Composite Floor Decks
|
|
|
- Leona Richardson
- 9 years ago
- Views:
Transcription
1 Precision Metal Forming Composite Floor Decks Steel Floor Decking Systems
2 PMF Floor Decking The most comprehensive range of steel floor decking systems available anywhere in the world. Shallow Composite Floor Decks Four different PMF profiles provide the optimum solution for short to medium unpropped or propped span conditions. In steel construction the composite floor profile is placed on the top flange of the beam. The steel section is generally designed to act compositely with the floor slab. Deep Composite Floor Decks PMF can offer two deep deck profiles that can span approximately six metres unpropped. The Deep Composite decks are generally used with Slimdek construction, which is used in conjunction with the Asymmetric Slimflor Beam (ASB). The composite floor deck is supported by the lower flange of the ASB, which is wider than the top flange. Formwork (non-composite) Five steel profiles which act as permanent formwork, i.e. they remain in situ for the life of the building but, unlike composite profiles, do not act as reinforcement in the concrete slab. The five profiles range in height from 32 mm to 100mm to offer the optimum solution to every design.
3 Introduction The benefits of PMF Composite Floor Decking Speed Large areas of deck can be rapidly craned into position and up to 400m 2 laid by one team per day. With minimal mesh reinforcement and pumped concrete, the completed floor can quickly follow. Working platform Once laid, the deck acts as a safe working platform for all following trades. Temporary props can usually be eliminated. Construction stage bracing The deck acts as lateral restraint to the beams and acts as a diaphragm, transmitting wind load from the outer steelwork to the core. Thus once the decking is fixed, it contributes significantly to the stability of the structure. Weight Due to the intrinsic efficiency of composite construction and the displacement of concrete by the profile shape, considerably less concrete is used than in conventional reinforced concrete construction. This reduces both the primary structure and foundations. Height Composite beams use the slab as a compression element, which increases their stiffness and reduces their size. The composite slab itself has a very low centre of reinforcement compared to a conventionally reinforced slab and therefore does not need the same depth. These savings translate to a reduced floor zone and thus overall floor height. Fire Extensive testing and fire engineering work by PMF and The Steel Construction Institute have resulted in fire ratings of up to 4 hours being available with the use of light mesh within the composite slab and no protection to the deck. Services PMF composite floor decks incorporate systems for the easy attachment of services, negating the requirement to fix into concrete. Composite Floor Decks 1
4 Introduction PMF deep composite floor decks. PMF Deep Composite Floor decks used in Slimdek construction offer all the benefits of shallow deck composite construction, with some significant additional benefits. Long span decks The deck will be designed to span 6m unpropped and up to 9m propped with corresponding reduction in steelwork. Shallow floor depth The deck is contained within the beam depth, which produces a slim floor. This leads to savings in cladding costs and either helps to reduce the overall building height or enables an extra floor to be added for buildings of 10 storys plus. Service integration The shape of the deep decks permits services to be installed between the deck ribs, effectively within the slab depth. This leads to further reductions in the floor zone. Inherent fire resistance A fire resistance of 60 minutes can be achieved without fire protection to the steelwork or deck. 2 Composite Floor Decks
5 Product Selector Product Selector Shallow Composite Floor Decks ComFlor 46 Cost effective ultra nestable profile. Typical unpropped span 3.0m Page 4 ComFlor 51 Traditional re-entrant profile. Typical unpropped span 3.0m 8 ComFlor 70 Optimum design, combined trapezoidal and re-entrant profile. Typical unpropped span 3.5m 12 ComFlor 100 For European style, longer span, non composite beam applications. Typical unpropped span 4.5m 16 Design Details Construction Details Installation Guidance Deep Composite Floor Decks ComFlor 210 Long span deck, can be used with Corus Slimdek system. Typical unpropped span 5.5m 32 SD 225 Longest span deck, used for Corus Slimdek applications. Typical unpropped span 6.0m 36 Design Details Construction Details Installation Guidance Formwork (non composite) Profile range 52 References Health & Safety Transport & Handling Design Cd 54 Composite Floor Decks 3
6 ComFlor 46 ComFlor 46 - From the PMF Shallow Composite Profile Range ComFlor 46, first introduced in 1985, is a simple trapezoidal composite deck with a strong and reliable shear bond performance. The profile is economic and nestable, reducing transport and handling costs. Nestable. The ultra efficient nesting capability of ComFlor 46 reduces the transport volume of the product. This fact combined with the simplicity of ComFlor 46 also makes it ideal for export. Easy service suspension. Ceilings and lightweight services can easily be attached to the punched hangar tabs, which can be included with ComFlor 46. These must be specified at time of order. Low concrete usage The trapezoidal shape profile of ComFlor 46 reduces the volume of concrete used, with resultant savings in structural and foundation costs. 4 Composite Floor Decks
7 ComFlor 46 ComFlor 46 Design information Full design program on CD (inside back page) ComFlor 46 Composite Slab - Volume & Weight Weight of Concrete (kn/m 2 ) Concrete Slab Depth volume Normal weight Concrete Lightweight Concrete (mm) (m 3 /m 2 ) Wet Dry Wet Dry Volume & weight table notes 1. Deck and beam deflection (i.e. ponding is not allowed for in the table. 2. Deck and mesh weight is not included in the weight of concrete figures. 3. Density of concrete is taken as: Normal weight (wet) 2400 kg/m 2 Normal weight (dry) 2350 kg/m 2 Lightweight (wet) 1900 kg/m 2 Lightweight (dry) 1800 kg/m 2 Section Properties (per metre width) Nominal Design Height to Moment of Ultimate Moment capacity thickness thickness Profile weight Area of steel neutral axis inertia (knm/m) (mm) (mm) (kn/m 2 ) (mm 2 /m) (mm) (cm 4 /m) Sagging Hogging Design Notes Deck material Zinc coated steel to BS EN 10147:1992, Fe E 280G, Z275, with a guaranteed minimum yield stress of 280 N/mm 2. Minimum zinc coating mass is 275 g/m 2 total including both sides. Quick reference tables The quick reference load/span and fire design tables, on the following 2 pages are intended as a guide for initial design, based on the parameters stated below the tables. The PMF calculation suite contained on the CD at the back of this literature provides a full design program. Please refer to page 56 for help on using the software. Anti-crack mesh BS 5950: Part 4 currently recommends that anticrack mesh should comprise 0.1% of slab area. The Eurocode 4 recommendation is that anticrack mesh should comprise 0.2% of slab area for unpropped spans and 0.4% of slab area for propped spans. PMF in conjunction with The Steel Construction Institute has agreed to modify the requirement with regard to anti-crack mesh, to comply with the Eurocode 4 recommendations. Accordingly, the mesh shown in the quick reference tables complies with EC4 and the design program defaults to these values. Where EC4 mesh rules are used, the mesh may be reduced midspan - see Design Information on page 20. The reduced British Standard mesh values may still be used by overriding this default in the design program. Mesh top cover must be a minimum of 15mm, and a maximum of 30mm. Mesh laps are to be 300mm for A142 mesh and 400mm for A193, A252 & A393 mesh. Fire For details of the performance of composite slabs comprising ComFlor 46 decking under a fire condition with nominal anti-crack mesh, please refer to the quick reference fire load tables in this brochure. For other simplified design cases or for full fire engineering, refer to the design CD. Technical services PMF Technical Department offer a comprehensive advisory service on design of composite flooring, which is available to all specifiers and users. Should queries arise which are not covered by this literature or by the design CD, please contact us. Composite Floor Decks 5
8 ComFlor 46 ComFlor 46 Normal weight concrete - quick reference tables ComFlor 46 Span table - Normal weight Concrete MAXIMUM SPAN (m) Deck Thickness (mm) Props Span Fire Slab Mesh Rating Depth Total Applied Load (kn/m 2 ) (mm) No Temporary props 1 Line of Temporary props 1 hr 120 A Simple 1.5 hr 130 A span slab 145 A & deck 2 hr 200 A A hr 120 A Double 1.5 hr 130 A span slab 145 A & deck 2 hr 200 A A A hr 130 A xA Simple 130 A hr span slab 145 2xA xA hr 200 2xA xA A hr 130 A xA Double 130 A hr span slab 145 2xA xA hr 200 2xA xA Composite Floor Decks
9 ComFlor 46 ComFlor 46 Lightweight concrete - quick reference tables ComFlor 46 Span table - Lightweight Concrete MAXIMUM SPAN (m) Deck Thickness (mm) Props Span Fire Slab Mesh Rating Depth Total Applied Load (kn/m 2 ) (mm) No Temporary props 1 Line of Temporary props 1 hr 110 A Simple 1.5 hr 120 A span slab 130 A & deck 2 hr 200 A A hr 110 A Double 1.5 hr 120 A span slab 130 A & deck 2 hr 200 A A A hr 120 A A Simple 120 A hr span slab 130 A A hr 200 2xA xA A hr 120 A A Double 120 A hr span slab 130 A A hr 200 2xA xA Parameters assumed for quick reference span tables Mesh Spans Deck Bearing width Prop width Deflection Deflection Concrete grade See notes on previous page. Measured centre to centre of supports. Standard deck material specification (see previous page). The width of the support is assumed to be 150mm. Assumed to be 100mm. Construction stage L/130 or 30mm (ponding has been taken into account). Composite stage L/350. The concrete is assumed to be Grade 35 with a maximum aggregate size of 20mm. The wet weight of concrete is taken to be normal weight 2400kg/m 3 and lightweight 1900 kg/m 3. The modular ratio is 10 for normal weight and 15 for lightweight concrete. Construction load 1.5 kn/m 2 construction load is taken into account,in accordance with BS 5950:Part 4. No allowance is made for heaping of concrete during the casting operation. See design notes. Applied load Simplified fire design method Fire engineering method Fire insulation Span/depth ratio The applied load stated in the tables is to cover imposed live load, partition loads, finishes, ceilings and services. However the dead load of the slab itself has already been taken into account and need not be considered as part of the applied load. The fire recommendations in the tables are based on the simplified design method. The fire engineering (FE) method may be used to calculate the additional reinforcement needed for fire, load and span conditions beyond the scope of these tables. The FE method of design is provided in the design CD. The minimum slab thickness indicated in each table, for each fire rating satisfies the fire insulation requirements of BS 5950: Part 8. Slab span to depth ratio is limited to 30 for lightweight concrete and 35 for normal weight concrete. Composite Floor Decks 7
10 ComFlor 51 ComFlor 51 - From the PMF Shallow Composite Profile Range ComFlor 51 is a traditional dovetail reentrant composite floor deck. This profile provides an excellent mechanical key into the concrete slab, offering a strong shear bond performance, which is augmented by cross stiffeners located in the profile trough. ComFlor 51 presents a virtually flat soffit and a relatively thin slab is required to meet fire design requirements. Shear studs The wide trough of ComFlor 51 permits a flexible and efficient placement of shear studs. Fire performance of the composite beams Even for two hours fire rating, the top flange of the steel beam does not require fire protection, when used with ComFlor 51 composite deck. Under floor services Services are easy to attach to ComFlor 51, with the ribs presenting a dovetailed recessed groove in the concrete slab at 152.5mm centres. This provides the perfect connection for service hangars via a wedge nut or similar type device. Fire performance of the slab The dovetail presents a very small opening and contributes little to the transfer of heat through the slab in the event of fire. Thus a lesser slab depth is needed for fire design purposes. 8 Composite Floor Decks
11 ComFlor 51 ComFlor 51 Design information Full design program on CD (inside back page) ComFlor 51 Composite Slab - Volume & Weight Weight of Concrete (kn/m 2 ) Concrete Slab Depth volume Normal weight Concrete Lightweight Concrete (mm) (m 3 /m 2 ) Wet Dry Wet Dry Volume & weight table notes 1. Deck and beam deflection (i.e. ponding is not allowed for in the table. 2. Deck and mesh weight is not included in the weight of concrete figures. 3. Density of concrete is taken as: Normal weight (wet) 2400 kg/m 2 Normal weight (dry) 2350 kg/m 2 Lightweight (wet) 1900 kg/m 2 Lightweight (dry) 1800 kg/m 2 Section Properties (per metre width) Nominal Design Height to Moment of Ultimate Moment capacity thickness thickness Profile weight Area of steel neutral axis inertia (knm/m) (mm) (mm) (kn/m 2 ) (mm 2 /m) (mm) (cm 4 /m) Sagging Hogging Design Notes Deck material Zinc coated steel to BS EN 10147:1992, Fe E 350G, Z275, with a guaranteed minimum yield stress of 350 N/mm 2. Minimum zinc coating mass is 275 g/m 2 total including both sides. Quick reference tables The quick reference load/span and fire design tables, on the following 2 pages are intended as guide for initial design, based on the parameters stated below the tables. The PMF calculation suite contained on the CD at the back of this literature provides a full design program. Please refer to page 56 for help on using the software. Anti-crack mesh BS 5950: Part 4 currently recommends that anticrack mesh should comprise 0.1% of slab area. The Eurocode 4 recommendation is that anticrack mesh should comprise 0.2% of slab area for unpropped spans and 0.4% of slab area for propped spans. PMF in conjunction with The Steel Construction Institute has agreed to modify the requirement with regard to anti-crack mesh, to comply with the Eurocode 4 recommendations. Accordingly, the mesh shown in the quick reference tables complies with EC4 and the design program defaults to these values. Where EC4 mesh rules are used, the mesh may be reduced midspan - see Design Information on page 20. The reduced British Standards mesh values may still be used by overriding this default in the design program. Mesh top cover must be a minimum of 15mm, and a maximum of 30mm. Mesh laps are to be 300mm for A142 mesh and 400mm for A193, A252 & A393 mesh. Fire For details of the performance of composite slabs comprising ComFlor 51 decking under a fire condition with nominal anti-crack mesh, please refer to the quick reference fire load tables in this brochure. For other simplified design cases or for full fire engineering, refer to the design CD. Technical services PMF Technical Department offer a comprehensive advisory service on design of composite flooring, which is available to all specifiers and users. Should queries arise which are not covered by this literature or by the design CD, please contact us. Composite Floor Decks 9
12 ComFlor 51 ComFlor 51 Normal weight concrete - quick reference tables ComFlor 51 Span table - Normal weight Concrete MAXIMUM SPAN (m) Deck Thickness (mm) Props Span Fire Rating Slab Depth Mesh Total Applied Load (kn/m 2 ) 1.2 (mm) No Temporary props 1 Line of Temporary props 1 hr 101 A Simple 1.5 hr 110 A span slab 125 A & deck 2 hr 200 A A hr 101 A Double 1.5 hr 110 A span slab 125 A & deck 2 hr 200 A A A hr 110 A A Simple 110 A hr span slab 125 A A hr 200 2xA xA A hr 110 A A Double 110 A hr span slab 125 A A hr 200 2xA xA Composite Floor Decks
13 ComFlor 51 ComFlor 51 Lightweight concrete - quick reference tables ComFlor 51 Span table - Lightweight Concrete MAXIMUM SPAN (m) Deck Thickness (mm) Props Span Fire Rating Slab Depth Mesh Total Applied Load (kn/m 2 ) 1.2 (mm) No Temporary props 1 Line of Temporary props 1 hr 101 A Simple 1.5 hr 105 A span slab 115 A & deck 2 hr 200 A A hr 101 A Double 1.5 hr 105 A span slab 115 A & deck 2 hr 200 A A A hr 105 A A Simple 105 A hr span slab 115 A A hr 200 2xA xA A hr 105 A A Double 105 A hr span slab 115 A A hr 200 2xA xA Parameters assumed for quick reference span tables Mesh Spans Deck Bearing width Prop width Deflection Deflection Concrete grade See notes on previous page. Measured centre to centre of supports. Standard deck material specification (see previous page). The width of the support is assumed to be 150mm. Assumed to be 100mm. Construction stage L/130 or 30mm (ponding has been taken into account). Composite stage L/350. The concrete is assumed to be Grade 35 with a maximum aggregate size of 20mm. The wet weight of concrete is taken to be normal weight 2400kg/m 3 and lightweight 1900 kg/m 3. The modular ratio is 10 for normal weight and 15 for lightweight concrete. Construction load 1.5 kn/m 2 construction load is taken into account,in accordance with BS 5950:Part 4. No allowance is made for heaping of concrete during the casting operation. See design notes. Applied load Simplified fire design method Fire engineering method Fire insulation Span/depth ratio The applied load stated in the tables is to cover imposed live load, partition loads, finishes, ceilings and services. However the dead load of the slab itself has already been taken into account and need not be considered as part of the applied load. The fire recommendations in the tables are based on the simplified design method. The fire engineering (FE) method may be used to calculate the additional reinforcement needed for fire, load and span conditions beyond the scope of these tables. The FE method of design is provided In the design CD. The minimum slab thickness indicated in each table, for each fire rating satisfies the fire insulation requirements of BS 5950: Part 8. Slab span to depth ratio is limited to 30 for lightweight concrete and 35 for normal weight concrete. Composite Floor Decks 11
14 ComFlor 70 ComFlor 70 - From the PMF Shallow Composite Profile Range ComFlor 70 is designed for optimum performance in span capacity, economy, composite performance and concrete usage. The economy and spanning capacity of a trapezoidal profile is combined with the interlocking shear performance of a re-entrant to give major performance advantages. Standard shear studs are fully effective with ComFlor 70 The profile is 70mm deep, including the top re-entrant section, but the height of the main trapezoidal section at 55mm defines the critical zone projecting from the base of the shear connector to the web-toflange junction of the profile. This point was confirmed in The Steel Construction Institute note AD147, following tests. The shear connector should project at least 35mm above the main trapezoidal section, meaning that a standard 95mm stud is conservatively adequate for use with ComFlor 70 profile. Reduced slab depth and concrete usage The slab depth required for fire and structural design is minimised by the profile design. The concrete usage is further reduced by the profile shape, which eliminates another effective 26mm from the slab depth. Reduced slab depth and concrete usage results in lower overall floor height, lower dead load structure and foundations, lower concrete cost. Optimum shear stud placement The arrangement of stiffeners in the ComFlor 70 trough allows shear studs to be positioned centre trough, which makes them fully effective in both directions, for composite beam design ie. no reductions in stud capacity due to deck geometry. Fire properties of 55mm deep profile Not only can the top re-entrant section be disregarded for stud design, tests have also confirmed that it is too small to contribute to the transmission of heat energy through the slab in a fire. Taking the effective profile height as 55mm results in a reduced overall slab depth being required for any particular fire rating. Low cost and fast service connection Low cost connector devices can be used with the small sized re-entrant, for the hanging of ceilings and services direct to the profile. 12 Composite Floor Decks
15 ComFlor 70 ComFlor 70 Design information Full design program on CD (inside back page) ComFlor 70 Composite Slab - Volume & Weight Weight of Concrete (kn/m 2 ) Concrete Slab Depth volume Normal weight Concrete Lightweight Concrete (mm) (m 3 /m 2 ) Wet Dry Wet Dry Volume & weight table notes 1. Deck and beam deflection (i.e. ponding is not allowed for in the table. 2. Deck and mesh weight is not included in the weight of concrete figures. 3. Density of concrete is taken as: Normal weight (wet) 2400 kg/m 2 Normal weight (dry) 2350 kg/m 2 Lightweight (wet) 1900 kg/m 2 Lightweight (dry) 1800 kg/m 2 Section Properties (per metre width) Nominal Design Height to Moment of Ultimate Moment capacity thickness thickness Profile weight Area of steel neutral axis inertia (knm/m) (mm) (mm) (kn/m 2 ) (mm 2 /m) (mm) (cm 4 /m) Sagging Hogging Design Notes Deck material Zinc coated steel to BS EN 10147:1992, Fe E 350G, Z275, with a guaranteed minimum yield stress of 350 N/mm 2. Minimum zinc coating mass is 275 g/m 2 total including both sides. Quick reference tables The quick reference load/span and fire design tables, on the following 2 pages are intended for initial design, based on the parameters stated below the tables. The PMF calculation suite contained on the CD at the back of this literature provides a full design program. Please refer to page 56 for help on using the software. Anti-crack mesh BS 5950: Part 4 currently recommends that anticrack mesh should comprise 0.1% of slab area. The Eurocode 4 recommendation is that anticrack mesh should comprise 0.2% of slab area for unpropped spans and 0.4% of slab area for propped spans. PMF in conjunction with The Steel Construction Institute has agreed to modify the requirement with regard to anti-crack mesh, to comply with the Eurocode 4 recommendations. Accordingly, the mesh shown in the quick reference tables complies with EC4 and the design program defaults to these values. Where EC4 mesh rules are used, the mesh may be reduced midspan - see Design Information on page 20. The reduced BS mesh values may still be used by overriding this default in the design program. Mesh top cover must be a minimum of 15mm, and a maximum of 30mm. Mesh laps are to be 300mm for A142 mesh and 400mm for A193, A252 & A393 mesh. Fire For details of the performance of composite slabs under a fire condition with nominal anticrack mesh, please refer to the quick reference fire load tables. For other simplified design cases or for full fire engineering, refer to the design CD. Technical services PMF Technical Department offer a comprehensive advisory service on design of composite flooring, which is available to all specifiers and users. Should queries arise which are not covered by this literature or by the design CD, please contact us. Composite Floor Decks 13
16 ComFlor 70 ComFlor 70 Normal weight concrete - quick reference tables ComFlor 70 Span table - Normal weight Concrete MAXIMUM SPAN (m) Deck Thickness (mm) Props Span Fire Rating Slab Depth Mesh Total Applied Load (kn/m 2 ) (mm) No Temporary props 1 Line of Temporary props 1 hr 125 A Simple 1.5 hr 135 A span slab 150 A & deck 2 hr 200 A A hr 125 A Double 1.5 hr 135 A span slab 150 A & deck 2 hr 200 A A A hr 135 A A Simple 135 A hr span slab 150 A A hr 200 2xA xA A hr 135 A A Double 135 A hr span slab 150 A A hr 200 2xA xA Composite Floor Decks
17 ComFlor 70 ComFlor 70 Lightweight concrete - quick reference tables ComFlor 70 Span table - Lightweight Concrete MAXIMUM SPAN (m) Deck Thickness (mm) Props Span Fire Rating Slab Depth Mesh Total Applied Load (kn/m 2 ) No Temporary props 1 Line of Temporary props 1 hr 115 A Simple 1.5 hr 125 A span slab 135 A & deck 2 hr 200 A A hr 115 A Double 1.5 hr 125 A span slab 135 A & deck 2 hr 200 A A A hr 125 A A Simple 125 A hr span slab 135 A A hr 200 2xA xA A hr 125 A A Double 125 A hr span slab 135 A A hr 200 2xA xA Parameters assumed for quick reference span tables Mesh Spans Deck Bearing width Prop width Deflection Deflection Concrete grade See notes on previous page. Measured centre to centre of supports. Standard deck material specification (see previous page). The width of the support is assumed to be 150mm. Assumed to be 100mm. Construction stage L/130 or 30mm (ponding has been taken into account). Composite stage L/350. The concrete is assumed to be Grade 35 with a maximum aggregate size of 20mm. The wet weight of concrete is taken to be normal weight 2400kg/m 3 and lightweight 1900 kg/m 3. The modular ratio is 10 for normal weight and 15 for lightweight concrete. Construction load 1.5 kn/m 2 construction load is taken into account,in accordance with BS 5950:Part 4. No allowance is made for heaping of concrete during the casting operation. See design notes. Applied load Simplified fire design method Fire engineering method Fire insulation Span/depth ratio The applied load stated in the tables is to cover imposed live load, partition loads, finishes, ceilings and services. However the dead load of the slab itself has already been taken into account and need not be considered as part of the applied load. The fire recommendations in the tables are based on the simplified design method. The fire engineering (FE) method may be used to calculate the additional reinforcement needed for fire, load and span conditions beyond the scope of these tables. The FE method of design is provided in the design CD. The minimum slab thickness indicated in each table, for each fire rating satisfies the fire insulation requirements of BS 5950: Part 8. Slab span to depth ratio is limited to 30 for lightweight concrete and 35 for normal weight concrete. Composite Floor Decks 15
18 ComFlor 100 ComFlor From the PMF Shallow Composite Profile Range ComFlor 100, has a very strong profile shape and offers the capability to span up to 4.5metres without props. Designed particularly for Continental European application, the ComFlor 100 also brings considerable benefits to the British designer looking for longer unpropped spans. The profile is not suitable for use with shear stud connectors. No temporary props ComFlor 100 can carry wet concrete and construction loads to 4.5m without temporary propping, (depending on slab depth) thereby leaving a clear area beneath the floor under construction. Further savings of labour and prop hire are also realised. Large concrete volume reduction Although a deep slab is required, the ComFlor 100 profile greatly reduces the volume of concrete needed and thus the cost and weight of concrete. Suitable for traditional construction ComFlor 100 is suitable to be placed onto masonry walls or standard design noncomposite steel beams. 16 Composite Floor Decks
19 ComFlor 100 ComFlor 100 Design information Full design program on CD (inside back page) ComFlor 100 Composite Slab - Volume & Weight Weight of Concrete (kn/m 2 ) Concrete Slab Depth volume Normal weight Concrete Lightweight Concrete (mm) (m 3 /m 2 ) Wet Dry Wet Dry Volume & weight table notes 1. Deck and beam deflection (i.e. ponding is not allowed for in the table. 2. Deck and mesh weight is not included in the weight of concrete figures. 3. Density of concrete is taken as: Normal weight (wet) 2400 kg/m 2 Normal weight (dry) 2350 kg/m 2 Lightweight (wet) 1900 kg/m 2 Lightweight (dry) 1800 kg/m 2 ComFlor 100 is not designed for use with shear studs (i.e. not for composite beam design) Section Properties (per metre width) Nominal Design Height to Moment of Ultimate Moment capacity thickness thickness Profile weight Area of steel neutral axis inertia (knm/m) (mm) (mm) (kn/m 2 ) (mm 2 /m) (mm) (cm 4 /m) Sagging Hogging Design Notes Deck material Zinc coated steel to BS EN 10147:1992, Fe E 280G, Z275, with a guaranteed minimum yield stress of 280 N/mm 2. Minimum zinc coating mass is 275 g/m 2 total including both sides. Quick reference tables The quick reference load/span and fire design tables, on the following 2 pages are intended for initial design, based on the parameters stated below the tables. The PMF calculation suite contained on the CD at the back of this literature provides a full design program. Please refer to page 56 for help on using the software. Anti-crack mesh BS 5950: Part 4 currently recommends that anticrack mesh should comprise 0.1% of slab area. The Eurocode 4 recommendation is that anticrack mesh should comprise 0.2% of slab area for unpropped spans and 0.4% of slab area for propped spans. PMF in conjunction with The Steel Construction Institute has agreed to modify the requirement with regard to anti-crack mesh, to comply with the Eurocode 4 recommendations. Accordingly, the mesh shown in the quick reference tables complies with EC4 and the design program defaults to these values. Where EC4 mesh rules are used, the mesh may be reduced midspan - see Design Information on page 20. The reduced BS mesh values may still be used by overriding this default in the design program. Mesh top cover must be a minimum of 15mm, and a maximum of 30mm. Mesh laps are to be 300mm for A142 mesh and 400mm for A193, A252 & A393 mesh. Fire For details of the performance of composite slabs under a fire condition with nominal anticrack mesh, please refer to the quick reference fire load tables. For other simplified design cases or for full fire engineering, refer to the design CD. Technical services PMF Technical Department offer a comprehensive advisory service on design of composite flooring, which is available to all specifiers and users. Should queries arise which are not covered by this literature or by the design CD, please contact us. Composite Floor Decks 17 Secret Fix Product Selector 9
20 ComFlor 100 ComFlor 100 Normal weight concrete - quick reference tables ComFlor 100 Span table - Normal weight Concrete MAXIMUM SPAN (m) Deck Thickness Props Span Fire Rating Slab Depth Mesh Bar Reinforcement Total Applied Load (kn/m 2 ) 1.2 (mm) 12mm No Temporary props 1 Line of Temporary props Simple span slab & deck Double span slab & deck Simple span slab & deck Simple span slab & deck 1 hr 170 A252 None hr 180 A393 None hr 195 A393 None A393 None hr 170 A142 None hr 180 A252 None hr 195 A393 None A393 None hr 170 A393 One per trough xA393 One per trough hr 180 A393 One per trough xA393 One per trough hr 195 A393 One per trough xA393 One per trough hr 170 A393 One per trough xA393 One per trough hr 180 A393 One per trough xA393 One per trough hr 195 A393 One per trough xA393 One per trough Composite Floor Decks
21 ComFlor100 ComFlor 100 Lightweight concrete - quick reference tables ComFlor 100 Span table - Lightweight Concrete MAXIMUM SPAN (m) Deck Thickness Props Span Fire Rating Slab Depth Mesh Bar Reinforcement Total Applied Load (kn/m 2 ) 1.2 (mm) 12mm No Temporary props 1 Line of Temporary props Simple span slab & deck Double span slab & deck Simple span slab & deck Simple span slab & deck 1 hr 160 A252 None hr 170 A252 None hr 180 A393 None A393 None hr 160 A142 None hr 170 A142 None hr 180 A393 None A393 None hr 160 A252 One per trough xA393 One per trough hr 170 A393 One per trough xA393 One per trough hr 180 A393 One per trough xA393 One per trough hr 160 A252 One per trough xA393 One per trough hr 170 A393 One per trough xA393 One per trough hr 180 A393 One per trough xA393 One per trough Parameters assumed for quick reference span tables Mesh Spans Deck Bearing width Prop width Deflection Deflection Concrete grade See notes on previous page. Measured centre to centre of supports. Standard deck material specification (see previous page). The width of the support is assumed to be 150mm. Assumed to be 100mm. Construction stage L/130 or 30mm (ponding has been taken into account). Composite stage L/350. The concrete is assumed to be Grade 35 with a maximum aggregate size of 20mm. The wet weight of concrete is taken to be normal weight 2400kg/m 3 and lightweight 1900 kg/m 3. The modular ratio is 10 for normal weight and 15 for lightweight concrete. Construction load 1.5 kn/m 2 construction load is taken into account,in accordance with BS 5950:Part 4. No allowance is made for heaping of concrete during the casting operation. See design notes. Applied load Simplified fire design method Fire engineering method Fire insulation Span/depth ratio The applied load stated in the tables is to cover imposed live load, partition loads, finishes, ceilings and services. However the dead load of the slab itself has already been taken into account and need not be considered as part of the applied load. The fire recommendations in the No Prop section of these tables are based on the simplified design method. The fire engineering (FE) method has been used to calculate the reinforcement needed for fire,load and span conditions in the propped section of these tables. The FE method of design is provided in the design CD which may be used for further design situations. The minimum slab thickness indicated in each table, for each fire rating satisfies the fire insulation requirements of BS 5950: Part 8. Slab span to depth ratio is limited to 30 for lightweight concrete and 35 for normal weight concrete. Composite Floor Decks 19
22 Design Information Shallow Composite Floor Decks -Design information Composite Floor Decking design is generally dictated by the construction stage condition, the load and span required for service and the fire resistance required for the slab. The deck design is also influenced by the composite beam design. Design Parameters Fire rating dictates minimum slab depth. Concrete type also dictates minimum slab depth and influences unpropped deck span. Deck span (unpropped) usually dictates general beam spacing. Slab span (propped deck) dictates maximum beam spacing. Two Stage Design All Composite Floors must be considered in two stages. Wet Concrete and Construction load carried by deck alone. Cured Concrete carried by composite slab. General design aims Generally designers prefer to reduce the requirement to provide temporary propping and so the span and slab depth required governs the deck selection. Fire requirements usually dictate slab depth. For most applications, the imposed load on the slab will not limit the design. Quick Reference and Full Design. The combination of this manual and design CD makes both quick reference and full design easy. Indicative design may be carried out from the printed tables, however the software on the CD greatly increases the scope available to the Design Engineer and allows the engineer to print a full set of calculations which can be used for submission to a Local Authority. British Standards and Eurocodes The Software user is offered a choice to design to either BS5950 Parts 4 and 3 or to Eurocode 4. The quick reference tables are designed to BS5950 Part 4, with the important exception of the mesh recommendations. Anti-crack mesh BS5950 : Part 4 currently recommends that anti-crack mesh should comprise 0.1% of slab area. The Eurocode 4 recommendation is that anti-crack mesh should comprise 0.2% of slab area for unpropped spans and 0.4% of slab area for propped spans. PMF in conjunction with The Steel Construction Institute has agreed to modify the requirement with regard to anti-crack mesh, to comply with the Eurocode 4 recommendations. Accordingly, the mesh shown in the quick reference tables complies with EC4 and the design program defaults to these values. The reduced BS mesh values may still be used by overriding this default in the design program. In slabs subject to line loads, the mesh should comprise 0.4% of the cross-sectional area of the concrete topping, propped and unpropped. These limits ensure adequate crack control in visually exposed applications (0.5 mm maximum crack width). The mesh reinforcement should be positioned at a maximum of 30 mm from the top surface. Elsewhere, 0.1% reinforcement may be used to distribute local loads on the slab (or 0.2% to EC4). Mesh laps are to be 300mm for A142 mesh and 400mm for A193, A252 & A393. Reduced Mesh Where EC4 mesh rules are used, as recommended by Steel Construction Institute and PMF, the full stipulated mesh applies to the slab 1.2m either side of every support. Outside of this, i.e. in the midspan area, the mesh area may be halved (to 0.2% for propped and 0.1% for unpropped construction), provided there are no concentrated loads, openings etc. to be considered. Also the reduced midspan mesh must be checked for adequacy under fire, for the rating required. 1.2m 1.2m 1.2m 1.2m Bar Reinforcement The Axis Distance of bar reinforcement defines the distance from the bottom of the ribs to the centre of the bar, which has a minimum value of 25 mm, and a maximum value of the profile height. Where used, bar reinforcement is placed at one bar per profile trough. Transverse Reinforcement. PMF composite floor decks contribute to transverse reinforcement of the composite beam, provided that the decking is either continuous across the top flange of the steel beam or alternatively that it is welded to the steel beam by stud shear connectors. For further information refer to BS5950:Part 3: Section 3.1.Clause Concrete choice Lightweight concrete (LWC) uses artificially produced aggregate such as expanded pulverised fuel ash pellets. LWC leads to considerable advantages in improved fire performance, reduced slab depth, longer unpropped spans and reduced dead load. However, LWC is not readily available in some parts of the country. Normal weight concrete uses a natural aggregate and is widely available. The strength of the concrete must meet the requirements for strength for the composite slab and shall not be less than 25N/mm 2 for LWC or 30N/mm 2 for NWC. Similarly, the maximum value of concrete strength shall not be taken as greater than 40 for LWC or 50 for NWC. The modular ratio defines the ratio of the elastic modulus of steel to concrete, as modified for creep in the concrete. In design to BS5950 and BS8110, the cube strength is used (in N/mm 2 ). In design to EC3, the cylinder strength is used (in N/mm 2 ). The concrete grade (C30/37) defines the (cylinder/cube strength) to EC3. Support Beam Support Beam Support Beam Diagram showing full mesh area over supports 20 Composite Floor Decks
23 Shallow Composite Floor Decks -Design information Design Information Concrete Density In the absence of more precise information, the following assumptions may be made: The wet density is used in the design of the profiled steel sheets and the dry density, in the design of the composite slab. Fire Design Density kg/m 3 Wet Dry Modular Ratio LWC NWC Fire insulation The fire insulation requirements of BS 5950: Part 8, must be satisfied and are taken into account in the tables and design software. Span/depth ratio Slab span to depth ratio is limited to a maximum of 30 for lightweight concrete and 35 for normal weight concrete. Shear connectors in fire situation If shear connectors are provided, any catenary forces transferred from the slab to the support beams can be ignored within the fire resistance periods quoted. Fire Design methods There are two requirements for fire design: * Bending resistance in fire conditions. * Minimum slab depth for insulation purposes. The capacity of the composite slab in fire may be calculated using either the Simple Method or the Fire Engineering Method. The simple method will be the most economic. The fire engineering method should be used for design to Eurocodes. The Simple Method: The Simple Method may be used for simply supported decks or for decks continuous over one or more internal supports. The capacity assessment in fire is based on a single or double layer of standard mesh. Any bar reinforcement is ignored. The Fire Engineering Method: The Fire Engineering Method is of general application. The capacity assessment in fire is based on a single or double layer of standard mesh at the top and one bar in each concrete rib. For the shallow decks, the program assumes the bar is positioned just below the top of the steel deck. For CF70 with a raised dovetail in the crest, the bar will be placed below the dovetail. The quick reference tables for shallow composite floors generally use the simplified fire design method (except CF100), which utilises the anti-crack mesh as fire reinforcement. Increased load span capability under fire may be realised by including bar reinforcement and using the fire engineering method of design. Deflection Limits Deflection Limits would normally be agreed with the client. In the absence of more appropriate information, the following limits should be adopted: Construction Stage Le/130 (but not greater than 30mm) Imposed load deflection Le/350 (but not greater than 20mm) Total load deflection Le/250 (but not greater than 30mm) According to BS5950 Part 4, ponding, resulting from the deflection of the decking is only taken into account if the construction stage deflection exceeds Ds/10. Le is the effective span of the deck and Ds is the slab overall depth (excluding non-structural screeds). The deflection under construction load should not exceed the span/180 or 20mm overall, whichever is the lesser, when the ponding of the concrete slab is not taken into account. Where ponding is taken into account the deflection should not exceed the span/130 or 30mm overall. The quick reference tables do take ponding into account, if deflection exceeds Ds/10, or Le/180, and thus use span/130 or 30mm as a deflection limit. It is recommended that the prop width should not be less than 100mm otherwise the deck may mark slightly at prop lines. Vibration The dynamic sensitivity of the composite slab should be checked in accordance with the Steel Construction Institute publication P076: Design guide on the vibration of floors. The natural frequency is calculated using the selfweight of the slab, ceiling and services, screed and 10% imposed loads, representing the permanent loads and the floor. In the absence of more appropriate information, the natural frequency of the composite slab should not exceed 5Hz for normal office, industrial or domestic usage. Conversely, for dance floor type applications or for floors supporting sensitive machinery, the limit may need to be set higher. For design to the Eurocodes, the loads considered for the vibration check are increased using the psi-factor for imposed loads (typically 0.5). The natural frequency limit may be reduced to 4Hz, because of this higher load, used in the calculation. Loads and Load Arrangement Loading information would normally be agreed with the clients. Reference should also be made to BS 6399 and to EC1. Factored loads are considered at the ultimate limit state and unfactored loads at the serviceability limit state. Unfactored loads are also considered in fire conditions. Partial factors are taken from BS5950, EC3 and EC4. Loads considered at the construction stage consist of the slab self weight and the basic construction load. The basic construction load is taken as 1.5 kn/m 2 or 4.5/Lp (whichever is greater), where Lp is the span of the profiled steel sheets between effective supports in metres. For multi span unpropped construction, the basic construction load of 1.5 kn/m 2 is considered over the one span only. On other spans, the construction load considered is half this value (i.e kn/m 2 ). Construction loads are considered as imposed loads for this check. Loads considered at the normal service stage consist of the slab self weight, superimposed dead loads and imposed loads. Composite Floor Decks 21
24 Design Information Shallow Composite Floor Decks -Design information Openings Openings can be accommodated readily in composite slabs, by boxing out prior to pouring concrete and cutting out the deck after concrete has cured (see sitework section on page 31. The design of openings depends on their size: Extra bars in slab (over the deck) B Small Openings up to 300 mm square - do not normally require additional reinforcement. Medium Openings between 300 mm and 700 mm square - normally require additional reinforcement to be placed in the slab. This is also the case if the openings are placed close together. Opening B A A Large Openings greater than 700mm square - should be trimmed with additional permanent steelwork back to the support beams. Opening Rules Where W = width of opening across the span of the deck. 1. The distance between the opening and unsupported edge must be greater than 500mm or W, whichever is the greater. 2. Openings must not be closer together than 1.5W (of the largest opening) or 300mm, whichever is the greater. If they are closer they must be considered as one opening. 3. Not more than 1 / 4 width of any bay is to be removed by openings. 4. Not more than 1 / 4 width of deck span is to be removed by openings. Where these rules are not satisfied, the openings must be fully trimmed with support steelwork. Centre Line of Floor Beam Transverse reinforced concrete beam strip Reinforcement around opening If the opening falls within the usual effective breadth of concrete flange of any composite beams (typically span/8 each side of the beam centre line), the beam resistance should be checked assuming an appropriately reduced effective breadth of slab. Slab design around openings It may be assumed that an effective system of beam strips span the perimeter of the opening. The effective breadth of the beam strips should be taken as d o /2, where d o is the width of the opening in the direction transverse to the decking ribs. Only the concrete above the ribs is effective. The transverse beam strips are assumed to be simply supported, and span a distance of 1.5 d o. The longitudinal beam strips are designed to resist the load from the transverse beam strips, in addition to their own proportion of the loading. Centre Line of Floor Beam Extra bars in troughs Reinforcement Extra reinforcement is provided within the beam strips to suit the applied loading. This reinforcement often takes the form of bars placed in the troughs of the decking. Additional transverse or diagonal bars may be used to improve load transfer around the opening. Mesh Section A-A Extra bars in troughs d o /2 d o Deck Span Effective span of transverse beam strips = 1d o Mesh Section B-B d o /2 d o /2 d o /2 Longitudinal reinforced concrete beam strips Load paths and beam strips around medium to large openings Extra bars over deck 22 Composite Floor Decks
25 Shallow Composite Floor Decks -Design information Design Information Design of Shear Studs Composite beam design. Savings in beam weight of up to 50% can be achieved when the composite slab is effectively anchored to the steel beam. The slab will then act as a compression flange to the beam. Non-beneficial side Crushing Beneficial side Force applied to shear stud The methods of connection between slab and beam is generally by means of through deck welding of 19mm diameter shear studs of varying height, which are fixed to the beam after the decking has been laid. Top Flange of beam Off-centre welding of shear-connectors Force applied to slab Crushing Headed studs When deck profile ribs are running perpendicular to the steel beam i.e. compositely connected to the composite slab, the capacity of headed studs should be taken as their capacity in a solid slab but multiplied by the reduction factor k. The table relates to 95mm high, 19mm diameter shear studs. The calculation method for k differs between BS5950 Part 3 and Eurocode 4. Suitability of decks Shear studs cannot be placed on profile stiffeners, and with CF70 and CF46, the position of the stiffeners dictates the shear stud position. With CF70, the trough containing the side lap rib prevents central placement of studs but the other two troughs have twin stiffeners, which allow central placement of studs which means site supervision is kept to a minimum. The profile height of CF70 is taken at 55mm see page 12. NB: CF100 is not suitable for use with shear studs. Non-welded shear connectors Hilti shear connectors may be used. Refer to Hilti for further information. Design guide The Steel Construction Institute / Metal Cladding & Roofing Manufacturers Association P300 Composite Slabs and Beams using Steel Decking: Best Practice for Design and Construction is recommended by PMF for further reference. THROUGH DECK WELDED STUD REDUCTION FACTOR k BS5950 Part 3 centre placed, Unfavourably placed favourably placed or studs offset placed studs (2) 1 stud/rib 2 studs /rib 1 stud/rib 2 studs /rib CF CF46 & CF EC4 Ribs perpendicular Ribs parallel (transverse) to beam to beam 1 stud/rib 2 studs /rib CF70,CF46 & CF51-1mm or less CF46 & CF CF70,CF46 & CF51 - greater than 1mm CENTRAL STUDS OFFSET PLACED STUDS NON-CENTRAL STUDS *76mm = 4d for 19mm studs 57mm = 3d for 19mm studs 76*mm min 57*mm min 76*mm min 20mm min, edge of stud to edge of beam Composite Floor Decks 23
26 Construction Details Shallow Composite Floor Decks - Construction details Plan view of typical floor layout Deck notation Edge trim dimensions Y X Edge trim reference F75 X Tie member dimensions Indicates cut plate 245 mm wide F75 Beam member centreline C P 245 Distance (mm) from centreline of tie member to Setting Out Point (s.o.p.) of decking first sheet C D Indicates cut deck Indicates bay which requires temporary propping. F75 X = distance (mm) from centreline of beam to edge of slab (parallel to deck span) Y = distance (mm) from centreline of tie member to edge of slab (perpendicular to deck span) Floor level Number of sheets Phase Decking lengths Bundle number Span of decking Y F75 Typical side detail Tie Member centres Y Steel stud Edge trim CF70 Floor Decking 20 min Cantilever dimension For Cantilevers over 150mm, additional reinforcement is required. See table p.27 for maximum Cantilevers without props. Universal Beam Typical side detail Tie Member centres Steel stud X Unsupported edge detail 100mm minimum Edge trim Edge trim Restraint strap at 600mm centres Restraint strap CF51 Floor Decking 20 min Universal Beam See typical plan for dimension X & Y Reinforcement as specified Timber bearer Temporary prop 24 Composite Floor Decks
27 Shallow Composite Floor Decks - Construction details Construction Details Typical end detail Butt joint Edge trim X Beam centres Stud on centreline of beam 20 min Edge of flange to side of stud 50 min Restraint straps at 600mm centres Cantilever dimensions see table p.29 Universal Beam Floor decking to have a 50mm minimum bearing on top flange of beam When studs are used deck is to extend 20mm minimum beyond the stud Universal Beam CF70 Floor Decking Studs in pairs or staggered where a butt joint occurs Deck to be butt jointed over centreline of beam Typical end Cantilever Step in floor Edge trim fixed to decking sheet X Beam centres Steel stud if applicable Edge trim fixed to align with edge of beam Restraint straps at 600mm centres Dimension X required Maximum Cantilever 500mm, greater Cantilevers require temporary props and additional reinforcement or steelwork brackets connected to the Universal Beam Universal Beam CF70 Floor Decking to extend to edge trim CF70 Decking to centreline of beam RSA to be wide enough to provide sufficient bearing and allow fixing of deck without drill fouling top flange of beam above Universal Beam CF70 Decking with a minimum 50mm bearing Composite Floor Decks 25
28 Construction Details Shallow Composite Floor Decks -Construction details End detail alternative 1 End detail alternative 2 X Beam centres X Beam centres Stud on centreline of beam Restraint strap Steel stud Edge trim Restraint strap at 600mm centres Universal Beam CF51 Floor Decking to extend to edge trim Edge trim Cantilever dimension Universal Beam CF51 Floor Decking to centreline of beam 20 mm min. For Cantilevers over 150mm additional reinforcement is required. See table on p.27 for maximum cantilever without props Side cantilever with stub bracket Typical edge with plate Dimension required Edge Trim Steel stud CF70 Floor Decking Y Beam centres Edge trim Restraint strap CF70 Floor Decking Steel stub as designed by the engineer 20 mm min Closure plate in 2mm flat steel strip to suit remainder of floor area to a maximum of 245mm. Reference CP245 (plate width) Universal Beam Universal Beam 26 Composite Floor Decks
29 Shallow Composite Floor Decks -Construction details Construction Details Beam at perimeter wall 25 X Beam centres Typical wall end detail Overall wall dimension CE100 edge trim leaving room for 25mm Korkpak joint Restraint strap Stud on centreline of beam CF51 Floor Decking to extend to edge trim Edge trim to align with edge of wall CF70 Floor Decking with 75mm (minimum) bearing onto wall Perimeter wall 100mm wall shown here Universal Beam Typical wall side detail Deck Inside of wall detail Wall outer dimensions Steel or wall to wall 10 mm min Masonry fixing to wall at 500mm c/c Edge trim to align with edge of wall 100mm wall shown here CF70 Floor Decking with 75mm (minimum) bearing onto wall CF70 Floor Decking with 50mm (minimum) bearing onto steel angle RSA, RSC or Universal Beam Perimeter wall Composite Floor Decks 27
30 Sitework Shallow Composite Floor Decks -Sitework Deck fixing Immediately after laying, the deck must be fixed through its trough to the top of the supporting structure. Powder actuated pins or self-drilling screws are used. Side lap fixings are required at 1000mm centres for CF46, CF70 and CF100. Where shear studs are being used, the deck requires two fixings per sheet per support at sheet ends and one fixing per sheet at intermediate supports. Where shear studs are not employed, the deck must be fixed as follows: To Steel To Masonry or Concrete To side laps or closures etc. FIXING INFORMATION FOR SHALLOW DECKING Heavy duty powder actuated fixings - Hilti ENP2 nail/spit SBR14 or equivalent Self-drilling screws. To steel up to 11mm thick - SFS SD x 32 / EJOT HS 38 or equivalent. To steel up to 17mm thick SFS TDC-T-6.3 x 38 or equivalent Pre drill hole - use self tapping fixing suitable for masonry/ concrete - SFS TB-T range/ejot 4H32 or equivalent Self drilling stitching screw typically SFS SL range / EJOT SF25 or equivalent FIXING SPACINGS Telephone numbers of fixings suppliers EJOT Erico Hilti SFS Spit ComFlor 46 ComFlor 51 ComFlor 100 & ComFlor 70 End fixing 3 per sheet (2 per sheet when 2 per sheet 2 per sheet using shear studs) Intermediate 2 per sheet supports (1 per sheet when 1 per sheet 1 per sheet using shear studs) Side laps 1 fixing at 1000mm c/c (not required for CF 51) Side fixing onto support 1 fixing at 600mm c/c Deck fixing on CF 70 Butt joint in decking Intermediate support 3 fixings per sheet (CF46 & CF70) 2 fixings per sheet (CF51 & CF100) on both sides of butt joint 2 fixings per sheet (CF46 & CF70) 1 fixing per sheet (CF51 & CF100) 3 fixings per sheet (CF46 & CF70) 2 fixings per sheet (CF51 & CF100) Side lap, CF46 & CF70, CF100 fixing at 1000mm CF51 does not require side lap fixing 28 Composite Floor Decks
31 Shallow Composite Floor Decks -Sitework Sitework Bearing requirements End bearing and shared bearing (minimum) Continuous bearing (minimum) 50mm 50mm 75mm Steel Section Steel Section 70mm 70mm 100mm Masonry Masonry Edge trim This is used to retain the wet concrete to the correct level at the decking perimeters. It is fixed to the supports in the same manner as the deck and the top is restrained by straps at 600mm centres, which are fixed to the top of the deck profile, by steel pop rivets or selfdrilling screws. Edge trim Selector Edge Maximum Cantilever (mm) trim Galv. Steel Edge Trim Thickness (mm) depth x x x x x x x 0 x - not recommended Composite Floor Decks 29
32 Sitework Shallow Composite Floor Decks -Sitework Shear connectors Most commonly used shear connectors are 19mm diameter headed studs, which are welded to the support beam through the deck, a process carried out by specialist stud welding contractors. Site conditions must be suitable for welding and bend tests carried out as appropriate. The spacing and position of the shear connectors is important and must be defined by the design engineer on the deck set out drawings. Minimum Spacing: The minimum centre-tospacing of stud shear connectors should be 5d along the beam and 4d between adjacent studs, where d is the nominal shank diameter. Where rows of studs are staggered, the minimum transverse spacing of longitudinal lines of studs should be 3d. The shear stud should not be closer than 20mm to the edge of the beam. See page 23. Further guidance on shear studs for designers and installers may be found in The Steel Construction Institution publications: P300 Composite Slabs and Beams Using Steel Decking: Best Practice for Design and Construction, P055 Design of Composite Slabs and Beams with Steel Decking. Mesh placement Standard reinforcing mesh, such as A142, A193 and A252 is usually required, positioned towards the top of the slab. The top cover to the reinforcement mesh should be a minimum of 15mm and a maximum of 30mm. Support stools are required to maintain the correct mesh height. The mesh must be lapped by 300mm for A142 and A193 mesh, and by 400mm for A252 and A393 mesh. Casting concrete Before the concrete is poured, the decking must be cleared of all dirt and grease, which could adversely influence the performance of the hardened slab. The oil left on the decking from the roll forming process does not have to be removed. Concrete should be poured evenly, working in the direction of span. Care should be taken to avoid heaping of concrete in any area during the casting sequence. Construction and day joints should occur over a support beam, preferably also at a deck joint. Ceilings and services hanger systems The dovetail shaped re-entrant rib on ComFlor 51 and the 15mm high raised minidovetail re-entrant stiffener on ComFlor 70 profiles allow for the quick and easy suspension of ceiling and services, using either of the two following suspension systems. (a) Threaded wedge nut fixings ComFlor 51 ComFlor 70 Wedges are dovetail shaped steel blocks, which are threaded to take metric bolts or threaded rods. The wedge nut hanger system is installed after the concrete of the composite slab has been poured and is hardened. Installation For installation of the system, wedge nuts are inserted into the raised re-entrants of the profile before being rotated 90 degrees, after which the dovetail shaped wedge nuts will lock into the dovetail re-entrants under vertical loading. Finally, the bolts or threaded rods are finger tightened up to the roof of the reentrants and mechanically tightened. (b) GTD-clip hangar fixings GTD-clip hangar fixings are cold formed thin steel hangers with circular openings in the soffit to take metric bolts, threaded rods or further pipe clamp hangers. The system is installed after the composite slab has been poured and the concrete is sufficiently hardened. Installation To install the GTD-clips, the two dovetail shaped ends are compressed by hand and inserted into the dovetail re-entrant of the profile, before being rotated 90 degrees. One then lets go of the two ends and the clip will snap into position and is tightly connected. Finally, bolts, threaded rods or pipe clamps are connected into the soffit opening of the GTD-clip. Loadbearing Capacities System Thread Maximum Size Static Working Load (kg) Wedge Nut GTD - Clip GTD - Clip & N/A 45 Pipe Clamp A minimum safety factor of 4 has been applied to the safe working load capacities 30 Composite Floor Decks
33 Sitework Shallow Composite Floor Decks -Sitework Openings Openings greater than 300mm must be designed by the engineer, with extra reinforcement placed around the opening. Openings up to 700mm can be accommodated readily in composite slabs, by boxing out prior to pouring concrete and cutting out the deck after concrete has cured. Larger openings require support trimming steel, which must be installed prior to the decking. The decking is cut away immediately and the opening edges are then treated like any other perimeter with edge trim. Note: do not cut the opening in the steel deck prior to concreting, or before the concrete has cured. Timber shutter Dense polystyrene block Temporary supports The safe design and installation of temporary props is the responsibility of the main contractor or designated sub-contractor. Where temporary supports are required by the design, these must provide continuous support to the profiled sheeting. Spreader beams (timbers) are used, supported by temporary props at one metre centres. [a] The timbers and props must be of adequate strength and construction [b] The temporary supports are placed at midspan or at other suitable centres if more supports per span are required. Please contact PMF Technical Department [c] The spreader beams or timbers are to provide a minimum bearing width of l00mm. The spreaders must not deflect more than 10mm and should be placed narrow edge up, see diagram. [d] The propping structure is not to be removed until the concrete has reached at least 70% of its characteristic strength. The horizontal bearer timbers must be at least 100mm wide and should be propped at no more than 1m centres. Sometimes the specification may call for 150mm wide bearers, as determined by the structural engineer or concreting contractor. Temporary Props Timber Bearer Guide (shallow decks) All to be min. 100mm wide Slab depth (mm) Bearer depth(mm) up to Temporary support using an Acrow type prop Composite Floor Decks 31
34 ComFlor 210 ComFlor From the PMF Deep Composite Profile Range The original SlimFlor long span steel deck, ComFlor 210 has the capability to span up to 6 metres in unpropped construction. Suitable for use in Corus Slimdek construction, which offers minimal structural depth, fast construction and many other benefits. With cross and longitudinal stiffeners, CF210 is structurally efficient and offers excellent composite action with the concrete. Simple single bar reinforcement in each trough, combined with anti-crack mesh near the top of the concrete slab gives the composite slab superb structural strength and fire properties. The nestable profile shape reduces transport and handling costs. Up to 2 hours fire rating with unprotected soffit. 32 Composite Floor Decks
35 ComFlor 210 ComFlor 210 Design information Full design program on CD (inside back page) ComFlor 210 Composite Slab - Volume & Weight Weight of Concrete (kn/m 2 Concrete Slab Depth volume Normal weight Concrete Lightweight Concrete (mm) (m 3 /m 2 ) Wet Dry Wet Dry Volume & weight table notes 1. Deck and beam deflection (i.e. ponding is not allowed for in the table. 2. Deck and mesh weight is not included in the weight of concrete figures. 3. Density of concrete is taken as: Normal weight (wet) 2400 kg/m 2 Normal weight (dry) 2350 kg/m 2 Lightweight (wet) 1900 kg/m 2 Lightweight (dry) 1800 kg/m 2 Section Properties (per metre width) Nominal Design Height to Moment of Ultimate Moment Capacity thickness thickness Profile weight Area of steel neutral axis inertia (knm/m) (mm) (mm) (kn/m 2 ) (mm 2 /m) (mm) (cm 4 /m) Sagging Hogging Design Notes Deck material Zinc coated steel to BS EN 10147:1992, Fe E 350G, Z275, with a guaranteed minimum yield stress of 350 N/mm 2. Minimum zinc coating mass is 275 g/m 2 total including both sides. Quick reference tables The quick reference load/span and fire design tables on the following 2 pages are intended for initial design, based on the parameters stated below the tables. The PMF calculation suite contained on the CD at the back of this literature provides a full design program. Please refer to page 56 for help in using the software. Anti-crack mesh BS 5950: Part 4 currently recommends that anticrack mesh should comprise 0.1% of slab area. The Eurocode 4 recommendation is that anticrack mesh should comprise 0.2% of slab area for unpropped spans and 0.4% of slab area for propped spans. PMF in conjunction with the Steel Construction Institute has agreed to modify the requirement with regard to anti-crack mesh, to comply with the Eurocode 4 recommendations. Accordingly, the mesh shown in the quick reference tables complies with EC4 and the design program defaults to these values. Where EC4 mesh rules are used, the mesh may be reduced midspan - see Design Information on page 42. The reduced BS mesh values may still be used by overriding this default in the design program. Mesh top cover must be a minimum of 15mm, and a maximum of 30mm. Mesh laps are to be 300mm for A142 mesh and 400mm for A193, A252 & A393 mesh. Technical services PMF Technical Department offer a comprehensive advisory service on design of composite flooring, which is available to all specifiers and users. Should queries arise which are not covered by this literature or by the design CD, please contact us. Composite Floor Decks 33
36 ComFlor 210 ComFlor 210 Normal weight concrete - quick reference tables ComFlor 210 Span table - Normal weight Concrete MAXIMUM SPAN (m) Total Applied Load (kn/m 2 ) Props Span Fire Slab Mesh 3.5kN/m 2 5kN/m 2 10kN/m 2 Rating Depth Bar Size (mm) (mm) No Temporary props 1 Line of Temporary props 2 Lines of Temporary props 280 A hr 300 A A Simple 290 A span 1.5 hr 300 A slab 350 A A hr 350 A A A hr 300 A xA Simple 290 A span 1.5 hr 300 A slab 350 2xA A hr 350 2xA xA A hr 300 A xA Continuous 290 A span 1.5 hr 300 A slab 350 2x A A hr 350 2xA xA A hr 300 A xA Simple 290 A span 1.5 hr 300 A slab 350 2x A A hr 350 2xA xA A hr 300 A xA Continuous 290 A span 1.5 hr 300 A slab 350 2x A A hr 350 2xA xA Parameters assumed for quick reference span tables Mesh Spans Deck Bearing width Prop width Deflection Deflection See notes on previous page. Measured centre to centre of supports. Standard deck material specification (see previous page). The width of the support is assumed to be 200mm. Assumed to be 100mm. Construction stage L/130 or 30mm (ponding has been taken into account). Composite stage L/350. Concrete grade The concrete is assumed to be Grade 35 with a maximum aggregate size of 20mm. The wet weight of concrete is taken to be normal weight 2400kg/m 3 and lightweight 1900 kg/m 3. The modular ratio is 10 for normal weight and 15 for lightweight concrete. Construction load Refer to page 41 for details. No allowance is made for heaping of concrete during the casting operation. 34 Composite Floor Decks
37 ComFlor 210 ComFlor 210 Lightweight concrete - quick reference tables ComFlor 210 Span table - Lightweight Concrete MAXIMUM SPAN (m) Total Applied Load (kn/m 2 ) Props Span Fire Slab Mesh 3.5kN/m 2 5kN/m 2 10kN/m 2 Rating Depth Bar Size (mm) (mm) No Temporary props 1 Line of Temporary props 2 Lines of Temporary props 270 A hr 300 A A Simple 280 A span 1.5 hr 300 A slab 350 A A hr 350 A A A hr 300 A xA Simple 280 A span 1.5 hr 300 A slab 350 2xA A hr 350 2xA xA A hr 300 A xA Continuous 280 A span 1.5 hr 300 A slab 350 2x A A hr 350 2xA xA A hr 300 A xA Simple 280 A span 1.5 hr 300 A slab 350 2x A A hr 350 2xA xA A hr 300 A xA Continuous 280 A span 1.5 hr 300 A slab 350 2x A A hr 350 2xA xA Bar reinforcement End Anchorage for bar reinforcement. All cases require properly anchored L-bars at the supports, except for those boxed in red. Cases boxed in red may have straight bars, with an anchorage length of 70mm from the edge of the support. See Design Notes on page 42 for further information. One bar is placed in each profile trough, the cover to deck soffit is assumed at 70mm. Fire Span/depth ratio The Fire Engineering method (FE) has been used to calculate the reinforcement needed to achieve the fire rating. The minimum slab thickness indicated in each table for each fire rating satisfies the fire insulation requirements of BS 5950 : Part 8. This is limited to 30 for lightweight concrete and 35 for normal weight concrete. Composite Floor Decks 35
38 SD 225 SD From the PMF Deep Composite Profile Range SD 225 is the latest addition to PMF s flooring range. Developed specifically for Corus Slimdek system, SD225 offers up to 6.5 metres unpropped span. Corus Slimdek engineered flooring solution is a unique structural floor system which uses Asymmetric SlimFlor Beams, where the bottom flange is wider than the top flange. The SD225 steel deck bears on the lower flange of the beam which results in a minimal overall floor depth, the concrete that surrounds the beam provides composite action without the need for shear studs, and fire protection to the beam. The Slimdek system is fast, eliminates temporary props, is structurally optimized and saves on cladding costs. The system also reduces building height or enables extra floors to be built. SD 225 deck is a state of the art cold formed profile design offering fully optimized composite and load carrying characteristics. The re-entrant section to the top flange of the profile enhances composite action and offers easy services attachment. The deck is designed to offer flexible service integration (as described in Steel Construction Institute publication Service Integration in Slimdek ). Up to 2 hours fire rating with unprotected soffit. 36 Composite Floor Decks
39 SD 225 SD 225 Design information Full design program on CD (inside back page) ComFlor 225 Composite Slab - Volume & Weight Weight of Concrete (kn/m 2 Concrete Slab Depth volume Normal weight Concrete Lightweight Concrete (mm) (m 3 /m 2 ) Wet Dry Wet Dry Volume & weight table notes 1. Deck and beam deflection (i.e. ponding is not allowed for in the table. 2. Deck and mesh weight is not included in the weight of concrete figures. 3. Density of concrete is taken as: Normal weight (wet) 2400 kg/m 2 Normal weight (dry) 2350 kg/m 2 Lightweight (wet) 1900 kg/m 2 Lightweight (dry) 1800 kg/m 2 Section Properties (per metre width) Nominal Design Height to Moment of Ultimate Moment capacity thickness thickness Profile weight Area of steel neutral axis inertia (knm/m) (mm) (mm) (kn/m 2 ) (mm 2 /m) (mm) (cm 4 /m) Sagging Hogging Design Notes Deck material Zinc coated steel to BS EN 10147:1992, Fe E 350G, Z275, with a guaranteed minimum yield stress of 280 N/mm 2. Minimum zinc coating mass is 275 g/m 2 total including both sides. Quick reference tables The quick reference load/span and fire design tables, on the following 2 pages are intended as a guide for initial design, based on the parameters stated below the tables. The PMF calculation suite contained on the CD at the back of this literature provides a full design program. Please refer to page 56 for help in using the software. Anti-crack mesh BS 5950: Part 4 currently recommends that anticrack mesh should comprise 0.1% of slab area. The Eurocode 4 recommendation is that anticrack mesh should comprise 0.2% of slab area for unpropped spans and 0.4% of slab area for propped spans. PMF in conjunction with The Steel Construction Institute has agreed to modify the requirement with regard to anti-crack mesh, to comply with the Eurocode 4 recommendations. Accordingly, the mesh shown in the quick reference tables complies with EC4 and the design program defaults to these values. Where EC4 mesh rules are used, the mesh may be reduced midspan - see Design Information on page 42. The reduced BS mesh values may still be used by overriding this default in the design program. Mesh top cover must be a minimum of 15mm, and a maximum of 30mm. Mesh laps are to be 300mm for A142 mesh and 400mm for A193, A252 & A393 mesh. Technical services PMF Technical Department offer a comprehensive advisory service on design of composite flooring, which is available to all specifiers and users. Should queries arise which are not covered by this literature or by the design CD, please contact us. Composite Floor Decks 37
40 SD 225 SD 225 Normal weight concrete - quick reference tables SD 225 Span table - Normal weight Concrete MAXIMUM SPAN (m) Total Applied Load (kn/m 2 ) Props Span Fire Slab Mesh 3.5kN/m 2 5kN/m 2 10kN/m 2 Rating Depth Bar Size (mm) (mm) No Temporary props 1 Line of Temporary props 2 Lines of Temporary props 295 A hr 320 A A A Simple 1.5 hr 320 A span slab 350 A A hr 350 A A A hr 320 A xA A Simple 1.5 hr 320 A span slab 350 2xA A hr 350 2xA xA A hr 320 A xA Continuous 305 A hr 320 A Slab 350 2xA A hr 350 2xA xA A hr 320 A xA A Simple 1.5 hr 320 A span slab 350 2xA A hr 350 2xA xA A hr 320 A xA Continuous 305 A hr 320 A Slab 350 2xA A hr 350 2xA xA Parameters assumed for quick reference span tables Mesh Spans Deck Bearing width Prop width Deflection Deflection See notes on previous page. Measured centre to centre of supports. Standard deck material specification (see previous page). The width of the support is assumed to be 200mm. Assumed to be 100mm. Construction stage L/130 or 30mm (ponding has been taken into account). Composite stage L/350. Concrete grade The concrete is assumed to be Grade 35 with a maximum aggregate size of 20mm. The wet weight of concrete is taken to be normal weight 2400kg/m 3 and lightweight 1900 kg/m 3. The modular ratio is 10 for normal weight and 15 for lightweight concrete. Construction load Refer to page 41 for details. No allowance is made for heaping of concrete during the casting operation. See design notes. 38 Composite Floor Decks
41 SD 225 SD 225 Lightweight concrete - quick reference tables SD 225 Span table - Lightweight Concrete MAXIMUM SPAN (m) Total Applied Load (kn/m 2 ) Props Span Fire Slab Mesh 3.5kN/m 2 5kN/m 2 10kN/m 2 Rating Depth Bar Size (mm) (mm) No Temporary props 1 Line of Temporary props 2 Lines of Temporary props 285 A hr 320 A A A Simple 1.5 hr 320 A span slab 350 A A hr 350 A A A hr 320 A xA A Simple 1.5 hr 320 A span slab 350 2xA A hr 350 2xA xA A hr 320 A xA Continuous 1.5 hr 295 A A Slab 350 2x A A hr 350 2xA xA A hr 320 A xA A Simple 1.5 hr 320 A span slab 350 2x A A hr 350 2xA xA A hr 320 A xA Continuous 1.5 hr 295 A A Slab 350 2x A A hr 350 2xA xA Bar reinforcement End Anchorage for bar reinforcement. All cases require properly anchored L-bars at the supports, except for those boxed in red. Cases boxed in red may have straight bars, with an anchorage length of 70mm from the edge of the support. See Design Notes on page 42 for further information. One bar is placed in each profile trough, the cover to deck soffit is assumed at 70mm. Fire Span/depth ratio The Fire Engineering method (FE) has been used to calculate the reinforcement needed to achieve the fire rating. The minimum slab thickness indicated in each table for each fire rating satisfies the fire insulation requirements of BS 5950 : Part 8. This is limited to 30 for lightweight concrete and 35 for normal weight concrete. Composite Floor Decks 39
42 Design Information Deep Composite Floor Decks -Design information Deep Composite Floor Decks will be considered where longer span (4m plus) floor slabs are required. When combined with Corus Slimdek system, deep decks are designed to achieve a very shallow overall structural floor-hence the term Slim Floor Construction. Deep Composite Floor Decks PMF Deep Composite Floor Decks will be used in one of these applications: 1 Corus Slimdek system. 2 Long span composite concrete/steel floor deck in composite steel construction. 3 Long span composite concrete/steel floor deck in masonry construction. The design considerations relating to the decking are similar for all these applications. Corus Slimdek System The most recent slim floor development produced by Corus is the Slimdek system. This system comprises Asymmetric Slimflor beams and deep SD225 decking. Asymmetric Slimflor Beam (ASB), which is a hot rolled section with a narrower top flange than bottom flange. The principle of Slimdek is that the steel deck (and thus the composite concrete slab) bears on the lower flange of the beam, thus containing the beam within the floor slab. Three different types of Slimflor beam are produced: Slimflor Fabricated Beam (SFB), which is a Universal Column section with a wide flange plate welded to its underside. Rectangular Hollow Slimflor Beam (RHSFB), which is a rectangular hollow section with a flange plate welded to its lower face (generally used for edge beams). 40 Composite Floor Decks
43 Design Information Deep Composite Floor Decks -Design information Slimdek Design Procedure There are two distinct stages for which the elements of the Slimdek system must be designed. The first is the construction stage, during which the beams and decking support the loads as non-composite sections. The second is the final stage, during which the decking and concrete act together to form composite slabs, as do (generally) the ASBs and slab. SFBs and RHSFBs will act compositely if shear studs have been provided. The key design points are: Consideration of the required spans will allow the depth of the beams to be determined. Construction load 1.5 kn/m 2 x 1.6 Self weight x 1.4 3m Clear span m Loading on deep decking at Construction stage. Reduced construction load 0.75 kn/m 2 x 1.6 Consideration of the required fire resistance will allow the depth of slab to be determined, as a function of the cover required for the beams and the decking. Having established these scheme design parameters, detailed design of the beams and slab can be undertaken. The following slab depths should be considered as typical: 280 ASB sections mm deep slab 300 ASB sections mm deep slab. These depths will provide adequate cover to the ASB for it to act compositely with the slab. For SFBs a greater range of slab depths may be considered for a given depth of beam; the slab depth requirement will depend on whether shear studs must be accommodated to make the SFB act compositely. Slimdek Beam Design The design of the beams in the Slimdek system is presented in The Corus Slimdek Manual and Design Software which is available from Corus Construction Centre Further detailed design information is available in The Steel Construction Institute publications: P300 Composite Slabs and Beams Using Steel Decking: Best Practice for Design and Construction, P055 Design of Composite Slabs and Beams with Steel Decking. Please see references section for further information. Decking Design In addition to considering the self-weight of the slab, the design of the deep decking should take into account temporary construction loads. These construction loads differ slightly from those that should be considered for shallow decking, because of the considerably greater spans that can be achieved with deep decking. Construction Stage Loading The 1.5 kn/m 2 construction load required by BS should only be applied over the middle 3m of the span, as shown above. A reduced load of 0.75 kn/m 2 (as specified in EC4) may be applied outside this region, as it would be overly conservative to apply the full load of 1.5kN/m 2 over the entire span. The effect of concrete ponding should be taken into account (by increasing the self weight of the slab) if the deflection under self-weight alone exceeds the lesser of span/180 or 20mm. If temporary props are used to support the decking during construction, a construction load of 1.5 kn/m2 should be considered as acting over the complete span (between permanent supports). Although a lower value might be justifiable over parts of the span, a constant load should be considered for design simplicity. Temporary propping (when required) The spacing of temporary props is governed by the ability of the decking to resist combined bending and shear in the hogging (negative) moment regions over the lines of props. It is recommended that the spacing between the props should be relatively close, so that local loads do not cause damage to the decking (2.5m to 3.5m spacing depending on the slab weight). A 100 mm wide timber bearer should be used to distribute the load at these points. End Bearing The end bearing of the sheets should be specified as 50 mm. The flange widths are such that this bearing can be achieved, whilst still allowing the sheets to be dropped vertically into position (i.e. without having to thread them between the top and bottom flanges). Composite Floor Decks 41
44 Design Information Deep Composite Floor Decks -Design information Slab Design The design of composite slabs using deep decking differs from that for shallow decking in the following ways: Placing bar reinforcement in the troughs of the decking increases the ultimate load resistance of the slab. The benefit of these bars is considered in both the normal and fire conditions. The slab depth may need to be chosen not only to satisfy the structural, durability and fire resistance requirements of the slab itself, but also to provide appropriate cover over ASB or Slimflor beams. The reinforcing bars in the troughs of the decking provide additional tensile area to that provided by the decking, and thus enhance the bending resistance of the composite slab. Bar diameters range from 8 mm to 32 mm, depending on the span and fire resistance requirements. Vertical reaction Support Slip between deck and concrete Longitudinal shear bond Straight bars may be used to achieve 60 minutes fire resistance (provided that shear stresses are low). In other cases, L bars should be used to provide sufficient end anchorage in fire conditions. Cracking It is normal for some cracking to occur in the slab over the beams. These cracks run parallel with the beams and are not detrimental to the structural behaviour of the slab. They may be controlled by mesh reinforcement provided across the tops of the beams. Guidance on the detailing of reinforcement to control cracking may be found in the Corus Slimdek manual. Additional reinforcement may be required to fulfil the following roles: Transverse reinforcement adjacent to shear connectors. U-bars at composite edge beams. Additional crack control reinforcements Strengthening around openings. Strengthening at positions of concentrated loads. Bar reinforcement Action of composite slab with reinforcement in ribs. ø L Mid span Stress distribution Concrete in compression Tension in decking and bar reinforcement Fire Resistance Concrete thickness above deck Fire resistance NWC LWC 60min 70mm 60mm 90min 80mm 70mm 120min 95mm 80mm One of the principal considerations governing the choice of slab depth is the required fire resistance period. Minimum depths are given above as a function of the concrete type and fire resistance required and are based on insulation requirements. The Fire Engineering Method: The capacity assessment in fire is based on a single or double layer of standard mesh at the top and one bar in each concrete rib. For CF210 or SD 225 decking, the bar is placed at an axis distance, dependent on the fire resistance period. The axis distance must not be less than 70mm. To maximise fire resistance capacity the axis distance needs to be 70, 90 and 120mm (from the soffit of the deck) for 60, 90 and 120 mins. fire resistance, respectively. However where fire resistance is not the limiting factor it may be more effective for the axis distance to be at the minimum. Reduced Mesh Where EC4 mesh rules are used, as recommended by The Steel Construction Institute and PMF, the full stipulated mesh applies to the slab 1.2m either side of every support. Outside of this, i.e. in the midspan area, the mesh area may be halved (to 0.2% for propped and 0.1% for unpropped construction), provided there are no concentrated loads, openings etc. to be considered. Also the reduced midspan mesh must be checked for adequacy under fire, for the rating required. 1.2m 1.2m 1.2m 1.2m 12ø L 25 ø L Support Beam Support Beam Support Beam 100mm 100mm 50ø L Diagram showing full mesh area over supports Detailing requirements for deep composite slabs (need for L bars depends on level of shear stress). 42 Composite Floor Decks
45 Design Information Deep Composite Floor Decks -Design information Vibration The dynamic sensitivity of the composite slab should be checked in accordance with the SCI publication P076: Design guide on the vibration of floors. The natural frequency is calculated using the self-weight of the slab, ceiling and services, screed and 10% imposed loads, representing the permanent loads and the floor self weight. In the absence of more appropriate information, the natural frequency of the composite slab should not exceed 5Hz for normal office, industrial or domestic usage. For designs using SD225 or CF210 decking, this limit may be reduced to 4Hz if the design has been carried out on the assumption of simple supports at the ends. Conversely, for dance floor type applications or for floors supporting sensitive machinery, the limit may need to be set higher. In the Slimdek system, consideration should be given to the system frequency of the floor as a whole if the natural frequency of the slab and/or the supporting beam is less than 5Hz. For design to the Eurocodes, the loads considered for the vibration check are increased using the psi-factor for imposed loads (typically 0.5). The natural frequency limit may be reduced to 4Hz, because of this higher load used in the calculation. Partial Continuity Partial continuity for deep decking: Tests have shown that the SD 225 or CF210 composite slabs supported on a steel beam and provided with adequately detailed continuity mesh reinforcement over the steel beam support exhibits a degree of continuity at the support. The beneficial effect of partial continuity at the supports may be taken into account by specifying CONTINUOUS in the Span Type field. When this option is specified, the following assumptions are made by the design software; a 20% reduction in the deflections of the composite slab at the normal design stage. a 30% reduction in the deflections when assessing the natural frequency of the slab. This is justified by the lower stress levels during vibration. In this case, the amount of mesh reinforcement is increased to a minimum of 0.4% of the cross-sectional area of the concrete topping in order to develop sufficient continuity in the slab. Note that in all cases, partial continuity is ignored in assessing the capacity of the composite slab at the normal design stage. Service Attachments The SD225 decking facilitates the fixing of services and suspended ceilings. Hangars can be used to support services running either parallel or perpendicular to the decking span. Special Lindapter fixing clips can achieve a safe working load of 1kN per fixing. These allow service pipes to be suspended directly from the decking between the ribs. Alternatively, selfdrilling self-tapping screws may be used to attach hangers to the decking after the concrete has been placed. Openings in the Slab Provision for vertical service openings within the floor slab will necessitate careful design and planning. The following summarises the options that are available to the designer: Openings up to 300 mm x 300 mm can be accommodated anywhere in the slab over a crest section of the deck, normally without needing additional reinforcement. Openings up to 400 mm wide x 1000 mm long may be taken through the crest of the deep decking. Additional reinforcement, which should be designed in accordance with BS 8110, may be required around the opening. Openings up to 1000 mm wide x 2000 mm long may be accommodated by removing one rib (maximum) of the decking, fixing suitable edge trims and providing additional reinforcement to transfer forces from the discontinuous rib. The slab should be designed as a ribbed slab in accordance with BS 8110, with decking being used as permanent formwork. Guidance may be found in the Corus Slimdek Manual. Opening up to 1000mm T12 bar x 1500 long Opening Centre-line of ribs ASB beam 300 Minimum A142 mesh throughout ASB beam Design of small and medium size openings in the slab If an opening greater than 300 mm x 300 mm lies within the effective width of slab adjacent to a beam (L/8), the beam should be designed as non-composite. A close grouping of penetrations transverse to the span direction of the decking should be treated as a single large opening. Service Integration The Slimdek system offers considerable opportunity for the integration of services. This is covered in detail in Corus Construction Centre publication Slimdek - Structure and services integration. stresses in the composite slab in fire conditions are derived from a model which assumes full continuity at one end and a simple support at the other (i.e a propped cantilever condition). Larger openings will generally require trimming by secondary beams. Composite Floor Decks 43
46 Construction Details Deep Composite Floor Decks - Construction Details End fixing onto ASB Notch in decking on beam side of diaphragm to allow viewing of concrete around the beam and to allow easy handling of the deck in the construction stage Asymmetric SlimFlor Beam Beam centres SD225 End diaphragm SD225 Floor Decking with 50mm minimum bearing onto Asymmetric Beam 72mm for 280ASB100 75mm for 280ASB136 and 300ASB mm min Side fixing onto ASB Beam centres Asymmetric SlimFlor Beam SD225 Floor Decking to extend to edge trim 20 mm min Perimeter with trim Cut plates 100 min Beam centres Beam centres Restraint strap at 600mm centres Edge trim SD225 Floor Decking SD225 Floor Decking 150 max 50 mm min Asymmetric SlimFlor Beam Asymmetric SlimFlor Beam Closure plate (CP153 etc) 2mm flat steel plate size to suit remainder of floor area (maximum 245mm wide) 44 Composite Floor Decks
47 Deep Composite Floor Decks - Construction Details Construction Details Cut deck - Option 1 Cut deck - Option 2 Beam centres 100 min SD225 Deck cut along top section only 100 min Beam centres SD225 Deck cut along top section only Asymmetric SlimFlor Beam Closure flashing Asymmetric SlimFlor Beam Closure flashing Cut deck - Option 3 Beam centres 100 min Asymmetric SlimFlor Beam SD225 Deck cut along top section only Closure flashing Unsupported edge Unsupported edge with closure flashing Restraint strap Edge trim Edge trim Restraint strap at 600 mm centres Reinforcement as specified Closure flashing Reinforcement as specified Temporary props required for spans greater than 500mm 100 min Temporary prop Composite Floor Decks 45
48 Construction Details Deep Composite Floor Decks - Construction Details Steel trims Slab depth (150 max) 90 (150 max) 50 min (steel) 75 min (blockwork) Notations used on deck layout drawing Number of sheets Floor level Phase Bundle number Decking lengths Span of decking Z2 94 Prop decking in this area Side of decking run that requires Z flashing Distance from centreline of tie member to sop of first decking sheet End fixing onto RHS Side fixing onto RHS Beam centres SD225 End diaphragm 30 Beam centres 600 Deck s.o.p. RHS with steel plate (300x200 RHS shown here) 75 SD225 Floor Decking with mm minimum bearing onto steelwork 100 SD225 Floor Decking 46 Composite Floor Decks
49 Construction Details Deep Composite Floor Decks - Construction Details End fixing onto blockwork 75 min Restraint strap Construction dimension Edge trim with 75mm bottom leg (min) to be fixed before decking sheet is laid SD225 End diaphragm Blockwall width SD225 Floor Decking with 100mm bearing (75 min) Side fixing onto blockwork Restraint strap at 600mm centres A minimum gap of 100mm is required to allow fixing Edge trim with 75mm bottom leg (min) to be fixed before decking sheet is laid Blockwall width 75 SD225 Floor Decking Construction dimension Cut Plate on Blockwork 75 min Construction dimension Restraint strap at 600mm centres Edge trim with 75mm bottom leg (min) to be fixed before decking sheet is laid Blockwall width SD225 Floor Decking CP245 flat plate Z flashing or decking sheet which must have sufficient bearing for a blockwork fixing Maximum flat plate width is 245 mm Composite Floor Decks 47
50 Sitework Deep Composite Floor Decks - Sitework End Diaphragms Steel end diaphragms, as manufactured by PMF, are essential for both deep deck systems to ensure the structural integrity of the deck. The end diaphragms, are fixed first and are supplied in lengths of 1800 mm, to cover three PMF deep deck profiles. They are fixed using at least two shot-fired pins for each length; in the Slimdek system the end diaphragms align with the edge of the lower flange of the beam. Single diaphragms are available with prepunched service holes in two types. Type 1 has one 160mm diameter hole; Type 2 has one elongated 160mm diameter hole to make opening 320mm wide x 160mm high. Unpunched single diaphragms are also available. Where the deep deck lands onto a support at a rake, the single diaphragms are used doubled up, and adjusted on site to take up the extra length required due to the fact that the end of the deck is at a raked angle to the support rather than at right angles. The concrete that the diaphragms entrap around the Asymmetric Slimflor Beam, give the beam its fire rating, therefore the diaphragms must be placed strictly according to specification. End diaphragm for SD225 End diaphragm for ComFlor 210 Deck Fixing The decking sheets are then manually lowered individually onto the beams. In the Slimdek system, the end bearing of the sheets should be 50 mm; the flange widths are such that this can be achieved, whilst still being able to drop the sheets vertically into position (i.e. without having to thread them between the top and bottom flanges). Once the sheets for the whole bay are in place, they are secured to the beam flanges using heavy duty shot-fired fixings. The required number of main fixings for SD225 is two per trough, one on both sides of the centre dovetail section. CF 210 requires one main fixing per trough. Where CF210 deck is being used with Asymmetric SlimFlor Beams, the top flange of the profile must be notched back by 50mm, so that the concrete can be observed passing between the end diaphragm and the beam to allow concrete to flow into the beam. (SD225 is supplied pre-punched). The crown of the deck sheet is fixed to the top of the diaphragms using two self drilling screws for SD225, or one self drilling screw for CF210. When fixing to other types of supports such as reinforced concrete, or load bearing walls, 2 suitable fixings must be used in each SD225 trough (one per CF210 trough), as for the steel supports. To Steel To Masonry or Concrete To side laps or closures etc. Telephone numbers of fixings suppliers EJOT Hilti Lindapter SFS Spit FIXING INFORMATION FOR DEEP DECKING Heavy duty powder actuated fixings - Hilti ENP2 nail/spit SBR14 or equivalent Self-drilling screws. To steel up to 11mm thick - SFS SD x 32 / EJOT HS 38 or equivalent. To steel up to 17mm thick SFS TDC-T-6.3 x 38 or equivalent Pre drill hole - use self tapping fixing suitable for masonry/ concrete - SFS TB-T range / EJOT 4H32 or equivalent Self drilling stitching screw typically SFS SL range / EJOT SF25 or equivalent FIXING SPACINGS SD225 ComFlor 210 End fixing 2 per trough 1 per trough Side laps 1 fixing through top flat of 1 fixing with shear clip at small dovetail at 1000mm c/c 350mm c/c Side fixing 1 fixing at 600mm c/c 1 fixing at 600mm c/c onto support 48 Composite Floor Decks
51 Deep Composite Floor Decks - Sitework Sitework Fixing of Comflor heavy duty shot fired pin per trough for fixing into steelwork End diaphragm End diaphragm Side laps stitched at 350mm centres including trough shearbond clip View from above 1 heavy duty shot fired pin per trough for fixing into steelwork Deck top Beam top Side Laps The SD225 dovetail shaped side lap detail offers a positive interlock and once engaged should be stitched using self drilling fasteners through the top flat of the dovetail at 1000mm centres. With both profiles, where the first and last sheet lands on a support, the edge of the sheet must be fixed to the support at 600mm centres. CF210 side laps are to be stitched at 350mm centres with 5.5mm diameter self drilling screw, the location is marked by an indentation in the overlap tail. Every side lap fastener must fix and locate a trough shear connector clip into position. The clip is partly responsible for the composite action of the decking and must not be omitted unless the CF210 is being used as formwork only. ComFlor 210 shear clip Composite Floor Decks 49
52 Sitework Deep Composite Floor Decks - Sitework Edge Details The steelwork must be stable and adequately restrained with support for the deck around columns and openings. The PMF deep decking can be easily cut, and fitted, to accommodate columns and other awkward shapes. Where there is no supporting steelwork, brackets fixed to the column will have to be used for local support to the deck. Fit restraint straps at 600mm c/c to prevent any bowing of edge trim. Light steel edge trim is used to form the edges of the slab and to infill where the 600 mm profile of the deck does not align with the parallel supports. Supplied in 3m lengths as standard, and offered in thickness of 1.2 mm to 2.0 mm, the edge trims are fixed to the perimeter steel beams, using the same shot fired fasteners that secure the deck. The upper leg is strapped to the crown of the profile, to prevent buckling during the concrete pouring operation. Cantilevers PMF deep decks can be Cantilevered in its length up to 500 mm during construction. When Cantilevers are required perpendicular to the span of the profile, stub beams or some similar type of support has to be supplied. In both cases, the Cantilever must be assessed, for the final stage, in accordance with BS8110 Part 1, to determine whether additional reinforcement is required. Edge trim depth (mm) Edge trims selector Maximum Cantilever (mm) Galv. Steel Edge trim thickness (mm) x x 0 x = not recommended Reinforcement The decking forms a part of the slab reinforcement, with the remainder being supplied by a bar in each trough of the decking and a mesh placed near to the top of the slab. Reinforcement should be fixed in accordance with the requirements of the Structural Designer. Normally, circular plastic spacers are used to position the bars 70 mm from the base of the trough. This distance can increase to 90 or 120 mm (respectively) when 90 or 120 minutes fire resistance are required. There may be additional mesh or bar requirements to fix adjacent to the supports or edge beams, or above beams for crack control purposes. Any shear studs that are required (to make SFBs or RHSFBs composite) may be welded to these sections during fabrication, because they do not interfere with the decking. If they are to be welded on site, the precautions and procedures outlined on page 28 should be considered. 50 Composite Floor Decks
53 Deep Composite Floor Decks - Sitework Sitework Temporary Props In instances when the design spans exceed the construction stage capacity of the decking, it is necessary to support the weight of the wet concrete and construction loads, by using additional temporary supports. The supports should offer a continuous bearing of at least 100 mm width to the underside of the deck. where temporary supports are used it is important that: The timbers and supports are of adequate strength. The props are placed at mid-span, or at third span, as required. The propping structure is not to be removed until the concrete has achieved 75% of its design strength. The horizontal bearer timbers must be at least 100mm wide and should be propped at no more than 1m centres. Sometimes the specification may call for 150mm wide bearers. TEMPORARY PROPS Timber Bearer Guide (deep decks) All to be min. 100mm wide Slab Depth Bearer Depth (mm) (mm) Penetrations Openings should be made through the wide crown of the profile. The openings should be boxed out prior to the pouring of the concrete, and the metal of the deck only cut once the concrete has achieved 75% of its design strength. Casting Concrete All grease, dirt and debris, which could have an adverse effect upon the performance of the cured slab, must be cleared before the application of the concrete can commence. The deck may have some lubricant from the roll forming process on its surface. This does not have to be removed. Care should be taken during the application of the concrete, to avoid heaping, and the close working of unnecessarily large number of operatives. Unsupported Edges All unsupported edges must be propped, and may require additional reinforcement. Timber shutter for opening Dense polystyrene block for opening Temporary support using an Acrow type prop Composite Floor Decks 51
54 Formwork Formwork (non-composite) PMF Permanent Formwork Profile Range PMF manufacture a range of five profiles which are used as permanent formwork. Permanent formwork remains in situ for the life of the building but, unlike composite flooring profiles, it does not act as reinforcement in the concrete slab. The steel decking supports the wet concrete and construction loads. Temporary propping can be eliminated. The concrete slab requires full structural bar or mesh reinforcement. The wide range of PMF formwork profiles ensure the optimum solution is available. Maximum Spans of Permanent Single or Double span Profile Steel Thickness Profile weight 100mm 150mm 200mm 250mm (mm) (kn/m 2 ) F32S F35 F46 F60 F Construction Details These are similar to shallow composite flooring. Refer to pages Sitework This is similar to shallow composite flooring. Refer to pages Mesh Concrete Reinforcement Formwork Concrete Slab Depth Profile Height Concrete Usage Table Weight of Concrete (kn/m 2 ) Profile Slab Depth above profile (mm) ED (mm) 100mm 150mm 250mm F32S F F F F To determine concrete usage increase slab depth above profile by ED mm. 52 Composite Floor Decks
55 Formwork Formwork (non-composite) PMF Permanent Formwork Profile Range F32S Cover width 960 F Cover width 900 F Cover width 900 F Cover width 800 F Cover width 700 Composite Floor Decks 53
56 Reference Transport & Handling For general information on Transport, Handling and Storage, refer to the relevant Corus PMF leaflet, contained within the main ring binder. Information of particular interest to Composite Flooring Contractors is given below. Receiving Decking Composite Floor Decking is packed into bundles of up to 24 sheets, and the sheets are secured with metal banding. Each bundle may be up to 950mm wide (the overall width of a single sheet) by 750 mm deep, and may weigh up to 2.5 tonnes, depending on sheet length (average weight is about 1.5 tonnes). Loads are normally delivered by articulated lorries approximately 16 m long with a maximum gross weight of up to 40 tonnes, and a turning circle of approximately 19 m. The Main Contractor should ensure that there is suitable access and appropriate standing and off-loading areas. Each bundle has an identification tag. The information on each tag should be checked by operatives from the decking contractor (or, if they are not on site, the Main Contractor) immediately upon arrival. In particular, the stated sheet thickness should be checked against the requirement specified on the contract drawings, and a visual inspection should be made to ensure that there is no damage. Lifting Bundles The bundles should be lifted from the lorry. Bundles should never be off-loaded by tipping, dragging, dropping or other improvised means. Care is needed when lifting the decking bundles; protected chain slings are recommended. Unprotected chain slings can damage the bundle during lifting; when synthetic slings are used there is a risk of the severing them on the edges of the decking sheets. If timber packers are used, they should be secured to the bundle before lifting so that when the slings are released they do not fall to the ground (with potentially disastrous results). Bundles must never be lifted using the metal banding. Positioning the Decking The support steelwork should be prepared to receive the decking before lifting the bundles onto it. The top surface of the underlying beams should be reasonably clean. When thru-deck welding of shear studs is specified, the tops of the flanges should be free of paint or galvanising. The identification tags should be used to ensure that bundles are positioned on the frame at the correct floor level, and in the nominated bay shown on the deck layout drawing. The bundles should be positioned such that the interlocking side laps are on the same side. This will enable the decking to be laid progressively without the need to turn the sheets. The bundles should also be positioned in the correct span orientation, and not at 90 o to it. Care should be taken to ensure that the bundles are not upside down, particularly with trapezoidal profiles. The embossments should be oriented so that they project upwards. Placement of Decking The breaking open of bundles and installation of decking should only begin if all the sheets can be positioned and secured. This will require sufficient time and suitable weather. The decking layout drawing should also be checked to ensure that any temporary supports that need to be in position prior to deck laying are in place. Access for installation will normally be achieved using ladders connected to the steel frame. Once they have started laying out the sheets, the erectors will create their own working platform by securely fixing the decking as they progress. The laying of sheets should begin at the locations indicated on the decking layout drawings. These would normally be at the corner of the building at each level; to reduce the number of leading edges, i.e. unprotected edges, where the decking is being laid. When the bundles have been properly positioned, as noted above, there should be no need to turn the sheets manually, and there should be no doubt which way up the sheet should be fixed. Individual sheets should be slid into place and, where possible, fixed to the steelwork before moving onto the next sheet. This will minimise the risk of an accident occurring as a result of movement of a sheet when it is being used as a platform. (However, for setting-out purposes, it may be necessary to lay out an entire bay using a minimum number of temporary fixings before fully securing the sheets later). Sheets should be positioned to provide a minimum bearing of 50 mm on the steel support beams. The ends of adjacent sheets should be butted together. A gap of up to 5 mm is generally considered not to allow excessive seepage, but, if necessary, the ends of the sheets may be taped together. When end gaps are greater than 5 mm, it is normally sufficient to seal them with an expanding foam filler. The longitudinal edges should be overlapped, to minimise concrete seepage. Cutting Sheets Where necessary, sheets may be cut using a grinder or a nibbler. However, field cutting should be kept to a minimum and should only be necessary where a column or other obstruction interrupts the decking. Gaps adjacent to the webs of columns should be filled in with off-cuts or thin strips of steel. Decking sheets shown as continuous on the decking layout drawing should never be cut into more than one length. Also, sheets should never be severed at the location of a temporary support, and the decking should never be fastened to a temporary support. As the work progresses, unwanted scraps and off-cuts should be disposed of in a skip placed alongside the appropriate level of working. The skip should be positioned carefully over a support beam to avoid overloading the decking If a skip is not available, scraps should be gathered for collection by the Main Contractor as soon as is possible. Partially used bundles should be secured, to avoid individual sheets moving in strong winds. 54 Composite Floor Decks
57 Reference References - Health & Safety British Standards The design guidance given in this brochure and on the attached software complies, where relevant, with the following Standards. Composite Floor Deck 1. BS 5950: Part Structural use of steelwork in building: Code of practice for design of composite slabs with profiled steel sheeting. Composite Steel Beams 2. BS 5950: Part 3: Design in composite construction: Section 3.1: Code of practice for design of simple and continuous composite beams. Profiled Steel Deck 3. BS 5950: Part Structural use of steelwork in building: Code of practice for design of light gauge profiled steel sheeting. Fire Resistance 4. BS 5950: Part Structural use of steelwork in building: Code of practice for fire resistant design. Concrete 5. BS 8110: Part 1: 1997 Structural use of concrete: Code of practice for design and construction. 6. BS 8110: Part 2: 1985 Structural use of concrete: Code of practice for special circumstances. Reinforcement 7. BS 4483: 1998 Specification for steel fabric for the reinforcement of concrete. 8. BS4449:1997 Specification for carbon steel bars for the reinforcement of concrete. Eurocode 4 9. ENV : Design of steel structures. Supplementary rules for cold formed thin gauge members ans sheeting. 10. ENV : Design of Composite steel and concrete structures. General rules for building. 11. ENV : Design of composite steel and concrete structures. Structural fire design. 12. SCI - P : Design guide on the vibration of floors. SCI in association with CIRIA (1989). Health & Safety Handling Hazards Zinc coated steel decking should be handled with care; it may be delivered with soluble protective layer of oil, which can cause contamination to lacerated skin. Decking will have sharp edges and corners. Adequate gloves and protective clothing should be worn when handling decking. Eye Hazards Eye protectors conforming to the specification in BS 2092:1987 should always be worn, when breaking the strapping around bundles because the sudden release of tension creates a risk to eyes. Particles of metal also create eye hazards when cutting steel, and eye protection should be worn, during this activity. Noise Hazards Noise may be hazardous whilst handling or cutting decking, shot firing, etc, adequate ear defenders should be worn. Respiratory Hazards Fumes containing oxides of iron and zinc are produced during welding or flame cutting and if inhaled these may cause metal fume fever; this is a short-lasting condition with symptoms similar to those of influenza. In conditions of exposure to such hazards, the use of respiratory equipment is recommended. Explosives and Fumes When using shot fired fixings explosives and fumes may create a hazard. Occupational Exposure Limits Limits for iron and zinc oxides are 5g/m (8 hours TWA) and 10mg/m (10 minutes TWA). (OE recommendation) Summary of Protective Measures Wear adequate gloves and protective clothing and safety goggles. Ensure adequate ventilation and use personal protective equipment. Follow instructions for safe handling, use, disposal and control of cartridges issued by equipment supplier. Ensure adequate ventilation and / or use personal respiratory protective equipment. Use appropriate ear defenders or earplugs. General Safety Points Follow the good practice outlined here and in SCI publications. Always fix deck securely before using as a working platform. Steel end diaphragms, as manufactured by PMF, are essential for both deep deck systems to ensure the structural integrity of the deck. Rigorously employ all personal safety measures such as hard hats, protective clothing. Rigorously employ all site safety measures such as safety lines, edge protection, properly tied ladders. Don t leave any unfixed decking sheets. Don t heap concrete or drop from any height. Don t put heavy loads on unprotected deck. Don t place props on uncured concrete. Don t cut holes/voids in the deck prior to concreting. Composite Floor Decks 55
58 Reference Composite Floor Design Disc Use of the CD The Composite Floor Design disc is to be found opposite. If it is missing, PMF will send or a replacement version free of charge. Please note that the software will be updated from time to time without prior notice. The disc is for use on Windows based PCs and does not Auto-start. Place CD in drive, click Start - Run - Browse. When in CD drive, double click ComDek folder - setup. The software must be installed, i.e. will not run directly from the CD; it requires less than 2MB of disc space once installed. The program COMDEK was developed by the Steel Construction Institute for Corus PMF. Use of the design program Choose BS5950 or Eurocodes. All the variables start with a default value, however check or input new variables on both Datasheet1 and Datasheet2. When satisfied click analyse to run the calculations. Job details may be entered for a formal printout. It is not necessary to put in shear connectors (shear studs) for the composite slab design (shear connectors are used primarily for the benefit of the beam not the slab). However if shear connectors are to be used, then the design software allows end anchorage to be accounted for which in some cases will improve the load capacity of the composite slab. Before accepting a particular design as satisfactory, it is highly advisable to print out the calculations and check that all the input parameters are correct. Design criteria and methods The design program has been produced by the Steel Construction Institute on behalf of PMF. Help function on disc. The Help function on the design program contains all the detailed information that is used to produce the calculations. Hoofdkantoor ING Amsterdam; ASB ComFlor 100/ Composite Floor Decks
59
60 Whilst Precision Metal Forming have taken every care to ensure the accuracy of the information, data or advice contained in this brochure, no liability in respect of such information or advice whether given negligently or not, can be accepted by the company. Precision Metal Forming retain the right to amend the technical specifications of any range of profiles, coatings and colours shown without prior notice. Copyright 2002 Corus Designed by Plum Design & Advertising Ltd. Precision Metal Forming Severn Drive Tewkesbury Business Park Tewkesbury Gloucestershire GL20 8TX Tel: +44 (0) Fax: +44 (0) PMFCFD01:5000:UK:09/2002
Foreword. This manual provides technical information for designers and contractors to design and plan the construction operation.
Foreword Foreword This manual provides technical information for designers and contractors to design and plan the construction operation. The body of the manual is split into eight distinct sections: 1.
Eurocode 4: Design of composite steel and concrete structures
Eurocode 4: Design of composite steel and concrete structures Dr Stephen Hicks, Manager Structural Systems, Heavy Engineering Research Association, New Zealand Introduction BS EN 1994 (Eurocode 4) is the
DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia
DESIGN OF SLABS Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia Introduction Types of Slab Slabs are plate elements
Best Practice in Best Pra ctice in teel constr uction - onstr industrial B uildings esidential Buildings 01 Introduction 02 Key Design Factors
Best Practice in Steel Construction - Industrial Residential Buildings Contents The Steel Construction Institute (SCI) develops and promotes the effective use of steel in construction. It is an independent,
Structural Products. CI/SfB (23) Nh2 P356 August 2008
Structural Products CI/SfB (23) Nh2 P356 August 2008 Kingspan Toolkit Kingspan Multideck Design Software, for the analysis and design of composite slabs and the selection of the correct Multideck product,
COMPOSITE SLABS AND BEAMS USING STEEL DECKING: BEST PRACTICE FOR DESIGN AND CONSTRUCTION
cyan plate magenta plate yellow plate black plate MCRMA Technical Paper No. 13 SCI Publication P300 CI/SfB REVISED EDITION Composite Slabs and Beams Using Steel Decking: Best Practice for Design and Construction
Preliminary steel concrete composite bridge design charts for Eurocodes
Preliminary steel concrete composite bridge 90 Rachel Jones Senior Engineer Highways & Transportation Atkins David A Smith Regional Head of Bridge Engineering Highways & Transportation Atkins Abstract
DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,
DESIGN OF SLABS Dr. G. P. Chandradhara Professor of Civil Engineering S. J. College of Engineering Mysore 1. GENERAL A slab is a flat two dimensional planar structural element having thickness small compared
The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow.
9.2 One-way Slabs This section covers the following topics. Introduction Analysis and Design 9.2.1 Introduction Slabs are an important structural component where prestressing is applied. With increase
TABLE OF CONTENTS. Roof Decks 172 B, BA, BV Deck N, NA Deck. Form Decks 174.6 FD,.6 FDV Deck 1.0 FD, 1.0 FDV Deck 1.5 FD Deck 2.0 FD Deck 3.
Pages identified with the NMBS Logo as shown above, have been produced by NMBS to assist specifiers and consumers in the application of New Millennium Building Systems Deck products. Pages identified with
Contents. 01 Introduction 1. 02 Key Design Factors. 03 Floor Systems. 04 Special Floor Systems 27. 05 Beam Connections.
Best Practice in Steel Construction - Commercial Buildings Contents The Steel Construction Institute (SCI) develops and promotes the effective use of steel in construction. It is an independent, membership
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE
TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General
EN 1994 - Eurocode 4: Design of composite steel and concrete structures. Composite slabs
1 EN 1994 - Eurocode 4: Design of composite steel and concrete structures Composite slabs Stephen Hicks BEng(Hons), PhD(Cantab.) Senior Manager Building Engineering The Steel Construction Institute Silwood
Design Manual to BS8110
Design Manual to BS8110 February 2010 195 195 195 280 280 195 195 195 195 195 195 280 280 195 195 195 The specialist team at LinkStudPSR Limited have created this comprehensive Design Manual, to assist
Optimum proportions for the design of suspension bridge
Journal of Civil Engineering (IEB), 34 (1) (26) 1-14 Optimum proportions for the design of suspension bridge Tanvir Manzur and Alamgir Habib Department of Civil Engineering Bangladesh University of Engineering
Technical Notes 3B - Brick Masonry Section Properties May 1993
Technical Notes 3B - Brick Masonry Section Properties May 1993 Abstract: This Technical Notes is a design aid for the Building Code Requirements for Masonry Structures (ACI 530/ASCE 5/TMS 402-92) and Specifications
Formwork for Concrete
UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Formwork for Concrete Horizontal Formwork Design and Formwork Design
THE DEVELOPMENT OF DESIGN METHODS FOR REINFORCED AND UNREINFORCED MASONRY BASEMENT WALLS J.J. ROBERTS
THE DEVELOPMENT OF DESIGN METHODS FOR REINFORCED AND UNREINFORCED MASONRY BASEMENT WALLS J.J. ROBERTS Technical Innovation Consultancy Emeritus Professor of Civil Engineering Kingston University, London.
Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high.
CI/SfB Tn6 L6813 September 2013 RIW CAVITY DRAIN R20 R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high. Other systems are available for specific uses,
STEEL BUILDINGS IN EUROPE. Multi-Storey Steel Buildings Part 10: Guidance to developers of software for the design of composite beams
STEEL BUILDINGS IN EUROPE Multi-Storey Steel Buildings Part 10: Guidance to developers of software for the design of Multi-Storey Steel Buildings Part 10: Guidance to developers of software for the design
METHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
Detailing of Reinforcment in Concrete Structures
Chapter 8 Detailing of Reinforcment in Concrete Structures 8.1 Scope Provisions of Sec. 8.1 and 8.2 of Chapter 8 shall apply for detailing of reinforcement in reinforced concrete members, in general. For
SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems:
Reading Assignment SLAB DESIGN Chapter 9 of Text and, Chapter 13 of ACI318-02 Introduction ACI318 Code provides two design procedures for slab systems: 13.6.1 Direct Design Method (DDM) For slab systems
Design and Construction of Cantilevered Reinforced Concrete Structures
Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-68 Design and Construction of Cantilevered Reinforced Concrete Structures
Welded Fabric. The CARES Guide to Reinforcing Steels Part 5. Installation of welded fabric on a major contract. 1.0 Introduction
Welded Fabric 1.0 Introduction Welded fabric, often referred to as mesh, is a machine welded grid arrangement of reinforcing bars or wires. It is covered by British Standard BS4483. This was revised in
GRC Porticos. Lightweight entrance porticos ABBEY ARTSTONE
GRC Porticos Lightweight entrance porticos ABBEY ARTSTONE GRC Porticos Lightweight entrance porticos Abbey Artstone's range of lightweight products designed for the construction industry is the only range
Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig. 7.21 some of the trusses that are used in steel bridges
7.7 Truss bridges Fig. 7.21 some of the trusses that are used in steel bridges Truss Girders, lattice girders or open web girders are efficient and economical structural systems, since the members experience
5 Steel elements. 5.1 Structural design At present there are two British Standards devoted to the design of strucof tural steel elements:
5 Steel elements 5.1 Structural design At present there are two British Standards devoted to the design of strucof steelwork tural steel elements: BS 449 The use of structural steel in building. BS 5950
Optimising plate girder design
Optimising plate girder design NSCC29 R. Abspoel 1 1 Division of structural engineering, Delft University of Technology, Delft, The Netherlands ABSTRACT: In the design of steel plate girders a high degree
Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14
Draft Table of Contents Building Code Requirements for Structural Concrete and Commentary ACI 318-14 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE (ACI 318 14) Chapter 1 General 1.1 Scope of ACI 318
Fire and Concrete Structures
Fire and Concrete Structures Authors: David N. Bilow, P.E., S.E., Director, Engineered Structures, Portland Cement Association 5420 Old Orchard Road, Skokie, IL 60077,Phone 847-972-9064, email: [email protected]
1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona
for Earthen Material and Straw Bale Structures SECTION 70 - GENERAL "APPENDIX CHAPTER 7 - EARTHEN MATERIAL STRUCTURES 70. Purpose. The purpose of this chapter is to establish minimum standards of safety
16. Beam-and-Slab Design
ENDP311 Structural Concrete Design 16. Beam-and-Slab Design Beam-and-Slab System How does the slab work? L- beams and T- beams Holding beam and slab together University of Western Australia School of Civil
Introduction. Eurocodes. Specification. Cost
Introduction Eurocodes Specification Cost Structural Eurocodes BS EN 1990 (EC0): BS EN 1991 (EC1): Basis of structural design Actions on Structures BS EN 1992 (EC2): BS EN 1993 (EC3): BS EN 1994 (EC4):
PART 1 GENERAL 1.1 SECTION INCLUDES
J-1 Section 09110 Long Form Specification INTERIOR METAL STUD FRAMING This section includes lightweight, usually 0.036 inch (0.9 mm) thick or lighter, non-axial load bearing metal stud framing including
ENGINEERING SCIENCE H1 OUTCOME 1 - TUTORIAL 3 BENDING MOMENTS EDEXCEL HNC/D ENGINEERING SCIENCE LEVEL 4 H1 FORMERLY UNIT 21718P
ENGINEERING SCIENCE H1 OUTCOME 1 - TUTORIAL 3 BENDING MOMENTS EDEXCEL HNC/D ENGINEERING SCIENCE LEVEL 4 H1 FORMERLY UNIT 21718P This material is duplicated in the Mechanical Principles module H2 and those
Timber Decks. Technical Note. March 2007
Timber Decks Technical Note. March 2007 This Technical Note contains general information for residential timber decks and floor frame structures for veranda s, patios etc which are exposed to the weather.
SEISMIC DESIGN. Various building codes consider the following categories for the analysis and design for earthquake loading:
SEISMIC DESIGN Various building codes consider the following categories for the analysis and design for earthquake loading: 1. Seismic Performance Category (SPC), varies from A to E, depending on how the
Rockwool Flexi Insulation Application Guide
Pitched roof Rafters InterMediate floors INTERNAL partitions external Framed walls separating floors Separating Walls Rockwool Flexi Insulation Application Guide Ground floor The perfect fit for any framed
Understanding BS EN 771-3: Aggregate concrete masonry units
60 Charles Street, Leicester LE1 1FB Tel: 0116 253 6161 Fax: 0116 251 4568 Email: [email protected] Website: www.cba-blocks.org.uk February 2006 Understanding BS EN 771-3: Aggregate concrete
Insulated Roof & Wall Panels. Product Data Sheet. Trapezoidal Insulated Roof Panels KS1000 RW
Insulated Roof & Wall Panels Trapezoidal Insulated Roof Panels KS1000 RW Overview Kingspan roof panel systems present a superior system compared to conventional multi-part site assembled systems. They
8 EXTRA LIGHT GRC SANDWICH ELEMENTS FOR ROOFING IN INDUSTRIAL BUILDINGS
8 EXTRA LIGHT GRC SANDWICH ELEMENTS FOR ROOFING IN INDUSTRIAL BUILDINGS MARICA DELLA BELLA and DIEGO CIAN Precompressi Centro Nord S.p.A., Italy SUMMARY: Secondary roofing elements, complementary to the
Page 1 of 18 28.4.2008 Sven Alexander Last revised 1.3.2010. SB-Produksjon STATICAL CALCULATIONS FOR BCC 250
Page 1 of 18 CONTENT PART 1 BASIC ASSUMPTIONS PAGE 1.1 General 1. Standards 1.3 Loads 1. Qualities PART ANCHORAGE OF THE UNITS.1 Beam unit equilibrium 3. Beam unit anchorage in front..1 Check of capacity..
Chapter 2 Basis of design and materials
Chapter 2 Basis of design and materials 2.1 Structural action It is necessary to start a design by deciding on the type and layout of structure to be used. Tentative sizes must be allocated to each structural
9.3 Two-way Slabs (Part I)
9.3 Two-way Slabs (Part I) This section covers the following topics. Introduction Analysis and Design Features in Modeling and Analysis Distribution of Moments to Strips 9.3.1 Introduction The slabs are
INTRODUCTION TO LIMIT STATES
4 INTRODUCTION TO LIMIT STATES 1.0 INTRODUCTION A Civil Engineering Designer has to ensure that the structures and facilities he designs are (i) fit for their purpose (ii) safe and (iii) economical and
APPENDIX H DESIGN CRITERIA FOR NCHRP 12-79 PROJECT NEW BRIDGE DESIGNS
APPENDIX H DESIGN CRITERIA FOR NCHRP 12-79 PROJECT NEW BRIDGE DESIGNS This appendix summarizes the criteria applied for the design of new hypothetical bridges considered in NCHRP 12-79 s Task 7 parametric
MECHANICS OF SOLIDS - BEAMS TUTORIAL 2 SHEAR FORCE AND BENDING MOMENTS IN BEAMS
MECHANICS OF SOLIDS - BEAMS TUTORIAL 2 SHEAR FORCE AND BENDING MOMENTS IN BEAMS This is the second tutorial on bending of beams. You should judge your progress by completing the self assessment exercises.
Design guide. Part 1: Structural Design
Design guide Part 1: Structural Design Design guide Part 1: Structural Design Advantages: Fast Economical Strong Insulating Environmentally friendly Versatile Modernist house supplied by SIPBuild Vernacular
ADVANCED SYSTEMS FOR RATIONAL SLAB REINFORCEMENT
ADVANCED SYSTEMS FOR RATIONAL SLAB REINFORCEMENT CASPER ÅLANDER M. Sc. (Civ. Eng.) Development manager Fundia Reinforcing Abstract This paper deals with rational and fast ways to reinforce concrete slabs.
Numerical modelling of shear connection between concrete slab and sheeting deck
7th fib International PhD Symposium in Civil Engineering 2008 September 10-13, Universität Stuttgart, Germany Numerical modelling of shear connection between concrete slab and sheeting deck Noémi Seres
A transverse strip of the deck is assumed to support the truck axle loads. Shear and fatigue of the reinforcement need not be investigated.
Design Step 4 Design Step 4.1 DECK SLAB DESIGN In addition to designing the deck for dead and live loads at the strength limit state, the AASHTO-LRFD specifications require checking the deck for vehicular
How To Build A Luxury Apartment Complex In London
Post Tensioning Awards 2009 Project Summary Type of structure Location Architects Structural Engineer Residential with leisure suites including Swimming pool, Cinema, Virtual Golf, Wine Cellars, and Parking
Technical Assignment 2 TABLE OF CONTENTS
2 TABLE OF CONTENTS Executive Summary...3 Introduction..5 Gravity Loads......6 Design Codes......7 Materials..8 Existing Structural System.. 10 Existing Floor System 15 Alternate Floor Framing Systems...17
Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12)
Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Design Criteria AASHTO LRFD Bridge Design Specifications, 6th Edition; Structures Detailing Manual (SDM); Structures Design Guidelines (SDG)
Structural Design Calculation For Pergola
Structural Design Calculation For Pergola Revision :5 Prepared by :EC Date : 8/10/009 CONTENTS 1. Introduction... Design Code and Reference 3. Design Synopsis 4. Design Parameters 4.1 Design Load. 4. Design
Steel joists and joist girders are
THE STEEL CONFERENCE Hints on Using Joists Efficiently By Tim Holtermann, S.E., P.E.; Drew Potts, P.E.; Bob Sellers, P.E.; and Walt Worthley, P.E. Proper coordination between structural engineers and joist
STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM
Chapter 9 STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM 9.1 BACKGROUND Steel is widely used in the construction of multi-storey buildings. However, steel construction is seldom used and is traditionally
Eurocode 2: Design of concrete structures
Eurocode 2: Design of concrete structures Owen Brooker, The Concrete Centre Introduction The transition to using the Eurocodes is a daunting prospect for engineers, but this needn t be the case. Industry
Reinforced Concrete Slab Design Using the Empirical Method
Reinforced Concrete Slab Design Using the Empirical Method BridgeSight Solutions for the AASHTO LRFD Bridge Design Specifications BridgeSight Software TM Creators of effective and reliable solutions for
Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar
Problem 1 Design a hand operated overhead crane, which is provided in a shed, whose details are: Capacity of crane = 50 kn Longitudinal spacing of column = 6m Center to center distance of gantry girder
Fire safety in timber buildings
Fire safety in timber buildings Introduction Fire spread in buildings is a risk to life safety for which the Building Regulations (for England and Wales 1,2, Scotland 3 and Northern Ireland 4 ) aims to
Timber Frame Construction
Timber Frame Construction Introduction Design and Detailing What is timber? Failure modes History of timber frame construction Forms of timber frame construction Live and dead loads Wind loads Roof construction
Aluminium systems profile selection
Aluminium systems profile selection The purpose of this document is to summarise the way that aluminium profile selection should be made, based on the strength requirements for each application. Curtain
Conceptual design and design examples for multi-storey buildings
Brussels, 18-20 February 2008 Dissemination of information workshop 1 Conceptual design and design examples for multi-storey buildings Dr.-Ing. Christian Müller Dipl.-Ing. Matthias Oppe RWTH Aachen Overview
4B-2. 2. The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.
Shear Walls Buildings that use shear walls as the lateral force-resisting system can be designed to provide a safe, serviceable, and economical solution for wind and earthquake resistance. Shear walls
Steel and composite bridges in Germany State of the Art
Steel and composite bridges in Germany State of the Art Univ.-Prof. Dr.-Ing. G. Hanswille Institute for Steel and Composite Structures University of Wuppertal Germany Univ.-Prof. em. Dr.-Ing. Dr. h.c.
FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS
FUTURE SLAB PENETRATIONS and DEMOLITION of POST-TENSIONED FLOORS 1.0 INTRODUCTION Post-tensioned floor slabs in Australia and South East Asia are now universally regarded as the most cost effective form
LEGACY REPORT. www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council. *Corrected March 2014
ICC-ES Legacy Report PFC-3700* Issued October 2003 www.icc-es.org (00) 423-57 (52) 99-0543 A Subsidiary of the International Code Council Legacy report on the 1997 Uniform Building Code and the 2000 International
New approaches in Eurocode 3 efficient global structural design
New approaches in Eurocode 3 efficient global structural design Part 1: 3D model based analysis using general beam-column FEM Ferenc Papp* and József Szalai ** * Associate Professor, Department of Structural
Composite Construction with KÖCO- Stud Welding Technology IMPRESSIVE TECHNOLOGY 6/2005 1.1
Composite Construction with KÖCO- Stud Welding Technology IMPRESSIVE TECHNOLOGY 6/2005 1.1 Composite Construction with KÖCO Stud Welding Technology What is composite construction? An outstanding feature
Partitioning & Ceiling Product Information
Partitioning & Ceiling Product Information tel + 44 (0) 1384 412448 fax + 44 (0) 1384 4494 email [email protected] web www.drywallsteelsections.co.uk tel + 44 (0) 1384 412448 fax + 44
Eurocode 5: Design of timber structures
Eurocode 5: Design of timber structures Arnold Page, BSc, BD, MIWSc. Structural timber engineering consultant Introduction BS EN 1995 consists of three parts: Part 1-1: General. Common rules and rules
MECHANICS OF SOLIDS - BEAMS TUTORIAL 1 STRESSES IN BEAMS DUE TO BENDING. On completion of this tutorial you should be able to do the following.
MECHANICS OF SOLIDS - BEAMS TUTOIAL 1 STESSES IN BEAMS DUE TO BENDING This is the first tutorial on bending of beams designed for anyone wishing to study it at a fairly advanced level. You should judge
Document type: Practice Note Title: External and internal membranes Document number: AC2234 Version: 5. 1. Purpose
Document type: Practice Note Title: External and internal membranes Document number: AC2234 Version: 5 1. Purpose The purpose of this practice note is to address the incidence of deck and roof membrane
Long Carbon Europe Sections and Merchant Bars. Slim Floor. An innovative concept for floors
Long Carbon Europe Sections and Merchant Bars Slim Floor An innovative concept for floors Fire resistant Integrated Flexible Architectes Claude Vasconi et Jean Petit - Chambre de Commerce Luxembourg Contents
4.3.5 - Breakaway Walls
4.3.5 - Breakaway Walls Elevation of a structure on a properly designed foundation reduces the potential for water damage from flooding. When the space below the lowest elevated floor is maintained free
The Analysis of Open Web Steel Joists in Existing Buildings
PDHonline Course S117 (1 PDH) The Analysis of Open Web Steel Joists in Existing Buildings Instructor: D. Matthew Stuart, P.E., S.E., F.ASCE, F.SEI, SECB, MgtEng 2013 PDH Online PDH Center 5272 Meadow Estates
Fire Preventive and Fireproof Performance Test and Evaluation Procedure Manual
BR BO-01-02 Effective from June 1, 2000 Revision: March 26, 2002 Fire Preventive and Fireproof Performance Test and Evaluation Procedure Manual (Unofficial Manual) Technical Appraisal Department, Building
ick Foundation Analysis and Design
ick Foundation Analysis and Design Work: ick Foundation Location: Description: Prop: Detail analysis and design of ick patented foundation for Wind Turbine Towers Gestamp Hybrid Towers Date: 31/10/2012
Corus Construction & Industrial. Steel-framed car parks
Corus Construction & Industrial Steel-framed car parks Contents Avebury Boulevard multi-storey car park Milton Keynes Contents Contents 5 Introduction Attributes of good car park design Advantages of steel
FLOORS REINFORCEMENT Shear Stud Connector for steel- concrete composite structures cold applied by pins
www.tecnaria.com FLOORS REINFORCEMENT Shear Stud Connector for steel concrete composite structures cold applied by pins HIGHPERFORMANCE FLOORS COMPOSITE STEEL AND CONCRETE STRUCTURES: STATIC AND ECONOMIC
Quality Regulations for Profiles
Quality Regulations for Profiles September 2010 Quality Regulations for Profiles Page 2/42 Contents Preface... 4 1. Terms and Definitions... 5 1.1 Third parties... 5 1.2 Independent laboratories... 5 1.3
SECTION 3 DESIGN OF POST- TENSIONED COMPONENTS FOR FLEXURE
SECTION 3 DESIGN OF POST- TENSIONED COMPONENTS FOR FLEXURE DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: TREY HAMILTON, UNIVERSITY OF FLORIDA NOTE: MOMENT DIAGRAM CONVENTION In PT design,
Cable ladder installation at S.C.M. Chemicals Limited s titanium dioxide Plant in Western Australia
Exel Composites Cable Support Systems offer engineers a structural product for solving many design and plant engineering problems, enabling long term reliable support of expensive and often critical cables.
SECTION 3 DESIGN OF POST TENSIONED COMPONENTS FOR FLEXURE
SECTION 3 DESIGN OF POST TENSIONED COMPONENTS FOR FLEXURE DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: TREY HAMILTON, UNIVERSITY OF FLORIDA NOTE: MOMENT DIAGRAM CONVENTION In PT design,
SECTION 5 ANALYSIS OF CONTINUOUS SPANS DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: BRYAN ALLRED
SECTION 5 ANALYSIS OF CONTINUOUS SPANS DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: BRYAN ALLRED NOTE: MOMENT DIAGRAM CONVENTION In PT design, it is preferable to draw moment diagrams
ETABS. Integrated Building Design Software. Composite Floor Frame Design Manual. Computers and Structures, Inc. Berkeley, California, USA
ETABS Integrated Building Design Software Composite Floor Frame Design Manual Computers and Structures, Inc. Berkeley, California, USA Version 8 January 2002 Copyright The computer program ETABS and all
Monocouche Best Practice Guide. New-Build Housing Managing movement to avoid cracking
Monocouche Best Practice Guide New-Build Housing Managing movement to avoid cracking Avoiding Cracking For The Designer Visible cracks in render are unsightly and although not hazardous to the construction
Structural fire design Eurocode 5-1.2 Timber structures
Background and Applications Brussels, 18-20 February 2008 Dissemination of information workshop 1 Structural fire design Eurocode 5-1.2 Timber structures Jochen Fornather Austrian Standards Institute [email protected]
INTRODUCTION TO BEAMS
CHAPTER Structural Steel Design LRFD Method INTRODUCTION TO BEAMS Third Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering Part II Structural Steel Design and Analysis
A Case Study Comparing Two Approaches for Applying Area Loads: Tributary Area Loads vs Shell Pressure Loads
1 A Case Study Comparing Two Approaches for Applying Area Loads: Tributary Area Loads vs Shell Pressure Loads By Dr. Siriwut Sasibut (Application Engineer) S-FRAME Software Inc. #1158 13351 Commerce Parkway
Simplified Design to BS 5400
Simplified Design to BS 5400 Bridge Design to the Eurocodes Simplified rules for use in student projects (Document RT1156) Version Date of Issue Purpose Author Technical Reviewer Approved 1 Distribution
Connex. Mortarless Masonry Block System
Connex Mortarless Masonry Block System Connex Mortarless block wall system from Boral The Boral Connex mortarless system comprises three modular components which key together eliminating the need for mortared
PRESTRESSED CONCRETE FLOORING BEAMS
PRESTRESSED CONCRETE FLOORING BEAMS TRIED & TRUSTED Introduction Established in 2001 TT Concrete Products Limited has become a prominent manufacturer of prestressed concrete flooring beams throughout the
Chapter. Earthquake Damage: Types, Process, Categories
3 Chapter Earthquake Damage: Types, Process, Categories Earthquakes leave behind a trail of damage and destruction. People s lives are affected by the loss of loved ones, destruction of property, economic
STEEL BUILDINGS IN EUROPE. Single-Storey Steel Buildings Part 8: Building Envelope
STEEL BUILDINGS IN EUROPE Single-Storey Steel Buildings Part 8: Building Envelope Single-Storey Steel Buildings Part 8: Building Envelope 2 - ii Part 8: Building Envelope emissions
Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span
formwork formwork Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span has grown to become one of the major players in the scaffolding and
