Simple Earned Value (Using MS Project 2010)
|
|
|
- Opal Wilkinson
- 10 years ago
- Views:
Transcription
1 Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained using % Complete. Earned Value is typically done based on dollar amounts but can also be done using manhours or quantities. Earned Value provides a third dimension to cost reporting. Most financial project reporting provides Budget vs Actual costs. Some systems time phase the Budget (Planned Value) to provide Budget vs Actual costs at a point in time. Earned Value provides a third element so that a determination of schedule performance can be made (compare Planned with Earned) and a determination of cost performance can be made (compare Actual with Earned). Earned Value also provides the ability to validate the Estimate at Completion (forecast cost) so a comparison against Budget at Completion can be predicted. To undertake Earned value measurement you require: A time phased Budget (which is maintained) at the project level or Work Package level Recording of Actual costs against the project level or Work Package level Recording of Earned Value against the same work packages and in the same reporting period as the Actual cost are collected A way of measuring Earned value against a work package (Earned Value Technique, in this case mainly 0/100%) Note for the purposes of this document, a work package is considered as a discrete WBS scope piece: Team Team Team Schedule status PM or schedule support Actual costs from timesheets Estimated Actuals (accruals etc) Calculated EV/BCWP based on milestones Updated Financial model PM or cost support AC/ACWP via Cost model Should include an ETC and EAC EV calc spreadsheet PM or cost support Corrective action plans EV progress report PMs Steering Committee Level 8, 140 Bourke St t (03) Melbourne, Vic 3000 f (03) ABN Version 3 Page 1 of 7
2 The diagram above shows information flow in a typical EVM System using MS Project, note the need for a EV calculation spreadsheet. Note, in MS Project % Complete is % of Duration complete, this should never be forgotten and users should not try to disconnect the two fields. Percent Complete is calculated by the tool, not user entered. There are also other percent complete fields including a Physical Percent Complete which could provide an option to those wanting a more complex Earned Value solution where users enter the percent complete. Step 1 - Establish the Performance Measurement Baseline (Planned Value curve) Estimating Detailed estimates will need to be created for each WBS element, these are typically built and refined progressively over a number of weeks in conjunction with scheduling. Estimates, by their very nature, include both labour and fixed costs plus allowances for risk and uncertainty. For more information on Estimating, refer the CCG Estimating and Cost Management standard and associated templates. Scheduling Detailed schedules will be created for each WBS element, these are typically built and refined progressively over a number of weeks. The detailed schedules will need to be mapped to the Work packages via coding fields. As per normal practice, dependencies and durations will need to be reviewed to ensure date consistency. The schedule will be statused up to an agreed Status date and Baselined from a date perspective once the schedule is agreed/signed off. Determining the dollar spread Dollar spreading inside MS Project is often the most difficult and time consuming component. You need a basis for spreading dollars. Rarely will MS Project tasks align with budgets. Hopefully you will have manhours for major elements. One technique we have used involves spreading based on a weighted system of manhours for the detailed tasks, this works quite well. The heart of the simple Earned Value technique is using a Lump sum dollar only allocation to milestones. There should ideally be a milestone per reporting period. Hrs $$ $$ Allocating dollars to Tasks and Milestones If using a Milestone based Simple Earned Value approach, the only time you will need to allocate dollars to tasks will be for level of effort tasks such as Project Management. Note the technique will multiply the duration based percent complete by the Baseline cost. To assign dollars directly to tasks or Milestones: 1. Set up a new resource, eg Vendor 2. Double click resource, change Type to Cost. 3. Assign to task then change cost amount via the Assign Resources form Page 2 of 7
3 Hint: Add the Costs column to the table section of the Gantt Chart to see the costs accrue. Never use the column Fixed Costs, they do not form part of the time phased costing extracted via Resource Usage views. Do not allocate costs to Summaries. Extracting Planned Value (Time phased budget) The Simple Earned Value technique ignores complexity associated with Early vs Late forecasts. A Schedule could follow the Late curve and still be considered on schedule. Time phased budgets are calculated in MS Project using the Early dates. If users want to set on Late dates, they should temporarily set all As Soon as Possible tasks to As Late As Possible or manually manipulate schedule before extracting Planned value figures. Early Start $ A B Late Finish Time To extract the Time phased budget (from the Baseline file): 1. From the Project tab, select Visual Reports 2. Select time period, typically Months 3. Select New Template 4. Select Excel and Resource Usage 5. Use Field Picker to Remove All, then add only Cost 6. Click OK then OK 7. In Excel click on right hand side Cost and Monthly Calendar, on the left hand side expand the time period to show the monthly data as per the example below 8. Then Copy/Paste it into your control spreadsheet and include formulas for cumulative values, graphs etc. To extract the Time phased budget via the Resource Usage view: 1. Change view to Resource Usage 2. Add Cost column to table if not already there 3. Adjust Timescale to monthly 4. Format, Details to show Cost only 5. Group and/or roll up assignments as need be 6. Copy and Paste data to Excel. Note you will need to manually enter the timescale and separately copy the left and right hand sides of the vertical screen divider. 7. Tidy up as need be in Excel separating incremental and cumulative data, prepare graphs etc. Page 3 of 7
4 Warning - Do not use the BCWS field in MS Project, due to inconsistencies with the way it deals with Status date it cannot be trusted. Baseline control Baseline change will need to be carefully managed in the schedule: Copy/Paste of tasks and milestones cannot be used once Baseline is set Deleting Baseline activities with costs assigned will affect EV calculations. It is better to allocate a new Resource called Baseline change, allocate a negative value equivalent to the original value then set any task/milestone with costs assigned but no longer needed to be 100% complete as of the date of Baseline change along with text NOT NEEDED. It would be OK to delete any task/milestone no longer required which does not have costs assigned. Resetting the Baseline on existing activities is not recommended unless a major replan has been done. New tasks/milestones can be added, if costs are involved then allocate via a Resource called Baseline change. Set the Baseline on the new tasks/milestones by exception but be careful it is consistent with the rest of the Baseline. A manual reconciliation check will need to be put in place to verify/validate Baseline costs in the schedules before extracting EV data. A simple way may be to verify the total Baseline cost at the project summary level against the Excel spreadsheet BAC. Step 2 Set up MS Project calculated field Due to inconsistencies within MS Project in the calculation of Earned Value (BCWP) relating to the Status date, a trusted method for EV calculation is to customise a field using a formula (with a Gantt Chart or similar view active): 1. From the Format tab, select Custom Fields 2. Select Cost1 and renaming it Calc EV 3. Click Formula and enter [Baseline Cost]*[% Complete]/ Click OK then for Calculation for task and group summary rows click Rollup then select Sum 5. Click OK 6. Add the Calc EV field to the Gantt table as well as % Complete and verify field is working through a couple of simple tests. Page 4 of 7
5 Warning - Do not use the BCWP field in MS Project, due to inconsistencies with the way it deals with Status date it cannot be trusted. Step 3 Status update Status date A key to the reporting will be the Status date, considered 5pm. At this point all Tasks/Milestones to the left of the Status date will need to be set as complete, otherwise they need to be rescheduled to the right of the Status date. In progress tasks will need to show actual work/duration up to the Status date and remaining work/duration after the Status date. It is recommended that end of month Status dates are used as this typically coincides with finance cut off. It is easier to move the schedule status date than change finance cut off timing. Actual Costs Actual costs should be easy enough to get from the accounting system, usually available within 3-4 days after the end of month. Actual costs may be at the project level or a more detailed Work package level depending on the accounting system and cost codes. Include Accruals (or Estimated Actuals) as necessary for invoices not received, Timesheet not entered etc. Enter Actual costs into your tracking spreadsheet, typically incremental. A cumulative figure can then be derived using a simple formula. Extracting Earned Value Assuming the Baseline was set and maintained, extracting EV from MS Project is a simple process of reading off the Calc EV value against the Project summary (or work package if doing this at a lower level) and entering in the tracking spreadsheet as a cumulative figure. An incremental figure can then be derived using a simple formula. Step 4 Reporting Since Excel is used, numerous options are available for reporting, at a project level or at Work Package level if the data is available, including: Derivation of variance values (Schedule Variance, Cost Variance, Variance at Completion) Derivation if indices (Schedule Performance Index, Cost Performance Index) Derivation of an Independent Estimate at Complete Graphical analysis including determination of Schedule Variance from a time perspective Graphical analysis of indices trends Schedule Variance (time) Page 5 of 7
6 Useful EV formulas include: SV = EV-PV Schedule Variance (-ve bad) CV = EV-AC Cost variance (-ve bad) SPI = EV/PV Schedule Performance Index (<1.0 bad) CPI = EV/AC Cost Performance Index (<1.0 bad) IEAC = AC + (BAC EV) /CPI or IEAC = AC + (BAC EV) /(0.8xCPI + 0.2xSPI) Complexities More complex EV measurement techniques More complex methods of EV measurement could be catered to such as other Earned Value Techniques using additional custom fields, IF statements and possibly the Physical Percent Complete field. This may include asking for a subjective measure of % Complete during Status collection then applying it to discrete elements, something that takes a lot more effort. Implementing such a system is beyond the scope of these notes. Contingency/Management Reserve Core Consulting Group has adopted the following definitions: Project Contingency An amount of Budget set aside for managing undefined Risks and addressing unknowns, controlled by the Project Manager and authorised by the project Governance authority. Project Contingency is included in the Performance Measurement Baseline, is usually considered Undistributed budget and controlled through formal Baseline change. Management Reserve An amount of Budget set aside by the sponsor for managing scope change and risks beyond the control of the project. It is typically controlled by the sponsor or higher level governance authorities and is not considered part of the Performance Measurement Baseline. Contingency/Management Reserve is one of the more complex areas of Cost Management. Typically Contingency forms part of the Baseline for EVM, in other words it is planned to be used. Contingency is also used for unexpected additional in scope work, eg rework. It should not be used to mask over spend. Accountability Funding Business Cost Performance Measurement Baseline (BAC) Management Reserve Sponsor WBS Control Account Undistributed Budget Contingency Project Manager Discrete Work Packages Level of Effort Tasks Planning Packages Page 6 of 7
7 In EVM Budget and scope are tied together, you cannot change one without changing the other. Contingency should not to be confused with Undistributed budget (budget not yet assigned to Work Packages) or Risk budgets (for managing defined risks). There are often rules around when and how Contingency can be used, usually it is up to the Steering Committee and/or Sponsor (advised by the Project manager) to authorise. Some projects also have formal Risk budgets set up as a result of risk planning, they are considered Undistributed budgets and are included in the Baseline. Risk budgets are typically used for risk response plans (reducing likelihood, reducing impact) and sometimes to fund the impact of a risk. Contingency is best kept as a separate control account with Baseline change used to move budget across to active control accounts. It can be included and/or excluded from reports as necessary. In MS Project, unused Contingency would be via allocated a separate Resource named Contingency which is allocated to tasks such as Contingency allowance or Rework allowance, scheduled only in the future (always 0%). Allocated Contingency would be done by using the same resource Contingency but allocated where it is required, including completed activities. The allocated Contingency and the unused Contingency should add up and reconcile to the total Contingency budget. Page 7 of 7
CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT
CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT PREPARED BY James E Aksel, PMP [email protected] http://www.msprojectdblog.com http://www.projectpmo.com Page 1 of 19 Table
Planning and Scheduling Your Project Using Microsoft Project 2003
Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering [email protected] Meeting Protocol Agenda Project File Project Calendar Creating
Earned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
Project Management: Tracking Progress and Earned Value with MS Project 2003
Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain
INSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
MSP How to guide session 2 (Resources & Cost)
MSP How to guide session 2 (Resources & Cost) 1. Introduction Before considering resourcing the schedule it is important to ask yourself one key question as it will require effort from the scheduler or
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
Applied Project Management ( APM )
Applied Project Management Applied Project Management ( APM ) TRAINING PROGRAM Page 1 Of 7 APPLIED PROJECT MANAGEMENT PRO PROGRAM OVERVIEW This course provides in-depth Project Management Training and
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Introduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
How To Manage A Project
Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management
Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1
Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.
This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts. To begin, how does the Prime integrate the subcontractor
Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Rules on using templates 1) Must reference the template used 2) Use
AACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
Using Earned Value Management for Improving Processes. By Cynthia K. West
Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.
Earned Value Analysis Exercise
Earned Value Analysis Exercise www.spmbook.com Author: Adolfo Villafiorita Revision: 2 (205-02-06) Given the following project plan: ID Task Immediate Predecessor (*) Expected Duration (days) Budget ($)
IST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
An introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
Project Control with ProTrack
Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS
Estimating Cost at Completion - Judgment & EV Information
Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number
Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB
Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin
Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015
Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2
Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01
PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.
Predicting progress on your project
www.nonsuch.co [email protected] Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant
What is Costrac? Approval of Budget against WBS. Feasibility Study Completed. Define & Map WBS. Approval of WBS. Estimate
The outcome of any venture is most often affected by the ready availability of useful information on which timely decisions can be taken. For project success, the need is therefore to know where you re
Appendix D Glossary Of Terms
Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used
Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes
Lecture Slides for Managing and Leading Software Projects Chapter 8: Measuring and Controlling Work Processes developed by Richard E. (Dick) Fairley, Ph.D. to accompany the tet Managing and Leading Software
EVM.01. Earned Value Analysis Why it Doesn't Work
EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects
300 Scheduling and Budgeting
Jefferson Science Associates, LLC 300 Scheduling and Budgeting Project Control System Manual Revision 7-16 - 300 Scheduling and Budgeting This chapter of the JSA Project Control System Manual describes
CLARITY PPM TIPS, TRICKS, and TERMINOLOGY
CLARITY PPM TIPS, TRICKS, and TERMINOLOGY Clarity PPM Knowledge Sharing Series Helping the Clarity PPM Community Members Benefit from Best Practice TABLE OF CONTENTS 1 OVERVIEW... 3 2 OVERVIEW PAGE...
A Gentle Introduction to Earned Value Management Systems
A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
Brainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
Microsoft Project 2010
Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window
Creating a New Project
Creating a New Project Microsoft Project is a project management software program designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets,
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
Project Cost Management
Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present
FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight
SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office
Earned Value User s Guide
ENTC 419 Project Management Earned Value User s Guide Jacob Terkelsen Project Manager Digerati Group Table of Contents TABLE OF CONTENTS... 2 INTRODUCTION... 3 REQUIREMENTS... 3 LAYOUT... 4 IMPLEMENTATION...
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 [email protected]
Earned Value and Agile Reporting
Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,
Assessing Schedule Performance with Earned Value
FEATURED PAPER OCTOBER 2007 Time Is Up: Assessing Schedule Performance with Earned Value By Robert Van De Velde Time drives projects. Quick and accurate evaluation of schedule performance is crucial. Quantitative
PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION
PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and
Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166
Towards a Complete Earned Value Analysis Sam Sharp and Peter Hall Paper # 166 Planned vs Actual A purely accounting approach to project tracking involves the monitoring of status by simply comparing actual
Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. [email protected]
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of
Chapter 7: Project Cost Management. Munawar [email protected]
Chapter 7: Project Cost Management Munawar [email protected] Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.
CVR/IT Consulting LLC
2011 CVR/IT Consulting LLC All Rights Reserved 1 www.cvr-it.com [email protected] Overview Easy Earned Value CVR/IT Consulting LLC 2011 CVR/IT Consulting LLC All Rights Reserved 2 Introduction Earned Value
10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.
PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition
Brillig Systems Making Projects Successful
Metrics for Successful Automation Project Management Most automation engineers spend their days controlling manufacturing processes, but spend little or no time controlling their project schedule and budget.
Project Cost Management
Project Cost Management Martin Pazderka [email protected] INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda
Project Execution - PM Elements
Performance Initial Release 1. Introduction to Project Tracking and Reviewing Once a project has advanced to the phase of performance, the consistent and constant flow of information on the true status
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
Project Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
Agile and Earned Value. A white paper. October 2013. Author Stephen Jones, Sellafield Ltd
Agile and Earned Value A white paper October 2013 Author Stephen Jones, Sellafield Ltd This document is a whitepaper produced by the APM Planning, Monitoring and Control SIG. It represents the thoughts
Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.
Project Management ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann Riko Wichmann, MPY Zeus Student Seminar - PM, 14.11.2003 1 Project Management - Training Program - Project Scope Management
Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
NE-50413B Mastering Microsoft Project 2010
NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need
PMO Metrics Recommendations
Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project
Mastering Microsoft Project 2010
Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project
Tracking Budgets and Schedules
Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft
Unit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
Project Management Quick Reference Guide for MS Project 2010
Project Management Quick Reference Guide for MS Project 2010 Project 2010 offers flexibility and choice by providing tailored work management solutions for individuals, teams, and the enterprise. Besides
Beginning Microsoft Project
Beginning Microsoft Project BEGINNING MICROSOFT PROJECT...1 WHAT IS PROJECT? WHAT IS IT USED FOR?...1 PROJECT WINDOWS... 1 Views and Tables...1 PHASE 1: PLANNING AND SETTING UP PROJECT...2 PLANNING AND
technical tips and tricks
technical tips and tricks Looking for schedule variances Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
CDC UNIFIED PROCESS JOB AID
Purpose The purpose of this document is to provide guidance on the practice of using Microsoft Project and to describe the practice overview, requirements, best practices, activities, and key terms related
Contract Cash Flow & Performance Analysis. PERCEPTION Helping The Shipyard Stay On Budget
Contract Cash Flow & Performance Analysis PERCEPTION Helping The Shipyard Stay On Budget 1 Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge
Earned Value Management Tutorial Module 8: Reporting. Prepared by:
Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.
1 Start a new project
Project Management Quick Reference Guide for Microsoft Project 2010 Before beginning a new project, an organization must determine whether the project fits its strategic goals. Executives should classify
Expert Reference Series of White Papers. Importance of Schedule and Cost Control
Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project
Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.
Planning and Managing Software Projects 2011-12 Class 10 Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Microsoft Project 2013 Guide to Task and Resource Planning
Starting a Project The Microsoft Project 2013 Start screen Double click Blank Project, select a Recent project, or click Open Other Projects to work on a saved project stored on disk or on SkyDrive. To
PERCEPTION. Tracking Progress & EAC
PERCEPTION Tracking Progress & EAC 1 Maximize Efficiency Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge their competition. They can focus
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant
BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s
Chapter 3: Project Cost Management
Chapter 3: Project Cost Management Learning Objectives o Understand the importance of project cost management. o Explain basic project cost management principles, concepts, and terms. o Discuss different
MTAT.03.244 Software Economics. Lecture 6: Software Cost Estimation (part II)
MTAT.03.244 Software Economics Lecture 6: Software Cost Estimation (part II) Marlon Dumas marlon.dumas ät ut. ee Outline Review of Effort Estimation Homework Discussion on book chapter by Caper Jones Earned
Metrics for Agile Projects:
Metrics for Agile Projects: Finding the right tools for the job Agile project managers have a wide range of metrics to choose from when it comes to tracking the progress of Agile projects. By understanding
Monthly Payroll to Finance Reconciliation Report: Access and Instructions
Monthly Payroll to Finance Reconciliation Report: Access and Instructions VCU Reporting Center... 2 Log in... 2 Open Folder... 3 Other Useful Information: Copying Sheets... 5 Creating Subtotals... 5 Outlining
Since 1985, the Test Program Set (TPS) development
Applying Management Reserve to Software Project Management Walter H. Lipke Oklahoma City Air Logistics Center, Directorate of Aircraft Maintenance, Software Division Today s standard of practice for managing
ELECTRO-MECHANICAL PROJECT MANAGEMENT
CHAPTER-9 ELECTRO-MECHANICAL PROJECT MANAGEMENT Y K Sharma,SDE(BS-E), 9412739241(M) E-Mail ID: [email protected] Page: 1 Electro-mechanical Project Management using MS Project Introduction: When
DCMA DCMA-EA PAM 200.1. October 2012
DCMA Earned Value Management System (EVMS) Program Analysis Pamphlet (PAP) DCMA-EA PAM 200.1 October 2012 THE DCMA ENGINEERING AND ANALYSIS EXECUTIVE DIRECTOR IS RESPONSIBLE FOR ISSUANCE AND MAINTENANCE
OVERVIEW. Microsoft Project terms and definitions
PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training
Tracking Software Development Progress with Earned Value and Use Case Point
ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with
PMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620
DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT-81861 Approval Date: 20120620 AMSC Number: D7549 Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing
Basic Concepts of Earned Value Management (EVM)
Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data
Accounting System. Page 1 of 9
Page 1 of 9 Accounting System In support of program management and Earned Value Management, the accounting system must be able to relate costs incurred to work accomplished. Not all accounting systems
SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT
1 PMSC Quarterly Meeting, February 1 2, 2011, Fort Worth, Texas SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT Increasing the Probability Program of Success (PoPS)by Connect the dots between
L10: Budgeting and Cost Control. Olivier de Weck
ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen
CA Clarity Project & Portfolio Manager
CA Clarity Project & Portfolio Manager Project Management User Guide v12.1.0 This documentation and any related computer software help programs (hereinafter referred to as the "Documentation") are for
Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by
Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones
Earned Value Management System Description
LCLS Project Management Document # 1.1-015 Project Management Revision 3.0 Earned Value Management System Description Patricia Mast (LCLS Project Controls Manager) Signature Date Mark Reichanadter (LCLS
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,
plans based on actual cost, schedule and technical progress of work [1, 9].
An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
The To Complete Performance Index
The To Complete Performance Index transforming project performance Walt Lipke 1.1 PMI - Oklahoma City Chapter 1.0 +1 405 364 1594 [email protected] www.earnedschedule.com Index 1.3 1.2 TCPI vs CPI TCPI
