PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP
|
|
|
- Shavonne Morrison
- 9 years ago
- Views:
Transcription
1 PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP
2 PROJECTS PROGRESS WELL UNTIL 70% Quick progress until 60-70% complete. Then we discover the project is in distress. (mod. KERZNER 2011, p.48)
3 A PROJECT IS IN DISTRESS, IF It exhibits a performance trend that, continued, will result in failure Its performance has exceeded metric values and is a high risk for failure It has recently experienced a significant change that may result in failure (mod. WYSOCKI 2014, p.448)
4 WHY PROJECTS BECOME DISTRESSED? Poor, inadequate, or no requirements documentation Complexity of requirements not recognized Unmanageable project scope Inappropriate or insufficient sponsorship Unwillingness to make (tough) decisions Lag time between project approval and Kick-Off No credibility in the baseline plan No plan revision after significant cuts in resources Estimates done with little planning or thought (mod. WYSOCKI 2014, pp )
5 WHY DO WE SEE IT LATE? No metrics Wrong metrics Fear of what health checks may reveal (mod. KERZNER 2011, p.48)
6 A PROJECT IS A SYSTEM It can get out of balance The longer we wait to fix, the longer it takes to return to equilibrium The controls must be designed to discover out-of-balance situations early and put get-well plans in place quickly. (mod. WYSOCKI 2012, p.280) 6
7 HIGHLIGHTS: 1. PROJECTS PROGRESS WELL UNTIL THEY ARE 70% COMPLETE 2. PROJECT FAILURE IS A PROCESS THAT OFTEN STARTS AT THE BEGINNING 3. WE RECOGNIZE PROBLEMS LATE BECAUSE WE DO NOT MEASURE
8 EARNED VALUE MANAGEMENT (EVM) A method of performance measurement integrating project scope, cost, and schedule measures to help assess and measure project performance and progress. EVM develops and monitors three key dimensions for each work package and control account: PLANNED VALUE (PV) EARNED VALUE (EV) ACTUAL COST (AC)
9 THE KEY DIMENSIONS PLANNED VALUE (PV): the authorized budget assigned to the scheduled work to be accomplished for a schedule activity or work breakdown structure component. EARNED VALUE (EV): the value of work performed expressed in terms of the approved budget assigned to that work for a schedule activity or work breakdown structure component. ACTUAL COST (AC): total costs actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity or work breakdown structure component.
10 VARIANCES FROM THE BASELINE SCHEDULE VARIANCE (SV): a measure of schedule performance SV = EV PV. Can indicate a project falling behind its baseline schedule. COST VARIANCE (CV): a measure of cost performance CV= EV AC. CV at the end of the project will be the difference between the budget at completion (BAC) and the actual amount spent. CV is particularly critical because it indicates the relationship of physical performance to the costs spent.
11 PERFORMANCE INDEXES SCHEDULE PERFORMANCE INDEX (SPI): a measure of progress achieved compared to progress planned. SPI = EV/PV. SPI<1.0 indicates less work was completed than was planned. SPI>1.0: more work was completed than planned. COST PERFORMANCE INDEX (CPI): a measure of the value of work completed compared to the actual cost or progress made. CPI = EV/AC. Is considered the most critical EVM metric and measures the cost efficiency for the work completed. CPI<1.0 indicates a cost overrun for work completed. CPI>1.0: cost underrun of performance.
12 COST/SCHEDULE PERFORMANCE Months of the project life (NICHOLAS 2008, p.437)
13 CALCULATE THE EVM VALUES PLANNED Situation I Situation II Situation III TIME SCOPE PV , , , , ,00 EV 2 500, , ,00 AC 2 500, , ,00 EAC PV , , ,00
14 LIMITATIONS OF EVM METRICS TIME and COST are basically the only two metrics QUALITY and VALUE of the project cannot be calculated Completing a project within time and cost does not imply success No information for corrective action Stakeholders do not always understand the meaning of the metrics. (mod. KERZNER 2011, p.70)
15 HIGHLIGHTS: 4. EARNED VALUE MANAGEMENT AIMS TO MEASURE PROJECT PERFORMANCE BY INTEGRATING SCOPE, COST, AND SCHEDULE 5. PLANNED VALUE, EARNED VALUE AND ACTUAL COST ARE ITS KEY DIMENSIONS 6. EVM HAS MANY LIMITATIONS
16 THE PROJECT MANAGEMENT TRIANGLE TIME QUALITY COST SCOPE
17 QUALITY Degree to which a set of inherent characteristics fulfills requirements
18 QUALITY REVOLUTION PAST The responsibility of workers Defects should be hidden Quality problems lead to conflicts Corrections should be minimally documented Increased quality will increase project costs Quality is internally focused Quality will not occur without close supervision Quality occurs during project execution PRESENT Everyone s responsibility Defects should be brought to the surface Quality problems lead to cooperative solutions Documentation is essential for lessons learned Improved quality saves money Quality is customer focused People want to produce quality products Quality occurs at initiation and must be planned for (mod. KERZNER 2009, p.874)
19 GRADE A category assigned to products or services having the same functional use but different technical characteristics
20 (BEGLEY et al. Nature 2015;525:25)
21 CRITICISMS OF CITATION COUNTS 1. Scientific quality is a complex phenomenon and cannot be measured on a one-dimensional scale 2. Authors cite publications that have had little intellectual influence on their paper 3. Authors do not cite many that have had 4. Authors overlook relevant publications 5. Researchers use publication strategies distorting bibliometrics 6. Citations databases cover only a part of publications 7. The publication must be read and assessed (mod. BORNMANN et al. in CRONIN & SUGIMOTO 2014, p.217)
22 HIGHLIGHTS: 7. QUALITY IS THE DEGREE OF FULFILLING REQUIREMENTS 8. VIEWS OF QUALITY HAVE PROFOUNDLY CHANGED SINCE 1950s 9. GRADE CAN BE HIGH, BUT QUALITY LOW.
23 QUALITY MANAGEMENT PROCESSES 1. PLAN QUALITY identify quality requirements and/or standards for the project and product, and document how the project will demonstrate compliance 2. PERFORM QUALITY ASSURANCE audit the quality requirements and the results from quality control measurements to ensure appropriate quality standards and operational definitions are used 3. PERFORM QUALITY CONTROL monitor and record results of executing the quality activities to assess performance and recommend necessary changes
24 HOW TO PLAN COST-BENEFIT ANALYSIS COST OF QUALITY BENCHMARKING FLOWCHARTING PROPRIETARY QM METHODOLOGIES
25 COST OF QUALITY (COQ) The total cost of quality-related efforts and deficiencies The sum of conformance and nonconformance costs (BLOCHER et al. 2010, p.761)
26 COQ S COMPONENTS COSTS OF NONCONFORMANCE: Internal failure costs Rework Reinspection Corrective action costs External failure costs Replacement Product recall and liability Reputation Lost sales and ill-will COSTS OF CONFORMANCE: Prevention costs Training Quality programs (plan and execute) Investments (improve and redesign) Appraisal costs Inspection Testing (BLOCHER et al. 2010, pp )
27 OUTPUTS OF QUALITY PLANNING QUALITY MANAGEMENT PLAN QUALITY METRICS QUALITY CHECKLISTS PROCESS IMPROVEMENT PLAN PROJECT DOCUMENT UPDATES
28 QUALITY METRIC An operational definition that describes, in specific terms, a project or product attribute and how the quality control process will measure it. A MEASUREMENT its actual value, TOLERANCE allowable variations of the metrics.
29 CONTINUOUS IMPROVEMENT PROCESS (CIP) A closed-loop cycle of sequential steps designed to bring about continual improvement through a process of (1) DISCOVERY, (2) APPLICATION, (3) REVIEW, (4) CORRECTIVE ACTION. The Shewhart cycle (Plan-Do-Review-Act), Six Sigma s DMAIC (Define- Measure-Analyze-Improve-Control), and TOC s Five Focusing Steps (5FS) are among the best known methodologies. (COX & SCHLEIER 2010, p.404)
30 HOW TO PERFORM QUALITY ASSURANCE QUALITY AUDITS PROCESS ANALYSIS
31 A QUALITY AUDIT A structured review to determine whether project activities comply with organizational and project policies, processes, and procedures. ITS OBJECTIVES: Identify all the good/best practices being implemented Identify all the gaps/shortcomings Share the good practices introduced/implemented Proactively offer assistance to improve implementation Highlight contributions of each audit in the lessons learned repository.
32 OUTPUTS of PERFORM ASSURANCE PROJECT MANAGEMENT PLAN UPDATES CHANGE REQUESTS
33 HOW TO PERFORM QUALITY CONTROL INSPECTION STATISTICAL SAMPLING PARETO CHART
34 PARETO CHART A histogram, ordered by frequency of occurrence, that shows how many results were generated by each identified cause. Illustrates the 80/20 rule. 89% of [year 2004 citations of Nature papers] was generated by just 25% of our papers (EDITORIAL. Nature 2005;435:1004) eto_chart_of_titanium_investment_casting_defects.svg
35 HIGHLIGHTS: 10. QM CONSISTS OF PLANNING, CONTROLING AND (!) ASSURING 11. COST OF QUALITY: NONCONFORMANCE COSTS ARE ALWAYS HIGH 12. PARETO CHART ILLUSTRATES THE UBIQUITOUS 80/20 RULE
QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP
QUALITY AND PERFORMANCE IN PROJECTS Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
IST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
PROJECT QUALITY MANAGEMENT
8 PROJECT QUALITY MANAGEMENT Project Quality Management includes the processes required to ensure that the project will satisfy the needs for which it was undertaken. It includes all activities of the
An introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
Certification Preparation Course LATVIKON (R.E.P.)Centre
PMP Certification Preparation Course LATVIKON (R.E.P.)Centre ABOUT THIS COURSE Your ability as a project manager to demonstrate best practices in Project Management both on the job and through professional
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
INSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
Certification Exam Objectives: PK0-003
Certification Exam Objectives: PK0-003 INTRODUCTION The CompTIA Project + examination is designed for business professionals involved with projects. This exam will certify that the successful candidate
Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Rules on using templates 1) Must reference the template used 2) Use
Project Cost Management
Project Cost Management Martin Pazderka [email protected] INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda
Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
Project Management Institute (PMBOK 2000) PMP Preparation Worksheet
Project Integration Management Processes required to ensure that the various elements of the project are properly coordinated to meet / exceed stakeholder expectations. Project Plan Development Other ning
pm4dev, 2008 management for development series Project Quality Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2008 management for development series Project Quality Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
Brainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
Using Earned Value Management for Improving Processes. By Cynthia K. West
Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.
Earned Value and Agile Reporting
Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,
700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.
About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints
The Importance of Project Quality Management. What Is Project Quality? The International Organization for Standardization (ISO)
Chapter 8 Project Quality Management November 17, 2008 2 The Importance of Project Quality Management Many people joke about the poor quality of IT products People seem to accept systems being down occasionally
Quality Perspective: Managing Software Development Projects
Economy Informatics, vol. 11, no. 1/2011 99 Quality Perspective: Managing Software Development Projects Felician ALECU Academy of Economic Studies, Bucharest, Romania [email protected] In order to better achieve
Expert Reference Series of White Papers. Importance of Schedule and Cost Control
Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project
PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and their
Introduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
Project Quality Management
Project Quality Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB
Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin
Quick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
Module 5 Cost Management PMP Exam Questions
Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
Measurement Strategies in the CMMI
Measurement Strategies in the CMMI International Software Measurement & Analysis Conference 9-14 September 2007 Rick Hefner, Ph.D. Director, Process Management Northrop Grumman Corporation One Space Park,
The Two Most Useful Earned Value Metrics: the CPI and the TCPI
PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was
Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1
Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control
AACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
Tracking Budgets and Schedules
Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is
CDC UNIFIED PROCESS PRACTICES GUIDE
Document Purpose The purpose of this document is to provide guidance on the practice of Quality Management and to describe the practice overview, requirements, best practices, activities, and key terms
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
Agile Project Management Controls
0 Agile Project Management Controls Issues with EVM and a Viable Alternative: Agile Project Management (PM) Tool ICEAA Conference, June 2015 San Diego, CA Blaze Smallwood, Booz Allen Hamilton Omar Mahmoud,
THE PROJECT MANAGEMENT PROCESS FROM A QUALITY MANAGEMENT PROFESSIONAL S PERSPECTIVE:
THE PROJECT MANAGEMENT PROCESS FROM A QUALITY MANAGEMENT PROFESSIONAL S PERSPECTIVE: More Than Just the Project Quality Management Knowledge Area for Successful Project Management ASQ BLUE RIDGE SECTION
Unit 6: Quality Management (PMBOK Guide, Chapter 8)
(PMBOK Guide, Chapter 8) Historically, quality management questions have been difficult for some exam takers for two major reasons: 1) over-reliance on their previous training and personal experience (rather
Chapter 7: Project Cost Management. Munawar [email protected]
Chapter 7: Project Cost Management Munawar [email protected] Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.
A Gentle Introduction to Earned Value Management Systems
A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
Earned Value Management for Enterprise Resource Planning Implementations
Earned Value Management for Enterprise Resource Planning Implementations Venu Kotamraju Abstract ERP implementations are a special breed of projects. They are often characterized by aggressive timelines,
PROJECTS SCHEDULING AND COST CONTROLS
Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to
Earned Value Analysis Exercise
Earned Value Analysis Exercise www.spmbook.com Author: Adolfo Villafiorita Revision: 2 (205-02-06) Given the following project plan: ID Task Immediate Predecessor (*) Expected Duration (days) Budget ($)
Predicting progress on your project
www.nonsuch.co [email protected] Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you
Business Continuity Position Description
Position Description February 9, 2015 Position Description February 9, 2015 Page i Table of Contents General Characteristics... 2 Career Path... 3 Explanation of Proficiency Level Definitions... 8 Summary
PMP Project Management Professional Study Guide, Third Edition
PMP Project Management Professional Study Guide, Third Edition Joseph Phillips McGraw-Hill is an independent entity from the Project Management Institute, Inc. and is not affiliated with the Project Management
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.
PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition
Project Cost Management
Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present
PMP Examination Tasks Puzzle game
PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in
How to Use EVM to Maintain Quality in an Agile Environment. A National Asset for National Missions 1
How to Use EVM to Maintain Quality in an Agile Environment 1 Agenda Key Terms and Calculations Earned Value Management System Supporting Systems Practical Example Earned Value Management in an Agile Environment
Text. Key Performance Measures in a Lean Agile Program. Thomas Blackburn 2/19/2015
Text Key Performance Measures in a Lean Agile Program Thomas Blackburn 2/19/2015 Goal and Objectives Discussion on Current Performance Measurement in Agile Shared understanding of measures that can drive
Why is Quality Important? Definition
QUALITY SYSTEMS By Daryle Niedermayer, I.S.P., PMP Why is Quality Important? Clients & users expect quality What if jetliners crashed as often as Microsoft Windows? Poor quality results in rework at additional
plans based on actual cost, schedule and technical progress of work [1, 9].
An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan
GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E
C O U R S E C E GPMCEP GLOBAL PROJECT MANAGEMENT, LLC Project Management Professional (PMP) Certification Exam Prep Global Project Management, LLC is a Global Registered Education Provider (R.E.P.) of
performance management system that is based on Earned Schedule Management.
The aim of this presentation is to share lessons learned from using a project performance management system that is based on Earned Schedule Management. Earned Schedule Management is a new method created
Appendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs
HUMAN RESOURCE MANAGEMENT Organizational planning Staff Acquisition Project interfaces such as organizational interfaces, technical interfaces and interpersonal interfaces. Staffing requirements Staffing
Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. [email protected]
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of
Input, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) [email protected] 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
Principles of Project Management
IPM 2012 Conference Principles of Project Management David Radkovich, PMP, EVP Subsystem Technologies [email protected] Karen Jordan, PMP Subsystem Technologies [email protected]
THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH
THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects
Overview of Florida Information Technology Project Management and Oversight Standards. Jason M. Allison, Executive Director
Overview of Florida Information Technology Project Management and Oversight Standards Jason M. Allison, Executive Director AGENCY FOR STATE TECHNOLOGY Statutory duties and responsibilities of AST: Establish
Making project management indispensable for business results. Project Management 101
Making project management indispensable for business results. Project Management 101 Donald E. Moore, MBA, PMP, President of PMI NB Kelly Barter, Chapter Manager of PMI NB AGM April 28, 2011 Topics of
Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166
Towards a Complete Earned Value Analysis Sam Sharp and Peter Hall Paper # 166 Planned vs Actual A purely accounting approach to project tracking involves the monitoring of status by simply comparing actual
Certified Software Quality Engineer (CSQE) Body of Knowledge
Certified Software Quality Engineer (CSQE) Body of Knowledge The topics in this Body of Knowledge include additional detail in the form of subtext explanations and the cognitive level at which the questions
PMBOK 5 th Edition Crash Course
PMP Certification Exam Preparation PMBOK 5 th Edition Crash Course with Bill Doescher, PMP, MBA, CSM Pi Principal i lconsultant tand Product tdevelopment tdirector Bill Doescher, PMP Product Development
Chapter 3: Project Cost Management
Chapter 3: Project Cost Management Learning Objectives o Understand the importance of project cost management. o Explain basic project cost management principles, concepts, and terms. o Discuss different
Performance Measurement
Performance Measurement Introduction Performance measurement is a fundamental building block of TQM and a tal quality organisation. Hisrically, organisations have always measured performance in some way
Earned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
Crosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
January 2011 Six Sigma SIG Meeting
Six Sigma and Project Management ASQ 502 Baltimore LSS SIG Geoffrey Withnell Dynamics Research Corp. January 2011 Six Sigma SIG Meeting I ll Ill give you a moment to digest this Some truthinpresenting
Metrics for Agile Projects:
Metrics for Agile Projects: Finding the right tools for the job Agile project managers have a wide range of metrics to choose from when it comes to tracking the progress of Agile projects. By understanding
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s
How To Manage A Project
Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management
PMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
output: communications management plan
Q1. (50 MARKS) A. List the nine PMBOK knowledge areas and give a one sentence description of the purpose of each knowledge area along with at least one output (document etc.) and its purpose. 1.Project
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,
PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and
Performance Management
Performance Management www.eiilmuniversity.ac.in Subject: PERFORMANCE MANAGEMENT Credits: 4 SYLLABUS Concept of project quality Definitions of Quality and Grade, Features, Development of Quality as a Competitive
Learning Six Sigma Theory
Independent Learning Pursuit FX Competency The following essay was written by a student in the School for New Learning, in support of an Independent Learning Pursuit (ILP). The student has agreed to share
PMI Lexicon of Project Management Terms
Project Management Institute PMI Lexicon of Project Management Terms Version 3.0 Published by: Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA Phone:
Project Quality Management. Project Management for IT
Project Quality Management 1 Learning Objectives Understand the importance of project quality management for information technology products and services Define project quality management and understand
Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process
Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01
PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.
A Comparison of PMI s PMBOK Guide Versions 4 & 3
PM WORLD TODAY FEATURED PAPER MAY 2009 A Comparison of PMI s PMBOK Guide Versions 4 & 3 By Germán Bernate The Project Management Institute PMI announced on December 31, 2008 the availability of PMBOK Version
Schedule Compression
Schedule Compression The need to reduce the time allowed for a schedule, or a part of a schedule is routine, some of the times the need arises include: When the initial schedule is too long to meet contractual
Earned Value Management Guidelines
Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application
Simple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management
Earned-Value Benchmarks for Re-baselining Your Project
500 Thoreau Street Concord, MA 01742 USA +978.369.9009 [email protected] ($39.95 for 4 PDUs; $59.95 for 6 PDUs) Earned-Value Benchmarks for Re-baselining Your Project Handy benchmarks to help you re-baseline
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
5.1 Project Control Overview
5.1 Project Control Overview Project Control is a formal process in project management. In most respects, there is not a lot of room for creativity in the Control Phase of project management. The PMBOK
Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015
Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2
Schedule Adherence a useful measure for project management
Schedule Adherence a useful measure for project management Walt Lipke PMI Oklahoma City Chapter Abstract: Earned Value Management (EVM) is a very good method of project management. However, EVM by itself
