EASTERN MUNICIPAL WATER DISTRICT SMALL SEWAGE LIFT STATION GUIDELINES, STANDARD DRAWINGS, AND SPECIFICATIONS

Size: px
Start display at page:

Download "EASTERN MUNICIPAL WATER DISTRICT SMALL SEWAGE LIFT STATION GUIDELINES, STANDARD DRAWINGS, AND SPECIFICATIONS"

Transcription

1 Last Update: 07/12/16 EASTERN MUNICIPAL WATER DISTRICT SMALL SEWAGE LIFT STATION GUIDELINES, STANDARD DRAWINGS, AND SPECIFICATIONS EASTERN MUNICIPAL WATER DISTRICT 2270 TRUMBLE ROAD PERRIS, CALIFORNIA (951) Prepared by KRIEGER & STEWART, INCORPORATED 3602 UNIVERSITY AVENUE RIVERSIDE, CALIFORNIA (951)

2 [Page Left Intentionally Blank]

3 TABLE OF CONTENTS

4 [Page Left Intentionally Blank]

5 Last Update: 07/12/16 TABLE OF CONTENTS SECTION PAGE I. Introduction 1 II. Procedures 1 III. General 6 IV. Capacity 7 V. Sewage Lift Station Site 8 VI. Force Main 9 VII. Lift Station 10 VIII. Electrical and Controls 13 IX. Emergency Power 13 X. Telemetry Equipment 15 APPENDIX A Sample Design Calculations TABLES Table 1 Related District Standard Drawings DETAILED PROVISIONS Refer to the latest Standard Detailed Provision Sections located at the following web site ( Section Section Section Section Section Section Section Section Section Section Section General Safety Requirements Maintenance Manual Requirements Temporary Sewage Lift Station Demolition Construction Methods & Earthwork Control Density Fill Asphalt Concrete Paving Formwork for Cast-in-Place Concrete Reinforcing Cast-in-Place Concrete Concrete Masonry Units Chemical Resistant Coatings i

6 Last Update: 07/12/16 TABLE OF CONTENTS (Continued) Section Section Section Section Section Small Submersible Sewage Lift Station with Emergency Standby Power Generation Small Submersible Sewage Lift Station without Emergency Standby Power Generation Electrical Panel Sunshade Structure Plug Valves Electrical Short Circuit/Coordination Study, Arc Flash Hazard Study, and Field Testing of Electrical System Refer to the latest Standard Detailed Provision Sections located at the following web site ( SMALL SEWAGE LIFT STATION STANDARD DRAWINGS (11 x 17) DRAWING FILE Title Sheet G-1 D Typical Site Plans C-1 D Wet Well Plans, Section, and Detail (120 gpm to 260 gpm capacity) M-1A D Wet Well Plans, Section, and Detail (260 gpm to 500 gpm capacity) M-1B D Miscellaneous Wet Well Details and Sections M-2 D Wet Well Structural Plans, Sections, and Details (120 gpm to 260 gpm capacity) Wet Well Structural Plans, Sections, and Details (260 gpm to 500 gpm capacity) Electrical Panel Sunshade Structure Foundation Plan, Elevation, and Section S-1A D S-1B D S-2 D Electrical Symbols, Abbreviations, and Lighting Fixture Schedule E-1 D Single Line Diagram (With Standby Generator), MCC Plan and Elevations E-2A D ii

7 Last Update: 07/12/16 TABLE OF CONTENTS (Continued) SMALL SEWAGE LIFT STATION STANDARD DRAWINGS (11 x 17) DRAWING FILE Single Line Diagram (Without Standby Generator), MCC Plan and Elevations E-2B D Control Diagrams E-3 D RTU Status/Alarm Signal Wiring Diagrams E-4 D MCC and Sunshade Grounding Plan and Service Pedestal Detail E-5 D Miscellaneous Details ME-1 D Typical Temporary Small Lift Station Demolition Site Plan D-1 D Demolition Plan, Section, and Details D-2 D iii

8 [Page Left Intentionally Blank]

9 GUIDELINES

10 [Page Left Intentionally Blank]

11 Last Update: 07/12/16 EASTERN MUNICIPAL WATER DISTRICT SMALL SEWAGE LIFT STATION GUIDELINES I. Introduction Sewage collection within the District service area shall be provided by the construction of gravity sewers, except where it is demonstrated unfeasible and pumping is required. If a sewage lift station is proposed, it shall be the developer's responsibility to provide the services of a licensed civil engineer to demonstrate to the District that a sewage lift station is the most feasible method for sewage conveyance. These guidelines present basic concepts and general criteria for small sewage lift station facilities with capacities not exceeding 500 gpm. Each lift station shall be reviewed and approved by the District from concept through design, construction, and start-up. Detailed Provision Sections 11200, 11210, and and the Standard Drawings are provided to present lift station construction requirements. Detailed Provision Section and the Standard Drawings are provided to present demolition requirements for temporary lift stations. The District reserves the right to modify and supplement these guidelines, specifications, and drawings to require additional facilities, depending upon the specific project location, limitations, and changes in government regulations and standards. II. Procedures Prior to the District's approval and acceptance of a temporary or permanent sewage lift station, developer and developer's engineer shall comply with the following requirements: A. Design and Construction of Temporary or Permanent Small Sewage Lift Stations 1. Developer's engineer shall acquire and review these guidelines; Detailed Provision Sections 11200, 11210, and 13123, and other Detailed Provision Sections referenced in these guidelines; and the Standard Drawings. 2. Developer and engineer shall request a concept meeting with District staff to demonstrate the need for a sewage lift station and to review requirements, guidelines, criteria, right-of-way, and location of specific project facilities. District will provide list of approved materials. 1

12 Last Update: 07/12/16 3. Developer shall submit all documentation requested by the District in order to demonstrate the need for a sewage lift station, including the following: a. Complete calculations for sewage flows within the entire drainage area tributary to the lift station. b. Preliminary drawings showing planned gravity collection system within the lift station drainage area, including point(s) of connection to existing or future gravity interceptor sewers, if any. c. Determination whether the proposed lift station will be temporary or permanent. d. Calculations establishing the required lift station capacity for initial planned development and ultimate development. e. Preliminary drawings showing the proposed alignment for the lift station force main including point of discharge. 4. If the District concurs that a lift station is required, developer's engineer shall submit design calculations, drawings, and specifications for District approval as follows: a. Preliminary design calculations and information including required capacity, hydraulic analyses, pump selections, and system curves, and preliminary site layout. Sample design calculations are included in Appendix A. Depending upon location, the District will establish site improvements such as masonry block wall or chain link fence, asphalt concrete or concrete pavement, lighting, access, etc. District will provide specialty specifications to be used. b. Submit 75% complete construction drawings. c. Submit legal plat and description for proposed property in fee title and/or easements for lift station site and force main (if applicable). Legal plats and description shall conform to EMWD's standards. Contact District's Right-of-Way Department for details. Note, final plans will not be signed until this information is received and reviewed for conformance to site plan. 2

13 Last Update: 07/12/16 d. Submit final design and 100% complete construction drawings. As a minimum, construction drawings prepared by the developer shall include a title sheet and detailed site plan. The title sheet shall include a summary of project specific requirements and data (see sample title sheet provided herein). As a minimum, the lift station site plan shall show the following: Location of all proposed facilities (referenced to site property lines or easement boundary). Location of gravity sewer and manholes. Provide bearings and distances along each gravity sewer segment shown on the Site Plan. Provide invert elevations (inlet and outlet) at each manhole. Gravity sewers shall be labeled with pipe size and material. Manholes shall be labeled with size and Standard Drawing reference. Location of emergency bypass manhole directly adjacent to wet well. All collection sewers entering the lift station site shall terminate at the emergency bypass manhole. Emergency bypass manhole shall be provided with a 36" diameter fiberglass reinforced plastic (FRP) manhole cover. Provide invert elevations at bypass manhole inlet and outlet. Location of force main and emergency bypass connection. Provide bearings and distances along each force main segment shown on the Site Plan. Provide center grade elevations at each horizontal and vertical point of inflection (HPI and VPI). Force main shall be labeled with pipe size, material, and class. Location of each electrical conduit, pull box, junction box, and SCE service and transformer. Refer to Conduit Schedule on Electrical Drawings for conduit destinations. Label all conduits shown in the Conduit Schedule. 3

14 Last Update: 07/12/16 Location of all site improvements, including site fencing or masonry block walls and access gate(s). Where masonry block walls are selected for site security, label top of wall and top of footing for each wall segment. Walls shall be constructed level. Walls shall step as required to provide a minimum of 6'- 0" height from outside finished grade. Provide a construction detail for masonry block wall and concrete footing showing all dimensions, reinforcing steel, block type, and grouting requirements. Provide details for site fencing and access gates if District standard fencing and gates are not used. Finished grades for all proposed facilities and site improvements. As a minimum, grades (elevations) shall be provided for all concrete slabs and roofs, asphalt concrete paving (along pavement edges and flow lines, adjacent to concrete slabs and roofs, etc.), masonry block walls and footings, and finish grading adjacent to site improvements. Location of microwave and radio communications antenna and tower for District SCADA communications. Developer shall coordinate with District during final design so that District can survey the site to determine if an antenna tower will be required based on the site's location. District will provide required antenna mounting height and details for antenna tower for developer's engineer to include on Construction Drawings. Developer will pay all costs for construction of antenna. 5. Prior to construction submit signed final design "approved for construction" SCE service plan to District. 6. Prior to construction (installation), shop drawing submittals for all proposed equipment and materials shall be submitted to the District for approval. 7. Construction of facilities shall be in accordance with approved construction drawings and District specifications. District will provide inspection of facilities, witness start-up, and provide final inspection of facilities. District staff shall receive final operation and maintenance manuals for all equipment a minimum of 10 working days prior to receiving training for station operation and equipment operation. A factory trained equipment manufacturer's representative shall provide the training. 4

15 Last Update: 07/12/16 B. Demolition of Temporary Small Sewage Lift Stations Plans for temporary lift stations shall include construction drawings and demolition drawings. Submittal of demolition documents (drawings and specifications) for District review shall coincide with submittal of the corresponding construction documents. Procedures required for District approval of temporary lift station demolition documents are as follows: 1. Developer's engineer shall acquire and review Detailed Provision Section and the Standard Drawings. 2. Developer and engineer shall request a concept meeting with District staff to discuss future diversion of sewage flow from the temporary lift station to a gravity sewer, de-activation and demolition of lift station facilities, and the anticipated schedule for performing the work. 3. Submit 75% complete demolition drawings and specifications (if requested by District). 4. Submit 100% complete demolition drawings. As a minimum, demolition drawings prepared by the developer shall include a detailed site plan. A sample demolition site plan is included herein for reference.. The demolition site plan shall show the removal of all facilities not addressed by the Standard Drawings. As a minimum, the site plan shall show demolition of site improvements including fencing, walls, gates, paving, driveways, lighting, electrical, and drainage facilities. 5. Submit 100% complete demolition checklist per Detailed Provision Section 02051, Exhibit A. 6. Submit a detailed cost estimate for performing the lift station demolition work. Demolition requirements shown on the Standard Drawings, and contained in Detailed Provision Section represent minimum District requirements. Depending upon the proposed re-use of the temporary lift station site, developer may elect to require more extensive demolition, including the complete removal of all below grade facilities. 5

16 Last Update: 07/12/16 III. General A. Raw sewage lift stations shall be designed and constructed in accordance with District guidelines herein, District standards (drawings and specifications), good engineering practice, applicable government regulations, Riverside County Health Services Department and State Water Resources Control Board, Division of Drinking Water (SWRCB DDW), Cal OSHA, Standard Specifications for Public Works Construction (Standard Specification), California Building Code, National Electric Code, Uniform Fire Code, and as approved by the District. B. Facilities shall be designed by a licensed civil engineer, registered in the State of California, experienced in the design of wastewater lift station facilities. Prior to commencing design, the Engineer shall submit to the District a statement of qualifications showing that he has designed a minimum of five sewage lift stations. The statement of qualifications shall include the name, client, capacity, and construction cost for each sewage lift station. Drawings and specifications shall be submitted for review and approval by the District. Soils investigation shall be performed for the lift station site and related interceptor sewer and force main. Sewer, force main, and lift station construction drawings shall be submitted simultaneously; sewer and force main shall include plan (1"=40') and profile (vertical 1"=4', horizontal 1"=40'), and lift station shall include site plan and standard drawings showing structural, mechanical, and electrical plans, sections, and details with project specific requirements. Sewer and force main plans shall be prepared in accordance with the District's "Guidelines for Sewer System Plans". C. All costs of temporary facilities shall be borne by the developer. D. Upon approval and acceptance by the District, facilities shall be owned by the District. Ownership shall include the lift station site and right-of-way for force main and gravity sewers. Gravity sewers and force main shall be constructed on District property, District right-of-way, or within public right-of-way whenever possible. Easements for gravity sewers and force main will only be considered under special conditions. All right-of-way and easement documents shall be submitted and approved by District prior to approval of the construction drawings. All right-of-way and easement documents shall be conveyed to the District and recorded prior to acceptance of facilities. 6

17 Last Update: 07/12/16 E. Prior to completion of the facility and District acceptance, complete records shall be furnished to the District including: 1. As-built record drawings. 2. Final approved shop drawings and submittals for all equipment and materials. 3. As-built electrical and control diagrams. 4. Minimum three copies of Operation and Maintenance Manuals for all equipment. 5. District staff training for station operation and equipment operation and maintenance. 6. Right-of-way, grant deed, and easement records. 7. All construction and operating permits. IV. Capacity A. The theoretical calculated peak flow shall be based on the development to be serviced with consideration of the entire drainage area and master planned facilities. The design flow shall be determined by increasing the theoretical calculated dry weather peak flow determined from entire drainage area by 20% (i.e. peak flow x 1.20 = design flow). Pumping units and wet well size shall be selected based on the design flow. Flows shall be provided for initial and ultimate conditions. If necessary, lift stations shall be located to maximize sewage collection for the entire drainage area and shall conform to the District's Wastewater Master Plan. Lift station pumping capacity may be dictated by minimum acceptable force main size and velocity criteria herein. B. Where Master Plan facilities have not been established, the developer shall be responsible to prepare wastewater flow projections for the drainage area. C. Hydraulic calculations and system/pump curves for pump sizing and required capacity shall be submitted for both initial and ultimate peak flows. System curves shall be developed for friction coefficients of C=120 and C=140. System curves shall include minor friction losses (i.e. fittings and valves in discharge piping at wet well and fittings in force main). Pumps shall be selected based on friction coefficient of C=140. Developer's engineer shall select a minimum of three District-approved pump manufacturers and plot C=120 and C=140 system curves on each pump curve. 7

18 Last Update: 07/12/16 D. Downstream sewers shall be evaluated to ensure adequate capacity is available for receiving lift station sewage flow. V. Sewage Lift Station Site A. Site shall be of adequate size to operate, maintain, and repair the lift station facilities incorporating access for truck cranes and sewer cleaning trucks (Vactor trucks). B. All permanent sewage lift station sites require the parcel to be deeded to the District. Before construction, a Grant Deed with legal description and plat map must be prepared, approved, and recorded by the District. Refer to District typical layout drawings for plat map preparation. C. As a minimum, site shall be secured by commercial grade 6-foot high chainlink fence with 3-strand barbed wire or a 6-foot high masonry block wall. Access gate(s) shall include minimum 20-foot wide double gate for vehicles. Chainlink fencing and gates shall be provided in accordance with District Standard Drawing D-672. D. Entire site shall be provided with asphalt concrete pavement or concrete pavement, and adequate drainage facilities. Access driveway(s) to the site shall be 20-foot wide (minimum) and constructed of asphalt concrete pavement or reinforced concrete pavement. Asphalt concrete pavement or reinforced concrete pavement shall be designed to accommodate AASHTO H20-44 vehicle loading. E. If required by the District, based on proximity of the facility to other public facilities, residences, or buildings, landscaping shall be provided in accordance with the surrounding area. F. Potable water shall be provided to the site by hose bibs with antisiphon devices, water meter, and a backflow prevention device as approved by the District and SWRCB DDW. G. All lift stations shall have a street address sign affixed to the fence at the front of the station. H. Site shall be provided with a lighting system designed to minimize off site impacts while maintaining functionality for maintenance personnel working on lift station components. As a minimum, each site shall be provided with an "area light" activated by a photocell and a 150W "work light" activated by a manual switch located in the Main Control Panel. "Area light" shall comply with County of Riverside Ordinance Number Regulating Light Pollution. 8

19 Last Update: 07/12/16 I. Odor control components include: concrete slab for emergency shower and eyewash station, concrete pad for District furnished chemical storage tank, 120v receptacle for District furnished chemical feed pump, and conduit sleeve from receptacle stanchion to wet well. Emergency shower and eyewash station slab shall be located on the side of the chemical tank pad where the chemical delivery truck will be logically positioned. J. If required by the District, based on the location of the facility, a microwave and radio communications tower shall be provided for District SCADA communications at developer's expense. VI. Force Main A. Force main size (diameter) shall be based on the following: 1. Lift station design flow rate (one pump operating) with minimum velocity of 3 fps and maximum velocity of 6 fps. 2. Minimum size shall be 4-inch inside diameter. Where 4-inch mains are required, two (2) parallel pipelines shall be constructed for system reliability. Each force main shall be provided with the necessary valves and fittings to allow operation of either force main or both force mains. 3. Where a single 4-inch force main is inadequate to convey the peak flow rate (i.e. force main velocity exceeds maximum allowable velocity), the next larger size pipe diameter shall be used. 4. Where force main length exceeds 6,000 L.F., two (2) parallel pipelines shall be constructed for system reliability. Each force main shall be provided with the necessary valves and fittings to allow for operation of either force main or both force mains. B. Material shall be PVC per ANSI/AWWA C900 (minimum DR-18). Pipeline shall be constructed using restrained joints per District Standard Drawing B-663. C. Pipeline profile shall avoid intermediate high points if feasible. All high points shall be provided with combination sewage air and vacuum valve installation and special corrosive resistant pipeline materials. D. Onsite pipe cover shall be minimum 36-inches. 9

20 Last Update: 07/12/16 E. Separation from water lines shall be in accordance with SWRCB DDW. Additionally, a minimum 10-foot horizontal clearance shall be provided from site walls, site fencing, electrical facilities, storm drain facilities, and gravity sewer. F. Where force main connects to a new or existing discharge manhole, the discharge manhole shall be lined per Standard Detailed Provision Section at developer's expense. The District may require multiple manholes be lined at developer's expense. VII. Lift Station A. Raw sewage lift station shall be the submersible type with 100% redundancy, electrical service, switchgear, emergency power (if required by the District), and appurtenances. Standard Drawings M-1A, M-1B, M-2, and ME-1 are provided to present equipment and piping plans, sections, and details for the lift station. B. Raw Sewage Pumps 1. Number of pumps furnished shall provide complete redundancy. Minimum of two identical pumps each sized for 100% station capacity shall be installed. Typically, constant speed pumps will be provided; however, discharge to the downstream system may require use of variable speed drives. 2. Pump Requirements a. Raw sewage non-clog submersible pumps. Pump impellers shall be enclosed single port, recessed vortex, or grinder type. The specific pump impeller type to be used for the project will be determined by the District based on application and availability. b. Minimum 4-inch discharge. c. Ability to pass minimum 3-inch diameter sphere. d. Maximum 1800 rpm explosion-proof submersible motor with moisture and temperature sensors. e. Motor and cooling rating suitable to run dry for 15 minutes without damage to the pump. f. UL or Factory Mutual explosion-proof rating without being submerged. 10

21 Last Update: 07/12/16 g. Constructed of corrosion resistant materials and provided with corrosion resistant factory coating. h. Acceptable manufacturers are Essco, Wilo-EMU, Fairbanks-- Nijhuis, Wemco Flowserve, Xylem-Flygt, and ABS. i. Prior to acceptance, pump tests shall be performed to verify pump curves and system head curves. 3. Pump Mounting and Removal a. Provide rail-type guide system with intermediate supports to allow pump removal without removal of discharge piping or entering the wet well. All materials to be 316 stainless steel. b. Provide 316 stainless steel cable or chain fastened to each pump. The District will utilize their crane truck for removal of pumps. c. Electrical cable(s) shall be spliced at a junction box located 30- inches above wet well roof and meet all provisions of the NEC. 4. Spare parts shall include one set of seals and bearings. C. Wet Well Requirements 1. Class IV reinforced concrete pipe (RCP) per ASTM C76 with two circular reinforcement cages (quadrant or elliptical cages will not be allowed) and flush bell and spigot joints. Bell and spigot joints shall be provided with rubber gaskets and shall be suitable for a hydrostatic head of 50 feet per ASTM C361. Wet well shall also include reinforced concrete base and cover. Wet well reinforced concrete base shall be placed on a 12-inch thick mat of crushed miscellaneous base per SSPWC Section , Fine Gradation. Interior concrete surfaces ( including wall and roof) shall be coated with a field applied 100% solids epoxy lining system by Carboline, Sauereisen, or Tenemec per District Standard Small Submersible Sewage Lift Station Specifications. Wet well bottom shall be provided with concrete fillets sloping towards the pumps. 2. Wet well shall be sized based on maximum pump motor cycling time of six starts per hour at 1/2 design capacity and to provide adequate spacing for installation of two pumping units (see Table on Standard Drawing G-1 for wet well size versus flow capacity). 11

22 Last Update: 07/12/16 3. Concrete roof shall have a hatch opening (one hatch for both pumps) for pump removal/installation. Hatches shall be all stainless steel construction as manufactured by U.S.F. Fabrication, Flygt, Bilco, or equal, with lockable diamond plate covers, safety chain, spring assisted hinges, and swing-out interior safety grating. Portable temporary handrail system (Railguard 200 by Garlock Safety Systems, or equal) shall be provided around hatch opening. 4. Discharge piping inside the wet well shall be flanged, Schedule stainless steel. All stainless steel piping, fittings, and flanges shall be shop welded (field welding not permitted except where noted on District Standard Drawings). All welds shall be pickled and passivated in the shop (pickling paste shall be applied to District approved field welds). Discharge piping shall be designed for a maximum velocity of 6 to 8 feet per second. Discharge piping shall be properly supported with pipe supports. 5. Pipe supports, brackets, and all other equipment and fasteners within the wet well shall be 316 stainless steel. 6. All collection sewers shall join and enter a single manhole just prior to entering the wet well. Only one sewer shall enter the wet well to allow the District to plug influent sewer and bypass around wet well for maintenance and repairs. D. Pump Discharge Piping Out of Wet Well 1. Discharge from each pump shall exit the wet well below grade, then rise above grade for location of check valves and isolation plug valves. 2. Each pump shall be provided with 150 lb swing check valve (AWWA C508 with bronze trim) and shut-off valves (eccentric non -lubricated plug valve). Sewage combination air and vacuum valves shall be provided at high points. 3. A bypass connection to the force main shall be provided for station bypass with portable pumps. 12

23 Last Update: 07/12/16 VIII. Electrical and Controls A. All electrical equipment shall be in accordance with the NEC and, where applicable, meet all requirements for hazardous locations. Developer shall coordinate with the electrical utility providing electrical service. Station shall be provided with a separate utility transformer and metering section with main circuit breaker. Utility transformer and metering section shall be located in a separate fenced-in area (see Typical Site Plan s). Primary power to the station shall be 480 volt, 60 Hz, 3-phase service per utility providers' standards. Singlephase 120-volt power shall be provided for lights, controls, convenience receptacles, and miscellaneous equipment. Provide a minimum of four spare 20A, 120-volt circuit breakers. All conduit shall be run concealed below grade or in concrete slabs, and shall not impose tripping or maintenance hazards. All exposed conduit shall be pvc-coated rigid steel pipe. B. Electric switchgear shall be mounted in a NEMA 1 gasketed enclosure (with NEMA 3R wrapper) Motor Control Center with removable buckets, and shall include, as a minimum, main circuit breaker, motor starters with thermal overload protection, selector switch (hand -off-auto), run and fail lights, and elapsed time meter as shown on Standard Drawings E-2A and E-2B. Switchgear shall be General Electric, Eaton/Cutler Hammer, Allen-Bradley, or Schneider Electric/Square D (no substitutes). The MCC doors shall face north or east. C. Complete controls for automatic pump operation shall be provided per Standard Drawing E-3. D. An electrical panel sunshade structure shall be provided per Standard Drawing S- 2. E. Separate sunshades shall be provided to protect any items that can deteriorate from exposure to the sun and are not protected by the electrical panel sunshade structure. F. An electrical short circuit/coordination study, arc flash hazard study, and field testing of the electrical system shall be performed. IX. Emergency Power If required by the District, lift station facilities shall include permanent emergency power generation facilities. These facilities shall consist of an engine driven emergency power generator with integral fuel storage tank and an automatic transfer switch. Lift stations not requiring permanent emergency power generation facilities shall be provided with a manual transfer switch that will allow connection of a District portable emergency power generator. 13

24 Last Update: 07/12/16 Permanent emergency power generation facilities shall conform to the following: A. Provide a prefabricated skid-mounted diesel engine driven, radiator-cooled, automatic emergency standby generator to power the lift station during normal power failure. B. Generator set shall be as manufactured by Olympian (supported by Caterpillar), Caterpillar, Cummins, or Generac. C. Generator set shall automatically start upon failure of normal power and be sized to operate lighting loads, and both pumping units (duty and standby) with maximum voltage DIP of 20 percent. D. Generator set shall be provided with a weatherproof sheet metal housing. Exhaust system shall be fully insulated and equipped with a critical grade silencer. E. Generator set shall be equipped with all sound attenuating equipment, enclosures, and devices necessary to conform with applicable city or county noise ordinances. Design Engineer shall supplement the requirements of Detailed Provisions provided herein (Section 11200) with all generator sound attenuating measures necessary to comply with the applicable noise ordinances. F. Fuel tank for generator shall be base type mounted with unit. Tank shall be double walled welded steel sized for a minimum of 24 hours of continuous operation at 100% of generator capacity. Tank shall have secondary containment and alarm floats for low fuel and fuel in secondary containment area. Facilities shall meet local fire department criteria. A full tank of fuel shall be provided at developer's expense at the completion of construction. G. Generator set shall be "pre-certified"/"pre-approved" by South Coast Air Quality Management District (SCAQMD) for emergency standby power service, and shall meet all current SCAQMD air emission regulations. A Level 3 diesel particulate filter (DPF) verified by California Air Resources Board shall be provided at the developer's expense if required to meet the emission requirements of SCAQMD Rule Developer's engineer shall determine whether a passive DPF or active DPF will be required. For a passive DPF to be considered, it must operate at exhaust temperatures that are low enough not to require a load bank for regeneration. Developer's engineer shall submit the DPF to the District along with technical data and supporting calculations for review and acceptance. 14

25 Last Update: 07/12/16 All SCAQMD permits, including payment of fees for the first year of operation shall be furnished by developer. Permits shall have no less than a 200 hour annual operating limit with no less than 50 hours for maintenance and testing. The SCAQMD permit to construct shall be transferred into a permit to operate prior to acceptance by the District. H. Generator shall have the highest available tier rating, in accordance with EPA Tier Certification requirements. I. Automatic transfer switch (ATS) shall be provided to switch from normal utility power to standby emergency power upon normal power fail, and switch back to normal power when restored. ATS shall have indicating lights for normal power, emergency power, and a digital panel indicating volts and amps. Acceptable manufacturers are Olympian, ASCO, or Russelectric. J. If the District requires the developer to provide a standby generator that is larger than what is necessary to support the proposed lift station equipment (based on future development flows to the lift station), then the developer shall provide a load bank sized to provide the difference between the proposed equipment load and the future equipment load. X. Telemetry Equipment District will furnish, install, and program telemetry equipment system, including remote telemetry unit (RTU) to transmit alarm conditions to existing SCADA system. Contractor shall terminate all alarm signals on terminal blocks in the Main Control Panel (MCP) as shown on Standard Drawing E-4. Contractor shall connect from MCP terminal blocks to District furnished RTU terminal block. 15

26 Last Update: 07/12/16 [Page Left Intentionally Blank] 16

27 APPENDIX A SAMPLE DESIGN CALCULATIONS

28 [Page Left Intentionally Blank]

29

30

31

32

33

34

35

36

37

38 [Page Left Intentionally Blank]

39 TABLES

40 [Page Left Intentionally Blank]

41 Last Update: 07/12/16 TABLE 1 RELATED DISTRICT STANDARD DRAWINGS Refer to the latest Standard Drawings located at the following web site ( Standard Dwg. No. Description B-286B Trench Backfill (for PVC forcemain) B-590 5/8" Meter Service Connection, 1" Copper Tubing B-590A 5/8" Service Connection, 1" Copper Tubing B-591 1" Meter Service Connection, 1" Copper Tubing B-591A 1" Service connection, 1" Copper Tubing B-597 Backflow Prevention Assembly Installation Diagram B-656 Location Wire Installation B-663 Standard Restraint (Tee, Dead End, Bend) B-665 Guard & Marker Posts D-672 Chain Link Fence Details SB-08 Locking Type Manhole Cover & Frame SB-30 Reinforced Precast Shallow Manhole SB-53 Precast Reinforced Concrete, 48" & 60" I.D. Manhole SB-56 Precast Non-Reinforced Concrete, 48" I.D. Manhole SB-61 Manhole Cover & Frame SB-157 Pipe Zone Bedding for Sewer Pipe SB-158 Trench Backfill for Sewer Pipe SB-159 Classification of Pipe Zone Bedding for Sewer Pipe Sewer Guideline for Manhole Sizing *Refer to the latest Guideline Standards located at the following web site: (

42 [Page Left Intentionally Blank]

43 DETAILED PROVISIONS

44 [Page Left Intentionally Blank]

45 Revised 07/12/16 SPECIFICATIONS - DETAILED PROVISIONS Section Temporary Sewage Lift Station Demolition C O N T E N T S PART 1 - GENERAL DESCRIPTION REFERENCE SPECIFICATIONS, CODES, AND STANDARDS CONTRACTOR SUBMITTALS JOB CONDITIONS... 2 PART 2 - PRODUCTS IMPORTED FILL MATERIAL... 3 PART 3 - EXECUTION GENERAL POLLUTION CONTROL PROTECTION EQUIPMENT, PIPING, AND APPURTENANCES CONCRETE STRUCTURES AND IMPROVEMENTS SITEWORK EXISTING UTILITIES DISPOSAL OF DEMOLISHED MATERIALS PATCHING AND REPAIRING CLEANING SALVAGE... 9

46 [Page Left Intentionally Blank]

47 Temporary Sewage Lift Station Demolition SECTION TEMPORARY SEWAGE LIFT STATION DEMOLITION PART 1 - GENERAL 1.01 DESCRIPTION A. The Contractor shall furnish all labor, materials, and equipment necessary to perform and complete demolition work specified herein. B. The Work includes demolition of existing temporary sewage lift station facilities, abandonment of existing force main and gravity sewer, and re-construction of gravity sewer manhole(s). Existing lift station facilities to be removed and disposed, removed and salvaged, or to remain are summarized in Exhibit A attached at the end of these specifications. C. Contractor shall comply with the requirements of the District, government agencies, and utilities having jurisdiction over the work, such as, but not limited to: work in the public right-of-way (if applicable), hours of work, and removal of utilities. D. Re-construction of gravity sewer manhole(s) may require work to be performed within the public right-of-way. Contractor shall apply for and procure all permits and licenses, including encroachment permits required by the City or County having jurisdiction over the right-of-way. Contractor shall give all notices necessary and incidental to the prosecution of the work. It is the responsibility of the Contractor to contact the jurisdictional agency and make himself knowledgeable of their requirements. E. Demolition shall include the cost of "Final Disposal" of all debris, waste, and rubbish in a manner that complies with all local, state, and federal laws, regulations, and ordinances REFERENCE SPECIFICATIONS, CODES, AND STANDARDS The Work covered under this Section shall comply with current editions of the following specifications, codes, and standards: A. District Detailed Provisions Section 01000, General Safety Requirements B. California Building Code C. National Electrical Code

48 Temporary Sewage Lift Station Demolition D. State and Federal Occupational Health and Safety Administration (OHSA) Standards 1.03 CONTRACTOR SUBMITTALS Contractor shall provide submittals in accordance with the General Conditions, Section F - Labor and Construction. Submittals shall include, but shall not be limited to, the following: A. Demolition Schedule Prior to commencing demolition activities, Contractor shall submit for District's approval a complete coordination schedule for all demolition work, including shut-off of lift station pumping units, and deactivation and removal of electric power service to ensure uninterrupted sewage conveyance. B. Encroachment Permit Where work is required to be performed in the public right-of-way, Contractor shall submit a copy of the encroachment permit obtained from the City or County agency having jurisdiction over the right-of-way. C. Preconstruction Video Contractor shall prepare a video recording in the presence of the District's Inspector showing the existing lift station site, lift station facilities, and condition of structures and improvements adjacent to areas of demolition and alteration. Copies of the video recording shall be submitted to the District's Inspector prior to commencing work. D. Insurance Certificates Contractor shall not commence work until he has obtained all insurance required under the District's General Conditions, Section F Labor and Construction. Contractor shall submit all necessary documents to demonstrate compliance with the District's insurance requirements, including Worker's Compensation Insurance Certificate and Certificate of Liability Insurance. E. Hot Work Permit Prior to initiating hot work, Contractor shall submit a Hot Work Permit application to the District. Hot work includes, but is not limited to, any work involving grinding, cutting, torching, welding, soldering, brazing, powder-actuated tools and all other similar applications producing a spark, flame, or heat that is capable of initiating fires or explosions JOB CONDITIONS District assumes no responsibility for actual condition of the existing lift station facilities to be demolished. The Contractor shall visit the site and inspect the existing facilities, to ascertain their condition and impact on demolition activities.

49 Temporary Sewage Lift Station Demolition Existing lift station facilities pump raw sewage from the District's gravity sewer collection system. Contractor shall assume that all lift station piping, wet well and associated appurtenances are filled with raw sewage, including grease, grit, and debris. Prior to commencing demolition of lift station facilities, Contractor shall dewater and clean said facilities as necessary and as specified herein. PART 2 - PRODUCTS 2.01 IMPORTED FILL MATERIAL All imported fill material shall be select soil material, non-expansive with an expansion index of less than 20, free of vegetative matter and other deleterious substances, granular with a Sand Equivalent (SE) greater than 30, and shall not contain rocks or other irreducible matter with a maximum dimension greater than 4 inches. Fill material shall be approved by the District prior to use onsite. PART 3 - EXECUTION 3.01 GENERAL A. Contactor shall not commence with lift station demolition activities until receipt of District's written direction to proceed. Contractor shall not interrupt sewage conveyance at any time during demolition work. The first demolition work activity shall consist of diverting sewage from the lift station wet well or onsite bypass manhole to the gravity collection system. Contractor shall reconfigure the diversion manhole to the lift station or onsite bypass manhole to block sewage conveyance to the lift station facilities and open up conveyance to the gravity collection system. Contractor shall maintain continuous conveyance of raw sewage throughout reconfiguring the manhole base. B. All demolition work shall be completed within 90 days, commencing from the time the new sewer is placed in-service. Prior to commencing demolition work, Contractor shall submit a written request to District for additional time if demolition work is anticipated to take longer than 90 days. C. Site grading and compaction shall be performed as specified herein. Relative compaction of 95% shall mean soil compacted to a dry density exceeding 95% of the maximum dry density in accordance with ASTM D Compaction testing will be provided by the District. However, any costs for retesting of compaction due to the Contractor's negligence shall be paid for by the Contractor.

50 Temporary Sewage Lift Station Demolition POLLUTION CONTROL A. Water sprinkling, temporary enclosures, chutes, and other suitable methods shall be used to limit dust and dirt rising and scattering in the air. Comply with government regulations pertaining to environmental protection. B. Water shall not be used when it creates hazardous or objectionable conditions such as erosion, flooding, or pollution. C. Water contaminated with sediment or hazardous or toxic materials shall not be allowed to run off into the public storm drain system (including street gutters). Such runoff shall be intercepted, collected and disposed of according to existing environmental regulations PROTECTION A. Contractor shall perform his operations so that existing improvements which have not been designated for demolition are not damaged, including roads and other paved surfaces adjacent to or in the vicinity of the work site. Contractor shall repair and restore any disturbed or damaged private or public improvements which results from his operations (except that which is specifically a part of the Contract Work) to the satisfaction of the District, or the agency having jurisdiction over said improvements, all at the Contractor's expense. B. Interior and exterior shoring, bracing, or supports shall be provided to prevent sudden collapse of structures to be demolished and to prevent movement, settlement or collapse of adjacent facilities to remain. C. Existing vegetation, landscaping materials, structures, and appurtenances, which are not to be demolished, shall be protected and maintained as necessary. D. Provide safeguards, including warning signs, barricades, temporary fences, warning lights, and other similar items that are required for protection of work personnel and public during demolition and removal operations. Maintain fences, barricades, lights, and other similar items around exposed excavations until such excavations have been completely backfilled and no longer constitute a hazard or dangerous condition. Excavations in the public right-of-way shall be completely backfilled or covered with vehicle safety plates at the end of each work day. E. During demolition activities, Contractor shall protect all nearby existing equipment such as the motor control center and main control panel from dust caused by demolition activities by covering with drop-curtains or other similar methods.

51 Temporary Sewage Lift Station Demolition F. Demolition work involving grinding, cutting, torching, welding, or similar applications producing a spark, flame, or heat that is capable of initiating fires or explosions ( "hot work") shall be performed in conformance with OSHA 29CFR and NFPA 51B at a minimum. Prior to commencing any hot work, Contractor shall obtain a Hot Work Permit from the District and confirm that all fire prevention and protection requirements have been implemented EQUIPMENT, PIPING, AND APPURTENANCES A. All mechanical and electrical equipment shall be disconnected and removed. Mechanical and electrical equipment to be salvaged for the District is designated in Section 3.11 herein. Equipment and appurtenances not listed therein shall be considered waste and shall be disposed of by the contractor. B. All equipment, piping, and appurtenances inside the wet well shall be removed. Wet well discharge piping embedded in remaining wet well wall sections (deeper than 5 feet) shall be abandoned in-place. Contractor shall furnish and install blind flanges at the end of the remaining pipe spools. C. All above grade discharge piping, valves, and appurtenances shall be removed. Vertical pipe risers shall be removed to below grade transition with horizontal piping. Below grade horizontal piping runs deeper than 48 inches shall be abandoned in-place. The appropriate blind flanges, caps, threaded plugs, etc. shall be provided at the ends of all abandoned piping. Contractor shall flush the sewage force main piping to be abandoned with water, and then fill the piping with control density fill per District Detailed Provisions Section Contractor shall review the District's as-built drawings for the existing sewage force main(s) to determine the extent of the filling and conditions affecting same. Contractor shall plug the end of the sewage force main(s) at the discharge manhole to prevent any control density fill from entering the manhole and gravity sewage collection system. Contractor shall provide observation personnel at the discharge manhole during filling operations to ensure the integrity of the force main plug is maintained. D. All miscellaneous above grade mechanical and electrical appurtenances such as air valves, pipe supports, electrical receptacles, light fixtures, poles, and foundations, shall be removed and disposed. E. All electrical conductors shall be disconnected from the associated equipment and removed from the conduit. All above grade conduit shall be removed. Vertical conduit risers shall be removed to below grade transition with horizontal conduit. Below grade horizontal conduit runs deeper than 36 inches shall be abandoned in-place. Conduit caps shall be provided at the ends of all abandoned conduit.

52 Temporary Sewage Lift Station Demolition F. Voids created by removal of below grade facilities and appurtenances shall be backfilled with select fill material compacted to 95% minimum relative compaction CONCRETE STRUCTURES AND IMPROVEMENTS A. Demolition shall proceed in a systematic manner, in accordance with all permits and approved submittals. B. All concrete structures and improvements shall be demolished and disposed. As a minimum, concrete structures and improvements to be demolished include: wet well roof, upper 5 feet of wet well shaft, electrical panel foundation slab, standby generator foundation slab, discharge piping support slab, odor control chemical tank support slab, SCE transformer support slab, below grade electrical pull boxes and vaults, and site lighting pole foundations. At lift station installations where gravity sewage will no longer enter the site, the onsite bypass manhole shall be demolished, which shall consist of removal of the manhole roof/cone and the upper 5 feet of the manhole shaft. C. Concrete walls and roofs shall be demolished in sections. Contractor shall provide bracing and shoring as necessary to prevent structure collapse. D. Prior to commencing lift station wet well demolition, Contractor shall dewater and clean the wet well, and remove all equipment and appurtenances. Contractor shall then remove submersible sewage pumping units, including base elbows, guide rails and support brackets, access stabilizer, float switches and ultrasonic level transducer or bubbler system, discharge piping, pipe supports, and all related items. Following wet well cleaning and equipment removal, Contractor shall commence wet well demolition. Contractor shall remove wet well roof and upper wet well shaft sections to a minimum depth of 5 feet below existing or ultimate finished grade, whichever is greater. Contractor shall core drill the wet well foundation in 4 places, equally spaced. Each core drill shall be 12-inch diameter. Contractor shall fill the remaining wet well shaft with sand (minimum SE of 30) compacted to 90% relative compaction. The remaining wet well excavation (upper 5 feet or more) shall be backfilled with select fill material and compacted to 95% minimum relative compaction. E. Unless specified otherwise, footings, foundation walls, below-grade construction and concrete slabs on grade shall be demolished and removed to a depth which will not interfere with new construction, but not less than 24 inches below existing ground surface or future ground surface, whichever is lower. All below

4.0 SEWER LIFT STATION AND FORCE MAIN GUIDELINES

4.0 SEWER LIFT STATION AND FORCE MAIN GUIDELINES 4.0 SEWER LIFT STATION AND FORCE MAIN GUIDELINES 4.01 INTRODUCTION Sewage collection within Western Municipal Water District s (Western s) service area shall be provided by the construction of gravity

More information

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent

More information

SECTION 02221 SELECTIVE DEMOLITION

SECTION 02221 SELECTIVE DEMOLITION SECTION 02221 PART 1 -GENERAL 1.01 DESCRIPTION This section includes all material, labor, machinery and supervision required to demolish and remove the following items where applicable and as noted on

More information

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees. The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT

SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT The purpose of these specifications is to insure that there are minimum

More information

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT

More information

Town House 11265 Center Highway North Huntingdon, PA 15642

Town House 11265 Center Highway North Huntingdon, PA 15642 APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House

More information

SECTION 02630 STORM DRAINAGE SYSTEM

SECTION 02630 STORM DRAINAGE SYSTEM SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions. SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings

More information

SECTION 807 PUMP STATION REHABILITATION

SECTION 807 PUMP STATION REHABILITATION SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing

More information

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements

CONTENTS. Yale University Design Standards. Underground Electrical Duct Bank. A. Summary. B. System Design and Performance Requirements 16600 Underground Electrical Duct Bank This document provides design standards only, and is not intended for use, in whole or in part, as a specification. Do not copy this information verbatim in specifications

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection

More information

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System

Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System An application for the construction or alteration of an individual subsurface sewage disposal system shall

More information

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations. DIVISION 16 ELECTRICAL SECTION 16100 - ELECTRICAL PART 1 - GENERAL SCOPE All electrical work as shown on the drawings and as necessary to provide a complete electrical system. Include primary service,

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

SECTION 5 DRAFTING STANDARDS

SECTION 5 DRAFTING STANDARDS SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.

More information

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

Beacon Hill Sewer District Standard Specifications

Beacon Hill Sewer District Standard Specifications Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

SECTION 3 SANITARY SEWER DESIGN

SECTION 3 SANITARY SEWER DESIGN SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary

More information

Fire Pump Plan Review March 2010

Fire Pump Plan Review March 2010 Fire Pump Plan Review March 2010 Date of Review: / / Permit Number: Business/Building Name: Address of Project: Designer Name: Designer s Phone: Contractor: Contractor s Phone: Occupancy Classification:

More information

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel

More information

MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION

MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION Fire Pump Plan Review 2009 International Fire Code and NFPA 20 Date of Review / / BLD201 - Project Address: Project Name: Contractor s Business

More information

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or

More information

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,

More information

SANITARY SEWER SPECIFICATIONS

SANITARY SEWER SPECIFICATIONS SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,

More information

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with

More information

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application.

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application. ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application. Article II provides rules governing the allowable connection to the City POTW and the construction and inspection of

More information

Underground Commercial Electric Service

Underground Commercial Electric Service Underground Commercial Electric Service SCANA Corporation 2013 Revised: June 2013 Table of Contents SECTION PAGE I. Specification and Requirements 2 A. General B. Definition of Terms C. Company and Developer

More information

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by

More information

SECTION 02401 SHEETING, SHORING AND BRACING

SECTION 02401 SHEETING, SHORING AND BRACING SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State

More information

City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014

City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014 City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014 Section Subsection Name Date Modification Division 1 All subsections General Provisions

More information

MOBILE HOME LAW. Revised November 2001

MOBILE HOME LAW. Revised November 2001 MOBILE HOME LAW Revised November 2001 TABLE OF CONTENTS: SECTION 1: SECTION 2: SECTION 3: SECTION 4: SECTION 5: SECTION 6: SECTION 7: SECTION 8: SECTION 9: SECTION 10: SECTION 11: SECTION 12: INTENT DEFINITIONS

More information

SWIMMING POOL, SPA, & HOT TUB GUIDELINES

SWIMMING POOL, SPA, & HOT TUB GUIDELINES SWIMMING POOL, SPA, & HOT TUB GUIDELINES Pool permit cost is based on the total value of the project. See Permit Fee Schedule Table 1A. A. Adopted construction codes and installation requirements 1. 2015

More information

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and

More information

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes)

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) Maintenance Office Administrative Office Billing Office 530-426-7802 530-426-7800 916-332-4872

More information

Pump Specifications 250 Series Submersible Sump / Effluent Pump 2 Solids handling

Pump Specifications 250 Series Submersible Sump / Effluent Pump 2 Solids handling Pump Specifications 250 Series Submersible Sump / Effluent Pump 2 Solids handling 250_P1 R10/7/2015 Copyright 2015 Liberty Pumps Inc. All rights reserved. Specifications subject to change without notice.

More information

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation 644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING

More information

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, Storm Drain Installation, of these Standard Provisions. SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and

More information

CHAPTER 8 CIVIL DESIGN

CHAPTER 8 CIVIL DESIGN CHAPTER 8 CIVIL DESIGN A. GENERAL This Chapter includes standards and design considerations for other civil engineering design in structural, drainage and utilities. Design considerations for electrical

More information

Special Specification 7021 Water Main and Sewer Line Replacements

Special Specification 7021 Water Main and Sewer Line Replacements Special Specification 7021 Water Main and Sewer Line Replacements 1. DESCRIPTION Furnish, install, or replace water pipe, water valves, water meters and boxes, water service connections, fire hydrant assemblies,

More information

EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines

EXHIBIT A. Technical Specifications for Water and Sewer Service Lines EXHIBIT "A Technical Specifications for Water and Sewer Service Lines Water and Sewer Line Bedding and Backfill: Drawings show cross-section of trench, pipe laid on top of 6" min. bedding material, bedding

More information

Appendix S Pump Station Evaluation

Appendix S Pump Station Evaluation Appendix S Pump Station Evaluation Technical Memorandum Date: October 12, 2001 To: Re: Orange County Utilities Task 6.4 Raw Wastewater Pump Stations 1.0 Summary In accordance with Task 6.4 of the Orange

More information

Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems

Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems The septic tank-absorption field sewage treatment system is composed of two major elements; the

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE 1.0 GENERAL 1.1 DESCRIPTION This section addresses the procedures to be employed for pipe bursting existing water/sewer pipelines, as identified on the drawings, and replacing with new Restrained Joint

More information

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...

More information

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant

More information

2010 Residential Water Heater Replacement Check List

2010 Residential Water Heater Replacement Check List 2010 Residential Water Heater Replacement Check List The intent of this check list is to provide installers a general reference for the enforcement of code requirements in the Greater San Diego Area. This

More information

SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section 01 33 00 - Submittals.

SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section 01 33 00 - Submittals. SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS PART 1: GENERAL 1.01 SCOPE A. Abandonment in place, by cutting and capping, of existing water mains, hydrants, service lines, and valves. B. Abandonment in

More information

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION SPECIFICATION EO-5023 REVISION 3 MARCH 2003 REQUIREMENTS FOR

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

BLADDER SURGE CONTROL SYSTEM

BLADDER SURGE CONTROL SYSTEM PART I GENERAL 1.01 Description BLADDER SURGE CONTROL SYSTEM This specification describes the requirements for a Bladder Surge Control System. The purpose of the system is to minimize transient pressures

More information

Specifications for Residential Property Owners Connection to New Public Sewer

Specifications for Residential Property Owners Connection to New Public Sewer Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the

More information

2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS

2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS 2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS Water system improvements proposed for inclusion into Western s service area shall be designed in accordance with all appropriate AWWA standards, include

More information

Chapter 9 Sanitary Sewers

Chapter 9 Sanitary Sewers Chapter 9 Sanitary Sewers S:/Engineering/Design Standards/Chapter 9 12/29/2014 Section 9.1 Topic General Requirements Chapter 9 Sanitary Sewers Page 9-1 9.2 Plan Submittals 9-1 9.3 Determination of Flow

More information

Element D Services Plumbing

Element D Services Plumbing Medical Vacuum and Gas PART 1 - GENERAL 1.01 OVERVIEW A. This section addresses medical vacuum, waste anesthetic gas disposal, compressed air, oxygen, nitrous oxide, nitrogen and carbon dioxide systems.

More information

HELIPORT FUEL/WATER SEPARATOR MODEL H-200

HELIPORT FUEL/WATER SEPARATOR MODEL H-200 HELIPORT FUEL/WATER SEPARATOR MODEL H-200 Suite 150 Voice 1-973-540-0011 55 Madison Avenue Fax 1-973-540-0131 Morristown, NJ 07960-6012 Email info@heliport.com U.S.A. Web www.heliport.com A. PRINCIPLE

More information

Chapter 3 Pre-Installation, Foundations and Piers

Chapter 3 Pre-Installation, Foundations and Piers Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory

More information

ELECTRIC/DIESEL FIRE PUMP CHECK LIST

ELECTRIC/DIESEL FIRE PUMP CHECK LIST BUILDING NAME: DESIGNER: SCO REPRESENTATIVE: PUMP MANUF.: LOCATION: INSTALLER: DATE: OWNER NAME: INSTALLATION Certificate for flushing and hydrostatic test furnished Piping been hydrostatically tested

More information

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

Underground Service Requirements and Instructions

Underground Service Requirements and Instructions This packet includes all FKEC underground service requirements, instructions, procedures and drawings. If you are considering underground power service please review this document in its entirety (3 page

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks

More information

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Storm Sewer Trenchless Upgrade Alternatives and Recommendations Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

Section 02702 SEWER PIPE INSTALLATION AND TESTING

Section 02702 SEWER PIPE INSTALLATION AND TESTING PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete

More information

DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST

DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST CERTIFICATION 1. Did the engineer submit a certificate of completion utilizing the appropriate page of the issued

More information

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued)

WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued) BIDDER'S PROPOSAL (continued) Item Estimated No. Description Quantity Unit Unit Cost Total Cost BASE BID 1 Traffic Control 1 LS $ $ 2 Construction Area Signs 1 LS $ $ 3 Excavation Safety 1 LS $ $ 4 Reset

More information

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1

More information

Mechanical Installation

Mechanical Installation Page -1-1. INTRODUCTION AND PURPOSE 1.1. This specification covers the installation, testing and precommissioning of mechanical equipment. Work is to be performed in conjunction with the manufacturer s

More information

SUFFOLK COUNTY DEPARTMENT OF HEALTH SERVICES TOXIC/HAZARDOUS MATERIAL TRANSFER FACILITY DESIGN GUIDELINES

SUFFOLK COUNTY DEPARTMENT OF HEALTH SERVICES TOXIC/HAZARDOUS MATERIAL TRANSFER FACILITY DESIGN GUIDELINES SUFFOLK COUNTY DEPARTMENT OF HEALTH SERVICES TOXIC/HAZARDOUS MATERIAL TRANSFER FACILITY DESIGN GUIDELINES 1.0 GENERAL 1.1 Article 12 of the Suffolk County Sanitary Code requires that toxic/hazardous material

More information

Underground Storage Tanks

Underground Storage Tanks Underground Storage Tanks An Informational and Guidance Document for the University Community. Please contact Yale Environmental Health and Safety for latest Regulatory Requirements. A typical UST installation

More information

FY08 SEWER POINT REPAIRS BID TABULATION

FY08 SEWER POINT REPAIRS BID TABULATION 6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "

More information

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe. SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price

More information

SECTION 33 32 16.15 MEDIUM SIZED LIFT STATIONS

SECTION 33 32 16.15 MEDIUM SIZED LIFT STATIONS SECTION 33 32 16.15 MEDIUM SIZED LIFT STATIONS PART 1: GENERAL 1.01 SCOPE A. This Section contains the requirements for a fully operational duplex submersible sewage pump station. Medium sized lift stations

More information

SECTION 15410 GROUND WATER STORAGE TANKS

SECTION 15410 GROUND WATER STORAGE TANKS SECTION 15410 GROUND WATER STORAGE TANKS PART 1 GENERAL.01 SCOPE A. Section Includes Requirements for designing, fabricating, and erecting a welded steel ground storage tank..02 SYSTEM DESCRIPTION A. Design

More information

SECTION 02200 SUPPORT OF EXCAVATION

SECTION 02200 SUPPORT OF EXCAVATION SECTION 02200 PART 1 GENERAL 1.01 DESCRIPTION A. Section including specifications for design and installation of excavation support. B. Section also includes specifications for excavation support systems

More information

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors. SUBDRAINS AND FOOTING DRAIN COLLECTORS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subdrains B. Subdrain Cleanouts and Outlets C. Footing Drain Collectors D. Storm Sewer Service and Connections 1.02 DESCRIPTION

More information

SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE

SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE PART 1: GENERAL 1.01 SECTION INCLUDES PVC pressure pipe and fabricated fittings in nominal sizes 4-inches through 12-inches with cast iron pipe equivalent

More information

SECTION 01 50 00 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

SECTION 01 50 00 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS SECTION 01 50 00 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS PART 1 - GENERAL 1.01 GENERAL REQUIREMENTS A. Regulations: Comply with industry standards and applicable laws and regulations of authorities

More information

CHAPTER 5. Storm Sewer

CHAPTER 5. Storm Sewer CHAPTER 5 Storm Sewer A. Introduction All proposed developments shall have a properly designed and constructed storm water conveyance system. This chapter deals only with the conveyance system. Storm water

More information

IRRIGATION PUMPING Table of Contents - Section 900

IRRIGATION PUMPING Table of Contents - Section 900 IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS

More information