1 Public Disclosure Authorized SOUTH ASIA South Asia Energy and Mining Global Practice IBRD/IDA Specific Investment Loan FY 2011 Seq No: 8 ARCHIVED on 01-Jun-2015 ISR18947 Implementing Agencies: Public Disclosure Authorized Key Dates Key Project Dates Board Approval date:21-jun-2011 Planned Mid Term Review Date:09-Feb-2015 Original Closing Date:31-Dec-2016 Project Development Objectives Effectiveness Date:29-Sep-2011 Actual Mid-Term Review Date:09-Feb-2015 Revised Closing Date:31-Dec-2016 Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) The development objectives are to: (a) establish cross-border transmission capacity between India and Nepal of about 1000 MW to facilitate electricity trade between the two countries; and, (b) increase the supply of electricity in Nepal by the sustainable import of at least 100 MW. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Component A1: Muzaffarpur-Sursand 400 kv Transmission Line (Non-IDA financed):(cost $29.70 M) Public Disclosure Authorized Component A2: Dhalkebar-Bhittamod 400 kv Transmission Line (non-ida financed):(cost $17.90 M) Component B1: Hetauda-Dhalkebar-Inarwa Transmission Line and Substations:(Cost $ M) Component B2: Synchronization of Operation of the Nepal and Indian Grids:(Cost $10.00 M) Component C: Technical Advisory Services:(Cost $11.00 M) Componet B3: Transmission Lines and IFMIS of NEA:(Cost $39.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Unsatisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Satisfactory 6/1/2015 Page 1 of 8

2 Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions Two Special Purpose Vehicles (SPVs) in India and Nepal are managing the construction of the Dhalkebar-Muzzaffarpur transmission line. TATA Power Company and KEC India Limited are responsible for construction of transmission lines in Nepal and India portion respectively. There is a good progress in implementation of this transmission line. All the private land required for the tower footings have been acquired and construction activities is going on. In the Muzzaffarpur- Sursand section (Indian side), out of 233 towers, 184 foundations and 157 towers has been erected. Similarly, 27 kms of stringing has been completed. The construction of this section of the DM line is expected to be completed by June Similarly, in Dhalkebar- Bhittamod (Nepal side) section out of 112 towers 67 foundations and 37 towers has been erected. Power Transmission Company Nepal (PTCN) is planning to complete the line by June As the new interconnecting substation at Dhalkebar would not be ready by June 2015, the DM line is planned to be operated at 132 kv initially for short period and connect to the old Dhalkebar substation. In this regard, NEA needs to ensure that in addition to adequate capacity being available in the 132 kv bus-bar (Dhalkebar), downstream 11 kv network is also available to transmit the power to consumers. Schematic single line diagrams for the transmission lines are provided in the Annex 5. All the contract orders for Hetauda-Dhalkebar-Inaruwa (HDI) have now been placed. After a delayed start, the progress in construction of HDI transmission line has been satisfactory. The detailed route alignment survey and preparation of plan profile is completed. The check survey is 96.25% completed. There is also good progress in collecting land parcel data for tower foundations and tower erection work. Out of 399 locations, land parcels data for tower foundations have been completed for 383. Out of 790 tower locations, 176 foundations works have been completed, and 111 towers are erected. Land necessary for the construction of 220 kv substations at Hetauda, Dhalkebar and Inaruwa has been acquired. The contract agreement for Dhalkebar substation has been executed on June 12, 2014 with Central China Power Grid International Economic & Trade Co., China. The contractor has mobilized its staff at site and at the moment working on ground leveling. As per the contract duration, completion of the Dhalkebar substation will take 15 months. As per the current work progress, the substation would not be ready when the DM line under component A1 and A2 will be complete. As an alternative measure the DM line is planned to be connected to old Dhalkebar substation at 132 kv operating voltage until the new substation is ready. This connection would have limited transfer capacity of about 200 MW which would be sufficient to receive the 150 MW of electricity that NEA has agreed to purchase from India that would be available from July The team had requested NEA to immediately start revising the previous study on power system synchronization by hiring consultants with expertise in power system dynamic studies. This activity however, is on hold as Nepal and India has formed a committee under the leadership of the Joint Secretary Mr. Keshav Dhoj Adhikari to review the power systems of both countries including study of synchronization of power system of both countries. The Systems Planning Department of NEA and POWERGRID of India are jointly reviewing the issues involved in synchronizing India and Nepal power systems. The team will closely follow-up the progress of this report and if the report prepared the committee is found to be satisfactory, then we will request the project to process with procurement of necessary power system stabilizers. Hetauda-Bharatpur (HB) 220 kv transmission line and associated sub-stations. There is a good progress in implementation of this transmission line. Supply of all equipment including towers has been completed, except for nine multi circuit towers. The structural drawing for the 4D towers are under preparation. Land acquisition has been completed in Chitwan district and 95% of land acquisition completed in Makwanpur district. Right of Way (RoW) compensation for these districts are under progress. Out of 226 tower locations, 99 tower foundations have been completed and 50 towers are erected. There is also good progress in implementation of associated substations and switching stations. Bharatpur-Bardaghat (BB) 220 kv transmission line. About 100% of supply has arrived at site since long time; after a long delay due to hurdles in forest clearance the construction activities have started. So far eight foundations have been completed. With the help of cadastral map 80 percent of land parcels have been identified. Supply of Conductor, Earth wire and OPGW for the Transmission Line. Contract Agreement for Supply of Conductor, Earth wire and OPGW has been signed between NEA and Apar Industries Pvt. Limited, India on March 14, Advance payment is made and Letter of Credit has been opened. The contract time has been extended from January 8, 2015 to July 7, Type test of the conductor is on-going. Delivery of 2,000 km ACSR Moose conductor is expected by May NEA Integrated Financial Management Information System (IFMIS). After issuing Request for Proposal (RFP) to the shortlisted firms, NEA has received two proposals for acquisition, installation, and commissioning and operation maintenance of a system integrator for an integrated financial management information system (IFMIS) of NEA. NEA had submitted the technical evaluation report to the Bank for no-objection. We found that the evaluation report is incomplete as it does not include scoring the firms. NEA will be resubmitting the technical evaluation report including technical scores. Contract Agreement of Transmission Master Plan has been concluded between NEA and EDF France on December 2, Most of the data collection works is complete. Phase I Report that include Demand Forecast, Generation Scenario / Export Potential have been submitted by EDF. Relevant data has been collected, peak and off-peak conditions are defined, load growth is forecasted, generation expansion scenario is defined, and gird modelling is under way. Design of optimum target network is underway, planning criteria is prepared and is under discussion. Draft AS-IS report is submitted for on Analysis of NEA s Implementation Process and Recommendation under the transmission master plan and the consultant is preparing recommendation for the revised process. A workshop was organized March 2015 in Nepal to discuss the implementation process among stake holders. The consultant conducted training on transmission planning for four NEA engineers. Training on overhead standards and PLS-CADD will be conducted in Nepal. 6/1/2015 Page 2 of 8

3 Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- High High Macroeconomic -- Substantial Substantial Sector Strategies and Policies -- Substantial Substantial Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and Sustainability -- Moderate Moderate Fiduciary -- Substantial Substantial Environment and Social -- Moderate Moderate Stakeholders -- Moderate Moderate Other Overall -- Substantial Substantial Results Project Development Objective Indicators PHINDPDOTBL Cross-Border Transmission Capacity (Megawatt, Custom) Value Date 27-May Dec Apr Dec-2016 PHINDPDOTBL Quantity of electricity imported from India into Nepal under the PSA (Gigawatt-hour (GWh), Custom) Value Date 27-May Dec Apr Dec /1/2015 Page 3 of 8

4 Overall Comments Intermediate Results Indicators Construction Progress (Text, Custom) Value 0 83 foundations completed and 21 towers erected. 176 foundations completed and 111 towers erected. Line operational Date 27-May Dec Feb Dec-2016 Synchronization of Nepal grid and India grid (Text, Custom) Value No synchronization No Synchronization No Synchronization Power system stabilizers installed and systems synchronized Transmission System Master Plan (Text, Custom) Value 0 Preliminary draft report submitted for zone 6 Preliminary draft report submitted for zones 4, 5 and 6. Final Transmission System Master Plan developed. Date 27-May Dec Dec Dec /1/2015 Page 4 of 8

5 Construction progress (Text, Custom) Value 0 83 tower foundations and 21 towers erected 176 foundations completed and 111 towers erected Line operational Date 27-May Dec Feb Dec-2016 Construction progress (Text, Custom) Value 25% of tower foundation completed 83 foundations and 21 towers erected 176 foundations completed and 111 towers erected Line operational Date 17-May Dec Feb Dec-2016 Transmission lines constructed or rehabilitated under the project (Kilometers, Core) Value Transmission lines constructed under the project (Kilometers, Core Breakdown) Value /1/2015 Page 5 of 8

6 Transmission lines constructed or rehabilitated under the project (Kilometers, Core) Value Transmission lines constructed under the project (Kilometers, Core Breakdown) Value Transmission lines constructed or rehabilitated under the project (Kilometers, Core) Value Date 17-May Dec Apr Dec-2016 Transmission lines constructed under the project (Kilometers, Core Breakdown) Value Date 17-May Dec Dec Dec /1/2015 Page 6 of 8

7 Transmission lines constructed or rehabilitated under the project (Kilometers, Core) Value Date 27-May Dec Dec Dec-2016 Transmission lines constructed under the project (Kilometers, Core Breakdown) Value Date 27-May Dec Dec Dec-2016 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P IDA Effective XDR % P IDA Effective XDR % P IDA-H6600 Effective XDR % P IDA-H8580 Effective XDR % Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P IDA Effective 21-Jun Jul Sep Dec Dec-2016 P IDA Effective 24-Jun Sep Dec Dec Dec-2016 P IDA-H6600 Effective 21-Jun Jul Sep Dec Dec-2016 P IDA-H8580 Effective 24-Jun Sep Dec Dec Dec /1/2015 Page 7 of 8

8 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) P Additional Financing for Nepal-India Electricity Transmission and Trade Project 6/1/2015 Page 8 of 8

The World Bank DRC - Agriculture Rehabilitation and Recovery Support (P092724)

The World Bank DRC - Agriculture Rehabilitation and Recovery Support (P092724) AFRICA Congo, Democratic Republic of Agriculture and Rural Development Global Practice IBRD/IDA Specific Investment Loan FY 2010 Seq No: 9 ARCHIVED on 23-Jun-2015 ISR19885 Implementing Agencies: UNOPS

More information

Coral Reef Rehabilitation and Management Program- Coral Triangle Initiative (COREMAP-CTI) (P127813)

Coral Reef Rehabilitation and Management Program- Coral Triangle Initiative (COREMAP-CTI) (P127813) Public Disclosure Copy EAST ASIA AND PACIFIC Indonesia Environment Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 2 ARCHIVED on 03-Feb-2015 ISR17440 Implementing Agencies: Ministry

More information

Public Disclosure Copy

Public Disclosure Copy EUROPE AND CENTRAL ASIA Turkey Energy & Extractives Global Practice Recipient Executed Activities Investment Project Financing FY 2015 Seq No: 1 ARCHIVED on 25-Jan-2016 ISR22040 Implementing Agencies:

More information

The World Bank Ethiopia General Education Quality Improvement Project II (P129828)

The World Bank Ethiopia General Education Quality Improvement Project II (P129828) AFRICA Ethiopia Education Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 5 ARCHIVED on 14-Mar-2016 ISR22564 Implementing Agencies: Ministry of Education Key Dates Key Project Dates

More information

Implementation Status & Results Report Strengthening of Planning, Investment, Fiduciary and Procurement cap. (P148830)

Implementation Status & Results Report Strengthening of Planning, Investment, Fiduciary and Procurement cap. (P148830) LATIN AMERICA AND CARIBBEAN Bolivia Governance Global Practice Institutional Development Fund FY 2014 Seq No: 2 ARCHIVED on 28-Sep-2015 ISR20669 Implementing Agencies: Ministry of Development Planning

More information

Public Disclosure Copy

Public Disclosure Copy SOUTH ASIA Afghanistan Agriculture Global Practice Recipient Executed Activities Specific Investment Loan FY 2014 Seq No: 6 ARCHIVED on 21-Dec-2015 ISR21980 Implementing Agencies: Key Dates Key Project

More information

Financing New High Voltage Transmission Lines in Nepal Using HTLS Conductors Surendra Rajbhandari, Nepal Electricity Authority Zhang Lei, ADB South

Financing New High Voltage Transmission Lines in Nepal Using HTLS Conductors Surendra Rajbhandari, Nepal Electricity Authority Zhang Lei, ADB South Financing New High Voltage Transmission Lines in Nepal Using HTLS Conductors Surendra Rajbhandari, Nepal Electricity Authority Zhang Lei, ADB South Asia Energy Division Asia Clean Energy Forum June 2015

More information

The World Bank. Public Disclosure Copy. Public Disclosure Copy

The World Bank. Public Disclosure Copy. Public Disclosure Copy Implementation Status & Results Turkey Electricity Distribution Rehabilitation Project (P096801) Operation Name: Electricity Distribution Rehabilitation Project (P096801) Project Stage: Implementation

More information

The World Bank. Key Dates. Project Development Objectives. Component(s) Overall Ratings. Public Disclosure Copy

The World Bank. Key Dates. Project Development Objectives. Component(s) Overall Ratings. Public Disclosure Copy Implementation Status & Results Turkey Electricity Distribution Rehabilitation Project (P096801) Operation Name: Electricity Distribution Rehabilitation Project (P096801) Project Stage: Implementation

More information

Implementation Status & Results Brazil BR Municipal APL: Teresina Enhancing Municipal Governance and Quality of Life Project (P088966)

Implementation Status & Results Brazil BR Municipal APL: Teresina Enhancing Municipal Governance and Quality of Life Project (P088966) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil BR Municipal APL: Teresina Enhancing Municipal Governance and Quality of Life Project (P088966)

More information

The Philippines Leyte-Bohol Interconnection Project

The Philippines Leyte-Bohol Interconnection Project The Philippines Leyte-Bohol Interconnection Project External Evaluator: Toshiyuki Katagiri, Tomomi Ito (The Japan Economic Research Institute) Field Survey: November 2006, February 2007 1. Project Profile

More information

Implementation Status & Results Brazil Rio Grande do Norte Integrated Water Resources Management (P089929)

Implementation Status & Results Brazil Rio Grande do Norte Integrated Water Resources Management (P089929) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Rio Grande do Norte Integrated Water Resources Management (P089929) Operation Name: Rio Grande

More information

Grid Operations and Planning

Grid Operations and Planning Grid Operations and Planning Report Kent Saathoff ERCOT Board of Directors April 20, 2010 Kent Content Summary March 2010 Operations Peak Demand: Actual vs. Forecast On-line Resources: Total at Peak and

More information

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission

More information

Terms of Reference For Project Supervision Consultants of South Asia Sub regional Economic Cooperation Power System expansion Project

Terms of Reference For Project Supervision Consultants of South Asia Sub regional Economic Cooperation Power System expansion Project Terms of Reference For Project Supervision Consultants of South Asia Sub regional Economic Cooperation Power System expansion Project 1. Background and Definitions 1.1. Nepal is facing chronic power shortages.

More information

NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) Project Management Directorate

NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) Project Management Directorate NEPAL ELECTRICITY AUTHORITY (An Undertaking of Government of Nepal) Project Management Directorate Terms of Reference (ToR) For Consulting Services For Feasibility Study of Second Nepal-India 400 kv Cross

More information

Section 1: Executive Summary

Section 1: Executive Summary Section 1: Executive Summary SECTION 1: EXECUTIVE SUMMARY 1.1 SECTION PURPOSE This report has been prepared for the Nevada Energy Assistance Corporation (NEAC), a 501(c)(3) non-profit agency; in support

More information

Morris S. Stover, P.E. Sponsor, Transmission Area

Morris S. Stover, P.E. Sponsor, Transmission Area Page 1 of 5 Job Function Morris has nearly 28 years in the power industry including design and construction of transmission line and substation facilities, He has extensive experience in contract development

More information

A. 5MWp SPV Plant at Khimsar, Rajasthan. B. 5MWp SPV Plant Installed Technologies. D. 5MWp SPV Plant Challenges. E. 5MWp SPV Plant - Performance

A. 5MWp SPV Plant at Khimsar, Rajasthan. B. 5MWp SPV Plant Installed Technologies. D. 5MWp SPV Plant Challenges. E. 5MWp SPV Plant - Performance An overview & Performance Analysis of 5 MWp Solar PV Plant at Khimsar, Rj Rajasthan Reliance Industries Limited June 2, 2011 July 2010 Contents A. 5MWp SPV Plant at Khimsar, Rajasthan B. 5MWp SPV Plant

More information

STRATEGIC ISSUES OF THE ELECTRICITY COMPANY OF GHANA PRESENTATION BY MR. WILLIAM HUTTON-MENSAH (AG. MANAGING DIRECTOR) ELECTRICITY COMPANY OF GHANA

STRATEGIC ISSUES OF THE ELECTRICITY COMPANY OF GHANA PRESENTATION BY MR. WILLIAM HUTTON-MENSAH (AG. MANAGING DIRECTOR) ELECTRICITY COMPANY OF GHANA STRATEGIC ISSUES OF THE ELECTRICITY COMPANY OF GHANA PRESENTATION BY MR. WILLIAM HUTTON-MENSAH (AG. MANAGING DIRECTOR) OUTLINE OF PRESENTATION (ECG) 2 Introduction Map of Operational Area Company Mandate,

More information

Last revised: September 1, 2014 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS

Last revised: September 1, 2014 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS Last revised: September 1, 2014 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS EVP, Chief Operations Officer, has primary responsibility for the overall planning, operations and control of the transmission

More information

Estimation of electrical losses in Network Rail Electrification Systems

Estimation of electrical losses in Network Rail Electrification Systems Estimation of electrical losses in Network Rail Electrification Systems Page 1 of 16 Contents 1. BACKGROUND...3 2. PURPOSE...3 3. SCOPE...3 4. DEFINITIONS & ABBREVIATIONS...4 5. NETWORK RAIL INFRASTRUCTURE

More information

REPORT 2016/066 INTERNAL AUDIT DIVISION. Audit of management of technical cooperation projects in the Economic Commission for Africa

REPORT 2016/066 INTERNAL AUDIT DIVISION. Audit of management of technical cooperation projects in the Economic Commission for Africa INTERNAL AUDIT DIVISION REPORT 2016/066 Audit of management of technical cooperation projects in the Economic Commission for Africa Overall results relating to the effective management of technical cooperation

More information

ASIAN DEVELOPMENT BANK PPA: LAO 22065

ASIAN DEVELOPMENT BANK PPA: LAO 22065 ASIAN DEVELOPMENT BANK PPA: LAO 22065 PROJECT PERFORMANCE AUDIT REPORT ON THE NAM NGUM-LUANG PRABANG POWER TRANSMISSION PROJECT (Loans 928-LAO[SF]/1308-LAO[SF]) IN THE LAO PEOPLE S DEMOCRATIC REPUBLIC

More information

CHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska. February 10, 2014

CHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska. February 10, 2014 CHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska February 10, 2014 QUESTIONS AND ANSWERS TO: Prospective Proposers FROM: Chugach Electric Association, Inc. 5601 Electron Drive Anchorage, Alaska SUBJECT:

More information

Welcome to our open house. Thanks for coming. Please sign in and help yourself to refreshments. Energizing your community. www.fortisbc.

Welcome to our open house. Thanks for coming. Please sign in and help yourself to refreshments. Energizing your community. www.fortisbc. Welcome to our open house Thanks for coming Please sign in and help yourself to refreshments Integrated System Plan (ISP) Looks ahead 20 years to identify the energy and infrastructure needs of our customers

More information

Industries Association. ERCOT Successes and Challenges

Industries Association. ERCOT Successes and Challenges Texas Renewable Energy Industries Association ERCOT Successes and Challenges Laura Doll Board Chair Electric Reliability Council of Texas November 7, 2011 ERCOT Overview The ERCOT market covers roughly

More information

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS 14:8-4.1 Scope This subchapter sets forth net metering requirements that apply to electric power suppliers, basic generation service providers

More information

Wind Power Programme in India

Wind Power Programme in India Wind Power Programme in India Ministry of New & Renewable Energy 1 st August 2012, New Delhi 1 Renewable Power Sector in INDIA Share of Installed Renewable Capacity 13% 4% 13% 70% Wind Solar Hydro Biomass

More information

Transmission Planning in the ERCOT Interconnection

Transmission Planning in the ERCOT Interconnection Transmission Planning in the ERCOT Interconnection Warren Lasher Manager, Long-Term Planning and Policy Department of Energy Electricity Advisory Committee The ERCOT Interconnection The ERCOT Region is

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2

More information

RESTRUCTURING PAPER ON A PROPOSED RESTRUCTURING OF HEALTH SECTOR SUPPORT PROJECT JUNE 2, 2005 TO THE GOVERNMENT OF GUINEA APRIL 25, 2013

RESTRUCTURING PAPER ON A PROPOSED RESTRUCTURING OF HEALTH SECTOR SUPPORT PROJECT JUNE 2, 2005 TO THE GOVERNMENT OF GUINEA APRIL 25, 2013 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized AFTHW AFR Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED RESTRUCTURING

More information

TANZANIA ELECTRIC SUPPLY COMPANY LTD (TANESCO) PRESENTATION ON THE TANZANIAN SOLAR PV-HYBRID WORKSHOP HELD IN BERLIN, GERMANY

TANZANIA ELECTRIC SUPPLY COMPANY LTD (TANESCO) PRESENTATION ON THE TANZANIAN SOLAR PV-HYBRID WORKSHOP HELD IN BERLIN, GERMANY TANZANIA ELECTRIC SUPPLY COMPANY LTD (TANESCO) PRESENTATION ON THE TANZANIAN SOLAR PV-HYBRID WORKSHOP HELD IN BERLIN, GERMANY 16 TH MARCH 2015 by Eng. Patrice Tsakhara Principal Engineer Small Power Projects

More information

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Pakistan Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Final Report: Executive Summary - November 2015 for USAID Energy Policy

More information

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network

More information

San Francisco Municipal Transportation Agency Asset Management and Incremental Progress. Robert L. Peskin, AECOM Arlington, VA

San Francisco Municipal Transportation Agency Asset Management and Incremental Progress. Robert L. Peskin, AECOM Arlington, VA San Francisco Municipal Transportation Agency Asset Management and Incremental Progress Robert L. Peskin, AECOM Arlington, VA Overview Regional Transit Capital Inventory project State of Good Repair report

More information

PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS

PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS FEBRUARY 2008 PB POWER PB Power Page i EXECUTIVE SUMMARY General

More information

Brochure Introducing HVDC

Brochure Introducing HVDC Brochure Introducing HVDC ABB and HVDC The world s first commercial high-voltage direct current (HVDC) link, situated between the Swedish mainland and the island Gotland, was delivered by ABB already in

More information

HTS Cables: Pitfalls and Potential LIPA Cable Project. J. Maguire American Superconductor. DOE Wire Workshop January, 2007 Panama City, FL

HTS Cables: Pitfalls and Potential LIPA Cable Project. J. Maguire American Superconductor. DOE Wire Workshop January, 2007 Panama City, FL HTS Cables: Pitfalls and Potential LIPA Cable Project J. Maguire American Superconductor DOE Wire Workshop January, 2007 Panama City, FL LIPA Project Overview Long Island Power Authority Holbrook Substation

More information

Smart Metering Initiative ADWEA Program

Smart Metering Initiative ADWEA Program Smart Metering Initiative ADWEA Program Saeed Nassouri Technical Advisor Abu Dhabi Water & Electricity Authority (ADWEA) Dec 2010 Company Background SMART GRID Basics AMI Project Strategy Project Scope

More information

Term Sheet for Lease in Cambridge, Massachusetts

Term Sheet for Lease in Cambridge, Massachusetts 1/22/15 Term Sheet for Lease in Cambridge, Massachusetts D A T E D A S O F : J A N U A R Y X X, 2015 PREAMBLE: Landlord and Tenant (each as defined below) hereby enter this Term Sheet (this Term Sheet

More information

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)

More information

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach READ AND DELETE For best results with this template, use PowerPoint 2003 10 November 2015 Background and Importance of ICA Definition:

More information

Electrical Considerations for HVDC Transmission Lines. Joe Mooney, PE

Electrical Considerations for HVDC Transmission Lines. Joe Mooney, PE Electrical Considerations for HVDC Transmission Lines Joe Mooney, PE POWER Engineers has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of

More information

GLOBAL AND CHINESE ARBITRARY WAVEFORM GENERATORS INDUSTRY, 2016 MARKET RESEARCH REPORT

GLOBAL AND CHINESE ARBITRARY WAVEFORM GENERATORS INDUSTRY, 2016 MARKET RESEARCH REPORT GLOBAL AND CHINESE ARBITRARY WAVEFORM GENERATORS INDUSTRY, 2016 MARKET RESEARCH REPORT View Complete Report @ http://www.market-research-reports.com/458492-arbitrarywaveform-generators-industry Published

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY 1. 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): ENERGY 1. 1. Sector Performance, Problems, and Opportunities Country Partnership Strategy: Bangladesh, 2011 SECTOR ASSESSMENT (SUMMARY): ENERGY 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Power generation gap. Bangladesh endures long

More information

Treasure Valley Electric Plan - Community Advisory Committee

Treasure Valley Electric Plan - Community Advisory Committee Treasure Valley Electric Plan - Community Advisory Committee What is a transmission line and why are they necessary? A transmission line is used to conduct electricity between two points. Without high

More information

National Fund for Environmental Protection and Water Management. activities in climate protection

National Fund for Environmental Protection and Water Management. activities in climate protection National Fund for Environmental Protection and Water Management activities in climate protection National Fund for Environmental Protection and Water Management Witold Retke Head of Green Investment Scheme

More information

1. Project Profile and Japan s ODA Loan

1. Project Profile and Japan s ODA Loan Sri Lanka Transmission and Grid Substation Development Project 1. Project Profile and Japan s ODA Loan Report Date: September 2002 Field Survey: July/August 2001 Site Map: Sri Lanka Site Photo: Matara

More information

SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES

SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES SAMPLE TERMS OF REFERENCE FOR ELECTRICITY SECTOR PRIVATIZATION TRANSACTION ADVISORY SERVICES Table of Contents 1st. INTRODUCTION... 3 2nd. ELECTRICITY SECTOR BACKGROUND. 4 3rd. SCOPE OF WORK. 6 PHASE :

More information

GLOBAL AND CHINESE HOME INDUSTRY, 2016 MARKET RESEARCH REPORT

GLOBAL AND CHINESE HOME INDUSTRY, 2016 MARKET RESEARCH REPORT GLOBAL AND CHINESE HOME INDUSTRY, 2016 MARKET View Complete Report @ http://www.market-research-reports.com/458464-homeindustry Published By -> Prof Research Published-> Jun 2016 No. of Pages-> 150 Introduction:

More information

46575 STEG Tunisia power transmission project EBRD/EIB/STEG ENVIRONMENTAL AND SOCIAL ACTION PLAN (ESAP)

46575 STEG Tunisia power transmission project EBRD/EIB/STEG ENVIRONMENTAL AND SOCIAL ACTION PLAN (ESAP) 46575 STEG Tunisia power transmission project EBRD/EIB/STEG ENVIRONMENTAL AND SOCIAL ACTION PLAN (ESAP) Main STEG departments involved in the ESAP: DEQ: Division for Equipment (responsible for implementing

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

AFRICAN DEVELOPMENT BANK

AFRICAN DEVELOPMENT BANK AFRICAN DEVELOPMENT BANK EMERGENCY POWER INFRASTRUCTURE REHABILITATION PROJECT - PHASE I SUPPLEMENTARY GRANT PROPOSAL COUNTRY : ZIMBABWE APPRAISAL REPORT ONEC DEPARTMENT December 2013 Table of Contents

More information

Financing of Wind Projects: IFC s Perspective. Walid Labadi 2nd IEL-ANADE May, 2012

Financing of Wind Projects: IFC s Perspective. Walid Labadi 2nd IEL-ANADE May, 2012 Financing of Wind Projects: IFC s Perspective Walid Labadi 2nd IEL-ANADE May, 2012 IFC was established in 1956 to promote private sector development and is a member of the World Bank Group IFC Power Sector

More information

WATER / WASTEWATER & POWER PROJECTS LAST 5 YEARS. No of Staff Provided by BCE. Overall Project Value (SR)

WATER / WASTEWATER & POWER PROJECTS LAST 5 YEARS. No of Staff Provided by BCE. Overall Project Value (SR) WATER / WASTEWATER & POWER PROJECTS LAST 5 YEARS A. Completed December 2001 Shedgum Debottlenecking # 45943/00 47.34 Million Total 600.8 Million 154 n American Oil Co. (ARAMCO) ARAMCO Feb. 1998 to Dec.

More information

TARIFF AND GOVERNANCE ASSESSMENT

TARIFF AND GOVERNANCE ASSESSMENT Power System Expansion and Efficiency Improvement Investment Program (RRP BAN 42378) A. Tariff Assessment 1. Introduction TARIFF AND GOVERNANCE ASSESSMENT 1. Electricity tariffs in Bangladesh are unbundled

More information

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E DIRECT TESTIMONY RAJESH GUPTA PROJECT MANAGER, ENTERGY SERVICES, INC.

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E DIRECT TESTIMONY RAJESH GUPTA PROJECT MANAGER, ENTERGY SERVICES, INC. BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E s : D IN THE MATTER OF THE APPLICATION OF ENTERGY ARKANSAS, INC. FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED TO CONSTRUCT AND OPERATE

More information

GLOBAL AND CHINESE GLASS JARS INDUSTRY, 2016 MARKET RESEARCH REPORT

GLOBAL AND CHINESE GLASS JARS INDUSTRY, 2016 MARKET RESEARCH REPORT GLOBAL AND CHINESE GLASS JARS INDUSTRY, 2016 MARKET View Complete Report @ http://www.market-research-reports.com/458790-glass-jarsindustry Published By -> Prof Research Published-> Jun 2016 No. of Pages->

More information

FIXED CHARGE: This is a cost that goes towards making the service available, including

FIXED CHARGE: This is a cost that goes towards making the service available, including ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment March 20, 2009 Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Table of Contents:

More information

AMSC s Superconductor Cable Technologies for Electric Utilities

AMSC s Superconductor Cable Technologies for Electric Utilities International Workshop 2014 AMSC s Superconductor Cable Technologies for Electric Utilities Michael Ross, P.E. Managing Director of Superconductor Power Systems AMSC Corporate Facts Headquartered in MA,

More information

Summary of Electric Transmission Assessment Report

Summary of Electric Transmission Assessment Report Summary of Electric Transmission Assessment Report January 2010 Assessment and Analysis of the State-Of-the-Art High-Voltage Electric Transmission Systems with Specific Focus on High-Voltage Direct Current

More information

Relion. Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE

Relion. Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE Relion Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE Fast substation busbar protection with IEC 61850 and GOOSE Falu Elnät AB applies new power

More information

Monetary Policy and Mortgage Interest rates

Monetary Policy and Mortgage Interest rates Monetary Policy and Mortgage Interest rates July 2014 Key Points: Monetary policy, which operates through changes in the official cash rate (OCR), is the main lever of macroeconomic management in Australia

More information

TERMS OF REFERENCE (ToR)

TERMS OF REFERENCE (ToR) TERMS OF REFERENCE (ToR) Consultancy services for Monitoring the Implementation of Computerized Integrated Financial Management Information System (IFMIS) of BREB & PBSs for Institutional Strengthening

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Project Number: 44219 June 2014 Proposed Loan, Technical Assistance Grant, and Administration of Grants Nepal: South Asia Subregional

More information

FINANCIAL RESULTS Q2 2015

FINANCIAL RESULTS Q2 2015 FINANCIAL RESULTS Q2 2015 CEO CHRISTIAN RYNNING-TØNNESEN CFO HALLVARD GRANHEIM 23 July 2015 Highlights Solid underlying results (EBITDA) - Lower Nordic prices offset by increased production and contribution

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

Electricity Exchanges in South Asia The Indian Energy Exchange Model

Electricity Exchanges in South Asia The Indian Energy Exchange Model Electricity Exchanges in South Asia The Indian Energy Exchange Model 18 Mar 14 Rajesh K Mediratta Director (BD) rajesh.mediratta@iexindia.com www.iexindia.com In this presentation Overview - Indian Market

More information

The Current Portfolio and Implementation Lessons

The Current Portfolio and Implementation Lessons ONGOING PROGRAM AND KEY LESSONS The Bank has had an active program in Albania for nearly two decades and a number of lessons have been learned over that period. The lessons have been divided into three

More information

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE 1 1 Welcome to The Eldorado-Ivanpah Transmission Project Open House How is the open house organized? This

More information

Transmission Network Performance Report

Transmission Network Performance Report Transmission performance report cover.qxp 06/25/2008 11:50 AM Page 1 Transmission Network Performance Report 25 Research Drive Westborough, MA 01582 www.nationalgrid.com CD4369 (6/08) Fiscal Year 2008

More information

REQUEST FOR PRE-QUALIFICATION FOR SHORT-LISTING OF TOWER CONTRACTORS, CONDUCTOR & INSULATOR SUPPLIERS

REQUEST FOR PRE-QUALIFICATION FOR SHORT-LISTING OF TOWER CONTRACTORS, CONDUCTOR & INSULATOR SUPPLIERS REQUEST FOR PRE-QUALIFICATION FOR SHORT-LISTING OF TOWER CONTRACTORS, CONDUCTOR & INSULATOR SUPPLIERS TO FACILITATE POWERGRID S PARTICIPATION IN 765 kv TRANSMISSION LINE PROJECTS UNDER TARIFF BASED COMPETITIVE

More information

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3 rd & 4 th Floor, Chanderlok Building, 36, Janpath, New Delhi 110 001 Tel : 23753920/ Fax : 23753923

CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3 rd & 4 th Floor, Chanderlok Building, 36, Janpath, New Delhi 110 001 Tel : 23753920/ Fax : 23753923 CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3 rd & 4 th Floor, Chanderlok Building, 36, Janpath, New Delhi 110 001 Tel : 23753920/ Fax : 23753923 Ref.No.: 2/7(8)/2008-RIMS/Policy/CERC Dated: 29 th

More information

GUIDE TO CREATING A CAPITAL CAMPAIGN PLAN: CONTENTS

GUIDE TO CREATING A CAPITAL CAMPAIGN PLAN: CONTENTS GUIDE TO CREATING A CAPITAL CAMPAIGN PLAN: CONTENTS NOTE (9-17-10): This Guide wasn t designed as a template for a capital campaign plan. It was originally created as a tool and proposal attachment for

More information

Growth pause rather than structure break How robust is the recovery?

Growth pause rather than structure break How robust is the recovery? Growth pause rather than structure break How robust is the recovery? Prof. Dr. Michael Hüther Director of the Institut der deutschen Wirtschaft Köln PK Hanover Fair, 19 April 2010 1 Agenda Where we are

More information

Offshore Work Packages

Offshore Work Packages Rampion Offshore Wind Farm Offshore Work Packages Meet The Buyer Naren Mistry, Engineering Manager 26 th Feb 2014 Rampion Offshore Project Scope Design, manufacture, transportation and Installation: Up

More information

Merchant Interconnectors

Merchant Interconnectors Merchant Interconnectors David Newbery EPRG Winter Research Seminar Cambridge 15 December 2006 http://www.electricitypolicy.org.uk Outline Strong pressure from EC to increase interconnection impeded by

More information

NETWORK OUTPUT MEASURES CONSULTATION

NETWORK OUTPUT MEASURES CONSULTATION NETWORK OUTPUT MEASURES CONSULTATION Great Britain s electricity transmission network transmits high-voltage electricity from where it is produced to where it is needed throughout the country. It broadly

More information

Proposed Action: Morrow Flat Substation Construction and Related Improvements Near Boardman, Oregon

Proposed Action: Morrow Flat Substation Construction and Related Improvements Near Boardman, Oregon DOE F 1325.8 e Electronic Form Approved by CGIR - 01/20/95 (8-89) United States Government memorandum Department of Energy Bonneville Power Administration DATE: August 8, 2014 REPLY TO ATTN OF: KEC-4 SUBJECT:

More information

2017 Budget and Grid Management Charge Initial Stakeholder Meeting

2017 Budget and Grid Management Charge Initial Stakeholder Meeting 2017 Budget and Grid Management Charge Initial Stakeholder Meeting June 16, 2016 Page 1 Agenda Topic 2017 Budget Process & GMC Rate Outlook Managing Employee Compensation Presenter(s) Ryan Seghesio & April

More information

TERMS OF REFERENCE FOR THE HUMAN RESOURCES AND COMPENSATION COMMITTEE

TERMS OF REFERENCE FOR THE HUMAN RESOURCES AND COMPENSATION COMMITTEE I. PURPOSE The purpose of the Human Resources and Compensation Committee (the Committee ) is to assist the Board in fulfilling its obligations relating to human resource and compensation policy and related

More information

Schedule-4(A3) Page 1 of 5. Specification No.: JPL/KWTL/A3 (Package-A3) To: Bidder's Name & Address

Schedule-4(A3) Page 1 of 5. Specification No.: JPL/KWTL/A3 (Package-A3) To: Bidder's Name & Address Specification : JPL/KWTL/A3 (Package-A3) Page 1 of 5 Tower Package (Package-A3) for 400 kv D/C (Quad Bundle) Karcham Wangtoo Abdullapur Line Part III associated with Karcham Wangtoo HEP Transmission System

More information

ERCOT Monthly Operational Overview (March 2014) ERCOT Public April 15, 2014

ERCOT Monthly Operational Overview (March 2014) ERCOT Public April 15, 2014 ERCOT Monthly Operational Overview (March 2014) ERCOT Public April 15, 2014 Grid Operations & Planning Summary March 2014 Operations The peak demand of 54,549 MW on March 3 rd was greater than the mid-term

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS Virginia Electric and Power Company TERMS AND CONDITIONS XXIV. GENERATOR INTERCONNECTION STANDARD Electric generator interconnection service includes only the ability to interconnect an electric generator

More information

Internal Audit Report. Enterprise Geographic Information System Phase 1. October 7, 2002. To:

Internal Audit Report. Enterprise Geographic Information System Phase 1. October 7, 2002. To: October 7, 2002 To: D.G. Geisheimer L.B. Coghlan I.N. Block E. Hong R. Threlkeld G.N. Sherlock B.G. Elton M. Costello L.I. Bell Audit and Risk Management Committee Internal Audit Report Enterprise Geographic

More information

Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms

Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms The future of Wind Farms As offshore wind farms move towards deploying higher capacity

More information

Presentation. Lightning Protection practices in Bangladesh :An overview

Presentation. Lightning Protection practices in Bangladesh :An overview Presentation on Lightning Protection practices in Bangladesh :An overview Abidur Rahaman Dept. of Applied Physics and Electronics University of Dhaka, Bangladesh Outline Lightning and lightning protection

More information

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003 F R C C FRCC Standards Handbook FRCC Automatic Underfrequency Load Shedding Program Revision Date: July 2003 FRCC Underfrequency Load Shedding Program Modification and Approval Process Requests to modify

More information

India: Equity Investment in and Loan to Infrastructure Development Finance Company

India: Equity Investment in and Loan to Infrastructure Development Finance Company Validation Report Reference Number: VR-22 Project Numbers: 31901 and 38926 Investment Numbers: 7138 and 7211 December 2013 India: Equity Investment in and Loan to Infrastructure Development Finance Company

More information

Load Dispatcher (Class Code 5223) Task List

Load Dispatcher (Class Code 5223) Task List A. Load Dispatching, General Load Dispatcher (Class Code 5223) Task List 1. Prior to work shift speaks to Load Dispatcher(s), reviews hardcopy and computer logs, and looks at the dispatcher's diagram board

More information

ITP Evaluation Process Plan Cross-Tie Transmission Line

ITP Evaluation Process Plan Cross-Tie Transmission Line ITP Evaluation Process Plan Cross-Tie Transmission Line The goal of the coordinated Interregional Transmission Project (ITP) evaluation process is to achieve consistent planning assumptions and technical

More information

Instructions for use:

Instructions for use: TRANSMISSION MONTHLY PROJECT PROGRESS REPORT INSTRUCTIONS FOR COMPLETION TEMPLATE Instructions for use: PURPOSE OF FORM: The Transmission monthly Project Progress Report form is to be used by the Transmission

More information

Hyperlinks are Inactive

Hyperlinks are Inactive Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

PMR DASHBOARD - PROJECT MILESTONES BY COUNTRY as of April 12, 2016

PMR DASHBOARD - PROJECT MILESTONES BY COUNTRY as of April 12, 2016 Implementing Country EoI Endorsement PMR DASHBOARD - PROJECT MILESTONES BY COUNTRY as of April, 0 OF Endorsement Expert Review Process Completed Draft MRP Presentation Endorsement MRP Grant Allocation

More information

XLPE PRODUCTION PLANT FOR THIRUVALLA UNIT OF TRACO CABLE LTD

XLPE PRODUCTION PLANT FOR THIRUVALLA UNIT OF TRACO CABLE LTD PROJECT PROFILE ON XLPE PRODUCTION PLANT FOR THIRUVALLA UNIT OF TRACO CABLE LTD Prepared by: TRACO CABLE COMPANY LIMITED IV TH FLOOR, KSHB OFFICE COMPLEX PANAMPILLY NAGAR KOCHI-682036 September 2012 PROJECT

More information