1 WATER-POWERED DRILLING INSIDE STOCKHOLM S CENTRAL STATION FOUNDATION REINFORCEMENT PROJECT Water-Powered Drilling inside Stockholm s Central station LKAB Wassara, All rights reserved.
2 WATER-POWERED DRILLING INSIDE STOCKHOLM S CENTRAL STATION LKAB Wassara AB, Stockholm, Sweden (Photo courtesy of Jernhusen) The Stockholm Central station has been sinking 1 mm per year and needed reinforcement of the foundation. This was done by drilling and setting casing all the way down to the bedrock. Niches were cut out from the side of the existing foundation walls, big enough to allow access for a small drill rig. Wassaras water-powered DTH hammer was prescribed for the project as the environment was sensitive in several ways. STOCKHOLM CENTRAL WAS A SINKING STATION The Central station in Stockholm is the very central point in the Swedish railway system. 80% of all domestic journeys by train starts or ends here. An average of commuters pass here every day. The station was completed in 1871, with some parts built on what used to be a lake. Before building the station, parts of the lake was filled with sand, gravel and boulders. Numerous oak pillars serves as foundation, but later on it became clear that the pillars don t reach the bedrock. Measurements indicated that the main station building was sinking more than 1 mm per year. FOUNDATION REINFORCEMENT The landlord Jernhusen hired the construction and project management company Forsenprojekt for the reinforcement project. The contractor Lemminkäinen was awarded the contract for the later part of the foundation works. This part of the project included the installation of 428 steel piles, placed every second meter in the foundation wall and down into the bedrock. The sensitive environment demanded as benign drilling as possible. No noisy machinery or dust in the air was allowed. Any vibrations must be kept at a minimum. The water-powered drilling with Wassara is the only percussion drilling technology that meets these demands. A PROJECT WITH MANY PARTICULAR DEMANDS As parts of the building are listed as a National Heritage, strict national laws applies; the building must not be damaged. The available workspace for the operation was quite cramped, due to bulky foundation walls. To further complicate the works, multiple parallel construction projects were running at the same time. As the public area was in full operation, some commuters were passing very close to the drill site every day. This pushed the environmental aspects with low noise even further. It also made the moving of drill rigs and other machinery limited to off-peak hours. DRILLING INSIDE THE FOUNDATION WALLS Niches were cut out from the side of the foundation walls, big enough to allow access for a small drill rig. The drilling and casing advancing was done all the way down to the bedrock, an average of 16 meters. LKAB Wassara AB info.wassara@lkab.com (5)
3 Water-Powered Drilling inside Stockholm s Central station The formation was full of oak logs that had to be drilled through. After the casing was set, arrangements were made in the walls to enable the support of the new pillars. This was repeated every second meter of the wall. CREATING NEW SPACE The Central station s lower hall accommodates several stores and small shops. In order to create more space, the number of the rather bulky foundation walls needed to be minimized in this area. Some m 2 of new area has been created in the lower hall. This was achieved by excavation of new areas and lowering of the floor level, as well as replacing bulky walls with supporting steel pillars. PLEASED CONTRACTOR Oskar Nilsson at Lemminkäinen was Site Manager during the reinforcement project. - The drilling went as planned, he says. When drilling indoors, we arranged for the return water to be collected and pumped away. The oak logs didn t cause too much of a problem. Our biggest challenge was the logistics; working so close to the commuters that walked by every day as it demanded special arrangements for our machinery and hoses. Drilling and casing advancing inside a niche PROJECT TIME January 2010 March 2013 Equipment used DTH hammer Wassara W80 Wassara W100 Wassara W120 The new pillars (in the bottom) are now supporting the foundation. The niche is ready to be closed and filled with concrete. Drilled RD-piles Wassara W150 Ruukki RD90, RD 115, RD140, RD170 & RD220 The W80 hammer Rig Geomachine Kelpo S Pump Drilling fluid Lemminkäinen HP500/180 Clean water The W100 hammer Drill pipe 76, 89, 102 and 140 mm Borehole length Scope of drilling Geologic formation meters meters Sand, gravel and boulders, together with oak logs The W120 hammer The W150 hammer LKAB Wassara AB info.wassara@lkab.com (5)
4 Water-Powered Drilling inside Stockholm s Central station RIG ON THE MOVE The moving of the rig was often limited to off-peak hours when working close to public areas. SETTING UP FOR THE NEXT BOREHOLE Aligning for the next casing, indoors under the Central Station. The tight spaces made the alignment of the drill rig complicated. DRILLING IN CRAMPED WORKSPACES The drilling went as planned, despite the cramped workspace in the niches. The welding of the casing pipes presented another challenge. THE WALLS As the foundation with oak pillars don t reach the bedrock, the walls were sinking 1 mm per year. (Illustration courtesy of Lemminkäinen) REINFORCEMENT WORKS The drilling and casing advancing was done all the way down to the bedrock, up to 24 meters. (Illustration courtesy of Lemminkäinen) MANAGING THE WATER The incoming water came from municipality sources. Arrangements were made for the return water to be collected and pumped away. LKAB Wassara AB info.wassara@lkab.com (5)
5 WASSARA COST-EFFICIENT AND ENVIRONMENTALLY FRIENDLY DRILLING LKAB Wassara is a Swedish company developing and manufacturing unique waterpowered drilling systems for high performance in surface- as well as underground drilling operations. The heart of the Wassara drilling system is the world patented water-powered down-the-hole hammer. The drilling systems have been used for more than 20 years in various applications within many industries; mining, exploration, ground engineering, dams, geothermal, marine, oil & gas storage. Our experience covers more than 25 million drilled metres working in different locations around the world. Reference studies can be found on our website. LKAB Wassara was founded in 1988 and is owned by LKAB. LKAB is an international high-tech minerals group that produces iron ore products for the steel industry and other mineral products for many other industries and applications. Explore more at LKAB Wassara AB info.wassara@lkab.com
SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS
SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located
More informationSPEEDROC D30. Surface Drill Rig for marble, granite, sandstone and limestone in the dimension stone industry.
SPEEDROC D0 Surface Drill Rig for marble, granite, sandstone and limestone in the dimension stone industry. SPEED UP YOUR PROFITS SPEEDROC D0 IS A VERSATILE AND FLEXIBLE DRILL RIG, TAILORMADE FOR THE DIMENSION
More information2013 WJTA-IMCA Conference and Expo September 9-11, 2013 Houston, Texas Paper REFRACTORY REMOVAL BY HIGH PRESSURE WATERJET
2013 WJTA-IMCA Conference and Expo September 9-11, 2013 Houston, Texas Paper REFRACTORY REMOVAL BY HIGH PRESSURE WATERJET D. Wright StoneAge, Inc. Durango, Colorado, U.S.A. ABSTRACT The removal of refractory
More informationources of Drinking Water
The drop on water Sources of Drinking Water Did you know that 40 per cent of Nova Scotians get their water privately from a drilled well, a dug well, or a surface water source? The other 60 per cent rely
More informationWhitepaper. Modular Substation Cable Termination Design. Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada
Whitepaper Modular Substation Cable Termination Design Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada Abstract The methods for cable penetrations into modular industrial substations are
More informationAtlas Copco Surface drill rigs. SmartROC T35/ T40. Hole diameter: SmartROC T35: 64 115 mm (2 1 /2 4 1 /2 ) SmartROC T40: 76 127 mm (3 5 )
Atlas Copco Surface drill rigs SmartROC T35/ T40 Hole diameter: SmartROC T35: 64 115 mm (2 1 /2 4 1 /2 ) SmartROC T40: 76 127 mm (3 5 ) When smart means easy and efficient Main benefits Combines low fuel
More informationBUTE Department of Construction Management and Technology
BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):
More informationSample Career Ladder/Lattice for Energy (Petroleum Sector)
Click on a job title to see examples of descriptive information about the job. Click on a link between job titles to see the critical development experiences needed to move to that job on the pathway.
More informationSupplier ID: 26421. Local Office: GLASGOW 69 Buchanan Street Glasgow G1 3HL
M D & FOUNDATIONS MIDLANDS Supplier ID: 26421 MINI PILING PILING REINFORCED CONCRETE UNDERPINNING DRILLING & GROUTING SITE INVESTIGATION & PILE TESTING NATIONWIDE SPECIALIST PILING & FOUNDATION SERVICES
More informationHow will the construction of the City Line affect you? English
English How will the construction of the City Line affect you? How the City Line will affect people living, working or using public transport in Stockholm. The City Line will be noticed! The City Line
More informationTHE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION
THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION GROUP 867 ARCHITECTURAL, ENGINEERING AND OTHER TECHNICAL SERVICES Excerpt from CPCprov-en-Publication.doc - United Nation Statistic Division Group Class Subclass
More informationMember Nation Report 2010 from Denmark.
Member Nation Report 2010 from Denmark. The has during the year 2010 arranged 6 member meetings including two technical site visits. The first technical site visit covered the 5.3 km long Leipzig City
More informationDRILLING & FOUNDATION EQUIPMENT SAFETY INSTITUTION OF ENGINEERS AUSTRALIA MECHANICAL 21.11.2013
DRILLING & FOUNDATION EQUIPMENT SAFETY INSTITUTION OF ENGINEERS AUSTRALIA MECHANICAL 21.11.2013 1. EN 16228-1../7 & EN 791 & EN 996 2. STABILITY OF THE RIGS; 3. AUSTRALIAN STANDARDS AND REGULATION RELATED
More informationhs2 Ground A non-technical guide
hs2 Ground Investigations A non-technical guide Contents HS2 ground investigations 1 Essential Q&A 2 2 In-ground investigation techniques 9 2.1 Cable percussion borehole 10 2.2 Rotary core borehole 12
More informationExploration for natural gas
FACT SHEET NO. 42 Exploration for natural gas Quick facts QGC holds licences from the Queensland Government called Authorities to Prospect that allow us to explore in areas known as tenements We work with
More informationMicropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com
More informationThe Follo Line Project
The Follo Line Project Longest. UrbAN. Complex. Faster. 2015/1 Norwegian National Rail Administration the follo line project 1 2 the follo line project The project The Follo Line Project is currently the
More informationHYDRAULIC BREAKERS SB RANGE. A solid body, an innovative tool guiding system and a remarkable hydraulic design
HYDRAULIC BREAKERS SB RANGE A solid body, an innovative tool guiding system and a remarkable hydraulic design Solid productivity you can rely on! We introduced the innovative hydraulic breaker 50 years
More information2010-2011 Contractor of the Year
U.S. Army Corps of Engineers: Little Calumet River Stage VII Steel Sheet Piling Installation Hammond, Indiana Thatcher worked two rigs concurrently one on the north side and one on the south. The United
More informationWorkplace Incident Fatalities Accepted by the Workers Compensation Board in 2014
Workplace Incident Fatalities Accepted by the Workers Compensation Board in 2014 Workplace Incident Fatalities Year to date, numbers as of December 31, 2014 Workplace Incident fatalities are cases where
More informationQUESTIONNAIRE AND PROPOSAL FOR CONTRACTORS ALL RISK INSURANCE
GA Insurance House, Ralph Bunche Road, P O Box 42166-00100 Nairobi, Kenya. Telephone: 2711633 Fax 2714542 E-mail: insure@gakenya.com QUESTIONNAIRE AND PROPOSAL FOR CONTRACTORS ALL RISK INSURANCE AGENT:
More informationTypes of Mining - Expert Table
See page 6 Minerals Downunder Teacher Guide (2002) - Activity 4a Types of Mining - Expert Table How to Jigsaw Information 1. Divide the class into Home Groups of five for the five different types of mining
More informationSUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
More informationElectricity to your property
Vattenfall Distribution AB Electricity to your property How an electrical connection is made and what you need to consider How electricity reaches your property 8 simple steps! 1. Please leave plenty of
More informationMoving Small Mountains Vesuvius Dam Rehab
Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,
More informationUNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA
UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA John R. Wolosick, P.E.,D.GE 1, Michael W. Terry, P.E. 2, W. David Kirschner 3 and Robert F. Scott Jr. P.E. 4 SYNOPSIS In
More informationUse of Fly ash from KKAB, for sealing of landfills
Use of Fly ash from KKAB, for sealing of landfills Kristina Hargelius M.Sc. Civ. Eng. Kristina.hargelius@ramboll.se Abstract The paper must include an abstract, which should be no more than and 150 words.
More informationINSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!
In-situ Testing! Insitu Testing! Insitu testing is used for two reasons:! To allow the determination of shear strength or penetration resistance or permeability of soils that would be difficult or impossible
More informationCapital Project Management and Construction
Capital Project Management and Construction Project Management is Tough: Most project managers are just thrust into the roles. College engineering programs don t cover practical construction. Project management
More informationAtlas Copco at Fresnillo
UNDERGROUND DRILLING 41 Atlas Copco s Simba M4 C drill rig is used at the Fresnillo mine in Mexico Ace in the hole Ailbhe Goodbody looks at the use of in-the-hole drilling in the underground mining industry,
More informationAll Products Brochure
All Products Brochure Rental Pioneer Pump design and build the largest range of dry prime portable pumps in the world. With over forty models of high flow and high pressure pumps, the company has a pump
More informationCIRCULAR 2009. ircular PLANNING SERIES
5 HIERARCHY CIRCULAR 2009 OF DEVELOPMENTS ircular PLANNING SERIES Scottish Planning Series CIRCULAR 5 2009 Hierarchy of Developments July 2009 Crown copyright 2009 ISSN 0141-514X ISBN 978 0 7559 7572 3
More informationA History and Overview of the Barnett Shale
A History and Overview of the Barnett Shale Drilling The Dale Operating / Fourth Street 'A' Gas Unit #1H, East Downtown Fort Worth, Texas October, 2006, Courtesy of Dale Operating, Photo by Mike Fuentes
More informationMORE CARE. BUILT IN. VOLVO EXCAVATOR. hydraulic hammers
MORE CARE. BUILT IN. VOLVO EXCAVATOR hydraulic hammers For extra-tough conditions, Volvo hammers deliver high impact Stubborn rock. Concrete debris. Frost-locked earth. These are the kinds of conditions
More informationSTRADA ENERGY INTERNATIONAL LIMITED INVESTOR PRESENTATION
STRADA ENERGY INTERNATIONAL LIMITED INVESTOR PRESENTATION JANUARY 2016 THE COMPANY Privately owned Geothermal Energy Company Headquartered in Jersey, Channel Islands, with global operations Highly experienced
More informationInnovative solution for heat recovery of ventilation air in older apartment buildings - with low intervention affecting the residents
Innovative solution for heat recovery of ventilation air in older apartment buildings - with low intervention affecting the residents Innovative solution for heat recovery of ventilation air in older apartment
More informationCITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES
CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention
More informationEXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS
NMP 1.4 EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS Index Purpose... 2 Application... 2 Referral Agency... 2 Associated Requirements... 2 Referenced Standards...2 Definitions...
More informationWhat is water main cleaning & lining
What is water main cleaning & lining The Borough s water distribution system includes cast iron pipe. The program involves cleaning older section of cast iron pipe and lining it with cement mortar. Over
More informationTRENCHLESS TECHNOLOGY RESOURCE CENTRE TRENCHLESS TECHNOLOGY GUIDELINES
TRENCHLESS TECHNOLOGY RESOURCE CENTRE TRENCHLESS TECHNOLOGY GUIDELINES SECOND EDITION PIPEJACKING AND MICROTUNNELING NEW VERSION AUGUST 2005 1 OVERVIEW Pipe jacking and microtunnelling, including pilot
More informationSöderströmtunnel: immersion in downtown Stockholm, Sweden
Söderströmtunnel: immersion in downtown Stockholm, Sweden J. Glückert Dipl.-Ing, Züblin Ground Engineering, Stuttgart, Germany N.H.J. Vink MSe, M. Reijm BSc, P.T. van Westendorp BSc Strukton Immersion
More informationBOREHOLE SEALING IN A COAXIAL HEAT EXCHANGER BY BENTONITE TREATMENT
BOREHOLE SEALING IN A COAXIAL HEAT EXCHANGER BY BENTONITE TREATMENT Frank.B.Cruickshanks, Olof Andersson, James Bardsley Climate Change Division, Meteorological Service of Canada, 45 Alderney Drive, Dartmouth,
More informationSelim BORA President www.summa.com.tr
ENERGY INVESTMENTS Summa was founded in 1989, in Ankara, Turkey by its honorary President Mr. Mete Bora in order to work as an international construction company. Summa, which is working in international
More informationMILWAUKEE CITY HALL FOUNDATION RESTORATION. Project Update November 12, 2014
MILWAUKEE CITY HALL FOUNDATION RESTORATION Project Update November 12, 2014 Milwaukee City Hall Building History/Fast Facts - City Hall is a masonry and iron superstructure - Originally constructed from
More informationHow a Ground Source Heat Pump Works for a School or College
How a Ground Source Heat Pump Works for a School or College Vertical System Image courtesy of Climate Master 1 Geothermal avoids the need for outdoor equipment..reducing vandalism and liability Image courtesy
More informationGrounding and Bonding Against Static Electricity. Jon Koppari, CSP, MS Occupational Safety and Health Instructor OSHA Training Institute
Grounding and Bonding Against Static Electricity Jon Koppari, CSP, MS Occupational Safety and Health Instructor OSHA Training Institute Objectives Identify Sources of Ignition. Identify Hazards associated
More informationAXIS system used to install gravity flow sewer Laser-guided boring technology capable of pinpoint, on-grade accuracy
AXIS system used to install gravity flow sewer Laser-guided boring technology capable of pinpoint, on-grade accuracy The City of Kitchener, Ontario, Canada, was in a dilemma. After repeated breakdowns
More informationC-2 Construction, Inc. - NAICS Codes
C-2 Construction, Inc. - NAICS Codes 212313 - Crushed and Broken Granite Mining and Quarrying This U.S. industry comprises: (1) establishments primarily engaged in developing the mine site, and/or mining
More informationZhao et al. 2.2 Experimental Results in Winter Season The analysis given below was based on the data collected from Nov. 2003 to Mar. 15, 2004.
Proceedings World Geothermal Congress 2005 Antalya, Turkey, 24-29 April 2005 A Case Study of Ground Source Heat Pump System in China Jun Zhao, Chuanshan Dai, Xinguo Li, Qiang Zhu and Lixin Li College of
More informationChallenges and Opportunities for Small Businesses Engaged in Energy Development and Energy Intensive Manufacturing
Statement of Toby Mack, EEIA President, Before the U.S Senate Committee on Small Business and Entrepreneurship July 14, 2015 Challenges and Opportunities for Small Businesses Engaged in Energy Development
More informationMechanical Systems Proposal revised
Mechanical Systems Proposal revised Prepared for: Dr. William Bahnfleth, Professor The Pennsylvania State University, Department of Architectural Engineering Prepared by: Chris Nicolais Mechanical Option
More informationSECTION 02401 SHEETING, SHORING AND BRACING
SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State
More informationDrainage. Information for those with problem drains
Drainage Information for those with problem drains Contents 1 Purpose 2 Introduction 2 Explanations: what is a drain and what is a sewer 3 Explanation of the responsibilities for public and private sewers
More informationBRIDGES ARE relatively expensive but often are
Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the
More informationFederation of Piling Specialists July 2010
Examples of Hazards associated with Piling and Diaphragm Walling Works and how these might be managed within the design phase of a project (neither exhaustive nor exclusive) This list of examples has been
More informationBreaking new ground in subsea excavation and trenching. www.agr.com
Breaking new ground in subsea excavation and trenching. www.agr.com and the people to make it happen AGR Subsea has a wealth of experience in solving subsea challenges, from rock removal to BOP recovery,
More informationManaging the Island s Water Resources Planning for the future
Managing the Island s Water Resources Planning for the future www.jerseywater.je Executive summary The Water Resources Management Plan identifies the effects of climate change and population, on the water
More informationRainwater Harvesting
Rainwater Harvesting With climate change now a reality rather than a speculated possibility, the demand on water resources has gone up, whilst the amount of water available for supply has gone down. Forth
More informationSPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN
SPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN XXXX FARM (CITY OR COUNTY), MICHIGAN CONTACT (NAME), OWNER CERTIFICATION: I hereby certify that I have examined the facility, and being familiar with the
More informationRULES AND REGULATIONS CONTRACTOR WORK
RULES AND REGULATIONS CONTRACTOR WORK CARILLON 227 West Trade Street Suite 330 Charlotte, NC 28202 The following Rules and Regulations shall govern the operation of contractor work in the Building. For
More informationADVANTAGES OF USING THE HYBRID GEOTHERMAL OPTION
ADVANTAGES OF USING THE HYBRID GEOTHERMAL OPTION J. B. Singh, PE* Gustav Foster, Jr. PE** *J and P Engineers, P.A. 14 Kory Drive Kendall Park, NJ 08824 USA phone: 732-940-7994 fax: 732-940-5528 **Conectiv
More informationAging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over
ewer utility crossing pedestrian bridge Aging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over the river at
More informationPRELIMINARY REPORT ON THE NORTHSTAR #1 CLASS II INJECTION WELL AND THE SEISMIC EVENTS IN THE YOUNGSTOWN, OHIO AREA
PRELIMINARY REPORT ON THE NORTHSTAR #1 CLASS II INJECTION WELL AND THE SEISMIC EVENTS IN THE YOUNGSTOWN, OHIO AREA Tom Tomastik, Geologist, ODNR, Division of Oil and Gas Resources Management PURPOSE AND
More informationFY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
More informationNW Natural & Pipeline Safety
NW Natural & Pipeline Safety We Grew Up Here NW Natural is an Oregon-based utility company founded in 1859. The company purchases natural gas for its core market in western Oregon and southwestern Washington,
More informationHow a Ground Source Heat Pump Works for Commercial Buildings
How a Ground Source Heat Pump Works for Commercial Buildings 1 Geothermal avoids the need for outdoor equipment..reducing vandalism and liability Image courtesy of Climate Master 2 Why geothermal heat
More informationCardok Sàrl CP37 CH-1295 Tannay Switzerland Phone: 0041 22 77 66 051 info@cardok.com
CARDOK CARLIFT Fast access to underground garages Fast, Silent, Discreet, Design, High-Tech Installation to replace an access ramp on private property Dimensions: (Built to measure, all dimensions can
More informationQuick fix for frost heave:
Quick fix for frost heave: HELICAL PILES Megan Milbradt Civil Engineer Basin Electric Power Shane Vasbinder Civil Engineer Basin Electric Power Concrete piers were 6 inches to 2 feet out of the ground.
More informationPLANNING CAREFUL NORTH VANCOUVER PIPE BURST REQUIRES
WATER & SEWER REHAB TECHNOLOGIES NORTH VANCOUVER PIPE BURST REQUIRES CAREFUL PLANNING Close proximity to storage silos, poor ground conditions and clogged storm sewer pipe puts trenchless contractor to
More informationCompressors Buying Guide
Compressors Buying Guide Below is a copy of a booklet which will help you make a compressor purchase! Included is information on... Horse Power (HP) Pressure (PSI) Cubic Feet Per Minute (CFM) Tank Sizes
More informationSASTT contact details:
SASTT contact details: Web: www.sastt.org.za President: Andries Lötz Tel: (011) 688 1483 Fax: (011) 688 1524 E-mail: alotz@jwater.co.za Honorary director: Joop van Wamelen Tel: (012) 567 4026 Fax: 086
More informationGLOSSARY OF TERMINOLOGY
GLOSSARY OF TERMINOLOGY AUTHORIZED PILE LENGTHS - (a.k.a. Authorized Pile Lengths letter) Official letter stating Engineer's recommended length of concrete piles to be cast for construction of foundation.
More informationThe Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
More informationA Guide to Asbestos in your Home
A Guide to Asbestos in your Home IL25 A Guide to Asbestos in your Home A Guide to Asbestos in your home South Derbyshire District Council Housing Services Civic Offices, Civic Way, Swadlincote, Derbyshire
More informationELECTRIC PERISTALTIC MORTAR POINTING PUMP
ELECTRIC PERISTALTIC MORTAR POINTING PUMP pointing gun & control valve ACF405 PERISTALTIC PuMP hopper feed roller & tube pump for refurbishment & repair trades heritage & conservation bridge & underground
More informationCompliance Guidance for Motor Vehicle Waste Disposal Wells in Oregon September 2015
Compliance Guidance for Motor Vehicle Waste Disposal Wells in Oregon September 2015 Underground Injection Control Program 700 NE Multnomah Street Suite 600 Portland, OR 97232 Phone: 503-229-6371 800-452-4011
More informationSWIMMING POOL, SPA, & HOT TUB GUIDELINES
SWIMMING POOL, SPA, & HOT TUB GUIDELINES Pool permit cost is based on the total value of the project. See Permit Fee Schedule Table 1A. A. Adopted construction codes and installation requirements 1. 2015
More informationRENEW. A Water Main Cleaning and Lining Program Designed to Improve Water Quality and Service
Investing in Our Infrastructure RENEW A Water Main Cleaning and Lining Program Designed to Improve Water Quality and Service 1500 Ronson Road P.O. Box 1500 Iselin, New Jersey 08830-3020 renew Hotline 800-549-3802
More informationTremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete
Tremie Concrete Underwater concrete plays an important role in the construction of offshore structures. It may be used to tie together various elements in composite action (i.e., to tie piling to the footing).
More informationITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT
ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load
More information50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance
02/15 Labko GRP cesspools Instructions for installation, operation and maintenance Reliable solutions Wastewater treatment systems Contents 1 LABKO CESSPOOLS... 3 1.1 GENERAL... 3 1.2 IMPORTANT TO KNOW
More informationBasements and Deep Building Construction Policy 2014
Basements and Deep Building Construction Policy 2014 APPROVAL Council / CEO 27 October 2014 VERSION NO: Version 1.0 TRIM REF: 14/67838 REVIEW 30/10/2019 RESPONSIBLE EXECUTIVE General Manager City Assets
More informationUse of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair
Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Eric M. Klein, P. E., Rummel, Klepper & Kahl, LLP, Baltimore, Maryland Kenneth B. Andromalos, P. E., Brayman Environmental,
More informationwww.the Floor Heating Warehouse.co.uk
www.the Floor Heating Warehouse.co.uk Underfloor Heating Installation Guide (Grundfoss Pump System) General Overview: Our water based underfloor heating system can be installed by your own plumber or heating
More informationPreventing water damage in the basement
Preventing water damage in the basement Thousands of home insurance claims are filed every year. Some losses are major, others aren t, but they re always an inconvenience and usually avoidable! As prevention
More informationoil care Looking after your heating oil in the south east
oil care Looking after your heating oil in the south east We are the Environment Agency. It s our job to look after your environment and make it a better place for you, and for future generations. Your
More informationBeacon Hill Sewer District Standard Specifications
Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions
More informationDave s Sheet Metal Bending Brake
Dave s Sheet Metal Bending Brake I started building a Zenith CH601XL from plans in mid January 2006. After several failed attempts to bend the rudder spar I ended up going to a local sheet metal shop for
More informationDeep geothermal FAQ s
What is geothermal energy? Deep geothermal FAQ s What is the deep geothermal resource in Cornwall? What are the benefits for Cornwall? What are Engineered/Enhanced Geothermal Systems (EGS) or Hot Dry Rocks?
More informationUp-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet
More informationEXPLAINING GROUNDWATER AND WATER WELLS
EXPLAINING GROUNDWATER AND WATER WELLS This document aims to provide a non-technical description of groundwater: how it occurs, how it moves underground, and the basic principles behind constructing and
More informationFinal thesis. Feasibility of Chinese offshore market. Hogeschool van Utrecht IHC HOLLAND. Supervisor: Mr R.kok
Final thesis Feasibility of Chinese offshore market Hogeschool van Utrecht IHC HOLLAND Supervisor: Mr R.kok Mediatheek HVU 1. INTRODUTION ABSTRACT 1.1 Company profile.........l 1.2 Thesis definition....
More informationFact sheet 6: for farmers
Fact sheet 6: for farmers Fuel Oil Storage February 2011 Are you planning to substantially alter your fuel oil store, or add a new one? If so, this fact sheet will help you meet the requirements of The
More informationThe Pipelines Regulations, 2000
PIPELINES, 2000 P-12.1 REG 1 1 The Pipelines Regulations, 2000 being Chapter P-12.1 Reg 1 (effective April 1, 2000) as amended by the Statutes of Saskatchewan, 2014, c.21. NOTE: This consolidation is not
More informationCAST IRON THE BASICS. Heatline - Cast Iron Radiators SMOOTH FLAT FILE TO REMOVE ANY SWARF. ONE TIME. ASSEMBLY. JOINTS SHOULD BE TIGHTENED.
CAST IRON THE BASICS 1. DO NOT LIFT ON YOUR OWN. 2. ONLY LIFT THE RADIATOR VERTICALLY. 3. DO NOT LIFT MORE THAN 8/10 SECTIONS AT ANY ONE TIME. 4. POSITION THE RADIATOR BEFORE FINAL ASSEMBLY. 5. THIS PRODUCT
More informationDelving into drains. Reprinted with permission from PROFESSIONAL ROOFING magazine. December 2012 by the National Roofing Contractors Association.
Delving into drains Reprinted with permission from PROFESSIONAL ROOFING magazine. December 2012 by the National Roofing Contractors Association. Installing retrofit roof drains can help you increase sales
More informationHOW TO REMOVE NONFRIABLE ASBESTOS (AC) WATER PIPE
HOW TO REMOVE NONFRIABLE ASBESTOS (AC) WATER PIPE A Guide for Meeting DEQ Rules Exposure to asbestos can result in severe health impacts and the Department of Environmental Quality (DEQ regulates the removal,
More informationrepairing leaks to your service pipe increasing water efficiency
repairing leaks to your service pipe increasing water efficiency nobody loves a leak A water leak on your property is a waste of a precious resource. If left running it may cause damage to your property
More informationForensic engineering of a bored pile wall
NGM 2016 Reykjavik Proceedings of the 17 th Nordic Geotechnical Meeting Challenges in Nordic Geotechnic 25 th 28 th of May Forensic engineering of a bored pile wall Willem Robert de Bruin Geovita AS, Norway,
More informationExploration. Exploration methods
Exploration Activities related to establishing a mineral deposit through geological, geophysical and geochemical methods. It is preceded by Prospecting and followed by Planning & Development. Geological
More information