLANNING Span Lengths 40 ft. R.R. Min. Height for a Train Vert. Curve-Sight 50 mph PRIMARILY GEOMETRY STANDARDS vs. PROPERTY FEATURES. Existing Ground State Route M-63 over CSX Railroad St. Joseph, Michigan PHASE II: DESIGN-Acquire Geo Info 40 ft. Loose/soft sand, peat, sediment, and marl. G.W.T. R.R. Sand fill 50 ft. Loose Sands Organic Clayey Silt (OH-marl) w% = 45 to 65, LL= 60 to 70, c = 500 to 1100 psf 120 ft. Medium Dense Sands Very Dense Sands State Route M-63 over CSX Railroad Center of Rotation DESIGN-Check Stability MASS ROTATION Traffic Loads Weight 40 ft. R R.R. G.W.T. Sand fill Loose/soft sand, peat, sediment, and marl. 50 ft. Loose Sands Organic Clayey Silt (OH-marl) w% = 45 to 65, LL= 60 to 70, c = 500 to 1100 psf F.S > ft. Medium Dense Sands Soil Shear Strengths Very Dense Sands BYRUM
19 Sand Embankment Light Slag Embankment Abutment Front Slope 1:2 19
20 Light Slag Embankment Approach Side Slope 1:3 State Route M-63 over CSX Railroad DESIGN-Check Stability-SLIDING BLOCK Traffic Loads Active 40 ft. Loose/soft sand, peat, sediment, and marl. G.W.T. R.R. Passive Sand fill 50 ft. Loose Sands Organic Clayey Silt (OH-marl) w% = 45 to 65, LL= 60 to 70, c = 500 to 1100 psf F.S > ft. Medium Dense Sands Soil Shear Strengths Very Dense Sands BYRUM-2000 Sand Embankment 20
21 Light Slag Embankment State Route M-63 over CSX Railroad Lightweight slag fill (90 pcf) DESIGN REQUIREMENTS-STABILITY $$$$$$$ Geogrid Expanded Polystyrene (EPS) Ultra-Lightweight fill (10 pcf) 40 ft. p v < 3,200 psf G.W.T. p v < 2,500 psf R.R. Sand fill Loose/soft sand, peat, sediment, and marl. 50 ft. Loose Sands Organic Clayey Silt (OH-marl) w% = 45 to 65, LL= 60 to 70, c = 500 to 1100 psf 120 ft. Medium Dense Sands NOTE: For 40 of sand, p v 4,400 psf Very Dense Sands BYRUM-2000 State Route M-63 over CSX Railroad DESIGN REQUIREMENTS-SETTLEMENT Wick Drains-Accelerate Settlement 40 ft. H-piles: Major Drag-down forces R.R. G.W.T. Sand fill Loose/soft sand, peat, sediment, and marl. 50 ft. Loose Sands Organic Clayey Silt (OH-marl) w% = 45 to 65, LL= 60 to 70, c = 500 to 1100 psf 120 ft. H-piles: Drive to 110 ton, use 80 ton for bridge design Very Dense Sands BYRUM
22 State Route M-63 over CSX Railroad Other Design Services Contract Special Provisions -Wait Periods for Settlement/Strength Gain -Geotechnical Instrumentation During Const. -Wick Drains to Accelerate Settlement -Special Materials; Properties and Control Construction Services Geotechnical Instrumentation during Const. - Possibly Allow Contractor to Proceed Early -Identify Nature of Unusual Movements -Justify (or not) Extra Expense Recommended -Justify (or not) Design Procedure Used. BYRUM-2000 TYPICAL BRIDGE FOUNDATIONS Bridge Scour Hydraulics Reasons why bridges fail Scour caused by many flow patterns In general, water velocity high enough to move sediment. 22
23 Causes of Bridge Scour Contraction scour Bed degradation Vortices Out-flanking River widening??? Abutment scour causes pier failure! Contraction Scour For some bridges the width of the river has been narrowed to reduce span length. This smaller flow cross-sectionalsectional area leads to higher velocity (V=Q/A) If increased velocity is high enough, then the sediment will start to erode. Contraction Scour Schematic Original riverbanks Reduced flow area Bridge Abutments 23
24 Riverbed Degradation Some rivers have beds that are naturally degrading due to conditions upstream or downstream. Any bridge piers or abutments built will need to have a deeper foundation. Degradation Failure,Ariz. Riverbed Aggradation Some rivers have beds that are naturally aggrading due to conditions upstream or downstream. Higher riverbed leads to increased flow depth and bridge over-topping. 24
25 Vortices Around Abutments Flood Level Normal Level Flood Channel Wake Vortex Abutment Toe Vortex Downward Flow/Front Vortex Return Flow Main Channel Vortices Around Piers PLAN A Wake Vortex Horseshoe Vortex SECTION A-A A Downward Roller River Out-Flanking Bridge Opening Some rivers continue to meander and migrate in plan view. River may go around (out-flank) the bridge opening, or attack abutment. Q 25
26 Example of River Meander River Widening How can river widening lead to bridge failure???? Widening river should reduce velocity! Widening Out-Flanking Widening leads to decreased velocity. Decreased velocity can lead to sediment deposition (water not fast enough to transport sediment anymore.) Deposition can form point bars. Point bars divert flow towards bank. This causes bank erosion that threatens abutment. 26
27 Widening Leads to Flow Diverted at Abutment Q Depositional Point Bar Abutment Scour Affects Pier Q Abutment Scour Threatened Pier Environmental Concerns Any changes made to the river can cause harm to fish and wildlife. Some fish feed off the bottom sediments of a river. When we change the river characteristics, we change the sediment size on the river bed. If we don t change the river, then nobody can blame us for environmental damage. 27
How To Check For Scour At A Bridge
Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway
More informationSafe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
More informationBRIDGES ARE relatively expensive but often are
Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the
More informationScour and Scour Protection
Design of Maritime Structures Scour and Scour Protection Steven A. Hughes, PhD, PE Coastal and Hydraulics Laboratory US Army Engineer Research and Development Center Waterways Experiment Station 3909 Halls
More informationBRIDGE SCOUR INVESTIGATION: DEVELOPING A SCREENING AND HYDRAULIC VULNERABILITY RATING SYSTEM FOR BRIDGES B.HERON 1 & C.BOWE 2
BRIDGE SCOUR INVESTIGATION: DEVELOPING A SCREENING AND HYDRAULIC VULNERABILITY RATING SYSTEM FOR BRIDGES B.HERON 1 & C.BOWE 2 1 O Connor Sutton Cronin Consulting Engineers, Dublin, Ireland 2 Iarnród Éireann,
More informationHow to Design and Build a Fence/G traverse Bridge or Graffiti Project
Outline Project Location Project Description Project History Site Constraints Geotechnical Investigation & Soil Profile Foundation Design Process Photos Project Location Project Limits: The Grand River
More informationEmergency repair of Bridge B421
Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)
More informationCIVL451. Soil Exploration and Characterization
CIVL451 Soil Exploration and Characterization 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally
More informationState of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
More informationChapter 4 SUBSURFACE INVESTIGATION GUIDELINES
Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES Final SCDOT GEOTECHNICAL DESIGN MANUAL August 2008 Table of Contents Section Page 4.1 Introduction...4-1 4.2 Subsurface Investigation...4-2 4.2.1 Preliminary
More informationMicropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com
More informationCHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES
GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES WATER RESOURCES MANAGEMENT DIVISION Water Investigations
More informationBRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM
BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for
More informationChapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile
Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality
More informationCivil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
More informationGEOTECHNICAL ENGINEERING FORMULAS. A handy reference for use in geotechnical analysis and design
GEOTECHNICAL ENGINEERING FORMULAS A handy reference for use in geotechnical analysis and design TABLE OF CONTENTS Page 1. SOIL CLASSIFICATION...3 1.1 USCS: Unified Soil Classification System...3 1.1.1
More informationInformational Workshop Public Meeting Kanawha Falls Bridge Project
Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal
More informationTable of Contents 16.1 GENERAL... 16.1-1. 16.1.1 Overview... 16.1-1 16.1.2 Responsibilities... 16.1-1
Table of Contents Section Page 16.1 GENERAL... 16.1-1 16.1.1 Overview... 16.1-1 16.1.2 Responsibilities... 16.1-1 16.1.2.1 Geotechnical Section/Bridge Bureau Coordination... 16.1-1 16.1.2.2 Geotechnical
More informationEXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL
EXAMPLE DESIGN OF CANTILEVERED WALL, GRANULAR SOIL A sheet pile wall is required to support a 2 excavation. The soil is uniform as shown in the figure. To take into account the friction between the wall
More informationDesign and Construction of Auger Cast Piles
Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com CONTENTS 1.
More informationANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY
ANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY ANNEX D1: BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN DRA FOR SAFETY D1-1 ANNEX D1 BASIC CONSIDERATIONS
More informationNo allowance will be made for classification of different types of material encountered.
PROJECT : Repair/ Maintenance of Flood Control and Drainage Structures Along Butuan City Cagayan de Oro City Iligan City Road LOCATION : San Antonio, Jasaan, Misamis Oriental SUBJECT : General Notes and
More informationRehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.
Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir Presented By: Doug Stachler, P.E. Project Organization Owner Delaware County Engineers Office Design Consultant CH2M HILL Contractor Double
More informationSPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT
SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT 1.0 SOIL IMPROVEMENT 1.1 General Soil Investigation Information are provided in Part B1 annex as a guide to the Contractor for his consideration
More informationHow To Design A Foundation
The Islamic university - Gaza Faculty of Engineering Civil Engineering Department CHAPTER (2) SITE INVESTIGATION Instructor : Dr. Jehad Hamad Definition The process of determining the layers of natural
More informationHow To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska
APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED
More informationOhio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES
Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 1 PLAN SUBGRADES Geotechnical Bulletin GB1 was jointly developed by the Offices
More informationMoving Small Mountains Vesuvius Dam Rehab
Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,
More informationStream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration
Stream Rehabilitation Concepts, Guidelines and Examples Pierre Y. Julien Wuhan 2005 Objectives Part I - Stream restoration and rehabilitation: 1. Present and discuss important concepts, laws, criteria
More informationCITY UTILITIES DESIGN STANDARDS MANUAL
CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.
More informationCHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE
CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE 9.1 INTRODUCTION An important reason that composite piles have not gained wide acceptance in the civil engineering practice is the lack of a long
More informationEmergency Spillways (Sediment basins)
Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]
More informationDesign, Testing and Automated Monitoring of ACIP Piles in Residual Soils
Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Stephen W. Lacz 1, M. ASCE, P.E. and Richard C. Wells 2, F. ASCE, P.E. 1 Senior Professional, Trigon Kleinfelder, Inc., 313 Gallimore
More informationKWANG SING ENGINEERING PTE LTD
KWANG SING ENGINEERING PTE LTD 1. INTRODUCTION This report represents the soil investigation works at Aljunied Road / Geylang East Central. The objective of the soil investigation is to obtain soil parameters
More informationUSE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch
USE OF MICROPILES IN TEXAS BRIDGES by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch DEFINITION OF A MICROPILE A micropile is a small diameter (typically less than 12 in.), drilled and
More informationValue of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective
Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective FHWA NATIONAL GEOTECHNICAL PROGRAM www.fhwa.dot.gov/engineering/geotech Why Geotechnical Instrumentation? Provide warning
More informationThe unit costs are based on the trend line of the 3 low bids for the average quantity.
Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally
More information2015 ODOT Bridge Design Conference May 12, 2014. DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.
2015 ODOT Bridge Design Conference May 12, 2014 DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement Mary Ann Triska 2015 HDR, all rights reserved. Presentation Outline Project
More informationPrattsville Berm Removal Project. 1.0 Project Location
Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed
More informationRIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.
RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover
More informationTYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR
TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR If you listen to the hype, it sounds like there must be 20 or 30 different types of piers out there. Company A says they have an
More informationWelded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road,
Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road, Wolverhampton, WV6 0PJ Tel 01902 712200 Fax 01902 714096 e-mail sales@hy-tengabions.com
More informationBUTE Department of Construction Management and Technology
BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):
More informationUse and Application of Piezocone Penetration Testing in Presumpscot Formation
Use and Application of Piezocone Penetration Testing in Presumpscot Formation Craig W. Coolidge, P.E. Summit Geoengineering Services, Rockland, Maine ABSTRACT: This paper examines the advantages and limitations
More informationTHE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS
Chapter 11 Slope Stabiliza bilization and Stability of Cuts and Fills THE OBJECTIVES OF ROUTINE ROAD CUTS AND FILLS are 1) to create space for the road template and driving surface; 2) to balance material
More informationNational Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination
Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)
More informationMETHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
More informationTable of Contents. July 2015 12-1
Table of Contents 12.1 General... 3 12.2 Abutment Types... 5 12.2.1 Full-Retaining... 5 12.2.2 Semi-Retaining... 6 12.2.3 Sill... 7 12.2.4 Spill-Through or Open... 7 12.2.5 Pile-Encased... 8 12.2.6 Special
More informationPILE FOUNDATIONS FM 5-134
C H A P T E R 6 PILE FOUNDATIONS Section I. GROUP BEHAVIOR 6-1. Group action. Piles are most effective when combined in groups or clusters. Combining piles in a group complicates analysis since the characteristics
More informationManaging Our Water Retention Systems
Managing Our Water Retention Systems 29th Annual USSD Conference Nashville, Tennessee, April 20-24, 2009 Hosted by Corps of Engineers On the Cover Wolf Creek Dam is on the Cumberland River in South Central
More informationIH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
More informationMinimizes sediment and debris from entering storm drains that lead to waterways and watercourses.
4.5-p DRAIN INLET PROTECTION Alternative Names: DI protection, Drop Inlet Protection DESCRIPTION Storm drain inlet (DI) protection slows and ponds stormwater, and filters sediment and debris before it
More informationTECHNICAL NOTE Lining of Casings with SaniTite HP Pipe
TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TN 5.18 October 2015 In sanitary sewer, it is often necessary to use trenchless technology methods to install a casing pipe under high volume roads,
More informationHigh Capacity Helical Piles Limited Access Projects
High Capacity Helical Piles Limited Access Projects Tel 403 228-1767 Canada, USA, Russia Brendan ODonoghue 519 830-6113 Presentation Summary 1. Helical piles Background on large diameter shafts and helices
More informationCity of Austin Stream Restoration Program Mid-Atlantic Stream Restoration Conference, Rocky Gap, MD November 2011
Welcome City of Austin Stream Restoration Program Mid-Atlantic Stream Restoration Conference, Rocky Gap, MD November 2011 Morgan Byars, P.E. City of Austin Watershed Protection Department Environmental
More informationCONCRETE SEGMENTAL RETAINING WALL SYSTEM
CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Vintage TM unit segmental retaining wall (SRW)
More informationOutlet stabilization structure
Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural
More informationGeotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur
Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur Lecture No. # 13 (Refer Slide Time: 00:18) So last class, it was
More informationGUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No.
GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES Materials Engineering Report No. 2009-8M (Supersedes Report No. 21) F CHOWDHURY GEOMECHANICS AND STRUCTURAL MATERIALS ENGINEER S REHMAN GEOTECHNICAL
More informationPENNDOT 3D MODELING FOR STRUCTURES WORKSHOP. Presented by: Steven Pletcher and Chris Daniels, P.E. October 21, 2014
PENNDOT 3D MODELING FOR STRUCTURES WORKSHOP Presented by: Steven Pletcher and Chris Daniels, P.E. October 21, 2014 Agenda Introduction G.A. & F.C. Wagman History Process used to prepare 3D models Estimating
More informationResidential Foundations and Basements
Residential Foundations and Basements Disclaimer All of the following information is based on the 2006 International Residential Code with Kentucky Amendments. As some information is paraphrased, article
More informationGuo, James C.Y. (2004). Design of Urban Channel Drop Structure, J. of Flood Hazards News, December,
Guo, James C.. (004). esign of Urban Channel rop Structure, J. of Flood azards News, ecember, Guo, James C.., (009) Grade Control for Urban Channel esign, submitted to Elsevier Science, J. of ydro-environmental
More informationDesigned and Engineered to Perform
History EARTH CONTACT PRODUCTS, L.L.C., is a family owned company, based in Olathe, Kansas. This company was built upon Don May s U.S. Patented fourth-generation Steel Piering System that has led to the
More informationChapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
More informationSPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)
Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks
More informationBMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.
BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems
More informationNeversink River East Branch
Neversink River East Branch Management Unit 10 Summary of Post-Flood Recommendations Intervention Level Full restoration of the stream reach including the eroding bank site between Station 38380 and Station
More informationJOHNSON STREET BRIDGE REPLACEMENT PROJECT
JOHNSON STREET BRIDGE REPLACEMENT Victoria, BC GEOTECHNICAL INVESTIGATION REPORT Prepared for: City Hall No. 1 Centennial Square Victoria, BC VW 1P Prepared by: Stantec 7 Dominion Street, Suite 5 Burnaby,
More informationGeotechnical Investigation using Standard Penetration Test (SPT) in Rangamati, Bandarban and Khagrachari Towns
1. Introduction 1.1 Scope of Work The Asian Disaster Preparedness Centre (ADPC) is implementing the project Seismic Hazard and Vulnerability Mapping for Rangamati, Bandarban and Khagrachari Municipality.
More informationNUMERICAL ANALYSIS OF SEEPAGE THROUGH EMBANKMENT DAMS (CASE STUDY: KOCHARY DAM, GOLPAYEGAN)
NUMERICAL ANALYSIS OF SEEPAGE THROUGH EMBANKMENT DAMS (CASE STUDY: KOCHARY DAM, GOLPAYEGAN) *Reza Naghmehkhan Dahande 1 and Ahmad Taheri 2 1 Department of Civil Engineering-Water Management, Islamic Azad
More information2010-2011 Contractor of the Year
U.S. Army Corps of Engineers: Little Calumet River Stage VII Steel Sheet Piling Installation Hammond, Indiana Thatcher worked two rigs concurrently one on the north side and one on the south. The United
More informationThe International Workshop on Micropiles, 2007
MICROPILE FOUNDATION REPAIR AND UNDERPINNING, ARTS AND SCIENCE MUSEUM, UNIVERSITY OF PUERTO RICO, MAYAGUEZ Presented at: International Society of Micropiles (ISM) The International Workshop on Micropiles,
More informationCONCRETE SEGMENTAL RETAINING WALL SYSTEM
CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Classic 8 with PCS unit segmental retaining wall
More informationLand Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
More informationSpecification Guidelines: Allan Block Modular Retaining Wall Systems
Specification Guidelines: Allan Block Modular Retaining Wall Systems The following specifications provide Allan Block Corporation's typical requirements and recommendations. At the engineer of record's
More informationSTORMWATER MANAGEMENT CHECKLIST
STORMWATER MANAGEMENT CHECKLIST *This checklist must be completed and part of the Land Disturbing Permit submittal for review if the acreage disturbed is one (1) acre or more: I. SUPPORTING DATA Narrative
More informationSIENA STONE GRAVITY RETAINING WALL INSTALLATION SPECIFICATIONS. Prepared by Risi Stone Systems Used by permission.
SIENA STONE GRAVITY RETAINING WALL INSTALLATION SPECIFICATIONS Prepared by Risi Stone Systems Used by permission. 1-800-UNILOCK www.unilock.com FOREWORD This outline specification has been prepared for
More informationRole of Underwater Substructure Inspections in Bridge Management
Role of Underwater Substructure Inspections in Bridge Management R. RICHARD AVENT MOHAMED ALAWADY DAVID J. MUKAI Louisiana State University INTRODUCTION In the past, the condition of underwater substructures
More informationThe demand for new roadway
Designing strong walls on weak soils Civil engineers have options to remedy foundation soil problems and meet project cost and schedule requirements. By Fadi Faraj, P.E.; Michael H. Garrison, P.E.; and
More informationEurocode 7 - Geotechnical design - Part 2 Ground investigation and testing
Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering
More informationINDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode
INDIRECT METHODS SOUNDING OR PENETRATION TESTS STANDARD PENETRATION TEST (SPT) Reference can be made to IS 2131 1981 for details on SPT. It is a field edtest to estimate e the penetration e resistance
More informationIndex. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
More informationStorm Drain Inlet Protection
Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective
More informationStrength Determination of "Tooth-Paste" Like Sand and Gravel Washing Fines Using DMT
Strength Determination of "Tooth-Paste" Like Sand and Gravel Washing Fines Using DMT David L. Knott, P.E. and James M. Sheahan, P.E. HDR Engineering, Inc. 3 Gateway Center Pittsburgh, PA 15222-1074 Phone:
More informationWashington 98102-3699, mike.bailey@hartcrowser.com
LESSONS LEARNED FROM A STONE COLUMN TEST PROGRAM IN GLACIAL DEPOSITS Barry S. Chen 1, P.E., Member, Geo-Institute and Michael J. Bailey 2, P.E., Member, Geo-Institute ABSTRACT A stone column test program
More informationAppendix H Dredging and Stream Channel Restoration
Appendix H Dredging and Stream Channel Restoration Mankind s intrusion into the natural environment in West Virginia began in earnest following the Civil War when extractive industries and settlement all
More information2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS
2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the
More informationNumerical Modeling and Simulation of Extreme Flood Inundation to Assess Vulnerability of Transportation Infrastructure Assets
Numerical Modeling and Simulation of Extreme Flood Inundation to Assess Vulnerability of Transportation Infrastructure Assets 2015 University Transportation Center (UTC) Conference for the Southeastern
More informationSection 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
More informationWEATHERING, EROSION, AND DEPOSITION PRACTICE TEST. Which graph best shows the relative stream velocities across the stream from A to B?
NAME DATE WEATHERING, EROSION, AND DEPOSITION PRACTICE TEST 1. The diagram below shows a meandering stream. Measurements of stream velocity were taken along straight line AB. Which graph best shows the
More informationUSE OF GEOSYNTHETICS FOR FILTRATION AND DRAINAGE
USE OF GEOSYNTHETICS FOR FILTRATION AND DRAINAGE Prof. G L Sivakumar Babu Department of Civil Engineering Indian Institute of Science Bangalore 560012 Functions of a Filter Retain particles of the base
More informationCatchment Scale Processes and River Restoration. Dr Jenny Mant Jenny@therrc.co.uk. The River Restoration Centre therrc.co.uk
Catchment Scale Processes and River Restoration Dr Jenny Mant Jenny@therrc.co.uk The River Restoration Centre therrc.co.uk 3 Main Catchment Elements Hydrology Energy associated with the flow of water affects
More informationTable 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection
More informationSite Investigation. Some unsung heroes of Civil Engineering. buried right under your feet. 4. Need good knowledge of the soil conditions
This is an attempt to create a stand alone self learning module on site investigation. Fasten your seat belts. Sit back, relax and enjoy. 1 2 Site Investigation Some unsung heroes of Civil Engineering
More informationThe Basics of Chapter 105 Waterways and Wetlands Permitting in PA
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA April 17, 2013 Goal To develop a basic understanding of PA Department of Environmental Protection (DEP) and US Army Corps of Engineers
More informationTests and Analyses on Shear Strength Increment of Soft Soil under Embankment Fill
Tests and Analyses on Shear Strength Increment of Soft Soil under Embankment Fill Guanbao Ye Professor Key Laboratory of Geotechnical and Underground Engineering,Tongji University, Ministry of Education,
More informationAnalysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina
Analysis of the Interstate 0 Twin Bridge s Collapse During Hurricane Katrina By Genda Chen, Emitt C. Witt III, David Hoffman, Ronaldo Luna, and Adam Sevi The Interstate 0 Twin Span Bridge over Lake Pontchartrain
More informationVacuum Consolidation Dewatering in Sediment Remediation
Vacuum Consolidation Dewatering in Sediment Remediation Anatomy of contaminated sediment volume Vacuum Consolidation Dewatering (VCD) Underwater dewatering for volume reduction. VCD application modes and
More informationAPPENDIX F GEOTECHNICAL REPORT
The City of Winnipeg Bid Opportunity No. 101-2016 Template Version: C420150806 - RW APPENDIX F GEOTECHNICAL REPORT AECOM 99 Commerce Drive 204 477 5381 tel Winnipeg, MB, Canada R3P 0Y7 204 284 2040 fax
More informationREAL-TIME SLOPE AND WALL MONITORING AND REPORTING USING 3-D MEMS-BASED, IN-PLACE INCLINOMETER SYSTEM
REAL-TIME SLOPE AND WALL MONITORING AND REPORTING USING 3-D MEMS-BASED, IN-PLACE INCLINOMETER SYSTEM Aaron J. Muck, P.E., M.ASCE Swaminathan Srinivasan (Vasan), P.E., M.ASCE H.C. Nutting/Terracon Monitored
More information