1 Overview of Florida Information Technology Project Management and Oversight Standards Jason M. Allison, Executive Director
2 AGENCY FOR STATE TECHNOLOGY Statutory duties and responsibilities of AST: Establish IT project management and oversight standards Establish rules for the State Data Center Establish rules for IT Security Establish IT architecture standards Identify opportunities for standardization and consolidation of IT services Recommend consolidations of agency data centers or computing facilities Develop best practices for IT procurement (with DMS) Manage the state data center Perform project oversight on IT projects as required by section , F.S. 2
3 Florida Information Technology Project Management and Oversight Standards State Agencies must comply with Florida Information Technology Project Management and Oversight Standards when implementing IT projects (Section (3), F.S.) Cabinet Agencies must comply with these standards for IT projects with a total cost of $25 million or more and that impacts one or more other agencies (Section , F.S.) 3
4 Florida Information Technology Project Management and Oversight Standards Standards include: Performance measurements and metrics that objectively reflect the status of an IT project based on a defined and documented project schedule, cost, and scope Methodologies for calculating acceptable variances in the projected versus actual schedule, cost, and scope of an IT project Reporting requirements, including requirements designed to alert all defined stakeholders that an IT project has exceeded acceptable variances Content, format and frequency of project updates Rule , Florida Administrative Code 4
5 Florida Information Technology Project Management and Oversight Standards AST Project Assurance Office Collaborate with state agencies to: Develop and use consistent project management standards and methodologies Facilitate project oversight and assessment Strive for high performing IT projects across the state 1. Establish Florida IT Project Management and Oversight Standards Provide training Provide templates Conduct assessments to determine compliance with these standards 2. Perform oversight on IT projects Perform risk assessment and assist agencies in identifying project issues Recommending corrective action plans Report to the Governor s Office, House and Senate 5
6 Florida Information Technology Project Management and Oversight Standards Development of Standards: Virginia Information Technology Agency Georgia Technology Authority Michigan Department of Technology Management and Budget Reviewed and Endorsed by Gartner: As we discussed, in general I found the guidelines that it sets forth to be comprehensive, thorough and in keeping with good industry practices. We discussed a few minor suggestions, though the procedures put forth in the document are well-focused on reducing the risk on I.T. projects; as mentioned, some additional illustration (e.g. with process diagrams) might render the document more easily accessible. However, the guidelines were quite clear and complete and would I expect be quite effective in the hands of a good project management organization in helping to assure satisfactory project delivery. 6
7 Florida Information Technology Project Management and Oversight Standards are based on the project s risk and complexity (R&C) characteristics 7
8 RISK An uncertain event or condition that, if it occurs, could have a positive or negative effect on a project s objectives. COMPLEXITY - Technological and management characteristics of the project and the potential impacts, both positive and negative, that these characteristics could have on the project s risks. 8
9 RISK & COMPLEXITY ASSESSMENT Assists agencies in determining the level of project management control necessary to adequately manage a given project in order to reduce risk and increase the probability of success. Rule , Florida Administrative Code 9
10 RISK & COMPLEXITY ASSESSMENT Specialized Assessments for different project lifecycle phases: Pre-Charter R&C Assessment AST-F-0505A R&C Assessment Workbook Initiation Gate R&C Assessment Planning Gate R&C Assessment Event-Driven R&C Assessment Each assessment builds on the last to provide a cumulative R&C Score Aligns IT projects into 1 of 4 R&C categories: 10
11 DOCUMENT REQUIREMENTS Although specific documents are specified throughout the rule, no specific formats are required except for the Project Status Report As long as the content supplies the information required by the rule, any document or group of documents will meet the rule requirement Use existing agency documents, forms, templates Use existing state documents, forms, templates Use separate or comprehensive documents (PMP) Use AST-developed templates AST will provide a series of suggested, guideline templates These may be taken and revised, amended, edited and used for the project 11
12 PROJECT LIFECYCLE PHASES Initiation Planning Execution Closeout Monitoring and Controlling 12
13 Initiation Develop the key information needed to describe, approve, and start the project Communicate this information to all stakeholders Project and business sponsors approve and sign off Rule , Florida Administrative Code 13
14 Initiation Pre-Charter R&C Assessment 4 3 C C Business Case and Alternative Analysis 4 3 C C 4 3 R R R Cost Benefit Analysis Project Charter Centralized Project Repository PMP Certified Project Manager Risk Manager Employ Independent Verification & Validation (IV&V) Initiation Gate R&C Assessment R = Recommended C = Charter 14
15 Planning Develop and approve detailed project planning documents These planning documents will guide all work throughout the project Rule , Florida Administrative Code 15
16 Planning Project Management Plan R S 4 3 S S 4 3 S S S S 3 2 S Project Plan Summary Project Scope and Objectives Work Breakdown Structure (WBS) Organizational & Governance Structure Resource Plan Project Schedule -SPI and CPI -Schedule Update Project Budget Project Spend Plan Communications Plan R= Recommended S = PP Summary 16
17 Planning 4 3 S 2 Change Management Plan 4 3 S S Quality Management Plan S Deliverable Acceptance Plan S Risk Management Plan Project Management Plan S S 4 3 S S S Issue Management Plan Procurement Management Plan Organizational Change Management Plan System Security Plan Requirements Traceability Matrix (RTM) Planning Gate R&C Assessment S = PP Summary 17
18 Execution Execute and manage all activities described in the Project Management Plan, WBS, SOW and other contract documents Use project change management & governance processes for all changes to the approved baseline Develop an Operations and Maintenance Plan (O&M Plan) Agency project management activities required during the Execution phase are further described in Monitoring and Controlling. Rule , Florida Administrative Code 18
19 Monitoring and Controlling Spans all phases of the project Regular review of project status Identify variances from approved project cost, schedule, and scope Monitor and control the project as described in the Project Management Plan or the Project Plan Summary Rule , Florida Administrative Code 19
20 Monitoring and Controlling Project Schedule 4 3 Use Earned Value Management (SPI and CPI) to assess schedule variance 2 1 Evaluate baseline schedule against current progress Project Cost 20
21 Monitoring and Controlling Earned Value (EV) - Represents the value of the work that is actually accomplished as of a specific date. Earned Value is an objective way of measuring performance and predicting future outcomes by enabling: Reporting progress with greater confidence Decision-making by management EV combines measurements of scope, schedule, and costs 21
22 Monitoring and Controlling R R R 4 3 R R Project Scope Project Change Project Procurement Project Risk Project Issues Decision Tracking Action Item Tracking Requirements Traceability Matrix Lessons Learned (gathered throughout project) R= Recommended 22
23 Monitoring and Controlling Status Reports The agency will report project status based on R&C Category 4 3 R R Bi-Weekly Interim Project Status Report (abbreviated report) Monthly Status Report (full report) 1 Project Status Overview AST-F-0505B Status Report Form 2 Project Progress 3 Project Issues / Risks 4 Project Spend Plan 5 Project Summary R= Recommended 23
24 Closeout Lessons Learned Project Closeout Report (PCR) Post Implementation Review (PIR) Report Rule , Florida Administrative Code 24
25 COMPLIANCE Grandfather clause for existing projects AST annual assessment of agency compliance Agencies may request variance or waiver Section , F.S. Rule , Florida Administrative Code 25
26 AST PROJECT OVERSIGHT Section , F.S. AST will complete oversight on: State agency IT projects $10 million+ Funded in the GAA or any other law Cabinet agency IT projects $25 million + Impacts one or more other agencies Rule , Florida Administrative Code 26
27 AST PROJECT OVERSIGHT The agency and AST will work together to: Establish oversight parameters Update and review project schedule weekly Perform monthly project reviews to determine schedule, scope or cost variance, and assess project risks and issues Create quarterly project reports 27
28 AST PROJECT OVERSIGHT If scope, schedule or cost variance is outside of acceptable variance range, the agency and AST will work together to: Perform Diagnostic Risk Assessment Review Project Documentation Develop Preliminary Findings / Recommendations Develop Corrective Action Plan 28
29 AST PROJECT OVERSIGHT If an IT project is identified as high-risk due to the project exceeding acceptable variance ranges, AST will report quarterly to: Executive Office of the Governor President of the Senate Speaker of the House of Representatives 29
30 AST PROJECT OVERSIGHT Other requirements of AST Oversight projects: The project must adhere to the requirements of an R&C Category 4 Project The project must use a PMP certified Project Manager The project must employ Independent Verification & Validation (IV&V) 30
31 RECAP AST Oversight requirement began January 1, 2015 Oversight Agreement Monthly Reviews Quarterly Reports Rule Chapter 74-1A, F.A.C. - Florida Information Technology Project Management and Oversight Standards became effective July 16, 2015 Formal AST Compliance Assessments begin July 1, 2016 Risk and Complexity Assessment Project Management and Documentation Based on R&C Category Earned Value Management (EVM) 31
32 32
33 AST PROJECT ASSURANCE OFFICE Director Shelley McCabe, PMP Project Managers Lisa Hopkins, PMP Rebecca Green, PMP Mike Avello, PMP Beverly Bonasorte, PMP
34 Jason Allison Executive Director / State CIO Agency For State Technology 4050 Esplanade Way, Suite 115 Tallahassee, FL For Rule 74-1, F.A.C. and Incorporated Forms: 34
OFFICE OF THE CIO. PROCEDURE Informational VERSION: 1.0
OFFICE OF THE CIO PROCEDURE Informational VERSION: 1.0 Purpose Project Management of Major or Large NDUS Information Technology Projects Project Managers Guide/Checklist This procedural process will ensure
More informationPHASE 8: IMPLEMENTATION PHASE
PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the
More informationMNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
More informationATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES
1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through
More informationAppeals Case Management System Project. Scope Management Plan. November 20, 2014
Appeals Case Management System Project Version 1.0 Health and Human Services Agency, Office of Systems Integration Template Revision History REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF
More informationPROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
More information- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and
More informationHHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC)
Office of the Chief Information Officer Office of the Assistant Secretary for Resources and Technology Department of Health and Human Services HHS OCIO Policy for Information Technology (IT) Enterprise
More informationID Task Name Time Pred
0 UC Modernization Project Plan 1115 d 1 1 Phase I - Business Case Development and Competitive Procurement 205 d 2 1.1 Complete Initial Feasibility Study 55 d 3 1.2 Prepare and Issue LBR 30 d 2 4 1.3 Competitive
More informationSCOPE MANAGEMENT PLAN <PROJECT NAME>
SCOPE MANAGEMENT PLAN TEMPLATE This Project Scope Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
More informationITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...
More informationPROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
More informationPMP Examination Tasks Puzzle game
PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in
More informationLMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012
PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 TABLE OF CONTENTS INTRODUCTION... 2 PROJECT MANAGEMENT APPROACH... 2 PROJECT SCOPE... 2 MILESTONE LIST... 2 SCHEDULE BASELINE
More informationCOMMONWEALTH OF VIRGINIA
COMMONWEALTH OF VIRGINIA Information Technology Resource Management (ITRM) PROJECT MANAGER SELECTION AND TRAINING STANDARD Virginia Information Technologies Agency (VITA) Reviews This publication was reviewed
More informationCertification Preparation Course LATVIKON (R.E.P.)Centre
PMP Certification Preparation Course LATVIKON (R.E.P.)Centre ABOUT THIS COURSE Your ability as a project manager to demonstrate best practices in Project Management both on the job and through professional
More informationEnterprise Project Management Initiative
Executive Summary Enterprise Project Management Initiative At a time when budgetary challenges became more and more aggressive, the Commonwealth of Kentucky determined in late 2000 it must develop a more
More informationPHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
More informationPHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
More informationProject Management Professional (PMP) Examination Content Outline
Project Management Professional (PMP) Examination Content Outline Project Management Institute Project Management Professional (PMP ) Examination Content Outline Revised August 2011 Published by: Project
More informationIndependent Verification and Validation of SAPHIRE 8 Software Project Plan
INL/EXT-09-17022 Rev. 2 Independent Verification and Validation of SAPHIRE 8 Software Project Plan March 2010 The INL is a U.S. Department of Energy National Laboratory operated by Battelle Energy Alliance
More informationPHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
More informationCertification Exam Objectives: PK0-003
Certification Exam Objectives: PK0-003 INTRODUCTION The CompTIA Project + examination is designed for business professionals involved with projects. This exam will certify that the successful candidate
More informationIT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
More informationDepartment of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
More information2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster
2-Day Workshop Project JumpStart The Workshop Designed to Launch Projects Faster Traditional Classroom / Onsite Course No. 665 Duration: 2 days Credits: 14 PDUs / 1.4 CEUs Prerequisites Twelve hours of
More informationCrosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
More informationProgram Management Professional (PgMP) Examination Content Outline
Program Management Professional (PgMP) Examination Content Outline Project Management Institute Program Management Professional (PgMP ) Examination Content Outline April 2011 Published by: Project Management
More informationProject Management Professional (PMP) Examination Content Outline
Project Management Professional (PMP) Examination Content Outline Project Management Institute Project Management Professional (PMP) Examination Content Outline June 2015 Published by: Project Management
More informationIT Project Governance Manual Version 1.1
IT Project Governance Manual Version 1.1 A Mandatory Reference for ADS Chapter 577 New Reference: 04/13/2010 Responsible Office: CIO File Name: 577mak_041310 UNITED STATES AGENCY FOR IT Project Goverance
More informationProject Management Guidelines
Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.
More informationProject Scope Management in PMBOK made easy
By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating
More informationBiometrics Enterprise Architecture Project Management Plan (BMEA PMP)
Biometrics Enterprise Architecture Project Management Plan (BMEA PMP) Version 1.0 Prepared by: Date: November 24, 2008 Revision History Purpose Revision Date Level 11/17/2009 First Draft 1.0 Responsible
More informationCentral Project Office: Charter
Central Project Office: Charter ITCS: Central Project Office EAST CAROLINA UNIVERSITY 209 COTANCHE STREET, GREENVILLE, NC 27858 1 Table of Contents INTRODUCTION... 3 PURPOSE... 3 EXPECTED BENEFITS... 3
More informationCOMMONWEALTH OF VIRGINIA
COMMONWEALTH OF VIRGINIA Information Technology Resource Management (ITRM) TECHNOLOGY MANAGEMENT PROJECT MANAGEMENT STANDARD Virginia Information Technologies Agency (VITA) Reviews This publication was
More informationProject Management Professional (Certified by PMI)
Project Management Professional (Certified by PMI) PMI certified Project Management Professional credential is the most important industryrecognized certification for project managers. This recognition
More informationFlorida PALM Quarterly Project Oversight Report: Comprehensive Review For January March 2015
Department of Financial Services Florida Planning, Accounting, and Ledger Management (PALM) For Period: January March 2015 Quarter Ending: 3/31/2015 Agency Name: Department of Financial Services Project
More informationProject Management Skills for Trainers. William H. Dannenmaier Bill@PlantLeadership.com
Project Management Skills for Trainers William H. Dannenmaier Bill@PlantLeadership.com Instructor Bill William H. (Bill) Dannenmaier MA, MBA, PMP Experience Former US Navy Officer 30 years project management
More informationProgram Title: Advanced Project Management Knowledge, Skills & Software Program ID: #1039168 Program Cost: $4,690 Duration: 52.
Program Title: Advanced Project Management Knowledge, Skills & Software Program ID: #1039168 Program Cost: $4,690 Duration: 52.5 hours Program Description The Advance Project Management Knowledge, Skills
More informationVisit www.pm-prepcast.com for Exam Resources P a g e 16
Module and Lesson Directory No Lesson Title Type Duration Module 00.0 Welcome & Exam Overview 1. L00.00 Welcome Video 28:28 Module 00.1 Student Workbook 2. L00.10 PM PrepCast Student Workbook PDF -- Module
More informationIntroduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
More informationEnterprise Performance Life Cycle Management. Guideline
Enterprise Performance Life Cycle Management Guideline Version 2.1 PREPARED BY THE ENTERPRISE PROGRAM MANAGEMENT OFFICE MAY 2011 Table of Contents Document Control...i 1. Introduction... 2 1.1 Purpose...
More informationThe 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
More informationPHASE 5: DESIGN PHASE
PHASE 5: DESIGN PHASE During the Design Phase, the system is designed to satisfy the requirements identified in the previous phases. The requirements identified in the Requirements Analysis Phase are transformed
More informationProgram Title: Advanced Project Management Program ID: #1025924 Program Cost: $3,780 Duration: 37.5 hours. Program Description
Program Title: Advanced Project Management Program ID: #1025924 Program Cost: $3,780 Duration: 37.5 hours Program Description The Advance Project Management course is a training offering for professionals
More informationIT SYSTEM LIFE-CYCLE AND PROJECT MANAGEMENT
United States Department of Agriculture Agricultural Marketing Service Directive 3130.8 IT SYSTEM LIFE-CYCLE AND PROJECT MANAGEMENT I. PURPOSE... 1 II. POLICY... 1 III. DEFINITIONS... 1 IV. DOCUMENTATION
More informationBest Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
More informationRequest for Resume (RFR) for Project Manager (Senior) CATS+ Master Contract All Master Contract Provisions Apply. Section 1 General Information
Request for Resume (RFR) for Project (Senior) Section General Information RFR Number: (Reference BPO Number) Functional Area (Enter One Only) Q00R00 BPO # 060B900 in ADPICS Functional Area 0 IT Management
More informationInformation Technology Project Oversight Framework
i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11
More informationProject Management Professional (PMP) Boot Camp
Project Management Professional (PMP) Boot Camp According to the Project Management Institute, the world's leading association for the project management profession: "PMP Certification is the profession's
More informationU.S. Department of Education Federal Student Aid
U.S. Department of Education Federal Student Aid Lifecycle Management Methodology Stage Gate Review Process Description Version 1.3 06/30/2015 Final DOCUMENT NUMBER: FSA_TOQA_PROC_STGRW.NA_001 Lifecycle
More informationPHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
More informationProject Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
More informationFinal. North Carolina Procurement Transformation. Governance Model March 11, 2011
North Carolina Procurement Transformation Governance Model March 11, 2011 Executive Summary Design Approach Process Governance Model Overview Recommended Governance Structure Recommended Governance Processes
More informationTime Management. Herb Pollard III
Time Management A Small Business Perspective Herb Pollard III Project Manager for Time Management - Pollard PMI Slide 1 Introduction: Time Management - Pollard PMI Slide 2 Project Phases and the Areas
More informationITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
More informationSecond Amendment To the HIPAA 5010 and ICD-10 Technical Assistance and Support Services Contract
Second Amendment To the HIPAA 5010 and ICD-10 Technical Assistance and Support Services Contract This second Amendment to Contract Number is effective as of December 12, 2011, between the Iowa Department
More informationSTATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840
MARYLAND STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 Bobbie S. Mack, Chairman David J. McManus, Jr., Vice Chairman Rachel T. McGuckian Patrick H. Murray Charles
More informationProject Management for Everyone
Project Management for Everyone Contact Information Adam Donaldson, PMP Business Management & Analysis Group System, Analytics & Insights Group Phone: (202) 994-6867 Email: adonald@gwu.edu Objectives Basic
More informationProject Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1)
Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Date: October 1, 2014 Version: 3.1 DOCUMENT REVISION HISTORY Version Date Changes Updated By 0.1 02/13/014 Initial
More informationProject Management Plan Template
Abstract: This is the project management plan document for . This is a controlled document and should be maintained in a configuration environment. Project Management Plan Template Contents REVISION
More informationLEXEVS OPERATIONS AND MAINTENCE SUPPORT PROJECT MANAGEMENT PLAN
LEXEVS OPERATIONS AND MAINTENCE SUPPORT PROJECT MANAGEMENT PLAN Version Number: 1.0 Version Date: October 1, 2014 VERSION HISTORY Version Number Implemented By Revision Date Approved By Approval Date 1.0
More informationNUMBER 107-004-030 PO EFFECTIVE DATE. July 1, 2015 REFERENCE/AUTHORITY. Procedure: 107-004-030 PR APPROVED SIGNATURE
STATEWIDE POLICY DIVISION NUMBER 107-004-030 PO EFFECTIVE DATE July 1, 2015 REFERENCE/AUTHORITY SUPERSEDES Policy #107-004-030 Feb. 1, 2004 PAGE NUMBER Pages 1 of 7 Chief Information Office POLICY OWNER
More informationIT Project Management Methodology. Project Execution Support Guide. Version 0.3
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Execution Support Guide Version 0.3 Table of Contents 1 INTRODUCTION... 4 1.1 When should Project Execution
More informationIT GOVERNANCE POLICY
State of Illinois Department of Central Management Services IT GOVERNANCE POLICY Effective December 15, 2008 Revised: January 03, 2012 Version 1.1 1 State of Illinois Department of Central Management Services
More informationThe PMP Application Process
The PMP Application Process The purpose of this document is to explain the PMP application process and provide helpful links and tools for submitting your application. Reference: The reference for the
More informationPartnering for Project Success: Project Manager and Business Analyst Collaboration
Partnering for Project Success: Project Manager and Business Analyst Collaboration By Barbara Carkenord, CBAP, Chris Cartwright, PMP, Robin Grace, CBAP, Larry Goldsmith, PMP, Elizabeth Larson, PMP, CBAP,
More informationProgram Title: Advanced Project Management Program ID: #1025924 Program Cost: $3,780 Duration: 37.5 hours. Course Description
Program Title: Advanced Project Management Program ID: #1025924 Program Cost: $3,780 Duration: 37.5 hours Course Description This course is the flagship course for Project Management certifications including
More informationVoteCal Statewide Voter Registration System Project. Master Project Management Plan. Version 1.2
VoteCal Statewide Voter Registration System Project Master Project Management Plan Version 1.2 October 2010 October 2010 i REVISION HISTORY REVISION # DATE OF RELEASE OWNER SUMMARY OF CHANGES 0.1 3/12/2009
More informationExpert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam
Expert Reference Series of White Papers Tips and Techniques to Pass the PMP Exam 1-800-COURSES www.globalknowledge.com Tips and Techniques to Pass the PMP Exam Dan Stober, PMP Introduction Passing the
More informationCPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
More informationAppendix E Program Management Plan Template
Appendix E Program Management Plan Template Version 2 March 7, 2005 This page is intentionally left blank. Version 2 March 7, 2005 Title Page Document Control Panel Table of Contents List of Acronyms Definitions
More informationMINNESOTA STATE POLICY
Version: 2.00 Approved Date: 02/24/2012 Approval: Signature on file MINNESOTA STATE POLICY From the Office of Carolyn Parnell Chief Information Officer, State of Minnesota IT Project Portfolio Data Management
More informationB o a r d of Governors of the Federal Reserve System. Supplemental Policy Statement on the. Internal Audit Function and Its Outsourcing
B o a r d of Governors of the Federal Reserve System Supplemental Policy Statement on the Internal Audit Function and Its Outsourcing January 23, 2013 P U R P O S E This policy statement is being issued
More informationhttp://www.io4pm.org IO4PM - International Organization for Project Management
THE ONLY BOOK CAN SIMPLY LEARN PROJECT MANAGEMENT! Page 1 Contents ABOUT THE AUTHOR... 3 WHAT IS PROJECT MANAGEMENT?... 5 ORGANIZATIONAL INFLUENCES AND PROJECT LIFECYCLE... 11 PROJECT MANAGEMENT PROCESSES...
More informationAssessment of NCTD Program Management Framework for Positive Train Control Program
Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation
More informationAudit of Veterans Health Administration Blood Bank Modernization Project
Department of Veterans Affairs Office of Inspector General Audit of Veterans Health Administration Blood Bank Modernization Project Report No. 06-03424-70 February 8, 2008 VA Office of Inspector General
More informationPMAP. Project Management At Penn PMAP
Project Management At Penn 1 Fundamentals Course Objective To provide you with an overview of Topics Project Management at Penn () Project Governance Phases & Project Management Activities Project Management
More informationIT Project Management Practices Guide
IT Project Management Practices Guide Introduction The IT Project Management Practices Guide (Guide) contains a repeatable, institutionwide approach for the management of application development and/or
More informationHow To Train Project Management
PROJECT MANAGEMENT TRAINING PROGRAM 2006 EWPM Book by DLBALLC and DGHELLC - All Right Reserved Page 1 of 35 Revision History REV DESCRIPTION DATE APPROVED 2006 EWPM Book by DLBALLC and DGHELLC - All Right
More informationProject Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
More informationGPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E
C O U R S E C E GPMCEP GLOBAL PROJECT MANAGEMENT, LLC Project Management Professional (PMP) Certification Exam Prep Global Project Management, LLC is a Global Registered Education Provider (R.E.P.) of
More informationPgMP Credential. Christopher Talmont, PMP, PMI-RMP. February 23, 2011
PgMP Credential Christopher Talmont, PMP, PMI-RMP February 23, 2011 A b o u t M e 7 years of experience as an instructor and consultant of project scheduling software and best practices 4 years of experience
More informationPROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in this Project Scope Statement is implicitly excluded from the project. Create links to referenced documents (e.g., Link_To_ ) by using Insert
More informationDevelop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
More informationProject Management for Everyone
Project Management for Everyone Contact Information Adam Donaldson, PMP Business Management & Analysis Group Phone: (202) 994-6867 Cell: (240) 472-2171 Email: adonald@gwu.edu Objectives Basic understanding
More informationPHASE 9: OPERATIONS AND MAINTENANCE PHASE
PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.
More information08-13 VALIDATION (IV&V) PROGRAM MANAGEMENT
ASSESSMENT REPORT ORACLE E-BUSINESS SUITE RELEASE 2 INDEPENDENT VERIFICATION AND 08-13 VALIDATION (IV&V) PROGRAM MANAGEMENT September 30, 2008 OFFICE OF INSPECTOR GENERAL WASHINGTON, DC 20401 Memorandum
More informationGovernmental Oversight and Accountability Committee
The Florida Senate BILL ANALYSIS AND FISCAL IMPACT STATEMENT (This document is based on the provisions contained in the legislation as of the latest date listed below.) Prepared By: The Professional Staff
More informationPractical Project Management For Administrative Professionals
Practical Project Management For Administrative Professionals Presented By: Rhonda Scharf, CSP Certified Speaking Professional ON THE RIGHT TRACK 1 PROJECT MANAGEMENT FOR ADMINISTRATIVE PROFESSIONALS What
More informationOnline Saturday & Sunday 4-Day Live PMP Training
Online Saturday & Sunday 4-Day Live PMP Training Course Syllabus: DAY 1: Welcome a. Who is BOBCAT Academy? b. Introduce Yourself c. Follow Us Module 1: Course Introduction a. Course Dates b. Start/Stop
More informationPMI Certified: PMP - Project Management 5 Days
www.etidaho.com (208) 327-0768 PMI Certified: PMP - Project Management 5 Days Course Description This PMP certification training class is designed for individuals who have on-the-job project management
More informationTHE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
More informationFamily Computer Centre
PMP - Project Professional 35 Contact Hours Comprehensive Training Program Designed on the basis of Project Body of Knowledge (PMBOK Guide) Family Computer Centre Ground Floor, Al Rayyan Complex P. O Box:
More informationSoftware and Hardware Configuration Management
DOWNLOADED AND/OR HARD COPY UNCONTROLLED Verify that this is the correct version before use. AUTHORITY DATE Jeffrey Northey (original signature on file) IMS Manager 07/09/2014 Doug Dorrer (original signature
More informationProject Management Life Cycle (PMLC)
Project Management Life Cycle (PMLC) Page 2 Project Management Life Cycle (PMLC) Introduction PMLC Working Group IT Business Process Management(BPM) IT Project Management Office (PMO) Finance System Support
More informationTenStep Project Management Process Summary
TenStep Project Management Process Summary Project management refers to the definition and planning, and then the subsequent management, control, and conclusion of a project. It is important to recognize
More informationProject Management Planning
The Project Plan Template The Project Plan The project plan forms the basis for all management efforts associated with the project. A project plan template is included in this document. The information
More informationInput, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) Marc.Conrad@luton.ac.uk 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
More information