LPS 10-Year Facilities Plan Update Lincoln Public Schools

Save this PDF as:
 WORD  PNG  TXT  JPG

Size: px
Start display at page:

Download "LPS 10-Year Facilities Plan Update Lincoln Public Schools"

Transcription

1 LPS 10-Year Facilities Plan Update

2 Presentation Objectives 1. Renew Process of LPS 10-Year Facilities Plan Annual Update. 2. Provide Board of Education a Working Document that Defines Current LPS Facilities & Infrastructure Needs.

3 It s Been Nearly 10-Years Since the MGT of America Comprehensive District Master Plan Development Document Was Finalized. It s Been Nearly 8-Years Since the Final Report of the Superintendents Student Housing Task Force. This Report Recommended Four Over-Arching Needs:

4 1. Improve Indoor Air Quality and Handicapped Accessibility. 2. Stop Relying on Portable Classrooms. 3. Maximize Use of Existing Facilities. 4. Plan For Appropriate Expansion of Existing Schools and Construction of New Ones To Meet Growing Community-Wide Needs.

5 Construction Project Summary Project Name # Sites Spent to Date Bond Projects 28 $ 276,930, Phase 2 6 $ 41,681, Phase 2B 5 $ 26,216, Phase 3 5 $ 32,846, Educare/Belmont 1 $ 3,101, DDSEC 1 $ 1,775, Total 46 $ 382,551, Data Center 1 $ 1,507, Print Shop 1 $ 823, LPSDO 1 $ 16,263, Total 3 $ 18,594, Project Related Expenses $ 10,613, Total Spent 49 $ 411,760,201.00

6 We Owe Our Success To A Visionary Board Of Education, AND Supportive Community Enabling Us To Accomplish What We Have To Date.

7 Facility Information Total Number of LPS Facilities: Total Square Footage of Buildings High Schools (7 - including Hawthorne Facility) Middle Schools (11) Elementary Schools (38) Specialized Schools (2 -Yankee Hill & Bryan Facility) Portable Buildings (26) Support Facilities (6 - includes Seacrest) Leased Space (3 Focus Programs, 2 Office Bldg.) Total School Site & Support Center Acres Total Replacement Value of LPS Buildings Total Undeveloped Site Acres (11 Sites) Number of Facilities & Maintenance Staff 64* 7,149,081* 2,329,550 1,720,067 2,778,875 34,296 35, ,067 93, $1,142,338, * Leased property not included 3 Community Centers included

8 Other Statistical Facts LPS Is The Largest Employer In The City Of Lincoln LPS Is One Of The Top 3 Consumers Of Energy In The City Of Lincoln Since 2002 (Last 10 Years), The City Of Lincoln s Population Grew By 12.2% Since 2002 (Last 10 Years), Lincoln Public School s Population Grew By 14.6% (4,488 Students)

9 3,500 LPS Student Population by Grade Level 3,000 2,500 Student Population 2,000 1,500 1, Grade Level

10 LPS Incoming & Outgoing Classes 3,100 3,000 2,900 Population 2,800 2,700 2,600 2,500 2,400 FY FY FY FY FY Kindergarten 12th Grade FY FY FY FY FY th Grade 2,688 2,715 2,825 2,757 2,795 Kindergarten 2,973 3,091 2,987 3,035 2,825 Difference

11 More Statistical Facts LPS FM Staff Currently Service More Than 3500 Individual Heat Pumps.

12

13 More Statistical Facts LPS FM Staff Currently Maintains Approximately 1,121 Miles of Geothermal Loop Piping (Vertical).

14 from Lincoln, NE to State College, PA miles

15 More Statistical Facts LPS FM Grounds and Custodial Operations Crews Currently Remove Snow On More Than 200 Acres of Concrete Walks, Paths, Playgrounds And Parking Areas & They Mow In Excess of 480 Acres Of Lawns and Play Fields.

16 1 Square Mile 640 Acres Each Quarter Section Contains 160 Acres

17 More Statistical Facts LPS FM and Custodial Crews Manage, Inspect and Maintain Over 130 Acres Of Roofing.

18 134 x 43,560 = 5,837,040 x $11 00 Acres S.F./Acre Square Feet Today s Replacement Cost Is More Than $64 Million Replacement Cost per S.F.

19 Fact: LPS Is A Large, Fast Growing Organization.

20 Fact: Keeping Up With Routine Maintenance, Renovations and Modifications Based On Current Growth Trends Has Become Much More Difficult.

21 Our Community Expects Excellent, Well Maintained Facilities. AND Our Students & Staff Deserve A Safe, Secure, Comfortable Learning Environment.

22 LPS 10-Year Facilities Plan Update (3 Key Points) Point 1 The LPS Facilities & Infrastructure Are In The Best Shape/Condition They Have Ever Been.

23 Kooser E.S.

24 Schoo M.S.

25 Eastridge E.S.

26 Culler M.S.

27 Elliott E.S.

28 Lincoln High School

29 Southeast H.S.

30 Northeast H.S.

31 East H.S.

32 Mickle M.S.

33 Hartley E.S.

34 Zeman E.S.

35 Fredstrom E.S.

36 LPS 10-Year Facilities Plan Update Due To: City Growth & Development (3 Key Points) Point 2

37 1973 City of Lincoln Land Area (sq. mi.) Population ,670 District Area (sq. mi.) High Schools Middle Schools Elementary Schools Specialized Schools Support Facilities Annex Sites District Total Sq. Ft (51) 3,501,944* Site Acres Undeveloped Sites Student Enrollment Total Staff Maintenance Staff (17) ,122 1,803* 69*

38 1993 City of Lincoln Land Area (sq. mi.) Population ,505 District Area (sq. mi.) High Schools Middle Schools Elementary Schools Specialized Schools Support Facilities Portable Buildings District Total Sq. Ft (53) 4,367,327 Site Acres Undeveloped Sites Student Enrollment Total Staff Maintenance Staff (9) ,990 3,173* 67*

39 2013 City of Lincoln Land Area (sq. mi.) Population ,341 District Area (sq. mi.) High Schools Middle Schools Elementary Schools Specialized Schools Support Facilities Portable Buildings District Total Sq. Ft (64) 7,064,729 Site Acres Undeveloped Sites Student Enrollment Total Staff (FTE) Maintenance Staff (11) ,911 5,659* 126

40 Land Area (square miles) Population ,670 City of Lincoln , ,341 District Area (square miles) High Schools Middle Schools Elementary Schools Specialized Schools Support Facilities Annex Sites/Portable Buildings District Total Sq. Ft (51) 3,501,944* (53) 4,367, (64) 7,064,729 Site Acres Undeveloped Sites (17) (9) (11) Student Enrollment Total Staff O&M Staff 30,122 1,803* 69* 29,990 3,173* 67* 36,911 5,659* 126

41

42 LPS 10-Year Facilities Plan Update Due To: City Growth & Development Changes In Technology (3 Key Points) Point 2

43

44 LPS 10-Year Facilities Plan Update Due To: City Growth & Development Changes In Technology (3 Key Points) Point 2 Changes In Curriculum & Curriculum Delivery

45

46 LPS 10-Year Facilities Plan Update Due To: City Growth & Development Changes In Technology (3 Key Points) Point 2 Changes In Curriculum & Curriculum Delivery Security & Communication Priorities

47

48 LPS 10-Year Facilities Plan Update Due To: City Growth & Development Changes In Technology (3 Key Points) Point 2 Changes In Curriculum & Curriculum Delivery Security & Communication Priorities Global Interest In Sustainable Practices

49

50 LPS 10-Year Facilities Plan Update Due To: City Growth & Development Changes In Technology (3 Key Points) Point 2 Changes In Curriculum & Curriculum Delivery Security & Communication Priorities Global Interest In Sustainable Practices Community Use Expectations

51 COMMUNITY USE OF LPS FACILITIES LAST YEAR, COMMUNITY GROUPS UTILIZED LPS FACILITIES IN EXCESS OF 125,000 HOURS THIS YEAR, OVER 78,000 RESERVATIONS MADE (SO FAR)

52 Due To: LPS 10-Year Facilities Plan Update (3 Key Points) City Growth & Development Changes In Technology Changes In Curriculum & Curriculum Delivery Security & Communication Priorities Global Interest In Sustainable Practices Community Use Expectations Point 2 We Still Have Facilities & Infrastructure Needs

53 FM Budget/Funding A Lean Machine Contracted Services Budget # of Facilities District Square Footage # of Students FY 2000/2001 $2,432, ,454,938 31,354 FY 2009/2010 $1,898, ,897,886 34,941 FY 2010/2011 $1,809, ,886,482 35,847 FY 2011/2012 $1,202, ,965,566 36,485 FY 2012/2013 $1,809, ,113,993 36,902

54 Roofing Life Cycle

55 HVAC Life Cycle

56 Infrastructure

57 LPS 10-Year Facilities Plan Update (3 Key Points) Point 3 We (LPS Staff) Believe That With The Support Of The Planning Committee, Board Of Education And The Community, We Can Produce An Appropriate Plan To Accommodate Such Needs.

58 10-Year Facilities Plan Adopted 4/27/2010

59 10-Year Facilities Plan Adopted 4/27/2010 (with Updates)

60 10-Year Facilities Plan April 2011 Proposed Update

61 LPS 10-Year Facilities plan Update

62 LPS 10-Year Facilities Plan Update Expanding Our Needs List A New Format How Do We Continue To Provide A Safe, Secure and Comfortable Learning Environment? AND Accommodate The Following:

63 LPS 10-Year Facilities Plan Update City Growth And Development Changes In Technology Changes In Curriculum & Curriculum Delivery Implementation Of Timely Security and Communication Practices & Architecture Providing More Community Access and Integration Into Our Facilities Sound Sustainability Practices

64 LPS 10-Year Facilities Plan Update Communication w/ Students and Staff Good Planning Communication w/ Parents Good Planning Communication w/ Community Good Planning

65 LPS 10-Year Facilities Plan Update

66 LPS 10-Year Facilities Plan Update

67

68 Current LPS Vacant Sites City of Lincoln 2040 Service Limit

69 Career Academy SE M.S. w/ YMCA SE E.S. Northwoods SE E.S. T.B.D. Zoo School

70 W. Lincoln E.S. Elliott E.S Randolph E.S. Norwood Park E.S. Northeast H.S. Lefler M.S. Schoo M.S.

71 Humann E.S. Belmont E.S Park M.S. Bryan Facility H.S. Modifications (Career Academy)

72 Seacrest Activities Complex Bleacher Projects H.S. Camera Projects Window Replacement Saratoga E.S. Security Entrances Card Access

73 A Decade of Growth City Population Student Population Facilities Sq. Ft. Electricity Rates Outside Use (estimated) 2001/ / /2013 Growth % Increase 233, ,341 28,597 12% 30,688 35,176 4,488 15% 5,583,099 7,063,550 1,480,451 27% $ /Therm $ /Therm $ /Therm 16% 70, , , %

74 Annual Utility Cost $7,000, $6,000, $5,000, $4,000, $3,000, $2,000, $1,000, $

Guideline for Construction Reimbursement Rates. 160-5-4-.16 (a) 7. Educational Facility Site, Construction, and Reimbursement

Guideline for Construction Reimbursement Rates. 160-5-4-.16 (a) 7. Educational Facility Site, Construction, and Reimbursement Guideline for Construction Reimbursement Rates 160-5-4-.16 (a) 7 Educational Facility Site, Construction, and Reimbursement Facilities Services Unit Effective Date: 05-30-12 NEW CONSTRUCTION REIMBURSEMENT

More information

Office of Property Management OPM (AM)

Office of Property Management OPM (AM) Office of Property Management OPM (AM) MISSION Support the District Government through building operations, real estate management and capital construction. SUMMARY OF SERVICES The Office of Property Management

More information

MEMORIAL PUBLIC SCHOOL FACILITY INFORMATION. Central St. Catharines Elementary Schools Accommodation Review

MEMORIAL PUBLIC SCHOOL FACILITY INFORMATION. Central St. Catharines Elementary Schools Accommodation Review MEMORIAL PUBLIC SCHOOL FACILITY INFORMATION Central St. Catharines Elementary Schools Accommodation Review October 2012 EAST AND SOUTH LINCOLN ELEMENTARY SCHOOLS ACCOMMODATION REVIEW Memorial Public School

More information

Comparing Maintenance Costs of Geothermal Heat Pump Systems with Other HVAC Systems: Preventive Maintenance Actions and Total Maintenance Costs

Comparing Maintenance Costs of Geothermal Heat Pump Systems with Other HVAC Systems: Preventive Maintenance Actions and Total Maintenance Costs DA-00-1-2 Comparing Maintenance Costs of Geothermal Heat Pump Systems with Other HVAC Systems: Preventive Maintenance Actions and Michaela A. Martin, P.E. Melissa G. Madgett Patrick J. Hughes, P.E. Member

More information

Groton School Facilities Initiative. Building Construction Scenarios & Site Selection Update

Groton School Facilities Initiative. Building Construction Scenarios & Site Selection Update Groton School Facilities Initiative Building Construction Scenarios & Site Selection Update + 1 Introduction Recap of Options from 7/25 Meeting Introduction The S/L/A/M Collaborative Grant Reimbursement

More information

Barrie Primary Care Campus

Barrie Primary Care Campus Barrie Primary Care Campus Barrie Primary Care Campus Location The Barrie Primary Care Campus will lead the market as the most advance primary health care center in Ontario. It will be a significant development

More information

Appoquinimink s 2016 Proposal for State-issued Certificates of Necessity

Appoquinimink s 2016 Proposal for State-issued Certificates of Necessity Board of Education Presentation Appoquinimink s 2016 Proposal for State-issued Certificates of Necessity Presented by Superintendent Matt Burrows March 8, 2016 What is a Certificate of Necessity? A document

More information

PINER-OLIVET UNION SCHOOL DISTRICT

PINER-OLIVET UNION SCHOOL DISTRICT PINER-OLIVET UNION SCHOOL DISTRICT BOARD MEMEBERS: LISA ANDERSON - PRESIDENT WILLIAM CAMPBELL - VICE PRESIDENT BETH MEAD - CLERK MARDI HINTON - MEMBER CINDY PRYOR - MEMBER JENNIE SNYDER - SUPERINTENDENT

More information

Washoe County School District Facilities Management Department 2012/2013 Departmental Plan

Washoe County School District Facilities Management Department 2012/2013 Departmental Plan Attachment A Washoe County School District Facilities Management Department 2012/2013 Departmental Plan Mission Facilities Management is committed to the timely repair, maintenance and cleanliness of Washoe

More information

W. Burke Royster, Superintendent Greenville County Schools

W. Burke Royster, Superintendent Greenville County Schools W. Burke Royster, Superintendent Greenville County Schools People Students Processes Programs People Preparing Individuals for Dynamic Leadership Director of Academic Innovation and Technology Summer Academy/Upstate

More information

w www.kyschooldesigns.org

w www.kyschooldesigns.org w www.kyschooldesigns.org A collaborative project of AIA Kentucky, Kentucky School Boards Association, Kentucky Association of School Superintendents, Kentucky Association of School Administrators Name

More information

Fairfax County Public Schools

Fairfax County Public Schools Fairfax County Public Schools PROGRAM DESCRIPTION Fairfax County Public Schools (FCPS) determines the need for new facilities and additions to existing schools by comparing available capacity with anticipated

More information

COMPREHENSIVE FACILITIES MASTER PLANNING. Presented By: Kevin A. MacQuarrie, Principal

COMPREHENSIVE FACILITIES MASTER PLANNING. Presented By: Kevin A. MacQuarrie, Principal COMPREHENSIVE FACILITIES MASTER PLANNING Presented By: Kevin A. MacQuarrie, Principal STRATEGIC GOALS AND VISION Student Achievement Safe Schools Communication Budget Project Creek Watch Math Team Health

More information

Description of Project Statewide Student Data Warehouse

Description of Project Statewide Student Data Warehouse Description of Project Statewide Student Data Warehouse The Department of Education (DE) uses Rebuild Iowa Infrastructure Fund funding to support critical components of Iowa s Statewide Longitudinal Data

More information

Jefferson County Public Schools. Society for Marketing Professional Services 2013

Jefferson County Public Schools. Society for Marketing Professional Services 2013 Jefferson County Public Schools Society for Marketing Professional Services 2013 SMPS 2013 8 May 2013 JeffCo Schools County & District Facts JEFFERSON COUNTY, COLORADO Population 540,000 Area 773 Square

More information

37TH ANNUAL MAINTENANCE & OPERATIONS COST STUDY SCHOOLS BY JOE AGRON

37TH ANNUAL MAINTENANCE & OPERATIONS COST STUDY SCHOOLS BY JOE AGRON Karen Wagner High School San Antonio, Texas Architect: PBK Photographer: Jud Haggard 37TH ANNUAL MAINTENANCE & OPERATIONS COST STUDY SCHOOLS BY JOE AGRON As tough economic conditions and rapidly rising

More information

Facilities Management County Administration Building 300 Monroe Avenue NW, Grand Rapids, MI 49503-2206 Phone: (616) 632-7600 Fax: (616) 632-7715

Facilities Management County Administration Building 300 Monroe Avenue NW, Grand Rapids, MI 49503-2206 Phone: (616) 632-7600 Fax: (616) 632-7715 Facilities Management County Administration Building 3 Monroe Avenue NW, Grand Rapids, MI 4953-226 Phone: (616) 632-76 Fax: (616) 632-7715 Mission To manage County facilities and projects striving for

More information

Step 2: Define Project Objectives

Step 2: Define Project Objectives Why GREEN Small-scale renovations to large-scale new construction and master planning, owners are embracing sustainable practices in order to lessen their environmental impact and to reduce their operating

More information

Leased School Buildings and Facilities Located Off School Property

Leased School Buildings and Facilities Located Off School Property INSTRUCTION GUIDE FOR LEASE APPROVAL AND BUILDING AID PUBLIC SCHOOL DISTRICTS OUTSIDE OF NEW YORK CITY Leased School Buildings and Facilities Located Off School Property To be used for the instruction

More information

INDIVIDUAL CAMPUS PLAN ASSESSMENT. No. of Non- Non-Instructional Area. Size Sq. Ft.

INDIVIDUAL CAMPUS PLAN ASSESSMENT. No. of Non- Non-Instructional Area. Size Sq. Ft. ED. SPEC. ELEMENTARY SCHOOL SPACE BUDGET Program Menchaca ES Page 1 of 6 INDIVIDUAL CAMPUS PLAN ASSESSMENT al s Non- al s Size Pre-Kindergarten / Kindergarten - Classrooms 8 8 925 7,400 (minimum or 25

More information

Program: Facilities and Construction Management. Program Based Budget 2016-2018. Facilities and Construction Management. Page 81

Program: Facilities and Construction Management. Program Based Budget 2016-2018. Facilities and Construction Management. Page 81 Program: Program Based Budget 2016-2018 Page 81 Program: Vision: To develop and maintain town buildings which are safe, comfortable and welcoming to all. Mission Statement: To provide technical expertise

More information

PAGE INTENTIONALLY LEFT BLANK

PAGE INTENTIONALLY LEFT BLANK PAGE INTENTIONALLY LEFT BLANK TABLE OF CONTENTS I. Introduction 1 Page II. Documentation of Existing Educational Programs 1 and Instructional Space III. State Square Footage Standards 2 IV. Space Allocation

More information

The following terms should be understood prior to review of the Services Policy:

The following terms should be understood prior to review of the Services Policy: 1.0 BACKGROUND AND PURPOSE The Department of Facilities Management (FM) at the Colorado School of Mines has developed a Services policy to define for the campus community the types of services provided

More information

the Most Out of Your Facilities Christopher P. Hodges, P.E., CFM, LEED-AP, IFMA Fellow

the Most Out of Your Facilities Christopher P. Hodges, P.E., CFM, LEED-AP, IFMA Fellow Maximizing Building Life Cycle to Get the Most Out of Your Facilities Christopher P. Hodges, P.E., CFM, LEED-AP, IFMA Fellow Facility Engineering i Associates The Financial i Case for Facilities Corporate

More information

Ballot Measures. Bremerton School District No. 100-C. Explanatory Statement (Prepared by the attorney for the district as prescribed by law.

Ballot Measures. Bremerton School District No. 100-C. Explanatory Statement (Prepared by the attorney for the district as prescribed by law. Bremerton School District No. 100-C Capital Projects Levy The Board of Directors of Bremerton School District No. 100- C adopted Resolution No. 2015/2016-08 concerning capital projects and technology.

More information

1. Background. 2. Why this is Relevant to the 2014 Bond. 3. Attachments

1. Background. 2. Why this is Relevant to the 2014 Bond. 3. Attachments Issue Paper # 8: Modernization Renovation Projects 1. Background BSD s student population has grown since the last capital bond in 2006 and facilities have experienced normal wear and aging leading to

More information

Los Angeles Community College District

Los Angeles Community College District Los Angeles Community College District BLUE AND GREEN TOGETHER Developing Sustainable Integrated Approaches to Green Technologies and Water Usage Green California Schools and Community Colleges October

More information

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF EDUCATION 333 MARKET STREET HARRISBURG, PA 17126-0333

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF EDUCATION 333 MARKET STREET HARRISBURG, PA 17126-0333 Pennsylvania Department of Education COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF EDUCATION 333 MARKET STREET HARRISBURG, PA 17126-0333 Student Services Report Monday, April 07, 2008 Entity: Ephrata Area

More information

SQUARE FOOTAGE REQUIREMENTS FOR USE IN DEVELOPING THE LOCAL FACILITIES PLANS AND STATE CAPITAL OUTLAY APPLICATIONS FOR FUNDING

SQUARE FOOTAGE REQUIREMENTS FOR USE IN DEVELOPING THE LOCAL FACILITIES PLANS AND STATE CAPITAL OUTLAY APPLICATIONS FOR FUNDING SQUARE FOOTAGE REQUIREMENTS FOR USE IN DEVELOPING THE LOCAL FACILITIES PLANS AND STATE CAPITAL OUTLAY APPLICATIONS FOR FUNDING GEORGIA DEPARTMENT OF EDUCATION FACILITIES SERVICES UNIT December 8, 2003

More information

Facilities Management Department

Facilities Management Department Mission To provide safe and well maintained facilities that fulfill the needs of our customers. Fairfax County Budget Plan (Vol. 1) - 255 AGENCY DASHBOARD Key Data FY 2013 FY 2014 1. Rentable Sq. Feet

More information

Facilities Maintenance & Operations

Facilities Maintenance & Operations Office of Superintendent of Public Instruction Facilities Maintenance & Operations Classified Adequacy Staffing Report December 2010 TABLE OF CONTENTS EXECUTIVE SUMMARY... 3 INTRODUCTION TO FACILITIES

More information

Frequently Asked Questions

Frequently Asked Questions Byron Area Schools Frequently Asked Questions Bond Proposal How did this come about? For several years the Byron Area Schools Board of Education has included upgrading facilities as one of the district

More information

PEABODY ELEMENTARY SCHOOL

PEABODY ELEMENTARY SCHOOL INITIAL YEAR BUILT 1880 BUILDING AREA 37,800 SF CURRENT PROGRAM CAPACITY 210 ENROLLMENT 2008 165 WARD 6 PROPOSED PROGRAM CAPACITY 220 Site Plan PEABODY - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

August 2013 K-12 Schools Grant Round - Awards

August 2013 K-12 Schools Grant Round - Awards August 2013 K-12 Schools Grant Round - Awards Awarded: Aug 15, 2013 POLITICAL SUB NAME COUNTY SHORT DESCRIPTION Recommended Award Description Award Amount ALEXANDER PSD #2 MCKENZIE MODULAR TEACHER HOUSING

More information

the Charter School Facility

the Charter School Facility An Analysis of the Charter School Facility Landscape in New Jersey January 2013 The National Charter School Resource Center is funded by the U.S. Department of Education s Office of Innovation and Improvement

More information

Chief Building Official

Chief Building Official Chief Building Official To be considered, please submit a cover letter, résumé with salary history and five (5) professional references to: Ms. Patricia Palmer Director, Community and Human Resources 22

More information

PROCEDURES FOR THE NONPUBLIC AGING SCHOOLS PROGRAM (FISCAL YEAR 2015)

PROCEDURES FOR THE NONPUBLIC AGING SCHOOLS PROGRAM (FISCAL YEAR 2015) PROCEDURES FOR THE NONPUBLIC AGING SCHOOLS PROGRAM (FISCAL YEAR 2015) August 2014 These procedures are available for download at: http://www.pscp.state.md.us Applications for this program must be submitted

More information

CAPITAL EXPENDITURES

CAPITAL EXPENDITURES CAPITAL EXPENDITURES 1 CAPITAL EXPENDITURES CAPITAL EXPENDITURES PLANNING On March 1, 2010 the AmherstPelham Regional School committee adopted a policy for developing a formal capital needs planning process.

More information

Public Works Program Area Summary

Public Works Program Area Summary Overview The agencies in the Public Works program area have both an external and internal focus. They are responsible for designing and building County infrastructure, such as administrative buildings,

More information

NORTHWEST TECHNICAL INSTITUTE

NORTHWEST TECHNICAL INSTITUTE NORTHWEST TECHNICAL INSTITUTE Enabling Laws Act 6 of 22 A.C.A. 6-5-9 et seq. History and Organization History - Northwest Vocational Technical School (NTI) was established in 975 and became Northwest Technical

More information

PLUMMER ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

Among other things, completion of the project will allow expansion at the campus to include 6 th -8 th graders and serve over 1,000 students.

Among other things, completion of the project will allow expansion at the campus to include 6 th -8 th graders and serve over 1,000 students. 1003 K Street NW Suite 700 Washington, DC 20001 202.223.4505 phone 202.223.4504 fax www.kippdc.org May 2, 2014 REQUEST FOR PROPOSAL ( RFP ) FOR CONSTRUCTION MANAGEMENT SERVICES FOR AN EXPANSION PROJECT

More information

NEW CASTLE COUNTY Department of Land Use FAQ. Child Day Care

NEW CASTLE COUNTY Department of Land Use FAQ. Child Day Care NEW CASTLE COUNTY Department of Land Use FAQ Child Day Care A. Child Day Care in General: Under the New Castle County Unified Development Code (UDC), Child Day Care can be provided in two different settings:

More information

Guideline for Square Footage Requirements for Educational Facilities. 160-5-4-.16 (a) 4. Educational Facility Site, Construction, and Reimbursement

Guideline for Square Footage Requirements for Educational Facilities. 160-5-4-.16 (a) 4. Educational Facility Site, Construction, and Reimbursement Guideline for Square Footage Requirements for Educational Facilities 160-5-4-.16 (a) 4 Educational Facility Site, Construction, and Reimbursement Facilities Services Unit Effective Date: 05-30-12 Page

More information

Proposal for Improving/Expanding Facilities for Career and Technology Education

Proposal for Improving/Expanding Facilities for Career and Technology Education Proposal for Improving/Expanding Facilities for Career and Technology Education Career and Technology Education embraces quality instructional partnerships with business and industry to successfully prepare

More information

How to Analyze and Communicate Preventive Maintenance Address Now or Pay Later

How to Analyze and Communicate Preventive Maintenance Address Now or Pay Later How to ANALYZE AND COMMUNICATE PREVENTIVE MAINTENANCE - ADDRESS NOW - OR PAY LATER Tuesday, February 22, 2012, 10:15 a.m. 11:30 a.m. John Poytress Moderator Clovis USD Doug Halverson Presented by Clovis

More information

Construction Bond Audit Report. Office of Auditor General

Construction Bond Audit Report. Office of Auditor General Construction Bond Audit Report (This page was left blank) TABLE OF CONTENTS Executive Summary 5 Background, Scope and Objectives, and Methodology....7 Audit Findings, Recommendations, and Management s

More information

PROSPECTUS ALTERATION DENVER FEDERAL CENTER BUILDING 53 LAKEWOOD, CO

PROSPECTUS ALTERATION DENVER FEDERAL CENTER BUILDING 53 LAKEWOOD, CO FY2015 Project Summary The General Services Administration (GSA) proposes a repair and alteration project to undertake system and architectural repairs as well as alteration of existing space at the Denver

More information

Facility Status Review

Facility Status Review POLICY 409 APPENDIX A Page 1 of 5 Facility Status Review (NAME OF SCHOOL) (SCHOOL DISTRICT) (DATE PREPARED) POLICY 409 APPENDIX A Page 2 of 5 1. LOCATION: Full address (Insert picture of the school) 2.

More information

DRAPER ELEMENTARY SCHOOL

DRAPER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1953 BUILDING AREA 54,000 SF CURRENT PROGRAM CAPACITY 250 ENROLLMENT 2008 84 WARD 8 PROPOSED PROGRAM CAPACITY 325 Site Plan DRAPER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

DEPARTMENT OF ADMINSTRATIVE SERVICES BUSINESS PLAN

DEPARTMENT OF ADMINSTRATIVE SERVICES BUSINESS PLAN DAS continues to work its strategic plan developed for FY 2012 through FY 2015. The key elements of the strategic plan formulate the framework for the business plan and establish the basis for the rates

More information

University Services: Making the University of Minnesota Work. Facilities Management Bridge Group FY13 Budget Overview Presentation January 17, 2012

University Services: Making the University of Minnesota Work. Facilities Management Bridge Group FY13 Budget Overview Presentation January 17, 2012 University Services: Making the University of Minnesota Work Facilities Management Bridge Group FY13 Budget Overview Presentation January 17, 2012 1 University Services Org Chart Operating Budget: $ 389.6

More information

DISTRICT WIDE: MAGNET, CHARTER SCHOOLS AND PROGRAMS

DISTRICT WIDE: MAGNET, CHARTER SCHOOLS AND PROGRAMS DISTRICT WIDE: MAGNET, CHARTER SCHOOLS AND PROGRAMS FEEDER SYSTEM: 1 HIGH SCHOOLS = (3) Garrett Academy of Technology Academic Magnet HS Septima Clark Academy MIDDLE SCHOOL + HIGH SCHOOL = (2) School of

More information

CALLOWAY COUNTY SCHOOLS DISTRICT FACILITIES PLAN

CALLOWAY COUNTY SCHOOLS DISTRICT FACILITIES PLAN DISTRICT "SHELL" SUBMISSION DATE: 4/17/13 (delete following Hearing) KDE "SHELL" RESUBMISSION DATE: 4/19/13 (delete following Hearing) KBE APPROVAL DATE: JUNE 2013 CALLOWAY COUNTY SCHOOLS DISTRICT FACILITIES

More information

Executive Summary. Clarion-Goldfield High School

Executive Summary. Clarion-Goldfield High School Clarion-Goldfield Community School Mr. Dennis March, Principal 1111 Willow Drive Clarion, IA 50525-0393 Document Generated On October 2, 2015 TABLE OF CONTENTS Introduction 1 Description of the School

More information

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION INTRODUCTION The 5-Year District Facilities Work Program is a very important document. The Department of Education, Legislature, Governor's Office, Division of Community Planning (growth management), local

More information

Regional Entrepreneur Center - (606) 564-2707 http://legacy.maysville.kctcs.edu/mayrec/services.html

Regional Entrepreneur Center - (606) 564-2707 http://legacy.maysville.kctcs.edu/mayrec/services.html With its idyllic setting and close proximity to two large cities, the -Mason County area is the perfect place to live and work. It combines the friendly hospitality of the south, the commerce of the north

More information

PROPERTY FOR LEASE. 3 rd Floor Office Suite, Maxwell House, Armada Way, Plymouth PL1 1HZ

PROPERTY FOR LEASE. 3 rd Floor Office Suite, Maxwell House, Armada Way, Plymouth PL1 1HZ PROPERTY FOR LEASE 3 rd Floor Office Suite, Maxwell House, Armada Way, Plymouth PL1 1HZ Third storey office suite at junction of Mayflower Street and Armada Way Situated within Plymouth s shopping district

More information

CHAPTER 5 - "R1" SINGLE-FAMILY RESIDENTIAL DISTRICT

CHAPTER 5 - R1 SINGLE-FAMILY RESIDENTIAL DISTRICT CHAPTER 5 - "R1" SINGLE-FAMILY RESIDENTIAL DISTRICT Section 5-1. Regulations: The regulations set forth in this chapter, or set forth elsewhere in this ordinance when referred to in this chapter, are the

More information

9,940 SF Office Building

9,940 SF Office Building 204 East Rhapsody Drive, San Antonio, Texas 78216 BUILDING SIZE 9,940 Sq. Ft. (According to Bexar Appraisal District) LAND SIZE 0.6862 Acre or 29,890 Sq. Ft. (According to Bexar Appraisal District) BUILDING

More information

Supplemental Plan Check Corrections Sheet for Bicycle Parking Ordinance (Effective 3/13/2013)

Supplemental Plan Check Corrections Sheet for Bicycle Parking Ordinance (Effective 3/13/2013) Supplemental Plan Check Corrections Sheet for Bicycle Parking Ordinance (Effective 3/13/2013) Plan Check PCIS application number: - - Job Address Zone: P.C. Engineer (E-mail: firstname.lastname@lacity.org)

More information

Priority #1 Old Gymnasium Replacement and Improvements

Priority #1 Old Gymnasium Replacement and Improvements Priority #1 Old Gymnasium Replacement and Improvements $ 5,800,000 State Funding The Division of Health, Physical Education and Recreation (HPER) is located in the Lewy Lee Fieldhouse (built in 1960) and

More information

Facilities Use and Management

Facilities Use and Management Facilities Use and Management Overview The Facilities Use and Management chapter covers the following departments: Construction Management Environmental Compliance Maintenance The Overview section of this

More information

TENNESSEE BASIC EDUCATION PROGRAM 2.0

TENNESSEE BASIC EDUCATION PROGRAM 2.0 TENNESSEE BASIC EDUCATION PROGRAM 2.0 HANDBOOK FOR COMPUTATION Revised April 2014 TENNESSEE DEPARTMENT OF EDUCATION OFFICE OF LOCAL FINANCE 710 JAMES ROBERTSON PARKWAY NASHVILLE, TENNESSEE 37243-0381 FY

More information

Schools Under Construction for N.I.S.D.

Schools Under Construction for N.I.S.D. October 2009 NORTHSIDE INDEPENDENT SCHOOL DISTRICT Schools Under Construction for N.I.S.D. Facilities Construction Vernon Dunagin, AIA Assist. Superintendent of Facilities & Operations Leroy San Miguel

More information

Proposal for Lease of Next 50 Pavilion

Proposal for Lease of Next 50 Pavilion Academy of Interactive Entertainment (AIE WA) 1 Proposal for Lease of Next 50 Pavilion 305 Harrison Street Armory Suite 405 Seattle, WA 98109-4623 October 1, 2015 2 5A. General Overview The Academy of

More information

Raising the Bar: A Comparison Study of Iowa s Current and Proposed Energy Code

Raising the Bar: A Comparison Study of Iowa s Current and Proposed Energy Code Raising the Bar: A Comparison Study of Iowa s Current and Proposed Energy Code Julia Gauthier, LEED AP BD+C Jeanne Huntsman, AIA, LEED Green Associate The Weidt Group Raising the Bar Special statements

More information

Facilities Central Operational Rates and Charging Methodology FY13 & Base for FY14 Planning

Facilities Central Operational Rates and Charging Methodology FY13 & Base for FY14 Planning Facilities Central Operational Rates and Charging Methodology FY13 & Base for FY14 Planning Questions please contact John Kaufhold, Director of Finance & Administration Facilities Rates: Physical Plant

More information

Auto Repair & Mini Lube Facility 12903 Nacogdoches Road - San Antonio TX For Lease For Sale

Auto Repair & Mini Lube Facility 12903 Nacogdoches Road - San Antonio TX For Lease For Sale made. This presentation is offered subject to prior placement and withdrawal, cancellation or modification without notice. 112012 Page 1 Location: Northeast San Antonio / 78217 Convenient to Loop 410,

More information

We know what brings schools together.

We know what brings schools together. School Work We know what brings schools together. About Us Martin Gardner Architecture, P.C. has been providing excellence in design and building consulting services in eastern Iowa for nearly 30 years.

More information

Cherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016

Cherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016 Cherokee Trail High School 25901 East Arapahoe Road Aurora, Colorado 80016 Year Opened 2003 Current Square Footage 391,000 Site Acreage 86.22 cherokeetrail.cherrycreekschools.org $279,200 Asphalt and concrete

More information

Organizational Structure

Organizational Structure Organizational Structure 12 Organizational Structure The Superintendent of Schools shall oversee and hold responsible the Assistant Superintendent of Supporting Services for the implementation of the Comprehensive

More information

CHILD DEVELOPMENT SPECIALIST AUTHORIZATION Renewal Application Checklist

CHILD DEVELOPMENT SPECIALIST AUTHORIZATION Renewal Application Checklist CHILD DEVELOPMENT SPECIALIST AUTHORIZATION Renewal Application Checklist Applicant s Name: Application to become a Child Development Specialist (CDS) is accomplished through school district submission

More information

School Board Proposed Capital Improvements Program. Fiscal Years 2014-2023

School Board Proposed Capital Improvements Program. Fiscal Years 2014-2023 School Board Proposed Capital Improvements Program Fiscal Years 2014-2023 TABLE OF CONTENTS Summary Page 1 Capital Projects Pages 2-6 Capital Projects Description Pages 7-14 SCHOOL BOARD PROPOSED CAPITAL

More information

Heating & Cooling Efficiency

Heating & Cooling Efficiency Heating & Cooling Efficiency Advantages of Geothermal HVAC Efficiency Keith Swilley Gulf Power Company Why Gulf Power Promotes Energy Efficiency? Customer Satisfaction Education Help Customers Make Smart

More information

Vacant. Campus 70 FM 1960 W, Houston, TX 77090

Vacant. Campus 70 FM 1960 W, Houston, TX 77090 Vacant College Campus 70 FM 1960 W, Houston, TX 77090 70 FM 1960 W Size: 31,622 SF, single story, former grocery anchor in retail center. Location: At intersection of I-45 and FM 1960, North Houston. Entire

More information

Agenda Item Action Request Apex Town Council

Agenda Item Action Request Apex Town Council Agenda Item Action Request Apex Town Council PUBLIC HEARING QUASI-JUDICIAL No. 08 Meeting Date: 12/17/2013 Requestor: Planning Department Presenter(s): June Cowles, Senior Planner Item Description Quasi-Judicial

More information

FOR LEASE. 823 Pilot Rd. - Data Center. Las Vegas, NV. Property Features:

FOR LEASE. 823 Pilot Rd. - Data Center. Las Vegas, NV. Property Features: Property Features: Located in Hughes Airport Center Close proximity to McCarren International Airport, I-15, I-215 and the Las Vegas Strip First class 420 acre 3.3 million sq. ft. business park Turnkey

More information

Executive Director s Recommendation Commission Meeting: March 5, 2015

Executive Director s Recommendation Commission Meeting: March 5, 2015 Executive Director s Recommendation Commission Meeting: March 5, 2015 PROJECT Curseen-Morris Processing and Distribution Center Parking Lot 900 Brentwood Avenue NE Washington, DC SUBMITTED BY United States

More information

ELEMENTARY SCHOOL ORDER OF MAGNITUDE ESTIMATE March 28, 2013

ELEMENTARY SCHOOL ORDER OF MAGNITUDE ESTIMATE March 28, 2013 ELEMENTARY SCHOOL ORDER OF MAGNITUDE ESTIMATE March 28, 2013 CEDAR PARK ELEMENTARY (INTERIM FACILITY) Minor Renovate Existing School Students On Site FALL 2015 OPEN MACC I Minor Renovate Existing School

More information

Executive Summary. San Antonio Country Day Montessori School. Mrs. Betty Williams, Principal 4194 Jung Road San Antonio, TX 78247

Executive Summary. San Antonio Country Day Montessori School. Mrs. Betty Williams, Principal 4194 Jung Road San Antonio, TX 78247 Mrs. Betty Williams, Principal 4194 Jung Road San Antonio, TX 78247 Document Generated On December 1, 2014 TABLE OF CONTENTS Introduction 1 Description of the School 2 School's Purpose 4 Notable Achievements

More information

STRATEGIC TECHNOLOGY PLAN

STRATEGIC TECHNOLOGY PLAN STRATEGIC TECHNOLOGY PLAN 2015-2018 Approved: February 1, 2016 Table of Contents Introduction Vision and Mission Statement The DESE Local Technology Plan Guidelines Strategic Planning and Budgeting Goals

More information

Court Facilities LINK TO THE COMPREHENSIVE PLAN. Fairfax County's Comprehensive Plan has established a number of objectives and policies in order to:

Court Facilities LINK TO THE COMPREHENSIVE PLAN. Fairfax County's Comprehensive Plan has established a number of objectives and policies in order to: Court Facilities PROGRAM DESCRIPTION The current focus of the County s criminal justice system is to provide adequate court facilities and update aging jail security systems. LINK TO THE COMPREHENSIVE

More information

SCHOOL DISTRICT BUILDING RENOVATION 2016 Opportunity Questions and Answers

SCHOOL DISTRICT BUILDING RENOVATION 2016 Opportunity Questions and Answers SCHOOL DISTRICT BUILDING RENOVATION 2016 Opportunity Questions and Answers WHAT IS THE ISSUE? Last year our School Board entered into a full-scale study of our educational facilities conducted by the Ohio

More information

SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST

SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST SODA SPRINGS HIGH SCHOOL REPAIRS AND UPGRADES SITE Construction Estimate = $100,000

More information

Online Survey Executive Summary

Online Survey Executive Summary Online Survey Executive Summary Center Moriches School District March 9, 2015 Online Survey Executive Summary METHODOLOGY The following results are based on a website and paper survey of 356 residents

More information

375 - Central Washington University Capital Project Request. 2015-17 Biennium

375 - Central Washington University Capital Project Request. 2015-17 Biennium Starting Fiscal Year: 2012 Project Class: Program Agency Priority: 3 Project Summary CWU completed a self-funded predesign on the existing vacated Samuelson Union Building (SUB) in June 2010, which was

More information

City of Maysville - (606)

City of Maysville - (606) With its idyllic setting and close proximity to two large cities, the -Mason County area is the perfect place to live and work. It combines the friendly hospitality of the south, the commerce of the north

More information

CHILLED WATER SYSTEM MASTER PLAN GEORGIA INSTITUTE OF TECHNOLOGY. David W. Wade, P.E. RDA Engineering, Inc. Atlanta, Georgia

CHILLED WATER SYSTEM MASTER PLAN GEORGIA INSTITUTE OF TECHNOLOGY. David W. Wade, P.E. RDA Engineering, Inc. Atlanta, Georgia CHILLED WATER SYSTEM MASTER PLAN GEORGIA INSTITUTE OF TECHNOLOGY David W. Wade, P.E. RDA Engineering, Inc. Atlanta, Georgia ABSTRACT Hosting the 1996 Olympic Village resulted in accelerated dormitory construction

More information

For Lease Sale in in Kitsap County

For Lease Sale in in Kitsap County For Lease Sale in in Kitsap County Former Kitsap Bank - Bremerton $949,000 6733 State Highway 303 Next to Walmart, Kitsap Credit Union, eineke, cdonald s. 3,580 SF building; 38,333 SF site with 231 feet

More information

DAVIESS COUNTY SCHOOLS DISTRICT FACILITIES PLAN

DAVIESS COUNTY SCHOOLS DISTRICT FACILITIES PLAN DISTRICT "SHELL" SUBMISSION DATE: 11/13/12 questions 11/26/12 (delete following Hearing) KDE "SHELL" RESUBMISSION DATE: 11/19/12 revised 11/26/12 (delete following Hearing) KBE APPROVAL DATE: FEBRUARY

More information

Special Purpose Local- Option Sales Tax IV

Special Purpose Local- Option Sales Tax IV Special Purpose Local- Option Sales Tax IV and Positioning APS for Continued Success in the Future August 13, 2012 1 Background Passage of SPLOST Referenda Referendum 1: 1997-2002 Referendum 2: 2002-2007

More information

Portland s Financial District. Overview FOR SALE RETAIL/OFFICE BUILDING 6-8 CITY CENTER, PORTLAND, MAINE

Portland s Financial District. Overview FOR SALE RETAIL/OFFICE BUILDING 6-8 CITY CENTER, PORTLAND, MAINE FOR SALE RETAIL/OFFICE BUILDING Portland s Financial District Overview 6-8 City Center is a well know 4-story retail and office building with a mix of granite and brick architecture and interesting interior

More information

VILLAGE OF PLEASANT PRAIRIE COMMERCIAL COMMUNICATION PERMIT

VILLAGE OF PLEASANT PRAIRIE COMMERCIAL COMMUNICATION PERMIT VILLAGE OF PLEASANT PRAIRIE COMMERCIAL COMMUNICATION PERMIT CLASS 1 COLLOCATION New Commercial Communication Structure Substantial Modification Please check one of the following: CLASS 2 COLLOCATION OTHER

More information

NWC Culebra & FM 1560 @ ALAMO RANCH PARKWAY HIGH-GROWTH FAR NW SAN ANTONIO, TX

NWC Culebra & FM 1560 @ ALAMO RANCH PARKWAY HIGH-GROWTH FAR NW SAN ANTONIO, TX Stillwater Ranch Scarborough Silver Oaks 1,700 lots Jefferson M.S. Ward SITE Carmel Canyon Apts 124 units Culebra Creek Soccer Park Meadows of Bridgewood 2,700 lots 1604 Greater Northwest ALAMO RANCH 3,500

More information

North East Independent School District 2011 Bond Proposal

North East Independent School District 2011 Bond Proposal North East Independent School District 2011 Bond Proposal North East ISD Garrett J. Sullivan, Executive Director Construction Management & Engineering Department The Process Community Planning and Advisory

More information

FOR SALE: $489,000. 7578 Seymour Highway Wichita falls, TX 76310 TC TRAILERS BUSINESS

FOR SALE: $489,000. 7578 Seymour Highway Wichita falls, TX 76310 TC TRAILERS BUSINESS 7578 Seymour Highway Wichita falls, TX 76310 TC TRAILERS BUSINESS FOR SALE: $489,000 Very good Real Estate! Includes 6.15 Acres, 2400 Sq. Ft. Building with Septic & Fence. Lots of Potential. VERY BANKABLE.

More information

Information Systems. Background

Information Systems. Background Background The goal of the Information Systems is to provide an integrated set of information systems to efficiency and effectively support the administration and operational needs of the District. Functional

More information

Post Occupancy Evaluation (POE) Technical Instructions

Post Occupancy Evaluation (POE) Technical Instructions 1.0 Purpose These technical instructions define the typical steps required by HHS personnel in the use of the. The POE consists of a detailed and systematic assessment of a facility that is operational

More information