The Netherlands Licensing procedure offshore windfarms. Sander de Jong Rijkswaterstaat Noordzee
|
|
- Emil Crawford
- 8 years ago
- Views:
Transcription
1 The Netherlands Licensing procedure offshore windfarms Sander de Jong Noordzee Stralsund, Wednesday
2 Offshore windfarms in NL - Today s Situation Round 1 2 windfarms operational (220 MW) offshore near Egmond (IJmuiden) 2 Licensing procedure Offshore Wind Stralsund,
3 3 Licensing procedure Offshore Wind Stralsund,
4 4 Licensing procedure Offshore Wind Stralsund,
5 Offshore windfarms in NL - Today s Situation Round 1 2 windfarms operational (220 MW) offshore near Egmond (IJmuiden) Round 2 12 permits for the building of new windfarms available Financial support for just 3 of those windfarms (app. 720 MW) Low expectancy for remaining 9 permits 5 Licensing procedure Offshore Wind Stralsund,
6 6 Licensing procedure Offshore Wind Stralsund,
7 BARD/TYPHOON BUITENGAATS 300 MW AND THE WINNERS ARE BARD/TYPHOON ZEE-ENERGIE 300 MW ENECO Q MW 7 Licensing procedure Offshore Wind Stralsund,
8 Offshore windfarms in NL - Today s Situation Round 1 2 windfarms operational (220 MW) offshore near Egmond (IJmuiden) Round 2 12 permits for the building of new windfarms available Financial support for just 3 of those windfarms (app. 750 MW) Low expectancy for remaining 9 permits Round 3 Large areas designated for offshore windfarms No additional funding / subsidiary New Energy Policy Plan expected 2014/2015 Offshore Wind? 8 Licensing procedure Offshore Wind Stralsund,
9 AREAS DESIGNATED FOR WIND BUT NO FUNDING ASSIGNED IJMUIDEN-VER BORSELE 9 Licensing procedure Offshore Wind Stralsund,
10 12 PERMITS FOR OFFSHORE WIND KEY ISSUES IN PERMITS: SHIPPING AND HELICOPTERS 10 Licensing procedure Offshore Wind Stralsund,
11 Shipping safety / efficiency 11 Wind op Zee
12 Helicopter-approach availability of the platform 12 Wind op Zee
13 12 PERMITS FOR OFFSHORE WIND KEY ISSUES IN PERMITS: ECOLOGICAL IMPACTS 13 Licensing procedure Offshore Wind Stralsund,
14 Ecological impacts Application needs Environmental Impact Assesment 14 Licensing procedure Offshore Wind Stralsund,
15 Ecological impacts Application needs Environmental Impact Assesment All individual EIA-reports indicate no significant effects 15 Licensing procedure Offshore Wind Stralsund,
16 Ecological impacts Application needs Environmental Impact Assesment All individual EIA-reports indicate no significant effects Cumulative effects (all 12 permits together) unclear 16 Licensing procedure Offshore Wind Stralsund,
17 Ecological impacts Application needs Environmental Impact Assesment All individual EIA-reports indicate no significant effects Cumulative effects (all 12 permits together) unclear An appropriate assessment (EC directive) is needed 17 Licensing procedure Offshore Wind Stralsund,
18 Ecological Headliners Underwaternoise by pile driving harbour porpoises and seals disturbed Fish-larvaea provide food for birds Waddensea = habitat (NPA) 18
19 3 PERMITS DENIED too much effects on feeding birds too close to habitat Waddensea (NPA) 19 Licensing procedure Offshore Wind Stralsund,
20 Ecological impacts -> permit measures No pile driving during the fish-larvaea season No pile driving while seals (and their cubs) are migrating No pile driving allowed: 1 january 1 july No pile driving allowed in areas that interfere 20 Licensing procedure Offshore Wind Stralsund,
21 AREA WADDEN NOORD NATIONAL INTERFERENCE = RATHER SIMPLE AREA IJMUIDEN-VER AREA HOLLANDSE KUST 21 Licensing procedure Offshore Wind Stralsund,
22 GERMAN SEALS AND HARBOUR PORPOISES 160 db(a) INTERNATIONAL INTERFERENCE = IMPOSSIBLE?! UK INSTALLING > 30 GIGAWATT!! BELGIANS EIA is BANDWIDTH 2-7 MW TURBINES INSTALLING TECHNIQUE? 22 Licensing procedure Offshore Wind Stralsund,
23 FINDING and EXCHANGING INFORMATION IS ESSENTIAL FOR FUTURE WINDFARMS 23 Licensing procedure Offshore Wind Stralsund,
24 Goals of Shortlist and Masterplan Fish-larvaea labtests in permit: 100% mortality within 1000 m shortlist: sole (solea solea) shows lower mortality (14% 400 m) Sea mammals in permit: avoidance seals 80 km, harbour porpoise 12 km shortlist: avoidance seals 80 km, harbour porpoise 40 km Lesser seagull huge differences between populations Krammer and Texel model for impact-calculation is updated with flightspecs Underwater noise measurement needs standardization 24 Licensing procedure Offshore Wind Stralsund,
25 Let s work together for a sustainable future! 25 Wind op Zee
Underwater Noise and Licensing of Offshore Windfarms in the Netherlands. Sander de Jong Rijkswaterstaat Noordzee
Underwater Noise and Licensing of Offshore Windfarms in the Netherlands Sander de Jong Noordzee Amsterdam, Friday 10.02.2012 Offshore windfarms in NL - Today s Situation Round 1 2 windfarms operational
More informationEnvironmental aspects of offshore wind energy. Jakob Asjes Jakob Asjes IMARES, Institute for Marine Resources and Ecosystem Studies
Environmental aspects of offshore wind energy Jakob Asjes Jakob Asjes IMARES, Institute for Marine Resources and Ecosystem Studies Contents Part 1 8.45 9.30 hrs Overview Dutch/North Sea situation Dutch/European
More informationEffects of Underwater Noise
Effects of Underwater Noise Impact pile driving noise prediction Marten Nijhof, Christ de Jong, Bas Binnerts, Michael Ainslie 2 Wind energy agenda Dutch energy agreement for sustainable growth (2013):
More informationDutch wind energy strength
Dutch wind energy strength Chris Westra (senior consultant ECN) (general manager We@Sea) www.we-at-sea.org www.ecn.nl www.haveneilandopzee.nl 2010 The start in 1972 here we are now: 2010 Drivers for offshore
More informationPart B: Description and assessment of the cumulative effects of implementing the Roadmap for Offshore Wind Power
Framework for assessing ecological and cumulative effects of offshore wind farms Part B: Description and assessment of the cumulative effects of implementing the Roadmap for Offshore Wind Power Version
More informationTranslating ecological research results into wind farm practice The Danish experience. Niels-Erik Clausen. 2 Risø DTU
Translating ecological research results into wind farm practice The Danish experience Niels-Erik Clausen We@Sea Conference, Den Helder Holland 12-13 February 2009 Outline The Danish offshore monitoring
More informationWind Farm Zone. Offshore wind energy. in the Netherlands. Project & Site Description. # Borssele
# Borssele Offshore wind energy Wind Farm Zone in the Netherlands Project & Site Description The roadmap from 1,000 to 4,500 MW offshore wind capacity >> Sustainable. Agricultural. Innovative. International.
More informationDe Industrie. KIvI Niria Jaarcongres 2010. De uitdagingen voor windenergie op zee. Ballast Nedam Offshore. Dolf Elsevier van Griethuysen
KIvI Niria Jaarcongres 2010 De uitdagingen voor windenergie op zee De Industrie Ballast Nedam Offshore Dolf Elsevier van Griethuysen Arnhem, 6 oktober 2010 Offshore Windpark Egmond aan Zee (2006) HLV Svanen
More informationFramework for assessing ecological and cumulative effects of offshore wind farms. Part A: Methods. Version 1.1
Framework for assessing ecological and cumulative effects of offshore wind farms Part A: Methods Version 1.1 2 Framework for assessing ecological and cumulative effects Part A Contents Summary of FAECE
More informationExperience from the first large scale tidal turbine EIA in Europe. How do we work towards effective and proportionate EIA?
Independent, integrated thinking Experience from the first large scale tidal turbine EIA in Europe How do we work towards effective and proportionate EIA? Liz Foubister IEMA Webinar 30 th July 2014 What
More informationPrevention of the ecological effects of offshore windfarms in licensing and spatial planning - an overview
Prevention of the ecological effects of offshore windfarms in licensing and spatial planning - an Prevention of the ecological effects of offshore windfarms in licensing and spatial planning - an dr.
More informationEffects of offshore wind farms on birds
AARHUS VERSITY DEPARTMENT OF BIOSCIENCE 11. OCTOBER 2012 Effects of offshore wind farms on birds Ib Krag Petersen, Anthony D. Fox, Mark Desholm, Johnny Kahlert and Thomas K. Christensen Department of Bioscience
More informationA consultancy perspective: Building consensus on wildlife monitoring
June 30, 2015 A consultancy perspective: Building consensus on wildlife monitoring Gareth Lewis, Director Pro-Tide Work Package 2 Environmental Aspects, Final workshop (Isle of Wight 30 th June 2015).
More informationEnergy Valley and NNOW in Offshore Wind an example
Energy Valley and NNOW in Offshore Wind an example Rimini, 6 November 2013 Albert van der Hem, MSc. Programme Manager Offshore Wind Contents Energy Valley NNOW Offshore Wind Market Features Infrastructure
More informationINSTALLATION and LOGISTICS of OFFSHORE WIND FARMS
POWER Offshore Summer School 2006 INSTALLATION and LOGISTICS of OFFSHORE WIND FARMS Gerard van Bussel The Netherlands Offshore transport and installation vessels Semi Submersible Sheer leg crane Ship type
More informationHow Dutch innovations support 40% cost price reduction. June 13th 2013 How Dutch innovations support 40% cost price reduction 1
How Dutch innovations support 40% cost price reduction June 13th 2013 June 13th 2013 How Dutch innovations support 40% cost price reduction 1 Dutch Top Sector Policy Government policy to further strengthen
More informationPort facilities & offshore wind energy. ATO / We@Sea Conference Chris Westra
Port facilities & offshore wind energy ATO / We@Sea Conference Chris Westra Complexity of the construction of an offshore wind project Offshore wind installation Model description Wind Farms Harbour development
More informationEuropean Subsea Cable Report & Forecast 2015-2025
European Subsea Cable Report & Forecast 2015-2025 J/15/1226 May 2015 4C Offshore - OrbisEnergy Centre, Lowestoft, NR32 1XH T: +44 (0)1502 307 037 E: info@4coffshore.com Table of Contents 1. Executive Summary
More informationStrategy of the German Government on the use of off-shore wind energy
Strategy of the German Government on the use of off-shore wind energy in the context of its national sustainability strategy Ministries involved: Federal Ministry for the Environment, Nature Conservation
More informationA E O L I S F O R E C A S T I N G S E R V I C E S WIND FARM ENERGY ASSESSMENT - FEASIBILITY STUDY. Kees van Vliet
A E O L I S F O R E C A S T I N G S E R V I C E S WIND FARM ENERGY ASSESSMENT - FEASIBILITY STUDY Kees van Vliet September 2007 K o n i n g s l a a n 11 2 3 5 8 3 G V U t r e c h t T h e N e t h e r l
More informationSDE+ tender Borssele december 2015
SDE+ tender Borssele december 2015 Wind farm site decisions (incl. EIA and crossings) Soil, water, wind investigations wind farm sites National consenting procedure TenneT substation and export cables
More informationFish benefits from offshore wind farm development
Downloaded from orbit.dtu.dk on: Jul 02, 2016 Fish benefits from offshore wind farm development Leonhard, Simon B.; Stenberg, Claus; Støttrup, Josianne Gatt; Deurs, Mikael van; Christensen, Asbjørn; Pedersen,
More informationPPT Dutch offshore wind sector
PPT Dutch offshore wind sector Een presentatie over een presentatie > Agnes Agterberg RVO 2 december 2015 Inhoud Aanleiding PPT Dutch offshore wind sector Betrokken partijen In vogelvlucht door de PPT
More informationGetting smart(er) in Offshore Wind O&M
Getting smart(er) in Offshore Wind O&M 26-9-2014 Prof.dr. Gerard J.W. van Bussel Leerstoel Windenergie Faculteit Luchtvaart- en Ruimtevaarttechniek Delft University of Technology Challenge the future Inhoud
More informationUnderwater Noise Social Cost Benefit Analysis
Underwater Noise Social Cost Benefit Analysis Rijkswaterstaat June 2015 Final Report BD4543-101-100 A company of Royal HaskoningDHV HASKONINGDHV NEDERLAND B.V. SMC STRATEGY AND MANAGEMENT CONSULTANTS Laan
More informationBMP Guidelines. Environmental Impact Assessment (EIA) report for activities related to hydrocarbon exploration and exploitation offshore Greenland
BMP Guidelines for preparing an Environmental Impact Assessment (EIA) report for activities related to hydrocarbon exploration and exploitation offshore Greenland Danish National Environmental Research
More informationMonitoring and researching ecological effects of Dutch offshore wind farms Masterplan
Monitoring and researching ecological effects of Dutch offshore wind farms Masterplan A.R. Boon R. ter Hofstede C. Klok M. Leopold G. Blacquiere M.J.M. Poot R.A. Kastelein C.J. Camphuysen Deltares, 2010
More informationOffshore Wind Project Management
DEPARTMENT S, POST-GRADUATE AND MASTERPROGRAMMES ENGINEERING EN LIFE SCIENCES Experts by Experience! Offshore Wind Project Management BUILT ENVIRONMENT Offshore Wind Project Management (OWPM) Experts by
More informationDatabase of measurements on the offshore wind farm Egmond aan Zee
Database of measurements on the offshore wind farm Egmond aan Zee A.J. Brand J.W. Wagenaar P.J. Eecen M.C. Holtslag 1 1 TU Delft, Faculty Aerospace Engineering Presented at the the EWEA 2012 conference,
More informationFramework for assessing ecological and cumulative effects of offshore wind farms
Framework for assessing ecological and cumulative effects of offshore wind farms Cumulative effects of impulsive underwater sound on marine mammals Version 1.1 TNO report TNO 2015 R10335-A Cumulative
More informationMULTI-FUNCTIONAL USE OF OFFSHORE WIND FARMS, AN INVENTORY OF CHALLENGES AND OPPORTUNITIES
MULTI-FUNCTIONAL USE OF OFFSHORE WIND FARMS, AN INVENTORY OF CHALLENGES AND OPPORTUNITIES The WE@SEA research programme conducts multiple studies on future offshore wind energy application subdivided into
More informationWinddag 2015: Innovation need and necessity. Bob Meijer 20 juni 2015
Winddag 2015: Innovation need and necessity Bob Meijer 20 juni 2015 Objectives of the TKI Wind op Zee Economic benefits Cost reduction 174 Expedite the Energy Transition 40% 100 12 juni 2015 Winddag 2015:
More informationEcological Research on Offshore Wind Farms: International Exchange of Experiences
Catherine Zucco, Wolfgang Wende, Thomas Merck, Irene Köchling and Johann Köppel (eds.) Ecological Research on Offshore Wind Farms: International Exchange of Experiences PART A: Assessment of Ecological
More informationHelicopter Flight Operations to Offshore Windfarms
Helicopter Flight Operations to Offshore Windfarms Offshore/Onshore Aviation Conference 2 nd 3 rd September 2013, Kuala Lumpur Steffen Bechtel windpark heliflight consulting GmbH Am Kiel-Kanal 1 24106
More informationOffshore Pile Testing Campaign Wikinger
Offshore Pile Testing Campaign Wikinger Pile driving analysis, static and dynamic load tests in 40m water depth Jan Fischer, Fichtner Water & Wind GmbH, Hamburg, Germany Rob van Dorp, Allnamics BV, Den
More informationKey Environmental Issues a Follow-up
danish offshore wind Key Environmental Issues a Follow-up danish energy agency danish nature agency dong energy vattenfall danish offshore wind Key Environmental Issues a Follow-up danish energy agency
More informationDatabases. by David Cerda Salzmann
Databases by David Cerda Salzmann In the previous lecture... What data you need What you use it for This hour: where to get data from Introduction OWT Design Procedure Fatigue Loads Extreme Loads Site-specific
More informationPower output of offshore wind farms in relation to atmospheric stability Laurens Alblas BSc
Power output of offshore wind farms in relation to atmospheric stability Laurens Alblas BSc Photo: Vestas Wind Systems A/S 1 1. Introduction Background Atmospheric stability is known to influence wind
More informationCurrent Profiles at the Offshore Wind Farm Egmond aan Zee J.W. Wagenaar P.J. Eecen
Current Profiles at the Offshore Wind Farm Egmond aan Zee J.W. Wagenaar P.J. Eecen OWEZ_R_122_Current_profiles_20101111 ECN-E--10-076 NOVEMBER 2010 Abstract NoordzeeWind carries out an extensive measurement
More informationOffshore Windfarm Egmond aan Zee 4 years of Operation
Offshore Windfarm Egmond aan Zee 4 years of Operation CUEN Offshore Wind Energy Conference 28 June 2011, Cambridge Elke Delnooz Operations Support Manager www.noordzeewind.nl 1 Contents Project description
More informationThe installation and servicing
European Forum for Renewable Energy Sources The installation and servicing of offshore wind farms Kaj Lindvig, CSO, A2SEA A/S 16 th September 2010 A2SEA Started 1 st July 2000 100% dedicated offshore wind
More informationPart 2. Appendix 2O. Greater Black Backed Gull EIA Analysis
Part 2 Appendix 2O Greater Black Backed Gull EIA Analysis Greater Black Backed Gull EIA Analysis Introduction Natural England (NE) and JNCC (in their further detailed response to Relevant Representations,
More informationSound Solutions Construction of offshore wind farms without underwater noise
Sound Solutions Construction of offshore wind farms without underwater noise www.noordzee.nl/soundsolutions Together for a healthy North Sea 2012 / 2013 S. van den Akker, L. van der Veen. North Sea Foundation
More informationArchimer http://archimer.ifremer.fr
Please note that this is an author-produced PDF of an article accepted for publication following peer review. The definitive publisher-authenticated version is available on the publisher Web site Marine
More informationNON-TECHNICAL SUMMARY OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT FOR THE BAHCE WINDFARM PROJECT (135 MW)
Zorlu Plaza, 34310 Avcılar ISTANBUL / TURKIYE Tel: + 90 (212) 456-2300 Fax: +90 (212) 422-0099 www.zorlu.com.tr NON-TECHNICAL SUMMARY OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT FOR THE BAHCE WINDFARM
More information6 Oktober 2010... KIVI Niria congres Offshore Wind De uitdaging. Eneco wind. Ernst van Zuijlen
6 Oktober 2010... KIVI Niria congres Offshore Wind De uitdaging Eneco wind Ernst van Zuijlen Eneco Targets... Maximise the use of renewable energy 2012: 25% of electricity produced sustainable (50% wind)
More informationFirth of Forth Offshore Wind Farm Zone. Offshore and Onshore Project Information
Firth of Forth Offshore Wind Farm Zone Offshore and Onshore Project Information May 2012 Introduction Seagreen Wind Energy Limited (Seagreen) is a 50/50 joint venture between SSE and Fluor (UK) Limited.
More informationNorth Sea offshore wind Developments in the Netherlands
September 2015 North Sea offshore wind Developments in the Netherlands This updated briefing focuses on the legal framework and recent developments in offshore wind in the Netherlands. We expect to publish
More informationROADMAP ON MARINE RENEWABLE ENERGY
FAME PROJECT - INTERNATIONAL WORKSHOP TERESA SIMAS 1 20 TH NOVEMBER, 2012 OBJECTIVES Overview of marine renewable energy development and prospects CONTENTS Green House Gas emissions targets Renewable energy
More informationOffshore Wind in Germany
Offshore Wind in Germany Lessons to be learned voor NL ir. Han van Asten, Programma manager TenneT Den Haag, KIVI NIRIA, 'Wind op Zee = Winst voor Nederland', 20 sep 2012 KIVI NIRIA Wind op Zee = Winst
More informationFour decades of windpower development: some value sensitive design lessons. Frans A. van der Loo Brussels 22 november 2013
Four decades of windpower development: some value sensitive design lessons Frans A. van der Loo Brussels 22 november 2013 The context Dutch innovation policy: Energy topsector Bio-energy Energy efficiency
More information14.3 Zone of Theoretical visibility (ZTV) - with obstructions 14.26 Viewpoint 14: Minor Rd, south side of Stemster Hill
Beatrice Offshore Wind Farm Environmental Statement Table of Contents Seascape, Landscape and Visual Assessment Figures LIST OF FIGURES 14.1 Location Plan 14.24 Viewpoint 12: Navidale 14.2 Zone of Theoretical
More informationCorrosion in offshore wind energy. a major issue. Harald van der Mijle Meijer
Corrosion in offshore wind energy a major issue Harald van der Mijle Meijer Corrosion in offshore wind energy A major issue Introduction TNO Den Helder What are the relevant types of corrosion? How to
More informationBeatrice Offshore Wind Farm Ltd
About Beatrice Offshore Wind Farm Ltd Beatrice Offshore Wind Farm Limited (BOWL) is a joint venture partnership formed between SSE Renewables (50%) Repsol Nuevas Energias UK (25%) (formerly SeaEnergy Renewables)
More informationWho are we? *Based on an average annual domestic household electricity consumption of 4,700KWh (DECC).
Who are we? We re one of the world s leading power and gas companies. Here in the UK, we supply energy to more than 5 million customers, generate enough electricity for around 8 million homes and employ
More informationNorth Sea offshore wind Developments in the Netherlands
April 2016 North Sea offshore wind Developments in the Netherlands This updated briefing focuses on the legal framework and recent developments in offshore wind in the Netherlands. We expect to publish
More informationThe Bellevue Center for Obesity & Weight Management. Program Director: Manish Parikh, MD WEIGHT LOSS SURGERY INFORMATION SEMINAR
Wednesday, January 7, 2015 Wednesday, February 4, 2015 Wednesday, March 4, 2015 Wednesday, April 1, 2015 Wednesday, May 13, 2015 Wednesday, June 3, 2015 Wednesday, July 1, 2015 Wednesday, August 5, 2015
More informationWEIGHT LOSS SURGERY INFORMATION SEMINAR
Wednesday, January 6, 2016 Wednesday, February 3, 2016 Wednesday, March 2, 2016 Wednesday, April 6, 2016 Wednesday, May 4, 2016 Wednesday, June 1, 2016 Wednesday, July 6, 2016 Wednesday, August 3, 2016
More informationIMARES Wageningen UR. Underwater acoustic noise characteristics of the OWEZ wind farm operation (T1)
Underwater acoustic noise characteristics of the OWEZ wind farm operation (T1) Dick de Haan, Dirk Burggraaf, Jan Tjalling van der Wal, Ralf van Hal Report number: OWEZ_R_251 T1 2014-05-28 IMARES C069/13
More informationThe Market for Installation Vessels
The Market for Installation Vessels SPEAKER: Lars Nedergaard, A2SEA A/S Date: June 8, 2011 Agenda A2SEA The Offshore Wind Farm Harbour The Products The Vessels The Market 2 A2SEA SEA ENERGY 2002 SEA POWER
More informationNote: This App is under development and available for testing on request. Note: This App is under development and available for testing on request. Note: This App is under development and available for
More informationLogistic solutions for the installation of offshore wind farms
Presentation Logistic solutions for the installation of offshore wind farms Captain / Graduate Economist Andreas Wulf Agenda - German Offshore Projects - Situation today - Transportations - Installations
More informationBorssele Wind Farm Zone
Borssele Wind Farm Zone Project & Site Description >> Sustainable. Agricultural. Innovative. International. Foreword The Netherlands wants sustainable, reliable and available energy that is affordable
More informationSeismic surveys in Greenland An example of noise regulation at a cumulative level
Seismic surveys in Greenland An example of noise regulation at a cumulative level By Line A. Kyhn, Aarhus University Co-authors: Anders Mosbech, David Boertmann Content Underwater acoustics and noise Why
More informationMeteo Dashboard a decision support system for offshore wind farms. Delft Software Days Jan-Joost Schouten Harbour, Coastal and Offshore Engineering
Meteo Dashboard a decision support system for offshore wind farms Delft Software Days Jan-Joost Schouten Harbour, Coastal and Offshore Engineering Content: Objective Intro offshore wind System components
More information40km. 30km. 10km. Regional Seascape Units. Legend. Regional Seascape Units. UK Offshore Development. Figure 14.5 MM DL WW 01/02/2012 1:525,000 @ A3
, & radii around Site Study Area Regional Seascape Units Remote High Cliffs - Duncansby Head to Skirza Head Rocky Coastline - Skirza Head to Keiss Deposition Coastline - Sinclair s Bay Rocky Coastline
More informationOffshore Base Cuxhaven. Dr. Hans-Joachim Stietzel Head of Dept. for Economic Development City of Cuxhaven Germany
Dr. Hans-Joachim Stietzel Head of Dept. for Economic Development City of Cuxhaven Germany Nordseeheilbad Cuxhaven Slide 2 Slide 3 Slide 4 Slide 5 Message : Is the ideal production site for the offshore
More informationDocument number #12 DNS13006. Authors #20 Telephone: Date #40 AUGUST 2013
#0 INSPECTION REPORT Discipline or report series #0 Inspection VESTAS wind turbines Title #5 VESTAS WIND TURBINE #2 Report number #52 #3 Authors #20 Telephone: Date #40 AUGUST 203 Summary #60 6 UNIT VESTAS
More informationEnvironmental damage: Extending the Environmental Liability Directive into marine waters
Environmental damage: Extending the Environmental Liability Directive into marine waters Consultation on amending the Environmental Liability (Prevention and Remediation) Regulations (Northern Ireland)
More informationRhode Island Ocean SAMP - European Fisheries & Offshore Wind Farms Expert Advice & Guidance Final Report
Rhode Island Ocean SAMP - European Fisheries & Offshore Wind Farms Expert Advice & Guidance Final Report 1 Department of Natural Resources April 2010 Report prepared and written by: Andrew B Gill PhD Natural
More informationRound 3 zone appraisal and planning. A strategic approach to zone design, project identification and consent
Round 3 zone appraisal and planning A strategic approach to zone design, project identification and consent 7 May 2010 Table of contents Glossary of terms and abbreviations... 1 Purpose of this document...
More informationFigure 1: The existing 12 300 kw turbines with the Avedøre power plant, source [3].
HVIDOVRE OFFSHORE WIND FARM Hans Christian Sørensen SPOK ApS / Hvidovre Vindmøllelaug I/S, Blegdamsvej 4, DK 2200, Copenhagen N, Denmark, E-mail: consult@spok.dk, Phone: +45 35360219/+45 28110219, Fax:
More informationThe New Age of Helicopter Leasing
The New Age of Helicopter Leasing October 2015 Helicopter as Assets Multi-Use Versatility - Medium and heavy helicopters are employed in a variety of industries Offshore SAR - Oil and gas companies represent
More informationRECALLING Paragraph b of Article 13 of the Convention on the Protection of the Marine Environment of the Baltic Sea Area, 1974 (Helsinki Convention),
CONVENTION ON THE PROTECTION OF THE MARINE ENVIRONMENT OF THE BALTIC SEA AREA HELSINKI COMMISSION - Baltic Marine HELCOM 19/98 Environment Protection Commission 15/1 Annex 3 19th Meeting Helsinki, 23-27
More informationTaskForce LNG Noord-Nederland. The Northern interregional approach Rotterdam, 7-8 november 2013 Patrick A.J.P. Cnubben Energy Valley Foundation
TaskForce LNG Noord-Nederland The Northern interregional approach Rotterdam, 7-8 november 2013 Patrick A.J.P. Cnubben Energy Valley Foundation Agenda Energy Valley Foundation a short introduction Liquefied
More informationUser manual data files meteorological mast NoordzeeWind
User manual data files meteorological mast NoordzeeWind Document code: NZW-16-S-4-R03 Version: 2.0 Date: 1 October 2007 Author: ing. HJ Kouwenhoven User manual data files meteorological mast NoordzeeWind
More informationGRAVITY BASE FOUNDATIONS
GRAVITY BASE FOUNDATIONS 2 Crown with reference to Marine All Activity Map Concrete gravity base foundations able to be floated and towed out to deeper water windfarms and installed without specialist
More informationMinisterial Council Declaration, Annex 6 TMAP STRATEGY
Annex 6: MCD 2014 TMAP Strategy page 1 12 th Trilateral Governmental Conference on the Protection of the WaddenSea Tønder, 5 February 2014 Ministerial Council Declaration, Annex 6 TMAP STRATEGY Draft Version
More informationSustainability in the Dutch Power Sector
Sustainability in the Dutch Power Sector Fact Sheet Series Eneco Joseph Wilde-Ramsing, Tim Steinweg, Maaike Kokke September 2008 Eneco 1 Introduction This series of fact sheets is designed to investigate
More informationBOEM has identified three action alternatives within the subject EA:
Mr. James F. Bennett, Chief Office of Renewable Energy Programs Bureau of Ocean Energy Management 381 Elden Street, HM 1328 Herndon, Virginia 20170 Dear Mr. Bennett: The Marine Mammal Commission (the Commission),
More informationWELCOME TO THE BAD Á CHEÒ WIND FARM EXHIBITION
WELCOME TO THE BAD Á CHEÒ WIND FARM EXHIBITION Thank you for taking the time to attend The purpose of this exhibition is to explain why we have identified this site for a potential wind farm development
More informationAn energy of the future coming from the sea
An energy of the future coming from the sea MAP showing the location of the Calvados offshore wind farm Why do we install off the coast of Calvados? Calvados offshore 75 PIONEER location of offshore wind
More informationInstrumentation for Monitoring around Marine Renewable Energy Devices
Instrumentation for Monitoring around Marine Renewable Energy Devices 1 Introduction As marine renewable energy has developed, a set of consistent challenges has emerged following attempts to understand
More informationFeasibility Study for Marine Wildlife Tourism in Henningsvær and in the Vestfjord
1 Feasibility Study for Marine Wildlife Tourism in Henningsvær and in the Vestfjord Heike Vester Biologist, specialist for Marine Mammal Biology and Bio acoustics Ocean Sounds AS, Sauøya 1, 8312 Henningsvær
More informationNSW - MEP : Maritime and marine risk assessment of calamitous (oil) spills
Prepared for: NoordzeeWind NSW - MEP : Maritime and marine risk assessment of calamitous (oil) spills Report OWEZ_R_280_20_07_2006 July, 2006 Z3644.00 Prepared for: NoordzeeWind NSW - MEP : Maritime and
More informationEIA case for Hiiumaa offshore wind farm in Estonia
EIA case for Hiiumaa offshore wind farm in Estonia Georg Martin & Liis Rostin With contributions from Aune Aunapuu, Ramboll Eesti and materials from Nelja Energia Seminar on Environmental Impact Assessment
More informationSTATUS OF OFFSHORE WIND ENERGY DEVELOPMENT IN GERMANY
On behalf of: Deutsche WindGuard GmbH - Oldenburger Straße 65-26316 Varel - Germany +49 (0)4451 9515-0 - info@windguard.de - www.windguard.com Additional [MW] Cumulative [MW] Cumulative (31.12.) Additions
More informationPROJECT PROFILE DEVELOPMENT OF A 100MW OFFSHORE WIND FARM IN HONG KONG
Ref: PD/900/00/00 PROJECT PROFILE DEVELOPMENT OF A 100MW OFFSHORE WIND FARM IN HONG KONG July 2006 Revision 0 The Hongkong Electric Co., Ltd. TABLE OF CONTENT Page 1. BASIC INFORMATION...2 1.1 Project
More informationPlanning for Offshore Wind Developments in Michigan s Great Lakes Background Materials
Planning for Offshore Wind Developments in Michigan s Great Lakes Background Materials January, 2009 Prepared by Michael Klepinger, Mikinetics, LLC for Michigan Economic Development Corporation and the
More informationLOGISTIC BASE FOR WIND FARM BUILD AT SEA
LOGITRANS - VII KONFERENCJA NAUKOWO-TECHNICZNA LOGISTYKA, SYSTEMY TRANSPORTOWE, BEZPIECZEŃSTWO W TRANSPORCIE Tadeusz STUPAK 1 Ryszard WAWRUCH 2 maritime transport safety, wind farm at sea, logistic transport,
More informationPosition Statement regarding Offshore Wind Proposals on Lake Huron. Lake Huron Centre for Coastal Conservation
Position Statement regarding Offshore Wind Proposals on Lake Huron Lake Huron Centre for Coastal Conservation June 2010 Lake Huron Centre for Coastal Conservation (LHCCC) Corporate Position related to:
More informationInstallation, future demands for recruitment and competencies. Speaker: Hans Schneider Date: 4 April 2013
Installation, future demands for recruitment and competencies 1 Speaker: Hans Schneider Date: 4 April 2013 Chief Operating Officer, A2SEA A/S Hans Schneider, COO PROFESSIONAL EXPERIENCE Chief Operating
More informationRESOURCES FOR THIS LESSON
Food Chains and Food webs Teacher Notes AIM: To introduce simple food chains and food webs using species found around an offshore windfarm development to illustrate key concepts such as energy flows, trophic
More informationProfile. Offshore Wind Projects. Sustainable EPC and Marine Contractors
Profile Offshore Wind Projects Sustainable EPC and Marine Contractors Offshore Pipeline Installation Svanen, heavy lift installation vessel Company profile Van Oord is a pre-eminent contractor for dredging,
More informationPROGRESS. Predictive modelling versus empirical data collision numbers in relation to flight activity in 55 German wind farm seasons
, Hanna Timmermann, Marc Reichenbach ARSU GmbH, Oldenburg, Germany PROGRESS Predictive modelling versus empirical data collision numbers in relation to flight activity in 55 German wind farm seasons Project
More informationAcoustic and Visual Impacts of a 0.25 MW WTG at Huasai, Nakhon Si Thammarat in Southern Thailand
Acoustic and Visual s of a.25 MW WTG at Huasai, Nakhon Si Thammarat in Southern Thailand J. Waewsak 1,*, C. Kongruang 2, N. Matan 3 and C. Prompat 4 1 Solar and Wind Energy Research Unit, Department of
More informationOverview of Atlantic Offshore Renewable Energy Studies Program. Brian Hooker Office of Renewable Energy Programs
Overview of Atlantic Offshore Renewable Energy Studies Program Brian Hooker Office of Renewable Energy Programs February 2012 Completed Studies of Interest Compendium of Avian Information and Comprehensive
More informationSEFEC. With Open Coast Defence of Steel and Concrete built Barrier towards Total Energy Transition 2050 by Combining Water-, Wind- and Sun-Power
1. Description Multifunctional Flood Barrier SEFEC With Open Coast Defence of Steel and Concrete built Barrier towards Total Energy Transition 2050 by Combining Water-, Wind- and Sun-Power Description
More informationOffshore wind potential in Europe and review of offshore resource modelling techniques
Offshore wind potential in Europe and review of offshore resource modelling techniques Rebecca Barthelmie, Sten Frandsen & Sara Pryor (Risø National Laboratory, Wind Energy Department), Colin Morgan (Garrad
More information