Fleet Management of Construction Equipment- A Case Study of Road

Size: px
Start display at page:

Download "Fleet Management of Construction Equipment- A Case Study of Road"

Transcription

1 Fleet Management of Construction Equipment- A Case Study of Road Er.Roshan H.Bhoye * Student of Masters of Engineering SSGB COE&T Bhusawal,India roshanbhoye92@gmail.com Prof.P.M.Attarde Associate Professor SSGB COE&T Bhusawal,India vattarde75@rediffmail.com Abstract: Construction Equipment fleet management at its basic level addresses the problem of managing fleets of various construction equipments stationary as well as mobile such as dumpers, excavators, shovels, scrapers, belt conveying systems, graders, pavers, rollers, cranes, HMA plant, RMC plant, transit mixers, etc. Use of Equipment fleet management increases the productivity of overall site and increases the profitability through a proper equipment selection & optimization, production monitoring, tracking of equipments, maintaining a maintenance schedule, etc. Use of various sophisticated tools & techniques can be used for the same such as the telematics, GPS navigation, information transmission systems & various software s. Keywords: Fleet management, Equipment optimization, benefit analysis, theoretical fleet, and available fleet. L 1.0 INTRODUCTION arge contractors have been steadily increasing their investment in construction equipment to satisfy their needs in response to increased construction volume in recent years. The technical advancement of earthmoving equipment during the 20th century includes many improvements in key parts of machines making the machine mechanically more efficient. Hence major large construction operations and mega projects uses a large number of various construction equipments. This group of equipments collectively forms a Fleet.[1] The fleet operations have become complex due to a large number of manufacturers, various capacity and sizes of equipment available which makes the equipment selection a crucial task. After equipment selection the complexity further increases to optimize the size and number construction equipments in the fleet.[2] Moreover large and highly competitive markets for infrastructure projects especially BOT type of contract, enforces the contractors to complete the project as early as possible to start regaining the investments.[3] Fleet Management consist of conceptual sub-components such as equipment selection and assignment, equipment optimization, maintenance, production monitoring, material and position monitoring, etc.[4] * Corresponding Author The scope of this work is limited to equipment optimization and benefit analysis at the site through equipment production analysis. The case selected for the project is a highway construction project where considerable amount earthwork is involved. This project mainly aims to achieve optimum equipment utilization by construction equipment s fleet management.[5] This paper explains, To study the concept of fleet management for construction project and Equipment optimization and benefit analysis. 2.0 LITERATURE REVIEW According to Saurabh Rajendra Kadam, Prof. Dhananjay S Patil (2013),The main goal of the research is equipment optimization and benefit analysis at the site through equipment production analysis. Large numbers of construction equipment are required on construction site. The efforts of contractors are to constantly push machine capabilities forward. As the array of useful equipment expand, the importance of careful planning and execution of construction equipment s increases. The objective of the project is to predict the fleet production rate and to optimize the number and size of equipment s in the fleet to match the equipment to project situations. Equipment economics is taken into consideration for the optimization. [1]

2 Sujay Dandwate explains that Fleet management can be defined by three basic components: Equipment assignment and optimization, Production monitoring, and Position and material monitoring. Equipment assignment and optimization is the primary reason many construction companies choose to implement fleet management systems in the first place. By enabling the scheduling and assignment of all types of equipment from multiple manufacturers as well as shift change management from a central office location. The second critical element, production monitoring, is the ability to review information on machine cycle time, payload, loading performance and other key operational parameters. [2] Larry Orcutt (7 JUNE 2012) has examine the Division of Equipment the Caltrans Division of Research and Innovation (DRI) receives and evaluates numerous research problem statements for funding every year. DRI conducts Preliminary Investigations on these problem statements to better scope and prioritize the proposed research in light of existing credible work on the topics nationally and internationally. Online and print sources for Preliminary Investigations include the National Cooperative Highway Research Program (NCHRP) and other Transportation Research Board (TRB) programs, the American Association of State Highway and Transportation Officials (AASHTO), the research and practices of other transportation agencies, and related academic and industry research. [3] The Taxicab, Limousine, and Para transit Foundation explains that Maintenance is a complex activity involving such variants as equipment, statistics, cost administration, productive activity, and business. These variants must be well administered in order to be efficient. In the past, maintenance decisions have been limited to what kind of action to use (corrective or preventive) and to the definition of such variables as best frequency, best predictive technique, and best information organization. Today, due to the changing role of fleet management and maintenance, decisionmakers also must also consider the coordination of the human, physical, logistical, and logical structures of maintenance, which in turn must be combined with previous variables to create an integrated administration. [4] Construction equipment are used in all types of construction work viz highway work, building construction, bridges, dams, tunnels etc. but the fleet management of construction equipment are used in industry very rarely. It has proven its best results in various fields of construction, it is quality improvement technique in construction equipment and which reduces the cost of project as we know the total cost of project is depending on equipment. Position and material monitoring is the third key component. At its most basic level, fleet management is about monitoring equipment location for an entire fleet but beyond that, it also helps to ensure that machines are in the right location and that the amount and type of material they are moving is accurate. The study revealed to analyze performance factors such as dump movement and haul road congestion to boost overall site productivity. 3.0 MATERIALS AND METHODS Fleet management can be defined by three basic components of Equipment assignment and optimization, Production monitoring, and Position and material monitoring. Equipment assignment and optimization is the primary reason many construction companies choose to implement fleet management systems in the first place. By enabling the scheduling and assignment of all types of equipment from multiple manufacturers as well as shift change management from a central office location. The second critical element, production monitoring, is the ability to review information on machine cycle time, payload, loading performance and other key operational parameters. Fleet management provides visibility in real time to this kind of data which can be tracked by individual machine or operator, groups of machines, specific sites or an entire fleet enabling miners to make timely changes to improve loading performance and increase payload predictability. Position and material monitoring is the third key component. At its most basic level, fleet management is about monitoring equipment location for an entire fleet but beyond that, it also helps to ensure that machines are in the right location and that the amount and type of material they are moving is accurate. The study revealed to analyze performance factors such as dump movement and haul road congestion to boost overall site productivity Methodology 1. Study the actual composition of fleet at construction site. 2. Equipment optimization by Equipment productivity analysis using performance charts and other parameter such as distance, speed, number of trips, capacity, cycle time etc.

3 3. Study the site layout and site conditions with the planning & designing for current equipment utilization at the site. 4. Perform Benefit analysis by Comparing the actual and optimized fleet performance. 3.1 Equipment assignment and optimization Equipment assignment and optimization is the primary reason many construction companies choose to implement fleet management systems in the first place. By enabling the scheduling and assignment of all types of equipment from multiple manufacturers as well as shift change management from a central office location, fleet management helps minimize unproductive machine wait time and optimize equipment usage on site. 3.2 Production monitoring The second critical element, production monitoring, is the ability to review information on machine cycle time, payload, loading performance and other key operational parameters. Fleet management provides visibility in real time to this kind of data which can be tracked by individual machine or operator, groups of machines, specific sites or an entire fleet enabling fleet managers to make timely changes to improve loading performance and increase payload predictability. 3.3 Position and material monitoring Position and material monitoring The third key component. At its most basic level, fleet management is about monitoring equipment location for an entire fleet but beyond that, it also helps to ensure that machines are in the right location and that the amount and type of material they re moving is accurate. This type of data can be used to alert operators to misroutes before mistakes or safety hazards occur, as well as to analyse performance factors such as dump movement and haul road congestion to boost overall site productivity. 3.4 Fleet Problem and Action Plan The construction of dams, levees, highways, airports, commercial buildings and industrial plants utilize some type of earthmoving operations. Earth-moving is must on every construction site. Moreover all the mining operations include excavation and haulage. Earth-moving operations include excavating, hauling, placing, and compacting. Consider a virtual problem of moving of Aggregate stockpiled at a certain location A to certain location B which is 2 Km away. The total stockpile volume is 10,000 meter cube Equipment Selection The various factors governing equipment selection in earthmoving operations can be summarized as follows: 1) Budget & schedule. 2) Range of total size of work. (i.e. total of amount material to be moved) 3) Material condition. (i.e. if soil weather wet or dry) 4) Distance of soil movement. 5) Hauling road condition (i.e. off highway road or a public road) 6) Digging Depth 7) Working space available. 3.5 Study the actual composition of fleet at construction site Fleet management of Construction Equipment is the application of management techniques and systems in construction to complete projects on budget, on schedule, safely, and according to plans and specifications. The advent of powerful microcomputers, the advances in computer hardware and soft- ware, and their low costs have led to increased utilization of computers in various areas of construction management such as project management, scheduling, cost eliminating, bid markup analysis, accounting, submittal management, equipment management, materials management, and field management. The purpose of the study of composition of fleet at construction site, the equipment management system developed, A FLEET is a collection of four subsystems (modules): 1. Inventory management module. 2. Cost, time, and production records module. 3. Maintenance management module. 4. Report generator module FLEET is developed in D-BASE Relational database management system: 3.6 Equipment Management Practices: As the challenge of selecting, managing, and maintaining the equipment asset becomes more complex and costly every day, effective

4 management of these assets directly fuels the success for business by significantly minimizing direct and indirect costs of equipment while still concurrently ensuring high availability of equipment productivity. Realizing the right practices on equipment management is dependent on where the machines are in their lifecycle. Indeed, equipment management practices can be categorized into four groups: machine acquisition, operations, maintenance, and disposal. Key practices in each particular stage of machine lifecycle include, for example, procurement decision approach (equipment acquisition stage), safety and training programs (equipment operational stage), schedule PM inspection and standby repair-maintenance facilities (equipment maintenance stage), equipment economic life and replacement decisions (equipment disposal stage) Equipment planning: Equipment planning on major construction projects includes besides its selection the decision about working shifts, number and sizes of machines, the matching of units working in a team, procurement schedule and the arrangements of necessary technical staff to operate, service and repair of the equipment. Planning of workshop and stores facilities is also an important aspect of equipment planning. The type and equipment selected usually depends upon soil and valley conditions and upon the characteristics of material to be handled. Whether to use wheeled equipment or track equipment; to use bottom dump or rear dump trucks; to use drag line excavator or power shovel; to use cable ways or cranes and trestles for concrete placement are some of the questions that may have to be answered by the planner of construction equipment after considering soil and valley conditions of construction site. The number and size of machines selected depend upon the magnitude of work, working days available and number of shifts worked in a day Management requirements: Scope of work to be carried out. Use of available equipment. Suitability for job conditions. Size of equipment. Use of standard equipment. Uniformity in type. Unit cost of production. Country of origin. Availability of spare parts. Versatility. Table 1: Inventory Report, FLEET Selection of manufacturer. Suitability of local labour. Adaptability for future use. Technical considerations. Equip. No. (1) Description (2) Manufacturer (3) Purchase price (4) Estimated life (5) 1 Vibrating compactor Deere 15, Sheep foot roller Deere 75, Wheel loader Deere 35, Crawler tractor Deere 65, Tower scraper Cat 50, Off-highway truck Cat 35, Crawler crane Cat 50, Tower crane Cat 70, Risk management: Risk can be defined in a number of ways i) It signifies situations where the actual outcome of an activity or event is likely to deviate from the estimated or forecast value. ii) A working definition of risk would be along the following lines. Taking into consideration external aspects of a project risk can be defined as, Exposure to the possibility of economic and financial loss or gain, physical damages or injury, or delay as a consequence of the uncertainties

5 associated with pursuing a particular course of action. Risk = Probability of event *Magnitude of loss / gain. Risk can also be defined as the coalescence of all the uncertain factors, which shall have a combined negative effect on the objectives of the project Management practice and downtime: 1. Administrative time:- Time required for communication flow from user to manufacturer, time required for commercial formalities, and hours necessary to report a machine failure and give work directions for maintenance; 2. Supply time:- Time when repair is delayed due to non-availability of spare parts and materials necessary to perform maintenance; 3. Active repair:- Time when technicians are working on the equipment to actually commission it including both preventive and corrective maintenance. To minimize the consequential impact of downtime, contractors may opt to seek for substitute equipment, wait until the repair finished, accelerate work pace, modify work schedule, or transfer crews to other works. Heavy equipment practices have been categorized into four significant stages based on machine lifecycles, i.e. acquisition, operations, maintenance and disposal. 3.7 Equipment Maintenance and Repairs The maintenance of construction equipment is also vital to the contractor's success and profitability. The first step in a maintenance management system is a welldeveloped preventive management program. The preventive maintenance file keeps track of the schedule of preventive maintenance for different pieces of equipment and different types of maintenance. 1) Reduce unscheduled equipment downtime. 2) Increase on-shift and overall equipment availability. 3) Increase shop and mechanic efficiency and quality. 4) Pin-point machine deficiencies and initiate improvement. 5) Facilitate warranty requests from a manufacturer or rebuilder. 6) Aid new equipment selection and specification. 7) Improve predictability of inventory demand requirements 4.0 CONCLUSION The system presented is a user-friendly and practice-oriented system and is designed to demonstrate the accessibility of the database management systems. Development, acceptance, and continued use of such systems should contribute to the efficiency and profitability of contractors. FLEET provides this efficient as a foundation to good management practices and policies. More research work is still required in this field, so great scope of research is accessible for new researchers in this field. References [1] Saurabh Rajendra Kadam, Dhananjay S Patil, "CONSTRUCTION EQUIPMENT FLEET MANAGEMENT - A CASE STUDY" International Journal of Science and Research (IJSR) ISSN (Online): Index Copernicus Value (2013): 6.14 Impact Factor (2013): [2] Sujay Dandwate, Construction Equipment Fleet Management (Civil Engineering Department, D.Y.Patil College of Engineering, Akurdi, Pune-44, India International Journal Of Modern Engineering Research (IJMER). [3] Larry Orcutt, Division of Equipment, National Survey of Equipment Management Practices Preliminary Investigation Caltrans Division of Research and Innovation Produced by CTC & Associates LLC June 7, [4] The Taxicab, Limousine, and Paratransit Foundation "Fleet Management Solutions" By The Center for Transportation Studies at the University of Missouri-Saint Louis Under Sponsorship from Midwest Transportation Consortium. [5] Douglas D Gransberg, Optimizing Haul Unit Size And Number Based on Loading Facility Characteristics, Journal of Construction Engineering and Management, 1996, [6] SerjiAmirkhanian and Nancy J. Baker, Expert System for Equipment selection For Earth Moving Operations, Journal of Construction Engineering and Management, 1992, [7] NipeshPrdhanga and Jochen Teizer, Automatic spatio-temporal analysis of construction site equipment operations using

6 GPS data, Automation in Construction, 2013, [8] Simon D. smith, Earthmoving Production Estimation using Linear Regression Techniques, Journal of Construction engineering and Management, 1999, [9] C William Ibbs and Kenneth R. Tarveer, Integrated Construction Preventive Maintenance System, Journal of Construction engineering and Management, 1984, [10] ThanapanPrasertunganian and B.H.W Hadikasumo, Modeling the Dynamics of Heavy Equipment Management Practices and Downtime in Large Highway Contractors, Journal of Construction engineering and Management, 2009, [11] SaeedKarshenas, Truck Capacity Selection For Earthmoving, Journal of Construction engineering and Management, 1989, [12] Mohamed Marzouk and Osama Moselhi, Multiobjective Optimization of Earthmoving Operations, Journal of Construction engineering and Management, 2004, [13] Peurifoy, Schnexyder, shapira, Construction planning, equipment, methods. [14] V.B. Pandit, Norms for Production of Construction Machinery and Manual La Author s Biography Er.Roshan H.Bhoye obtained Bachelors Degree from Pune University. He is a student appearing for Masters Degree in Civil Engineering at SSGBCOE&T, Bhusawal, India and his area of specialization is Construction Technology and Management. Prof. P. M. Attarde received Masters Degree in Civil Engineering from University of Pune. His area of specialization is in Structural Engineering. He had published 05 research papers in international journals and 10 papers in conferences. He is a life member of various professional bodies.

Construction Equipment Fleet Management: Case Study of Highway Construction Project

Construction Equipment Fleet Management: Case Study of Highway Construction Project Construction Equipment Fleet Management: Study of Highway Construction Project 1 Saurabh Rajendra Kadam, 2 Prof. Dhananjay S Patil 1 P.G.Scholar, Department of Civil Engineering, Rajarambapu Institute

More information

Construction Equipment Fleet Management

Construction Equipment Fleet Management International OPEN ACCESS Journal Of Modern Engineering Research (IJMER) Construction Equipment Fleet Management Sujay Dandwate *(Civil Engineering Department, D.Y.Patil College of Engineering, Akurdi,

More information

Get more from Microsoft Dynamics AX with Maintenance Management from HSO

Get more from Microsoft Dynamics AX with Maintenance Management from HSO www.hso-equipment.com Get more from Microsoft Dynamics AX with Maintenance Management from HSO FACTSHEET MAINTENANCE MANAGEMENT CHALLENGES Keeping plant machinery and equipment in optimal productive condition

More information

Construction Planning, Equipment, and Methods

Construction Planning, Equipment, and Methods CHAPTER Construction Planning, Equipment, and Methods EQUIPMENT COST Sixth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering 3a By Dr. Ibrahim Assakkaf ENCE 420

More information

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

LEET CAT MINESTAR SYSTEM INTEGRATED FLEET MONITORING & MANAGEMENT FOR MINING

LEET CAT MINESTAR SYSTEM INTEGRATED FLEET MONITORING & MANAGEMENT FOR MINING CAT LEET MINESTAR SYSTEM INTEGRATED FLEET MONITORING & MANAGEMENT FOR MINING FLEET TRACK, MANAGE AND ASSIGN ALL TYPES OF EQUIPMENT With real-time machine tracking, assignment and productivity management,

More information

EQUIPMENT SAFETY EARTHMOVING MATERIAL HANDLING NAVFAC MIDLANT

EQUIPMENT SAFETY EARTHMOVING MATERIAL HANDLING NAVFAC MIDLANT EQUIPMENT SAFETY EARTHMOVING MATERIAL HANDLING COMMON EARTHMOVING EQUIPMENT SKID LOADERS BACKHOE FRONT END LOADER GRADERS SCRAPERS BULL DOZERS Lots of stuff Here! COMMON MATERIAL HAULING TRUCKS ALL TYPES

More information

TAXI. Redefining the. industry. Add a smile with every mile TAXI

TAXI. Redefining the. industry. Add a smile with every mile TAXI Redefining the TAXI industry TAXI Add a smile with every mile Real Time information of the fare and distance travelled Easy Booking Maximize vehicle use Look up the movement of all Taxis Improve customer

More information

Chapter 10. Hauling Equipment

Chapter 10. Hauling Equipment Chapter 10 Hauling Equipment The most common hauling equipment used for Army construction work are the 5- and 20-ton dump trucks, both of which are organic to most engineer units. Equipment trailers are

More information

Trackunit Telematics Solution. for OEM

Trackunit Telematics Solution. for OEM Trackunit Telematics Solution for OEM Trackunit Telematics is an indispensable tool for improving your business through a deeper understanding of machine usage and customer behaviour. It enables you to

More information

Programmes Elegible for CCD Points for Contractor Registration - 2015. Construction Industry Development Authority (CIDA)

Programmes Elegible for CCD Points for Contractor Registration - 2015. Construction Industry Development Authority (CIDA) Programmes Elegible for CCD Points for Contractor Registration - 5 Construction Industry Development Authority (CIDA) -January TITLE Lighting & Surge Protection System / TRG 0 27/0/5 Officers, Senior Supervisors

More information

2015-18 Department Business Plan. Fleet Services

2015-18 Department Business Plan. Fleet Services 2015-18 Department Business Plan Fleet Services Updated June 2016 My objective as Director of Fleet Services is to provide a comprehensive fleet program that supports our internal partners and the citizens

More information

CONSTRUCTION MANAGEMENT

CONSTRUCTION MANAGEMENT CONSTRUCTION MANAGEMENT Characteristic of Construction Industry One of the biggest sector as * total turnover is more than $3,9 trillion annually * 7 million employee (USA) Affects vast and different industries:

More information

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013 How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table

More information

Las Bambas Project. Joe Albright, Project Director 4 October 2012

Las Bambas Project. Joe Albright, Project Director 4 October 2012 Las Bambas Project j Joe Albright, Project Director 4 October 2012 Agenda Project Overview Highlights Challenges Initiatives Schedule Pictures Summary Assembly of the first two dozers that support the

More information

GPS BASED TRUCK DISPATCH SYSTEM (TDS) IN HIGHLY MECHANIZED BAUXITE MINES A CASE STUDY.

GPS BASED TRUCK DISPATCH SYSTEM (TDS) IN HIGHLY MECHANIZED BAUXITE MINES A CASE STUDY. GPS BASED TRUCK DISPATCH SYSTEM (TDS) IN HIGHLY MECHANIZED BAUXITE MINES A CASE STUDY. Dr Ashutosh Roul, PhD Senior Manager(Mines),NALCO. NALCO Asia s largest integrated Aluminium Complex, Encompassing

More information

10 TIPS. for better Fleet Management WHITE PAPER. Who should read this paper? CEOs CFOs COOs Fleet managers Finance executives

10 TIPS. for better Fleet Management WHITE PAPER. Who should read this paper? CEOs CFOs COOs Fleet managers Finance executives WHITE PAPER 10 TIPS for better Fleet Management by Valério Marques CEO, Frotcom International Who should read this paper? CEOs CFOs COOs Fleet managers Finance executives This paper shows that with a few

More information

What can I do with a major in Engineering Technology?

What can I do with a major in Engineering Technology? Lewis-Clark State College offers one and two year certificates, A.A.S. and B.A.S Degrees in Engineering Technology through the Technical and Industrial Division. You can learn more about the Technical

More information

INDEX 03010-1 DESCRIPTION 2 03010-2 MATERIALS 2 03010-3 APPROVAL OF SUBBASE COURSE 3 03010-4 CONSTRUCTION 4 03010-5 MEASUREMENT 6 03010-6 PAYMENT 6

INDEX 03010-1 DESCRIPTION 2 03010-2 MATERIALS 2 03010-3 APPROVAL OF SUBBASE COURSE 3 03010-4 CONSTRUCTION 4 03010-5 MEASUREMENT 6 03010-6 PAYMENT 6 03010_Dec22_2009.pdf Page 1 of 5 INDEX Page 03010-1 DESCRIPTION 2 03010-2 MATERIALS 2 03010-3 APPROVAL OF SUBBASE COURSE 3 03010-4 CONSTRUCTION 4 03010-5 MEASUREMENT 6 03010-6 PAYMENT 6 03010_Dec22_2009.pdf

More information

CONSTRUCTION EQUIPMENT AND METHODS

CONSTRUCTION EQUIPMENT AND METHODS CHAPTER Construction Planning, Equipment, and Methods Sixth Edition CONSTRUCTION EQUIPMENT AND METHODS A. J. Clark School of Engineering Department of Civil and Environmental Engineering 0 By Dr. Ibrahim

More information

JOURNAL OF INFORMATION, KNOWLEDGE AND RESEARCH IN MECHANICAL ENGINEERING

JOURNAL OF INFORMATION, KNOWLEDGE AND RESEARCH IN MECHANICAL ENGINEERING Automated Spares and Inventory Management System For Upstream Oil and Gas Producing Facilities Using RFID Based Item Tracking Integrated With Enterprise Resource Planning Through Centralized Onshore Sourcing

More information

AN AIRCRAFT TAXI SIMULATION MODEL FOR THE UNITED PARCEL SERVICE LOUISVILLE AIR PARK. W. Swain Ottman Angela C. Ford Gregory R.

AN AIRCRAFT TAXI SIMULATION MODEL FOR THE UNITED PARCEL SERVICE LOUISVILLE AIR PARK. W. Swain Ottman Angela C. Ford Gregory R. Proceedings of the 1999 Winter Simulation Conference P. A. Farrington, H. B. Nembhard, D. T. Sturrock, and G. W. Evans, eds. AN AIRCRAFT TAXI SIMULATION MODEL FOR THE UNITED PARCEL SERVICE LOUISVILLE AIR

More information

14. ENGINEERING AND CONSTRUCTION SCHEDULES. 14.1. Preparation of Schedules ALASKA ENERGY AUTHORITY AEA11-022 ENGINEERING FEASIBILITY REPORT

14. ENGINEERING AND CONSTRUCTION SCHEDULES. 14.1. Preparation of Schedules ALASKA ENERGY AUTHORITY AEA11-022 ENGINEERING FEASIBILITY REPORT 14. ENGINEERING AND CONSTRUCTION SCHEDULES The project procurement strategy and contract strategy based on the project risk profile have not yet been formulated. For the purposes of completing the construction

More information

ICT-BASED WORK MANAGEMENT TO SUPPORT UNMANNED CONSTRUCTION FOR POST-DISASTER RESTORATION

ICT-BASED WORK MANAGEMENT TO SUPPORT UNMANNED CONSTRUCTION FOR POST-DISASTER RESTORATION ICT-BASED WORK MANAGEMENT TO SUPPORT UNMANNED CONSTRUCTION FOR POST-DISASTER RESTORATION Shigeomi Nishigaki 1*, Kazutoshi Saibara 2, Shigeo Kitahara 3, Hajime Iwasaki 4, Kazuhiro Yamada 4, and Hideaki

More information

Nuclear Safe Work Practice 4.2. Operation of Light / Heavy Equipment

Nuclear Safe Work Practice 4.2. Operation of Light / Heavy Equipment Rev.0 September 5, 2011 VERIFY HARD COPY AGAINST WEB SITE IMMEDIATELY PRIOR TO USE Nuclear Safe Work Practice 4.2 Operation of Light / Heavy Equipment 1.0 PURPOSE/SCOPE NSWP 4.2-3 This Safe Work Practice

More information

Wireless Equipment Monitoring System

Wireless Equipment Monitoring System Wireless Equipment Monitoring System TM TM Komtrax gathers critical machine information to make fleet management easier and more effective. This data provides key information about your operators, machines,

More information

Model based quality assurance process in a infra construction. Case Riippa-Eskola RU2 double rail project

Model based quality assurance process in a infra construction. Case Riippa-Eskola RU2 double rail project Model based quality assurance process in a infra construction project Case Riippa-Eskola RU2 double rail project M. Jaakkola a and P. Toppi a a Destia Ltd, Development of Infra construction, Finland E-mail:

More information

CONSTRUCTION EQUIPMENT

CONSTRUCTION EQUIPMENT Equipment is a critical resource in the execution of most construction projects. The equipment fleet may represent the largest long-term capital investment in many construction companies. Consequently,

More information

Boerne Independent School District Job Description

Boerne Independent School District Job Description Boerne Independent School District Job Description Job Title: Fleet Manager Wage/ Hour Status: Reports to: Director of Transportation Pay Grade: Department: Transportation Date Revised: 12/4/2015 Primary

More information

ROAD EQUIPMENT MANAGEMENT: A CHALLENGE FOR CAPACITY BUILDING OF LOCAL CONTRACTORS IN TANZANIA

ROAD EQUIPMENT MANAGEMENT: A CHALLENGE FOR CAPACITY BUILDING OF LOCAL CONTRACTORS IN TANZANIA ROAD EQUIPMENT MANAGEMENT: A CHALLENGE FOR CAPACITY BUILDING OF LOCAL CONTRACTORS IN TANZANIA by Magesa Bairi * and Mrs. Marcelin Benedict ** ABSTRACT The shortage of equipment and Plant needed for proper

More information

TRACKING HAULING TRUCKS FOR CUT-FILL EARTHMOVING OPERATIONS

TRACKING HAULING TRUCKS FOR CUT-FILL EARTHMOVING OPERATIONS TRACKING HAULING TRUCKS FOR CUT-FILL EARTHMOVING OPERATIONS *Ali Montaser, and Osama Moselhi Department of Building, Civil and Environmental Engineering, Concordia University, Montreal, Quebec, Canada

More information

Enhance Production in 6 Steps Using Preventive Maintenance

Enhance Production in 6 Steps Using Preventive Maintenance Enhance Production in 6 Steps Using Preventive Maintenance 1 Enhance Production in 6 Steps Using Preventive Maintenance Preventive Maintenance (PM) is 30% less expensive than reactive approaches Using

More information

College of Agriculture, Engineering and Science INSPIRING GREATNESS

College of Agriculture, Engineering and Science INSPIRING GREATNESS School of Engineering College of Agriculture, Engineering and Science INSPIRING GREATNESS Don t accept what is, always ask what if. The School of Engineering is one of five Schools that form UKZN s College

More information

FACTORS TO CONSIDER WHEN PLANNING LANDFILL CONSTRUCTION 1

FACTORS TO CONSIDER WHEN PLANNING LANDFILL CONSTRUCTION 1 FACTORS TO CONSIDER WHEN PLANNING LANDFILL CONSTRUCTION 1 David J. Kerkes, Ph.D., P.E. Consulting Geotechnical (Civil) Engineer 1311 Mustang Trail Kingwood, Texas 77339 USA dkerkes@geotechconsultant.com

More information

Planning and Scheduling Consideration and Constraints in Automated Construction Environment. Chotchai Charoenngam, Ph.D. ABSTRACT

Planning and Scheduling Consideration and Constraints in Automated Construction Environment. Chotchai Charoenngam, Ph.D. ABSTRACT Planning and Scheduling Consideration and Constraints in Automated Construction Environment Chotchai Charoenngam, Ph.D. Assisatant Professor, School of Civil Engineering, Asian Institute of Technology,

More information

Construction Equipment Financing

Construction Equipment Financing Construction Equipment Financing Vinod Kothari 1012 Krishna 224 AJC Bose Road Kolkata 700 017. India email: vinod@vinodkothari.com www.vinodkothari.com Construction equipment The present size of the market

More information

Leica Jigsaw Jfleet Fleet Management System

Leica Jigsaw Jfleet Fleet Management System Leica Jigsaw Jfleet Fleet Management System You can t improve what you can t measure. You can t measure what you can t see. Unrivaled in their field Complete scalability Increased production & productivity

More information

SECTION ET3. Copyright Remote Control Technologies Pty Ltd

SECTION ET3. Copyright Remote Control Technologies Pty Ltd & AUTOMATION SYSTEMS PROTECTION SYSTEMS INFORMATION SYSTEMS SPE SECTION 3 Copyright Remote Control Technologies Pty Ltd www.rct.net.au sales@rct.net.au Control & Automation Protection Systems Over or improperly

More information

How Software solutions can help mining companies increase efficiency levels

How Software solutions can help mining companies increase efficiency levels How Software solutions can help mining companies increase efficiency levels Contents 3 Summary 4 The challenges of improving mining efficiencies 5 Software solutions helping mining companies increase efficiency

More information

CHALLENGER INSTITUTE OF TECHNOLOGY. Applied Engineering

CHALLENGER INSTITUTE OF TECHNOLOGY. Applied Engineering CHALLENGER INSTITUTE OF TECHNOLOGY Applied Engineering 2 Applied Engineering Graduates with real opportunities Challenger Institute s engineering training capitalises on its close liaison with industry

More information

TOWN OF FARMINGTON, CT REQUEST FOR PROPOSALS FOR CONSTRUCTION EQUIPMENT RENTALS AND ON CALL CONSTRUCTION SERVICES

TOWN OF FARMINGTON, CT REQUEST FOR PROPOSALS FOR CONSTRUCTION EQUIPMENT RENTALS AND ON CALL CONSTRUCTION SERVICES TOWN OF FARMINGTON, CT REQUEST FOR PROPOSALS FOR CONSTRUCTION EQUIPMENT RENTALS AND ON CALL CONSTRUCTION SERVICES The Town of Farmington Department of Public Works is seeking proposals for the purpose

More information

Position: HEAVY EQUIPMENT OPERATOR Classification: 3 Highway Personnel Member B & C

Position: HEAVY EQUIPMENT OPERATOR Classification: 3 Highway Personnel Member B & C Position: HEAVY EQUIPMENT OPERATOR Classification: 3 Highway Personnel Member B & C Position Purpose: The purposes of this position are to assist in maintaining all town rights-of-way, equipment and other

More information

CHAPTER 4 COST OF CONSTRUCTION LABOR AND EQUIPMENT

CHAPTER 4 COST OF CONSTRUCTION LABOR AND EQUIPMENT CHAPTER 4 COST OF CONSTRUCTION LABOR AND EQUIPMENT Construction labors influence every part of a project. They operate equipment and fabricate and install materials. Detailed estimate requires the breakdown

More information

Please contact a member of our sales team on 0845 055 8555

Please contact a member of our sales team on 0845 055 8555 Ctrack is a division of DigiCore Holdings, one of the world s largest vehicle tracking companies Established in 1985, Ctrack supports in excess of 750,000 systems across 56 countries on five continents

More information

Model based construction and Model based quality assurance process Contractor s experiences

Model based construction and Model based quality assurance process Contractor s experiences Model based construction and Model based quality assurance process Contractor s experiences Pasi Nurminen Destia Ltd is a Finnish infrastructure and construction service company. Building the Bigger Picture

More information

Performance Inspection The performance inspection must, as a minimum, include the following features, components, accessories, and tests.

Performance Inspection The performance inspection must, as a minimum, include the following features, components, accessories, and tests. Appendix H Record of Performance Inspection and Brake Test Off-Highway, Wheel-Type Construction Machines, Loaders, Dumpers, Scrapers, Graders, Tractor Water Wagons, and Similar-Type Machines General All

More information

Sustainable Resource Management Ltd

Sustainable Resource Management Ltd 6.0 Predicted nvironmental Impacts 6. Stages and Impacts Considered An nvironmental Impact Analysis has been carried out whereby all the possible environmental, socio economic and health & safety aspects

More information

PEOPLESOFT MAINTENANCE MANAGEMENT

PEOPLESOFT MAINTENANCE MANAGEMENT PEOPLESOFT MAINTENANCE MANAGEMENT KEY BENEFITS Streamline Maintenance Operations Manage Full Asset Lifecycle Lower Total Cost of Ownership Oracle s PeopleSoft Maintenance Management completes the Enterprise

More information

TRUCKS AND HAULING EQUIPMENT

TRUCKS AND HAULING EQUIPMENT CHAPTER Construction Planning, Equipment, and Methods TRUCKS AND HAULING EQUIPMENT Sixth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering 10 By Dr. Ibrahim Assakkaf

More information

MAXIMIZING UPTIME AND SAVINGS AKMETAL MADENCİLİK

MAXIMIZING UPTIME AND SAVINGS AKMETAL MADENCİLİK MAXIMIZING UPTIME AND SAVINGS AKMETAL MADENCİLİK WORKING HARDER MEANS WORKING SMARTER Two billion cubic meters is a lot of earthmoving and haulage. That s how much excavation and fill is needed to build

More information

Energy Efficiency Opportunities 2013 Public Report. This report contains data for financial year 2012/2013

Energy Efficiency Opportunities 2013 Public Report. This report contains data for financial year 2012/2013 2013 Public Report This report contains data for financial year 2012/2013 Corporation details Period to which the report relates Start Period 1 July 2012 End Period 30 June 2013 Controlling corporation

More information

Section 100 Contractor Quality Control Program

Section 100 Contractor Quality Control Program 7/21/2014 AC 150/5370-10G Section 100 Contractor Quality Control Program 100-01 General. When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and

More information

THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE. John R. Lethbridge

THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE. John R. Lethbridge Page 1 of 5 TRANSPORTATION, WATER AND URBAN DEVELOPMENT DEPARTMENT THE WORLD BANK November 1990 Transport No. PS-2 THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE John R. Lethbridge The use of outside

More information

MATERIALS CERTIFICATION SCHOOLS

MATERIALS CERTIFICATION SCHOOLS MATERIALS CERTIFICATION SCHOOLS 2011, Virginia Department of Transportation Registration Process Online Registration Enrollment and payment for all personnel in the Materials Certification Schools may

More information

Features. Emerson Solutions for Abnormal Situations

Features. Emerson Solutions for Abnormal Situations Features Comprehensive solutions for prevention, awareness, response, and analysis of abnormal situations Early detection of potential process and equipment problems Predictive intelligence network to

More information

Maximo for Fleet Management in Construction Projects. Khaled AlShami CCC, EAM Solutions Manager

Maximo for Fleet Management in Construction Projects. Khaled AlShami CCC, EAM Solutions Manager Maximo for Fleet Management in Construction Projects Khaled AlShami CCC, EAM Solutions Manager ELECTRIC GENERATORS & LIGHTING TOWERS 689 AIR COMPRESSORS 389 CRANES 855 EARTHMOVING EQUIPMENT 988 CIVIL

More information

FEMA's SCHEDULE OF EQUIPMENT RATES

FEMA's SCHEDULE OF EQUIPMENT RATES DEPARTMENT OF HOMELAND SECURITY FEDERAL EMERGENCY MANAGEMENT AGENCY RECOVERY DIRECTORATE PUBLIC ASSISTANCE DIVISION WASHINGTON, D.C. 20472 The rates on this Schedule of Rates are for applicant-owned equipment

More information

Is Truck Queuing Productive? Study of truck & shovel operations productivity using simulation platform MineDES

Is Truck Queuing Productive? Study of truck & shovel operations productivity using simulation platform MineDES Is Truck Queuing Productive? Study of truck & shovel operations productivity using simulation platform MineDES Dmitry Kostyuk Specialist Scientist, Group Resource and Business Optimisation 25 November

More information

Table of Contents ESF-3-1 034-00-13

Table of Contents ESF-3-1 034-00-13 Table of Contents Primary Coordinating Agency... 2 Local Supporting Agencies... 2 State, Regional, and Federal Agencies and Organizations... 3 Purpose... 3 Situations and Assumptions... 4 Direction and

More information

Keeping records and calculating eligible litres

Keeping records and calculating eligible litres Guide for fuel tax credit claimants Keeping records and calculating eligible litres Outlines the records you need to keep and how to calculate your eligible litres when you claim fuel tax credits. NAT

More information

SUPPLY CHAIN SERVICES

SUPPLY CHAIN SERVICES EB-0-0 Exhibit F Schedule Page of SUPPLY CHAIN SERVICES INTRODUCTION Supply Chain supports THESL asset management plans by ensuring that all required goods and services are available when needed. Strong

More information

CIVIL AND MINING CONTRACTORS

CIVIL AND MINING CONTRACTORS ALLIANCE CONTRACTING COMPANY PROFILE CIVIL AND MINING CONTRACTORS our people are our advantage 2 Introduction Alliance Contracting is a civil and mining contracting company operating throughout Western

More information

Leica Monitoring Solutions. Leica Monitoring Solutions Certainty builds confidence.

Leica Monitoring Solutions. Leica Monitoring Solutions Certainty builds confidence. Leica Monitoring Solutions Leica Monitoring Solutions Certainty builds confidence. Risk and Cost Reduction Proven Solutions Facing new challenges Engineering companies and contractors are facing challenges

More information

Enterprise Resource Planning Analysis of Business Intelligence & Emergence of Mining Objects

Enterprise Resource Planning Analysis of Business Intelligence & Emergence of Mining Objects Enterprise Resource Planning Analysis of Business Intelligence & Emergence of Mining Objects Abstract: Build a model to investigate system and discovering relations that connect variables in a database

More information

Design Simulations Deliver Measurable Performance

Design Simulations Deliver Measurable Performance Design Simulation for TransCar Automated Guided Vehicle System (AGVS) Forecast the ability of an automated material transport system design to perform the defined workload within the available space and

More information

Business ByDesign. The SAP Business ByDesign solution helps you optimize project management

Business ByDesign. The SAP Business ByDesign solution helps you optimize project management SAP Functions in Detail SAP Solutions for Small Businesses and Midsize Companies Efficient Project Management Drive Project Success with SAP Business ByDesign The SAP Business ByDesign solution helps you

More information

B2W Maintain. Setup and Preventive Maintenance

B2W Maintain. Setup and Preventive Maintenance B2W Maintain Setup and Preventive Maintenance Session Contents B2W Maintain - Setup and Preventive Maintenance... 2 1: Learning About Maintenance Categories... 3 2: Learning About Equipment Level Enhancements...

More information

[Author Name] [Type the abstract of the document here. The abstract is typically a short summary of the contentsof the document.] Utility Take-Home

[Author Name] [Type the abstract of the document here. The abstract is typically a short summary of the contentsof the document.] Utility Take-Home [Author Name] [Type the abstract of the document here. The abstract is typically a short summary of the contentsof the document.] Utility Take-Home Vehicle Policy Example Fleet Management Approved by:

More information

ENGINEERING, MAINTENANCE AND MANUFACTURE OF SPECIAL COMPONENTS

ENGINEERING, MAINTENANCE AND MANUFACTURE OF SPECIAL COMPONENTS RWE Power ENGINEERING, MAINTENANCE AND MANUFACTURE OF SPECIAL COMPONENTS The RWE Maintenance and Engineering Center RWE Power AG Maintenance and Engineering Center Frechener Straße 12 50226 Frechen CCS_0114

More information

Service Relationship Management Driving Uptime in Commercial Vehicle Maintenance and Repair

Service Relationship Management Driving Uptime in Commercial Vehicle Maintenance and Repair Service Relationship Management Driving Uptime in Commercial Vehicle Maintenance and Repair Table of Contents 1 About Decisiv 2 Introduction 3 Quality and Process Improvements 4 Efficiency Metrics for

More information

Plantcom s. Fleet Management. solutions are your competitive advantage. plantcom.com.au. contact@plantcom.com.au l

Plantcom s. Fleet Management. solutions are your competitive advantage. plantcom.com.au. contact@plantcom.com.au l After years of development, and with the assistance from the mining, construction, heavy transport and vehicle rental industries, Plantcom have developed a state of the art fleet management solution that

More information

Traffic Management Issue 1.0 Revision: v2 October 2014

Traffic Management Issue 1.0 Revision: v2 October 2014 Disclaimer IMPORTANT: The information in this guide is of a general nature, and should not be relied upon as individual professional advice. If necessary, legal advice should be obtained from a legal practitioner

More information

OPTIMIZATION OF LOAD HAUL DUMP MINING SYSTEM BY OEE AND MATCH FACTOR FOR SURFACE MINING

OPTIMIZATION OF LOAD HAUL DUMP MINING SYSTEM BY OEE AND MATCH FACTOR FOR SURFACE MINING OPTIMIZATION OF LOAD HAUL DUMP MINING SYSTEM BY OEE AND MATCH FACTOR FOR SURFACE MINING *Ram Prasad Choudhary Department of Mining Engineering, National Institute of Technology Karnataka, Surathkal-575025

More information

Chapter 11. MRP and JIT

Chapter 11. MRP and JIT Chapter 11 MRP and JIT (Material Resources Planning and Just In Time) 11.1. MRP Even if MRP can be applied among several production environments, it has been chosen here as a preferential tool for the

More information

Practical Management for Plant Turnarounds. Chapter 1

Practical Management for Plant Turnarounds. Chapter 1 Practical Management for Plant Turnarounds Chapter 1 Plant Turnaround Owners of commercial facilities, manufacturing processes, and industrial plants recognize that maintenance of their equipment assets

More information

Annex 2.2. Questionnaire for Solid Waste Management Survey

Annex 2.2. Questionnaire for Solid Waste Management Survey Annex 2.2 Questionnaire for Solid Waste Management Survey This Annex is a reproduction of Annex 2 of: WHO (1996). Guides for Municipal Solid Waste Management in Pacific Countries. Healthy Cities - Healthy

More information

QUICK GUIDE. How to Select an Effective Mobile Workforce Management Solution. How to Select an Effective Mobile Workforce Management Solution

QUICK GUIDE. How to Select an Effective Mobile Workforce Management Solution. How to Select an Effective Mobile Workforce Management Solution QUICK GUIDE How to Select an Effective Mobile Workforce Management Solution 1 How to Select an Effective Mobile Workforce Management Solution This Quick Guide will cover: What a comprehensive Mobile Workforce

More information

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS Business Procedure Traffic Management Document Number OHS-PROC-130 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya Hydro

More information

P & S Consumption Factor $ Annual P & S $ Potential

P & S Consumption Factor $ Annual P & S $ Potential 1 How to Build Aftermarket Sales 16 Tools to Build Your Service Labor Business The sweet sixteen that will make you dramatically more profitable. By Walter J. McDonald, President, Equipment Dealers want

More information

Cendec Systems Inc. http://www.cendec.com

Cendec Systems Inc. http://www.cendec.com The management of multi-million dollar assets and inventories can be a daunting task. For the past fifteen years, Oil and Gas companies have relied on Maintenance and Materials Management systems from

More information

Quality and Quality Control

Quality and Quality Control 1 Quality and Quality Control INSPECTION Inspection is the most common method of attaining standardisation, uniformity and quality of workmanship. It is the cost art of controlling the product quality

More information

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation. Part 1926 Subpart P Introduction The Occupational Safety and Health Administration (OSHA) issued its first Excavation and Trenching Standard in 1971 to protect workers from excavation hazards. Since then,

More information

2015-18 Department Business Plan. Fleet Services

2015-18 Department Business Plan. Fleet Services 2015-18 Department Business Plan Fleet Services My objective as Director of Fleet Services is to provide a comprehensive fleet management program that supports our internal partners and the citizens of

More information

Risk management a practical approach

Risk management a practical approach Risk management a practical approach Introduction Preventing work related accidents and injuries is the primary concern for all those involved in health and safety. Work related accidents and injuries

More information

Establishing a Cost Effective Fleet Replacement Program

Establishing a Cost Effective Fleet Replacement Program Establishing a Cost Effective Fleet Replacement Program Regardless of what purpose your company s fleet serves, there are certain fundamentals to keep in mind when designing and implementing a cost-effective

More information

Section 300 Base Courses

Section 300 Base Courses Table of Contents 1. Importance of Base Courses... 300-1 2. Types of Bases... 300-3 A. Cement Treated Permeable Base Course... 300-3 B. Bituminous Concrete Base Courses... 300-6 C. Superpave Asphalt HMA

More information

RCM Success Starts with CMMS

RCM Success Starts with CMMS RCM Success Starts with CMMS Ruth Olszewski, President CMMS data group, inc. 5701 N. Sheridan Road, Suite 17Q Chicago, Illinois 60660 Phone: (773) 275-8846 Fax: (801) 991-6567 ruth.olszewski@cmmsdatagroup.com

More information

CDW Technology Services

CDW Technology Services CDW Technology Services The Right Technology. Right Away. 20 Carlson Court Suite 300 Etobicoke, Ontario M9W 7K6 CDW.ca 800.97.CDWCA Optimize your IT investment with CDW Technology Services 34451 022607

More information

2012 Americas School of Mines

2012 Americas School of Mines www.pwc.com 2012 Americas School of Mines Maximizing Asset Management From Work Plan to Financial Performance Doug Stretton, Paul Ingram May 17, 2012 Presentation Summary Maximizing mining assets is often

More information

Trends In OWNING VS. RENTING CONSTRUCTION EQUIPMENT. By Andy Agoos

Trends In OWNING VS. RENTING CONSTRUCTION EQUIPMENT. By Andy Agoos Trends In OWNING VS. RENTING CONSTRUCTION EQUIPMENT By Andy Agoos CONSTRUCTION TRENDS AFFECTING YOUR DECISION For the past 50 years, equipment rental has become increasingly popular. Today in the United

More information

An Assessment of Nominal and Actual Hourly Production of the Construction Equipment Based on Several Earth-Fill Dam Projects in Iran

An Assessment of Nominal and Actual Hourly Production of the Construction Equipment Based on Several Earth-Fill Dam Projects in Iran 74 The Open Civil ering Journal, 2009, 3, 74-82 Open Access An Assessment of Nominal and Actual Hourly Production of the Construction Equipment Based on Several Earth-Fill Dam Projects in Iran Hamed Nabizadeh

More information

Creating value by satisfying customers

Creating value by satisfying customers 41 Creating value by satisfying customers Organizations that capture customers needs best and translate them into tailored products and services will be the leaders in any market or. Organizations with

More information

FLEET MANAGEMENT. Fleet Management s motto is If you make the time for us, We will make the time for you.

FLEET MANAGEMENT. Fleet Management s motto is If you make the time for us, We will make the time for you. FLEET MANAGEMENT Department Mission/Purpose Statement We are dedicated to be a well managed, responsive and preferred provider of fleet services and to meet all fuel, mechanical repairs, towing and vehicle

More information

Specialist remote area rental solutions.

Specialist remote area rental solutions. Specialist remote area rental solutions. Wet & Dry Hire Remote Area Mobilisation Modern Fleet of Specialised Plant & Equipment Highly Trained Indigenous Operators Competitive Prices Mine Site Ready Introducing

More information

Elko, Nevada. Service Center

Elko, Nevada. Service Center Elko, Nevada Service Center World-Class Fast Facts on Joy Global Glo b al Head q u ar ter s in Milw au k ee, W I... People Over 150 locations We attract, develop and retain highly-skilled manufacturing

More information

Fleet Features Contents

Fleet Features Contents Cat Fleet Fleet Features Real-time monitoring of mobile equipment and material movement Advanced truck assignment capabilities to optimize fleet productivity Material tracking supports precise blending

More information

Cost Estimating in Construction Part 1, Course #406. Presented by: PDH Enterprises, LLC PO Box 942 Morrisville, NC 27560 www.pdhsite.

Cost Estimating in Construction Part 1, Course #406. Presented by: PDH Enterprises, LLC PO Box 942 Morrisville, NC 27560 www.pdhsite. Cost Estimating in Construction Part 1, Course #406 Presented by: PDH Enterprises, LLC PO Box 942 Morrisville, NC 27560 www.pdhsite.com This course Cost Estimation in Construction Part 1 provides a study

More information

MANAGING LINEAR ASSETS Managing Linear Assets has always been a challenge; find out how customers leverage SAP to meet industry requirements.

MANAGING LINEAR ASSETS Managing Linear Assets has always been a challenge; find out how customers leverage SAP to meet industry requirements. WWW.WIPRO.COM MANAGING LINEAR ASSETS Managing Linear Assets has always been a challenge; find out how customers leverage SAP to meet industry requirements. Venkatesh Pulijala, EAM Consultant - Oil & Gas,

More information

Estimating Trench Excavation

Estimating Trench Excavation Estimating Excavation By Steven J. Peterson, PE, MBA Introduction excavation is often performed by hydraulic backhoe excavators. This is because hydraulic excavators are not only good at excavating below

More information

Fleet Management Information Systems. Presentation for: Ron Katz SVP, North American Sales. www.chevinfleet.com

Fleet Management Information Systems. Presentation for: Ron Katz SVP, North American Sales. www.chevinfleet.com Fleet Management Information Systems Presentation for: Ron Katz SVP, North American Sales Fleet Sustainability Meaningful fleet sustainability initiatives require a detailed understanding of the relationships

More information