2014 CHP RFO OFFERORS CONFERENCE CALL

Size: px
Start display at page:

Download "2014 CHP RFO OFFERORS CONFERENCE CALL"

Transcription

1 2014 CHP RFO OFFERORS CONFERENCE CALL December 4, 2014 at 9:00 am, Pacific Prevailing Time Webex: Meeting Number: Access Code: chp3 Conference: Call-in toll-free number: Participant code:

2 Overview Overview (Max Carpenter) 9:00 Part 1: RFO Materials (Benny Wu) 9:20 Part 2: Offer Template (Allison Galvan) 9:40 Part 3: Offer Evaluation (John McNamara) 10:00 Questions 10:20 Conclude Conference 10:30 This conference call is being recorded and will be made available at: On.sce.com/chprfo or Questions: We will accept your questions at the conclusion of each part. Please indicate that you have a question by submitting your question in Webex or by notifying the operator Page: 2

3 Scope of the Offerors Conference The purpose of this conference is to assist potential participants in SCE s 2014 CHP RFO Per D , SCE has a need for all resource types located in the western L.A. Basin and Moorpark sub-areas, including CHP projects, to meet local capacity requirements. We encourage projects meeting those requirements to participate in this CHP RFO We will not be discussing other SCE programs in this conference call We will not be discussing specific modifications to any of the documents or pro forma agreements This WebEx will be posted on the CHP website for review Page: 3

4 Independent Evaluator Merrimack Energy has been retained as the Independent Evaluator (IE) for this solicitation Wayne Oliver Barry Sheingold Primary role of the IE is to: Monitor SCE s solicitation and negotiation processes to ensure reasonable, fair and equal treatment of all potential counterparties Monitor SCE s valuation methodologies and selection processes to ensure reasonable, fair and equal treatment of all offers The IE is privy to all offer data, invited to participate in all negotiations and should be copied on all correspondence between SCE and Offerors KEY POINT: Offerors must copy the IE on all s and other correspondence sent to SCE at CHPRFO@sce.com Page: 4

5 CHP Settlement Agreement & Targets CHP Settlement Agreement set two key targets for SCE: Procure 1,402 MW from CHP resources by 2015 with intermediate targets corresponding to each of 3 CHP RFOs Obtain 2.17 MMT GHG savings from CHP resources by 2020 SCE Target Target Approved Estimated RFO Close Dates MW Target A 630 MW 616 MW 1 RFO 1 Jul 2012 (Track 1) MW Target B 378 MW (348 MW) 2 RFO 2 Mar 27, 2014 MW Target C 394 MW - RFO 3 Nov 2015 Total MW Target (by 2015) 1,402 MW 616 MW Total GHG Target (by 2020) 2.17 MMT 0.24 MMT KEY POINT: SCE will target a minimum of 53 MW (1402 MW 616 MW MW MW 3 ) and endeavor to make progress toward our GHG target in CHP RFO 3 SCE has entered into a bilateral agreement with a CHP resource for 385 MW 3, which is why the target procurement amount has been reduced Notes: 1. CPUC approved 542 MW of the 832 MW procured in CHP RFO 1; SCE procured an additional 74 MW through other Settlement-approved channels MW were subject to regulatory approval. Dry Creek (48 MW) was terminated; 348 MW still awaiting regulatory approval from CPUC MW was procured bilaterally and will count toward Target C. Contract is still awaiting regulatory approval from CPUC Page: 5

6 Keys to a Successful Offer Submit complete offer package(s) Incomplete offer packages may be disqualified Use the RFO Offer Structure Letter to clearly articulate your offer and any unique considerations Submit competitively priced offers SCE expects a robust solicitation response to this CHP RFO Offer multiple configurations/packages for consideration SCE prefers offers that can meet both CHP MW & GHG Targets Offer optionality, as appropriate Term can be varied up to the maximum (7 years for existing and expanded w/out collateral; 12 years for new, expanded w/ collateral, and repowered) SCE is seeking curtailment provisions when the CAISO prices are negative Page: 6

7 Keys to a Successful Offer(cont.) SCE has a stated preference to execute pro forma agreements CHP PPA (attachment C-1)was negotiated as part of the Settlement Agreement Utility Pre-scheduled Facility (UPF) Documents have been public and used extensively in SCE s All Source RFOs If you require modifications to the CHP PPA pro forma, begin with the SCEspecific PPA (attachment C-2) SCE seeks well developed projects. For new, expanded and repowered CHP Facilities, Offerors must show: Progress in the interconnection process or plan to obtain interconnection Projects requiring an Interconnection Study are eligible to participate in this RFO SCE will use the network upgrade cost contained in the project s Interconnection Study, if Interconnection Study exists, otherwise we will include a termination option based on negotiated upgrade cost Other demonstrated signs of a viable project: Site control and project development plans Permitting and interconnection status Strong financial backing Realistic on-line dates and forecasted operating performance Page: 7

8 Supplier Diversity SCE encourages small business entities as well as Women-Owned, Minority-Owned, and Disabled Veteran-Owned Business Enterprises ( WMDVBE ) to participate in the CHP RFO CPUC General Order 156 sets the rules governing the development of programs to increase participation of WMDVBEs in procurement of contracts from utilities as required by CPUC Code For additional information, please visit SCE s website, Guidance is also available at under the heading Help & Guidance Please contact Cristina Radu for question regarding Supplier Diversity Cristina.radu@sce.com Page: 8

9 Questions Page: 9

10 Part 1 RFO Materials Presented By Benny Wu Page: 10

11 QF and CHP Settlement Programs CHP Program Settlement Effective Date (11/23/2011) CHP RFO 1 12/15/11 Target A 630 MW Completed CHP RFO 2 9/12/13 Target B 378 MW Completed CHP RFO 3 ~ 11/2014 Target C 394 MW Upcoming Nov 14 Four Years After Settlement Effective Date (11/23/2015) 12/31/2020 RFO As determined in SCE LTPP Initial Program Period Second Program Period SCE CHP MW Target: 1402 MW CHP RFO Process SCE Launch CHP RFO (11/13/14) RFO Process Track 1 (~160 days) Negotiate PPA SCE Executes Track 1 PPAs (5/28/15) SCE Shortlist Offerors for Negotiations Offerors Qualification Date SCE Submit PPAs to CPUC for Approval Offerors Submit Indicative Offer Offerors Submit Final Offer SCE GHG Target: 2.17 MMT reduction Offerors Conference Call Time-line not drawn to scale Page: 11

12 Changes in this 3 rd CHP RFO No changes to the process of this CHP RFO. SCE has updated the documents to reflect latest pro-forma positions. Counterparties must use the new forms and not submit older forms used in prior CHP RFOs CHP Facility must be located in California Interconnected to the CAISO Controlled Grid and certified by the CAISO as a Participating Generator or must have firm transmission rights and deliver to a CAISO controlled interconnect Single track process for expanded, existing, new and repowered CHP facilities For those that require and have an Interconnection Study, SCE will use the upgrade cost from the study to evaluate the CHP Facility For those that require an Interconnection Study but do not have one, SCE will require a termination option in the PPA that will be triggered if upgrade costs exceed a specified amount SCE will not accept RA-only product from a CHP facility in this CHP RFO Page: 12

13 RFO Materials 2014 CHP RFO Instructions Attachment A Non-Binding Notice of Intent to Offer Attachment B Offer Template (please download latest revision) Attachment C1 Pro Forma CHP PPA (Settlement Agreement) Attachment C2 Pro Forma CHP PPA (SCE Specific) Attachment D1 EEI Master PP&S Agreement Cover Sheet Attachment D2 EEI Paragraph 10 to the Collateral Annex Attachment D3 UC Tolling Confirmation Attachment D4 RA Confirmation 2014 CHP RFO Materials are available at: On.sce.com/chprfo or Page: 13

14 Eligibility Requirements Eligible CHP Resources Existing, New, Expanded and Repowered CHP Facilities Nameplate capacity larger than 5 MW Meet the definition of cogeneration under California Public Utilities Code Meet the Emissions Performance Standard established by Public Utilities Code 8341 (Senate Bill 1368) Meet the federal definition of a qualifying cogeneration facility under 18 CFR implementing PURPA New CHP Resources must meet the FERC Fundamental Use Test (per guidance from the CPUC in Resolution E-4554) Utility Prescheduled Facility CHP Facility that met the PURPA efficiency requirements (18 C.F.R ) as of September 2007 and converts to a Utility Prescheduled Facility Refer to Settlement Agreement Section Page: 14

15 Product and Document Generating Facility Baseload CHP Facility UPF/ Dispatchable CHP Facility PPA Type CHP PPA (Attachments C-1 or C-2) EEI Master PPSA Cover Sheet (Attachment D-1); EEI P10 to the Collateral Annex (Attachment D-2); UC Tolling Confirmation (Attachment D-3); RA Confirmation (Attachment D-4) (collectively, Dispatchable Documents ) Product Power Product and Related Products Capacity, Energy, Ancillary Services, (each as defined in the UC Tolling Confirmation) and Capacity Attributes (as defined in the RA Confirmation), and any other product derived from or associated with each generating unit Delivery Point Scheduling Coordinator ( SC )/ Fuel Manager Economic Curtailment SCE prefers to be the SC, but Offeror may select another SC. Offeror may bid in an Economic Curtailment Option (see Exhibit U of the CHP PPA) CAISO SCE is the SC. SCE is not the fuel manager. N/A Pricing Capacity ($/kw-year) As bid As bid; shaped, as set forth in 2.06 of the RFO Instructions Heat Rate for Energy Pricing (Btu/kWh) As bid plus Variable Charge ($/kwh) Note: 1. For CHP facilities that offer both baseload and dispatchable products, Offeror should use the Dispatchable Documents with provisions added to include the baseload portion. If an Offeror desires to use another document for dispatch, it should contact SCE as soon as possible in order to provide information regarding its offer(s) and to obtain SCE s consent to use such document. 2. SCE will not accept RA-only product from a CHP facility in this CHP RFO. Page: 15

16 Term and Start Date* Facility Type Existing Expanded (w/o collateral) Expanded (w/ collateral) Repowered New Term Length No more than 7 years No more than 12 years Earliest Term Start Date Tier 2 Advice Letter Tier 3 Advice Letter Ninety (90) days after CPUC approval (expected approximately 3 months after Effective Date), February 1, 2016* N/A Ninety (90) days after CPUC approval (expected approximately 14 months after Effective Date), November 1, 2016* Latest Term Start Date No later than 2 years after the Effective Date No later than 3 years after CPUC Approval No later than 5 years after CPUC Approval * Based on executing RFO PPA on June 1, 2015 Page: 16

17 RFO Schedule CHP RFO 3 Schedule Date* Milestone 11/13/2014 Launch CHP RFO 3 12/11/2014 Offerors Submit Non binding Notice of Intent 1/8/2015 SCE reserves the right to modify the RFO schedule in its sole discretion Offerors Submit Indicative Offers Offerors who fail to submit these materials by the stated time may be disqualified by SCE in its sole discretion from further participation in this RFO. 2/19/2015 SCE notifies Short Listed Offerors Begin Negotiations 4/23/2015 Finalize All Agreements Offerors who fail to meet this negotiation deadline may be disqualified by SCE in its sole discretion from further participation in this RFO. Offerors Submit Final Binding Offers 4/30/2015 SCE will only consider Final Binding Offers from Offerors who have satisfied all the requirements set forth in the RFO Instructions. 5/21/2015 SCE notifies Selected Offerors 6/1/2015 Execution of Final Agreements ~7/31/2015 SCE Files Awarded PPA with CPUC for Approval Refer to CHP RFO Instructions Section 1.03 Page: 17

18 Key Dates and Submittal Information December 11 Submit Non-Binding Notice of Intent (Attachment A) January 8 Submit Complete Offer Submittal Package (CHP RFO Instructions Sections 3.01 to 3.03) the Offer Structure Letter (Exhibit A, last page in RFO Instructions) Submit two Offer e-binders, each on a USB flash drive by physical mail. For each project, the Offer e-binder must contain: Offer Structure Letter Offer Template (Attachment B) Applicable PPA document (Attachment C1, C2 or Attachments D1-D4) Generating facility description and applicable documents Site description and applicable documents Regulatory filings substantiating the offer data April 30, 2015 Submit Final Binding Offer Please get necessary approvals early to submit binding offer Offers need to be binding until we execute PPAs on June 1, 2015 Key Point: Submit Competitively Priced Offers Page: 18

19 Regulatory Approval of CHP Agreement CPUC and FERC Approval (Section 6.01 of RFO Instructions) SCE s obligations to purchase any product under a final agreement will only become effective upon receipt of CPUC Approval and the approval of FERC (when applicable) SCE will submit all PPAs awarded in this CHP RFO for CPUC Approval SCE will submit a Tier 2 Advice Letter for Existing CHP Facilities that execute the CHP PPA without material modification SCE will submit a Tier 3 Advice Letter for all other final agreements PPAs between SCE and any SCE affiliate require approval by FERC Emissions Performance Standard (EPS) Approvals For PPAs with term length equal to or greater than five (5) years, the CPUC must make a specific finding that the PPA is in compliance with the EPS Offeror must provide information to SCE on the Offer Template, on a confidential basis as necessary, to allow SCE to make a sufficient showing of compliance with the EPS Page: 19

20 Existing CHP w/ppa Wanting to Participate Early Termination of Existing PPA (Section 2.10 of RFO Instructions) SCE encourages counterparties with an existing PPA to participate in this CHP RFO If an Offer is based upon early termination of an existing PPA, please state in the Offer Structure Letter if the existing PPA contains an early termination right and, if SCE is the buyer, what the capacity recapture payment would be Page: 20

21 Document Conflicts This presentation is intended to be a summary level discussion of the information and requirements established in the RFO Materials and does not include all of the detailed information in the RFO Materials To the extent that there are any inconsistencies between the information provided in this presentation and the requirements established in the RFO Materials, the RFO Materials will govern To the extent that there are any inconsistencies in the RFO Materials, the hierarchy established in the RFO Instructions will govern Page: 21

22 RFO Communications 2014 CHP RFO website On.sce.com/chprfo or All RFO-related communications should be sent to: and to Wayne Oliver Page: 22

23 Questions Page: 23

24 Part 2 Offer Template Presented By Allison Galvan Page: 24

25 Questions Page: 25

26 Part 3 Offer Evaluation Presented By John McNamara Page: 26

27 CHP RFO Selection Process Receive indicative offers and run initial eligibility screen Quantitative review - Rank eligible offers based on NPV CHP Premium/MW and GHG reduction and remove outliers Qualitative review Ensure that all eligible indicative offers (including outliers) are added to or removed from short-list based on qualitative factors Create short-list and notify counterparties Negotiate agreements and receive final offers Re-run Quantitative and Qualitative review based on latest forecasts and information Select final offers and notify counterparties Page: 27

28 Quantitative Review NPV CHP Premium per MW & GHG Reduction Analysis Costs Contract Payments Based on the contract heat rates, variable charge, and capacity prices, expected generation and contract term Transmission Cost Cost adders for required network upgrades based on the best information available (e.g., completed Facilities Study, Phase 1 Interconnection Study (or equivalent), or better, etc.) Debt Equivalence Cost Cost of contract commitments on SCE s balance sheet GHG Cost Dependent on Seller s allocation of GHG Compliance Costs Congestion and Losses Location cost resulting from certain resource locations Benefits Energy Value Captures market value of the energy including a forecast for GHG while taking into account dispatchability* of resource Capacity Value** The value of the countable Resource Adequacy capacity (see next slide for details) Ancillary Services and Real Time Flexibility Value Some level of benefit may be attributed to projects bid as a Utility Prescheduled Facility Credit/Collateral Dependent on Seller s selection of various levels of Performance Assurance Congestion and Losses Locational benefit resulting from certain resource locations Proposals are ranked based on an NPV premium per MW & GHG*** basis that weighs costs and benefits to SCE s resource portfolio: [{$PV Costs} {$PV Benefits}] / MW = $ NPV CHP Premium per MW & [{$PV Costs} {$PV Benefits}] / GHG reduction = $ NPV CHP Premium per GHG reduction *UPF s energy production will be determined using a production simulation model and internal energy forecasts. CHP s generation will be determined using the expected generation information provided by each counterparty **As-available offers will not receive a RA benefit ***SCE is seeking cost effective GHG reduction consistent with the goals and objectives of the CHP Settlement Agreement Page: 28

29 Deriving Countable Resource Adequacy Capacity Existing CHP Resources: RA MWs equal current Net Qualifying Capacity (NQC) For calendar year 2018 and beyond RA NQC calculated as the minimum of (average peak period energy deliveries, 100% of Firm capacity offered) New or repowered CHP Resources: For the first two years RA NQC is based on Firm capacity offered and NQC profile derived from fleet Technology* Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec BIOMASS 71% 72% 71% 62% 66% 74% 76% 75% 75% 72% 71% 74% COGENERATION 64% 63% 60% 59% 61% 67% 68% 69% 65% 57% 57% 58% GEOTHERMAL 85% 85% 82% 80% 82% 79% 79% 78% 79% 79% 81% 83% After the first two years RA NQC calculated as the minimum of (average peak period energy deliveries, 100% of Firm capacity offered) UPF Offers RA MW: RA NQC based on submitted and validated RA capacity offered *Source: 2015 Technology Factors at Page: 29

30 Qualitative Review SCE may consider qualitative characteristics to determine inclusion in or exclusion from the short-list or tiebreakers, if any. These additional characteristics may include: Permitting and Interconnection (Environmental & Permitting Status, Electrical Interconnection, Fuel Interconnection & Source, Water Interconnection & Source) Pre-development Milestones (Project Financing Status, Project Development Experience, Thermal Host, FERC & CA QF Standards, Emissions Performance Standard) Development Milestones (Site Control, Large Equipment Status, Reasonableness of Commercial Operation Date) Transmission area Congestion, negative price, and curtailment considerations not captured in the quantitative valuation Portfolio fit of energy, capacity, & term Offeror concentration Dispatchability & curtailability Modifications to Pro Forma Offer price in excess of public or independent data Page: 30

31 Questions Page: 31

32 Additional Questions? and to Wayne Oliver Access the recording of this conference call at: Page: 32

Diverse Business Enterprises ( DBE ) Readiness Checklist to Sell Wholesale Power to SCE June 25, 2013

Diverse Business Enterprises ( DBE ) Readiness Checklist to Sell Wholesale Power to SCE June 25, 2013 Diverse Business Enterprises ( DBE ) Readiness Checklist to Sell Wholesale Power to SCE June 25, 2013 For questions regarding power procurement opportunities, please contact: Cristina Radu, Energy Contracts

More information

Energy Storage. Opportunities, Challenges and Solutions

Energy Storage. Opportunities, Challenges and Solutions Energy Storage Opportunities, Challenges and Solutions By Les Sherman February 2014 Energy Storage Opportunities, Challenges and Solutions By Les Sherman As our nation pursues ambitious goals towards substantially

More information

2014 EIA Energy Conference. Edward Randolph Director, Energy Division California Public Utilities Commission

2014 EIA Energy Conference. Edward Randolph Director, Energy Division California Public Utilities Commission 2014 EIA Energy Conference Edward Randolph Director, Energy Division California Public Utilities Commission July 14, 2014 Clean Electricity Policy Initiatives In California (Partial) Wholesale Renewables

More information

SUBJECT: Submission of Contract for Procurement of Renewable Energy from SCE's 2013 Renewables Portfolio Standard Solicitation

SUBJECT: Submission of Contract for Procurement of Renewable Energy from SCE's 2013 Renewables Portfolio Standard Solicitation STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 April 1, 2015 Advice Letter 3126-E Russell G. Worden Director, State Regulatory

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS RENEWABLE ENERGY CERTIFICATES SOURCED FROM RENEWABLE RESOURCES CERTIFIED BY THE CALIFORNIA ENERGY COMMISSION February 18, 2015 1.0 Introduction of Pittsburg Power Company dba Island

More information

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network

More information

California Distributed Generation (DG)

California Distributed Generation (DG) California Distributed Generation (DG) Timothy Alan Simon Commissioner, California Public Utilities Commission Chair, Gas Committee, National Association of Regulatory Utility Commissioners Harvard Electricity

More information

Contracts for Difference Round Guidance

Contracts for Difference Round Guidance 30th June 2014 Contracts for Difference Round Guidance Contracts for Difference Allocation Round 1 2014 CFD Round Guidance 3 rd October 2014 National Grid Delivery Body Page 1 CFD Allocation Round Guidance

More information

Welcome to the SDG&E Renewable Market Adjusting Tariff (Re-MAT) Program Overview Webinar

Welcome to the SDG&E Renewable Market Adjusting Tariff (Re-MAT) Program Overview Webinar Welcome to the SDG&E Renewable Market Adjusting Tariff (Re-MAT) Program Overview Webinar Renewable Market Adjusting Tariff (Re-MAT) Program Overview Webinar September 11, 2013 SDG&E Re-MAT Overview Webinar

More information

**Redacted, Public Version**

**Redacted, Public Version** Proceeding No.: A.10-10-xxx Exhibit No.: Witness: Tony Choi DIRECT TESTIMONY OF TONY CHOI SAN DIEGO GAS & ELECTRIC COMPANY **Redacted, Public Version** BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE

More information

Pacific Gas and Electric Company Renewable Auction Mechanism (RAM) Request for Offers. Renewable Auction Mechanism (RAM) Request for Offers

Pacific Gas and Electric Company Renewable Auction Mechanism (RAM) Request for Offers. Renewable Auction Mechanism (RAM) Request for Offers Renewable Auction Mechanism (RAM) Request for Offers Updated: March 2, 2016 i Table of Contents I. OVERVIEW... 1 OVERVIEW... 1 SCHEDULE... 1 1. Schedule Overview... 2 2. RFO Process... 3 DISCLAIMERS FOR

More information

Request for Proposals for Solar Renewable Energy Certificates RFP #1012 March 7, 2012

Request for Proposals for Solar Renewable Energy Certificates RFP #1012 March 7, 2012 Request for Proposals for Solar RFP #1012 March 7, 2012 1.0 INTRODUCTION GreenCo Solutions, Inc. (GreenCo) is seeking proposals for (RECs) from qualified solar resources. The purpose of this Request for

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS* COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun

More information

2014 Solicitation DGS Request for Proposals & ADGS Request for Information Conference. July 1, 2014

2014 Solicitation DGS Request for Proposals & ADGS Request for Information Conference. July 1, 2014 2014 Solicitation DGS Request for Proposals & ADGS Request for Information Conference July 1, 2014 Overview of the Conference Introduction Conference Agenda DGS and ADGS Overview RFP/RFI Schedule The DGS

More information

FERC Workshop on Price Formation: Scarcity and Shortage Pricing, Offer Mitigation, and Offer Caps in RTO and ISO Markets (Docket. No.

FERC Workshop on Price Formation: Scarcity and Shortage Pricing, Offer Mitigation, and Offer Caps in RTO and ISO Markets (Docket. No. FERC Workshop on Price Formation: Scarcity and Shortage Pricing, Offer Mitigation, and Offer Caps in RTO and ISO Markets (Docket. No. AD14-14-000) October 28, 2014 Market Presentation Design Title & Analysis

More information

Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8

Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007

More information

Alternative Options for the Availability Standard and Replacement Rule components of the Standard Capacity Product II Initiative March 18, 2010

Alternative Options for the Availability Standard and Replacement Rule components of the Standard Capacity Product II Initiative March 18, 2010 Alternative Options for the Availability Standard and Replacement Rule components of the Standard Capacity Product II Initiative March 18, 2010 CAISO/M&ID/SCP II Team March 18, 2010 page 1 Standard Capacity

More information

California s Energy Future

California s Energy Future California s Energy Future 1 Sunrise Powerlink Commitment and Imperial Valley Renewable Energy Projects Project Name Technology Location Contract Capacity (MW) Flowing across Sunrise Today (MW) Project

More information

Appendix A. Glossary. For. 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC

Appendix A. Glossary. For. 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC Appendix A Glossary For 2016 Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC Entergy Services, Inc. June 8, 2016 Website means the internet website https://spofossil.entergy.com/entrfp/send/2016ellrenewablerfp/index.htm.

More information

2009 Request for Proposals from Eligible Renewable Resource Suppliers for Electric Energy

2009 Request for Proposals from Eligible Renewable Resource Suppliers for Electric Energy 2009 Request for Proposals from Eligible Renewable Resource Suppliers for Electric Energy Appendix C Form of Seller s Proposal Version 2 Posted July 24, 2009 TABLE OF CONTENTS ARTICLE ONE: INTRODUCTION...1

More information

2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Arkansas, Inc.

2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Arkansas, Inc. 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Arkansas, Inc. Entergy Arkansas, Inc. May 26, 2016 TABLE OF CONTENTS 1. GENERAL INFORMATION... 1 1.1. Introduction...

More information

Opportunities for Biogas Digesters

Opportunities for Biogas Digesters Opportunities for Biogas Digesters Presented to the California Bioresources Alliance September 13, 2011 Jody S. London P.O. Box 3629 Oakland, California 94609 510/459-0667 jody_london_consulting@earthlink.net

More information

EE and Reliability: SCE s LCR RFO and Preferred Resources Pilot. ACEEE Energy Efficiency as a Resource National Conference Mohammed Aliuddin

EE and Reliability: SCE s LCR RFO and Preferred Resources Pilot. ACEEE Energy Efficiency as a Resource National Conference Mohammed Aliuddin EE and Reliability: SCE s LCR RFO and Preferred Resources Pilot ACEEE Energy Efficiency as a Resource National Conference Mohammed Aliuddin 1 Several major drivers have led to initiatives that are changing

More information

Business Requirements Specification

Business Requirements Specification Business s Specification Capacity Procurement Mechanism Replacement Doc ID: GNFDMDEHU6BB-46-53 Page 1 of 18 Disclaimer All information contained in this draft Business s Specification (BRS) as provided

More information

EMR Capacity Market Implementation Coordination Workshop

EMR Capacity Market Implementation Coordination Workshop EMR Capacity Market Implementation Coordination Workshop Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight

More information

2 CALCULATION OF BORROWING LIMITS

2 CALCULATION OF BORROWING LIMITS TARGETED LONGER-TERM REFINANCING OPERATIONS Updated modalities Following a decision by the ECB s Governing Council, the Eurosystem will conduct eight targeted longer-term refinancing operations (TLTROs)

More information

Analysis One Code Desc. Transaction Amount. Fiscal Period

Analysis One Code Desc. Transaction Amount. Fiscal Period Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00

More information

PG&E and Renewable Energy. Chuck Hornbrook Senior Manager Solar and Customer Generation

PG&E and Renewable Energy. Chuck Hornbrook Senior Manager Solar and Customer Generation PG&E and Renewable Energy Chuck Hornbrook Senior Manager Solar and Customer Generation PG&E and our Business What we do: Deliver safe, reliable, and environmentally responsible gas and electricity to approximately

More information

OKLAHOMA GAS AND ELECTRIC COMPANY REQUEST FOR INFORMATION. Solar Energy Purchase Power Agreement Information

OKLAHOMA GAS AND ELECTRIC COMPANY REQUEST FOR INFORMATION. Solar Energy Purchase Power Agreement Information OKLAHOMA GAS AND ELECTRIC COMPANY REQUEST FOR INFORMATION Solar Energy Purchase Power Agreement Information RFI Issue Date May 18, 2015 Responses Due June 15, 2015 1. RFI Purpose and Scope 1.1 Purpose

More information

Appendix 1 to Fish Pool Rulebook. Product Specifications and Trading schedule for Trading at Fish Pool markets

Appendix 1 to Fish Pool Rulebook. Product Specifications and Trading schedule for Trading at Fish Pool markets Appendix 1 to Fish Pool Rulebook Product Specifications and Trading schedule for Trading at Fish Pool markets Table of contents General provisions:... 2 Product Specifications Forwards and Futures:...

More information

OFF CAMPUS RENEWABLE ENERGY PROJECT DEVELOPMENT

OFF CAMPUS RENEWABLE ENERGY PROJECT DEVELOPMENT Request for Proposal OFF CAMPUS RENEWABLE ENERGY PROJECT DEVELOPMENT Stanford University RFP ISSUED 24 OCTOBER 2014 PRE PROPOSAL MEETING 5 NOVEMBER 2014 PROPOSALS DUE 17 NOVEMBER 2014 Table of Contents

More information

From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer

From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer Date: September

More information

Grid Operations and Planning

Grid Operations and Planning Grid Operations and Planning Report Kent Saathoff ERCOT Board of Directors April 20, 2010 Kent Content Summary March 2010 Operations Peak Demand: Actual vs. Forecast On-line Resources: Total at Peak and

More information

Hawai i s PV Challenge/Opportunity

Hawai i s PV Challenge/Opportunity Hawai i s PV Challenge/Opportunity UWIG Solar Integration Workshop Lahaina, Maui October 11, 2011 Mark Duda President, PO Box 37070 Honolulu HI, 96837 www.hsea.org mark@dephawaii.com Hawai i Market Drivers

More information

REVISED REQUEST FOR PRICING (RFP) FOR ELECTRICITY AGGREGATION SUPPLY SERVICES FOR THE CITY OF CHICAGO. Specification No. 112257 Required for use by:

REVISED REQUEST FOR PRICING (RFP) FOR ELECTRICITY AGGREGATION SUPPLY SERVICES FOR THE CITY OF CHICAGO. Specification No. 112257 Required for use by: REVISED REQUEST FOR PRICING (RFP) FOR ELECTRICITY AGGREGATION SUPPLY SERVICES FOR THE CITY OF CHICAGO Specification No. 112257 Required for use by: CITY OF CHICAGO (Department of Fleet and Facility Management)

More information

Southern California Edison Revised Cal. PUC Sheet No. 59134-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Southern California Edison Revised Cal. PUC Sheet No. 59134-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. Southern California Edison Revised Cal. PUC Sheet No. 59134-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 58300-E Schedule TOU-8-RBU Sheet 1 APPLICABILITY Applicable to the additional

More information

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017 From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days

More information

Appendix A Glossary For 2011 Western Region Request For Proposals (RFP) for Long-Term Supply Side Resources

Appendix A Glossary For 2011 Western Region Request For Proposals (RFP) for Long-Term Supply Side Resources Appendix A Glossary For 2011 Western Region Request For Proposals (RFP) for Long-Term Supply Side Resources Entergy Services, Inc September 30, 2011 RFP and the terms and acknowledgements set forth in

More information

Schedule NEM Sheet 1 NET ENERGY METERING

Schedule NEM Sheet 1 NET ENERGY METERING Southern California Edison Revised Cal. PUC Sheet No. 50927-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 49175-E* Schedule NEM Sheet 1 APPLICABILITY Applicable to Eligible Customer-Generators

More information

POLICY FEEDING RENEWABLE. How the Energy Bill might affect green electricity suppliers and also renewable generators

POLICY FEEDING RENEWABLE. How the Energy Bill might affect green electricity suppliers and also renewable generators FEEDING RENEWABLE POLICY How the Energy Bill might affect green electricity suppliers and also renewable generators Holly Tomlinson Regulation and Compliance Analyst for Ecotricity 18 th January 2013 Contents

More information

REQUEST FOR INFORMATION Issued: October 21, 2015 Solicitation for: Website Development Responses Due: 2:00 p.m. (Local Time) on November 18, 2015

REQUEST FOR INFORMATION Issued: October 21, 2015 Solicitation for: Website Development Responses Due: 2:00 p.m. (Local Time) on November 18, 2015 REQUEST FOR INFORMATION Issued: October 21, 2015 Solicitation for: Website Development Responses Due: 2:00 p.m. (Local Time) on November 18, 2015 INTRODUCTION: Because this procurement involves a service,

More information

Request for Proposal HQC2012-11-16. Evaluation of Saskatchewan s Lean Health Care Transformation: Phase 1

Request for Proposal HQC2012-11-16. Evaluation of Saskatchewan s Lean Health Care Transformation: Phase 1 Request for Proposal HQC2012-11-16 Evaluation of Saskatchewan s Lean Health Care Transformation: Phase 1 Issued: November 16, 2012 Table of Contents 1 Statement of Purpose... 3 2 About HQC... 4 3 Proposal

More information

Table of Contents. Real-Time Reliability Must Run Unit Commitment and Dispatch (Formerly G-203) Operating Procedure

Table of Contents. Real-Time Reliability Must Run Unit Commitment and Dispatch (Formerly G-203) Operating Procedure No. 2310 Table of Contents Purpose... 2 1. Responsibilities... 2 2. Scope/Applicability... 2 2.1 Background... 2 2.2 Scope / Applicability... 2 3. Detail... 3 3.1 Energy Dispatching... 3 3.1.2 Real-Time

More information

March 1, 2007 ADVICE 2107-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION

March 1, 2007 ADVICE 2107-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION Akbar Jazayeri Vice President, Revenue and Tariffs March 1, 2007 ADVICE 2107-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Late Payment Charge Revenue Balancing

More information

Energy Management. Electric Procurement Strategies. August 27, 2007

Energy Management. Electric Procurement Strategies. August 27, 2007 Energy Management Electric Procurement Strategies August 27, 2007 1 Presentation Outline Purpose Background City of Dallas procurement goals Procurement term Environmental goals Energy products Energy

More information

Tehachapi Wind Energy Storage Project (TSP)

Tehachapi Wind Energy Storage Project (TSP) Tehachapi Wind Energy Storage Project (TSP) Peer Review Presented by Mr. Loïc Gaillac October 20, 2011 San Diego, CA 1 Outline Policy Challenges SCE s Position SCE Smart Grid Vision Project Description

More information

[ELECTRICITY PROCUREMENT PLAN] Prepared in accordance with the Illinois Power Agency and Illinois Public Utilities Acts September 29, 2014

[ELECTRICITY PROCUREMENT PLAN] Prepared in accordance with the Illinois Power Agency and Illinois Public Utilities Acts September 29, 2014 2015 Anthony Star Director [ELECTRICITY PROCUREMENT PLAN] Prepared in accordance with the Illinois Power Agency and Illinois Public Utilities Acts September 29, 2014 Illinois Power Agency 2015 Electricity

More information

Robla School District

Robla School District Robla School District e-rate Y14 2011-2012 RFP 2011-02 CELLULAR PHONE SERVICE WITH WIRELESS INTERNET ACCESS November 3, 2010 Robla School District 5248 Rose St. Sacramento, CA 95838 SUMMARY The Robla School

More information

Solar Resource Measurement Importance. Wil Grady P.E. Southern California Edison Power Supply NREL PV Solar Resource Workshop Denver 2015

Solar Resource Measurement Importance. Wil Grady P.E. Southern California Edison Power Supply NREL PV Solar Resource Workshop Denver 2015 Solar Resource Measurement Importance Wil Grady P.E. Southern California Edison Power Supply NREL PV Solar Resource Workshop Denver 2015 1 Overview of SCE Large service territory 14 million residents 4.9

More information

SUBJECT: Submission of the El Cabo Contract for Procurement of Renewable Energy From SCE s 2014 Renewables Portfolio Standard Solicitation

SUBJECT: Submission of the El Cabo Contract for Procurement of Renewable Energy From SCE s 2014 Renewables Portfolio Standard Solicitation STATE OF CALIFORNIA Edmund G. Brown Jr., Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE SAN FRANCISCO, CA 94102-3298 June 20, 2016 Advice Letters 3360-E and 3360-E-A Russell G. Worden Director,

More information

Supply Quality Assurance

Supply Quality Assurance Supply Quality Assurance Electric / Gas T&D, Hydro, Solar and Fossil Fuel Power Generation 2014 Supplier Conference Jim Adamson Director, Supplier Quality Assurance Engaging With Suppliers How Supplier

More information

COMBINED HEAT AND POWER: POLICY ANALYSIS AND 2011 2030 MARKET ASSESSMENT

COMBINED HEAT AND POWER: POLICY ANALYSIS AND 2011 2030 MARKET ASSESSMENT CONSULTANT REPORT COMBINED HEAT AND POWER: POLICY ANALYSIS AND 2011 2030 MARKET ASSESSMENT Prepared for: Prepared by: California Energy Commission ICF International, Inc. FEBRUARY 2012 CEC 200 2012 002

More information

PV Farms Solar Electric Power for Wholesale Distribution

PV Farms Solar Electric Power for Wholesale Distribution PV Farms Solar Electric Power for Wholesale Distribution UC ENERGY WEEK 2010 California Solar Energy Workshop UC Davis Energy Institute Davis, California Larry Asera Chairman/CEO Asera Group, Inc. May

More information

MODALITIES OF THE TARGETED LONGER-TERM REFINANCING OPERATIONS

MODALITIES OF THE TARGETED LONGER-TERM REFINANCING OPERATIONS MODALITIES OF THE TARGETED LONGER-TERM REFINANCING OPERATIONS Following a decision by the ECB s Governing Council, the Eurosystem will conduct eight targeted longer-term refinancing operations (TLTROs)

More information

California s Energy Storage Mandate: Electricity Advisory Committee Meeting June 17, 2014. Melicia Charles California Public Utilities Commission

California s Energy Storage Mandate: Electricity Advisory Committee Meeting June 17, 2014. Melicia Charles California Public Utilities Commission California s Energy Storage Mandate: Electricity Advisory Committee Meeting June 17, 2014 Melicia Charles California Public Utilities Commission CPUC Mission The CPUC serves the public interest by protecting

More information

Demand Response FAQs

Demand Response FAQs 1 Under the current CAISO tariff, assuming it would otherwise meet the requirements under the CAISO tariff and business practice manuals to do so, can the Load associated with a retail meter participate

More information

ANNUAL REPORT FOR ENERGY EFFICIENCY PROGRAMS CALENDAR YEAR 2013

ANNUAL REPORT FOR ENERGY EFFICIENCY PROGRAMS CALENDAR YEAR 2013 ANNUAL REPORT FOR ENERGY EFFICIENCY PROGRAMS CALENDAR YEAR 2013 NMPRC EFFICIENT USE OF ENERGY RULE 17.7.2 NMAC JUNE 1, 2014 EPE s PY2013 Energy Efficiency Report Table of Contents SECTION I. EXECUTIVE

More information

ENERGY STORAGE UPDATE

ENERGY STORAGE UPDATE The UK solar gold rush: Navigating the end of the RO regime and preparing for CfDs ORRICK 1 In association with ENERGY STORAGE UPDATE 2014 California Storage RFO by Les Sherman and Rohit Sachdev 2 ORRICK

More information

Appendix D: Electricity Price Forecast Preliminary Draft

Appendix D: Electricity Price Forecast Preliminary Draft Preliminary Draft Introduction... 1 Findings... 2 Approach and Assumptions... 5 Demand Growth... 5 Firm Capacity Standards... 6 Planning Reserve Margin Targets... 6 Firm Capacity Credit... 7 Existing Resources...

More information

Power Tariff Structure in Thailand 23 October 2012, Singapore Dr. Pallapa Ruangrong Energy Regulatory Commission of Thailand

Power Tariff Structure in Thailand 23 October 2012, Singapore Dr. Pallapa Ruangrong Energy Regulatory Commission of Thailand Power Tariff Structure in Thailand 23 October 2012, Singapore Dr. Pallapa Ruangrong Energy Regulatory Commission of Thailand Singapore EAS ABOUT THAILAND Population 67 Million Customers (at end-2011) 19

More information

B O A R D M E E T I N G N a s h v i l l e, T e n n e s s e e November 6, 2014

B O A R D M E E T I N G N a s h v i l l e, T e n n e s s e e November 6, 2014 B O A R D M E E T I N G Nashville, Tennessee November 6, 2014 PRESIDENT S REPORT B i l l J o h n s o n President & CEO Energy Environment Economic Development FY 2014 Overall Performance Safety Record

More information

DRAFT. Appendix E-1 Proposal Evaluation Process Description For 2006 Request For Proposals (RFP) For Long-Term Supply-Side Resources

DRAFT. Appendix E-1 Proposal Evaluation Process Description For 2006 Request For Proposals (RFP) For Long-Term Supply-Side Resources DRAFT Appendix E-1 Proposal Evaluation Process Description For 2006 Request For Proposals (RFP) For Long-Term Supply-Side Resources Entergy Services, Inc. January 31April 17, 2006 DRAFT 2006 LONG-TERM

More information

July 2009 Request for Proposals (RFP) for Baseload Supply-Side Resources Bidders Q&A List Updated as of August 13, 2009

July 2009 Request for Proposals (RFP) for Baseload Supply-Side Resources Bidders Q&A List Updated as of August 13, 2009 July 2009 Request for Proposals (RFP) for Baseload Supply-Side Resources Bidders Q&A List Updated as of August 13, 2009 1) Will questions related to the July 2009 Baseload RFP be addressed at the LPSC

More information

Pre-Scheduling Operations

Pre-Scheduling Operations PJM Manual 10: Pre-Scheduling Operations Revision: 33 Effective Date: December 22, 2015 Prepared by Operations Support Division Generation Department PJM 2015 i Table of Contents PJM Manual 10: Pre-Scheduling

More information

August 27, 2007 Advice Letter 2146-E. Advice Letter 2146-E is effective August 31, 2007. Thank you for your time.

August 27, 2007 Advice Letter 2146-E. Advice Letter 2146-E is effective August 31, 2007. Thank you for your time. STATE OF CALIFORNIA ARNOLD SCHWARZENEGGER, Governor PUBLIC UTILITIES COMMISSION 505 VAN NESS AVENUE Tel. No. (415) 703-2626 SAN FRANCISCO, CA 94102-3298 August 27, 2007 Advice Letter 2146-E Akbar Jazayeri

More information

Overview of the CPUC s California Solar Initiative and DG Programs: James Loewen, Energy Division California Public Utilities Commission

Overview of the CPUC s California Solar Initiative and DG Programs: James Loewen, Energy Division California Public Utilities Commission Overview of the CPUC s California Solar Initiative and DG Programs: James Loewen, Energy Division California Public Utilities Commission For NREL Incentive Program Webinar September 27, 2012 www.cpuc.ca.gov/puc/energy/distgen/

More information

) ) ) ) ) The California Energy Commission will conduct a Business Meeting on:

) ) ) ) ) The California Energy Commission will conduct a Business Meeting on: STATE OF CALIFORNIA NATURAL RESOURCES AGENCY CALIFORNIA ENERGY COMMISSION 1516 Ninth Street Sacramento, California 95814 Main website: www.energy.ca.gov EDMUND G. BROWN JR., Governor In the matter of:

More information

Natural Gas Wholesale Prices at PG&E Citygate as of November 7, 2006

Natural Gas Wholesale Prices at PG&E Citygate as of November 7, 2006 QUARTERLY GAS ISSUES UPDATE December 26 I. Supply Issues Wholesale Natural Gas Prices Above normal temperatures and a lack of hurricane activity caused market prices to decrease in October. By November,

More information

P/T 2B: 2 nd Half of Term (8 weeks) Start: 25-AUG-2014 End: 19-OCT-2014 Start: 20-OCT-2014 End: 14-DEC-2014

P/T 2B: 2 nd Half of Term (8 weeks) Start: 25-AUG-2014 End: 19-OCT-2014 Start: 20-OCT-2014 End: 14-DEC-2014 2014-2015 SPECIAL TERM ACADEMIC CALENDAR FOR SCRANTON EDUCATION ONLINE (SEOL), MBA ONLINE, HUMAN RESOURCES ONLINE, NURSE ANESTHESIA and ERP PROGRAMS SPECIAL FALL 2014 TERM Key: P/T = Part of Term P/T Description

More information

Planned Procurement Opportunities Report. June 2015

Planned Procurement Opportunities Report. June 2015 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report June 2015 Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted

More information

P/T 2B: 2 nd Half of Term (8 weeks) Start: 26-AUG-2013 End: 20-OCT-2013 Start: 21-OCT-2013 End: 15-DEC-2013

P/T 2B: 2 nd Half of Term (8 weeks) Start: 26-AUG-2013 End: 20-OCT-2013 Start: 21-OCT-2013 End: 15-DEC-2013 2013-2014 SPECIAL TERM ACADEMIC CALENDAR FOR SCRANTON EDUCATION ONLINE (SEOL), MBA ONLINE, HUMAN RESOURCES ONLINE, NURSE ANESTHESIA and ERP PROGRAMS SPECIAL FALL 2013 TERM Key: P/T = Part of Term P/T Description

More information

NIPPC Board Meeting December 9, 2008. Meg Meal 120 Jersey Street San Francisco, CA 94114 Ph 415.285.9144 meg@megmeal.com

NIPPC Board Meeting December 9, 2008. Meg Meal 120 Jersey Street San Francisco, CA 94114 Ph 415.285.9144 meg@megmeal.com NIPPC Board Meeting December 9, 2008 Meg Meal 120 Jersey Street San Francisco, CA 94114 Ph 415.285.9144 meg@megmeal.com PPA debt equivalence what is it? Recent developments California Colorado Status in

More information

CALIFORNIA ISO BUSINESS PRACTICE MANUAL (BPM) FOR GENERATOR INTERCONNECTION AND DELIVERABILITY ALLOCATION PROCEDURES (GIDAP)

CALIFORNIA ISO BUSINESS PRACTICE MANUAL (BPM) FOR GENERATOR INTERCONNECTION AND DELIVERABILITY ALLOCATION PROCEDURES (GIDAP) CALIFORNIA ISO BUSINESS PRACTICE MANUAL (BPM) FOR GENERATOR INTERCONNECTION AND DELIVERABILITY ALLOCATION PROCEDURES (GIDAP) Introduction COMMENTS OF THE STAFF OF THE CALIFORNIA PUBLIC UTILITIES COMMISSION

More information

A Guide to Net Energy Metering and Your Billing Process

A Guide to Net Energy Metering and Your Billing Process Understanding Your Domestic Bill for Solar Customers A Guide to Net Metering and Your Billing Process SCE customers who produce their own power are eligible for a special metering and billing option called

More information

P/T 2B: 2 nd Half of Term (8 weeks) Start: 24-AUG-2015 End: 18-OCT-2015 Start: 19-OCT-2015 End: 13-DEC-2015

P/T 2B: 2 nd Half of Term (8 weeks) Start: 24-AUG-2015 End: 18-OCT-2015 Start: 19-OCT-2015 End: 13-DEC-2015 2015-2016 SPECIAL TERM ACADEMIC CALENDAR For Scranton Education Online (SEOL), Masters of Business Administration Online, Masters of Accountancy Online, Health Administration Online, Health Informatics

More information

Frequently Asked Questions PG&E s Power Purchase Agreement for Small Renewable Generation Feed-in Tariffs

Frequently Asked Questions PG&E s Power Purchase Agreement for Small Renewable Generation Feed-in Tariffs Frequently Asked Questions PG&E s Power Purchase Agreement for Small Renewable Generation Feed-in Tariffs What is the small renewable generation power purchase agreement? Effective February 20, 2008, PG&E

More information

REQUEST FOR PROPOSAL (RFP) NUMBER 151223 FOR UTILITY COMMODITIES RENEWABLE ELECTRIC POWER

REQUEST FOR PROPOSAL (RFP) NUMBER 151223 FOR UTILITY COMMODITIES RENEWABLE ELECTRIC POWER UTILITIES DEPARTMENT RESOURCE MANAGEMENT DIVISION REQUEST FOR PROPOSAL (RFP) NUMBER 151223 FOR UTILITY COMMODITIES RENEWABLE ELECTRIC POWER PRE-PROPOSAL TELECON: RFP SUBMITTAL DEADLINE: CONTRACT ADMINISTRATOR:

More information

BUSINESS LOAN APPLICATION

BUSINESS LOAN APPLICATION BUSINESS LOAN APPLICATION Superior National Bank & Trust Company 235 Quincy Street, P.O. Box 450 Hancock, MI 49930 phone 906.482.0404 toll-free 1.866.482.0404 1 INTRODUCTION Thank you for considering Superior

More information

Public Utilities - Proposed Cost Effectiveness Programs For 2012

Public Utilities - Proposed Cost Effectiveness Programs For 2012 STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr., Governor June 19, 2013 Advice Letter 2751-E Akbar Jazayeri Vice President, Regulatory Operations Southern

More information

Your guide to electricity pricing in Ontario

Your guide to electricity pricing in Ontario Your guide to electricity pricing in Ontario A guide designed to help you understand and decipher the components of your electricity bill for your Ontario-based commercial or manufacturing business. -

More information

The New Prior Approval Rate Application Process Frequently Asked Questions

The New Prior Approval Rate Application Process Frequently Asked Questions The New Prior Approval Rate Application Process Frequently Asked Questions 1. We understand that a complete underwriting manual must be filed electronically in SERFF with each private passenger automobile

More information

THE EUROPEAN GREEN BUILDING PROGRAMME. Technical Module on Combined Heat and Power

THE EUROPEAN GREEN BUILDING PROGRAMME. Technical Module on Combined Heat and Power THE EUROPEAN GREEN BUILDING PROGRAMME Technical Module on Combined Heat and Power Contents Foreword...1 1. Introduction...2 2. Inventory of the CHP system...3 3. Assessment of technical energy saving measures...5

More information

SCREEN ACTORS GUILD PRODUCERS HEALTH PLAN

SCREEN ACTORS GUILD PRODUCERS HEALTH PLAN SCREEN ACTORS GUILD PRODUCERS HEALTH PLAN General Information ELIGIBILITY RULES AND REQUIREMENTS Effective January 1, 2015 Eligibility for health coverage under the Screen Actors Guild-Producers Health

More information

Electric Market National Overview

Electric Market National Overview Electric Market Overview Electric Market National Overview 1122 Electric Market Overview: Generation Output and Temperatures Page 2 of 8 Weekly U.S. Electric Generation Output and Temperatures Electric

More information

Options for Trading of Electricity Savings in Shanghai

Options for Trading of Electricity Savings in Shanghai Options for Trading of Electricity Savings in Shanghai Shanghai Economic and Information Technology Commission 28 July 2014 Dr David Crossley, Senior Advisor The Regulatory Assistance Project 睿 博 能 源 智

More information

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market CALIFORNIA ISO Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market Prepared by the Department of Market Analysis California Independent System Operator September 1999 Table of Contents Executive

More information

PREPARED DIRECT TESTIMONY OF TODD J. CAHILL SAN DIEGO GAS & ELECTRIC COMPANY

PREPARED DIRECT TESTIMONY OF TODD J. CAHILL SAN DIEGO GAS & ELECTRIC COMPANY Application No.: A.0-0-. Exhibit No.: Witness: Todd J. Cahill Application of SAN DIEGO GAS & ELECTRIC COMPANY (U 0 E) for Recovery of Costs Related to the California Bark Beetle Infestation under the Catastrophic

More information

Informational Report of the California Independent System Operator Corporation

Informational Report of the California Independent System Operator Corporation California Independent System Operator Corporation June 30, 2016 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: Informational

More information

Eversource Energy. October 26, 2015. For the Period: Calendar Year 2015 Compliance

Eversource Energy. October 26, 2015. For the Period: Calendar Year 2015 Compliance Request For Proposals To Provide NEPOOL-GIS Certificates in Compliance With the Massachusetts Renewable Energy and Alternative Energy Portfolio Standards For the Period: Calendar Year 2015 Compliance October

More information

Release User Group Agenda

Release User Group Agenda Release User Group Agenda September 20, 2011 10:00 a.m. 10:55 a.m. (Pacific Time) Web Conference Information URL: https://www.connectmeeting.att.com Meeting Number: 8665282256 Access Code: 4914267 Conference

More information

CITY OF LANCASTER RFP NO. 621-15 LANCASTER PERFORMING ARTS CENTER TICKETING SOFTWARE SUBMISSION DEADLINE. July 24, 2015 BY 11:00 A.M.

CITY OF LANCASTER RFP NO. 621-15 LANCASTER PERFORMING ARTS CENTER TICKETING SOFTWARE SUBMISSION DEADLINE. July 24, 2015 BY 11:00 A.M. CITY OF LANCASTER RFP NO. 621-15 LANCASTER PERFORMING ARTS CENTER TICKETING SOFTWARE SUBMISSION DEADLINE July 24, 2015 BY 11:00 A.M. SUBMIT TO: Office of the City Clerk Lancaster City Hall 44933 Fern Avenue

More information

FILED 2-10-14 04:59 PM

FILED 2-10-14 04:59 PM BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA FILED 2-10-14 04:59 PM Application of San Diego Gas & Electric Company (U 902 M) for Approval of The SDG&E Solar Energy Project Application

More information

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems This Agreement is made and entered into this day of, 20, ( Effective Date ) by and between the Orlando Utilities Commission

More information

Demand Response Programs: Lessons from the Northeast

Demand Response Programs: Lessons from the Northeast Demand Response Programs: Lessons from the Northeast Charles Goldman E. O. Lawrence Berkeley National Laboratory CAGoldman@lbl.gov Mid Atlantic Demand Response Initiative Meeting Baltimore MD December

More information

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the

More information

Design issues For Net Zero Energy Buildings. Laura Aelenei 26 de Junho de 2012

Design issues For Net Zero Energy Buildings. Laura Aelenei 26 de Junho de 2012 Design issues For Net Zero Energy Buildings Laura Aelenei 26 de Junho de Summary 1.Context Building regulation/policy requirements Scientific advancements 2. Design issues for NZEB General ideas Solar

More information

Center Unified School District

Center Unified School District 8408 Watt Ave., Antelope, CA 95843 916-338-6337 / Fax 916-338-6339 BOARD OF TRUSTEES Gary Blenner Raymond F. Bender Matthew L. Friedman Libby Williams Donald E. Wilson SUPERINTENDENT Dr. Kevin Jolly, Ed.D

More information

Industries Association. ERCOT Successes and Challenges

Industries Association. ERCOT Successes and Challenges Texas Renewable Energy Industries Association ERCOT Successes and Challenges Laura Doll Board Chair Electric Reliability Council of Texas November 7, 2011 ERCOT Overview The ERCOT market covers roughly

More information

E&D Capacity Assessment and Other Issues

E&D Capacity Assessment and Other Issues 17 October 2013 Update on EMR Chris Andrew and Mark Walker Allen & Overy 2013 The UK Energy Policy Trilemma Security of Supply In the next decade a fifth of existing UK generating capacity will come off-line.

More information