Specifications for Residential Property Owners Connection to New Public Sewer

Size: px
Start display at page:

Download "Specifications for Residential Property Owners Connection to New Public Sewer"

Transcription

1 Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the project is certified for operation. SCDC Ordinance No Introduction Currently structures are connected to their own septic tank and leach fields. Naturally occurring bacteria in the septic tank break down the solids that flow into the tank. The liquified solids and water then leave the tank as a blackwater effluent. Until this project is completed effluent will continue to be dispersed into the ground through the property owner s leach field. This new system replaces the leach field. A collector system of pipes and four transmission pumping stations will transport the effluent from the septic tanks to the above ground, lined, evaporation ponds, located near County Road A-1. In order to maintain sufficient depth of collector pipes to prevent freezing, at the individual property boundaries, property owners may have either a full gravity system from their tank to the connection point or, if the septic tank is too deep in the ground or down hill from the collector pipe, then a service lift pump will need to be installed in the tank to pump the effluent to the collector pipe. During the design phase, efforts were made to plan the system layout to minimize the number of tanks that will require pumping. Now that the construction contract is getting started, additional attention is being put to questioning borderline locations, again with the goal of installing a minimum number of service lift pumps in tanks. General Requirements All property owners are responsible for providing a certified septic tank, equipped with an effluent filter inside the outlet end of the tank and an accessible tank lid on a riser for inspections and maintenance. And the owners are responsible for installing the pipe line and for connection the tank to the new system. The project will provide a 1 ½ inch Schedule 80 PVC capped connection at the property line. The contractor will install a capped cleanout within the road R/W and a pipe marker over the top of the connection point. For those tanks that will need service lift pumps during the new system construction period, the sewer system contract will install the pumps and electrical connections as a part of the District contract. The owner is still required to provide the certified tank, 1

2 provide the installed pipe from the tank to the property line connection point and make the pipe connection. Property owners will be required to install a service lift pump if not before the current contract is closed, if one is needed. However, in keeping with the goal of minimizing the number of septic tank lift pumps to be required, the District s engineers will work with property owners ahead of the contractors work progress. To accomplish the necessary level checks, the tank outlet end lid needs to be exposed so the water level in the tank can be recorded. Following a logical routing for the pipe, between the tank and the property line, a distance and difference in elevation will be determined. They will be looking for an acceptable drop in elevation for gravity flow. The timing for doing this will be dictated by the contractor s plan of work. Their schedule will be posted outside at the District office and kept current weekly. If the existing tank needs to be replaced, then consideration needs to be given where to put the new tank to serve the building and provide gravity flow from the tank to the property line if at all possible. We all want to avoid having to install a service lift pump. Again, the District s engineers will work with property owners to place a new tank in a location to provide gravity fall from the tank outlet to the District s system. The goal is to make these determinations before the Contractor (Sundt) begins work on your street, thus any adjustments to connection points can be made before work is done, thus avoiding a change order and added cost to the District. The engineers are available now to do these checks; see second paragraph below under Permits and Inspections. Permits and Inspections Sewer connection permits and applicable fees are required before any work is started by the property owner. Contact the District s office, located at Mahogany Way, Spalding Tract, Susanville, CA Septic tank and sewer line inspections must be requested at least 24 hours in advance. Contact the District s engineers at the field office trailer next to the District Office or call between 9AM and 11AM, Monday through Thursday for an inspection appointment. Inspection services are outlined in a later section of this document. Materials and Installation Requirements All of the work to be done by the property owner can be done at any time the sooner the better. However, the existing leach field must continue to be used until the contractor s (Sundt s) work is completed and the project is certified for operation. Existing septic tanks may be used if they pass inspection, including having a 2

3 serviceable baffle, leak test and installation of outlet filter and inspection/maintenance riser with lid that meet the specifications from Exhibit F of Ordinance No , following: Tank Source Size Tank Installation Cook s Concrete Products, Redding, or equal. Size, as determined by the District. The minimum tank size shall be 1000 gallon capacity. Septic tanks buried 3' or deeper or subject to traffic loading may require certification for loading conditions. Specify a 1 ½" or 2" PVC wall sleeve for the tank outlet to match the size of the lateral line needed to tie to the District s system. Use 4" of well-compacted sand, pea gravel or 3/4" minus rock under the tank, as bedding material. Smooth the bedding material to create a level pad with a tolerance of 1/4" in 20'. If native soil is not suitable for tank support, the District may require overexcavation and more sand or pea gravel. Call for inspection prior to setting tank. The Inspector will inspect the tank cavity, and should be present for the placing of the tank. Around and under external piping, use compacted 3/4" minus rock. Compact the backfill over and around tank to a minimum of 85% maximum dry density. Tank watertight test: Septic tank inlet and outlet pipes are plugged and the tank filled with clean water to the top. Twenty-four hours later the water level is to be inspected. The tank is either certified or use if the drop in water level is less than 1/4" from the top, or if the tank does not hold water, the owner will be required to replace the tank and a subsequent inspection will be made as indicated above after a new tank is installed. Access Riser Orenco, Roseburg , 24" diameter or NDS24-RIS Round Rise 24" TUF TITE 6" tall Riser and NDS 24-RISL Domed Lid 24" TUF TITE available from J. W. Woods, Susanville. Riser Installation Install with lids 1-3" above the surrounding surface. Bond with two-part epoxy from Orenco, cured 24 hours before backfilling. Call for inspection prior to backfilling. Lids to match riser size, installed with gasket and hex bolts. 3

4 Access lid sealed with a neoprene O-ring, 3 bolt design with ½" stainless bolts, with two cast recessed lifting bars. Lids to say Sewer or S. Effluent Filter Pipe Effluent Filter shall be installed inside the septic tank at the outlet end. The filter shall be Orenco Biotube Effluent Filter #FT or equal. 1 ½" or 2" SCH 40 PVC or SDR 17 HDPE. Fittings and service cleanouts are to be of the same type, class, and grade of material as the pipe or as approved by the engineer. Slope will be at least 1/8" per foot or as directed by the District. Use a minimum of bends and fittings. Use no bends greater than 45 O unless approved by the District. Check for water tightness of pipe joints by blocking the low end and installing an elbow and 5 foot high stand pipe at the high end of the pipe. Fill with water and let stand for 24 hours. A 1/4" drop in 24 hours is acceptable. Trace Wire Install 12 gauge solid-core trace wire, green, from the cleanout to the tank riser, wrapping around each twice. Connect to cleanout at ground level. Secure to pipe also every 20' and at all bends. Make splices and connections with waterproof heat shrink splice kits, or approved underground connector. Clean-Outs One at least five feet from the building, and one at least every 100 feet. Caps should be installed slightly below grade. In improved areas, (such as driveways) cover with a Brooks Type 1-RT or 3T box. Backfill Call for an inspection of the gravity line prior to backfilling. Thoroughly compact bedding and backfill material under and around service piping connection to septic tank so as to prevent differential settling and leakage into or out of connection. Provide 4" pipe bedding of 3/4" minimum crushed rock, pea gravel, or sand, free of sticks, stones, or other debris. Install piping and provide a minimum of 12 inches of pipe bedding material as pipe zone material around and above pipe. 4

5 In improved areas, such as driveways, above the pipe zone, use 3/4" crushed rock and compacted to 95% of maximum dry density. Compacted native material may be used in unimproved areas, such as lawns. Minimum cover is 30 inches unless authorized by the District. Sewer Lines Installations near existing waterlines and wells shall meet the Near Water Lines following: and Wells Near domestic water Parallel with water lines A gravity sewer line shall not be placed within one foot horizontally of a domestic water line. Pressure sewer lines from pumped septic tanks shall not be placed within 10 feet horizontally of a domestic water line unless it is placed inside a larger diameter SCH 80 PVC or DR 9.0 HDPE sleeve. Crossing a water line A minimum of 4 inches of vertical separation must be maintained above or below the water line at the sewer crossing. If the gravity sewer line crosses above, or within one foot below the water line, the sewer line must be sleeved inside a larger diameter Schedule 80 PVC or DR 9.0 HDPE sewer pipe for a minimum of 4 feet horizontally on each side of the water line. Near wells Schedule 40 PVC or HDPE sewer pipe is to be sleeved inside a larger diameter Schedule 40 PVC or HDPE sewer pipe when within 25 feet horizontally of a well. Sewer Lines Near Property Lines Sewer Lines Near Buildings Existing Leach Fields Sewer lines shall be installed at least one foot horizontally away from any property lines. Sewer lines shall be installed at least two feet horizontally away from any building. Existing leach fields shall be permanently abandoned after connecting to the community sewer system. A final inspection and certification will be performed to verify that all leach lines have been disconnected and abandoned with at least ten (10) feet of separation between the septic tank and the abandoned leach line. 5

6 At this time, and during System construction during 2006, the septic tank lift pump specifications and installation requirements are not included in this write-up. Their installation will be done by the Contractor as a part of their contract. The District assumes maintenance responsibility and ownership of the septic tank lift pump one year from the date of the system s final inspection. During this first year period, routine maintenance and repairs of the service lift pump, other than those due to improper installation, will be performed by the District s operators. Improper installations will be correct as warranty work under the Spalding Community Sewer System construction contract. Summary Responsibilities District Property Owner Sundt Construction Issue Connection Permit. Obtain Connection Permit. Construct Work with property owner Provide certified tank, used evaporation ponds. where grades may be -Uncover tank lids Install all pipes within a problem. -Pump sewage the road R/W Perform inspections. -Fill tank with water for 24 Install service lateral for hour leak test existing tanks only -Install filter at outlet from pipe main line to -Install access lid or the property line. Install new tank. Install service lift pump Install pipe from the tank. pkg. in tanks where to the property line. required, including Connect to new service electrical connections. lateral when system is complete and approved Disconnect and permanently abandon leach field. 6

7 Inspection Services by Lampe Engineering Septic System Inspections 1A Septic tank has been located, access manholes exposed and water level checked for gravity flow. 1B Septic tank pumped and inspected for structural defects, inflow of ground water, functioning baffle, inlet and outlet fittings in place. If the septic tank fails the inspection, the owner will be required to replace the tank and a subsequent inspection will be made after a new tank is installed. 2 Septic tank inlet and outlet pipes are plugged and the tank filled with clean water to the top. 24 hours later the water level is to be inspected. The tank is certified for use or if the tank does not hold water, the owner will be required to replace the tank and a subsequent inspection will be made after a new tank is installed. N A new septic tank must be supplied by a certified manufacturer, inspected for proper installation, structural defects and water tightness as outlined above for existing tanks. 3A Septic tank will be inspected for installation of effluent filter and access hole riser and lid. 3B Pipe line to connect tank to community service will be inspected for location, grade, air pockets, depth, separation from potable wells or sleeved, water tightness and type of pipe. Final - When the Community Sewer System Project is completed and certified for operation, the individual septic tanks will be disconnected from the leach field and connected to the new sewer collection system. The individual septic systems will be inspected to insure that the existing leach field has been abandoned and permanently disconnected from the septic tank outlet, the septic tank outlet is properly connected to the new effluent service connection line, and community system. And abandoned septic tanks are pumped and backfilled with sand to ensure they do not collapse. 7

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,

More information

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees. The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:

More information

Beacon Hill Sewer District Standard Specifications

Beacon Hill Sewer District Standard Specifications Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions

More information

Subsurface Sewage Treatment System (SSTS) Self-Install Guide

Subsurface Sewage Treatment System (SSTS) Self-Install Guide Subsurface Sewage Treatment System (SSTS) Self-Install Guide Hubbard County Environmental Services Updated: February 2010 Introduction The purpose of this guide is to familiarize the homeowner with some

More information

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes)

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) Maintenance Office Administrative Office Billing Office 530-426-7802 530-426-7800 916-332-4872

More information

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation 644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING

More information

Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System

Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System An application for the construction or alteration of an individual subsurface sewage disposal system shall

More information

EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines

EXHIBIT A. Technical Specifications for Water and Sewer Service Lines EXHIBIT "A Technical Specifications for Water and Sewer Service Lines Water and Sewer Line Bedding and Backfill: Drawings show cross-section of trench, pipe laid on top of 6" min. bedding material, bedding

More information

MS-6/2009 Model Specification and Checklist for Polyethylene (PE) Pipe for the Sliplining of Sewers

MS-6/2009 Model Specification and Checklist for Polyethylene (PE) Pipe for the Sliplining of Sewers MS-6/2009 Model Specification and Checklist for Polyethylene (PE) Pipe for the Sliplining of Sewers The Plastics Pipe Institute March 2009 1 DISCLAIMER This guideline has been prepared by the Plastics

More information

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions The purpose of this application example is to provide assistance to small and medium sized rural communities in the drafting of documents necessary for the efficient operation of water, wastewater, and

More information

FY08 SEWER POINT REPAIRS BID TABULATION

FY08 SEWER POINT REPAIRS BID TABULATION 6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "

More information

SECTION 02732 BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers.

SECTION 02732 BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers. SECTION 02732 BUILDING SEWERS PART 1 GENERAL 1.01 SECTION INCLUDES A. Lateral piping, fittings, and accessories. B. Connection of building sanitary drainage system to municipal sewers. 1.02 REGULATORY

More information

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, Storm Drain Installation, of these Standard Provisions. SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and

More information

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors. SUBDRAINS AND FOOTING DRAIN COLLECTORS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subdrains B. Subdrain Cleanouts and Outlets C. Footing Drain Collectors D. Storm Sewer Service and Connections 1.02 DESCRIPTION

More information

C. Trenching, Backfilling, and Compacting: STD SPEC H. Polyethylene Sheet or Tube Encasement: STD SPEC

C. Trenching, Backfilling, and Compacting: STD SPEC H. Polyethylene Sheet or Tube Encasement: STD SPEC STANDARD SPECIFICATION SECTION 15090 BLOW-OFF ASSEMBLIES PART 1 - GENERAL 1.01 DESCRIPTION This section includes materials, installation, and testing of blow-off assemblies. Unless otherwise noted on the

More information

PROCEDURES TO BE FOLLOWED IN APPLYING FOR A PERMIT TO INSTALL AN ON-SITE WASTEWATER SYSTEM (OWS)

PROCEDURES TO BE FOLLOWED IN APPLYING FOR A PERMIT TO INSTALL AN ON-SITE WASTEWATER SYSTEM (OWS) PROCEDURES TO BE FOLLOWED IN APPLYING FOR A PERMIT TO INSTALL AN ON-SITE WASTEWATER SYSTEM (OWS) 1. Complete the attached application and plot plan. Return the application and plot plan to the Routt County

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

SECTION 15062 POLYVINYL CHLORIDE GRAVITY SEWER PIPE AND FITTINGS

SECTION 15062 POLYVINYL CHLORIDE GRAVITY SEWER PIPE AND FITTINGS SECTION 15062 POLYVINYL CHLORIDE (PVC) GRAVITY SEWER PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for the manufacture and installation of polyvinyl chloride,

More information

CITY OF NEEDLES SEPTIC SYSTEM REQUIREMENTS

CITY OF NEEDLES SEPTIC SYSTEM REQUIREMENTS CITY OF NEEDLES SEPTIC SYSTEM REQUIREMENTS Area of Disposal Fields and Seepage Pits The minimum effective absorption area in disposal fields in square feet (m²) and in seepage pits in square feet (m²)

More information

SHORELINE SANITATION

SHORELINE SANITATION Septic System Report On:

More information

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

MUNICIPALITY OF ANCHORAGE

MUNICIPALITY OF ANCHORAGE MUNICIPALITY OF ANCHORAGE Mayor Dan Sullivan COMMUNITY DEVELOPMENT DEPARTMENT ON-SITE WATER & WASTEWATER PROGRAM 4700 Elmore Road P.O. Box 196650 Anchorage, AK 99519-6650 (907) 343-7904 fax (907) 343-7997

More information

Town House 11265 Center Highway North Huntingdon, PA 15642

Town House 11265 Center Highway North Huntingdon, PA 15642 APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House

More information

SUMMIT COUNTY COMBINED GENERAL HEALTH DISTRICT

SUMMIT COUNTY COMBINED GENERAL HEALTH DISTRICT Slide 1 Point of Sale Inspections for Property Transfers SUMMIT COUNTY COMBINED GENERAL HEALTH DISTRICT Slide 2 What does the rule say? Effective September 1, 2008, prior to a property transfer, any property

More information

SANITARY SEWER SPECIFICATIONS

SANITARY SEWER SPECIFICATIONS SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,

More information

B. Trenching, Backfilling, and Compacting: STD SPEC 02223. A. Submit submittal packages in accordance with Standard Specification Section 01300

B. Trenching, Backfilling, and Compacting: STD SPEC 02223. A. Submit submittal packages in accordance with Standard Specification Section 01300 STANDARD SPECIFICATION SECTION 15065 PLASTIC (PVC) GRAVITY SEWER PIPE PART 1 - GENERAL 1.01 DESCRIPTION A. This section includes materials, installation, and testing of PVC gravity sewer pipe conforming

More information

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe. SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price

More information

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials. PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,

More information

CHAPTER 6 - SANITARY SEWER

CHAPTER 6 - SANITARY SEWER CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings

More information

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent

More information

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of

More information

Sanitary Sewer Design Standards

Sanitary Sewer Design Standards Sanitary Sewer Design Standards Rogue Valley Sewer Services Revised 8/29/2012 Contents 1. Plan Review Procedures and Submittal Requirements 3 1.1 Pre-Design Meeting: 3 1.2 Initial Design Submittal: 3 1.3

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

Sewage Compliance Form Instructions

Sewage Compliance Form Instructions CITY OF JOHNSTOWN DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT 401 MAIN STREET ROOM 200 JOHNSTOWN, PA 15901 814-533-2017 FAX 814-539-5816 RENEE K. DALY DIRECTOR Sewage Compliance Form Instructions 1)

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems

Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems The septic tank-absorption field sewage treatment system is composed of two major elements; the

More information

Customer Procedures and General Information for Sewer Customers

Customer Procedures and General Information for Sewer Customers Customer Procedures and General Information for Sewer Customers Helpful Hints for Customers Ordinance Review of District and Customer Responsibility of New and Existing Sewer Lines Material and Manner

More information

Sanitary Sewer Design, Construction & Maintenance Manual

Sanitary Sewer Design, Construction & Maintenance Manual Sanitary Sewer Design, Construction & Maintenance Manual Version Issued: September 2010 Ryan Eastwood, P.E. Director of Engineering and Utilities City of Ashland, Kentucky Table of Contents 1) Purpose.....

More information

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL 155 E. Front Street (rear) Lititz, PA 17543 Phone (717) 625-1930 Fax (717) 625-1931 Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL CONSTRUCTION SPECIFICATIONS AND DETAILS

More information

SECTION 300 STORM SEWER AND SUMP PUMP DRAIN SYSTEMS

SECTION 300 STORM SEWER AND SUMP PUMP DRAIN SYSTEMS SECTION 300 STORM SEWER AND SUMP PUMP DRAIN SYSTEMS Section Title Page 301 General................................... 18 302 Materials.................................. 18 303 Design Requirements........................

More information

SECTION 5: SANITARY SEWER SYSTEM DESIGN

SECTION 5: SANITARY SEWER SYSTEM DESIGN SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities

More information

GASTON COUNTY BUILDING INSPECTIONS MANUFACTURED HOME PERMIT REQUIREMENTS

GASTON COUNTY BUILDING INSPECTIONS MANUFACTURED HOME PERMIT REQUIREMENTS GASTON COUNTY Department of Building Inspections Mailing Address: P. O. Box 1578, Gastonia, NC 28053-1578 Phone:(704) 866-3155 Street Address: 128 West Main Avenue, Gastonia, NC 28052 Fax:(704) 866-3966

More information

City of Shelbyville Site Inspection Checklist

City of Shelbyville Site Inspection Checklist City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather

More information

Septic System Owner s Manual

Septic System Owner s Manual Septic System Owner s Manual Sponsored by: copyright 2013 No part of this publication may be reproduced without our consent. www.callbrownies.com Brownie s Septic and Plumbing has provided quality service

More information

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant

More information

Emerging Technologies in Wastewater Collection Systems

Emerging Technologies in Wastewater Collection Systems Keville Enterprises Emerging Technologies in Wastewater Collection Systems Douglas McCutchen, CCM Brian Karmasin, P.E., BCEE CMAA Annual Conference Oct 2008 San Francisco, California Today s s Presentation

More information

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm: Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section

More information

CHAUTAUQUA COUNTY DEPARTMENT OF HEALTH DIVISION OF ENVIRONMENTAL HEALTH SERVICES

CHAUTAUQUA COUNTY DEPARTMENT OF HEALTH DIVISION OF ENVIRONMENTAL HEALTH SERVICES CHAUTAUQUA COUNTY DEPARTMENT OF HEALTH DIVISION OF ENVIRONMENTAL HEALTH SERVICES Hall R. Clothier Building 7 N.Erie St. Mayville, NY 14757 Phone: 716-753-4481 or 753-4798 Fax: 716-753-4344 VINCENT W. HORRIGAN,

More information

Septic System Evaluation Report

Septic System Evaluation Report Septic Check Inspections Cover Page Septic System Evaluation Report Inspection prepared for: John Smith Date of Inspection: 2/6/2015 Time: 9:00am Inspector: Matthew Raumikaitis GSDI #159 PO Box 831, Derry,

More information

SECTION 400 SANITARY SEWER SYSTEM

SECTION 400 SANITARY SEWER SYSTEM SECTION 400 SANITARY SEWER SYSTEM Section Title Page 401 General................................... 25 402 Materials.................................. 25 403 Design Requirements........................

More information

Residential On-Site Septic System Training ROSS(T)

Residential On-Site Septic System Training ROSS(T) Residential On-Site Septic System Training ROSS(T) Provided By: Tuolumne County Environmental Health E-mail address: rkostlivy@co.tuolumne.ca.us Phone Number: 209-533-5633 1 A Homeowner can evaluate the

More information

STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200 STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES PART 1 - GENERAL A. Description This section includes materials, testing, and installation of precast concrete

More information

CHAPTER 32 PLUMBING CODE

CHAPTER 32 PLUMBING CODE CHAPTER 32 PLUMBING CODE 32.01 DEFINITION Plumbing for the purpose of this chapter is hereby defined as follows: (a) As is stated in Section 145.01 (1), (a), (c), (d), and (e) of the Wisconsin Statutes.

More information

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection

More information

OVERVIEW OF SIDE SEWER REQUIREMENTS

OVERVIEW OF SIDE SEWER REQUIREMENTS NOVATO SANITARY DISTRICT MARIN COUNTY, CALIFORNIA OVERVIEW OF SIDE SEWER REQUIREMENTS 2001 OVERVIEW OF SIDE SEWER REQUIREMENTS TABLE OF CONTENTS Section 1. GENERAL INFORMATION... 1 1-01 Jurisdiction...

More information

505.3.6 For a building with a crawl space, see Figure 10. 505-1

505.3.6 For a building with a crawl space, see Figure 10. 505-1 505 WATER SERVICE INSTALLATION 505.1 DEFINITION A service line is comprised of the piping and related appurtenances including the connection installed from the Des Moines Water Works water main to the

More information

Northeast Tri County Health District

Northeast Tri County Health District Northeast Tri County Health District Standards and Guidance for Performance, Application, Design, and Operation & Maintenance Dosing Gravity Drainfield Systems Based on the Washington State DOH of Health

More information

CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1

CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1 CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm

More information

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...

More information

Unit 2 - Maintenance 2-1 Maintenance Recommendations

Unit 2 - Maintenance 2-1 Maintenance Recommendations Unit 1 - Design Criteria 1-1 General Specifications and Disposal Area Options 1-2 Filter Requirements, Sand Specifications, and Installation Requirements 1-3 Construction of the Sand Filter Unit 2 - Maintenance

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION Design Criteria Drainage Area The drainage area for storm drain inlets shall not exceed one acre. The crest elevations of these practices shall

More information

Section 02702 SEWER PIPE INSTALLATION AND TESTING

Section 02702 SEWER PIPE INSTALLATION AND TESTING PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete

More information

RECOMMENDED PROGRAM FOR WELL AND SEPTIC SYSTEM REAL ESTATE TRANSACTION INSPECTIONS

RECOMMENDED PROGRAM FOR WELL AND SEPTIC SYSTEM REAL ESTATE TRANSACTION INSPECTIONS Contra Costa Environmental Health 2120 Diamond Blvd., Suite 200 Concord, CA 94520 Phone: (925) 692-2500 Fax: (925) 692-2504 www.cchealth.org/eh/ RECOMMENDED PROGRAM FOR WELL AND SEPTIC SYSTEM REAL ESTATE

More information

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions. SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

CLEANING, INSPECTION, AND TESTING OF SEWERS

CLEANING, INSPECTION, AND TESTING OF SEWERS CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and

More information

A Practical Guide to Class 2 Sewage Treatment Systems (Leaching Pit)

A Practical Guide to Class 2 Sewage Treatment Systems (Leaching Pit) A Practical Guide to Class 2 Sewage Treatment Systems (Leaching Pit) Access Hatch Swale to take away drainage 150 mm (6 ) Inlet Open jointed material 500 mm (24 ) 900 mm (3 ) Impermeable soil High Groundwater

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

Septic System Design Manual

Septic System Design Manual Septic System Design Manual Prince George s County Health Department Largo Government Center 9201 Basil Court, Suite 318 Largo, Maryland 20774 (Office) 301-883-7681 (Fax) 301-883-7266 (January 2007) Table

More information

Close-Out Documents... 9

Close-Out Documents... 9 Water and Sanitary Sewer Service Connection Requirements Service Connection Requirements... 1 Application for Services... 2 Water Meter Application... 2 Wet Tap/Tie-in Connection Requirements... 3 Meter

More information

SANITARY SEWER SYSTEMS

SANITARY SEWER SYSTEMS SANITARY SEWER SYSTEMS I. Sanitary sewer size and slope design. A. Minimum size is 8 inch. B. Minimum flow velocity is 2 feet per second, 2 fps. C. Maximum flow velocity shall be 11 fps. D. Larger lines

More information

Constructing Cistern Installations

Constructing Cistern Installations Constructing Cistern Installations for Stormwater Management Downspout Screened inlet Overflow David McDonald & Bob Spencer Seattle Public Utilities Installing Rain Gardens & Cisterns Trainings for contractors,

More information

DIVISION 4300 STORM DRAINAGE

DIVISION 4300 STORM DRAINAGE DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES 33 00 00 SITE UTILITIES SECTION INCLUDES Domestic Water Fire Water Service Water Well Sanitary Sewer Storm Drains Foundation Drainage RELATED SECTIONS 03 30 00 Concrete 21 00 00 Fire Suppression - Sprinklers 22 00 00 Plumbing

More information

Learning Objectives. History of Vacuum Testing for Precast. Vacuum Testing. Terminology and purpose

Learning Objectives. History of Vacuum Testing for Precast. Vacuum Testing. Terminology and purpose : It Just Sucks! Presented by: Darryl Cloud Concrete Sealants, Inc. Learning Objectives In this course, you will learn: Terminology for Watertightness Equipment Tips, Tricks, and FAQ s History of Vacuum

More information

INDEX. Sec. No. Items Page Nos.

INDEX. Sec. No. Items Page Nos. INDEX Sec. No. Items Page Nos. 1. Types of Pipe............... MSSP- 2 2. Concrete Pipe............... MSSP- 2 thru MSSP-3 3. ABS and PVC Truss Pipe............... MSSP- 3 4. ABS and PVC Solid Wall Pipe...............

More information

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection

More information

Gas Meter Clearances and Service Installation Requirements

Gas Meter Clearances and Service Installation Requirements March 2015 Gas Meter Clearances and Service Installation Requirements Builder/Owner/Developer Requirements Call PSE s Customer Construction Services 1-888-321-7779 or visit PSE.com/CustomerConstruction

More information

ONSITE SEWAGE TREATMENT AND DISPOSAL SYSTEM REQUIREMENTS

ONSITE SEWAGE TREATMENT AND DISPOSAL SYSTEM REQUIREMENTS Onsite Sewage Treatment & Disposal System Requirements ONSITE SEWAGE TREATMENT AND DISPOSAL SYSTEM REQUIREMENTS 1. City of Ventura onsite sewage treatment and disposal system (Septic system) permit application

More information

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1001 SOUTH LEECHBURG HILL LEECHBURG, PA 15656 Phone: 724-845-9355 Fax: 724-845-1186 SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1. General

More information

DIVISION III SIDE SEWERS AND BUILDING SEWERS

DIVISION III SIDE SEWERS AND BUILDING SEWERS DIVISION III SIDE SEWERS AND BUILDING SEWERS III-1.000 DESCRIPTION 1.010 General A. All connections to public sanitary sewers, by connecting to an existing side sewer or building sewer, or by tapping an

More information

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER Village of Shorewood, Wisconsin SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER Prepared By: Thomas A. Zoulek, P.E., LEED A.P. Vice President Mid City Plumbing & Heating

More information

50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance

50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance 02/15 Labko GRP cesspools Instructions for installation, operation and maintenance Reliable solutions Wastewater treatment systems Contents 1 LABKO CESSPOOLS... 3 1.1 GENERAL... 3 1.2 IMPORTANT TO KNOW

More information

SECTION 02630 STORM DRAINAGE SYSTEM

SECTION 02630 STORM DRAINAGE SYSTEM SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE

More information

COUNTY OF SUFFOLK STEVEN BELLONE SUFFOLK COUNTY EXECUTIVE STANDARDS. James L. Tomarken, MD, MPH, MBA, MSW Commissioner of Health Services

COUNTY OF SUFFOLK STEVEN BELLONE SUFFOLK COUNTY EXECUTIVE STANDARDS. James L. Tomarken, MD, MPH, MBA, MSW Commissioner of Health Services COUNTY OF SUFFOLK STEVEN BELLONE SUFFOLK COUNTY EXECUTIVE SUFFOLK COUNTY DEPARTMENT OF HEALTH SERVICES DIVISION OF ENVIRONMENTAL QUALITY STANDARDS APPROVAL OF PLANS AND CONSTRUCTION - - SEWAGE DISPOSAL

More information

Preventing water damage in the basement

Preventing water damage in the basement Preventing water damage in the basement Thousands of home insurance claims are filed every year. Some losses are major, others aren t, but they re always an inconvenience and usually avoidable! As prevention

More information

Chapter 7 Plumbing Connections

Chapter 7 Plumbing Connections Chapter 7 Plumbing Connections 7-1 General All plumbing equipment and installations must be designed, constructed, and installed in accordance with this code and where not specific, to the applicable provisions

More information

OAR52 A-1 (September, 1981)

OAR52 A-1 (September, 1981) APPENDIX A SEWER PIPELINES (1) MINIMUM REQUIREMENTS FOR SEWER - PIPELINES (a) Capacity: Sewers shall be of such diameter as to pass without overflow, bypass, or back flow onto damageable property of a

More information

Jay R. Smith Mfg. Co.

Jay R. Smith Mfg. Co. Jay R. Smith Mfg. Co. Automatic Backwater Valve SMITH CUSTOMER DRIVEN FLOOD-GATE FEATURES Index Page Flood-Gate Features and Applications 2 How Flood-Gate Works 3 Flood-Gate Operation & Approvals 4 Valve

More information

Frequently Asked Questions about Septic Systems

Frequently Asked Questions about Septic Systems What is a septic tank? Where is my septic tank located? Do septic tanks last forever? What should and should not go into my septic tank? How can I tell if my septic tank is working properly? Why should

More information

Lets Think-TANK Septic Tank Purpose & Function

Lets Think-TANK Septic Tank Purpose & Function Barry-Eaton District Health Department Caring for the Community Since the 1930 s Lets Think-TANK Septic Tank Purpose & Function Filter Septic Tank Purpose & Function Collects and treats wastewater Separates

More information

SECTION 15200 GRAVITY SANITARY SEWERS. A. Gravity sanitary sewers and appurtenances, including stacks and service connections.

SECTION 15200 GRAVITY SANITARY SEWERS. A. Gravity sanitary sewers and appurtenances, including stacks and service connections. SECTION 15200 GRAVITY SANITARY SEWERS PART 1 GENERAL.01 SCOPE A. Gravity sanitary sewers and appurtenances, including stacks and service connections..02 SUBMITTALS A. Conform to requirements of Section

More information

astewater Septic Systems

astewater Septic Systems QUICK FACTS The drop on water Wastewater Septic Systems Wastewater is often referred to as sewage. This is water that has been used for washing, flushing, or manufacturing processes by homes, businesses,

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

SECTION VALVE BOXES AND METER VAULTS

SECTION VALVE BOXES AND METER VAULTS SECTION 03 48 20 VALVE BOXES AND METER VAULTS PART 1: GENERAL 1.01 SECTION INCLUDES A. Valve boxes for water and cleanout boxes for wastewater service. B. Meter boxes for water service. C. Meter vaults

More information

City Business Registration Number Signature Title

City Business Registration Number Signature Title INVITATION TO BID BID FORM Golf Course Barn Lift Station BID NO. 2013-13 City of Carlsbad 101 N. Halagueno Carlsbad, New Mexico 88220 or PO Box 1569 Carlsbad, New Mexico 88221 BID DUE DATE: Please submit

More information