1 Rebuilding Flood Damaged Roads in South East Queensland in the middle of the Coal Seam Gas Expansion/Explosion - A Local Governments Experience and Learning's David Pemberton Mobile Flood & Resource Program Manager - Western Downs Regional Council Abstract Local Government in Queensland, Australia over the past few years has been subjected to some of the most challenging engineering and infrastructure management issues ever encountered. Commencing in 2010 through to 2014 Queensland has been subjected to Flooding Disasters costing $13.6B in repairs. While the flood events were occurring, the state was also undergoing gas explosion with the development of the CSG - Coal Seam Gas Exploration and Development Boom in South West Queensland. Coal Seam Gas supplies 27% of the nations reserve and is expanding. This paper provides an overview of some of the challenges that Local Government has faced in repairing its Roads Infrastructure, whilst negotiating and accommodating the significant increased demand, impact and access on its roads caused by the CSG Gas Industry at the same time. Managing these complex challenges required a team that was committed and competent in delivering projects, contract and services in a proactive, positive and collaborative way. This paper presents an overview of the systems and processes that were established in meeting these challenges and shares some experiences, highlights and learnings to apply for the future Simplicity is the key and good relationships are pivotal. Sharing the experiences and lessons learned helps everyone plan for a better and brighter future. Key Words: Flood Reconstruction, Resource Contracts, Coal Seam Gas, Contract Management, Project Management, Relationship Contracting Pemberton Dave.docx Page 1 of 9

2 Introduction Western Downs Regional Council (WDRC) in 2010 encountered an era that will never be repeated in a lifetime of Local Government. Coal Seam Gas extraction was in its early infancy of being developed and the region began a prolonged and repeated experience of flooding across the region for a number of years. This paper shares the experiences, the challenges and the learnings that have evolved over time and provides some recommendations for the future should similar situations be encountered again. Background Western Downs Regional Council Statistics Size Area: = 38,000 sq.km Road Network Federal Roads: = 230 km State Roads: = 1,719 km Local Government o Sealed: = 2,103 km o Gravelled: = 4,320 km o Formed: = 953 km o Unformed: = 147 km Capacity Council Workforce: = 750 Staff Engineering Department: = 450 Staff Localities Regions (5) - Dalby, Tara, Chinchilla, Miles, Wandoan Year Capital & Maint. Flood Works Resource Works 2010 $18.6M $5.3M $0.8M 2011 $25.3M $96.6M $48.7M 2012 $87.2M $5.9M $61.0M 2013 $91.5M $69.0M $14.2M 2014 $22.1M $5.0M $5.0M The Challenges Delivery of such a significant program was beyond the capacity and capability of the Council. Options were considered about how to deliver Flood & Resource Works across the region. One of the major issues and risks for delivery was competing for contractors and skilled personnel against the high demand and salaries that was being paid across the region by the Resource Industries. Council was supposed to deliver the 2011 Flood works by June This was very quickly identified as not being achievable or practicable whilst achieving value for money. Early discussions were held with the Queensland Reconstruction Authority (QRA) to advise of Councils situation and its plan to deliver the 2011 Flood works by June Little did we know that we would then be flooded again in 2012, 2013 & 2014!!. Framework for WDRC established a contract Program Managers role who in turn established Two (2) Contractor Panels for delivery: - 1. Panel of Civil Contractors 2. Panel of Project Coordinators In order to deliver the actual works, Council explored a number of Contract delivery models. After much review, discussion and debate, Council established a relationship contract arrangement whereby incentives were provided by way of: - Removing Risk (Where known) Implementing Day Rates Pricing - Linked to Package Estimates Two Weekly Progress Claims & Payments Simplified Project Management Simplified Project Records Smaller Project Packaging Supporting & Developing Local Contractor Capacity Pemberton Dave.docx Page 2 of 9

3 Relationship Contract Delivery Low Project Management Overhead Framework for In order to meet increased QRA administrative and reporting requirements together with increased Council and community expectations, WDRC enhanced the previous model by: - Moving to Schedules of Rates Contracts Increasing Scope Verification Processes Increasing Scope Change Management, reporting and Approvals Processes. Increasing Quality Testing, Inspections and Reporting Implementing Contractors All Risk Insurance Increasing Project Management Team Contracts Framework The contractual frameworks were developed to meet reporting and management requirements set out by the Qld Disaster Relief & Recovery Arrangements - Guidelines & QRA Submission Guide. We started with the end reporting requirements in mind and then worked backwards to develop a simplified and streamlined system to meet all party s needs. The framework model comprised 3 spheres: - Project Management, Contract Management & overarching Relationship Management PM RM Civil Contractor Panel This panel system was established to enable Council to meet legislative procurement requirements. It enabled Council to engage contractors directly from this panel for project packages. Contractors were assessed based on price, skills, experience and track record. Project Coordination Panel CM This panel system was established to enable Council to meet legislative procurement requirements. It enabled Council to engage relevant project management staff with suitable skills, experience and reasonable charges to undertake project management and delivery, Project Packages Contracts Approved Contractors were invited to submit prices and programs to undertake Project Packages. Packages were compiled into groups based on locations, similar scope and approximately 3 months work. The Contracts were based on a AS 2124 Contractual Framework. The Technical Specification used for the works was NATSPEC. In 2014/15 Main Roads Specifications were also considered. Schedules used for pricing were a modified Form 4 - The form used by QRA in approving the scope of works for the projects. Allocation of packages were assessed by a panel and allocated based on price, performance, current workload whilst ensuring reasonable momentum was being maintained in overall program delivery Frameworks Contractors submitted package prices on a day rates schedule and packaged duration, delivery arrangement Frameworks Contractors submitted package prices on schedules of rates basis and packaged duration delivery arrangement. Contract Management Frameworks The main project team managing this project comprised of 5 staff:- Program Manager - 1 Project Coordinators - 3 Finance Officer - 1 Internal Operations Staff provided input and managed the delivery by internal day labour. Pemberton Dave.docx Page 3 of 9

4 Contract management systems were developed using 4 - IT tools: - 1. MS Word (Specifications), 2. MS Excel (Schedules, Claims, Monitoring & Reporting) 3. MS Project (Gantt Charting Projects Progress) 4. MS Outlook (All Communications) Pivot tables were used to summarise package information, roads registers, gravel demand production schedules, overall project and program performance. Project Packaging comprised similar projects within a region with an estimated duration of around 3 months work. This limited Councils exposure to risk on Contractors performance Successful contractors were selected based on price, skills, capability and availability. Monitoring on price, quality and performance was undertaken as part of progress claim process which occurred on a fortnightly basis. Any variances were addressed promptly to minimise disruption or ongoing issue or dispute. Contractors were required to take a minimum of 2 photos daily to record works in progress and also any variations or issues that arose on site. Photos were collected on a fortnightly basis with progress claims. Inspections were undertaken by project Coordinators a minimum of one site visit per week Frameworks Project packaging was similar to that model used for works, with the exception that the contracts were now a schedule of rates and higher risk projects had defects liability periods and retentions applied. Progress claims were undertaken on a monthly basis. Increased requirement for quality testing and reporting were implemented. Future contracts considered contractors past performance and relationships Inspections were undertaken by project Coordinators every two to three days maximum. Daily site inspection records were also implemented and utilised as a site instruction record if required. Contract Monitoring Contract Monitoring involved micro and macro management. At a micro level, each project and package was monitored on a fortnightly basis against tendered programs and price. Clear scheduling and project scoping together with on site prestart meetings assisted in keeping variations to a minimum. At a macro level the overall program delivery was monitored using MS project and Excel Pivot Tables to ensure that the overall program was being delivered within allocated timeframes and milestone targets. Monthly Progress Reports and Claims were being made to QRA. This was also supported by a quarterly review report on overall program delivery. These reports enable all parties to clearly see the state of play on program delivery. As issues arose during delivery, these were quickly addressed with the relevant parties to ensure that momentum was being maintained. Dalby Urban Works Delivering $27M worth of 2011 flood reconstruction works in an 18 month period was a mammoth task. Historically Dalby town undertook a capital spend of $1 to 1.5M per annum. This project comprised; lowering roads by 300 to 450mm, installation of stormwater drainage systems, relocation of services, installation of kerb and channel and rebuilding the roads. Council contributed $8M towards the complimentary works which comprised the drainage and kerb works. This area of town had no kerb and channel or stormwater systems. Under a normal works program this project would have taken decades to achieve. Pemberton Dave.docx Page 4 of 9

5 In order to undertake this project in such a short time extensive planning, design and community engagement had to be fast tracked. Designs were carried out internally within Council with external designers engaged on secondment. Three (3) External Contractors and two (2) Internal Construction Teams were established to deliver the works. Program delivery was centrally coordinated due to the significant number of road closures that had to occur. This resulted in a number of ongoing and changing detour routes on a two weekly basis. Community Engagement Delivering these major projects resulted in the establishment of a number of community engagement arrangements. The Dalby Urban Works involved a number of community displays and workshops with local residents to forewarn of the major impacts and disruptions that were going to occur. Council developed a section on its website where the community could be informed of up to date information. In addition to this, local residents received letter box drops advising of; Project Coordinator and Contractor contacts, together with details and impacts for access when their road was being closed to the public and how they could access their properties. This proactive approach resulted in minimal complaints and issues being raised during this works. Regionally Council published in the local papers details of the program delivery including the roads that were being reconstructed over the next 3 month period. Council Customer Service Centre were provided with regular updates of which contractors were working in the regions and how the Project Coordinator was to be contacted should an issue or a complaint be raised. Gravel & Water Resource Management Early on Council identified that supply of gravel and water would be an issue. Council considered options and decided that it would take control of the management and supply of these materials. A specialist environmental/gravel project officer was appointed to manage and coordinate the supply of gravel production and water supply. Gravel was either supplied as a crushed or uncrushed product depending on the pit and road works application. A number of gravel crushing contractors were established and engaged under the Contractor Panel. One of the main issues was securing access and approvals for the extraction of water and gravel from landholders. Council was competing against the resource industry demands that were prepared to pay significant royalties for gravel and water. Balancing Competing Issues Delivering both the Flood reconstruction works and the Resource Infrastructure upgrade works at the same time had a major impact on the roads and the community. Parts of the community were happy to see both occurring, other sections were not happy with the impact by the resource industry. Balancing the high demand from the resource industry which was prepared to pay a premium for delivery was challenging delivery of flood reconstruction works, where government were seeking to minimise costs and expenditure for flood works whilst still setting restricted timeframes for delivery. This was achieved through the delivery via relationship management. Lessons Learnt Overall, delivery of such a significant project was not without its challenges. What started out as relatively simple management process morphed into quite a complicated and detailed management and reporting process. This was mainly due to the ever changing and increased expectations being applied by the Federal and State Government. Pemberton Dave.docx Page 5 of 9

6 The underlying principal of keeping things simple and keeping the end outcomes in mind has been the success of delivering this program. Managing Risk, Scope & Issues needs to be at the forefront of any decision and process: - Setting up systems that can be easily understood and supported from all stakeholders is vital. Keep things simple. Do not get too prescriptive. Be more objective Be clear on what is expected at the end Be clear on how you wish to see things happen. Changes to process and systems can be achieved if communicated clearly. Often the experience encountered was the changes were communicated after the event or activity had passed. Identifying and communicating with your main stakeholders in these types of projects is critical. Stakeholders include: - The Government - Federal & State Your Local Government - Councillors, Executive and Operations Your Contractors Your Team; and most importantly Your Community - Businesses, Property Owners other Visitors In Summary 1. Quality is the Key 2. Communication is continuous & dynamic 3. Relationships are pivotal 4. Listen to all sides of the issue/s 5. Be prepared to change if needed. 6. Make a decision 7. Maintain a high standard 8. Keep long term impacts in mind 9. Developing skills within your organisation and with your local contractors provides an ongoing benefit The Way Forward Looking to the future, there has been a change in management requirements by QRA for delivering these types of projects. Some minor changes in delivery and systems management will be required to meet these changes. Having had the experience and hindsight of what has and has not worked WDRC would continue with its simplified and low project management delivery model for these types of projects. Conclusion Major Projects for medium sized Councils is quite a challenge. WDRC has adopted a low project management overhead, simplified process and relationship style contract approach in delivering its Major Flood & Resource Programs. Over the past 18 months, minor changes have been made to address issues as they arose, however this delivery model and the focus on relationship delivery of projects has been found to be very successful. References Nil Pemberton Dave.docx Page 6 of 9

7 Appendix A Project Delivery Trend Analysis Gravel Pit Demand Pivot Table Pemberton Dave.docx Page 7 of 9

8 Never underestimate the power of Pivot Tables!!! - Take up the Challenge and reap the Rewards. Pemberton Dave.docx Page 8 of 9

9 Author Biography David Pemberton David is a Consultant Engineering and Program Manager from LogIT Solutions that has been engaged by WDRC to assist in establishing, implementing and delivering the Major Project Works resulting from the Flood Reconstruction Damage of 2010, 2011, 2012, 2013 & the Resource Industry Expansion across the region. David has been a Director of Engineering within Local Government and has over 30 years of experience in Project Management, Design & Contract Management in Civil Engineering and Local Government. Postal Address: 424 West Street, Toowoomba, Qld Phone: Pemberton Dave.docx Page 9 of 9

A submission by Tumut Shire Council for the Productivity Commission Review into Natural Disaster Funding

A submission by Tumut Shire Council for the Productivity Commission Review into Natural Disaster Funding Tumut Shire COUNCIL A submission by Tumut Shire Council for the Productivity Commission Review into Natural Disaster Funding - 6 June 2014 Executive Summary Tumut Shire Council (TSC) is a medium sized

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

ITEM 4 CABINET PROCUREMENT COMMITTEE 1 OCTOBER 2013

ITEM 4 CABINET PROCUREMENT COMMITTEE 1 OCTOBER 2013 Wards Affected: All Wards ITEM 4 CABINET PROCUREMENT COMMITTEE 1 OCTOBER 2013 INVITATION TO TENDER PROVISION OF EXECUTIVE SEARCH AND SELECTION SERVICES (REF: CU2380) Author: Morag Shaw, Assistant Director,

More information

STRATEGIC ASSET MANAGER POSITION & PERSON DESCRIPTION February 2015

STRATEGIC ASSET MANAGER POSITION & PERSON DESCRIPTION February 2015 GENERAL Position & Person Descriptions form an important part of an integrated planning process to ensure that individual performance, and the required outputs and outcomes, align with the strategic and

More information

Infrastructure Asset Management Strategy

Infrastructure Asset Management Strategy Infrastructure Asset Management Strategy Strategy Owner Manager Parks and Assets Engineering and Infrastructure Creation Date 27 March 2006 Revision Date 4 March 2015 Please check Council s Intranet to

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

Status Report. Community Leaders Council

Status Report. Community Leaders Council Status Report Community Leaders Council 4 February 2016 Key points QGC is an integrated natural gas operator Our business transitioned in 2015 from a large scale construction business to an operator nearing

More information

How to get value for money from service providers on major projects

How to get value for money from service providers on major projects How to get value for money from service providers on major projects Session Focus Contracting as a relationship Identifying win/win arrangements Procurement & Planning on major projects Understanding the

More information

Trade Training Centres in Schools Programme

Trade Training Centres in Schools Programme Trade Training Centres in Schools Programme Discussion Paper for Stakeholder Consultations February 2007 1 Contents Introduction...3 Overview...3 Programme objectives...4 Priorities...4 A partnership approach...5

More information

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should

More information

Procurement, Contracting and Contract Management Policy

Procurement, Contracting and Contract Management Policy Procurement, Contracting and Contract Management Policy Corporate policy 8.4 Responsible Officer: Group Manager Accounting and Taxation Policy Custodian: Chief Finance Officer Division: Finance and Resources

More information

Project Appraisal and Scrutiny Committee Recommendation. E-mail, file storage system and server upgrades

Project Appraisal and Scrutiny Committee Recommendation. E-mail, file storage system and server upgrades Cambridge City Council To: Report by: Scrutiny committee: Wards affected: Executive Councillor for Customer Services and Resources James Nightingale, Head of ICT Client Services Strategy and Resources

More information

Standard Contract Provisions Roads. Volume 6 Early Contractor Involvement (ECI) Contract. Introduction

Standard Contract Provisions Roads. Volume 6 Early Contractor Involvement (ECI) Contract. Introduction Standard Contract Provisions Roads Volume 6 Early Contractor Involvement (ECI) Contract Department of Main Roads Table of Contents 1 USING THIS MANUAL...1 1.1 General Layout...1 1.2 Glossary of Terms...1

More information

QUALITY MANAGEMENT POLICY & PROCEDURES

QUALITY MANAGEMENT POLICY & PROCEDURES QUALITY MANAGEMENT POLICY & PROCEDURES Policy Statement Cotleigh Engineering Co. Limited specialises in the recruitment of engineering & technical personnel in the oil & energy, rail, civil engineering,

More information

Turning around morale and employee engagement within a dispersed construction business

Turning around morale and employee engagement within a dispersed construction business Turning around morale and employee engagement within a dispersed construction business Award Submission Contents Executive Summary 2 Situation Analysis 3 Goals and Objectives 4 Research 5 Target Publics

More information

Supervisor - Engineering Civil Construction

Supervisor - Engineering Civil Construction Supervisor - Engineering Civil Construction The City of Swan is the largest local government area within metropolitan Perth, covering more than 1,044 square kilometres and located less than 30 minutes

More information

Hertsmere Borough Council. Data Quality Strategy. December 2009 1

Hertsmere Borough Council. Data Quality Strategy. December 2009 1 Hertsmere Borough Council Data Quality Strategy December 2009 1 INTRODUCTION Public services need reliable, accurate and timely information with which to manage services, inform users and account for performance.

More information

Q UEENSLAND H EALTH INTRODUCING DEVOLUTION THROUGH COST CENTRE MANAGEMENT. How To Guide

Q UEENSLAND H EALTH INTRODUCING DEVOLUTION THROUGH COST CENTRE MANAGEMENT. How To Guide Q UEENSLAND H EALTH INTRODUCING DEVOLUTION THROUGH COST CENTRE MANAGEMENT How To Guide Foreword In modern health care organisations, clinicians and managers should continually explore options to enhance

More information

JOB DESCRIPTION. Property Manager Project Planning and Development Property Services JOB TITLE: DEPARTMENT: DIVISION: PRIME FUNCTION

JOB DESCRIPTION. Property Manager Project Planning and Development Property Services JOB TITLE: DEPARTMENT: DIVISION: PRIME FUNCTION G07/496 UNIVERSITY OF OTAGO Te Whare Wananga o Otago JOB DESCRIPTION JOB TITLE: DEPARTMENT: DIVISION: Property Manager Project Planning and Development Property Services PRIME FUNCTION To provide a comprehensive

More information

TITLE OF NOMINATION: 2004 Flood Restoration Program FULL NAME OF COUNCIL/ORGANISATION: Moree Plains Shire Council

TITLE OF NOMINATION: 2004 Flood Restoration Program FULL NAME OF COUNCIL/ORGANISATION: Moree Plains Shire Council TITLE OF NOMINATION: 2004 Flood Restoration Program FULL NAME OF COUNCIL/ORGANISATION: Moree Plains Shire Council ADDRESS, TELEPHONE, FACISIMILE AND EMAIL: PO Box 420, MOREE NSW 2400 Ph: 0267573276 Fax:

More information

UNSOLICITED PROPOSALS

UNSOLICITED PROPOSALS UNSOLICITED PROPOSALS GUIDE FOR SUBMISSION AND ASSESSMENT January 2012 CONTENTS 1 PREMIER S STATEMENT 3 2 INTRODUCTION 3 3 GUIDING PRINCIPLES 5 3.1 OPTIMISE OUTCOMES 5 3.2 ASSESSMENT CRITERIA 5 3.3 PROBITY

More information

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Australian National Audit Office Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Commonwealth of Australia 2002 ISBN 0 642 80678 0 10 December 2002 Dear Mr

More information

Highways Maintenance Capital Funding Self-Assessment Questionnaire for the Incentive Fund 1 Important information

Highways Maintenance Capital Funding Self-Assessment Questionnaire for the Incentive Fund 1 Important information Highways Maintenance Capital Funding Self-Assessment Questionnaire for the Incentive Fund 1 Important information What is the purpose of this questionnaire? In December 2014, the Secretary of State for

More information

Royalties for the Regions Floodplain Security Scheme Business Case

Royalties for the Regions Floodplain Security Scheme Business Case Royalties for the Regions Floodplain Security Scheme Business Case Version 3 October 2012 The Royalties for the Regions program is delivered through the Department of State Development, Infrastructure

More information

RISK MANAGEMENT STRATEGY

RISK MANAGEMENT STRATEGY RISK MANAGEMENT STRATEGY 2014-15 April 2014 Page 1 of 17 CONTENTS 1. Introduction 2. What is risk management? 3. Risk Management Policy Statement 4. Risk Management process 5. Roles and responsibilities

More information

Managing construction procurement risks

Managing construction procurement risks CONSTRUCTION PROCUREMENT BEST PRACTICE GUIDELINE #A5 Construction Industry Development Board Pretoria - Head Office Tel: 012 482 7200 Fraudline: 0800 11 24 32 Call Centre: 0860 103 353 E-mail: cidb@cidb.org.za

More information

Project Management Guide

Project Management Guide Appendix 1 to agenda item 10 Project Management Guide 1 Introduction 1.1 Purpose This section sets out the key principles and expectations for how project management should take place at Chichester District

More information

Housing Related Support Contract Management Framework 2009/10

Housing Related Support Contract Management Framework 2009/10 Housing Related Support Contract Management Framework 2009/10 0 If you would like this information in large print, audio tape or in any other format or language please contact the public information officer

More information

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue

Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority

More information

group environmental standards

group environmental standards group environmental standards The Leighton Group is a leading international contractor. We aim to be renowned for excellence, delivering through our operating brands and the empowerment of our people.

More information

Title: Rio Tinto management system

Title: Rio Tinto management system Standard Rio Tinto management system December 2014 Group Title: Rio Tinto management system Document No: HSEC-B-01 Standard Function: Health, Safety, Environment and Communities (HSEC) No. of pages: 23

More information

Social impact assessment. Guideline to preparing a social impact management plan

Social impact assessment. Guideline to preparing a social impact management plan Social impact assessment Guideline to preparing a social impact management plan September 2010 Looking forward. Delivering now. The Department of Infrastructure and Planning leads a coordinated Queensland

More information

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement

More information

Notice of CEO Performance and Remuneration Review Committee

Notice of CEO Performance and Remuneration Review Committee Notice of CEO Performance and Remuneration Review Committee Monday 30 March 2015 MEMBERSHIP Mayor Kevin Knight (Presiding Member) Cr Jim McLafferty Cr Lucas Jones Cr Justin Hanson Cr Paula Luethen-Soper

More information

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the

More information

Consultancy Services Proposal

Consultancy Services Proposal Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847

More information

QUALITY AGENCY REGULATOR PERFORMANCE

QUALITY AGENCY REGULATOR PERFORMANCE QUALITY AGENCY REGULATOR PERFORMANCE As part of its commitment to reduce unnecessary and inefficient regulation the Australian Government commenced a Regulator Performance Framework from 1 July 2015. The

More information

Project Assessment Framework Establish service capability

Project Assessment Framework Establish service capability Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.

More information

Page 1 of 24. To present the Asset Management Policy 2014 for Council adoption.

Page 1 of 24. To present the Asset Management Policy 2014 for Council adoption. Page 1 of 24 COMMUNITY AND SERVICES SPECIAL COMMITTEE REPORT 9 DECEMBER 2104 AGENDA ITEM 6.1 ASSET MANAGEMENT POLICY 2014 REVIEW Director: Manager: Ian Butterworth Director Infrastructure and Engineering

More information

Non-Current Asset Policies Tools

Non-Current Asset Policies Tools Non-Current Asset Policies Tools >> Sample Valuation Letters The following are two sample letters to independent valuers (or other relevant professionals) in respect of obtaining fair values for non-current

More information

FUTURE INDUSTRIES FUND SECTOR GROWTH PROGRAM. Program Guidelines. Victoria s Future Industries.

FUTURE INDUSTRIES FUND SECTOR GROWTH PROGRAM. Program Guidelines. Victoria s Future Industries. FUTURE INDUSTRIES FUND SECTOR GROWTH PROGRAM Program Guidelines Victoria s Future Industries. CONTENTS 1. Background 4 1.1 Future Industries Fund 4 2. Program Objective 5 2.1 Program overview 5 2.2 Stream

More information

Gosport Borough Council. Procurement Strategy. Pursuit of Excellence

Gosport Borough Council. Procurement Strategy. Pursuit of Excellence Gosport Borough Council Procurement Strategy Delivering for Gosport Pursuit of Excellence Contents Page 1 Introduction to Gosport Borough Council s 2 Procurement Strategy 2 Strategic framework 3 3 Procurement

More information

Project Management Competency Standards

Project Management Competency Standards BSB01 Business Services Training Package Project Management Competency Standards CONTENTS BSBPM401A Apply scope management techniques...3 BSBPM402A Apply time management techniques...8 BSBPM403A Apply

More information

Module 7: Change Management

Module 7: Change Management Module 7: Change Module 7: Change Integrating Project with Change They think by installing this system they will end my services let us see if they will ever manage to get it done What is the purpose of

More information

Government of Western Australia Department of Finance Government Procurement. Gateway. Tender Decision Workbook

Government of Western Australia Department of Finance Government Procurement. Gateway. Tender Decision Workbook Government of Western Australia Department of Finance Government Procurement Gateway Tender Decision Workbook ABOUT THIS WORKBOOK This workbook supports the Gateway review Tender Decision. It is the fourth

More information

Best practice guide for Councils when initially dealing with NBN Co. June 2011

Best practice guide for Councils when initially dealing with NBN Co. June 2011 Best practice guide for Councils when initially dealing with NBN Co June 2011 Table of contents Local Government Guide... 2 Introduction Preparation... 4 Consider the development of a local digital economy

More information

If New Zealand is to thrive, transport is vital for connected communities, and a growing economy.

If New Zealand is to thrive, transport is vital for connected communities, and a growing economy. Position description Title: Group: Location: Reports to: Position Status Maintenance Contract Manager HNO Regional Office (as applicable) Regional Performance Manager/Highway Manager Permanent Delegations

More information

Procurement Strategy and Contract Selection

Procurement Strategy and Contract Selection GUIDELINE Capital Works Management Framework Procurement Strategy and Contract Selection The suite of Capital Works Management Framework documents is available online www.hpw.qld.gov.au: The Capital Works

More information

Toronto Basement Flooding Protection Program

Toronto Basement Flooding Protection Program Toronto Basement Flooding Protection Program In August 2005, a storm exceeding a 1-in-100 year return frequency, hit the City of Toronto with over 150 mm of rainfall within a three hour period. While surface

More information

POSITION DESCRIPTION STRATEGIC PLANNING PROJECTS OFFICER

POSITION DESCRIPTION STRATEGIC PLANNING PROJECTS OFFICER POSITION DESCRIPTION STRATEGIC PLANNING PROJECTS OFFICER POSITION TITLE: Strategic Planning Projects Officer BAND: Negotiated DIRECTORATE: DEPARTMENT: Planning and Development Services WORK TYPE: Full

More information

Glenorchy City Council Asset Management Strategy for Infrastructure Assets

Glenorchy City Council Asset Management Strategy for Infrastructure Assets Glenorchy City Council Asset Strategy for Infrastructure Assets 2014/15 to 2017/18 Version 1.3 June 2014 Glenorchy City Council Asset Strategy for Infrastructure Assets Document Control Document Control

More information

City of Canning. Asset Management Strategy 2015 2018

City of Canning. Asset Management Strategy 2015 2018 City of Canning Asset Management Strategy 2015 2018 Document Control Version No Version Date Description TRIM Reference 1.0 11 December 2012 Asset Management Strategy D12/68776 2.0 23 September 2015 Updated

More information

Contract Management Guideline

Contract Management Guideline www.spb.sa.gov.au Contract Management Guideline Version 3.2 Date Issued January 2014 Review Date January 2014 Principal Contact State Procurement Board Telephone 8226 5001 Contents Overview... 3 Contract

More information

POSITION INFORMATION DOCUMENT

POSITION INFORMATION DOCUMENT POSITION INFORMATION DOCUMENT Position Title: Senior Manager, ICT Contracts Classification Code: ASO8 Division: ICT Services Directorate: ICT Contracts & Performance Management Type of Appointment: Branch:

More information

Construction (Design and Management) Regulations 2007

Construction (Design and Management) Regulations 2007 MEETING Finance, Procurement and Property Committee AGENDA ITEM 14 MEETING DATE 9 th July 2007 DOCUMENT NUMBER FEP 1052 SUBJECT REPORT Construction (Design and Management) Regulations 2007 (12/06/07) by

More information

Environment Committee 11 January 2016

Environment Committee 11 January 2016 Environment Committee 11 January 2016 Title Whole Life Costing of Footway Maintenance Treatments and Scheme Prioritisation Report of Wards Status Urgent Key Enclosures Commissioning Director, Environment

More information

CHANGE MANAGEMENT PLAN

CHANGE MANAGEMENT PLAN Appendix 10 Blaby District Council Housing Stock Transfer CHANGE MANAGEMENT PLAN 1 Change Management Plan Introduction As part of the decision making process to pursue transfer, the Blaby District Council

More information

Engineering Policy 146. Severe Weather Management Plans

Engineering Policy 146. Severe Weather Management Plans Engineering Policy 146 Severe Weather Management Plans January 2014 Contents Engineering Policy... 1 1 Policy statement... 1 2 Applicability... 1 3 Context... 1 4 Objectives and benefits... 1 5 Consultation...

More information

www.nams.au.com AN INNOVATIVE APPROACH TO LOCAL GOVERNMENT ROAD NETWORK MANAGEMENT

www.nams.au.com AN INNOVATIVE APPROACH TO LOCAL GOVERNMENT ROAD NETWORK MANAGEMENT AN INNOVATIVE APPROACH TO LOCAL GOVERNMENT ROAD NETWORK MANAGEMENT Peter Clewer: Asset Management Officer (Roads), Mornington Peninsula Shire Amy Wade, Manager Axim - A Downer EDI Works Business Abstract

More information

SCHEDULE A JOB DESCRIPTION

SCHEDULE A JOB DESCRIPTION SCHEDULE A JOB DESCRIPTION Job Title: Work Unit: Responsible To: Responsible For: Position Purpose: Financial Delegated Authority: Pay Range: Assets & Business Efficiency Coordinator Corporate and Governance

More information

4 Adoption of Asset Management Policy and Strategy

4 Adoption of Asset Management Policy and Strategy 4 Adoption of Asset Management Policy and Strategy Abstract The report recommends the adoption of an updated Asset Management Policy 2014 and an Asset Management Strategy 2014-2019. Both documents are

More information

Oadby and Wigston Borough Council PROCUREMENT STRATEGY

Oadby and Wigston Borough Council PROCUREMENT STRATEGY Oadby and Wigston Borough Council PROCUREMENT STRATEGY JUNE 2006 1 Contents Page(s) 1. Context...3 2. Oadby & Wigston s Vision for Procurement...3 3. Progress to Date...4 4. Procurement in the Organisation...4

More information

IT11 - Cloud Services for Off-Site Resilience

IT11 - Cloud Services for Off-Site Resilience UCD IT Services IT11 - Cloud Services for Off-Site Resilience Project Initiation Document Version 1.0 December 2 nd 2014 Version History Version Date Summary of Changes Changed by 1.0 02/12/2014 Initial

More information

SAFETY and HEALTH MANAGEMENT STANDARDS

SAFETY and HEALTH MANAGEMENT STANDARDS SAFETY and HEALTH STANDARDS The Verve Energy Occupational Safety and Health Management Standards have been designed to: Meet the Recognised Industry Practices & Standards and AS/NZS 4801 Table of Contents

More information

Outsourcing. Knowledge Summary

Outsourcing. Knowledge Summary Knowledge Summary Outsourcing P&SM professionals should have the knowledge and skills required to manage the outsourcing process and to advise colleagues of the most appropriate solution to obtain best

More information

Page 97. Executive Head of Asset Planning, Management and Capital Delivery

Page 97. Executive Head of Asset Planning, Management and Capital Delivery Page 97 Agenda Item 7 Report to: Strategy and Resources Committee Date: 16 December 2013 Report of: Executive Head of Asset Planning, Management and Capital Delivery Ward Location: Not applicable Author

More information

The FIDIC Suite of Contracts

The FIDIC Suite of Contracts Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October

More information

Asset Management Strategy

Asset Management Strategy Asset Management Strategy File Ref: CM.STD.6 Synergy Ref: NMP1331737 Version: 25/06/2013 City of Albany 2013 102 North Road, Yakamia WA 6330 PO Box 484, ALBANY WA 6331 Tel: (08) 9841 9333 Fax: (08) 9841

More information

City Deal Procurement Strategy to 2020

City Deal Procurement Strategy to 2020 City Deal Procurement Strategy 2015 to 2020 Contents Foreword Summary of City Deal 1. Background 2. Strategic Objectives 2.1 City Deal Governance 2.2 Working in Partnership 2.3 City Deal A Unified Approach

More information

Contract Management Checklist. Preparation

Contract Management Checklist. Preparation Contract Management Checklist Preparation This section deals with laying good foundations before a contract is let. The contract should be actively managed. You should have a plan for doing this, which

More information

One Government Contract Management Framework. September 2014

One Government Contract Management Framework. September 2014 One Government Contract Framework September 2014 One Government Contract Framework Table of contents 1 Introduction... 4 2 Purpose... 4 3 Scope... 5 3.1 Contract management planning starts before a contract

More information

Queensland Reconstruction Authority. 2010/11 Queensland flood and cyclone disaster. Value for Money Strategy

Queensland Reconstruction Authority. 2010/11 Queensland flood and cyclone disaster. Value for Money Strategy Queensland Reconstruction Authority 2010/11 Queensland flood and cyclone disaster EXECUTIVE SUMMARY The Queensland Reconstruction Authority (the Authority) has been established as a statutory authority

More information

Manchester City Council Report for Resolution. Report to: Personnel Committee 16 November Deputy Chief Executive (Growth and Neighbourhoods)

Manchester City Council Report for Resolution. Report to: Personnel Committee 16 November Deputy Chief Executive (Growth and Neighbourhoods) Manchester City Council Report for Resolution Report to: Personnel Committee 16 November 2016 Subject: Report of: Project Director Our Town Hall Deputy Chief Executive (Growth and Neighbourhoods) Summary

More information

An appropriate degree in Environmental Science or Environmental Engineering or equivalent.

An appropriate degree in Environmental Science or Environmental Engineering or equivalent. SECTION A: GENERAL INFORMATION Title: Senior Environmental Project Manager Division: Minerals & Energy Resources Branch: Mining Regulation & Rehabilitation Section: Mine Completion Occupant: HRMS record

More information

Contents. Introduction Page 3. Section 1 Strategic Aim Page 4. Section 2 Professionally Resourced Page 5

Contents. Introduction Page 3. Section 1 Strategic Aim Page 4. Section 2 Professionally Resourced Page 5 Contents Introduction Page 3 Section 1 Strategic Aim Page 4 Section 2 Professionally Resourced Page 5 Section 3 Economic, Social and Environmental Impact Page 6 Section 4 Community Benefits Page 7 Section

More information

Contract Management. Brief 22. Public Procurement. September 2011

Contract Management. Brief 22. Public Procurement. September 2011 Brief 22 September 2011 Public Procurement Contract Management C O N T E N T S The process of contract management Contract management in practice Post contract performance review www.sigmaweb.org This

More information

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document

More information

Road Assets & Expenditure

Road Assets & Expenditure Report on Local Government Road Assets & Expenditure 2014/15 walga.asn.au Report on Local Government Road Assets & Expenditure 2014/15 Acknowledgements A special note of appreciation is extended to Clive

More information

Draft Business Case 2017/18. Staff Travel. Proposal Details

Draft Business Case 2017/18. Staff Travel. Proposal Details Proposal Details Proposal Name: Portfolio: Senior Responsible Officer: Proposal Lead: Reform and Governance Laureen Donnan Sue Williams 1. Summary and Rationale The council recognises the need for some

More information

Finance Sub Committee 24 June Splash Leisure Pool

Finance Sub Committee 24 June Splash Leisure Pool Agenda Item 11 Finance Sub Committee 24 June 2013 Splash Leisure Pool Purpose of report: To consider the future of Splash Leisure Pool. It should be noted by councillors that future costs referred to in

More information

READING BOROUGH COUNCIL HEAD OF FINANCE DATE: 8 JULY 2015 AGENDA ITEM: 5 AUDIT & INVESTIGATIONS QUARTERLY PROGRESS REPORT

READING BOROUGH COUNCIL HEAD OF FINANCE DATE: 8 JULY 2015 AGENDA ITEM: 5 AUDIT & INVESTIGATIONS QUARTERLY PROGRESS REPORT READING BOROUGH COUNCIL HEAD OF FINANCE TO: AUDIT & GOVERNANCE COMMITTEE DATE: 8 JULY 2015 AGENDA ITEM: 5 TITLE: AUDIT & INVESTIGATIONS QUARTERLY PROGRESS REPORT LEAD COUNCILLOR: COUNCILLOR STEVENS PORTFOLIO:

More information

Department of Planning, Transport and Infrastructure JOB AND PERSON SPECIFICATION

Department of Planning, Transport and Infrastructure JOB AND PERSON SPECIFICATION Department of Planning, Transport and Infrastructure JOB AND PERSON SPECIFICATION Title of Position: Senior Project Manager Directorate: Public Transport Services Classification Code: ASO7 Branch/Section:

More information

Brentwood Borough Council

Brentwood Borough Council Brentwood Borough Council Strategy March 2014 Page 1 of 11 Index 1. Foreword... 3 2. Introduction... 4 2.1 The Purpose of... 4 2.2 The Current Situation... 4 2.3 Our Vision for... 5 2.4 Our Definition

More information

ASSET MANAGEMENT STRATEGY

ASSET MANAGEMENT STRATEGY ASSET MANAGEMENT STRATEGY Adopted May 2011 Table of Contents Page 1. Introduction 3 2. Purpose 4 3. Asset Register System 4 4. Asset Management Working Group 4 5. Asset Management Plans 5 6. Condition

More information

Safety, Health, Environment and Quality Management. The Biffa Way

Safety, Health, Environment and Quality Management. The Biffa Way Safety, Health, Environment and Quality Management. The Biffa Way We will keep our people, our customers and the environment safe and take action if we see danger. Ian Wakelin Chief Executive 2 SHEQ Management

More information

POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT

POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT The intent of this policy is to establish a University-wide governance structure for managing contracts and other legally binding documents. The Policy

More information

Contract and Vendor Management Guide

Contract and Vendor Management Guide Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier

More information

Supplementary Agenda Monday 23 April 2012 Council Chambers 126-138 Main Road Speers Point 7.00pm

Supplementary Agenda Monday 23 April 2012 Council Chambers 126-138 Main Road Speers Point 7.00pm Supplementary Agenda Monday Council Chambers 126-138 Main Road Speers Point 7.00pm Matters Referred: Extension of CMS software Brian Bell General Manager Note: Council Meeting Agendas will be available

More information

ISLINGTON & SHOREDITCH HOUSING ASSOCIATION JOB DESCRIPTION. Operations. Operations Director

ISLINGTON & SHOREDITCH HOUSING ASSOCIATION JOB DESCRIPTION. Operations. Operations Director ISLINGTON & SHOREDITCH HOUSING ASSOCIATION JOB DESCRIPTION Title of Post Section/department To whom immediately responsible For whom immediately responsible Job Purpose Partnering Contacts Manager Operations

More information

Procurement Strategy The City Council s Procurement Strategy for the period

Procurement Strategy The City Council s Procurement Strategy for the period Procurement Strategy The City Council s Procurement Strategy for the period 2014-2016 1 Name Content Creator Darren Pearce, Strategic Manager Corporate Procurement, Stoke-on-Trent City Council darren.pearce@stoke.gov.uk

More information

Logan City Council. Strategic Planning and Performance Management Framework

Logan City Council. Strategic Planning and Performance Management Framework Logan City Council Strategic Planning and Performance Management Framework 1 Table of contents 1. Overview 3 a) Purpose 3 b) Key Features 3 2. Context 4 a) National Framework for Sustainability 4 b) Elements

More information

Contract Tender for Library Management System

Contract Tender for Library Management System Contract Tender for Library Management System AGENDA NO: Cabinet Date 4 th July 2012 Leader of the Council Key Decision Background Documents Location/Contact for inspection of Background Documents Main

More information

Risk & Opportunity Management Framework

Risk & Opportunity Management Framework Risk & Opportunity Management Framework January 2010 Version 1.0 Table of Contents 1 Preface... 14 1.1 Risk and Opportunity Management What is it?... 14 1.2 Purpose... 15 2 Risk Management Process... 15

More information

10.0 ASSET MANAGEMENT PRACTICES

10.0 ASSET MANAGEMENT PRACTICES 10.0 ASSET MANAGEMENT PRACTICES 10.1 Current Asset Management Practices This section outlines the decision making tools Taupō District Council (TDC) currently uses to determine long term maintenance, renewal

More information

RIIO T1 Business Plan Update. Delivery and Costs. December 2011

RIIO T1 Business Plan Update. Delivery and Costs. December 2011 NEW DOCUMENT RIIO T1 Business Plan Update December 2011 Ref: SPT_Upd_3 DELIVERY AND COSTS Following our business plan in July, Ofgem requested some further clarification on the following topics. This paper

More information

Project Management Framework

Project Management Framework Information Services Project Management Framework October 2003 Document ID No. Page 1 of 1 Contents 1. Introduction Page 3 2. Use of Framework Page 3 3. Project Register and Monitoring Page 4 4. Project

More information

FINDINGS AND RECOMMENDATIONS OF THE SURVEY OF ENGINEERING ENTERPRISE LEADERS GROUP ENERGY EFFICIENCY AND GREENHOUSE GAS REDUCTIONS

FINDINGS AND RECOMMENDATIONS OF THE SURVEY OF ENGINEERING ENTERPRISE LEADERS GROUP ENERGY EFFICIENCY AND GREENHOUSE GAS REDUCTIONS FINDINGS AND RECOMMENDATIONS OF THE SURVEY OF ENGINEERING ENTERPRISE LEADERS GROUP ENERGY EFFICIENCY AND GREENHOUSE GAS REDUCTIONS Contact: Lynne Reeder Senior Policy Analyst ph: 02 62706581 email: Lynne_Reeder@ieaust.org.au

More information

NZQA registered unit standard 25872 version 2 Page 1 of 5. Develop and implement a project plan to deliver on an Infrastructure works contract

NZQA registered unit standard 25872 version 2 Page 1 of 5. Develop and implement a project plan to deliver on an Infrastructure works contract Page 1 of 5 Title Develop and implement a project plan to deliver on an Infrastructure works contract Level 5 Credits 15 Purpose People credited with this unit standard are able to: explain relationship

More information

Procurement work plan - Mid-year update & progress report

Procurement work plan - Mid-year update & progress report Agenda Item Executive Leader (Advisory Panel). 2 December 2002 Report of the Director of Resources & Head of Financial Services Procurement work plan - Mid-year update & progress report Purpose 1 The purpose

More information

Indigenous Employment Evaluation Tool. The Centre for Social Responsibility in Mining. csrm

Indigenous Employment Evaluation Tool. The Centre for Social Responsibility in Mining. csrm Indigenous Employment Evaluation Tool The Centre for Social Responsibility in Mining csrm Introduction The Indigenous Employment evaluation (IEE) Tool is a reporting framework that has been developed as

More information