Earned Value Management for Enterprise Resource Planning Implementations
|
|
|
- Reginald Sims
- 9 years ago
- Views:
Transcription
1 Earned Value Management for Enterprise Resource Planning Implementations Venu Kotamraju Abstract ERP implementations are a special breed of projects. They are often characterized by aggressive timelines, high budgets and involvement of diverse teams. This emphasizes the need to have a reliable tool to measure the performance of ERP implementations throughout the execution phases. Earned Value Analysis, with its basis in cost, benefit and timeline is a good financial tool for Project managers. This paper starts by establishing the key concepts of Earned Value analysis. Metrics such as,,, CPI, SPI are explained at an overview level. Earned value analysis is then applied to the individual phases of a typical ERP implementation using an illustrative project. Each phase of the implementation such as, requirements gathering, is then analyzed by giving an overview of the phase, describing the major activities and then describing the M(Earned Value Management) activities that need to take place in that phase. This paper highlights how Earned value analysis can be used for ERP implementations with a focus on the phases of ERP implementation. Jun 2008
2 Introduction Enterprise Resource Planning (ERP) Implementations A special breed of projects Embarking on ERP implementation is a daunting task for any enterprise due to its inherently complex nature. The process often involves big budgets, long durations and large teams across multiple organizational units (IT, Business, Infrastructure, etc.). This places a great amount of stress on the IT and Business leadership involved. They are also a special breed of projects; they are part technology and part business. The primary differentiating factor is the heavy involvement of business and IT. Often, the primary reason for implementing a packaged ERP application is to redesign the existing business processes into industry standard best-of-breed processes, with the ability to scale up to the enterprise s growth plans. Given this unique nature of ERP implementations, the project management team assumes critical importance in measuring, monitoring and reporting the project status accurately. Most project managers engulf themselves in project plans, resource plans, risk registers, status reports and more status reports. What is often missing in those reports is a standard way of measuring, monitoring and reporting the status. In such a situation, project managers need all the tools and techniques they can get. The earned value technique, tailored for ERP implementation, offers one such performance measurement tool. Earned Value Analysis Key Concepts Earned value analysis or Earned Value Management (M) is a financial measurement tool that combines the conflicting aspects of scope, schedule and cost into a unified set of metrics. These metrics can be used for measuring, monitoring, reporting and forecasting project performance. It can be used through all the phases of a project, from Initiation to Closure. The building blocks of this technique are 1. Defining the Work Breakdown Structure (WBS) Identifying a mutually exclusive and collectively exhaustive set of activities/ tasks Identifying the level at which earned value analysis will be performed 2. Assign values to each WBS Item, also called Planned Values () Allocate the total budget into the individual items 3. Establishing earning rules for each WBS Item 0/100, 50/50 or 20/80 are some of the methods of tracking the value earned as a percentage complete of the work accomplished. Once these basic steps are achieved, a project plan can be created to track the project. As the tasks are started, the value earned can be tracked. Some of the common metrics available for measurement are: Planned Value (): is the Budgeted Cost for Work Scheduled (BCWS/ B) to be completed on an activity or WBS Item up. Earned Value (): is the Budgeted Cost of Work Performed (BCWP) Actual Cost (): is the total cost incurred in accomplishing the work scheduled. This must correspond to what was budgeted. 2 Infosys White Paper
3 $250, Months -> The chart above shows the interplay between the three components of the analysis. Based on these three variables, we can calculate the following indicators Cost Variance (CV) = - $250,000 SV In $ In Schedule Variance (SV) = - Infosys White Paper 3
4 $160,000 $140,000 CV $120,000 $80,000 $60,000 $40,000 $20, The first two set of indicators measure the cost and schedule variance of the work accomplished. The next two are efficiency indicators that can be used for forecasting the cost and schedule performance. Cost Performance Indicator (CPI) = / Schedule Performance Indicator (SPI) =/ ERP Implementation Phases Overview Note: This section refers to the Infosys Package implementation methodology (Intrak), explaining the various phases for a typical ERP Implementation. A typical ERP Implementation has the following stages Strategic Stage Planning Phase Business Case preparation Package Evaluation Phase Package solution options are generated and finalized Organizing Phase Project organization, methodology and change management processes finalized. This stage is the precursor to the project organization being formed. It is at this point that the Budget for the entire implementation is usually identified at the high level. Project Stage Project scoping Requirements Gathering To-Be Process Design Configuration and Development Cut-over and Support The individual phases and the nature of M for each phase has been discussed in the sections below. For this purpose, an illustrative ERP project has been used. Project Size 220 K USD Project Duration 18 Months 4 Infosys White Paper
5 Phase wise duration split PHASE NAME DURATION IN MONTHS Scoping 2 Requirements 4 To Be Design 4 Configuration and Development 4 Integration and Acceptance Testing 3 Cutover and Support 1 Total 18 Let us assume that these values were finalized during the strategic phase of the ERP implementation. M Application to ERP Phases Project Scoping Overview The activities in this phase are directed towards a clear-cut definition of the project with respect to its scope, requirements and resources. Major Activities Project Manager (Client) and scoping team selection Project Scope definition Project team formation Project team requirements identification Orientation Workshops Project planning and sign-off Formal kick-off Earned Value Analysis Activities This phase is key in establishing the basic building blocks for the M. WBS has to be built from the project scope definition WBS level, at which tracking will be done, has to be established. Note: At this point in time, the project management does not have the detailed information for all the tasks. Therefore, these values can later be refined during the requirements gathering stage. s have to be assigned to the WBS Items at the level at which planning will be done. This has to be discussed and agreed upon with the business users during the scope discussions. Earning rules for the WBS Items also have to be established in this phase. Finally, the Project Plan is created in this phase and it clearly establishes all the phases and the duration of the entire implementation. This project plan will be key to tracking the actual cost and earned values to the planned values. All of the above steps will be represented in the Project measurement plan, which is usually discussed with the key stakeholders during the Formal kickoff. At this point, most of the actual cost goes into establishing the cost, scope and operational baselines. s will also be toward the same tasks. The chart given below gives a graphical representation of the S- Curves, showing the, and values. We will continue to monitor these S-curves through the rest of the implementation phases Infosys White Paper 5
6 $250,000 SCOPING Months -> Requirements Gathering Overview The Core Business Processes (CBP), identified during Project Scoping phase, are used to derive the As-Is processes. The high level gap analysis is carried out. Major Activities Business Process Mapping Identification of sources of information Environment installation Training to core team (client) on specific modules Prepare for workshop Workshop to capture business processes High level Process mapping and Gap Analysis System Status Mapping M Activities This is the first phase where tracking costs, schedule and quality start to assume greater importance. Project Plan is being tracked and updated on a regular basis - usually on a weekly basis. Actual Cost starts to accumulate in this phase and can be obtained by combining the timesheet data, from the time tracking systems, along with resource cost details and other material costs from the project accounting systems. Most of the actual costs at this point are licensing, hardware and software costs that will be used throughout the course of the project. Schedule variance can be tracked at this point, using the s against the s. Tasks which have begun will get 20%, and completed tasks will get 100% as per the earning rule. Total can then be calculated as 6 Infosys White Paper
7 Due to the complex nature of ERP implementation, the requirements phase usually runs over budget. The key reasons for this are: Scope Change, due to new work item identification Complexity change, due to difficulty of getting information on existing process Lower productivity, due to team dynamics the various members of the team are working together for the first time and this could lead to lower productivity at the team level In the chart below, the project is shown to be ahead of schedule and over budget. $250,000 SCOPING REQUIREMENTS Months -> To-Be Design Overview The To-Be Design Phase involves key activities such as To-Be Process Design of the proposed solution, Data Migration Design, Configuring the proto-type, and conducting the Conference Room Pilot (CRP). Major Activities To-Be Process Design Functional Specifications for Custom Components, Data Migration Programs Configure the Proto-Type Conduct CRP Infosys White Paper 7
8 M Activities This is the phase where schedule and cost overruns have to be tracked with the utmost care. WBS Updates, if required, are done in this phase. All WBS Items are broken to the tracking level and their s are finalized The total of the project is baselined Actual cost values be obtained by combining the labor costs from the time keeping systems and material costs from the project accounting systems. Most of the s, at this point, are towards the deliverables for the project. Schedule variance can be tracked, using the s against s. This phase is also a good time to start predicting/ forecasting the cost and schedule performance. In this phase, forecasting ratios can be calculated and used. SV = - >0 is good; it indicates that the project is ahead of schedule. <0 indicates that the project is behind schedule SPI can be calculated as SPI = / This SPI can be used to forecast the completing of the design stage Additional CPI can be used for tracking the cost performance. CPI and SPI combined together give a very good tool to the project manager to tack corrective actions. In addition to tracking, correcting cost and schedule overruns, this phase also involves estimating the total budget at cost. END OF PROJECT B = Σ BEGINING The Budget at Completion (B) indicates the total for the project at completion Using the CPI and B, we can calculate the Expected Budget at Completion (E). The Estimate to Complete (ETC) is another key indicator to indicate the estimate of work left to be completed before the project can go live. 8 Infosys White Paper
9 In the chart below, the project is shown to be tracked closer to the of the budget. Both, the and s are approaching the s. $250,000 TO BE DESIGN SCOPING REQUIREMENTS Configuration & Development Overview Months -> The activities during this phase are directed towards: Technical Design, Development and Testing of custom components Final Configuration of the package/ components in accordance with the solution design, as per the To-Be processes document and Configuration plan. Training Train the Trainer System Integration Testing (Includes Regression Testing) UAT Data Migration of Master Data Major Activities Technical Design and Development of all Custom components Final Configuration Training System Integration Testing User acceptance Data Migration of Master Data Infosys White Paper 9
10 M Activities This phase involves configuration of the actual application along with component development This phase has peculiar characteristics as most of the work is technical in nature and tracking such work becomes even more critical. The first half of configuration and development can be easily tracked using the ratios of CPI/SPI, which is a good indicator of how the work is progressing. Any overruns are typical in nature, and the performance indicators are a good tool for the project manager to predict the schedule and cost for this phase. Also, using the metrics of E and ETC, the estimated budgets can be forecasted reasonably well. The second half of this phase is spent in testing. This phase too can be tracked using the CPI/SPI indicators, since testing usually involves two critical activities Test Execution Defect Resolution Both of the above activities are fairly predictable using the metrics available, such as execution progress measured in test cases executed per day, or in case of defects - defects resolved per day. The s and s start to approach closer to the s. Any deviations in this phase will result in overruns of cost and duration. $250,000 CONFIG AND D/ TESTING TO BE DESIGN SCOPING REQUIREMENTS Months -> 10 Infosys White Paper
11 Cutover & Support Overview The purpose of this phase is to ensure a smooth transition from the existing legacy system(s) to the new system (installed package), and to establish a procedure for issue resolution. This includes Perform Freeze Period Activities and Cut-Over Verify that the activities in the Go-Live Check List (system administration and establishment of Help Desk activities that need to be communicated/ coordinated to the client including Go-Live Readiness) have been accomplished Go-Live and Post Production Support Project Closure and Sign Off Major Activities Freeze Period and Cut-Over Verify Activities in the Go-Live Check List M Activities This phase requires tracking all the costs and s to the s Most of the costs for the project have been accrued and the values have been earned. E will be approaching the B and ETC will be approaching zero SPI/CPI over the entire project can be calculated for future projects Lessons learnt throughout the project execution stages around earning rules, such as what rules worked better for what system/team can be documented in this phase Lessons learnt around the work breakdown structure, such as how much effort was spent in breaking down a task to detail versus the benefit achieved in tracking the costs at that level can be documented in this phase. At this point, any contingencies in the budget will be utilized or released for other projects. $250,000 CONFIG AND D/ TESTING C U T O V E R TO BE DESIGN SCOPING REQUIREMENTS A N D S U P P O R T Months -> Infosys White Paper 11
12 Go live and Post Production Support In this phase, the project goes live as per the cutover plan. Continuous monitoring is carried out as per the established support process. All issues are captured using the production support systems as opposed to the defect tracking systems used earlier in the project. SPI and CPI, measured along the project duration, can be utilized for issue resolutions. Additionally, any lessons learnt in measuring the performance of the entire project execution can be passed on to the production support teams. Project closure and sign-off Intimate all team members about the project closure date and obtain their concurrence for the same Arrange for closure meeting in consultation with PMO Formally announce the closure of the project and take a sign-off from the PMO Conclusion Often, one of the biggest challenges in ERP implementations is the absence of a measurable parameter for its success. M provides an excellent measurement tool that can not only help during the implementation, but also in measuring the success of one project against another. An area that M does not focus on is the quality aspect of the project. However, with a robust SEI Capability Maturity Model (CMM) and a quality assurance at each phase, quality of the project can also be closely monitored. M, along with the CMM assessments, can be a very helpful tool in successfully implementing packaged applications. About the Author Venu Kotamraju (Associate Business Manager, Enterprise Solutions, Infosys) Venu has more than 8 years of experience in implementing packaged ERP solutions. His areas of specialization include the package implementation methodology, ERP program management and core financial, order to cash and procure to pay business process design. He has an exposure to various industries such as Retail, Hi Tech and Financial services sectors. Presenting at the Oracle Application User Group conferences in US and Australia, he has also co-authored Rapid Retail Store Opening An Oracle ebusiness Suite-based Solution. He is a Certified PMP (PMI, USA). He holds an MBA from IIM Bangalore, India and spent a term as an MBA exchange student at the Kenan Flagler Business School at UNC, Chapel Hill. He also holds a degree in Electronics Engineering from NIT (REC), Trichy. Read more on this at Infosys Blog
700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.
PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition
Chapter 7: Project Cost Management. Munawar [email protected]
Chapter 7: Project Cost Management Munawar [email protected] Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.
How To Implement An Enterprise Resource Planning Program
ERP Implementation Program Key phases of ERP implementation: Analysis of the company existing or designing new business process descriptions Inventory of the company s existing formal workflows or designing
SEI Level 2, 3, 4, & 5 1 Work Breakdown Structure (WBS)
SEI Level 2, 3, 4, & 5 1 Work Breakdown Structure (WBS) 1.0 SEI Product 1.1 SEI Level 2 Product 1.1.1 SEI Level 2 Process 1.1.1.1 Requirements Management Process 1.1.1.2 Software Project Planning Process
Blend Approach of IT Service Management and PMBOK for Application Support Project
Blend Approach of IT Service and PMBOK for Application Support Project Introduction: This paper addresses the process area, phases and documentation to be done for Support Project using Project and ITSM
An introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
Brainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
IST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
Project Execution - PM Elements
Performance Initial Release 1. Introduction to Project Tracking and Reviewing Once a project has advanced to the phase of performance, the consistent and constant flow of information on the true status
Introduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
Brillig Systems Making Projects Successful
Metrics for Successful Automation Project Management Most automation engineers spend their days controlling manufacturing processes, but spend little or no time controlling their project schedule and budget.
Sample Examination Questions
Sample Examination Questions The following questions are examples of the type of questions that appear on the PMP Certification Examination. Disclaimer: These questions are intended for study purposes
PMO Metrics Recommendations
Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project
INSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
ID Task Name Time Pred
0 UC Modernization Project Plan 1115 d 1 1 Phase I - Business Case Development and Competitive Procurement 205 d 2 1.1 Complete Initial Feasibility Study 55 d 3 1.2 Prepare and Issue LBR 30 d 2 4 1.3 Competitive
ERP Implementation Methodology SAFAL ERP
ERP Implementation Methodology SAFAL ERP Six Stage Implementation Plan SAFAL ERP Initiation Stage (IS) SRS Stage (SS) Development Stage (DS) Testing & Training Stage (TTS) Feedback & Review Stage (FRS)
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
Expert Reference Series of White Papers. Importance of Schedule and Cost Control
Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project
Project Cost Management
Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present
Project Management Certificate (IT Professionals)
Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.
Colorado Department of Health Care Policy and Financing
Colorado Department of Health Care Policy and Financing Solicitation #: HCPFRFPCW14BIDM Business Intelligence and Data Management Services (BIDM) Appendix B BIDM Project Phases Tables The guidelines for
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
Atern The latest version of the DSDM approach which makes DSDM appropriate to all types of project.
THE AGILE PROJECT LEADER S DICTIONARY This dictionary attempts to de-mystify the jargon around the world of Agile projects. Part 1 translates common Agile terms into more traditional words. Part 2 translates
Introduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
Project Knowledge Areas
From Houston S: The Project Manager s Guide to Health Information Technology Implementation. Chicago: HIMSS; 2011; pp 27 39. This book is available on the HIMSS online bookstore at www. himss.org/store.
ASAP- Accelerated SAP
ASAP- Accelerated SAP Vanessa Hong What is ASAP? What is ASAP Methodology? ASAP, accelerated SAP implement, means to go through the SAP implementation process efficiently. Accelerated SAP Methodology is
Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010
Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning
COINS EVA Earned Value Analysis
COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project
PHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
Project Cost Management
Project Cost Management Martin Pazderka [email protected] INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda
Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam
Expert Reference Series of White Papers Tips and Techniques to Pass the PMP Exam 1-800-COURSES www.globalknowledge.com Tips and Techniques to Pass the PMP Exam Dan Stober, PMP Introduction Passing the
PMP Examination Tasks Puzzle game
PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM 2015 Business Plan Chapter 3, Water Facilities Focus Area, Goal Number 4 June 2011 CAPITAL IMPROVEMENT PROGRAM
Fundamentals of Measurements
Objective Software Project Measurements Slide 1 Fundamentals of Measurements Educational Objective: To review the fundamentals of software measurement, to illustrate that measurement plays a central role
Earned Value and Agile Reporting
Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,
plans based on actual cost, schedule and technical progress of work [1, 9].
An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan
Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition
Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management
Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1
Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
Input, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) [email protected] 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
Certification Preparation Course LATVIKON (R.E.P.)Centre
PMP Certification Preparation Course LATVIKON (R.E.P.)Centre ABOUT THIS COURSE Your ability as a project manager to demonstrate best practices in Project Management both on the job and through professional
Module 1 Diploma of Project Management
Module 1 Diploma of Project Management Project Management Fundamentals in association with This two day course takes participants through all aspects of Project Management and provides in depth examination
PHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
PROJECT SCHEDULING AND TRACKING
PROJECT SCHEDULING AND TRACKING PROJECT SCHEDULING AND TRACKING Software project scheduling is an activity that distributes estimated effort across the planned project duration by allocating the effort
Cost Management. How Much Will This Project Cost?
Cost Management How Much Will This Project Cost? Moderator Janelle Abaoag Project Insight Marketing, Public Relations [email protected] www.projectinsight.net All participants will be on
Module 5 Cost Management PMP Exam Questions
Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional
Leveraging CMMI framework for Engineering Services
Leveraging CMMI framework for Engineering Services Regu Ayyaswamy, Mala Murugappan Tata Consultancy Services Ltd. Introduction In response to Global market demand, several OEMs adopt Global Engineering
How to Write a Software Process Procedures and Policy Manual for YOUR COMPANY
How to Write a Software Process for YOUR COMPANY 1. Introduction MicroTools is proposing to assist YOUR COMPANY in improving the existing software process. The purpose of this project is to both improve
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
IT Project Management Methodology. Project Execution Support Guide. Version 0.3
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Execution Support Guide Version 0.3 Table of Contents 1 INTRODUCTION... 4 1.1 When should Project Execution
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
PROJECT TRACKING and CONTROL
PROJECT TRACKING and CONTROL 1 Outline of Project Tracking & Control 2 Project Planning & Control Context 3 Realistic and Measurable Plans Create Measurable Plans! 4 Data Sources for Project Tracking 5
What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate
The outcome of any venture is most often affected by the ready availability of useful information on which timely decisions can be taken. For project success, the need is therefore to know where you re
The 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
PMBOK 5 th Edition Crash Course
PMP Certification Exam Preparation PMBOK 5 th Edition Crash Course with Bill Doescher, PMP, MBA, CSM Pi Principal i lconsultant tand Product tdevelopment tdirector Bill Doescher, PMP Product Development
Project Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
Your Software Quality is Our Business. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc.
INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc. February 2013 1 Executive Summary Adnet is pleased to provide this white paper, describing our approach to performing
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Improve Project Team Collaboration Using Microsoft Project Online
Improve Project Team Collaboration Using Microsoft Project Online Presented by Steven Vowles, PMP, CISA, MCTS Senior Program Director, Infor Consulting Services Global PMO April 29, 2016 1 Discipline!
SCOPE OF WORK. The scope of work of Implementation Partner (IP) shall include the following:
SCOPE OF WORK 1. Brief Scope of work The scope of work of Implementation Partner (IP) shall include the following: Supply and installation of ERP licenses including ATS ERP system implementation, Project
Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions
Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions Today s Business Challenges Adopt leading CRM practices and stream line processes Take advantage
P6 Analytics Reference Manual
P6 Analytics Reference Manual Release 3.2 October 2013 Contents Getting Started... 7 About P6 Analytics... 7 Prerequisites to Use Analytics... 8 About Analyses... 9 About... 9 About Dashboards... 10 Logging
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling
Cisco Unified Communications and Collaboration technology is changing the way we go about the business of the University.
Data Sheet Cisco Optimization s Optimize Your Solution using Cisco Expertise and Leading Practices Optimizing Your Business Architecture Today, enabling business innovation and agility is about being able
PROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam
44-76 mix 2 Number: MB5-705 Passing Score: 800 Time Limit: 120 min File Version: 22.5 http://www.gratisexam.com/ Exam Code:MB5-705 Exam Name: Managing Microsoft Dynamics Implementations Exam Exam A QUESTION
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
Assessment of NCTD Program Management Framework for Positive Train Control Program
Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation
Earned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP
QUALITY AND PERFORMANCE IN PROJECTS Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s
iapps Consulting DWC LLC Fixed Scope Offering (FSO) For Taleo Recruit and On-Boarding Drive Transformation Create Value
iapps Consulting DWC LLC Fixed Scope Offering (FSO) For Taleo Recruit and On-Boarding Drive Transformation Create Value 18-05-2015 1 About Us We are a technology and business consulting firm, focused on
A Report On project management Techniques for academia
A Report On project management Techniques for academia Great Teachers are Great Project Managers Held on 7th -8th march, 2015, Saturday- Sunday At Gujarat Technological University Nr. Vishwakarma Government
Planning an ERP Implementation Project @ Small and Medium Enterprises
Planning an ERP Implementation Project @ Small and Medium Enterprises 27 th Regional WIRC Conference 31 August 2012 Table of Contents What is an SME and ERP Why an ERP for the SME segment Assessing the
Certification Exam Objectives: PK0-003
Certification Exam Objectives: PK0-003 INTRODUCTION The CompTIA Project + examination is designed for business professionals involved with projects. This exam will certify that the successful candidate
Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP
PMP Formulae & Tips Cheat Sheet P a g e Integration Management Develop Project Charter process Project Selection Methods (>> Benefit Measurement Methods >> Economic Models -7) Present Value (PV) FV The
How To Implement Fusion Hcm
Fixed Scope Offering Fusion HCM Implementation Mindtree limited 2015 Agenda Business Objectives Product Overview Key Implementation Features Implementation Packages & Timelines High Level Scope Implementation
Project Management Professional (Certified by PMI)
Project Management Professional (Certified by PMI) PMI certified Project Management Professional credential is the most important industryrecognized certification for project managers. This recognition
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
Project Management: Tracking Progress and Earned Value with MS Project 2003
Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain
PROPOSAL XXX INFRASTRUCTURE MIGRATION PROJECT (RFP 20XX.XX.XX)
PROPOSAL XXX INFRASTRUCTURE MIGRATION PROJECT (RFP 20XX.XX.XX) PREPARED FOR: CLIENT Address City, Province / State, Index Contact: Name, Title PREPARED BY: VIMEX TECHNOLOGIES 604-126 West 3 rd Street North
Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:
Project Audit & Review Checklist The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Relevance (at this time) Theory & Practice (How relevant is this attribute
Fixed Scope Offering for Implementation of Taleo
Fixed Scope Offering for Implementation of Taleo Mindtree limited 2015 All third party identities used within this presentation are copyrighted properties of the respective companies. Viewers and users
Unit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
Project Management. Training Courses
Project Management Certification and Training Courses Table of Contents Page On Site Training 4 Custom Course Development and Training 5 Project Management Training and Certification Courses Project Management
EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS
14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya
ERP Project Management An Activity Based Approach
ERP Project Management An Activity Based Approach INTRODUCTION A concern for many ERP (Enterprise Resource Planning) project managers is how to control the risk of the ERP project. How the project manager
PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP
PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP PROJECTS PROGRESS WELL UNTIL 70% Quick progress until 60-70% complete. Then we discover the project is in distress.
Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015
Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2
The new ASAP Methodology
The new ASAP Methodology Overview of the new ASAP Methodology for Implementation 7.x and ASAP Business Add-Ons Jan Musil Director, Global Project Management Office SAP Field Services Raimar Hoeliner Program
L10: Budgeting and Cost Control. Olivier de Weck
ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen
Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB
Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
Crosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the