Procurement Strategy. Alpine Shire Council. Document Management. Next review date: Date approved/adopted: 1 March Approved by: Council

Size: px
Start display at page:

Download "Procurement Strategy. Alpine Shire Council. Document Management. Next review date: Date approved/adopted: 1 March Approved by: Council"

Transcription

1 Procurement Strategy Alpine Shire Council Document Management Approved by: Council Date approved/adopted: 1 March 2011 Next review date: Department: Corporate Services Contact person: Dianne Mahlstedt

2 2 Table of Contents Introduction...3 Aim...3 Objectives...3 Goals...3 Processes...4 Mapping...4 Stakeholder Communication...5 Spend Map Analysis...5 The Department...5 The Supplier Level...6 Category Management...6 Contract Management...7 Development and Refinement of E-Procurement Platforms and Process...7 Ensuring better access to Procurement Information...6 The Continuous Improvement of the Tendering and Selection Process...7 Supporting Documents...7 2

3 3 Introduction Alpine Shire Council spend over the last five years is approximately 59.8 million on goods and services. Procurement is recognised by Council and the Local Government sector as a growing area of importance. The Alpine Shire Council is committed to drive efficiencies in all its procurement practices while balancing effectiveness with social, environmental and economic objectives. Council has adopted a Centre-Led Procurement model and the following document outlines how the Procurement Department will manage Councils expenditure over the next four years. This document specifies the key strategic direction of the Procurement Department and the tools and process to develop the procurement chain. Aim The strategy has three (3) overall levels. 1. Objectives and Goals - The direction of the department 2. Processes - the action needed to meet the objectives 3. Activities occurring under each process Goals The Procurement Department will achieve this by a commitment to the following goals: The search and implementation of best practice Procurement. Continuous improvement of all tools, templates, procedures and policies The reduction of time (double handling, repetition) in the procurement process Ensuring Council Procurement complies with relevant legislation and state policies and directions. Identification and implementation of cost savings Engagement with key internal stakeholders, suppliers and peers in the wider Local Government sector A commitment to strengthening, streamlining, standardising and simplifying all Procurement tools, templates, procedures and policies. Achieving environmental sustainability by:- i. Maintaining and restoring our natural assets ii. Using our resources more efficiently, and iii. Reducing our everyday environmental impact 3

4 4 Objectives The Procurement Departments main role is to provide leadership and management to the whole procurement process. Its priority is to assist Council in making better procurement decisions by providing best practice procurement tools, template, processes, and policies. The Department is also there to assist Council executive and Councillors in understanding the What, Why, When and How of Council Purchasing: with a special emphasis on how Council can purchase better. Processes To achieve these goals the Procurement Department has identified seven major processes for the Procurement Strategy: 1. Stakeholder Communication and Training 2. Spend Map Analysis 3. Ensuring better access to Procurement Information 4. The Continuous Improvement of the Tendering Process 5. Supplier Engagement and Training 6. Contract Management 7. Development of E-Procurement Platforms and Process Each process will be performed as part of a never ending continuous improvement loop. As one activity is completed in a process, another one will take its place, ensuring the Procurement Department continually focuses on improving and refining each process, with the continuous aim of strengthening, streamlining standardising, and simplifying, all procurement tools, templates, procedures and policies within Council. It is also noted that many activities within one process will overlap and influence other processes, with the high likelihood of one activity being shared by two or more processes. The continuous improvement loop is defined as a series of never ending questions posed for the purpose of stimulating thinking on procurement within Council and determining enhancements that can be implemented. The strategy attempts to reach best practice procurement by making small incremental changes daily and weekly over a long period of time. Mapping Mapping will be the main tool used in the continuous improvement loop. This technique involves (4) four major steps: 1 Development of new process and practices 4

5 5 2 Identifying Changes 3 Determining how to make changes 4 Implementing Changes, and 5 Reviewing before returning to step 1 Stakeholder Communication Stakeholder communication is one of the most significant processes in the Procurement Strategy. The majority of key procurement decisions within Council, such as annual spends, are usually made by employees outside of Procurement. Therefore significant improvement to Council s procurement process will require the active support of key stakeholders within the organisation. The success the Procurement Department relies on how it interacts with these internal stakeholders in all facets of procurement, from the placing of simple purchase orders right through to a million dollar tender. The strategy seeks to turn the Procurement Department from one that transacts with other departments to one that implements a cultural change across Council. Spend Map Analysis Spend Map Analysis is the second most important process within the Procurement Strategy and involves the Procurement Department conducting reviews and audits of how Council spends its money at three levels. 1 At the department 2 At the supplier 3 At the category The Department Spend map Analysis at the department looks at how buying is done at this level. It seeks to answer the following questions: What is the role of the department? What their goals are? What do they purchase? Who does the purchasing? How it is done? What suppliers they use? What contracts do they have If they don t purchase against a contract why not? How can waste be eliminated from the Purchasing as well as their processes and what efficiencies can be gained 5

6 6 The mapping will be used to determine what their current processes are, where they could improve and how they can get there. Unlike a traditional audit report, the mappings aim is not to find fault or proportion blame, but to identify areas of opportunity, then implement changes with the consent of the department. The overall aim of the procurement strategy, is not only about compliance to the Local Government Act, the strategy seeks to go beyond the government regulation compliance by focusing on best practice procurement and moving Council towards it through collaboration and cooperation. The Supplier Level Carrying on from the departmental review the major suppliers with Council will be analysed. The strategy will do a SWOT analysis of our major suppliers. The strategy seeks also to categorize Council contractors into Procurement categories. The Procurement Department s aim is to use the Procurement Categories developed for Local Government Victoria. Category Management Spend Map analysis involves an outward scan of the categories to analysis the major trends and issues. Questions to be asked will include: Who are the major suppliers are in each Category? What Contracts can Council tap into What are the major trends in the Category? What innovative products services are there? What are the threats and opportunities? The aim is to bring that information back into Council to assist departments purchasing in those categories but also to formulate better procurement decisions and process. Ensuring better access to Procurement Information The Procurement Department s aim is to ensure that all Procurement information is collated into a central point and is accessible to the relevant officers. This process involves: Collating of all Contract information Summarising Contract information for individual suppliers onto individual sheets for end users to absorb Listing all Annual Supply Contracts and agreements Council has entered into with contractors Listing all MAV and Procurement Australia registered contracts 6

7 7 The Continuous Improvement of the Tendering and Selection Process This will be an ongoing process looking at Policies and Procedures affecting the tendering and selection process including the documentation used. The key will be to strengthen, streamline, standardise and simplify them at every possible stage. Supplier Engagement and Training Engagement with key external stakeholders and suppliers through workshops to: Communicate Councils organisational approach to procurement Provide information on Council s annual capital expenditure Updates on tendering requirements and templates Contract Management Contract Management represents an important part of the procurement process at Alpine Shire Council. Poorly managed contracts lead to substandard quality and service, loss of money and in extreme circumstances injury and loss of life. The procurement strategy seeks to implement four important activities within this process 1. Early involvement in specification creation and review with the Procurement Department 2. The development of Council wide protocols and systems for the management of contracts and ongoing reviews to ensure compliance 3. The training and adoption by all procurement stakeholders in these protocols and systems Development of E-Procurement Platforms and Process Council will seek to streamline, standardise and simplify all Procurement tools, templates, procedures and policies through electronic platforms. Supporting Documents Alpine Shire Council Procurement Policy 7

Wales Procurement Policy Statement

Wales Procurement Policy Statement Wales Procurement Policy Statement In December 2012 I launched the Wales Procurement Policy Statement (WPPS) setting out the principles by which I expect public sector procurement to be delivered in Wales.

More information

Procurement & Supply Chain Team. Purpose of the Role

Procurement & Supply Chain Team. Purpose of the Role Role: Responsible To: Responsible For: Location: Procurement & Supply Chain Manager Assistant Director of Finance Procurement & Supply Chain Team Liverpool Purpose of the Role Oversee the group s procurement

More information

South Norfolk Council Business Continuity Policy

South Norfolk Council Business Continuity Policy South Norfolk Council Business Continuity Policy 1 Title: Business Continuity Policy Date of Publication: TBC Version: 2 Published by: Emergency Planning Team Review date: April 2014 Document Owner: Document

More information

Procurement the unlikely hero Rob Ackland CEO, LGA Procurement

Procurement the unlikely hero Rob Ackland CEO, LGA Procurement Procurement the unlikely hero Rob Ackland CEO, LGA Procurement Thank you to ArcBlue for supporting the Procurement Roadmap program and providing information used in the development of this presentation

More information

Position Description

Position Description Position Description POSITION TITLE Procurement Advisor POSITION NO 500268 DIRECTORATE DEPARTMENT Corporate Services Finance UNIT REPORTS TO Manager Finance CLASSIFICATION Band 7 LOCATION Civic Centre,

More information

NATIONAL E-PROCUREMENT PROJECT GUIDANCE NOTES

NATIONAL E-PROCUREMENT PROJECT GUIDANCE NOTES NATIONAL E-PROCUREMENT PROJECT GUIDANCE NOTES PROCUREMENT SPEND ANALYSIS Title: Procurement Analysis Identification: Supports organisations in gathering and analysing procurement spend to highlight system

More information

Supplier Qualification System (SQS)

Supplier Qualification System (SQS) Supplier Qualification System (SQS) for global visibility of Shell suppliers www.shell.com/supplier/qualification Supplier Qualification System (SQS) Shell values its relationships with suppliers and with

More information

DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy

DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy Part Two Part One Not Protectively Marked DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy. The Dorset & Wiltshire Fire and Rescue Authority (DWFRA)

More information

CHAPTER 1: BUSINESS CONTINUITY MANAGEMENT STRATEGY AND POLICY

CHAPTER 1: BUSINESS CONTINUITY MANAGEMENT STRATEGY AND POLICY Zurich Management Services Limited Registered in England: No 2741053 Registered Office The Zurich Centre, 3000 Parkway Whiteley, Fareham Hampshire, PO15 7JZ CHAPTER 1: BUSINESS CONTINUITY MANAGEMENT STRATEGY

More information

HOME GROUP JOB DESCRIPTION. Date:

HOME GROUP JOB DESCRIPTION. Date: HOME GROUP JOB DESCRIPTION 1 JOB DETAILS Job Title: Assistant Finance Business Partner (Care & Support) Reports to: Finance Business Partne Date: Ref: HOMEJD235 2 JOB PURPOSE Based centrally this role

More information

POSITION DESCRIPTION Number: PD:

POSITION DESCRIPTION Number: PD: POSITION DESCRIPTION Number: PD: The VALUES of The City of South Perth Customer Focus - To work together with our customers to achieve positive outcomes. Excellence - To develop a culture of flexibility,

More information

/ BROCHURE / CHECKLIST: PCI/ISO COMPLIANCE. By Melbourne IT Enterprise Services

/ BROCHURE / CHECKLIST: PCI/ISO COMPLIANCE. By Melbourne IT Enterprise Services / BROCHURE / CHECKLIST: PCI/ISO COMPLIANCE By Melbourne IT Enterprise Services CHECKLIST: PCI/ISO COMPLIANCE If your business handles credit card transactions then you ve probably heard of the Payment

More information

Responsibility Deal between Government and the waste and resource management sector. June 2011

Responsibility Deal between Government and the waste and resource management sector. June 2011 www.defra.gov.uk www.esauk.org Responsibility Deal between Government and the waste and resource management sector June 2011 Department for Environment, Food and Rural Affairs Nobel House 17 Smith Square

More information

ESKISP6046.02 Direct security architecture development

ESKISP6046.02 Direct security architecture development Overview This standard covers the competencies concerned with directing security architecture activities. It includes setting the strategy and policies for security architecture, and being fully accountable

More information

Procurement of Goods, Services and Works Policy

Procurement of Goods, Services and Works Policy Procurement of Goods, Services and Works Policy Policy CP083 Prepared Reviewed Approved Date Council Minute No. Procurement Unit SMT Council April 2016 2016/0074 Trim File: 18/02/01 To be reviewed: March

More information

Council Policy Business Continuity Management

Council Policy Business Continuity Management Policy Name: Business Continuity Management Council Policy Business Continuity Management ADOPTED BY COUNCIL: 19 th April 2016 DATE OF NEXT REVIEW: 18 th April 2020 RESPONSIBLE OFFICER: REFERENCES: Chief

More information

Procurement Strategy 2013-2017 Delivering Social Value for our Community

Procurement Strategy 2013-2017 Delivering Social Value for our Community Procurement Strategy 2013-2017 Delivering Social Value for our Community Making Bath & North East Somerset an even better place to live, work and visit 1 Picture courtesy of Bath & News Media Group Our

More information

SAMPLE QUESTIONS EXAM EXEMPLAR QUESTIONS. AD1 - Management in procurement and supply. Level 5 Advanced Diploma in Procurement and Supply

SAMPLE QUESTIONS EXAM EXEMPLAR QUESTIONS. AD1 - Management in procurement and supply. Level 5 Advanced Diploma in Procurement and Supply Level 5 Advanced Diploma in Procurement and Supply AD1 - Management in procurement and supply EXAM EXEMPLAR QUESTIONS CASE STUDY, QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 7 QUALIFICATIONS 2013

More information

Procurement policy Working with our suppliers to support strategic growth

Procurement policy Working with our suppliers to support strategic growth Procurement policy Working with our suppliers to support strategic growth Mission Statement The Procurement Department is the focal point for commercial relationships with Eversheds supply chains, ensuring

More information

Conducting Formative Research

Conducting Formative Research Conducting Formative Research 1 The foundation of any sound sanitation marketing program is formative research. Formative research follows a process and includes a set of tools that can be used to help

More information

Business Continuity Policy and Business Continuity Management System

Business Continuity Policy and Business Continuity Management System Business Continuity Policy and Business Continuity Management System Summary: This policy sets out the structure for ensuring that the PCT has effective Business Continuity Plans in place in order to maintain

More information

Employee Performance Management Policy and Procedure

Employee Performance Management Policy and Procedure Employee Performance Management Policy and Procedure Document Control Document Ref: HREPM001 Date Created: Sept 2007 Version: 1.4 Date Modified: April 2015 Revision due Author: Jane Milone Sign & Date:

More information

DSFRS Procurement Strategy 2013-2017

DSFRS Procurement Strategy 2013-2017 DSFRS Procurement Strategy 2013-2017 Saving money and improving safety Contents Introduction 2 Procurement aim 1: efficiency 2 Procurement aim 2: governance 2 Dsfrs Management 3 spend analysis 2012/2013

More information

Queensland Government Human Services Quality Framework. Quality Pathway Kit for Service Providers

Queensland Government Human Services Quality Framework. Quality Pathway Kit for Service Providers Queensland Government Human Services Quality Framework Quality Pathway Kit for Service Providers July 2015 Introduction The Human Services Quality Framework (HSQF) The Human Services Quality Framework

More information

OPERATIONAL CASE STUDY PRACTICE EXAM ANSWERS

OPERATIONAL CASE STUDY PRACTICE EXAM ANSWERS OPERATIONAL CASE STUDY PRACTICE EXAM ANSWERS The Practice Exam can be viewed at http://www.pearsonvue.com/cima/practiceexams/ These answers have been provided by CIMA for information purposes only. The

More information

Data Analytics Transforming our Understanding of Procurement in Local Government

Data Analytics Transforming our Understanding of Procurement in Local Government Data Analytics Transforming our Understanding of Procurement in Local Government Chris Newman MBA Director ArcBlue Consulting 21 November 2014 ArcBlue Consulting Group www.arcblue.com.au @arcblueconsulting

More information

UK Medical Marketing Courses 2011 / 2012 Programme

UK Medical Marketing Courses 2011 / 2012 Programme UK Medical Marketing Courses 2011 / 2012 Programme To book your place, please call: 0845 4090 897 or email: info@pilgrimconsultancy.co.uk Winning Product Launches Date: 3 rd and 4 th October 2011 Cost:

More information

ICT Digital Transformation Programme

ICT Digital Transformation Programme Officer and Date Item Cabinet 11 th May 2016 Public ICT Digital Transformation Programme Responsible Officer: Clive Wright, Chief Executive Email: Clive.wright@shropshire.gov.uk Tel: 01743 252007 1.0 Summary

More information

Position Description

Position Description Position Description Title Contracts Administration Officer Directorate Corporate Services Department Commercial and Property Services Location Camberwell Classification Band 5 Position code CRPRPPXXCAO

More information

Guideline. Records Management Strategy. Public Record Office Victoria PROS 10/10 Strategic Management. Version Number: 1.0. Issue Date: 19/07/2010

Guideline. Records Management Strategy. Public Record Office Victoria PROS 10/10 Strategic Management. Version Number: 1.0. Issue Date: 19/07/2010 Public Record Office Victoria PROS 10/10 Strategic Management Guideline 5 Records Management Strategy Version Number: 1.0 Issue Date: 19/07/2010 Expiry Date: 19/07/2015 State of Victoria 2010 Version 1.0

More information

Draft Guidance: Non-economic Regulators: Duty to Have Regard to Growth

Draft Guidance: Non-economic Regulators: Duty to Have Regard to Growth Draft Guidance: Non-economic Regulators: Duty to Have Regard to Growth January 2014 Purpose of this document The duty to have regard to the desirability of promoting economic growth (the growth duty )

More information

CIPS Exam Report for Learner Community:

CIPS Exam Report for Learner Community: CIPS Exam Report for Learner Community: Qualification: Unit: Exam series: Advanced diploma in procurement and supply AD2 Management risk in supply chains November, 2013 Exam Series INFORMATION FOR CANDIDATES

More information

Options for the Council s Debit & Credit Card (Merchant Acquirer) Contract Not a Key Decision

Options for the Council s Debit & Credit Card (Merchant Acquirer) Contract Not a Key Decision Cambridge City Council Item To: Report by: Relevant scrutiny committee: Wards affected: Executive Councillor for Strategy: Councillor Julie Smith Julia Minns Strategy & Resources Scrutiny Committee All

More information

Business Resources. QCF Units of Assessment Final NVQ Units April 2010

Business Resources. QCF Units of Assessment Final NVQ Units April 2010 Business Resources QCF Units of Assessment Final NVQ Units April 2010 6 Graphite Square Vauxhall Walk London SE11 5EE T: 0207 0919620 F: 0207 0917340 Info@skillscfa.org www.skillscfa.org Contents No. Title

More information

Weather the Storm. Knox City Council Wednesday, 6 June 2012. Flood Management Workshop

Weather the Storm. Knox City Council Wednesday, 6 June 2012. Flood Management Workshop Weather the Storm Flood Management Workshop report Knox City Council Wednesday, 6 June 2012 Flood Management Workshop Printed: 29 June 2012 P a g e 1 Weather the Storm Flood Management Workshop Knox City

More information

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Australian National Audit Office Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Commonwealth of Australia 2002 ISBN 0 642 80678 0 10 December 2002 Dear Mr

More information

Role Description Vendor Relationship Manager ICT

Role Description Vendor Relationship Manager ICT Role Description Vendor Relationship Manager ICT Classification/Grade/Band Clerk Grade 9/10 ANZSCO Code PCAT Code Date of Approval Primary purpose of the role The Vendor Relationship Manager ICT is responsible

More information

Role Reporting Information. Role Family Analyst (Why the family exists and how it adds value to EnergyAustralia)

Role Reporting Information. Role Family Analyst (Why the family exists and how it adds value to EnergyAustralia) Role Reporting Information Role Title Business Analyst Position Number Role Reports Directly To Practice Leader EnergyAustralia Group Executive Manager Chief Information Officer Date 10/08/2015 Role Family

More information

Opening Doors. The Charter for SME Friendly Procurement

Opening Doors. The Charter for SME Friendly Procurement Opening Doors The Charter for SME Friendly Procurement Foreword 99% of all Welsh businesses are Small and Medium Enterprises (SMEs) and the Welsh Assembly Government recognises and appreciates the very

More information

Section 7 Internal Control Framework

Section 7 Internal Control Framework Section 7 Internal Control Framework Contents Page 7.1 Internal Control and Risk Management... 3 7.1.1 Legislative Framework... 4 7.1.2 Accountability and Transparency... 13 7.2 Risk Management... 15 7.2.1

More information

Information Management Advice 50 Developing a Records Management policy

Information Management Advice 50 Developing a Records Management policy Information Management Advice 50 Developing a Records Management policy Introduction This advice explains how to develop and implement a Records Management policy. Policy is central to the development

More information

Certificate in procurement and supply operations

Certificate in procurement and supply operations Certificate in procurement and supply operations Unit content guide Leading global excellence in procurement and supply Introduction The Chartered Institute of Purchasing & Supply qualifications ladder

More information

ABERDEEN CITY COUNCIL. Name of Committee : Resources Management Committee

ABERDEEN CITY COUNCIL. Name of Committee : Resources Management Committee ABERDEEN CITY COUNCIL Name of Committee : Resources Management Committee Date of Meeting : 29 March 2007 Title of Report : CRM System Procurement Lead Officer : Jacek Nowak, Head of Customer Relations

More information

SUPPLY CHAIN CODE OF PRACTICE. Streamlining processes and increasing value for the oil and gas industry

SUPPLY CHAIN CODE OF PRACTICE. Streamlining processes and increasing value for the oil and gas industry SUPPLY CHAIN CODE OF PRACTICE Streamlining processes and increasing value for the oil and gas industry About The Supply Chain Code of Practice The Supply Chain Code of Practice (SCCoP) outlines a set

More information

Efficiency Review by Sir Philip Green

Efficiency Review by Sir Philip Green Efficiency Review by Sir Philip Green Key Findings and Recommendations The Government is failing to leverage both its credit rating and its scale 1 Introduction I was asked by the Prime Minister in mid

More information

DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY

DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY VERSION 1.0 ISSUED JULY 2015 CONTENTS Page CONTENTS VERSION CONTROL FOREWORD i ii iii POLICY 1 Scope 1 Aim and Objectives 1 Methods and Standards 1

More information

Position Description

Position Description Position Description POSITION TITLE Risk and Compliance Coordinator POSITION NO 500024 DIRECTORATE DEPARTMENT UNIT REPORTS TO Corporate Services Organisational Development Risk and Compliance Manager Organisational

More information

VICTORIAN GOVERNMENT DEPARTMENT ENVIRONMENTAL MANAGEMENT SYSTEM MODEL MANUAL

VICTORIAN GOVERNMENT DEPARTMENT ENVIRONMENTAL MANAGEMENT SYSTEM MODEL MANUAL MODEL FINAL VERSION 1, MARCH 2003 ACKNOWLEDGMENTS This Manual is based on Environment Australia s Model EMS 1 and has been adapted for use by Victorian Government agencies by Richard Oliver International.

More information

Business Continuity Policy. Version 1.0

Business Continuity Policy. Version 1.0 Business Continuity Policy Version.0 January 206 Contents Contents Version control Foreword Policy. Scope.2 Aim and objectives.3 Methods and standards.4 Responsibilities.5 Governance.6 Training and exercises

More information

Risk Management Policy

Risk Management Policy 1 Purpose Risk management relates to the culture, processes and structures directed towards the effective management of potential opportunities and adverse effects within the University s environment.

More information

Sector Development Ageing, Disability and Home Care Department of Family and Community Services (02) 8270 2218

Sector Development Ageing, Disability and Home Care Department of Family and Community Services (02) 8270 2218 Copyright in the material is owned by the State of New South Wales. Apart from any use as permitted under the Copyright Act 1968 and/or as explicitly permitted below, all other rights are reserved. You

More information

The Electrical Contractor Safety Program Guide

The Electrical Contractor Safety Program Guide The Electrical Contractor Safety Program Guide September 2013 Electrical Hazard Warning Sign Disclaimer Whilst this guide endeavors to provide general information on work health and safety issues relating

More information

UNSOLICITED PROPOSALS

UNSOLICITED PROPOSALS UNSOLICITED PROPOSALS GUIDE FOR SUBMISSION AND ASSESSMENT January 2012 CONTENTS 1 PREMIER S STATEMENT 3 2 INTRODUCTION 3 3 GUIDING PRINCIPLES 5 3.1 OPTIMISE OUTCOMES 5 3.2 ASSESSMENT CRITERIA 5 3.3 PROBITY

More information

ECO-Buy Limited. Australian Packaging Covenant Action Plan (Final) September 2012 June 2015

ECO-Buy Limited. Australian Packaging Covenant Action Plan (Final) September 2012 June 2015 ECO-Buy Limited Australian Packaging Covenant Action Plan (Final) September 2012 June 2015 1 Summary This is ECO-Buy s first action plan as a new Signatory to the Australian Packaging Covenant. We are

More information

Operations Manager Job Description March 2012

Operations Manager Job Description March 2012 Operations Manager Job Description March 2012 Thermaflo is seeking an experienced Operations Manager with a technical background in process engineering. At Thermaflo we strongly believe that the success

More information

Strategic Alliance. Business Continuity Policy

Strategic Alliance. Business Continuity Policy Version 1.1 April 2016 Contents Contents Version control Foreword Policy Scope Aim and objectives Methods and standards Responsibilities Governance Training and exercises Page i ii 1 2 2 2 Version 1.1

More information

Training Curriculum. Training Team

Training Curriculum. Training Team Training Curriculum Training Team Contents Welcome to Asite Training\...3 Training Techniques\...4 a) Presentation Style Training\...4 b) Classroom Style Training\...5 c) Self Study Learning\...6 Client

More information

DATA QUALITY STRATEGY

DATA QUALITY STRATEGY DATA QUALITY STRATEGY June 2008 G:\Performance Management\data quality\data Quality Strategy08.doc 1 CONTENTS CONTENTS 2 1. INTRODUCTION 3 2. BACKGROUND INFORMATION 3 3. THE PRINCIPLES OF DATA QUALITY

More information

Corporate Procurement Strategy 2014-2017

Corporate Procurement Strategy 2014-2017 Strategy 2014-2017 Strategy 2014-2017 Introduction The Brighton & Hove community is distinctive for its strong international flavour and vibrant diversity of cultures. The make-up of the local population,

More information

Version No: 2 Date: 27 July 2015. Data Quality Policy. Assistant Chief Executive. Planning & Performance. Data Quality Policy

Version No: 2 Date: 27 July 2015. Data Quality Policy. Assistant Chief Executive. Planning & Performance. Data Quality Policy Version No: 2 Date: 27 July 2015 Data Quality Policy Assistant Chief Executive Planning & Performance Data Quality Policy Contents 1. Summary Statement 2. Context 3. Purpose 4. Scope 5. Detail of the policy

More information

Position Description. Transactional Services/Accounting Services. Grade

Position Description. Transactional Services/Accounting Services. Grade Position Description Position Title Division Business Business Unit Grade Accountant Shared Services Shared Services Financial Services Transactional Services/Accounting Services Responsible For Participation

More information

School Maintenance: Getting Value for Money

School Maintenance: Getting Value for Money School Maintenance: Getting Value for Money WA Labor Consultation Paper August 2015 School Maintenance: Getting Value for Money Executive Summary Better Schools for our Kids WA Labor is committed to delivering

More information

Human Resource Change Management Plan

Human Resource Change Management Plan Structural Reform in Western Australian Local Governments Human Resource Change Management Plan A resource for the progression of your workforce through the structural reform process Contents Human Resource

More information

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should

More information

Sustainable Supply Chain Management Policy

Sustainable Supply Chain Management Policy pwc.com.au Sustainable Supply Chain Management Policy December 2014 Policy Owner Sommer Baxter, Procurement Director Business/Function Procurement - Finance & Business Services PwC Sustainable Supply Chain

More information

The Advanced Certificate in Performance Audit for International and Public Affairs Management. Workshop Overview

The Advanced Certificate in Performance Audit for International and Public Affairs Management. Workshop Overview The Advanced Certificate in Performance Audit for International and Public Affairs Management Workshop Overview Performance Audit What is it? We will discuss the principles of performance audit. The session

More information

To be used in conjunction with the Invitation to Tender for Consultancy template.

To be used in conjunction with the Invitation to Tender for Consultancy template. GUIDANCE NOTE Tendering for, choosing and managing a consultant Using this guidance This information is not intended to be prescriptive, but for guidance only. Appointing consultants for relatively small

More information

Developing a Project. Management System. Using Project Agency Template. Approach. - the Process and the Benefits

Developing a Project. Management System. Using Project Agency Template. Approach. - the Process and the Benefits Developing a Project Management System Using Project Agency Template Approach - the Process and the Benefits Project Agency June 2008 Developing your own Project Management System. Project Agency has worked

More information

INIVTATION TO TENDER - DOCUMENT BACK SCANNING SERVICE (REF:CU2410)

INIVTATION TO TENDER - DOCUMENT BACK SCANNING SERVICE (REF:CU2410) Wards Affected: All Wards ITEM 10 CABINET PROCUREMENT COMMITTEE 4 MARCH 2014 INIVTATION TO TENDER - DOCUMENT BACK SCANNING SERVICE (REF:CU2410) Authors: P Wheeler - Head of IT Strategic Development Tel:

More information

Enterprise Risk Management Policy

Enterprise Risk Management Policy Enterprise Risk Management Policy A Framework for Managing Opportunity and Risk Date: 27 November 2015 Version: 13.0 Classification: Unclassified Authors: Julie Holland - Risk Management Facilitator Quality

More information

SUSTAINABLE PROCUREMENT CENTRE OF EXCELLENCE FOR HIGHER EDUCATION. London Universities Environmental Group 8 th November 2011

SUSTAINABLE PROCUREMENT CENTRE OF EXCELLENCE FOR HIGHER EDUCATION. London Universities Environmental Group 8 th November 2011 SUSTAINABLE PROCUREMENT CENTRE OF EXCELLENCE FOR HIGHER EDUCATION London Universities Environmental Group 8 th November 2011 AGENDA Role of the SPCE Benefits Realisation SPCE Website Capacity Building

More information

AIRBUS CORPORATE ANSWER TO DISSEMINATE ENVIRONMENTAL MANAGEMENT SYSTEM. Environmental requirements for suppliers and management of the supply chain

AIRBUS CORPORATE ANSWER TO DISSEMINATE ENVIRONMENTAL MANAGEMENT SYSTEM. Environmental requirements for suppliers and management of the supply chain ACADEMY AIRBUS CORPORATE ANSWER TO DISSEMINATE ENVIRONMENTAL MANAGEMENT SYSTEM ECO-EFFICIENCY AND SUSTAINABILITY - G7 - ISSUE 1 Environmental requirements for suppliers and management of the supply chain

More information

Bedford Group of Drainage Boards

Bedford Group of Drainage Boards Bedford Group of Drainage Boards Risk Management Strategy Risk Management Policy January 2010 1 Contents 1. Purpose, Aims & Objectives 2. Accountabilities, Roles & Reporting Lines 3. Skills & Expertise

More information

The importance of using the right tools

The importance of using the right tools Benchmark Estimating Software Whitepaper The importance of using the right tools Benefits of an estimating software package over traditional spreadsheets Author: David Power Distribution Manager 49 Berry

More information

Info sheet : Considering labour standards in the procurement process

Info sheet : Considering labour standards in the procurement process Info sheet : Considering labour standards in the procurement process In line with the EU procurement rules and the Government s value for money principle, contracting authorities can take steps to consider

More information

Impartiality must be maintained in selecting suppliers to fulfil Council s requirements.

Impartiality must be maintained in selecting suppliers to fulfil Council s requirements. Title: Type: Council Adopted: 17 December 2014 File No: SF/491 TRIM Reference: 14/35410 Attachments: Guidelines (TRIM: 14/38862) 1. Purpose The purpose of this policy is to provide principles, processes

More information

Social Value briefing

Social Value briefing Social Value briefing About This Briefing This briefing is provided on behalf of the Department for Education s overarching strategic partnership for voluntary, community and social enterprise sector organisations

More information

CENTRAL BANK OF KENYA (CBK) PRUDENTIAL GUIDELINE ON BUSINESS CONTINUITY MANAGEMENT (BCM) FOR INSTITUTIONS LICENSED UNDER THE BANKING ACT

CENTRAL BANK OF KENYA (CBK) PRUDENTIAL GUIDELINE ON BUSINESS CONTINUITY MANAGEMENT (BCM) FOR INSTITUTIONS LICENSED UNDER THE BANKING ACT CENTRAL BANK OF KENYA (CBK) PRUDENTIAL GUIDELINE ON BUSINESS CONTINUITY MANAGEMENT (BCM) FOR INSTITUTIONS LICENSED UNDER THE BANKING ACT JANUARY 2008 GUIDELINE ON BUSINESS CONTINUITY GUIDELINE CBK/PG/14

More information

JOB DESCRIPTION. 1. JOB TITLE: Assistant Procurement Officer. 4. DEPARTMENT: Chief Financial Officer/Bursar s Office

JOB DESCRIPTION. 1. JOB TITLE: Assistant Procurement Officer. 4. DEPARTMENT: Chief Financial Officer/Bursar s Office JOB DESCRIPTION 1. JOB TITLE: Assistant Procurement Officer 2. REFERENCE NUMBER: HR13297a 3. ROLE CODE: APOBO 4. DEPARTMENT: Chief Financial Officer/Bursar s Office 5. ORGANISATION CHART: Chief Financial

More information

PROCUREMENT STRATEGY. Charity number SC004401

PROCUREMENT STRATEGY. Charity number SC004401 Charity number SC004401 PROCUREMENT STRATEGY 1.PURPOSE... 2 2.OUR ROLE... 2 3. STRATEGIC VISION... 2 4.SPEND DATA... 3 5. ROAD MAP... 4 6. STRATEGIC INTENT... 4 7. OBJECTIVES... 5 7.1 Efficiency Objectives...

More information

Procurement guidance Prequalifying suppliers

Procurement guidance Prequalifying suppliers Procurement guidance Prequalifying suppliers Procurement guidance: Prequalifying suppliers Page 2 of 21 Table of contents Table of contents... 2 Purpose of this Guide... 4 Who should read this Guide?...

More information

Corporate Performance Reporting

Corporate Performance Reporting Corporate Performance Reporting Policy Owner Manager Business Transformation Business Transformation Creation Date {15/05/2015} Revision Date {DD/MM/YYYY} Please check Council s Intranet to ensure this

More information

Health and Safety Policy Part 1 Policy and organisation

Health and Safety Policy Part 1 Policy and organisation Health and Safety Policy Part 1 Policy and organisation ICO H&S Policy Policy and organisation, June 2014 Page 1 of 6 1. Scope 1.1 The Health and Safety policy applies to all employees of the Information

More information

Business Continuity Management

Business Continuity Management Business Continuity Management Policy Statement & Strategy July 2009 Basildon District Council Business Continuity Management Policy Statement The Council is committed to ensuring robust and effective

More information

Management of Business Support Service Contracts

Management of Business Support Service Contracts The Auditor-General Audit Report No.37 2004 05 Business Support Process Audit Management of Business Support Service Contracts Australian National Audit Office Commonwealth of Australia 2005 ISSN 1036

More information

Consultancy spending approval process: Initial guidance to NHS foundation trusts

Consultancy spending approval process: Initial guidance to NHS foundation trusts Annex One Consultancy spending approval process: Initial guidance to NHS foundation trusts Summary 1. Monitor, the NHS Trust Development Authority (TDA) and NHS England are jointly implementing an approval

More information

Introduction. A guide to doing Business with Cumbria County Council

Introduction. A guide to doing Business with Cumbria County Council WHO ARE PROCESS PQQ E PROCUREMENT TO OBTAIN BUSINESS Introduction A guide to doing Business with Cumbria County Council The purpose of this booklet is to ease access to the purchasing mechanisms of Cumbria

More information

Records Management & Data Quality in the Contact Centre. Internal Audit Report 2013/14

Records Management & Data Quality in the Contact Centre. Internal Audit Report 2013/14 Records Management & Data Quality in the Report 2013/14 Records Management & Data Quality in the Ann Kirk & Julie Ball 19 May 2014 Contents Audit: Auditor: Records Management & Data Quality in the Ann

More information

Councillor David Chambers Date of Decision/Referral to O & S REPORT OF: STRATEGIC DIRECTOR (CORPORATE) SDC/08/37

Councillor David Chambers Date of Decision/Referral to O & S REPORT OF: STRATEGIC DIRECTOR (CORPORATE) SDC/08/37 REPORT TO INDIVIDUAL CABINET MEMBER FOR FINANCE, LEGAL AND ICT 20 MAY 2008 Key Decision YES Forward Plan Ref No Corporate Priority ALL Cabinet Portfolio Holder : Councillor David Chambers Date of Decision/Referral

More information

PROJECT MANAGEMENT PLAN CHECKLIST

PROJECT MANAGEMENT PLAN CHECKLIST PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,

More information

CORPORATE PERFORMANCE MANAGEMENT GUIDELINE

CORPORATE PERFORMANCE MANAGEMENT GUIDELINE -001 CORPORATE PERFORMANCE MANAGEMENT GUIDELINE -001 TABLE OF CONTENTS 1 Introduction... 3 1.1 Scope... 3 1.2 Purpose... 3 2 Performance Management Framework Overview... 4 3 Performance Management Framework...

More information

Integration of Risk Management and Internal Audit. Chartered Institute of Management Accountants, New Zealand

Integration of Risk Management and Internal Audit. Chartered Institute of Management Accountants, New Zealand Integration of Risk Management and Internal Audit Chartered Institute of Management Accountants, New Zealand Contents Understanding the three lines of defense governance model What is Risk? Risk Management

More information

Aberdeen City Council

Aberdeen City Council Aberdeen City Council Internal Audit Report Final Contract management arrangements within Social Care & Wellbeing 2013/2014 for Aberdeen City Council January 2014 Internal Audit KPI Targets Target Dates

More information

Government Communication Professional Competency Framework

Government Communication Professional Competency Framework Government Communication Professional Competency Framework April 2013 Introduction Every day, government communicators deliver great work which supports communities and helps citizens understand their

More information

Steel procurement in major projects: Guidance on the application of social issues. Purpose

Steel procurement in major projects: Guidance on the application of social issues. Purpose Steel procurement in major projects: Guidance on the application of social issues Purpose 1. This is a practical guide on how to incorporate social issues in major projects with a significant steel component.

More information

European Commission Green Public Procurement (GPP) Training Toolkit - Module 1: Managing GPP Implementation. Joint procurement.

European Commission Green Public Procurement (GPP) Training Toolkit - Module 1: Managing GPP Implementation. Joint procurement. European Commission Green Public Procurement (GPP) Training Toolkit - Module 1: Managing GPP Implementation Joint procurement Fact sheet Toolkit developed for the European Commission by ICLEI - Local Governments

More information

Risk Management Policy. Corporate Governance Risk Management Policy

Risk Management Policy. Corporate Governance Risk Management Policy Corporate Governance Risk Management Policy Approved by the Council of Ministers, May 2006 1. Background The Isle of Man Government is working to promote better risk management, with emphasis on the importance

More information

Royal Borough of Kensington and Chelsea. Data Quality Framework. ACE: A Framework for better quality data and performance information

Royal Borough of Kensington and Chelsea. Data Quality Framework. ACE: A Framework for better quality data and performance information Royal Borough of Kensington and Chelsea Data Quality Framework ACE: A Framework for better quality data and performance information March 2010 CONTENTS FOREWORD 2 A CORPORATE FRAMEWORK FOR DATA QUALITY

More information

Key Words: Flood Reconstruction, Resource Contracts, Coal Seam Gas, Contract Management, Project Management, Relationship Contracting

Key Words: Flood Reconstruction, Resource Contracts, Coal Seam Gas, Contract Management, Project Management, Relationship Contracting Rebuilding Flood Damaged Roads in South East Queensland in the middle of the Coal Seam Gas Expansion/Explosion - A Local Governments Experience and Learning's David Pemberton davep@logit.com.au Mobile

More information

Supplier Assurance Framework Good Practice Guide

Supplier Assurance Framework Good Practice Guide Supplier Assurance Framework Good Practice Guide Version 2.0 February 2015 1 P a g e V e r s i o n 2. 0 F e b 1 5 Contents INTRODUCTION... 3 SUPPLIER ASSURANCE FRAMEWORK OVERVIEW... 4 USING THE STATEMENT

More information