Design and construction aspects of piled foundations for Eureka Tower Project

Size: px
Start display at page:

Download "Design and construction aspects of piled foundations for Eureka Tower Project"

Transcription

1 Deep Foundations on Bored and Auger Piles Van Impe & Van Impe (eds) 2009 Taylor & Francis Group, London, ISBN Design and construction aspects of piled foundations for Eureka Tower Project Jim Slatter & Slav Tchepak Vibropile (Aust) Pty Ltd, Melbourne, Australia ABSTRACT: The Eureka Tower project involved the construction of a 300 m high 92-storey tower, the world s tallest apartment tower at the time, located in Melbourne s Southbank area. An unusual feature of the building is its slenderness, having a height to base ratio of 6 to 1. The construction of the foundations for the project proved to be a challenging task. The geological conditions at the site were complex, highly variable and posed significant construction and technical difficulties, with two layers of high to very high strength basalt above high strength Silurian Siltstone bedrock at a depth of approximately 35 m. The ground water table occurred at 2 m depth and the upper and lower basalt layers were not continuous across the site. To add to the complexity, the loadings imposed on the foundations by the structure were high. The lower basalt provided a suitable founding medium, provided that sufficient thickness was available to ensure that settlements of underlying soils were within acceptable limits. This was difficult to define because of the discontinuous nature of the lower basalt and the variable thickness of that stratum. The foundation solution that ultimately proved to be the most cost-effective was a combination of CFA piles founded on the very high strength lower basalt flow and Bored piles constructed under bentonite drilling fluid founded in the high strength Siltstone when there was insufficient thickness of the lower basalt. This paper discusses the design and construction aspects of the piled foundations for these challenging conditions, including the additional site investigation required to define areas appropriate for each pile type; construction of the piles and the special techniques required to ensure clean bases for the heavily loaded piles; and the testing regime that comprised Statnamic and Dynamic pile loading tests. 1 INTRODUCTION The site for the 92 storey apartment building was originally an industrial area. Because of its proximity to the CBD of Melbourne and the Yarra River, the area rapidly evolved to commercial and apartment usage. Extensive geotechnical work had been carried out for previous developments on the site, which were abandoned, partly because of the costs of providing economical foundation solutions for multistorey developments in the challenging soil conditions. Local builder Grocon proposed a 92 storey apartment building which presented even greater challenges for the structural, geotechnical and piling engineers to provide an economical foundation system given the high loadings that result from such tall structures. The structure had a relatively small footprint, resulting in a height to base ratio of 6 to 1. The top of the tower can flex up to 600 mm in high winds with resulting oscillations being dampened by two 300 ML water tanks on levels 90 and 91. The builder, Grocon, in conjunction with consulting structural engineers Connell Mott MacDonald and geotechnical consultants Golder Associates, issued documentation for the tower foundations comprising bored piles socketed into the strong Silurian bedrock. Initially the piling work was priced on the conforming solutions utilising bored methods, the equipment and expertise for which needed to be imported due to the requirement to penetrate up to 8 m of massive, very high strength Basalt at up to 1.5 m diameter. The costs of the conforming solutions considerably exceeded budget expectations both in terms of cost and program and the project was at significant risk of not proceeding. 2 SITE GEOLOGY The geological conditions at the site are complex and difficult. It is not possible to provide a simple tabulation of soil types with depth, nor will reproduction 323

2 Figure 1. Section DD. Figure 2. Section FF. 324

3 Figure 3. Final layout of CFA & bored piles. of bore logs provide a realistic depiction of the geotechnical conditions. The geological complexity of the site was primarily due to two layers of basalt occurring above the Silurian Siltstone bedrock that occurs at a depth of about 35 to 37 m depth. The upper basalt is sandwiched between layers of clay that varied in consistency from soft to very stiff. The upper basalt varied in thickness from zero to about 8 m and was typically of high strength, 80 to 100 MPa and most commonly highly fractured, with fracture spacings typically not greater than 300 mm The lower layer of basalt was generally overlain by dense sands and gravels, occasionally underlain by the same sand and gravel strata or occasionally sitting directly on the siltstone bedrock. The lower basalt was of very high strength, indicated by testing to be in excess of 200 MPa and tended to be massive. The ground water table occurred at 2 m depth. Neither the upper or lower basalts were continuous across the site. The siltstone bedrock was typically a strong rock (up to 80 MPa), with the upper 1 to 2 m being relatively highly jointed before becoming massive in formation. Cross sections from the relatively small site are shown in Figs. 1 and 2 that highlight the variability in soil conditions. 3 DESIGN CONSIDERATIONS Founding piles or pile groups on the upper, highly fractured basalt was not an option because of the high loads, which would result in excessive settlement of foundations due to the compressible soils underlying the upper basalt. By contrast the massive lower basalt provided a suitable founding medium, provided that sufficient thickness was available to ensure that settlements of underlying soils were within acceptable limits. This was difficult to define because of the discontinuous nature of the lower basalt and the variable thickness of that stratum. As a consequence, an extensive geotechnical investigation was performed by the geotechnical engineer to better characterise the condition and extent of the lower basalt with a view to revising the foundation solution. The geotechnical design responsibility remained with the geotechnical engineer, who determined that a minimum of 5 m of strong lower basalt would be required to ensure satisfactory performance of piles founded in that stratum. Where 5 m of basalt was not available, piles would need to be bored through the basalt and socketed into the underlying strong siltstone. A variety of solutions were considered including: An initial proposal to utilise 76 No m dia piles socketed into siltstone 110 No mm dia bored piles socketed into siltstone Foundation solutions included construction utilising conventional and reverse circulation drilling methods. Interestingly, because of the difficulties of penetrating the very high strength basalts in particular, costs were found to be cheaper for a larger number of 1200 mm dia piles compared to 1500 mm solutions, especially when relatively high strength 325

4 concrete (70 MPa) was used and piles loaded up to the safe structural limits of the pile shafts for both piletypes. A solution was then proposed by the piling contractor to use high capacity CFA piles founded on the lower basalts where possible, with 1200 mm dia bored piles socketed into siltstone where the lower basalts were less than 5 m thick. This solution was found to be significantly cheaper than all-bored pile solutions and offered considerable savings in construction programme. A final solution incorporating the following was adopted: 243 No. CFA piles 750 mm dia founded on the lower basalt, to a unit pile design (i.e. ultimate) load of 9250 kn (corresponding to a working load of approximately 6800 kn). 28 No.1200 mm dia bored piles socketed in siltstone for ultimate loads of up to 32 MN (working load approximately 25 MN). An allowable stress was adopted as 20 MPa in the basalt. The design of bored piles in the siltstone was done using the program ROCKET to ensure that estimated settlements of those piles would be compatible with bored piles founded in the basalt. Consequently the settlement at the top of the siltstone socket was restricted to 6 mm and resulted in sockets of 4.5 m length. 4 CONSTRUCTION ISSUES A number of issues had to be addressed, including: Proving the performance of CFA piles would be in accordance within specified criteria by load testing those piles. Confirming the constructability of the bored piles, to enable confirmation of production rates and pricing structure of those piles. Confirming that construction procedures for bored piles founded in either the basalt or the siltstone will be satisfactory and that those procedures can be implemented on a routine basis should the CFA trials not meet expectations. In addition to the above technical considerations, the site was also extremely congested due to the multiple concurrent activities which were had to be scheduled in order to meet the extremely challenging construction program. As a result, site management was critically important and the movement of each item of plant needed to be carefully co-ordinated in order to prevent clashes (see Figure 4). 4.1 CFA piles During the course of production piling approximately 75% of the piles required predrilling through the upper basalt layer using crane mounted drilling rigs. After predrilling, the excavation was backfilled with Figure 4. Site congestion was a major concern. cement stabilised sand, ready for construction of CFA piles. Predrilling of clustered piles was be sequenced such that following casting of any pile in the cluster, subsequent predrilling for the next pile would not take place for at least three days. CFA piles were drilled to effective refusal to found on top of the lower basalt and constructed using concrete injection techniques. Due to the sloping surface and negligible weathering profile of the lower basalt, specially designed rock drilling heads had to be adopted to ensure that CFA piles were adequately seated into the very high strength lower basalt. Every aspect of pile construction was fully monitored by on-board computers to ensure the highest quality construction. 4.2 Bored Piles Bored piles required drilling through up to two layers of high to very high strength basalt to socket into the high strength siltstone. Construction under bentonite drilling fluid was adopted as the most economical approach to the difficult conditions. The sockets were formed using conventional rotary drilling methods however extremely high 326

5 powered machines were required. A 55 tm crane mount drill was required to core through the very high strength basalt (Fig. 5). To facilitate base cleanliness, a series of purpose built tools were developed. Firstly a pilot hole/sump was formed centrally at the base of the 1200 mm diameter socket, a second tool was then deployed to mill a flat surface (or ledge) at the base of the pile (Fig. 6) and finally a third tool was used to sweep any debris on the milled ledge into the sump thus providing a high degree of cleanliness on the load bearing ledge at the pile toe (Fig. 7). The sump, which was formed by coring and chiselling was 600 mm diameter and 600 mm length. The purpose of the sump was to attract base debris during construction, ensuring the remaining 75% of base area to fully utilise end-bearing. Socket walls were grooved in accordance with the requirements of the ROCKET analyses, namely, a minimum 5.5 mm deep by 6 mm wide groove at 100 mm spacing. Piles were concreted within 24 hours of completion of socket drilling, with socket grooving and desanding (to ensure a maximum sand content of 1%) operations carried out on the same day as concreting. Socket inspections by underwater video camera proved the efficacy of construction methods in providing a clean pile base that would satisfactorily support the high loadings. 5 PILE TESTING An initial trial piling programme was instigated to confirm the veracity of the proposed CFA construction technique and to confirm the estimated construction programme. Two non-production CFA piles were constructed and load tested to destruction. While it was understood that all production CFA piles would be drilled to effective refusal, one Figure 6. Ledge, milling & sump coring tool. Figure 5. Coring of basalt. Figure 7. Ledge sweeping tool. 327

6 test pile was purposely terminated as soon as the auger reached the lower basalt, while the other was drilled to refusal. The purpose of the former was to simulate the potential effects of partial contact with the basalt. 5.1 Bored piles Load tests were not done on any bored piles, however a remote socket inspection device (SID) was used on two bored piles to verify the cleanliness of the milled and swept ledge, and the pile sump. The results of the SID inspections proved that unique construction procedure adopted for the pile toes had met the design objectives and that the ledge had been cleaned to satisfactorily high levels. On this basis the construction procedure for all future bore piles on the project was approved and strict QA procedures were implemented to ensure that these procedures were adhered to. 5.2 CFA piles The two trial CFA piles were subjected to load testing by Statnamic and dynamic methods. Dynamic tests were carried out using a drop hammer of 20 tonne mass after completion the Statnamic tests. The costs of doing Statnamic testing precluded testing of a large number of piles on the project, so the purpose of the subsequent dynamic tests on the trial piles was to gain a correlation with Statnamic and provide confidence in dynamic methods for future routine testing of production piles. The results of the loading tests on the trial piles are shown in Fig. 8. The results of the comparative tests indicated a slightly less stiff response from the dynamic tests compared to the Statnamic tests. However the performance of the piles for both tests was satisfactory. The magnitude of the mobilised loads during the tests was not sufficient to conclusively prove the difference in drilling methods. Although the piles were to be tested to destruction, it was not possible to impart sufficient energy during the tests to damage the piles. Pile Top Load (kn) Figure 8. Pile No Displacement (mm) DLT 128kJ Statnamic UPM Pile Top Load (kn) Pile No Displacement (mm) DLT362kJ Statnamic UPM Comparative statnamic and dynamic load tests. During routine piling an additional 5% of the piles were tested dynamically, with all results between the bounds of the DLT results indicated in Fig. 8. All parties were satisfied that the load testing regime was satisfactory given the level of QA available from the computerised monitoring of every CFA pile. 6 CONCLUDING REMARKS A cost-effective and innovative solution for the foundations for the Eureka Tower project was brought about by co-operation between consulting structural and geotechnical engineers and piling contractors in what were extremely difficult geotechnical conditions. The application of different pile types and construction techniques was novel and innovative and resulted in the final cost of the foundations being reduced by over 30% and the program reduced by approximately 3 months. The construction was performed in difficult circumstances compounded by the restricted space available on site. In this manner, the skills of all parties were utilised, to the benefit of the project. REFERENCES Seidel, J.P Rocket 3.0 Manual. Monash University. Melbourne. Golder Associates Report on geotechnical investigation. Eureka Tower. South Bank. No

Anirudhan I.V. Geotechnical Solutions, Chennai

Anirudhan I.V. Geotechnical Solutions, Chennai Anirudhan I.V. Geotechnical Solutions, Chennai Often inadequate In some cases, excess In some cases, disoriented Bad investigation Once in a while good ones Depends on one type of investigation, often

More information

PILE FOUNDATIONS FM 5-134

PILE FOUNDATIONS FM 5-134 C H A P T E R 6 PILE FOUNDATIONS Section I. GROUP BEHAVIOR 6-1. Group action. Piles are most effective when combined in groups or clusters. Combining piles in a group complicates analysis since the characteristics

More information

Design and Construction of Auger Cast Piles

Design and Construction of Auger Cast Piles Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com CONTENTS 1.

More information

The advantages and disadvantages of dynamic load testing and statnamic load testing

The advantages and disadvantages of dynamic load testing and statnamic load testing The advantages and disadvantages of dynamic load testing and statnamic load testing P.Middendorp & G.J.J. van Ginneken TNO Profound R.J. van Foeken TNO Building and Construction Research ABSTRACT: Pile

More information

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Stephen W. Lacz 1, M. ASCE, P.E. and Richard C. Wells 2, F. ASCE, P.E. 1 Senior Professional, Trigon Kleinfelder, Inc., 313 Gallimore

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

DESIGNING STRUCTURES IN EXPANSIVE CLAY

DESIGNING STRUCTURES IN EXPANSIVE CLAY DESIGNING STRUCTURES IN EXPANSIVE CLAY A GUIDE FOR A RCHITECTS AND E NGINEERS Table of Contents 1. Introduction Page 1 2. Common Foundation Systems Page 2 3. Drilled Piers Page 3 a. Skin Friction Piers

More information

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples Prof. V.S.Raju (Formerly: Director, IIT Delhi & Professor and Dean, IIT Madras) Email: rajuvs_b@yahoo.com

More information

How To Retaining Wall Guide

How To Retaining Wall Guide How To Retaining Wall Guide Before you start: Consents and Engineering Building Consent Retaining walls over 1.5m high will require a building consent from the Local Body Council. Walls that carry extra

More information

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations Cambridge City Council - East Cambridgeshire District Council - Fenland District Council, Huntingdonshire

More information

INDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode

INDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode INDIRECT METHODS SOUNDING OR PENETRATION TESTS STANDARD PENETRATION TEST (SPT) Reference can be made to IS 2131 1981 for details on SPT. It is a field edtest to estimate e the penetration e resistance

More information

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering

More information

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load

More information

KWANG SING ENGINEERING PTE LTD

KWANG SING ENGINEERING PTE LTD KWANG SING ENGINEERING PTE LTD 1. INTRODUCTION This report represents the soil investigation works at Aljunied Road / Geylang East Central. The objective of the soil investigation is to obtain soil parameters

More information

Design and installation of steel open end piles in weathered basalt. Luc Maertens*

Design and installation of steel open end piles in weathered basalt. Luc Maertens* Design and installation of steel open end piles in weathered basalt Luc Maertens* * Manager Engineering Department Besix, Belgium, lmaertens@besix.com Associate Professor Catholic University Leuven, luc.maertens@bwk.kuleuven.ac.be

More information

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:! In-situ Testing! Insitu Testing! Insitu testing is used for two reasons:! To allow the determination of shear strength or penetration resistance or permeability of soils that would be difficult or impossible

More information

How To Design A Foundation

How To Design A Foundation The Islamic university - Gaza Faculty of Engineering Civil Engineering Department CHAPTER (2) SITE INVESTIGATION Instructor : Dr. Jehad Hamad Definition The process of determining the layers of natural

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle EPB-TBM Face Support Control in the Metro do Porto Project, Portugal S. Babendererde, Babendererde Engineers LLC, Kent, WA; E. Hoek, Vancouver,

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL SCOPE This section of the specifications includes requirements for the Slurry Trench Cutoff Wall and related work as indicated on the

More information

Piling Datasheets. Continuous flight auger (CFA) Driven Rotary

Piling Datasheets. Continuous flight auger (CFA) Driven Rotary Piling Datasheets Continuous flight auger (CFA) Driven Rotary Continuous Flight Auger Piles (CFA) Technical Data Application Well suited to soft and/or water bearing ground where deep casings or bentonite

More information

Emergency repair of Bridge B421

Emergency repair of Bridge B421 Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)

More information

EVALUATING THE IMPROVEMENT FROM IMPACT ROLLING ON SAND

EVALUATING THE IMPROVEMENT FROM IMPACT ROLLING ON SAND EVALUATING THE IMPROVEMENT FROM IMPACT ROLLING ON SAND D.L. Avalle, Broons Hire (SA) Pty Ltd, Australia J.P. Carter, The University of Sydney, Australia Abstract Impact rolling, utilising a non-circular

More information

METHOD STATEMENT HIGH STRIAN DYNAMIC TESTING OF PILE. Prepared by

METHOD STATEMENT HIGH STRIAN DYNAMIC TESTING OF PILE. Prepared by METHOD STATEMENT HIGH STRIAN DYNAMIC TESTING OF PILE Prepared by Infratech ASTM CO., LTD. Contents Chapter Description Page Contents...... 1 List of Appendix. 1 1. Introduction.. 2 2. Test Method..2 3.

More information

ATLAS RESISTANCE Pier Foundation Systems

ATLAS RESISTANCE Pier Foundation Systems ATLAS RESISTANCE Pier Foundation Systems Foundation Repair Systems for Civil Construction Applications: Residential, Commercial, Industrial Atlas Resistance Piers have been used to restore and/or stabilize

More information

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located

More information

SERVICES 2015 ISO 18001

SERVICES 2015 ISO 18001 SERVICES 2015 A family business with a solid foundation of experience, we handle all aspects of site investigation.... Phase 1 Environmental Studies Phase 2 Intrusive Investigations Phase 3 Remediation

More information

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage 3.3. Evaluation of Building Foundation Damage Basic Terminology: Damage: Destruction, deformation, inclination and settlement of a building foundation caused by an earthquake. Damage grade: Degree of danger

More information

GLOSSARY OF TERMINOLOGY

GLOSSARY OF TERMINOLOGY GLOSSARY OF TERMINOLOGY AUTHORIZED PILE LENGTHS - (a.k.a. Authorized Pile Lengths letter) Official letter stating Engineer's recommended length of concrete piles to be cast for construction of foundation.

More information

PDCA Driven-Pile Terms and Definitions

PDCA Driven-Pile Terms and Definitions PDCA Driven-Pile Terms and Definitions This document is available for free download at piledrivers.org. Preferred terms are descriptively defined. Potentially synonymous (but not preferred) terms are identified

More information

Jack-in Piling Environmental Friendly Piling System

Jack-in Piling Environmental Friendly Piling System Jack-in Piling Environmental Friendly Piling System Part 1 - Chris Loh 7 Nov 12 CSC HOLDINGS LIMITED Gracious Piling Environmental Friendly Low Noise No Vibration Jack-in Piling How Many Decibels? Permissible

More information

ALLOWABLE LOADS ON A SINGLE PILE

ALLOWABLE LOADS ON A SINGLE PILE C H A P T E R 5 ALLOWABLE LOADS ON A SINGLE PILE Section I. BASICS 5-1. Considerations. For safe, economical pile foundations in military construction, it is necessary to determine the allowable load capacity

More information

1 Mobilisation and demobilisation 1 Deep boring sum 2 Cone penetration tests sum 3 Miscellenous tests sum

1 Mobilisation and demobilisation 1 Deep boring sum 2 Cone penetration tests sum 3 Miscellenous tests sum Malaysian Civil Engineering Standard Method of Measurement (MyCESMM) CLASS D: SITE INVESTIGATION WORK Measurement covered under other classes: Excavation not carried out for the purpose of soil investigation

More information

Dynamic Load Testing of Helical Piles

Dynamic Load Testing of Helical Piles Dynamic Load Testing of Helical Piles ANNUAL KANSAS CITY SPECIALTY SEMINAR 2014 JANUARY 10, 2014 Jorge Beim JWB Consulting LLC Pile Dynamics, Inc. Main Topics Brief description of the Dynamic Load Test

More information

Site Investigation. Some unsung heroes of Civil Engineering. buried right under your feet. 4. Need good knowledge of the soil conditions

Site Investigation. Some unsung heroes of Civil Engineering. buried right under your feet. 4. Need good knowledge of the soil conditions This is an attempt to create a stand alone self learning module on site investigation. Fasten your seat belts. Sit back, relax and enjoy. 1 2 Site Investigation Some unsung heroes of Civil Engineering

More information

GUIDELINE FOR HAND HELD SHEAR VANE TEST

GUIDELINE FOR HAND HELD SHEAR VANE TEST GUIDELINE FOR HAND HELD SHEAR VANE TEST NZ GEOTECHNICAL SOCIETY INC August 2001 CONTENTS Page 1.0 Introduction 2 2.0 Background 2 3.0 Recommended Practice 3 4.0 Undrained Shear Strength 3 5.0 Particular

More information

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code LEGACY REPORT Reissued November 1, 2003 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900

More information

UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA

UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA John R. Wolosick, P.E.,D.GE 1, Michael W. Terry, P.E. 2, W. David Kirschner 3 and Robert F. Scott Jr. P.E. 4 SYNOPSIS In

More information

vulcanhammer.net This document downloaded from

vulcanhammer.net This document downloaded from This document downloaded from vulcanhammer.net since 1997, your source for engineering information for the deep foundation and marine construction industries, and the historical site for Vulcan Iron Works

More information

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362 California Department of Transportation Doyle Drive Test Program Deep Soil Mixing (DSM) /Cutter Soil Mixing (CSM) Testing Report By Malcolm Drilling Company, Inc. 3524 Breakwater Ave., Suite 108 Hayward,

More information

Geotechnical Investigation using Standard Penetration Test (SPT) in Rangamati, Bandarban and Khagrachari Towns

Geotechnical Investigation using Standard Penetration Test (SPT) in Rangamati, Bandarban and Khagrachari Towns 1. Introduction 1.1 Scope of Work The Asian Disaster Preparedness Centre (ADPC) is implementing the project Seismic Hazard and Vulnerability Mapping for Rangamati, Bandarban and Khagrachari Municipality.

More information

APPENDIX A PRESSUREMETER TEST INTERPRETATION

APPENDIX A PRESSUREMETER TEST INTERPRETATION APPENDIX A PRESSUREMETER TEST INTERPRETATION PRESSUREMETER TEST INTERPRETATION Description of test The pressuremeter test, discussed in great detail by Martin (1977), Baguelin et al. (1978), Barksdale

More information

High Capacity Helical Piles Limited Access Projects

High Capacity Helical Piles Limited Access Projects High Capacity Helical Piles Limited Access Projects Tel 403 228-1767 Canada, USA, Russia Brendan ODonoghue 519 830-6113 Presentation Summary 1. Helical piles Background on large diameter shafts and helices

More information

CIVL451. Soil Exploration and Characterization

CIVL451. Soil Exploration and Characterization CIVL451 Soil Exploration and Characterization 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally

More information

Pile test at the Shard London Bridge

Pile test at the Shard London Bridge technical paper Pile test at the Shard London Bridge David Beadman, Byrne Looby Partners, Mark Pennington, Balfour Beatty Ground Engineering, Matthew Sharratt, WSP Group Introduction The Shard London Bridge,

More information

SECTION 10 WATER WELL SUPPLY 10.01 SCOPE OF WORK

SECTION 10 WATER WELL SUPPLY 10.01 SCOPE OF WORK 10.01 SCOPE OF WORK The work covered by this section of the specifications consists in furnishing all labor, equipment and material necessary to perform the installation of a Type I water supply well per

More information

Guide to working on Public Sewers

Guide to working on Public Sewers Guide to working on Public Sewers affected by Building Works Introduction Severn Trent Water Ltd requires the work to be done in order to protect the public sewer and minimise the risk of us having to

More information

REPORT. Earthquake Commission. Christchurch Earthquake Recovery Geotechnical Factual Report Merivale

REPORT. Earthquake Commission. Christchurch Earthquake Recovery Geotechnical Factual Report Merivale REPORT Earthquake Commission Christchurch Earthquake Recovery Geotechnical Factual Report Merivale REPORT Earthquake Commission Christchurch Earthquake Recovery Geotechnical Factual Report Merivale Report

More information

Dead load (kentledge) A structure over the test pile. Ground anchorage either by tension piles or ground anchors. Bi-directional (Osterberg-cell)

Dead load (kentledge) A structure over the test pile. Ground anchorage either by tension piles or ground anchors. Bi-directional (Osterberg-cell) Introduction Fugro LOADTEST Overview STATIC LOAD TESTING O-cell Bi-directional testing State of the art Dr Melvin England Fugro LOADTEST Static load tests Previous/existing technology Developments O-cell

More information

T2: Reduce overall transport cost by cost effective road rehabilitation and maintenance

T2: Reduce overall transport cost by cost effective road rehabilitation and maintenance PROJECT REPORT PR/INT/277/04 Dynamic Cone Penetrometer tests and analysis Technical Information Note By Colin Jones Sector: Theme: Project Title: Project Reference: Transport T2: Reduce overall transport

More information

Requirements for an Excavation and Lateral Support Plan Building (Administration) Regulation 8(1)(bc)

Requirements for an Excavation and Lateral Support Plan Building (Administration) Regulation 8(1)(bc) Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-57 Requirements for an Excavation and Lateral Support Plan Building

More information

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet

More information

Load Testing of Drilled Shaft Foundations in Limestone, Nashville, TN Dan Brown, P.E., Ph.D.

Load Testing of Drilled Shaft Foundations in Limestone, Nashville, TN Dan Brown, P.E., Ph.D. Dan A. Brown and Associates Consulting Geotechnical Engineers 300 Woodland Rd. (423)942-8681 Sequatchie, TN 37374 fax:(423)942-8687 Load Testing of Drilled Shaft Foundations in Limestone, Nashville, TN

More information

A CASE STUDY: DESIGN AND CONSTRUCTION OF FOUNDATION AND BRACED EXCAVATION AT A RECLAIMED SITE AT WATERFRONT

A CASE STUDY: DESIGN AND CONSTRUCTION OF FOUNDATION AND BRACED EXCAVATION AT A RECLAIMED SITE AT WATERFRONT A CASE STUDY: DESIGN AND CONSTRUCTION OF FOUNDATION AND BRACED EXCAVATION AT A RECLAIMED SITE AT WATERFRONT Rupert KY Leung Hyder Consulting Ltd Dr Eric SF Li Hyder Consulting Ltd Cheuk-lun Leung Drainage

More information

DESIGN OF PILES AND PILE GROUPS CONSIDERING CAPACITY, SETTLEMENT, AND NEGATIVE SKIN FRICTION

DESIGN OF PILES AND PILE GROUPS CONSIDERING CAPACITY, SETTLEMENT, AND NEGATIVE SKIN FRICTION DESIGN OF PILES AND PILE GROUPS CONSIDERING CAPACITY, SETTLEMENT, AND NEGATIVE SKIN FRICTION Introduction Bengt H. Fellenius, Dr.Tech., P.Eng. Background Notes for Demo Example for UniPile at www.unisoftltd.com

More information

Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file

Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file Notation B1 = lowest level of basement slab c = cohesion E = drained Young s Modulus Eu = undrained Young s Modulus

More information

The Installation and Load Testing of Drilled Shafts

The Installation and Load Testing of Drilled Shafts Presentation to the North American Chinese Geotechnical Engineers Association The Installation and Load Testing of Drilled Shafts at Clarksville, Virginia by James M. Sheahan, P.E. HDR Engineering, Inc.

More information

Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting

Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting MnDOT Contract No. 1003249 General Project Overview This work is located along Trunk Highway (TH) 23, for State Project (SP) 7305-124.

More information

load on the soil. For this article s examples, load bearing values given by the following table will be assumed.

load on the soil. For this article s examples, load bearing values given by the following table will be assumed. How Many Piers? By Gary Collins, P.E. A clear-cut guide to helical pier spacing Introduction Helical pier spacing is not an exact science. How many does it take to support a structure adequately or repair

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

Guidelines for Earthquake Bracing Residential Water Heaters

Guidelines for Earthquake Bracing Residential Water Heaters Guidelines for Earthquake Bracing Residential Water Heaters Department of General Services Division of the State Architect In accordance with the Health and Safety Code Section 19215, the Division of the

More information

Severn Trent Water Ltd has undergone a massive investment programme in the River Tame catchment over the

Severn Trent Water Ltd has undergone a massive investment programme in the River Tame catchment over the Tame Urban Pollution Management Foxton Road & Sir Johns Road CSOs - collaborative working to deliver innovative solutions Severn Trent Water Ltd has undergone a massive investment programme in the River

More information

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge. TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may

More information

Geotechnical Building Works (GBW) Submission Requirements

Geotechnical Building Works (GBW) Submission Requirements Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.

More information

EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK. Ellenbrook, W.A. Georgiou Group Pty Ltd

EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK. Ellenbrook, W.A. Georgiou Group Pty Ltd EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK Ellenbrook, W.A. Georgiou Group Pty Ltd GEOTPERT08050AZ-AH 27 March 2013 EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK Ellenbrook,

More information

Pro-Lift Steel Pile Foundation Repair

Pro-Lift Steel Pile Foundation Repair Pro-Lift Steel Pile Foundation Repair Pro-Lift Steel Pile Foundation Repair System Pro-lift steel piles are designed for the stresses of Texas soils. They can have multiple steel walls, depending on the

More information

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for

More information

Figure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate

Figure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate Addendum HELICAL PULLDOWN Micropile (HPM) Introduction The HPM is a system for constructing a grout column around the shaft of a standard Helical Screw Foundation (see Figure A1). To begin the process,

More information

CEEN 162 - Geotechnical Engineering Laboratory Session 7 - Direct Shear and Unconfined Compression Tests

CEEN 162 - Geotechnical Engineering Laboratory Session 7 - Direct Shear and Unconfined Compression Tests PURPOSE: The parameters of the shear strength relationship provide a means of evaluating the load carrying capacity of soils, stability of slopes, and pile capacity. The direct shear test is one of the

More information

hs2 Ground A non-technical guide

hs2 Ground A non-technical guide hs2 Ground Investigations A non-technical guide Contents HS2 ground investigations 1 Essential Q&A 2 2 In-ground investigation techniques 9 2.1 Cable percussion borehole 10 2.2 Rotary core borehole 12

More information

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No.

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No. GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES Materials Engineering Report No. 2009-8M (Supersedes Report No. 21) F CHOWDHURY GEOMECHANICS AND STRUCTURAL MATERIALS ENGINEER S REHMAN GEOTECHNICAL

More information

Pavements should be well drained both during and upon completion of construction. Water should not be allowed to pond on or near pavement surfaces.

Pavements should be well drained both during and upon completion of construction. Water should not be allowed to pond on or near pavement surfaces. Project No. 208-8719 January, 2009 Ref: 2-8719BR Anthony Hudson - Broadscale Geotechnical Investigation - Proposed Commercial Development - 52 Old Pacific Highway, Pimpama Page 32 iii) Pavements should

More information

BUTE Department of Construction Management and Technology

BUTE Department of Construction Management and Technology BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):

More information

The Verdura Wall check with your local building department

The Verdura Wall check with your local building department The Verdura Wall The Verdura Wall by Soil Retention Products, Inc of Carlsbad, California can be constructed as a gravity retaining structure or a geosynthetic reinforced segmental retaining wall, depending

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Doug Jenkins 1, Chris Lawson 2 1 Interactive Design Services, 2 Reinforced

More information

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598

WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598 Lessons Learned from Large Diameter Sanitary Sewer Pipe Bursting Project: Conversion of Abandoned Gravity Sewer Main Into Upsized Sanitary Force Main South San Francisco, CA Kent Von Aspern,* Collins Orton**

More information

MICROPILE FOUNDATIONS IN KARST: STATIC AND DYNAMIC TESTING VARIABILITY

MICROPILE FOUNDATIONS IN KARST: STATIC AND DYNAMIC TESTING VARIABILITY MICROPILE FOUNDATIONS IN KARST: STATIC AND DYNAMIC TESTING VARIABILITY Jesús Gómez, Ph.D., P.E Allen Cadden, P.E. O. Christopher Webster, P.E. Schnabel Engineering, Inc. Schnabel Engineering, Inc. Schnabel

More information

What is geotechnical risk?

What is geotechnical risk? 1 MANAGING GEOTECHNICAL RISK Dr David Cathie, Cathie Associates What is geotechnical risk? The saying "ignorance is bliss" applies well to geotechnical problems. Out of sight, out of mind often applies

More information

Geotechnical Investigation Test Report

Geotechnical Investigation Test Report Geotechnical Investigation Test Report Report No. htsc/rcd/ 3457 Dated: - 20/03/2010 Asphalt Standard Penetration Test as per IS 2131 ------------- IS 6403 Soil Job Card No - 1649 Cement Client/Department

More information

Federation of Piling Specialists July 2010

Federation of Piling Specialists July 2010 Examples of Hazards associated with Piling and Diaphragm Walling Works and how these might be managed within the design phase of a project (neither exhaustive nor exclusive) This list of examples has been

More information

Module 7 (Lecture 24 to 28) RETAINING WALLS

Module 7 (Lecture 24 to 28) RETAINING WALLS Module 7 (Lecture 24 to 28) RETAINING WALLS Topics 24.1 INTRODUCTION 24.2 GRAVITY AND CANTILEVER WALLS 24.3 PROPORTIONING RETAINING WALLS 24.4 APPLICATION OF LATERAL EARTH PRESSURE THEORIES TO DESIGN 24.5

More information

RECENT EXPERIENCES WITH BI-DIRECTIONAL STATIC LOAD TESTING

RECENT EXPERIENCES WITH BI-DIRECTIONAL STATIC LOAD TESTING RECENT EXPERIENCES WITH BI-DIRECTIONAL STATIC LOAD TESTING M. England BSc, MSc, PhD, MIC, P.F. Cheesman. Loadtest, 14 Scotts Avenue, Sunbury on Thames, TW16 7HZ, United Kingdom. Keywords: Bi-directional

More information

FRANKIPILE. High Pile Loads Optimum Adaptation to Foundation Soil Low-noise Manufacturing Process

FRANKIPILE. High Pile Loads Optimum Adaptation to Foundation Soil Low-noise Manufacturing Process FRANKIPILE High Pile Loads Optimum Adaptation to Foundation Soil Low-noise Manufacturing Process The FRANKIPILE Application possibilities The FRANKIPILE can be used in a wide range of foundation soil conditions

More information

Chapter 2 Basis of design and materials

Chapter 2 Basis of design and materials Chapter 2 Basis of design and materials 2.1 Structural action It is necessary to start a design by deciding on the type and layout of structure to be used. Tentative sizes must be allocated to each structural

More information

and the design of construction working platforms

and the design of construction working platforms Federation A presentation to the Australian Geomechanics Society Victoria i Branch 11 August 2010 Dr Stephen Buttling Piling rig bearing pressures and the design of construction working platforms 1 The

More information

Soils, Foundations & Moisture Control

Soils, Foundations & Moisture Control Soils, Foundations & Moisture Control Soil The top loose layer mineral and/or organic material on the surface of the Earth that serves as a natural medium for the growth of plants and support for the foundations

More information

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations from New construction foundations don t have to be a headache. The CHANCE Helical Pier Foundation System gives you the performance of concrete without the drawbacks and liabilities of driven piles and

More information

Treatment Practice for Controlling Water Damage in the Annular Space of Shaft Freezing Hole

Treatment Practice for Controlling Water Damage in the Annular Space of Shaft Freezing Hole An Interdisciplinary Response to Mine Water Challenges - Sui, Sun & Wang (eds) 2014 China University of Mining and Technology Press, Xuzhou, ISBN 978-7-5646-2437-8 Treatment Practice for Controlling Water

More information

Dimensional and Structural Data for Elliptical Pipes. PD 26 rev D 21/09/05

Dimensional and Structural Data for Elliptical Pipes. PD 26 rev D 21/09/05 Dimensional and Structural Data for Elliptical Pipes 21/09/05 Page 1 of 15 1. Foreword This document details a method for the structural design of Stanton Bonna Elliptical pipes for the common conditions

More information

product manual HS-4210 HS-4210_MAN_09.08 Digital Static Cone Penetrometer

product manual HS-4210 HS-4210_MAN_09.08 Digital Static Cone Penetrometer HS-4210_MAN_09.08 product manual HS-4210 Digital Static Cone Penetrometer Introduction This Manual covers the measurement of bearing capacity using the Humboldt Digital Static Cone Penetrometer (DSCP).

More information

CONDITION ASSESSMENT, REPAIR STRATEGY AND BUDGET ESTIMATE FOR OLP PIER 1 RMG YARD AREA

CONDITION ASSESSMENT, REPAIR STRATEGY AND BUDGET ESTIMATE FOR OLP PIER 1 RMG YARD AREA OLP Piraeus Port Authority S.A. Greece CONDITION ASSESSMENT, REPAIR STRATEGY AND BUDGET ESTIMATE FOR OLP PIER 1 RMG YARD AREA Draft Final Report December 2015 OLP Piraeus Port Authority S.A. Greece CONDITION

More information

Determination of Thermal Conductivity of Coarse and Fine Sand Soils

Determination of Thermal Conductivity of Coarse and Fine Sand Soils Proceedings World Geothermal Congress Bali, Indonesia, - April Determination of Thermal Conductivity of Coarse and Fine Sand Soils Indra Noer Hamdhan 1 and Barry G. Clarke 2 1 Bandung National of Institute

More information

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED

More information

DIRECTIONAL DRILLING

DIRECTIONAL DRILLING DIRECTIONAL DRILLING 1. General. Installation of pipelines through the levee embankment using directional drilling technology is prohibited. Installation of pipelines through a flood control project foundation

More information

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING 1 TABLE OF CONTENTS 1.0 Introduction and Purpose 3 2.0 Description of Work 3 3.0 Site Supervisor/Foremen Responsibilities 4 4.0 Equipment

More information

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT 1.0 SOIL IMPROVEMENT 1.1 General Soil Investigation Information are provided in Part B1 annex as a guide to the Contractor for his consideration

More information

A study on the Effect of Distorted Sampler Shoe on Standard Penetration Test Result in Cohesionless soil

A study on the Effect of Distorted Sampler Shoe on Standard Penetration Test Result in Cohesionless soil ISSN: 319-53 (An ISO 39: 00 Certified Organization) A study on the Effect of Distorted Sampler Shoe on Standard Penetration Test Result in Cohesionless soil Utpal Kumar Das Associate Professor, Department

More information