MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS
|
|
- Dominick Lamb
- 7 years ago
- Views:
Transcription
1 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the available lowest 2006, 2007, and 2008 bids for each MassHighway project. Please note that data is not available for every item because many items were not used during this timeframe. Please check the Weighted Average Bid Application, available via the MassHighway website, for the latest unit price data. In cases where unit price data is not available, it is recommended that a unit price be estimated using the available data for the next closest size member. It is important to recognize the necessity of varying the Office Estimate unit prices based on the quantity of the item in question. Since the MassHighway Capital Expenditure Program Office (CEPO) determines funding requirements for projects based on the Office Estimates, it is vital that the office estimate be as accurate as possible and in line with the actual contractor bids. Therefore, the goal shall be to use unit prices that will place the office estimate into the middle third of the bid "pack". This is generally accomplished by adjusting the weighted average unit prices based on the quantity of a particular item. Generally speaking, the larger the quantity of an item the cheaper it will be on a per unit basis. However, there is no hard and fast rule on how to apply this. The adjustment of unit prices is based on experience and judgement. It is better to over estimate (marginally) the unit price of an item than to under estimate it. Some assistance in estimating unit prices for structural items may be found in the representive graphs of the unit costs of main members, reinforcing steel, concrete items, prestressed concrete beams and structural steel. Of note is the number of projects listed for each item. The larger the number of projects the more reflective the average prices will be of the cost of the work. Also, unit price data that indicates an apparent reduction of a unit price over time is more likely an indicator of less complicated work or economies of scale. DEMOLITION OF SUPERSTRUCTURE Demolition of Superstructure is to be listed in the Office Estimate on a Lump Sum basis. Estimate the cost based on the total deck area in square yards of existing superstructure intended to be demolished. (reference charts for Estimating Cost). BRIDGE STRUCTURE LUMP SUM ITEM In general, the Bridge Structure Lump Sum Item is used to pay the Contractor a fixed price for the work done and no measurement of final pay quantity is required. However, the Bridge Structure Lump Sum Item can only be used for those elements of the structure for which the scope of work, the methods of construction, and the type and quantity of materials to be furnished are accurately defined on the plans and/or in the special provisions. All other items must utilize a Unit Price basis of payment since the Contractor's bid is based on estimated quantities that may vary considerably from the actual quantities required during construction. The breakdown of the Bridge Structure Lump Sum Item shall be provided in the Special Provisions and shall specify for each component part the sub-item number, the sub-item name, the quantity of each sub-item, and the unit of each sub-item quantity. The sub-item numbering, naming, and quantity unit convention shall match that used in the latest Standard Nomenclature as specified herein. Please refer to the sample provided on the next page. Guidelines 1 OF 31
2 GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS 10/16/2008 SCHEDULE OF BASIS FOR PARTIAL PAYMENT Within ten (10) days after the award of the Contract, the Contractor shall submit, in duplicate, for the approval of the Engineer, a schedule of unit prices for the major components of the bridge structure as listed below. The bridge structure Lump Sum breakdown quantities provided below are estimated and not guaranteed. The total of all partial payments to the Contractor shall equal the Lump Sum contract price regardless of the accuracy of the quantities furnished by the Engineer for the individual bridge components. The cost of labor and materials for any Item not listed but required to complete the work shall be considered incidental to Item and no further compensation will be allowed. SUB-ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL STEEL REINFORCEMENT FOR STRUCTURES 122,000 LB - COATED LAM. ELASTOMERIC BEARING W/O ANCHOR 13 EA - BOLTS ( K) PRESTRESSED CONCRETE BULB TEE 397 LF - BEAMS (NEBT 1400) STEEL M270 GRADE 36 GALVANIZED 2795 LB - MISCELLANEOUS 970. BITUMINOUS DAMP-PROOFING 228 SY 971. ASPHALTIC BRIDGE JOINT SYSTEM 59 LF PROTECTIVE SCREEN TYPE II 437 LF TOTAL COST OF ITEM = The above schedule applies only to the Bridge Structure No. A (BIN). Payment for similar materials and construction at locations other than at this bridge structure shall not be included under this Item. Sub-Item numbering is presented for information only in coordination with MassHighway Standard Nomenclature. Guidelines 2 OF 31
3 WEIGHTED AVERAGE UNIT PRICES TAKEN FROM STATEWIDE WEIGHTED AVERAGE BID PRICES AND BRIDGE STRUCTURE LUMP SUM BREAKDOWNS ITEM NO. UNITS TOTAL QUANTITY NO PROJECTS AVG. BID PRICE 2006 AVG. BID PRICE DEMOLITION OF SUPERSTRUCTURE OF BRIDGE LS SEE CHARTS FOR ESTIMATING COST NO REINFORCED CONCRETE EXCAVATION CY 1,121 5 $ BRIDGE EXCAVATION CY 54, $21.43 $ BRIDGE EXCAVATION WITHIN COFFERDAM CY $ CHANNEL EXCAVATION CY 12, $ CLASS B ROCK EXCAVATION CY $ $ GRAVEL BORROW FOR BRIDGE FOUNDATION CY $34.66 $ GRAVEL BORROW FOR BACKFILLING STRUCTURES AND PIPES CY $23.79 CRUSHED STONE FOR DRAIN., REVET AND/OR W. WORKS 156. TON 10 1 $60.00 FOUNDATIONS CRUSHED STONE FOR BRIDGE FOUNDATIONS TON $ CRUSHED STONE FOR INTEGRAL ABUTMENT PILES TON $ HOT MIX ASPHALT TON $79.38 $ HOT MIX ASPHALT DENSE BINDER COURSE FOR BRIDGES TON $89.94 $ PSI, 1.5 IN., 565 CEMENT CONCRETE CY PSI, 3/4 IN., 610 CEMENT CONCRETE CY PSI, 3/4 IN., 685 HP CEMENT CONCRETE CY PSI, 3/4 IN., 585 HP CEMENT CONCRETE CY PSI, 3/8 IN, 710 HP CEMENT CONCRETE CY SEE CHARTS FOR ESTIMATING COST SEE CHARTS FOR ESTIMATING COST SEE CHARTS FOR ESTIMATING COST SEE CHARTS FOR ESTIMATING COST SEE CHARTS FOR ESTIMATING COST CEMENT CONCRETE FORM LINER - FRACTURED FIN SY 0 $ UNDERWATER FOUNDATION INSPECTION UD 0 0 $ STEEL REINFORCEMENT FOR STRUCTURES - COATED LB 14,780, $ DRILLED AND CHEMICAL ANCHORED #5 DOWELS EA 0 0 $0.00 $ ARCH FRAME UNIT (4 FT. OR LESS WIDE - 20 TO FT. ARCH FRAME UNIT (4.01 TO 5 FT. WIDE - 20 TO FT. ARCH FRAME UNIT (5.01 TO 6 FT. WIDE - 20 TO FT. ARCH FRAME UNIT (OVER 6 FT. WIDE - 20 TO FT. ARCH FRAME UNIT (4 FT. OR LRSS WIDE - 25 TO FT. ARCH FRAME UNIT (4.01 TO 5 FT. WIDE - 25 TO FT. ARCH FRAME UNIT (5.01 TO 6 FT. WIDE - 25 TO FT. ARCH FRAME UNIT (OVER 6 FT. WIDE - 25 TO FT. ARCH FRAME UNIT (4 FT. OR LESS WIDE - 30 TO FT. ARCH FRAME UNIT (4.01 TO 5 FT. WIDE - 30 TO FT. EA 6 1 $32, $195, *Items are non-standard Avg. Contract Unit Prices 3 OF 31
4 WEIGHTED AVERAGE UNIT PRICES TAKEN FROM STATEWIDE WEIGHTED AVERAGE BID PRICES AND BRIDGE STRUCTURE LUMP SUM BREAKDOWNS ITEM NO ARCH FRAME UNIT (5.01 TO 6 FT. WIDE - 30 TO FT. ARCH FRAME UNIT (OVER 6 FT. WIDE - 30 TO FT. ARCH FRAME UNIT (4 FT. OR LESS WIDE - 35 TO FT. ARCH FRAME UNIT (4.01 TO 5 FT. WIDE - 35 TO FT. ARCH FRAME UNIT (5.01 TO 6 FT. WIDE - 35 TO FT. ARCH FRAME UNIT (OVER 6 FT. WIDE - 35 TO FT. ARCH FRAME UNIT (4 FT. OR LESS WIDE - 40 TO FT. ARCH FRAME UNIT (4.01 TO 5 FT. WIDE - 40 TO FT. ARCH FRAME UNIT (5.01 TO 6 FT. WIDE - 40 TO FT. UNITS TOTAL QUANTITY NO PROJECTS AVG. BID PRICE 2006 AVG. BID PRICE ARCH FRAME UNIT (OVER 6 FT. WIDE - 40 TO FT ARCH FRAME UNIT (4 FT. OR LESS WIDE - 45 TO FT. ARCH FRAME UNIT (4.01 TO 5 FT. WIDE - 45 TO FT. ARCH FRAME UNIT (5.01 TO 6 FT. WIDE - 45 TO FT ARCH FRAME UNIT (OVER 6 FT. WIDE - 45 TO FT ARCH FRAME UNIT (4 FT. OR LESS WIDE - 50 TO FT. ARCH FRAME UNIT (4.01 TO 5 FT. WIDE - 50 TO FT. ARCH FRAME UNIT (5.01 TO 6 FT. WIDE - 50 TO FT ARCH FRAME UNIT (OVER 6 FT. WIDE - 50 TO FT ARCH FRAME UNIT (4 FT. OR LESS WIDE - 55 TO FT. ARCH FRAME UNIT (4.01 TO 5 FT. WIDE - 55 TO FT. ARCH FRAME UNIT (5.01 TO 6 FT. WIDE - 55 TO FT ARCH FRAME UNIT (OVER 6 FT. WIDE - 55 TO FT ARCH FRAME UNIT (4 FT. OR LESS WIDE - 60 OR MORE FT. ARCH FRAME UNIT (4.01 TO 5 FT. OR LESS WIDE - 60 OR MORE FT. ARCH FRAME UNIT (5.01 TO 6 FT. OR LESS WIDE - 60 OR MORE FT ARCH FRAME UNIT (OVER 6 FT. OR LESS WIDE - 60 OR MORE FT PRECAST CONCRETE CULVERT (4 FT. SPAN - 2 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (4 FT. SPAN - 3 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (4 FT. SPAN - 4 FT. HEIGHT) F 0 0 $0.00 *Items are non-standard Avg. Contract Unit Prices 4 OF 31
5 WEIGHTED AVERAGE UNIT PRICES TAKEN FROM STATEWIDE WEIGHTED AVERAGE BID PRICES AND BRIDGE STRUCTURE LUMP SUM BREAKDOWNS ITEM NO. UNITS TOTAL QUANTITY NO PROJECTS AVG. BID PRICE 2006 AVG. BID PRICE PRECAST CONCRETE CULVERT (4 FT. SPAN - 5 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (4 FT. SPAN - 6 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (5 FT. SPAN - 2 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (5 FT. SPAN - 3 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (5 FT. SPAN - 4 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (5 FT. SPAN - 5 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (5 FT. SPAN - 6 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (6 FT. SPAN - 3 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (6 FT. SPAN - 4 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (6 FT. SPAN - 5 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (6 FT. SPAN - 6 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (7 FT. SPAN - 3 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (7 FT. SPAN - 4 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (7 FT. SPAN - 5 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (7 FT. SPAN - 6 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (7 FT. SPAN - 7 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (8 FT. SPAN - 4 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (8 FT. SPAN - 5 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (8 FT. SPAN - 6 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (8 FT. SPAN - 7 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (8 FT. SPAN - 8 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (10 FT. SPAN - 5 FT. HEIGHT) F 42 1 $1, PRECAST CONCRETE CULVERT (10 FT. SPAN - 6 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (10 FT. SPAN - 7 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (10 FT. SPAN - 8 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (10 FT. SPAN - 9 FT. HEIGHT) F 0 0 $ PRECAST CONCRETE CULVERT (10 FT. SPAN - 10 FT. HEIGHT) F 77 1 $1, PLAIN ELASTOMERIC BEARING EA 77 4 $ LAM. ELASTOMERIC BEARING W/ ANCHOR BOLTS (0 TO 50K) LAM. ELASTOMERIC BEARING W/ ANCHOR BOLTS (51 TO 100K) LAM. ELASTOMERIC BEARING W/ ANCHOR BOLTS (101 TO 150K) LAM. ELASTOMERIC BEARING W/ANCHOR BOLTS (151 TO 200K) LAM. ELASTOMERIC BEARING W/ANCHOR BOLTS (OVER 200K) LAM. ELASTOMERIC BEARING W/O ANCHOR BOLTS (0 TO 50K) EA 32 1 $2, EA 32 1 $4, EA 47 3 $ *Items are non-standard Avg. Contract Unit Prices 5 OF 31
6 ITEM NO. UNITS TOTAL QUANTITY NO PROJECTS AVG. BID PRICE /16/2008 WEIGHTED AVERAGE UNIT PRICES TAKEN FROM STATEWIDE WEIGHTED AVERAGE BID PRICES AND BRIDGE STRUCTURE LUMP SUM BREAKDOWNS LAM. ELASTOMERIC BEARING W/O ANCHOR BOLTS (51 TO 100K) LAM. ELASTOMERIC BEARING W/O ANCHOR BOLTS (101 TO 150K) LAM. ELASTOMERIC BEARING W/O ANCHOR BOLTS (151 TO 200K) LAM. ELASTOMERIC BEARING W/O ANCHOR BOLTS (OVER 200K) LAM. SLIDING ELASTOMERIC BEARING W/ ANCHOR BOLTS (0 TO 50K) LAM. SLIDING ELASTOMERIC BEARING W/ ANCHOR BOLTS (51 TO 100K) LAM. SLIDING ELASTOMERIC BEARING W/ ANCHOR BOLTS (101 TO 150K) LAM. SLIDING ELASTOMERIC BEARING W/ ANCHOR BOLTS (151 TO 200K) LAM. SLIDING ELASTOMERIC BEARING W/ ANCHOR BOLTS (OVER 200K) LAM. SLIDING ELASTOMERIC BEARING W/O ANCHOR BOLTS (0 TO 50K) LAM. SLIDING ELASTOMERIC BEARING W/O ANCHOR BOLTS (51 TO 100K) LAM. SLIDING ELASTOMERIC BEARING W/O ANCHOR BOLTS (101 TO 150K) LAM. SLIDING ELASTOMERIC BEARING W/O ANCHOR BOLTS (151 TO 200K) AVG. BID PRICE EA $ EA $ EA 58 4 $1, EA 34 1 $ EA 12 1 $ LAM. SLIDING ELASTOMERIC BEARING W/O ANCHOR BOLTS (OVER 200K) HIGH LOAD MULTI ROTATIONAL BEARING (0-500K) EA 50 6 $9, HIGH LOAD MULTI ROTATIONAL BEARING ( K) EA $8, HIGH LOAD MULTI ROTATIONAL BEARING ( K) EA 21 1 $8, HIGH LOAD MULTI ROTATIONAL BEARING ( K) EA 0 0 $ HIGH LOAD MULTI ROTATIONAL BEARING (>2000K) EA 0 0 $ XXX PRESTRESSED CONCRETE XXX BEAMS F SEE CHARTS FOR ESTIMATING COST 940. UNTREATED TIMBER PILES F 0 0 $ TREATED TIMBER PILES F 0 0 $ STEEL PILE HP 10 X 42 F 0 0 $0.00 $ STEEL PILE HP 10 X 57 F $ $ STEEL PILE HP 12 X 53 F 11,600 1 $ STEEL PILE HP 12 X 63 F 0 0 $ STEEL PILE HP 12 X 74 F 7,041 4 $ $ STEEL PILE HP 12 X 84 F 2,700 1 $ STEEL PILE HP 14 X 73 F 14,252 2 $ $ STEEL PILE HP 14 X 89 F 7,130 2 $ STEEL PILE HP 14 X 102 F 1,329 1 $ STEEL PILE HP 14 X 117 F 0 0 $ STEEL PIPE PILE 8-5/8 INCH OUTSIDE DIAMETER F 0 0 $0.00 *Items are non-standard Avg. Contract Unit Prices 6 OF 31
7 WEIGHTED AVERAGE UNIT PRICES TAKEN FROM STATEWIDE WEIGHTED AVERAGE BID PRICES AND BRIDGE STRUCTURE LUMP SUM BREAKDOWNS ITEM NO. UNITS TOTAL QUANTITY NO PROJECTS AVG. BID PRICE 2006 AVG. BID PRICE STEEL PIPE PILE 10 INCH OUTSIDE DIAMETER F 0 0 $ STEEL PIPE PILE 10-3/4 INCH OUTSIDE DIAMETER F 0 0 $ STEEL PIPE PILE 12 INCH OUTSIDE DIAMETER F 0 0 $ STEEL PIPE PILE 12-3/4 INCH OUTSIDE DIAMETER F 0 0 $ STEEL PIPE PILE 14 INCH OUTSIDE DIAMETER F 196,000 1 $ STEEL PIPE PILE 16 INCH OUTSIDE DIAMETER F 77,600 1 $ PRE-DRILLING FOR PILES F $ DRILLED ROCK SOCKET FOR PILES F 0 0 $ DRILLED SHAFT EXCAVATION 2.0 FEET DIAMETER F 1,286 2 $ DRILLED SHAFT EXCAVATION 3.0 FEET DIAMETER F $1, $ DRILLED SHAFT EXCAVATION 3.5 FEET DIAMETER F $ DRILLED SHAFT EXCAVATION 4.0 FEET DIAMETER F 2,657 6 $ $ DRILLED SHAFT EXCAVATION 4.5 FEET DIAMETER F 75 1 $ $ DRILLED SHAFT EXCAVATION 5 FEET DIAMETER F $ DRILLED SHAFT EXCAVATION 5.5 FEET DIAMETER F 0 0 $ DRILLED SHAFT EXCAVATION 6.0 FEET DIAMETER F 89 1 $ DRILLED SHAFT EXCAVATION 6.5 FEET DIAMETER F DRILLED SHAFT EXCAVATION 7.0 FEET DIAMETER F DRILLED SHAFT EXCAVATION 7.5 FEET DIAMETER F DRILLED SHAFT EXCAVATION 8.0 FEET DIAMETER F DRILLED SHAFT EXCAVATION 8.5 FEET DIAMETER F DRILLED SHAFT EXCAVATION 9.0 FEET DIAMETER F ROCK SOCKET EXCAVATION 2.0 FEET DIAMETER F $1, ROCK SOCKET EXCAVATION 3.0 FEET DIAMETER F $ $3, ROCK SOCKET EXCAVATION 3.5 FEET DIAMETER F 52 1 $1, ROCK SOCKET EXCAVATION 4.0 FEET DIAMETER F $1, $4, ROCK SOCKET EXCAVATION 4.5 FEET DIAMETER F 3,836 1 $2, ROCK SOCKET EXCAVATION 5.0 FEET DIAMETER F $2, ROCK SOCKET EXCAVATION 5.5 FEET DIAMETER F ROCK SOCKET EXCAVATION 6.0 FEET DIAMETER F ROCK SOCKET EXCAVATION 6.5 FEET DIAMETER F ROCK SOCKET EXCAVATION 7.0 FEET DIAMETER F ROCK SOCKET EXCAVATION 7.5 FEET DIAMETER F ROCK SOCKET EXCAVATION 8.0 FEET DIAMETER F ROCK SOCKET EXCAVATION 8.5 FEET DIAMETER F ROCK SOCKET EXCAVATION 9.0 FEET DIAMETER F OBSTRUCTION EXCAVATION 2.0 FEET DIAMETER F 95 1 $1, OBSTRUCTION EXCAVATION 3.0 FEET DIAMETER F $1, $2, OBSTRUCTION EXCAVATION 3.5 FEET DIAMETER F 56 2 $ *Items are non-standard Avg. Contract Unit Prices 7 OF 31
8 WEIGHTED AVERAGE UNIT PRICES TAKEN FROM STATEWIDE WEIGHTED AVERAGE BID PRICES AND BRIDGE STRUCTURE LUMP SUM BREAKDOWNS ITEM NO. UNITS TOTAL QUANTITY NO PROJECTS AVG. BID PRICE 2006 AVG. BID PRICE OBSTRUCTION EXCAVATION 4.0 FEET DIAMETER F $1, $2, OBSTRUCTION EXCAVATION 4.5 FEET DIAMETER F $ $2, OBSTRUCTION EXCAVATION 5.0 FEET DIAMETER F $1, $ OBSTRUCTION EXCAVATION 5.5 FEET DIAMETER F OBSTRUCTION EXCAVATION 6.0 FEET DIAMETER F OBSTRUCTION EXCAVATION 6.5 FEET DIAMETER F OBSTRUCTION EXCAVATION 7.0 FEET DIAMETER F OBSTRUCTION EXCAVATION 7.5 FEET DIAMETER F OBSTRUCTION EXCAVATION 8.0 FEET DIAMETER F OSTRUCTION EXCAVATION 8.5 FEET DIAMETER F OSTRUCTION EXCAVATION 9.0 FEET DIAMETER F TRIAL SHAFT 2.0 FEET DIAMETER F TRIAL SHAFT 3.0 FEET DIAMETER F TRIAL SHAFT 3.5 FEET DIAMETER F TRIAL SHAFT 4.0 FEET DIAMETER F $2, $1, TRIAL SHAFT 4.5 FEET DIAMETER F TRIAL SHAFT 5.0 FEET DIAMETER F TRIAL SHAFT 5.5 FEET DIAMETER F TRIAL SHAFT 6.0 FEET DIAMETER F TRIAL SHAFT 6.5 FEET DIAMETER F TRIAL SHAFT 7.0 FEET DIAMETER F * TRIAL SHAFT 7.5 FEET DIAMETER F TRIAL SHAFT 8.0 FEET DIAMETER F TRIAL SHAFT 8.5 FEET DIAMETER F TRIAL SHAFT 9.0 FEET DIAMETER F DRILLED SHAFT 2.0 FEET DIAMETER F 1,378 1 $ DRILLED SHAFT 3.0 FEET DIAMETER F 1,287 3 $ $ DRILLED SHAFT 3.5 FEET DIAMETER F $ DRILLED SHAFT 4.0 FEET DIAMETER F 4,114 7 $ $ DRILLED SHAFT 4.5 FEET DIAMETER F 1,215 2 $ $ DRILLED SHAFT 5.0 FEET DIAMETER F 13,618 2 $ $ DRILLED SHAFT 5.5 FEET DIAMETER F DRILLED SHAFT 6.0 FEET DIAMETER F 88 1 $1, DRILLED SHAFT 6.5 FEET DIAMETER F DRILLED SHAFT 7.0 FEET DIAMETER F DRILLED SHAFT 7.5 FEET DIAMETER F DRILLED SHAFT 8.0 FEET DIAMETER F DRILLED SHAFT 8.5 FEET DIAMETER F DRILLED SHAFT 9.0 FEET DIAMETER F 0 0 *Items are non-standard Avg. Contract Unit Prices 8 OF 31
9 WEIGHTED AVERAGE UNIT PRICES TAKEN FROM STATEWIDE WEIGHTED AVERAGE BID PRICES AND BRIDGE STRUCTURE LUMP SUM BREAKDOWNS ITEM NO. UNITS TOTAL QUANTITY NO PROJECTS AVG. BID PRICE 2006 AVG. BID PRICE PERMANENT CASING 2.0 FEET DIAMETER F 0 0 $ PERMANENT CASING 3.0 FEET DIAMETER F $ PERMANENT CASING 3.5 FEET DIAMETER F $ PERMANENT CASING 4.0 FEET DIAMETER F $ PERMANENT CASING 4.5 FEET DIAMETER F $ $ PERMANENT CASING 5.0 FEET DIAMETER F $ PERMANENT CASING 5.5 FEET DIAMETER F PERMANENT CASING 6.0 FEET DIAMETER F PERMANENT CASING 6.5 FEET DIAMETER F PERMANENT CASING 7.0 FEET DIAMETER F * PERMANENT CASING 7.5 FEET DIAMETER F PERMANENT CASING 8.0 FEET DIAMETER F PERMANENT CASING 8.5 FEET DIAMETER F PERMANENT CASING 9.0 FEET DIAMETER F CROSS HOLE SONIC TESTING ACCESS PIPES F 74, $6.51 $ CROSS HOLE SONIC TEST EA $ $1, OSTERBERG LOAD CELL AXIAL LOAD TEST EA 15 3 $220, $126, CONVENTIONAL AXIAL LOAD TEST EA 1 1 $57, PRECAST-PRESTRESSED CONC. PILE (12 IN.) F PRECAST-PRESTRESSED CONC. PILE (14 IN.) F 0 0 $ PRECAST-PRESTRESSED CONC. PILE (16 IN.) F 0 0 $ PRECAST-PRESTRESSED CONC. PILE (18 IN.) F 0 0 $ PRECAST-PRESTRESSED CONC. PILE (20 IN.) F 0 0 $ TEST PILE F 0 0 $ TIMBER TEST PILE EA 0 0 $ SHORT DURATION LOAD TEST EA 0 0 $ MAINTAINED LOAD TEST EA 2 1 $192, QUICK LOAD TEST EA 0 0 $ STATIC - CYCLIC (EXPRESS) LOAD TEST EA 2 1 $15, DYNAMIC LOAD TEST PREPARATION EA 6 2 $ DYNAMIC LOAD TEST BY CONTRACTOR EA $3, $3, PILE SHOES EA $ STEEL SHEETING LB 948,536 4 $ PERMANENT STEEL SHEETING SY 0 0 $ TEMPORARY STEEL SHEETING SY $ INTERIM STEEL SHEETING SY 0 0 $ EXCAVATION SUPPORT SYSTEM SY 0 0 $ COFFERDAM EA 0 0 $ TEMPORARY WATERWAY DIVERSION STRUCTURE EA 0 0 $0.00 *Items are non-standard Avg. Contract Unit Prices 9 OF 31
10 WEIGHTED AVERAGE UNIT PRICES TAKEN FROM STATEWIDE WEIGHTED AVERAGE BID PRICES AND BRIDGE STRUCTURE LUMP SUM BREAKDOWNS ITEM NO. UNITS TOTAL QUANTITY NO PROJECTS AVG. BID PRICE 2006 AVG. BID PRICE MSE WALL - NO COLOR - PLAIN SURFACE SY 1,133 5 $1, MSE WALL - NO COLOR - FORM LINER SURFACE SY 0 0 $ MSE WALL - INTEGRAL COLOR - PLAIN SURFACE SY 0 0 $ MSE WALL - INTEGRAL COLOR - FORM LINER SURFACE SY 0 0 $ STRUCTURAL STEEL M270 GRADE 36 PAINTED- MISCELLANEOUS STRUCTURAL STEEL M270 GRADE 36 GALVANIZED- MISCELLANEOUS LB SEE CHARTS FOR ESTIMATING COST STEEL M270 GRADE 50W UNCOATED ROLLED BEAM BRIDGE LB SEE CHARTS FOR ESTIMATING COST STEEL M270 GRADE 50W UNCOATED PLATE GIRDER BRIDGE LB SEE CHARTS FOR ESTIMATING COST STEEL M270 GRADE 50W UNCOATED BOX GIRDER BRIDGE STEEL M270 GRADE 50W UNCOATED TRUSS BRIDGE STEEL M270 GRADE 50W UNCOATED BASCULE STEEL M270 GRADE 50 PAINTED ROLLED BEAM BRIDGE STEEL M270 GRADE 50 PAINTED PLATE GIRDER BRIDGE STEEL M270 GR 50 PAINTED BOX GIRDER BRIDGE LB SEE CHARTS FOR ESTIMATING COST STEEL M270 GR 50 PAINTED TRUSS BRIDGE STEEL 270 GRADE 50 PAINTED BASCULE LB SEE CHARTS FOR ESTIMATING COST STEEL 270 GRADE 50 GALVANIZED ROLLED BEAM BRIDGE STEEL 270 GRADE 50 GALVANIZED PLATE GIRDER BRIDGE STEEL 270 GRADE 50 GALVANIZED BOX GIRDER BRIDGE STEEL 270 GRADE 50 GALVANIZED TRUSS BRIDGE STEEL 270 GRADE 50 GALVANIZED BASCULE STEEL 270 GRADE 50 GALVANIZED PAINTED ROLLED BEAM BRIDGE STEEL 270 GRADE 50 GALVANIZED PAINTED PLATE GIRDER BRIDGE STEEL 270 GRADE 50 GALVANIZED PAINTED BOX GIRDER BRIDGE STEEL 270 GRADE 50 GALVANIZED PAINTED TRUSS BRIDGE STEEL 270 GRADE 50 GALVANIZED PAINTED BASCULE STEEL 270 GRADE HPS50W UNCOATED ROLLED BEAM BRIDGE STEEL 270 GRADE HPS50W UNCOATED PLATE GIRDER BRIDGE STEEL 270 GRADE HPS50W UNCOATED BOX GIRDER BRIDGE STEEL 270 GRADE HPS50W UNCOATED TRUSS BRIDGE STEEL 270 GRADE HPS50W UNCOATED BASCULE BRIDGE STEEL 270 GRADE HPS50W PAINTED ROLLED BEAM BRIDGE STEEL 270 GRADE HPS50W PAINTED PLATE GIRDER BRIDGE STEEL 270 GRADE HPS50W PAINTED BOX GIRDER BRIDGE *Items are non-standard Avg. Contract Unit Prices 10 OF 31
11 WEIGHTED AVERAGE UNIT PRICES TAKEN FROM STATEWIDE WEIGHTED AVERAGE BID PRICES AND BRIDGE STRUCTURE LUMP SUM BREAKDOWNS ITEM NO. UNITS TOTAL QUANTITY NO PROJECTS AVG. BID PRICE 2006 AVG. BID PRICE STEEL 270 GRADE HPS50W PAINTED TRUSS BRIDGE STEEL 270 GRADE HPS50W PAINTED BASCULE BRIDGE STEEL 270 GRADE HPS50W AND 70W UNCOATED ROLLED BEAM BRIDGE STEEL 270 GRADE HPS50W AND 70W UNCOATED PLATE GIRDER BRIDGE STEEL 270 GRADE HPS50W AND 70W UNCOATED BOX GIRDER BRIDGE STEEL 270 GRADE HPS50W AND 70W UNCOATED TRUSS BRIDGE STEEL 270 GRADE HPS50W AND 70W UNCOATED BASCULE BRIDGE STEEL 270 GRADE HPS50W AND 70W PAINTED ROLLED BEAM BRIDGE STEEL 270 GRADE HPS50W AND 70W PAINTED PLATE GIRDER BRIDGE STEEL 270 GRADE HPS50W AND 70W PAINTED BOX GIRDER BRIDGE STEEL 270 GRADE HPS50W AND 70W PAINTED TRUSS BRIDGE STEEL 270 GRADE HPS50W AND 70W PAINTED BASCULE BRIDGE STUD SHEAR CONNECTORS EA 85, $ MEMBRANE WATERPROOFING FOR BRIDGE DECKS SY 143, $18.88 $ MEMBRANE WATERPROOFING (RUBBERIZED ASPHALT) SY 0 0 $ MEMBRANE WATERPROOFING FOR BRIDGE DECKS - SPRAY APPLIED SY $ WATERPROOFING PROTECTIVE COURSE SY 1, $45.83 $ MEMBRANE WATERPROOFING SY 3,132 5 $ SCUPPER EA 28 2 $4, SCUPPER AND DOWNSPOUT 970. BITUMINOUS DAMP-PROOFING SY 10, $8.95 $ ASPHALTIC BRIDGE JOINT SYSTEM F $ $ STRIP SEAL BRIDGE JOINT SYSTEM F 1,442 9 $ FINGER PLATE BRIDGE JOINT SYSTEM F $2, MODULAR BRIDGE JOINT SYSTEM F $1, METAL BRIDGE RAILING (3 RAIL), STEEL (TYPE S3-TL4) F 9,168 9 $ $ PROTECTIVE SCREEN TYPE I F $ PROTECTIVE SCREEN TYPE II F $ ALUMINUM HANDRAIL F $ PROTECTIVE SCREEN ELECTRIFICATION BARRIER F 0 0 $ TEMPORARY CONCRETE BRIDGE BARRIER F 1,660 4 $ TEMPORARY CONCRETE BRIDGE BARRIER REMOVE AND RESET F $ DUMPED RIPRAP TON 5,907 5 $ RIPRAP TON $47.21 *Items are non-standard Avg. Contract Unit Prices 11 OF 31
12 WEIGHTED AVERAGE UNIT PRICES TAKEN FROM STATEWIDE WEIGHTED AVERAGE BID PRICES AND BRIDGE STRUCTURE LUMP SUM BREAKDOWNS ITEM NO. UNITS TOTAL QUANTITY NO PROJECTS AVG. BID PRICE 2006 AVG. BID PRICE ROCK FILL TON 69 1 $ MODIFIED ROCKFILL TON 12,655 1 $ CHANNEL PAVING SY $ CONTROL OF WATER - STRUCTURE NO. LS 1 6 $36, *Items are non-standard Avg. Contract Unit Prices 12 OF 31
13 $2, ITEM VARIATION OF DEMOLITION COST Plotted by Number of Stages $2, Single Stage $2, Two Stages $1, Three or More Stages $ per Square Yard $1, $1, $1, $ $ $ $ ,000 1,200 1,400 1,600 1,800 Square Yards of Deck Area Demo - Item OF 31
14 $ VARIATION OF PRESRESSED CONCRETE DECK BEAM COST Per Linear Foot vs. Total Quantity S36-12 S36-15 $ $ S36-18 S36-21 $ per Linear Foot $ $ $50.00 $ ,000 Total Linear Feet Deck Beams (36") 14 OF 31
15 $1, VARIATION OF PRESRESSED CONCRETE DECK BEAM COST Per Linear Foot vs. Total Quantity $1, S48-12 S48-15 $1, $ S48-18 S48-21 $ per Linear Foot $ $ $ $ $ $ $ ,000 1,200 Total Linear Feet Deck Beams (48") 15 OF 31
16 VARIATION OF PRESTRESSED CONCRETE BOX BEAM COST Per Linear Foot vs. Total Quantity $ per Linear Foot $ $ $ $ $ $ B36-24 B36-27 B36-30 B36-33 B36-36 B36-39 B36-42 B36-45 B36-48 $ $ $ ,000 1,200 Total Linear Feet Box Beams (36") 16 OF 31
17 VARIATION OF PRESTRESSED CONCRETE BOX BEAM COST Per Linear Foot vs. Total Quantity $1, $ $ $ $ per Linear Foot $ $ $ $ $ $ B48-24 B48-27 B48-30 B48-33 B48-36 B48-39 B48-42 B48-48 $ ,000 1,250 1,500 1,750 2,000 Total Linear Feet Box Beams (48") 17 OF 31
18 VARIATION OF HP PRESTRESSED CONCRETE BOX BEAM COST Per Linear Foot vs. Total Quantity $ per Linear Foot $ $ $ $ $ $ HP B36-24 HP B36-27 HP B36-30 HP B36-33 HP B36-36 HP B36-39 HP B36-42 HP B36-45 HP B36-48 $ $ $ ,000 1,250 1,500 1,750 2,000 Total Linear Feet HP Box Beams (36") 18 OF 31
19 $ per Linear Foot $ $ $ $ $ $ VARIATION OF HP PRESTRESSED CONCRETE BOX BEAM COST Per Linear Foot vs. Total Quantity HP B48-24 HP B48-27 HP B48-30 HP B48-33 HP B48-36 HP B48-39 HP B48-42 HP B48-45 HP B48-48 $ $ $ ,000 1,250 1,500 1,750 2,000 Total Linear Feet HP Box Beams (48") 19 OF 31
20 VARIATION OF PRESTRESSED CONCRETE NEBT BEAM COST Per Linear Foot vs. Total Quantity $ $ $ $ per Linear Foot $ $ $ $0.00 NEBT 1000 NEBT 1200 NEBT 1400 NEBT 1600 NEBT ,000 1,250 1,500 1,750 2,000 Total Linear Feet Bulb Tees 20 OF 31
21 VARIATION OF HP PRESTRESSED CONCRETE NEBT BEAM COST Per Linear Foot vs. Total Quantity $ $ $ $ per Linear Foot $ $ NEBT 1000 NEBT 1200 $ NEBT 1400 NEBT 1600 $ ,000 1,250 1,500 1,750 2,000 Total Linear Feet NEBT 1800 HP Bulb Tees 21 OF 31
22 ITEM VARIATION OF M270 GR 36 GALV. STRUCTURAL STEEL COST Per Pound vs. Total Quantity $15.00 $14.00 $13.00 M270 GR 36W GALV. 1 (M270 GR 36W GALV. 1) Trendline $12.00 $11.00 $10.00 $ per Pound $9.00 $8.00 $7.00 $6.00 $5.00 $4.00 $3.00 $2.00 $1.00 $ Total Pounds 1,000 10,000
23 $10.00 $9.00 ITEM VARIATION OF M270 GR 50W UNCOATED ROLLED BEAM BRIDGE Per Pound vs. Total Quantity M270 GR 50W (M270 GR 50W) Trendline $8.00 $7.00 $ per Pound $6.00 $5.00 $4.00 $3.00 $2.00 $1.00 $0.00 1,000 10,000 Total Pounds 100,000 1,000,000 M270 GR 50W - Item OF 31
24 $ per Pound $5.00 $4.75 $4.50 $4.25 $4.00 $3.75 $3.50 $3.25 $3.00 $2.75 $2.50 $2.25 $2.00 $1.75 $1.50 $1.25 $1.00 $0.75 $0.50 $ ,000 ITEM VARIATION OF M270 GR 50W UNCOATED PLATE GIRDER Per Pound vs. Total Quantity 1,000,000 Total Pounds M270 GR 50W UNCOAT PLATE GIRDER (M270 GR 50W) Trendline 10,000,000 M270 GR 50W - Item OF 31
25 $5.00 $4.75 $4.50 ITEM STEEL M270 GR 50 PAINTED BOX GIRDER BRIDGE Per Pound vs. Total Quantity STEEL M270 GR 50 PAINTED BOX GIRDER Box Girder Trendline $4.25 $4.00 $3.75 $3.50 $ per Pound $3.25 $3.00 $2.75 $2.50 $2.25 $2.00 $1.75 $1.50 $1.25 $ ,000 1,000,000 Total Pounds 10,000,000 Struct. Steel - Item OF 31
26 $6.50 ITEM VARIATION OF 270 GR 50W PAINTED BASCULE Per Pound vs. Total Quantity $6.25 $6.00 $5.75 $5.50 $5.25 $5.00 $4.75 $4.50 $4.25 $ per Pound $4.00 $3.75 $3.50 $3.25 $3.00 $2.75 $2.50 $2.25 $2.00 $1.75 $1.50 $1.25 $ GR 50W PAINTED BASCULE (M270 GR 50W) Trendline 10, ,000 Total Pounds 1,000,000 10,000,000 M270 GR 50W - Item OF 31
27 WEIGHTED AVERAGE UNIT PRICES TAKEN FROM STATEWIDE WEIGHTED AVERAGE BID PRICES $ per CY VARIATION OF CEMENT CONCRETE COSTS 4000 PSI, 1-1/2 IN., 565 Cem. Conc. per cubic yard vs. total quantity (4000 PSI, 1-1/2 IN., 565 Cem. Conc.) Trendline $2, $2, $2, $2, $2, $1, $1, $1, $1, $1, $ $ $ $ $ ,000 10,000 Total Cubic Yards ITEM 901. SUB-ITEM DESCRIPTION QUANTITY UNIT UNIT PRICETOTAL VARIATION OF CEMENT CONCRETE COSTS 4000 PSI, 3/4 IN., 610 Cem. Conc. per cubic yards vs. total quantity 910.2$3, STEEL REINFORCEMENT FOR S 122,000 LB (4000 PSI, 3/4 IN., 610 Cem. Conc.) Trendline $3, COATED 922.4$2, LAM. ELASTOMERIC BEARING W 13 EA - BOLTS ( K) $2, PRESTRESSED CONCRETE BUL 397 LF $2, BEAMS (NEBT 1400) $1, STEEL M270 GRADE 36 GALVAN 2795 LB $1, MISCELLANEOUS $ $ $ ,000 10,000 Total Cubic Yards $ per CY ITEM 904. Cement Concrete 27 OF 31
28 VARIATION OF HIGH PERFORMANCE CONCRETE COST Per Cubic Yard vs. Total Quanity $2, $2, (4000 PSI, 3/4 IN., 585 HP Cem. Conc.) (4000 PSI, 3/4 IN., 585 HP Cem. Conc.) Trendline $2, $1, $1, $ per Cubic Yard $1, $1, $1, $ $ $ $ $ ,000 10, ,000 Total Cubic Yards HP Concrete - Item OF 31
29 VARIATION OF HIGH PERFORMANCE CONCRETE COST Per Cubic Yard vs. Total Quanity $2, $2, $2, (4000 PSI, 3/4 IN., 585 HP Cem. Conc.) 2007 (4000 PSI, 3/4 IN., 585 HP Cem. Conc.) 2008 (4000 PSI, 3/4 IN., 585 HP Cem. Conc.) 2006 (4000 PSI, 3/4 IN., 585 HP Cem. Conc.) Trendline 2007 (4000 PSI, 3/4 IN., 585 HP Cem. Conc.) Trendline 2008 (4000 PSI, 3/4 IN., 585 HP Cem. Conc.) Trendline $1, $1, $ per Cubic Yard $1, $1, $1, $ $ $ $ $ ,000 10, ,000 Total Cubic Yards
30 VARIATION OF HIGH PERFORMACE CONCRETE COST Per Cubic Yard vs. Total Quanity $3, $2, PSI, 3/8 IN., 710 HP Cem. Conc. (5000 PSI, 3/8 IN., 710 HP Cem. Conc.) Trendline $2, $2, $2, $ per Cubic Yard $2, $1, $1, $1, $1, $1, $ $ $ ,000 Total Cubic Yards HP Concrete - Item OF 31
31 $4.00 $3.75 $3.50 $3.25 $3.00 $2.75 ITEM VARIATION OF COATED REBAR COST Per Pound vs. Total Quantity Coated Rebar (Coated Rebar) Trendline $ per Pound $2.50 $2.25 $2.00 $1.75 $1.50 $1.25 $1.00 $0.75 $0.50 $0.25 1,000 10, ,000 Total Pounds 1,000,000 10,000,000 Coated Rebar - Item OF 31
The unit costs are based on the trend line of the 3 low bids for the average quantity.
Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally
More informationFY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
More informationWILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued)
BIDDER'S PROPOSAL (continued) Item Estimated No. Description Quantity Unit Unit Cost Total Cost BASE BID 1 Traffic Control 1 LS $ $ 2 Construction Area Signs 1 LS $ $ 3 Excavation Safety 1 LS $ $ 4 Reset
More informationFY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
More informationADDENDUM NO. 2. Contract Documents for REPLACEMENT OF PHOENIX STREET BRIDGE OVER THE TANKERHOOSEN RIVER VERNON, CONNECTICUT
ADDENDUM NO. 2 Contract Documents for REPLACEMENT OF PHOENIX STREET BRIDGE OVER THE TANKERHOOSEN RIVER VERNON, CONNECTICUT Bridge No. 1460008 (existing) Bridge No. 06806 (new) TO ALL BIDDERS: Anchor Engineering
More informationSECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
More informationSECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
More informationPTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE
FORM A PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE The following suggested specifications are written as a guide to assist the specifier in writing his own specifications. Specific circumstances
More informationTABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth
TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20
More informationBridge Type Selection
Bridge Type Selection The major consideration for bridge type selection for bridges on the State Aid system is initial cost. Future maintenance costs, construction time, and location are considered when
More informationSECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
More informationFDOT Specifications List
FDOT Specifications List TABLE OF CONTENTS DIVISION II CONSTRUCTION DETAILS CLEARING CONSTRUCTION SITE 110 Clearing and Grubbing... 152 EARTHWORK AND RELATED OPERATIONS 120 Excavation and Embankment...
More informationSUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
More informationSafe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
More informationResidential Deck Safety, Construction, and Repair
Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the
More informationChapter 22. Lump Sum Project Guidelines
Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11
More informationNOTICE TO CONTRACTORS. CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW
NOTICE TO CONTRACTORS CALL ORDER 700 FEDERAL PROJECT NO. STPD-6-2(122) LOCATION: US-34/US-6,CULBERTSON-McCOOK COUNTIES: HITCHCOCK RED WILLOW The Nebraska Department of Roads will receive sealed bids in
More informationSECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
More informationITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT
ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load
More informationSECTION 02630 STORM DRAINAGE SYSTEM
SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE
More informationUnit Price Averages Reports
Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation
More informationAIR RELEASE, CLEANOUT, AND SEWER MANHOLES
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing
More informationDIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
More informationCONSTRUCTION COST MODELS
CONSTRUCTION COST MODELS Prepared by: The New England Environmental Finance Center For the Maine Department of Transportation Office of Environmental Planning November 1, 2010 The following are a series
More informationFLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR
FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR ESTABLISHING CONSTRUCTION CONTRACT DURATION July 2010 DISCLAIMER: The following documentation as a whole was derived from Federal Highway Administration
More informationTECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General
More informationMaterials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections
Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built
More informationMicropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com
More informationTable 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection
More informationHigh Strain Dynamic Load Testing of Drilled Shafts
Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain
More informationStorm Sewer Trenchless Upgrade Alternatives and Recommendations
Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for
More informationLS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
More informationStructures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS
Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.
More informationWSDOT Bridge Elements
Chapter 4 WSDOT Bridge Elements 4.01 List of WSDOT Elements by Number 12 Concrete Deck............................... 4-14 13 Bridge Deck Surface........................... 4-14 14 Fully Supported Concrete
More informationDESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
More informationSECTION 701 CULVERT PIPE, ENTRANCE PIPE, STORM SEWER PIPE, AND EQUIVALENTS
SECTION 701 CULVERT PIPE, ENTRANCE PIPE, STORM SEWER PIPE, AND EQUIVALENTS 701.01 DESCRIPTION. Furnish and install culvert pipe, entrance pipe, and storm sewer pipe. Use units conforming to the dimensions,
More informationIH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
More informationCHAIN-LINK FENCES BID SPECIFICATIONS DESCRIPTION
CHAIN-LINK FENCES BID SPECIFICATIONS DESCRIPTION 1 This item shall consist of furnishing and erecting Chain-Link fence in accordance with these specifications and the details shown on the plans and in
More informationSAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS
Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and
More informationValue Engineering vs. Alternate Designs in Bridge Bidding
Value Engineering vs. Alternate Designs in Bridge Bidding Compares the advantages and disadvantages of alternate designs and value engineering in bidding of bridges as experienced in the State of Florida.
More informationVirginia Approach Spans
Virginia Concrete Conference 2009 Woodrow Virginia Approach Spans David Tackoor, HNTB Formerly of URS Corp for Potomac Crossing Consultants Woodrow 1 Second Severn Crossing 2 Medway Crossing (Channel Tunnel
More information4. ANCHOR BOLTS AND STRAPS a. ½" anchor bolts shall be embedded 7" into concrete a maximum of 6' on center and 12" from corners and ends of plates.
GENERAL CODE REQUIREMENTS (BASEMENTS) 1. FOOTINGS a. Footings shall be below frost line depth (42"). b. For an 8" foundation wall, footings shall be no less than 8" deep and 16" wide. c. Steel reinforcement
More informationQuality Control and Quality Assurance Guide
Quality Control and Quality Assurance Guide Bridge Division, Design Section October 2013 Table of Contents Chapter 1 About this Guide... 3 Chapter 2 Goals and Objectives... 5 Chapter 3 Participants...
More informationHigh Capacity Helical Piles Limited Access Projects
High Capacity Helical Piles Limited Access Projects Tel 403 228-1767 Canada, USA, Russia Brendan ODonoghue 519 830-6113 Presentation Summary 1. Helical piles Background on large diameter shafts and helices
More informationCOMMONLY USED RESIDENTIAL BUILDING CODES
COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section
More informationUp-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet
More informationChapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
More information11 Guardrail. W-Beam Guardrail Pre-Installation Inspection During Installation Basis for Use. Modified Guardrail. End Treatments and Transitions
11 Guardrail W-Beam Guardrail Pre-Installation Inspection During Installation Basis for Use Modified Guardrail End Treatments and Transitions Footings and Anchors Impact Attenuators Measurement and Payment
More informationvolume of concrete occupied by the drain pipe in a cast-in-place structure or structure extension.
715.01 430 volume of concrete occupied by the drain pipe in a cast-in-place structure or structure extension. No additional payment will be made for the repair or replacement of existing concrete damaged
More information~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:
Texas Depadment of Transpo,tation Bridge Condition Survey Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway: Irving Street Facility Name: Lone Wolf Bridge Structure Number: B00315-031
More informationAnderson Ground Storage Tank No. 1 Painting and Rehabilitation Project SAWS Job No. 13-0129 Solicitation No. B-15-020-DD. ADDENDUM No.
Anderson Ground Storage Tank No. 1 Painting and Rehabilitation Project SAWS Job No. 13-0129 Solicitation No. B-15-020-DD ADDENDUM No. 1 June 26, 2015 This addendum, applicable to work designated above,
More informationBRIDGE DESIGN MANUAL
BRIDGE DESIGN MANUAL 2003 Edition (U.S. Customary Units) State of Connecticut Department of Transportation Revisions: 7/04, 11/04, 1/05, 3/05, 1/09, 3/09, 2/11 PREFACE The Connecticut Department of Transportation
More informationMETHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
More informationResidential Decks. Planning and Development Services Department
Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: permitservices@opkansas.org Planning and Development Services Department Residential Decks
More informationBRIDGES ARE relatively expensive but often are
Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the
More informationSpecial Specification 7021 Water Main and Sewer Line Replacements
Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,
More informationFDOT DBE CERTIFICATION NAICS CODE GUIDE WITH CAP SIZES
NAICS CODE Highway, Street, and Bridge Construction SIZE CAP ($ MIL) 237310 Asphalt Roadway (includes 300, 320, 327, 330, 334, 336, 337, 338) Application of prime and tack coats, leveling surfaces and
More informationHow To Build A Road In A Townhouse
FDOT DBE CERTIFICATION SPECIALTY/ SHEET WITH CAP SIZES Highway, Street, and Bridge Construction SIZE CAP ($ MIL) 237310 Asphalt Roadway $ 22.41 Application of prime and tack coats, leveling surfaces and
More informationFOUNDATIONS SECTION UIP 1
UIP 1, PAGE 1 FOUNDATIONS FOUNDATION COSTS HILLSIDE CONSTRUCTION Foundation costs include all labor, materials and equipment, plus overhead and profit for the installing contractor. Buildings located on
More informationC. Section 014510 TESTING LABORATORY SERVICE.
SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,
More informationThe minimum reinforcement for the stem wall is the placement of:
PolySteel creates an ideal insulated stem wall for concrete slabs that can make this part of your project easier and faster, in addition to making your finished project more energy-efficient. Figures 3.20
More informationAcceptance Codes APPENDIX - A. Acceptance Criteria
1111 Receipt of a satisfactory Test Report from WSDOT Materials Laboratory is required indicating the lot (or lots) or batch of material meets the requirement of the specifications under which it is listed.
More informationSPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)
Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks
More informationHunter College school of Social Work Thesis Proposal
Fall 2009 Hunter College school of Social Work Thesis Proposal To analyze how energy efficiency can be implemented using facade and green roof redesign. It ties structural engineering concepts with existing
More informationNo allowance will be made for classification of different types of material encountered.
PROJECT : Repair/ Maintenance of Flood Control and Drainage Structures Along Butuan City Cagayan de Oro City Iligan City Road LOCATION : San Antonio, Jasaan, Misamis Oriental SUBJECT : General Notes and
More informationGEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER
GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER Professional Experience: Pride and Passion in the Art of Structural Engineering since 1979. Professional Registration: Professional
More informationHow to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013
How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table
More informationResidential Foundations and Basements
Residential Foundations and Basements Disclaimer All of the following information is based on the 2006 International Residential Code with Kentucky Amendments. As some information is paraphrased, article
More informationJames M. Pleasants Company
James M. Pleasants Company SUBMITTAL DATA GAINESVILLE MECHANICAL DECEMBER 20, 2013 PROJECT: GSU: J-183 HUMANITIES LAW BLDG. QUOTE NO:12116 ENGINEER: STEVENS & WILKINSON GASKETED PLATE HEAT EXCHANGER Tag:
More informationSECTION 02845 GUARDRAILS
SECTION 02845 GUARDRAILS PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals necessary and repair, replace or install all types of guardrails as specified herein
More informationCITY OF SAN ANTONIO. Issued By: Transportation and Capital Improvements Date Issued: February 10, 2016 ID NO.: 23-01472-05-03
CITY OF SAN ANTONIO Issued By: Transportation and Capital Improvements Date Issued: February 10, 2016 ID NO.: 23-01472-05-03 (010) FORMAL INVITATION FOR BIDS (IFB) to CONTRACT 2016-2017 TASK ORDER CONTRACT
More informationCCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
More informationROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS
ROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS 1. 2. 3. 3.0 Scope 1.1 This application standard shall be used where the authority having jurisdiction has adopted its use, and
More informationDIVISION 4300 STORM DRAINAGE
DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES
More informationCHAPTER 6 - SANITARY SEWER
CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings
More informationSTRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.
STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill
More informationRHODE ISLAND TURNPIKE AND BRIDGE AUTHORITY NEWPORT, RHODE ISLAND CONTRACT NO. 15-08
RHODE ISLAND TURNPIKE AND BRIDGE AUTHORITY NEWPORT, RHODE ISLAND CONTRACT NO. 15-08 STEEL REPAIRS AND PROTECTIVE COATING WEST APPROACH FOR THE EAST PASSAGE CROSSING OF NARRAGANSETT BAY (NEWPORT/PELL BRIDGE)
More informationThe work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
More informationSource: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.
Total project cost $2.5 billion (Canadian) Financed by tolls about $3 each direction. Total project length 37 km (McGill St in Vancouver to 216 th in Langley) The new Port Mann bridge 10 lanes (existing
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
More informationLos Angeles County Department Of Public Works. Land Development Division. Bond Calculation Sheets
Los Angeles County Department Of Public Works Land Development Division Bond Calculation Sheets Effective July 1, 2015 COUNTY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS LAND DEVELOPMENT DIVISION ROADS COST
More information2015 PRICE L IST INNOVATION THROUGH ENGINEERING 1-8 0 0-2 2 3-0 0 1 2 1-6 1 3-5 4 6-6 6 8 3 S A L E S @ A N C H O R C O N C R E T E.
2015 L IST INNOVATION THROUGH ENGINEERING 1-8 0 0-2 2 3-0 0 1 2 1-6 1 3-5 4 6-6 6 8 3 S A L E S @ A N C H O R C O N C R E T E. C O M 1 6 4 5 SYDENHAM ROAD KINGSTON ONTARIO C ANADA K7L4V4 WWW.ANCHORCONCRETE.COM
More informationSECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials
More informationCERTIFIED TECHNICIAN PROGRAM TRAINING MANUAL. Bridge Construction and Deck Repair
CERTIFIED TECHNICIAN PROGRAM TRAINING MANUAL Bridge Construction and Deck Repair Revised 2014 This material is to be used for training purposes only. Some of the procedures, field tests, and other operating
More informationState of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
More informationSECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
More information550 PIPE CULVERTS, SEWERS AND DRAINS
551.01 550 PIPE CULVERTS, SEWERS AND DRAINS 551 GENERAL 551.01 Description 551.02 Materials 551.03 Excavation 551.04 Protection of Excavation 551.05(a) Bedding for Rigid Pipe 551.05(b) Bedding for Non-Rigid
More informationSection 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
More information2008-2009 Cost Comparisons for Common Commercial Wall Systems
An Independent Study LA MS KY TN AL GA SC NC FL 2008-2009 Cost Comparisons for Common Commercial Systems CAPITAL BUILDING CONSULTANTS PROFESSIONAL CONSTRUCTION ESTIMATORS 2008 2009 INDEPENDENT COST COMPARISONS
More informationHIGH TENSION CABLE BARRIER
Special Provision September 11, 2006 SECTION 02845 S HIGH TENSION CABLE BARRIER PART 1 GENERAL 1.1 SECTION INCLUDES A. Cable barrier materials and installation procedures. 1.2 RELATED SECTIONS A. Section
More informationJune 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL
7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction
More informationIndex 20010 Series Prestressed Florida-I Beams (Rev. 07/12)
Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Design Criteria AASHTO LRFD Bridge Design Specifications, 6th Edition; Structures Detailing Manual (SDM); Structures Design Guidelines (SDG)
More informationSmooth cap sheet - 0-10 SQ $ 139.00. Smooth cap sheet - 11-50 SQ $ 63.00. Smooth cap sheet - 51-100 SQ $ 36.00 Smooth cap sheet - 101-200 SQ $ 36.
Demolition/Removal of Work 4-ply built up roofing to the insulation (smooth cap sheet) Smooth cap sheet - 0-10 SQ $ 63.00 Smooth cap sheet - 11-50 SQ $ 63.00 Smooth cap sheet - 51-100 SQ $ 35.00 Smooth
More informationEstimated Cost of Repair
1 Applicant: Property: Home: Business: Assessor: Applicant Number: Type of Loss: Hurricane Date Contacted: 1/18/2014 Date of Loss: 10/29/2012 Date Received: 1/14/2014 Date Inspected: 2/4/2014 Date Entered:
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS
San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these
More informationADDENDUM NO. 1. Manchester Boston Regional Airport, City of Manchester, NH
Hoyle, Tanner Project No. 093145 ADDENDUM NO. 1 Manchester Boston Regional Airport, City of Manchester, NH Construct Relocated Roadway Airport Service Rd. Outside Runway Object Free Area (ROFA); Construct
More informationSports and High Mast Lighting Poles Phone: (866) 474-7200 Fax: (817) 924-7049
Sports and High Mast Lighting Poles 4 High Mast Lighting Poles General American LitePole offers a raising and lowering system that allows for ease of maintaining the lighting system at ground level. Ideal
More informationLAYING BLOCK AND BRICK
LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct
More informationTECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines
More informationSECTION 15 AIR RELEASE VALVE ASSEMBLIES. 15-1 General
SECTION 15 AIR RELEASE VALVE ASSEMBLIES 15-1.01 Scope 15-1 General This section describes the requirements for furnishing and installing Air Release Valve Assemblies of the size and type shown on the plans,
More information