1 TRENCHLESS TECHNOLOGY IN PIPELINE CONSTRUCTION 2009 AMERICAN WATERWORKS ASSOCIATION PACIFIC NORTHWEST SPRING CONFERENCE Salem, Oregon May 6, 2009 Presented by: Ed Heavey, P.E.
2 Trenchless Construction Methods Pipe Bursting Auger Boring Pipe Ramming Microtunneling/Pipe Jacking Pilot Tube Microtunneling Horizontal Directional Drilling (HDD)
3 Pipe Bursting Two General Methods Static Pneumatic Applicable Pipe Types Concrete Clay Some Plastics Cast Iron
4 Pipe Bursting Advantages Replace existing pipe with minimal disturbance Increase pipe diameter New pipe follows invert of old pipe No need to abandon existing pipe Disadvantages Potential for surface heave and deformation of nearby utilities Temporary bypass necessary Bends and restrained joints problematic
5 Auger Boring Most common trenchless construction method Use auger to bore while advancing a steel casing Generally limited to lengths of feet Casing pipe diameters of 24 to 72 inches
6 Auger Boring Advantages Wide variety of ground conditions, including rock Common construction method Face access to remove obstructions Usually minimal surface disruption Disadvantages Difficult to maintain line & grade in certain ground conditions Difficult to steer Relatively large area required for jacking pit Dewatering usually required in granular soil
7 Pipe Ramming Pneumatic hammer used to drive welded steel or Permalok casing Typical casing pipe diameters of 4 to 72 inches (147-inch Permalok casing recently driven under a railway in Iowa) Applicable for short crossings of feet Pipe ramming can be used in conjunction with HDD to drive casing and to assist in pullback
8 Pipe Ramming
9 Pipe Ramming Advantages Suitable for a wide variety of soil conditions Can be driven at almost any angle Accommodates obstructions well Disadvantages Pipe difficult to steer. Goes where it s pointed VERY noisy! Dewatering generally required below groundwater table
10 Microtunneling/Pipe Jacking Microtunneling: small diameter tunneling using a remote controlled tunneling machine Pipe jacking: small diameter tunneling using a guided tunneling machine (i.e., operator located inside the boring machine and/or on the haul cart)
11 Microtunneling Two basic modes: Slurry Shield Earth Pressure Balance Machine advances off the end of the pipe string Hydraulic jacks advance the pipe string
12
13 Microtunneling
14
15
16 Microtunneling Jacking pipe: One-pass Concrete Clay Fiberglass (Hobas) Polycrete Two-pass Steel Casing (welded & Permalok) Ribs and lagging Typical Diameters of 24 inches up to inches Lengths up to 2,000 feet with intermediate jacking stations
17 Microtunneling/Jacking Pipe
18 Intermediate Jacking Stations (IJS)
19 Microtunneling
20 Microtunneling Advantages Handles wide variety of ground conditions No dewatering Minimal surface disruption Very accurate (slopes of 0.2% easily achieved) Disadvantages Requires large area for jacking shaft and support equipment Relatively high cost Obstructions problematic
21 Pipe Jacking Two machine types: Wheel machine Excavator machine Machine diameters of 44 to 100+ inches Wheel machines can be fitted with a closed face cutter head to control unstable ground conditions
22 Pipe Jacking
23
24 Pipe Jacking Advantages Handles wide variety of ground conditions Minimal surface disruption Very accurate Less costly then microtunneling Face access to deal with obstructions Disadvantages Requires large area for jacking shaft and support equipment Dewatering below groundwater table in running/flowing soil
25 Pipe Jacking Other things can also be jacked! 14 x 14 x 84 tunnel in Connecticut
26 Pilot Tube Microtunneling Hybrid of microtunneling, HDD, auger boring For small diameter pipes 4 to 24 inches Lengths of up to 250 ft Clay pipe most common Power cutting head allows pipes up to 44
27 Pilot Tube Microtunneling Three Stage Process Drill 4 pilot hole with slant face head Auger and temporary casing used to expand hole to product pipe OD Product pipe jacked into place
28
29 Pilot Tube Microtunneling
30 Pilot Tube Microtunneling Advantages Relatively small shafts Minimal surface disruption Very accurate Less costly than microtunneling Disadvantages Short drive lengths Dewatering below groundwater table (> 10 ft) Doesn t handle cobbles and boulders well Pipe size limited
31 Horizontal Directional Drilling Generally used when line & grade not critical Lengths of hundreds to thousands of feet Steel and HDPE most common pipe materials Diameters of a few inches up to 60 + inches
32 Horizontal Directional Drilling Three stage process Drill pilot hole Expand to accommodate pipe Pull back pipe
33 Horizontal Directional Drilling
34 Horizontal Directional Drilling Advantages Handles wide variety of ground conditions Steerable both horizontally and vertically Handles obstructions Doesn t require shafts Disadvantages Not well suited for gravity systems Open gravels problematic
35 Case History Skagit River Crossing Owner: City of Anacortes Project Team: MWH Civil Design & Construction Management Landau Associates Geotechnical Bennett & Staheli Trenchless Consultant
36 Project Details Construction: ,600 ft of 36 Steel Pipe Maximum depth of 50 ft below the river bottom
37
38
39 Geotechnical Explorations
40
41 Drilling the Borehole
42 Reaming the Hole
43 Assembling the Pipe
44 The Pull Back
45 The Pull Back
46 The Pull Back
47 Questions?
Pipe Bursting. Case Study at Zeeland, MI Collections Seminar September 6, 2012. Presentation Agenda. What is Pipe Bursting? What is Pipe Bursting?
Pipe Bursting Case Study at Zeeland, MI Collections Seminar September 6, 2012 By: Brian Hannon, PE and John Racek, PE Presentation Agenda What is Pipe Bursting? History of Pipe Bursting Types of Pipe Bursting
Trenchless Construction Technology and Issues
Trenchless Construction Technology and Issues Dr. Mohammad Najafi, P.E., F. ASCE Director, Center for Underground Infrastructure Research & Education (CUIRE) Professor and Director of Construction Engineering
Trenchless Technology for Drainage Structures
Trenchless Technology for Drainage Structures Richard S. Williammee, Jr., MSCE, P.E. District Materials Engineer Fort Worth District TxDOT 2011 Transportation Short Course October 11, 2011 There are textbooks
TRENCHLESS TECHNOLOGY RESOURCE CENTRE TRENCHLESS TECHNOLOGY GUIDELINES
TRENCHLESS TECHNOLOGY RESOURCE CENTRE TRENCHLESS TECHNOLOGY GUIDELINES SECOND EDITION PIPEJACKING AND MICROTUNNELING NEW VERSION AUGUST 2005 1 OVERVIEW Pipe jacking and microtunnelling, including pilot
Section 02415. Installation of pipe and casing for sanitary sewer by methods of augering.
ITY OF PRLN UGRING PIP OR SING FOR SWRS Section 02415 UGRING PIP OR SING FOR SWRS 1.0 G N R L 1.01 STION INLUS Installation of pipe and casing for sanitary sewer by methods of augering. References to Technical
STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.
STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill
Trenchless Methods for Service and Mainline Pipe Rehab and New Install
Trenchless Methods for Service and Mainline Pipe Rehab and New Install Eddie Ward TT Technologies, Inc. Tennessee Gas Association Distribution & Operations Conference April 9 th 11 th Murfreesboro, TN
CHAPTER 16 TRENCHLESS TECHNOLOGY
CHAPTER 16 TRENCHLESS TECHNOLOGY 2005 Trenchless Technology 16-1 Chapter 16 Table of Contents 16.1 Introduction 16-3 16.2 Getting Started 16-3 16.3 Site Investigation 16-3 16.3.1 Roadway 16-4 16.3.2 Stream
WEFTEC.06. Kent Von Aspern,* Collins Orton** *Carollo Engineers 2700 Ygnacio Valley Rd Suite 300 Walnut Creek, CA 94598
Lessons Learned from Large Diameter Sanitary Sewer Pipe Bursting Project: Conversion of Abandoned Gravity Sewer Main Into Upsized Sanitary Force Main South San Francisco, CA Kent Von Aspern,* Collins Orton**
Dewatering - Time and Cost Relief by way of Trenchless Construction
North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-04 Dewatering - Time and Cost Relief by way of Trenchless Construction Jenn Stillman,
Oil and Gas Pipeline Design, Maintenance and Repair
Oil and Gas Pipeline Design, Maintenance and Repair Dr. Abdel-Alim Hashem Professor of Petroleum Engineering Mining, Petroleum & Metallurgical Eng. Dept. Faculty of Engineering Cairo University [email protected]
Greensboro s Pilot Program for Water Pipe Bursting Leads to Expanded City Wide Program
North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TA-T3-05 Greensboro s Pilot Program for Water Pipe Bursting Leads to Expanded City
Installation of Large Diameter Buried Pipes
Installation of Large Diameter Buried Pipes Sullivan (Sully) Curran P. E., Executive Director I. Introduction and Scope There is an ongoing need to provide designers, specifiers, engineers, consultants
Repair or Replacement - Band-Aids vs. Surgery
Repair or Replacement - Band-Aids vs. Surgery Using RCP for the Replacement of Failed or Undersized Culverts www.concrete-pipe.org Introduction and Background Our Nation s infrastructure owners are facing
Tunnelling & Underground. Specialists
Tunnelling & Underground Specialists Mined Tunnels Excavation at Ayer Rajah Avenue, Singapore Introduction Amberg & TTI Engineering Pte Ltd (AETTI) was established in Singapore in 2002 by Amberg Engineering
Pneumatic Pipe Bursting
A Guide to Pneumatic Pipe Bursting with the GRUNDOCRACK SYSTEM Table of Contents 1) Foreword...4 2) Company Background...5 3) Pipe Bursting History...6 4) GRUNDOCRACK Concept...7 5) Project Considerations...
12/8/2014. Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA.
Brought To You By: This webcast is sponsored by NASSCO with the support of IPBA. 1 Pipe Bursting A Mature and Diverse Trenchless Technology December 10, 2014 1:00 3:00 pm Eastern How to Participate Today
DIRECTIONAL DRILLING
DIRECTIONAL DRILLING 1. General. Installation of pipelines through the levee embankment using directional drilling technology is prohibited. Installation of pipelines through a flood control project foundation
The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
Relining of Water Mains with. Flexible High Pressure Pipelines. Raedlinger Primus Line, Inc. Ivan Zubiaga Executive Vice President 2014
Relining of Water Mains with Flexible High Pressure Pipelines Raedlinger Primus Line, Inc. Ivan Zubiaga Executive Vice President 2014 Aging water main infrastructure The American Society of Civil Engineers
TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe
TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TN 5.18 October 2015 In sanitary sewer, it is often necessary to use trenchless technology methods to install a casing pipe under high volume roads,
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene
Technical Memorandum Cost Criteria for 2010 System Capacity Plan
2010 SASD SEWER SYSTEM CAPACITY PLAN UPDATE Technical Memorandum Cost Criteria for 2010 System Capacity Plan PREPARED BY: My Huynh DATE: September 13, 2011 REVIEWED BY: Sonny Lunde INTRODUCTION This Technical
Pipeline Replacement using Relining
Pipeline Replacement using Relining Mark Heathcote, March 2006 Relining of old pipeline systems is becoming an increasingly attractive option to asset owners and operators as an effective alternative to
Sewer systems: Failures and rehabilitation
Water Utility Journal 8: 17-24, 2014. 2014 E.W. Publications Sewer systems: Failures and rehabilitation C. N. Damvergis Hellenic Association of Hydraulic Works and Water Resources Management Consulting
A Revolution for Telecom, Electric, Gas, & Water"
"Pipe Bursting A Revolution for Telecom, Electric, Gas, & Water" Presented by the Leadership of the IPBA International Pipe Bursting Association A Division of NASSCO National Association of Sewer Service
Can You See It Coming? Examining and Mitigating the Common Causes of HDD Failures
North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 TM1-T2-04 Can You See It Coming? Examining and Mitigating the Common Causes of HDD Failures
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 [email protected]
1.3.2 Method of construction and restoration of existing water service connections. This shall include:
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam
Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam Education Master of Business Administration University of Houston, 1985 Bachelor of Science, Civil Engineering University
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer
FY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
Design and Construction of Auger Cast Piles
Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN [email protected] - www.geotill.com CONTENTS 1.
Flowtite Jacking Pipe
U.S. COMPOSITE PIPE SOUTH, LLC. MEMBER OF KTI PIPE GROUP OF COMPANIES Flowtite Jacking Pipe 18585 Samuels Rd. Zachary, La. 70791 PH. 225-658-6166 Fax 225-658-0947 www.flowtitepipe.com Flowtite GRP Pipe
Section 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
Pipe Bursting. Chapter 16
535 Introduction Underground service utilities in many American cities have been in place for over 100 years. While existing systems have functioned well beyond reasonably anticipated service life, underground
Section 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
AXIS system used to install gravity flow sewer Laser-guided boring technology capable of pinpoint, on-grade accuracy
AXIS system used to install gravity flow sewer Laser-guided boring technology capable of pinpoint, on-grade accuracy The City of Kitchener, Ontario, Canada, was in a dilemma. After repeated breakdowns
Identification of Practices, Design, Construction, and Repair Using Trenchless Technology Final Report October 2010
Identification of Practices, Design, Construction, and Repair Using Trenchless Technology Final Report October 2010 Sponsored by Iowa Highway Research Board (IHRB Project TR-570) Iowa Department of Transportation
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines
PLANNING CAREFUL NORTH VANCOUVER PIPE BURST REQUIRES
WATER & SEWER REHAB TECHNOLOGIES NORTH VANCOUVER PIPE BURST REQUIRES CAREFUL PLANNING Close proximity to storage silos, poor ground conditions and clogged storm sewer pipe puts trenchless contractor to
Emerging Technologies in Wastewater Collection Systems
Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation
DIRECTIONAL DRILLING BEST PRACTICES. Planning & Construction Considerations COMMITMENT & INTEGRITY DRIVE RESULTS
DIRECTIONAL DRILLING BEST PRACTICES Planning & Construction Considerations Today s presenters will be: Dennis M. Walsh, PE Sr. Project Manager Woodard & Curran Daniel D Eletto, PE Manager, Project Engineering
FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
Guidelines for Pipe Bursting
Guidelines for Pipe Bursting TTC Technical Report #2001.02 Jadranka Simicevic Raymond L. Sterling Prepared for: U.S. Army Corps of Engineers Engineering Research and Development Center (ERDC) 3909 Halls
Pipe bursting provides viable alternative for rehab work By Greg Key, U.S. Pipe
Pipe bursting provides viable alternative for rehab work By Greg Key, U.S. Pipe As the Environmental Protection Agency tightens groundwater quality regulations, old leaking sewers lines made of pipe clay,
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects
Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental
SECTION 02401 SHEETING, SHORING AND BRACING
SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State
1-800-327-8276 www.jfcson.com
Trenchless Cost Effective Internal Pipe Rehabilitation 101 East Broadway, Hackensack, N.J. 07601 Folsom, NJ Linden, NJ Beltsville, MD Sylmar, CA 1-800-327-8276 www.jfcson.com In-Weg Internal Joint Sealing
BUTE Department of Construction Management and Technology
BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):
San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth
TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20
LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR
LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR ABSTRACT Phil Hubbard, P.E., HRSD Paul Wilson, P.E., Brown and Caldwell* Mark Harber, P.E., Brown and Caldwell *301 Bendix Road, Suite 400 Virginia
Rehabilitation Alternatives. MWEA Collection System Seminar October 1, 2009
Rehabilitation Alternatives MWEA Collection System Seminar October 1, 2009 Overview Types of Rehabilitation Trenchless Categories On-Line Replacement In-Situ Options Selecting the Best Solution Types of
SPR PE Steel Reinforced Liner
ENGINEERED SOLUTIONS SPR PE Steel Reinforced Liner Reline Done Right Contech is your single source for rehabilitation of sanitary & storm sewers, culverts and bridges. Contech Engineered Solutions has
Water Main Lining A Sustainable Alternative to Open Cut Replacement
Water Main Lining A Sustainable Alternative to Open Cut Replacement Sean O Dell, PE Baxter & Woodman, Inc. B&W Client Seminar, Crystal Lake May 1, 2014 Agenda Why, What, When, Where, Who, How Reduction
HDPE. High-Density Polyethylene Pipe Systems. Meeting the challenges of the 21 st century
HDPE High-Density Polyethylene Pipe Systems Meeting the challenges of the 21 st century 1 Smooth-wall High-Density Polyethylene pipe systems Meeting the challenges of the 21 st century Piping made from
hs2 Ground A non-technical guide
hs2 Ground Investigations A non-technical guide Contents HS2 ground investigations 1 Essential Q&A 2 2 In-ground investigation techniques 9 2.1 Cable percussion borehole 10 2.2 Rotary core borehole 12
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
Morgan County Quality Water District Water Main Flood Damage Repair Project
North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show TM1-T5-02 Morgan County Quality Water District Water Main Flood Damage Repair Project Nathan Ferguson, Farnsworth Group,
REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS. Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC
REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC What is really out there? DO YOU DIG IT? INDUSTRY CONCERNS UNEXPECTED DEVELOPMENTS
LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE POTABLE WATER DISTRIBUTION SYSTEM
North American Society for Trenchless Technology (NASTT) No-Dig Show 2010 Chicago, Illinois May 2-7, 2010 Paper D-4-02 LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE
LIFELINE PIPELINE RESTORATION AND SEISMIC MITIGATION
LIFELINE PIPELINE RESTORATION AND SEISMIC MITIGATION Le Val LUND 1 And P E M ASCE 2 SUMMARY A number of methods are discussed which can be used for lifeline pipeline rehabilitation and improving the seismic
Water Technology Fact Sheet Pipe Bursting
Water Technology Fact Sheet INTRODUCTION Under the traditional dig-and-replace method of sewer rehabilitation, a replacement or additional parallel sewer line is constructed by digging along the entire
CONSTRUCTION COST OF UNDERGROUND INFRASTRUCTURE RENEWAL: A COMPARISON OF TRADITIONAL OPEN-CUT AND PIPE BURSTING TECHNOLOGY SEYED BEHNAM HASHEMI
CONSTRUCTION COST OF UNDERGROUND INFRASTRUCTURE RENEWAL: A COMPARISON OF TRADITIONAL OPEN-CUT AND PIPE BURSTING TECHNOLOGY by SEYED BEHNAM HASHEMI Presented to the Faculty of the Graduate School of The
Louisiana Administrative Code Title 51 Part XIII. Sewage Disposal
Louisiana Administrative Code Title 51 Part XIII. Sewage Disposal Regulations Regarding Septic Tank Installations with Field Beds/Absorption Trenches For Individual Residential Installations Chapter 3.
COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2
(PREVIEW) SP 36 (Part 2) : 1988 COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2 IS 1893 : 1979 (Reaffirmed 1987) CODE OF PRACTICE FOR SUBSURFACE INVESTIGATION FOR FOUNDATIONS 1.1 This code deals
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet
DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES
SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing
CULVERT REPLACEMENT USING PIPE RAMMING, TUNNELING, OR PIPE JACKING
North American Society for Trenchless Technology (NASTT) No-Dig Show 2010 Chicago, Illinois May 2-7, 2010 Paper A-5-05 CULVERT REPLACEMENT USING PIPE RAMMING, TUNNELING, OR PIPE JACKING Craig Camp, 1 Glenn
How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska
APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED
SETTLEMENT INSTRUMENTATION & MONITORING
SECTION 02445 SETTLEMENT INSTRUMENTATION & MONITORING PART 1 - GENERAL 1.01 SUMMARY A. The Work specified in this Section includes furnishing, installing, and monitoring settlement instrumentation to monitor
PILE FOUNDATIONS FM 5-134
C H A P T E R 6 PILE FOUNDATIONS Section I. GROUP BEHAVIOR 6-1. Group action. Piles are most effective when combined in groups or clusters. Combining piles in a group complicates analysis since the characteristics
Geotechnical Building Works (GBW) Submission Requirements
Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.
SECTION 02200 SUPPORT OF EXCAVATION
SECTION 02200 PART 1 GENERAL 1.01 DESCRIPTION A. Section including specifications for design and installation of excavation support. B. Section also includes specifications for excavation support systems
Appendix A: Acceptable pipe and fitting materials
Watercare Services Limited Water and Code of Practice Content from the NZS 4404:2010 Land development and subdivision infrastructure has been reproduced for use in the Infrastructure Design s Manual for
Guideline Specification for the Replacement of Mainline Sewer Pipes By Pipe Bursting
Guideline Specification for the Replacement of Mainline Sewer Pipes By Pipe Bursting Setting the Industry Standard for the Rehabilitation of Underground Utilities The International Pipe Bursting Association
Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives
North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 MM-T6-05 Utilizing Trenchless Technology to Achieve Watermain Asset Management Objectives
Beacon Hill Sewer District Standard Specifications
Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions
PRECAST CONCRETE BOX CULVERTS
PRECAST CONCRETE BOX CULVERTS OUTLINE Introduction Applications Manufacturing Methods Design Procedures & Joints Installation Quality Summary INTRODUCTION Four-sided culverts are typically referred to
INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!
In-situ Testing! Insitu Testing! Insitu testing is used for two reasons:! To allow the determination of shear strength or penetration resistance or permeability of soils that would be difficult or impossible
How To Use A Water Source Heat Pump
Geothermal Energy Using Water-Source Heat Pumps By VIRSTAR Corporation Geothermal Expertise Since 1978 All information contained herein is the exclusive property of VIRSTAR Corporation, all rights reserved.
Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA
FHWA Hollow Bar Soil Nail (HBSN) Test Program Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA Outline Introduction and motivation Installation methods for testing Testing and
Town House 11265 Center Highway North Huntingdon, PA 15642
APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House
Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing
Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering
Table of Contents 16.1 GENERAL... 16.1-1. 16.1.1 Overview... 16.1-1 16.1.2 Responsibilities... 16.1-1
Table of Contents Section Page 16.1 GENERAL... 16.1-1 16.1.1 Overview... 16.1-1 16.1.2 Responsibilities... 16.1-1 16.1.2.1 Geotechnical Section/Bridge Bureau Coordination... 16.1-1 16.1.2.2 Geotechnical
Milan M5 metro extension the construction of Lotto station
Milan M5 metro extension the construction of Lotto station Giuseppe LUNARDI, Rocksoil S.p.A., Italy [email protected] Luca MANCINELLI, Rocksoil S.p.A., Italy, [email protected] Massimiliano
PVC Pipe for Trenchless Installation
PVC Pipe for Trenchless Installation Design & Installation Guide 1 CONTENTS PAGE NUMBER Introduction 3 Applications 3 Features and Benefits 3 Product Data 4 Material Properties 4 Pipe Stiffness 4 Standards
GLOSSARY OF TERMINOLOGY
GLOSSARY OF TERMINOLOGY AUTHORIZED PILE LENGTHS - (a.k.a. Authorized Pile Lengths letter) Official letter stating Engineer's recommended length of concrete piles to be cast for construction of foundation.
EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL
EXAMPLE DESIGN OF CANTILEVERED WALL, GRANULAR SOIL A sheet pile wall is required to support a 2 excavation. The soil is uniform as shown in the figure. To take into account the friction between the wall
LS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
Sewer Rehabilitation Design Requirements
Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared
The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.